MODEL TERMS OF CONSTRUCTION CONTRACT. between. for SUBCONTRACT WORK
|
|
|
- Peregrine Briggs
- 9 years ago
- Views:
Transcription
1 MODEL TERMS OF CONSTRUCTION CONTRACT between CONTRACTOR and SUBCONTRACTOR for SUBCONTRACT WORK 2007 Construction Industry Contracts Committee i
2 Disclaimer The model terms are a set of general terms of contract intended to form part of a subcontract. By design it is generic in nature. By necessity every subcontract must have its own specific provisions to suit the project. Care must be taken when using these model terms as part of a subcontract. If necessary, advice must be sought for any particular project. CIDB and members of the CICC assume no liability whatsoever in contract, tort, or otherwise, if any party chooses to use these model terms to be part of a subcontract and suffers damages. Published by: M ALAYSIA QUALITY SYSTEM SIRIM ISO/IEC GUIDE 62 : 1999 Lembaga Pembangunan Industri Pembinaan Malaysia CONSTRUCTION INDUSTRY DEVELOPMENT BOARD MALAYSIA Ibu Pejabat CIDB, Tingkat 7, Grand Seasons Avenue, No. 72, Jalan Pahang, Kuala Lumpur. P.O. Box 12278, Kuala Lumpur, Tel: , Fax: E-mel: [email protected] Laman web: First print September 2006 Second print December 2006 Third print May 2007 (Revised) Construction Industry Development Board Malaysia ISBN ii
3 Construction work and subcontracting Much of construction work is subcontracted. The CIDB records show that over the last five years, an average of 5000 main contracts exceeding RM 500, each are entered into each year. It is common practice in the construction industry that for each main contract awarded, many more subcontracts are let out to domestic subcontractors. Domestic subcontracts are contracts where the contractors contract with subcontractors of their own choice. Whilst there are various standard terms of construction contracts published for main contracts and the corresponding nominated subcontracts, before this publication, there were no published standard terms of contract for domestic subcontract work in Malaysia. As a result, many subcontracts are entered into based on various in-house contracts drafted by main contractors. A significant number are let out on an ad-hoc and often incomplete basis. And many are let out entirely orally. Standardizing contracts The construction industry now has a choice of using the published Model Terms of Construction Contract for Subcontract Work. The publication is timely and in line with the strategic recommendations in the Construction Industry Master Plan, CIMP to enhance professionalism and improve standards in the construction industry. There are many benefits of having standardized terms of contracts. The advantages include: 1. It becomes more economical as there is no need to draft new terms of contract everytime a contract is let out. 2. It provides more certainty when tendering. 3. Familiarity makes it easier and quicker to be priced. 4. It creates the possibility of a more balanced allocation of risk between the contracting parties. 5. There is a higher chance of avoiding unwarranted disputes in court or arbitration. The use of the model terms as part of a stand alone subcontract The Model Terms of Construction Contract for Subcontract Work is intended to be used as part of a generally stand alone subcontract and not back-to-back to any one specific main contract. The generic drafting style means it can be used as subcontract terms with any main contract whether a one-off contract or published standard form such as the PWD 203A and 203 contracts, PWD Design & Build / Turnkey contract, PAM, IEM, CIDB, FIDIC, JCT, or other contracts published in relevant jurisdictions. It is also flexible enough that it can be made to be back-to-back with any particular main contract quite easily by incorporating reference to specific main contract provisions using the provisions in the appendix in the subcontract terms - if the parties choose to. iii
4 ACKNOWLEDGEMENT The drafting of the model terms of construction contract for subcontract work was led by Sr Noushad Ali Naseem Ameer Ali, President, The Institution of Surveyors Malaysia (ISM), 2006/2007. The draft was deliberated across a broad spectrum of the industry including relevant professional, trade, government, and academic institutions. CIDB Malaysia led several wide consultation sessions through workshops and forums to deliberate the policies and concepts. The key people who helped facilitate the workshops and forums include: Ir C K Khoo Ir Oon Chee Kheng Ir Steven K H Ng Lam Ko Luen Michael Mc Iver Nazir Muhamad Nor Prof Sr Dr Khairuddin Abdul Rashid Sariah Abdul Karib Sr Eddie Wong Weng Hong Sr Lim Chong Fong Sr Noridah Shaffii Sr Noushad Ali Naseem Ameer Ali Sr S Ramar Sr Shariza Sabri Sr Wan Maimun Wan Abdullah Tan Swee Im Tan Teng Khoon The Construction Industry Contracts Committee (CICC) The final outcome of the workshops and forums was a general consensus on concepts and policies. The draft was also endorsed by the CIDB Procurement Policy Advisory Committee. What has now been published is a generally industry consensual document published as the Model Terms of Construction Contract for Subcontract Work endorsed by key players in the construction industry. Following consensus, the Construction Industry Contracts Committee (CICC) was formed. For the purposes of the Model Terms of Construction Contract for Subcontract Work, CICC comprises: Lead : Construction Industry Development Board Malaysia (CIDB) Association of Consulting Engineers Malaysia (ACEM) Dewan Bandaraya Kuala Lumpur (DBKL) Jabatan Kerja Raya Malaysia (JKR) Malaysian Air-Conditioning and Refrigeration Association (MACRA) Malaysian Fire Protection Association (MFPA) Malaysian Lift and Escalator Association (MALEA) Master Builders Association Malaysia (MBAM) Persatuan Kontraktor Melayu Malaysia (PKMM) Pertubuhan Arkitek Malaysia (PAM) Real Estate and Housing Developers Association (REHDA) The Chartered Institute of Building Malaysia (CIOB) The Electrical and Electronics Association of Malaysia (TEEAM) The Institution of Engineers Malaysia (IEM) The Institution of Surveyors Malaysia (ISM) iv
5 AGREEMENT AND TERMS OF CONSTRUCTION CONTRACT FOR SUBCONTRACT WORK between [Contractor] and [Subcontractor] for [Short title of subcontract work] comprising part of [Short title of overall project] i
6 CONTENTS CONTENTS PAGE PART A AGREEMENT AND DEFINITIONS 4 1 Contract for subcontract work and date of contract 2 Parties to this contract Contractor and Subcontractor 3 Contract Administrator 4 Client 5 Overall project 6 Subcontractor s work 7 Contract documents 8 Date for starting the work 9 Date for completing the work 10 Price for the work 11 Singular and plural 12 Law governing this contract PART B TERMS OF CONTRACT 6 1 General obligations The Contractor s general obligations 1.2 The Subcontractor s general obligations 1.3 The Contractor s and Subcontractor s general obligations 2 Administration and changes to the work Contract administration 2.2 Instructions, decisions, certificates, and notices 2.3 Changes to the work 2
7 CONTENTS 3 Time obligations Date for starting the work 3.2 Work programme 3.3 Work progress 3.4 Date for completing the work 3.5 Starting and completing the work in sections 3.6 Adjusting the date for completing the work 3.7 Practical completion and practical completion certificate 3.8 Final completion certificate 3.9 Compensation for completing late 4 Payment Timing payment claims, payment certificates, and payment 4.2 Contents of payment certificates 4.3 Release of retained amount and final payment certificate 5 Quality, safety, health, and environmental obligations Quality 5.2 Breach of contract provisions relating to quality of work 5.3 Safety, health, and environment 6 Legal rights and termination Legal rights 6.2 Termination of the Subcontractor s employment under this contract by the Contractor 6.3 Suspension and termination of the Subcontractor s employment under this contract by the Subcontractor 6.4 Termination of the Contractor s employment and termination of contract with the Client 6.5 Compensation following termination 6.6 Procedures following termination of the Subcontractor s employment under this contract 7 Disagreement and resolution of disagreement Disagreement, negotiation, and mediation 7.2 Adjudication 7.3 Arbitration PART C APPENDIX TO AGREEMENT AND TERMS OF CONTRACT 24 3
