1 Requisition Approval Process (Quality Flowdown Provisions) QMS Process Coordinator: Process Leader: Christina Hunt Brad Wilcox Printed versions of the Quality Management System documents are for reference only and are subject to change at any time. It is the responsibility of all employees to verify the hardcopy version against the electronic copy on the Intranet. Page 1 of 13

2 DOCUMENT INFORMATION 1.0 Introduction The purpose of this procedure is to define the process in which variable quality provisions are established and communicated to the supplier through MACPAC to the requisition to ensure that purchased products and services meet quality design criteria. 2.0 Definitions / Acronyms Standard Quality Provisions (SQP) Variable Quality Provisions (VQP) SPOC General quality requirements applicable to all suppliers, in accordance with the SPOC Manual. The SPOC Manual is accessible through the Honeywell Supplier Portal Part, commodity or supplier specific quality requirements above those stated in SQPs that are specified in the requisition. Supplemental Purchase Order Provisions 3.0 References QMS QMS SPOC Manual QMS Image File Request and Validation Procedure for Out-sourced Software Receiving and Receiving Inspection Supplier Selection, Surveillance And Performance Rating Material Handling Guidelines 4.0 Forms / Records QMS Mail Survey Page 2 of 13

3 5.0 Procedure 5.1 Quality & Manufacturing Assurance (Q&MA or SQE) Responsibilities SQE shall: Providing the part or commodity specific quality provisions to the supplier through the requisition via MACPAC Reviewing drawings and specifications to gain knowledge of requirements. Note: Quality provisions are not required on non-product orders for consumables such as boxes, toothpicks, packaging materials, etc. When a requisition is received in RNAPR in MACPAC or when the Buyer notifies the SQE by phone or , the SQE shall flowdown quality provisions into the requisition through MACPAC XFQTEXT as follows: Selecting the appropriate supplier quality program; e.g., QS1, QS2 or QS3, using the appropriate VQP code. Note: Each requisition must have a specified quality program. Selecting any additional variable quality provisions by communicating the appropriate code(s) outlined in Section 6.0. Indicating that the part has been reviewed by adding, Reviewed by or Updated by and then initial and date at the end of the appropriate screen. Reviewing Engineering Change Orders (ECOs) to evaluate their affect on the quality provisions. If required, update the quality provisions to reflect the ECO change(s) and change the reviewed date. Note: Most ECOs do not affect quality provisions; therefore, a change in the reviewed date is only required when the ECO affects the quality provisions. Verifying the part number is set to OLA in the DEQA screen. SQE has the option to set the flag in the Insp Type field the default for this field is N. Note: Parts are not eligible for Dock-to-Stock (DTS) when Honeywell holds the TSO or PMA. The DTS flag can be turned off by indicating D in the Insp Type field in MACPAC. Adding or verifying the appropriate quality provisions (codes and part-specific, as applicable) are established in RNQAR or XFQTEXT Approving or disapproving the requisition in RNAPR after adding or verifying the appropriate quality provisions are established. Document reason for disapproval in FITEXT or by contacting the Buyer directly. If additional information is needed, contact the Buyer directly. MACPAC screen steps: RNAPR - Approve Requisition DEQA - Part Number Quality Setup RNQAR - Assign Text (Variable Quality Provision Codes) XFQTEXT - To add, change or delete QD (Quality Discretionary) text. 5.2 Redmond Designed Products Parts for Redmond Designed products transferred to Olathe shall be covered by this section. Parts for Redmond Designed products transferred to Olathe were originally transferred with Redmond codes. Redmond codes must be updated to Olathe codes for future procurements. Page 3 of 13

4 6.0 Change History and Applicability 6.1 QP Codes 1, 11 and 29 have been modified as of 7/7/98. QP Codes 4, 7, 16, 19 and 39 have been modified as of 9/9/98. QP Codes 42 and 45 have been modified and Code 47 added as of 1/22/99. QP Code 12 has been obsoleted and Code 48 added as of 4/12/99. QP Codes 22 through 28 have been modified as of 7/22/99. QP Codes 11, 38, 43 and 44 have been modified and Codes 49 and 50 added as of 8/11/00. QP Codes 5 and 9 have been modified and QP 51 added as of 03/15/02. QP Codes 2, 3 and 36 as of 11/1/02. QP Code 52 as of 5/9/03. QP Code 19 and 53 as of 7/18