8 PART A - AGREEMENT AND DEFINITIONS PART A AGREEMENT AND DEFINITIONS 1 Contract for subcontract work and date of contract This is a construction contract between the Contractor and Subcontractor for subcontract work. The date of this contract is stated in C.1. 2 Parties to this contract Contractor and Subcontractor The parties to this contract are Contractor and Subcontractor. Their signatures confirming their agreement to this contract, witnesses to their signatures, organization names, and other details are stated in C.2. 3 Contract Administrator 4 Client The Contract Administrator administers this contract. The Contract Administrator s name and details are stated in C.3. The work by the Subcontractor under this contract is part of the overall project the Contractor has contracted with the Client. The Client s name and details are stated in C.4. 5 Overall project The overall project is what the Contractor has contracted with the Client. A short title of the overall project is stated in C.5. 6 Subcontractor s work This contract as a whole sets out the full scope of the work by the Subcontractor. A short title of the Subcontractor s work under this contract is stated in C.6. This contract is independent of the contract between the Contractor and the Client except for provisions that are specifically incorporated into this contract, if any. 7 Contract documents The following documents form this contract: Part A: Agreement and definitions Part B: Terms of contract (iii) Part C: Appendix to Part A (Agreement and definitions) and Part B (Terms of contract) (iv) (v) (vi) Breakdown of work and prices [if any] Bills of quantities [if any] Schedule of rates [if any] 4
9 PART A - AGREEMENT AND DEFINITIONS (vii) (viii) (ix) Drawings [if any] Specifications [if any] Other documents stated in C.7 [if any] 8 Date for starting the work The Subcontractor must start the work on the date stated in C.8. If a date is not stated, the Contract Administrator must inform the Subcontractor the date for starting the work in writing. 9 Date for completing the work The Subcontractor must complete the work not later than the date stated in C.9. The date for completing the work may be adjusted according to provisions in this contract. 10 Price for the work The price for the Subcontractor s work is stated in C.10. This is the sum payable by the Contractor to the Subcontractor for the work by the Subcontractor. If the price is not stated, the Contract Administrator must calculate the price for the Subcontractor s work based on the breakdown of work and prices for the Subcontractor s work. If there is no breakdown of work and prices, then the Contract Administrator must calculate the price for the Subcontractor s work based on the actual work done using rates in the following order of priority: (iii) rates in the bills of quantities; if there are none then, rates in the schedule of rates; if there are none then, fair market rates. 11 Singular and plural In this contract all words in the singular include the plural and words in the plural include the singular, as the context requires. 12 Law governing this contract The law stated in C.11 governs this contract. 5
10 PART B - TERMS OF CONTRACT PART B - TERMS OF CONTRACT 1 General obligations 1.1 The Contractor s general obligations The Contractor s general obligations include the following: (iii) (iv) To give timely access to the relevant parts of the project site to the Subcontractor; To provide all relevant information and facilities in a timely manner to enable the Subcontractor to complete the work; To pay the Subcontractor according to provisions in this contract; and To name a Contract Administrator to administer this contract and to name a replacement whenever necessary. 1.2 The Subcontractor s general obligations The Subcontractor s general obligations include the following: (iii) (iv) To complete the work not later than the date for completing the work provided in this contract; To complete the work based on all the provisions in this contract; To pay the stamping fees for this contract; and To give a collateral warranty to the Client, if requested by the Contract Administrator. A collateral warranty is a warranty given by the Subcontractor directly to the Client giving the Client rights that are similar to the Contractor s rights under this contract. The collateral warranty may provide a similar or lesser obligation to that given by the Subcontractor to the Contractor under this contract. It must not provide a higher obligation than that provided in this contract. The Client may assign the collateral warranty to others. 6
11 PART B - TERMS OF CONTRACT 1.3 The Contractor s and Subcontractor s general obligations The Contractor s and Subcontractor s general obligations include the following: To cooperate with each other and all others involved in the overall project and not to disrupt anyone or cause anyone to incur any of the following: (a) (b) physical injury to persons or damage to property; financial loss or expense. To take up the following insurance: (a) (b) insurance that must be taken under the laws at the place where the work is done; and insurance stated in this contract to be taken by each party, if any. (iii) To comply with all laws at the place where the work is done. 7
12 PART B - TERMS OF CONTRACT 2 Administration and changes to the work 2.1 Contract administration The Contract Administrator must provide all relevant information to the Subcontractor in a timely manner to enable the Subcontractor to complete the work Except where stated differently elsewhere in this contract, the Contract Administrator must make all decisions under this contract. These include decisions on quality, quantity, financial, time, and contractual issues under this contract The Contract Administrator must administer this contract and make all decisions based on provisions in this contract. The Contract Administrator must make all decisions and carry out certification functions impartially and in a timely manner The Contract Administrator may delegate powers provided to the Contract Administrator under this contract to others. The Contract Administrator must inform the Subcontractor of any delegation of powers in writing. 2.2 Instructions, decisions, certificates, and notices The Contract Administrator may issue instructions to the Subcontractor on matters relating to the work All Contract Administrator s instructions, decisions, and certificates must be: (iii) in writing; dated; and clearly identified as the Contract Administrator s instruction, decision, and certificate respectively The Subcontractor must comply with all instructions issued by the Contract Administrator in a timely manner The Contractor and Subcontractor must comply with all decisions and certificates issued by the Contract Administrator in a timely manner All notices given by the Contract Administrator, Contractor, and the Subcontractor, and all claims made under this contract must be in writing, dated, and submitted in a timely manner. 8
13 PART B - TERMS OF CONTRACT Communication among the Contractor Administrator, Contractor, and the Subcontractor may be by post, , or fax but all instructions, decisions, certificates, and notices must be: sent by registered post; or delivered by hand with acknowledgement by the receiving party or office. 2.3 Changes to the work The Contract Administrator may issue instructions to change the work If: following an instruction, the Contract Administrator decides there is a financial effect on the Subcontractor s original price; and the instruction is not given as a result of any breach of contract or breach of the law by the Subcontractor, the Contract Administrator must certify the value of changed work in payment certificates. 9
14 PART B - TERMS OF CONTRACT 3 Time obligations 3.1 Date for starting the work The Subcontractor must start the work on the date stated in C If a date is not stated, the Contract Administrator must inform the Subcontractor in writing of the date for starting the work. 3.2 Work programme The Contractor must give the Subcontractor an up-to-date programme for the overall project The Subcontractor must give the Contract Administrator a work programme showing a breakdown of the work to be done by the Subcontractor and when each part of the work is planned to be done Both the Contractor and Subcontractor must update their own work programmes whenever there are significant changes which affect their work programmes. Whenever one party to this contract updates any programme, a copy must be given to the other party to this contract and to the Contract Administrator. 3.3 Work progress The Subcontractor must progress with the work in a timely manner, taking into account: (iii) the Subcontractor s date for completing the work; progress of the Contractor s work; and any disruption incurred. 3.4 Date for completing the work The Subcontractor must complete the work not later than the date stated in C.9. The date for completing the work may be adjusted according to provisions in this contract. 3.5 Starting and completing the work in sections If the work is to be started and completed in sections: the description of the sections of the work and the dates for starting and completing the various sections of the work must be stated in C.8 and C.9, or elsewhere in this contract; and all provisions in this contract will apply to each section of the work adjusted accordingly. 10
15 PART B - TERMS OF CONTRACT 3.6 Adjusting the date for completing the work The Subcontractor must notify the Contract Administrator in writing immediately: if the Subcontractor cannot start the work on the date for starting the work and progress of the work is affected; or whenever there is any disruption to the Subcontractor s work and progress of the work is affected The Subcontractor must also state the causes of disruption and show the impact of all disruptions on: (iii) the Subcontractor s work programme; the work to be done by the Subcontractor; and the Subcontractor s date for completing the work The Contract Administrator must assess the impact of all disruptions on: (iii) the Subcontractor s work programme; the work to be done by the Subcontractor; and the Subcontractor s date for completing the work If the Contract Administrator decides that any date for completing the work by the Subcontractor is affected and is directly caused by any of the following events, the Contract Administrator must adjust the date for completing the work: the act or failure to act by any one or more of the following persons or anyone within their control: (a) (b) (c) (d) (e) the Client; the Contractor; the Contract Administrator; other parties engaged by the Client; or other parties engaged by the Contractor. 11
16 PART B - TERMS OF CONTRACT (iii) (iv) (v) exceptionally inclement weather occurring at the place where the project is; exceptionally adverse natural environmental event beyond the control of the parties occurring at the place where the project is; an action of government authority, provided the action is not done as a result of any breach of contract or breach of the law by the Subcontractor; or if the Subcontractor suspends the work based on provisions in this contract The Contract Administrator may adjust any date for completing the work to be earlier or later than a previous date for completing the work, but the adjusted date must not be earlier than the original date for completing the work stated in C As an alternative to adjusting the date for completing the work to be later than an earlier date, the Contract Administrator may, if agreed by the Subcontractor, maintain the earlier date for completing the work and assess the extra cost incurred by the Subcontractor in accelerating the work. The Contract Administrator must then certify the extra cost of acceleration in payment certificates The Contract Administrator must decide all adjustments to the date for completing the work in a written certificate clearly identified as an adjustment of time certificate. 3.7 Practical completion and practical completion certificate The Subcontractor must complete the work based on the provisions in this contract The Subcontractor must inform the Contract Administrator in writing 7 days prior to the Subcontractor s estimated date for practically completing the work The Contract Administrator must decide whether and when the Subcontractor achieves practical completion When the Contract Administrator decides the Subcontractor has achieved practical completion, the Contract Administrator must immediately certify the date when the Subcontractor achieves practical completion. This must be done in a written certificate clearly identified as a practical completion certificate. 12
17 PART B - TERMS OF CONTRACT 3.8 Final completion certificate The Contract Administrator must issue a certificate clearly identified as a final completion certificate; when all breaches of the provisions of this contract which are instructed by the Contract Administrator to be rectified under this contract are rectified, or on the date or at the end of the period stated in C.12, whichever is later. 3.9 Compensation for completing late If the Subcontractor does not complete the work by the date for completing the work provided in this contract, the Subcontractor must pay financial compensation for the delay to the Contractor Financial compensation for delay is calculated for delay between when the Subcontractor s work should have been completed (the current date for completing the work) and when the work is actually completed (as confirmed by the Contract Administrator in a practical completion certificate) The rate for financial compensation for delay may be pre-specified as liquidated damages. This, if any, is stated in C.13 or it may be stated elsewhere in this contract If a pre-specified rate for financial compensation as liquidated damages for delay is not stated anywhere in this contract, the Contract Administrator must assess and certify in payment certificates a reasonable amount of compensation for direct financial loss and expense incurred by the Contractor due to the Subcontractor s delay The Contractor may waive the right to financial compensation for delay but this must be done in writing. 13
18 PART B - TERMS OF CONTRACT 4 Payment 4.1 Timing payment claims, payment certificates, and payment At the end of each month, the Subcontractor must submit a payment claim for the work done and all other claims as provided in this contract By the 15th of the following month, the Contract Administrator must value and certify the work done and all other amounts to be adjusted as provided in this contract, in a payment certificate If the parties agree to other payment arrangements such as fortnightly payments or stage payments, the timing, stages and prices must be clearly stated and attached as part of this contract. The Contract Administrator must then still issue payment certificates, but must certify based on the other payment arrangements The Contractor must pay the Subcontractor the amount due as stated in the payment certificate not later than the time stated in C Contents of payment certificates Except if agreed differently, all payment certificates must include all relevant items stated below Additions. The values of the following items which are relevant during the preparation of a payment certificate must be added: Cumulative value of the work properly done. The Contract Administrator must value the cumulative value of the work done based on the actual work done using the breakdown of work and prices for the Subcontractor s work. If there is no breakdown of work and prices, then the work must be valued based on the actual work done using rates in the following order of priority: (a) (b) (c) rates in the bills of quantities; if there are none then using, rates in the schedule of rates; if there are none then using, fair market rates. The net value of the changed work including additions and omissions properly instructed by the Contract Administrator and properly done by the Subcontractor. If the changed work is similar to that provided in this contract, the Contract Administrator must value the changed work based on the breakdown of work and prices for the Subcontractor s work. If there is no breakdown of work and prices, then the Contract Administrator must value the changed work using rates in the following order of priority: 14
19 PART B - TERMS OF CONTRACT (a) (b) (c) rates in the bills of quantities; if there are none then using, rates in the schedule of rates; if there are none then using, fair market rates. If the changed work is not similar to that provided in this contract, the Contract Administrator must value the changed work using: (d) (e) fair market rates; and if the work cannot be measured then, fair market daywork rates based on a breakdown of rates for materials, labour, plant, equipment, overheads and profits. (iii) (iv) (v) (vi) A percentage, stated in C.15, of the value of materials for the work delivered to the project site. A percentage, stated in C.16, of the value of materials for the work stored outside the project site, provided the materials are properly insured, clearly labeled, and are to be used for the work. The extra cost incurred by the Subcontractor in accelerating the work as provided in this contract, if any. Compensation for direct financial loss and expense, if claimed by the Subcontractor, valued by the Contract Administrator, if any one or more of the following persons or anyone within their control cause the Subcontractor to incur direct financial loss or expense: (a) (b) (c) (d) (e) the Client; the Contractor; the Contract Administrator; other parties engaged by the Contractor; or other parties engaged by the Client. The Contract Administrator must take into account all reasons for the direct financial loss and expense incurred by the Subcontractor. Any financial loss or expense incurred due to the Subcontractor s own fault must be excluded. 15
20 PART B - TERMS OF CONTRACT (vii) Compensation for direct financial loss and expense incurred by the Subcontractor, if any, valued by the Contract Administrator following suspension of the work or termination of the Subcontractor s employment as provided in this contract Deductions. Deduct the total of all the following: (iii) (iv) (v) (vi) The cumulative value certified under previous payment certificates. Compensation for delayed completion by the Subcontractor as provided in this contract. The adjustment in the value of the completed work due to a breach of the provisions of this contract by the Subcontractor which is not required by the Contract Administrator to be rectified by the Subcontractor. The cost of rectifying a breach of the provisions of this contract by the Subcontractor, which the Contract Administrator got others to rectify as provided in this contract. Compensation for direct financial loss and expense incurred by the Contractor, if any, valued by the Contract Administrator following termination of the Subcontractor s employment as provided in this contract. A percentage, as stated in C.17, of the sum of the total additions for the payment certificate as a retained amount Net amount due The net amount due is the total additions minus total deductions. The net amount due must be stated in all payment certificates. This is the amount the Contractor must pay to the Subcontractor. 4.3 Release of retained amount and final payment certificate The Contract Administrator must certify the release of half of the retained amount in a payment certificate issued not later than 7 days after the practical completion certificate is issued The Contract Administrator must certify the release of the second half of the retained amount in a final payment certificate after the final accounts are completed The final payment certificate must be issued not later than 7 days after the final completion certificate is issued If however, there is a net amount due from the Subcontractor to the Contractor, then the Contract Administrator must certify any of the retained amounts to be set off against amounts due to the Contractor. 16
21 PART B - TERMS OF CONTRACT 5 Quality, safety, health, and environmental obligations 5.1 Quality The Subcontractor must complete the work based on the provisions in this contract. 5.2 Breach of contract provisions relating to quality of work If the Subcontractor breaches any provision in this contract relating to the quality of the work, the Subcontractor must rectify the breach immediately. If the breach is not rectified immediately, the Contract Administrator must do one of the following: Instruct the Subcontractor to rectify the breach, clearly identifying the breach in writing. If the Subcontractor does not rectify the breach within 14 days from the date the Subcontractor receives the instruction, the Contract Administrator may get others to rectify the breach. The Contract Administrator must then charge the Subcontractor the cost of rectifying the breach in payment certificates; or Write to the Subcontractor instructing the breach not to be rectified. The Contract Administrator must then adjust the value of the work done, taking into account the breach, in payment certificates The Contract Administrator may continue to act on any breach by the Subcontractor relating to the quality of work throughout the contract until the final completion certificate is issued. 5.3 Safety, health, and environment Both the Contractor and the Subcontractor must: (iii) keep their part of the project site clean and safe at all times; comply with all safety, health, and environmental provisions in this contract; and comply with all laws relating to safety, health, and environment. 17
22 PART B - TERMS OF CONTRACT 6 Legal rights and termination 6.1 Legal rights The parties rights and obligations provided under this contract are additional to the parties rights and obligations in law generally. 6.2 Termination of the Subcontractor s employment under this contract by the Contractor If the Subcontractor: does not proceed with the work in a regular and timely manner; or persistently does not comply with the Contract Administrator s instructions, the Contract Administrator may give a written notice to the Subcontractor stating clearly what the breach is. The notice must also instruct the Subcontractor to rectify the breach and must warn the Subcontractor of the possibility of a termination if the breach is not rectified If the Subcontractor does not rectify the breach within 14 days from the date the Subcontractor receives the notice, the Contractor may then terminate, in writing, the Subcontractor s employment under this contract within 7 days following the end of the 14 day notice period If the Subcontractor commits the same breach again, the Contractor may terminate, in writing, the Subcontractor s employment within 7 days from the date of the breach without giving further notices. 6.3 Suspension and termination of the Subcontractor s employment under this contract by the Subcontractor If the Contractor does not pay the Subcontractor in accordance with the provisions of this contract, the Subcontractor may give a written notice to the Contractor for the breach to be rectified. The notice must warn the Contractor of the possibility of a termination or suspension or both if the breach is not rectified If following the notice the Contractor does not rectify the breach within 14 days from the date the Contractor receives the notice, the Subcontractor may then either: suspend the work by giving a written notice to suspend within 7 days following the end of the 14 day notice period; or terminate, in writing, the Subcontractor s employment under this contract within 7 days following the end of the 14 day notice period. 18
23 PART B - TERMS OF CONTRACT 6.4 Termination of the Contractor s employment and termination of contract with the Client If: the Contractor s employment under the contract with the Client is terminated; or the contract between the Client and the Contractor is terminated, the Subcontractor s employment under this contract is terminated automatically. The Contract Administrator must immediately inform the Subcontractor in writing, of the termination of the Subcontractor s employment under this contract. 6.5 Compensation following termination Following suspension of the work or termination of the Subcontractor s employment, the party who breaches this contract must compensate the other party for all direct financial loss and expense incurred by the other party If: the Subcontractor s employment under this contract is terminated automatically following the Contractor s employment or contract with the Client being terminated, and this was not caused by the Subcontractor s fault, the Contractor must compensate the Subcontractor for all direct financial loss and expense incurred by the Subcontractor The Contract Administrator must certify all compensation for direct financial loss and expense following suspension of the work or following termination of the Subcontractor s employment in payment certificates. 6.6 Procedures following termination of the Subcontractor s employment under this contract Following termination of the Subcontractor s employment under this contract: the Contract Administrator must continue to administer this contract as provided in this contract; the Contract Administrator must decide and issue instructions on all plant, equipment, materials and labour that are to be retained on the project site and those that are to be removed from the project site. The instructions must be issued within 7 days from the date of termination of the Subcontractor s employment under this contract; 19
24 PART B - TERMS OF CONTRACT (iii) the Subcontractor must then demobilize from the project site within 7 days from the date of the Contract Administrator s instructions; (iv) (v) (vi) the Contractor and Subcontractor must submit claims provided under this contract to the Contract Administrator within 30 days from the date of termination of the Subcontractor s employment under this contract; the Contract Administrator must, not later than the subsequent 30 days, prepare a payment certificate based on the provisions in this contract; and the Contractor and Subcontractor must submit all final claims under this contract as soon as possible to enable the Contract Administrator to close the accounts and issue a final payment certificate. 20
25 PART B - TERMS OF CONTRACT 7 Disagreement and resolution of disagreement 7.1 Disagreement, negotiation, and mediation If either the Contractor or Subcontractor disagrees with the other on any issue relating to this contract (including any decision or certification by the Contract Administrator), the parties are encouraged to negotiate and reach a settlement. The parties may also refer the disagreement to the highest authorities within each organization for the matter to be amicably resolved The parties may also agree to opt for mediation and get the help of a third party (a mediator) in their negotiations to reach a settlement If the parties agree to use mediation but cannot agree on a mediator, they may then request the person named in C.18 to recommend a mediator If the parties agree on a mediator, the parties and the mediator may proceed using any mediation procedures that they may agree on. If they cannot agree, the mediator may decide on the procedures to be used If at any time a settlement agreement is made, both parties are bound by the terms of the settlement agreement. The Contract Administrator, adjudicator, and arbitrator must also follow the agreements made by the parties to this contract If the terms of the settlement agreement are not complied with, either party may refer the matter to adjudication or arbitration as provided in this contract. 7.2 Adjudication At any time during this contract, either the Contractor or Subcontractor may request in writing for any disagreement arising under this contract to be resolved through adjudication. The written request must state what the disagreements are The parties may agree on an adjudicator, failing which, either party may write to the person named in C.19 for an adjudicator to be nominated Once an adjudicator accepts a nomination, the adjudicator is considered appointed. Both parties must comply with all instructions, procedures and rules decided by the adjudicator The adjudicator must act impartially between the two parties and must give a written decision based on this contract and the law in not more than 30 days from the date of the appointment. Upon the request of either party or the adjudicator, a further 30 days to give a written decision is automatically allowed. If both the Contractor and Subcontractor agree in writing, further extensions are allowed. Beyond these timeframes, the entire adjudication on the issues referred ends automatically and any adjudicator s decision does not bind any party. 21
26 PART B - TERMS OF CONTRACT The adjudicator may revise the Contract Administrator s decisions and certificates. The adjudicator may also make decisions and prepare any certificate that should have been done by the Contract Administrator but was not done The adjudicator s written decision, if made within the allowed period, including decisions on who pays for the adjudicator s fees and reimbursables relating to the adjudication, binds both parties Both the Contractor and Subcontractor must comply with all decisions made by the adjudicator. The Contract Administrator must also comply with all decisions made by the adjudicator when administering the contract Only an arbitrator or the courts can review or overrule the adjudicator s decisions. 7.3 Arbitration Apart from the parties choosing to resolve any disagreement through other provisions of this contract such as negotiation, mediation, adjudication, or by agreement, all disagreements relating to this contact must be referred to arbitration. Any disagreement on a settlement agreement and any issues decided by the adjudicator to be reviewed or overruled must also be referred to arbitration All requests to refer a disagreement to arbitration must be in writing, stating what the disagreements are An arbitration may however, only be started and continued following any one of the following events: (iii) (iv) (v) (vi) When the work is certified to be practically complete by the Contract Administrator; If one party thinks all that party s obligations under this contract have been completed; When one of the parties acts like that party is not bound by this contract; If the Subcontractor s employment under this contract has been terminated; If this contract has been terminated; or If both parties agree to go to arbitration at any time even before any of the events above. 22
27 PART B - TERMS OF CONTRACT The parties may agree on an arbitrator, failing which, either party may write to the person named in C.20 for an arbitrator to be nominated Once an arbitrator accepts a nomination, the arbitrator is considered appointed. Both parties may agree on the procedures and rules to be adopted in the arbitration, failing which the arbitrator will decide the procedures and rules Both parties must comply with all instructions and directions given and all decisions made by the arbitrator If the Contractor requests the Subcontractor to agree to an arbitrator already appointed under a related disagreement between the Contractor and any other party involved in this project, the Subcontractor must agree to this arbitration being heard together or consolidated with the other arbitration with the arbitrator already appointed under the other contract The arbitrator must be independent and must act impartially between the parties. The arbitrator s written award must be based on the provisions of this contract and the law. The arbitrator may revise the adjudicator s decisions and the Contract Administrator s decisions and certificates. The arbitrator may also make decisions and prepare any certificate that should have been done by the Contract Administrator but was not done The arbitrator s written award including decisions on costs of reference, costs of award and who pays for the arbitrator s fees and reimbursables relating to the arbitration, and in what proportion, is final and binds both parties Arbitration under this contract is governed by the Arbitration Act stated in C
28 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) C.1 A.1 Date of this contract: C.2 A.2 Contractor s and Subcontractor s signatures and details Contractor Subcontractor C.2 Authorised signature: C.2 Name of person who signs this contract: C.2 (iii) Identification card or passport number: C.2 (iv) Designation in organisation: C.2 (v) Name of organisation: C.2 (vi) Address for correspondence: 24
29 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) C.2 (vii) Telephone number: C.2 (viii) Fax number: C.2 (ix) address: C.2 (x) Signature of witness: C.2 (xi) Name of witness: C.2 (xii) Identification card or passport number: C.2 (xiii) Address of witness: 25
30 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) C.3 A.3 Contract Administrator s details C.3 Name of Contract Administrator: C.3 Name of organisation: C.3 (iii) Address for correspondence: C.3 (iv) Telephone number: C.3 (v) Fax number: C.3 (vi) address: 26
31 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) C.4 A.4 Client s details C.4 Name of organisation: C.4 Address for correspondence: C.4 (iii) Telephone number: C.4 (iv) Fax number: C.4 (v) address: 27
32 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) C.5 A.5 Short title of the overall project which the Contractor has contracted with the Client: C.6 A.6 Short title of the Subcontractor s work under this contract: C.7 A.7 (ix) Other documents, apart from those already listed in A.7 to (viii) which form this contract (if any): 28
33 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) C.8 and Date for starting the work: and Date for completing the work: Price for the Subcontractor s work: Ringgit Malaysia: (RM ) 29
34 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) C.11 A.12 Law governing this contract: If not stated, the law where the project is. C.12 B Date or period provided in B for issuing the final completion certificate: State date: Or State period: from If not stated, 12 months from the date the Subcontractor completes the work as stated in the practical completion certificate. C.13 B Financial compensation rate for delay by the Subcontractor, pre-specified as liquidated damages (if any): RM a day If not stated here or anywhere else in this contract, the Contract Administrator must assess and certify in payment certificates a reasonable amount of compensation for direct financial loss and expense incurred by the Contractor due to the Subcontractor s delay. 30
35 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) Time for payment: Not later than days from the date of a payment certificate. If not stated, not later than 30 days from the date of a payment certificate. Percentage of value of materials delivered to the project site to be included in payment certificates: % If not stated, 75%. Percentage of value of materials stored outside the project site to be included in payment certificates: % If not stated, 75%. 0%. Percentage of retention: % If not stated, 5% of the sum of the total additions under B
36 PART C - APPENDIX TO AGREEMENT AND TERMS OF CONTRACT Item Reference to Part A (Agreement and definitions) and Part B (Terms of contract) and description Particulars (Refer to other documents or add extra sheets if space is not sufficient) Person who recommends a mediator: If not stated, the Chief Executive or other authorized person from the Construction Industry Development Board Malaysia. Person who nominates an adjudicator: If not stated, the Chief Executive or other authorized person from the Construction Industry Development Board Malaysia. Person who nominates an arbitrator: If not stated, the Director or other authorized person from the Kuala Lumpur Regional Centre for Arbitration. Act governing arbitration If not stated, the prevailing Arbitration Act in Malaysia. 32
Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)
Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Document A101 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the in the year (In words, indicate day, month and year.)
HANDBOOK FOR THE PART III PROFESSIONAL EXAMINATION
MAJLIS PEPERIKSAAN SENIBINA LEMBAGA ARKITEK MALAYSIA (LAM) HANDBOOK FOR THE PART III PROFESSIONAL EXAMINATION LEMBAGA ARKITEK MALAYSIA 17th Floor, Block F JKR Headquarters Jalan Sultan Salahuddin 50582
How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner
SHORT FORM PRIME CONTRACT BETWEEN OWNER & CONTRACTOR This Agreement ( Contract ) is made this day of, 20, between ( Contractor ) and ( Owner ) at The work described in Section 1 below shall be performed
NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard
New Zealand Standard Conditions of contract for building and civil engineering construction Superseding (in part) NZS 3910:2003 NZS 3910:2013 COMMITTEE REPRESENTATION This Standard was prepared under the
GOVERNMENT OF MALAYSIA STANDARD FORM OF DESIGN & BUILD / TURNKEY CONTRACT (PWD FORM DB/T)
GOVERNMENT OF MALAYSIA STANDARD FORM OF DESIGN & BUILD / TURNKEY CONTRACT (PWD FORM DB/T) CONDITIONS OF CONTRACT FOR DESIGN & BUILD AND TURNKEY PROJECTS (PWD FORM DB/T) This form has been approved by Attorney
THE RULES. 2003-2013 MYNIC BERHAD. All rights reserved.
MYNIC'S (.my) DOMAIN NAME DISPUTE RESOLUTION POLICY THE RULES 2003-2013 MYNIC BERHAD. All rights reserved. MYNIC's (.my) Domain Name Dispute Resolution Policy THE RULES 1. General 1.1 All domain name disputes
Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer
Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland
PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:
Supply Chain Management Document Number: SCM006 Document Title: Supply Contract Version: 01 Purpose: Standard contract for all supplies of goods PREFACE The Contract for the Supply and Delivery of Goods
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,
CONTRACT CONDITIONS FOR LOGISTICS (2014)
CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member
This is the Annexure A to Positive Covenant between and Woollahra Municipal Council
This is the Annexure A to Positive Covenant between and Woollahra Municipal Council 1. Definitions and Interpretation 1.1. For the purpose of this covenant, the following definitions apply: Act means the
CLIENT / PROJECT MANAGER AGREEMENT
Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT
How To Write A Contract In The European
(Form-9) Agreement with Contractor for THIS AGREEMENT (hereinafter, together with the appendices and all the documents annexed hereto and forming an integral part hereof, referred to as the Contract )
PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS
PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS 2014 Public Sector Standard Conditions of Contract for Construction Works 2014 Building and Construction Authority First published 1995
Conditions of Contract for Consultancy Services
Conditions of Contract for Consultancy Services INGENIUM PO Box 118, Thames; Ph 07 868 3930, Fax 07 868 3930 www.ingenium.org.nz NZ Transport Agency Private Bag 6995, Wellington 6441; Ph 04 894 5400, Fax:
Mr and Mrs Sample and future owners or occupants of the Property and Your/their mortgage lender(s).
Contingent Buildings Insurance Indemnity Policy This Policy is the contract between You and the Insurer and it includes the Schedule and any endorsement, extension, plan or appendix issued with it. We
Engineering Council of South Africa
Government Gazette No. 26180, 2 April 2004 Page 1 of 30 Board Notice 42 of 2004 Engineering Council of South Africa Guideline Scope of Services and Tariff of Fees for Persons Registered in terms of the
Document Comparative
Document Comparative AIA Documents A401 2007 and A401 2007 SP AIA Document A401 2007 SP, Standard Form of Agreement Between Contractor and Subcontractor, for use on a Sustainable Project, establishes the
Introduction to SOP. Background. Background. Principles of SOP Act. Objectives of SOP Act
Introduction to SOP Background Building and Construction Industry Security of Payment (SOP) Act Objectives of Act Principles of Act Key Provisions of Act by Lim Jue Meng Jennifer Leong Ng Cher Cheng Feedback
ENERGY PERFORMANCE CONTRACT
DATED DAY OF ENERGY PERFORMANCE CONTRACT THE CUSTOMER SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT -AND- THE ESCO SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT [This document is a DRAFT provided only
BMT Tax Depreciation Pty Ltd - Terms of Engagement
BMT Tax Depreciation Pty Ltd - Terms of Engagement 1.0 Definitions and Interpretation 1.1 In this document, unless the context indicates a contrary intention: Agreement means these Terms of Engagement
Agreement Addendum for Hosting Services. 1. Definitions. 2. Service Provision. 3. Scope of Client's Use 1/6
Agreement Addendum for Hosting Services 1. Definitions 1.1 Application means the specific hosted application(s) for which the Hosting Services are provided, identified and described in the Schedule. 1.2
This document must be read in conjunction with Beacon Consulting s Fee Proposal. Together they form the Rules and Conditions of Service Delivery.
This document must be read in conjunction with Beacon Consulting s Fee Proposal. Together they form the Rules and Conditions of Service Delivery. CONTENTS CLAUSES Page 1. Services 1 2. Client s Undertakings
Dr. Simon Chee, Professor Michael Hor, Distinguished Guests, Ladies and. 2. Hong Kong has never been short of infrastructure and construction
Speech by the Hon Rimsky Yuen, SC, JP, Secretary for Justice Hong Kong Construction Arbitration Centre & University of Hong Kong Joint Conference on Construction Dispute Resolution 2015 Resolution of Construction
Back to Basics: Professional Indemnity Construction and Engineering
Back to Basics: Professional Indemnity Construction and Engineering December 2015 Table of Contents Table of Contents... 2 Introduction... 3 Part A - Understanding the construction industry... 4 1 Construction
XL INSURANCE (CHINA) COMPANY LIMITED EXCESS LIABILITY INSURANCE POLICY (OCCURRENCE FORM)
XL INSURANCE (CHINA) COMPANY LIMITED EXCESS LIABILITY INSURANCE POLICY (OCCURRENCE FORM) 1. PREAMBLE This Policy consists of: a) this Policy wording; and b) each endorsement issued by the Company and attached
Nominated Subcontractors on International Projects: Approaches to Risk Allocation
Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.
New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions
ACRS Lic No. A021974 Lic No. 192237C New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions *Definitions are in clause 19 1. FORMATION OF AGREEMENT 1.1 Acceptance of Quotation The Customer must accept
Public Works Contract. for. MINOR BUILDING and CIVIL ENGINEERING WORKS. designed by THE EMPLOYER
Public Works Contract for MINOR BUILDING and CIVIL ENGINEERING WORKS designed by THE EMPLOYER Office of Government Procurement Public Works Contract for Minor Building and Civil Engineering Works Designed
STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)
State License #CGC048773 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) This Agreement is made this day of, 200, by and
Financial Services Guidance Note Outsourcing
Financial Services Guidance Note Issued: April 2005 Revised: August 2007 Table of Contents 1. Introduction... 3 1.1 Background... 3 1.2 Definitions... 3 2. Guiding Principles... 5 3. Key Risks of... 14
PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED
DATED DAY OF 2015 PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED between MINISTER FOR COMMUNITIES AND SOCIAL INCLUSION - and - [INSERT PARTY NAME] ACN [INSERT] Page 1 of 1 TABLE OF CONTENTS BACKGROUND...
MGM CHINA HOLDINGS LIMITED
Hong Kong Exchanges and Clearing Limited and The Stock Exchange of Hong Kong Limited take no responsibility for the contents of this announcement, make no representation as to its accuracy or completeness
HONG LEONG INFINITE/ INFINITE CREDIT CARD TERMS AND CONDITIONS
HONG LEONG INFINITE/ INFINITE CREDIT CARD TERMS AND CONDITIONS The terms and conditions below are to be read together with the Hong Leong Bank ( the Bank ) Cardholder s Agreement Terms and Conditions (
Terms and Conditions for Purchase Orders for Recycling Materials
Terms and Conditions for Purchase Orders for Recycling Materials This Agreement is made by and between AEROJET-GENERAL CORPORATION, an Ohio corporation with a place of business at Rancho Cordova, California
REMODELING CONTRACT., remodeling contractor, whose address is, to on the property located at.
REMODELING CONTRACT I. Parties This contract is made and entered into on and specifies the terms the agreement between, homeowners, and, remodeling contractor, whose address is, to on the property located
4 Guidelines on Administration Charges for Reporting of Site Accidents
4 Guidelines on Administration Charges for Reporting of Site Accidents Version 1 August 2008 Disclaimer This publication is prepared by the Construction Industry Council (CIC) to report findings or set
Icetrak Fax to Email Contract Terms and Conditions
Section 1: General terms and conditions 1 Definitions Icetrak Fax to Email Contract Terms and Conditions 1.1 In these terms the words and expressions listed below shall have the following meanings: Act
Mako Networks Sales & Marketing, Inc. Terms & Conditions for End User System Access, Use & Service Supply
Mako Networks Sales & Marketing, Inc. Terms & Conditions for End User System Access, Use & Service Supply 1. Introduction a. Binding Terms: These terms and conditions constitute a legally binding agreement
Consumer Code. for Home Builders. This document contains the Rules that govern the behaviour of Home Builders and Home Warranty Bodies
Consumer Code for Home Builders This document contains the Rules that govern the behaviour of Home Builders and Home Warranty Bodies First Edition January 2010 Contents Meaning of words... 3 Introduction...
The FIDIC Suite of Contracts
Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October
Service Level Agreement for providing Annual Maintenance Services for STPI.in Project
Annexure SLA Service Level Agreement for providing Annual Maintenance Services for STPI.in Project This SERVICE LEVEL AGREEMENT is made on this the between Director, STPI Bangalore, Bangalore 560 100 (hereinafter
THE CITY OF EDMONTON PROJECT AGREEMENT VALLEY LINE LRT STAGE 1. Schedule 20. Dispute Resolution Procedure
THE CITY OF EDMONTON PROJECT AGREEMENT VALLEY LINE LRT STAGE 1 Schedule 20 Dispute Resolution Procedure VAN01: 3666224: v8 SCHEDULE 20 DISPUTE RESOLUTION PROCEDURE TABLE OF CONTENTS 1. DISPUTE RESOLUTION...
A Guide to Small Works. A brief explanation
A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here
Appendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
Performance Bond. Business):
Performance Bond CONTRACTOR (Name and Address): (Name and Address of Principal Place of Business): OWNER (Name and Address): City of Cedar Rapids City Clerk, 101 First Street SE Cedar Rapids, IA 52401
The FIDIC Form of Contract. The Fourth Edition of the Red Book. 2nd Edition. Nael G. Bunni
The FIDIC Form of Contract The Fourth Edition of the Red Book 2nd Edition Nael G. Bunni BSc, MSc, PhD, CEng, FIEI, FICE, FIStruct, FCIArb, FInstD, MconsEI b Blackwell Science Contents List of Figures List
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
NEC Users Group Workshop Defined Cost
NEC Users Group Workshop Defined Cost [email protected]; July 2014 Turner & Townsend plc July 14 making the difference Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption
WMP/LIABS/SDBTC/131227
1 1. The Licensee will have access to the Box at any time during the designated business hours of the Bank subject to such regulations as prescribed by the Bank except where access is prevented for reason(s)
MDB Harmonised Particular Conditions
FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st
Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement
Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the
10 20 ARBITRATION RULES
2010 ARBITRATION RULES MODEL ARBITRATION CLAUSE Any dispute, controversy or claim arising out of or in connection with this contract, or the breach, termination or invalidity thereof, shall be finally
PRODUCT CERTIFICATION RULES GOVERNING THE SCHEME JANUARY 2006
THE GAS SAFETY CERTIFICATION FOR GAS APPLIANCES AND COMPONENTS PRODUCT CERTIFICATION RULES GOVERNING THE SCHEME JANUARY 2006 MKP220.01 Issue Date: 2007-Oct-09 SAI Global Limited Copyright 2007 - ABN 67
CONTRACT MANAGEMENT POLICY
CONTRACT MANAGEMENT POLICY Section Finance Approval Date 25/08/2014 Approved by Directorate Next Review Aug 2016 Responsibility Chief Operating Officer Key Evaluation Question 6 PURPOSE The purpose of
Dated 29 February 2016. Flood Re Limited. Payments Dispute Process. Version 1.0
Dated 29 February 2016 Flood Re Limited Payments Dispute Process Version 1.0 1. General 1.1 The following provisions will apply to all disputes referred to and conducted under this Payments Dispute Resolution
INVESTMENT ADVISORY AGREEMENT
INVESTMENT ADVISORY AGREEMENT THIS INVESTMENT ADVISORY AGREEMENT is made on the Effective Date identified below by and between the investment advisors affiliated with BCG Securities, Inc. ( Advisor ),
CONTRACT FOR SALE AND PURCHASE OF ASSET BETWEEN. PETRONAS Chemical Derivatives Sdn Bhd ( COMPANY ) AND BUYER
CONTRACT FOR SALE AND PURCHASE OF ASSET BETWEEN PETRONAS Chemical Derivatives Sdn Bhd ( COMPANY ) AND BUYER This CONTRACT FOR THE SALE AND PURCHASE OF ASSET (hereinafter referred to as Contract ) is made
PROFESSIONAL PRACTICE EXAM MARCH 2009 PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS A PRACTITIONER AND ARCHITECTURAL SERVICE TO THE CLIENT
PROFESSIONAL PRACTICE EXAM MARCH 2009 Instructions to Candidates: 1 All questions are to be answered Where a question is in sections, each answer is to be clearly separated strictly in accordance with
7.4.1 Be required to make exhaustive or continuous on-site reviews;
SUPPLEMENTARY CONDITIONS TO THE CANADIAN STANDARD FORM OF CONTRACT FOR ARCHITECTURAL SERVICES DOCUMENT SIX 2006 EDITION RAIC 6 2006 FRASER HEALTH PROJECTS The following Supplementary Conditions are specific
SAMPLE. Professional Indemnity Insurance (PII) Policy 2015/16. lawcover.com.au Page 1
Professional Indemnity Insurance (PII) Policy 2015/16 Lawcover Insurance Pty Limited ABN 15 095 082 509 Level 13, 383 Kent Street Sydney NSW 2000 DX 13013 Sydney Market Street Telephone: 1800 650 748 (02)
Terms and Conditions for Tax Services
Terms and Conditions for Tax Services In the course of delivering services relating to tax return preparation, tax advisory, and assistance in tax controversy matters, Brady, Martz & Associates, P.C. (we
LOGGING SUBCONTRACT. Recital
LOGGING SUBCONTRACT This Logging Contract (this Contract ) is entered as of the day of, 200, by and between ("Contractor") and ("Subcontractor") as follows: Recital The owners of certain timber growing
ANNEXURE TO Australian Standard Minor Works Contract Conditions (Superintendent Administered) AS 4905 2002. Part A
ANNEXURE TO Australian Standard Minor Works Contract Conditions (Superintendent Administered) AS 4905 2002 Part A This Annexure shall be completed and issued as part of tender documents and subject to
IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer
THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE
COMMERCIAL CREDIT ACCOUNT APPLICATION
COMMERCIAL CREDIT ACCOUNT APPLICATION *Mandatory field required to process application Please complete the below form in BLOCK LETTERS ONLY ensuring all information is entered with as much detail as possible.
International Construction Warranties Limited. Terms & Conditions. Version UK1
International Construction Warranties Limited Terms & Conditions Version UK1 Rules of Registration Version 5 All Companies applying for or taking out a Warranty on a New Development with ICW shall comply
Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery
Document AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery INTRODUCTION Current practice in the construction industry promotes inefficiency when the key project
NOTE: SERVICE AGREEMENTS WILL BE DRAFTED BY RISK SERVICES SERVICE AGREEMENT
NOTE: SERVICE AGREEMENTS WILL BE DRAFTED BY RISK SERVICES SERVICE AGREEMENT Between: And: XXXXXX (the Contractor") Langara College 100 West 49 th Avenue Vancouver, BC V5Y 2Z6 (the College") The College
Measured development Construction and Engineering Training Supplement Guide
Construction and Engineering Training Supplement Guide Welcome Eversheds is the law firm behind some of the world s most ambitious construction and engineering projects. We have one of the biggest teams
PROCEDURES FOR THE NEW JERSEY DEPARTMENT OF BANKING AND INSURANCE MEDIATION PROGRAM FOR INSURANCE CLAIMS FOLLOWING STORM SANDY
Introduction PROCEDURES FOR THE NEW JERSEY DEPARTMENT OF BANKING AND INSURANCE MEDIATION PROGRAM FOR INSURANCE CLAIMS FOLLOWING STORM SANDY The Storm Sandy Mediation Program was established by the New
JCT Standard Building Contract 2011 - SBC/Q
JCT Standard Building Contract 2011 - SBC/Q Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: [email protected] www.rpp.co.uk Delivering Professional Solutions to the Property Industry
Framework Terms and Conditions
Introduction Framework Terms and Conditions These Framework Terms and Conditions form part of the contract to allow one or more Purchasing Agencies to purchase outcome-focussed services from the Provider.
Operating Agreement. WXYZ Company, LLC, a [State] Limited Liability Company
Operating Agreement WXYZ Company, LLC, a [State] Limited Liability Company THIS OPERATING AGREEMENT of WXYZ Company, LLC (the Company ) is entered into as of the date set forth on the signature page of
Internet Services Terms and Conditions
Internet Services Terms and Conditions 1. These terms and conditions These General Terms and Conditions apply to you if you are a business or residential telecommunications customer of Telnet Telecommunication
LEGAL INDEMNITY POLICY OF TITLE INSURANCE FOR COMMERCIAL PROPERTY COVERAGE FOR KNOWN RISK
LEGAL INDEMNITY POLICY OF TITLE INSURANCE FOR COMMERCIAL PROPERTY COVERAGE FOR KNOWN RISK ENGLAND & WALES (FORM KR E&W 03/09) SCHEDULE Online File Number 20499062 Policy Number KR (E&W) - 15317800316 Policy
AGENCY AGREEMENT ( Agreement )
AGENCY AGREEMENT ( Agreement ) PARTIES: CTC Transportation Insurance Services, LLC (CTC) and ("Agent ). Whereas, CTC is a California domiciled Managing General Agent and places coverage for commercial
SALEM STATE UNIVERSITY CLIPPERCARD MERCHANT AGREEMENT
SALEM STATE UNIVERSITY CLIPPERCARD MERCHANT AGREEMENT AGREEMENT made as of the day of by and between Salem State University, a Massachusetts state institution of higher learning having its principal offices
CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS
CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS 1. Definitions 1.1 In these Conditions: "Contract" means the contract between Peak Waste Recycling
ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS)
ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS) 1. Definitions In these Conditions: "Acceptance Form" means the acceptance form provided by Us to You with the Contract Documentation;
ICC UNIFORM RULES FOR CONTRACT BONDS
ICC UNIFORM RULES FOR CONTRACT BONDS issued as ICC publication No. 524, adopted by the ICC Executive Board on 23 April 1993, come into effect on 1 January 1994 Copyright 1993 International Chamber of Commerce.
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
Registration Procedures
REGISTRATION PROCEDURES 221 Registration Procedures Preamble These procedures ( Procedures ) are to be read in conjunction with FIFA Regulations for the Status and Transfer of Players ( FIFA Regulations
SCHEDULE 5 INSURANCE TABLE OF CONTENTS 1. INSURANCE REQUIREMENTS... 1
SCHEDULE 5 INSURANCE TABLE OF CONTENTS 1. INSURANCE REQUIREMENTS... 1 1.1 Project Specific Construction Period Insurance... 1 1.2 Additional Construction Period Insurance... 1 1.3 Operating Period Insurance
SCC ARBITRATION RULES OF THE ARBITRATION INSTITUTE OF THE STOCKHOLM CHAMBER OF COMMERCE
APPENDIX 3.13 SCC ARBITRATION RULES OF THE ARBITRATION INSTITUTE OF THE STOCKHOLM CHAMBER OF COMMERCE (as from 1 January 2010) Arbitration Institute of the Stockholm Chamber of Commerce Article 1 About
Design Development Agreement
Design Development Agreement June 2010 prepared by Larry Kirkland, PAN Council Member and The Law Office of Sarah Conley Disclaimer The Public Art Commission Agreement is made available as a service of
NHS Standard Contract 2015/16 General Conditions
NHS Standard Contract 2015/16 Draft for consultation December 2014 NHS Standard Contract 2015/16 Draft for consultation Version number: 1 First published: December 2014 Updated: Prepared by: NA NHS Standard
MINDSCAPE SOFTWARE LICENCE
MINDSCAPE SOFTWARE LICENCE By clicking the Accept button, Customer agrees that it has read, understood, and agreed to the terms and conditions of this Software Licence Agreement between Customer Mindscape
Number 34 of 2013 CONSTRUCTION CONTRACTS ACT 2013 ARRANGEMENT OF SECTIONS. 6. Right to refer payment disputes to adjudication.
Number 34 of 2013 CONSTRUCTION CONTRACTS ACT 2013 Section 1. Interpretation. ARRANGEMENT OF SECTIONS 2. Construction contracts: exceptions, etc. 3. Payments under construction contracts. 4. Payment claim
PENNSYLVANIA BUILDERS ASSOCIATION INSTRUCTIONS TO HOME IMPROVEMENT MODEL CONTRACT STANDARD FORM Introduction
PENNSYLVANIA BUILDERS ASSOCIATION INSTRUCTIONS TO HOME IMPROVEMENT MODEL CONTRACT STANDARD FORM Introduction Below are instructions for use with the Home Improvement Model Contract Standard Form, which
CONTRACTING HINTS AND TIPS
CONTRACTING HINTS AND TIPS Contents 1. Contract formation 2. Entire agreement clauses 3. Warranties and indemnities 4. Time of the essence 5. Contract variation 6. Exclusion and limitation clauses 7. Exercising
Terms and Conditions for Events and Services at the IET London: Savoy Place
Terms and Conditions for Events and Services at the IET London: Savoy Place Client Event Start Date Event End Date Event Timings Event (at which the Services are to be provided) @Event_Company_Name@ @Event_From_Date@
Breed Communications Limited - limited company consultancy agreement 230113
Limited Company Consultancy Master Agreement DATED BETWEEN:- (1) Breed Communications Limited (Company Number 4809384) whose registered office is c/o Hilton Consulting, 119 The Hub, 300 Kensal Rise, London
inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development
construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery SUBCONTRACTING ARRANGEMENTS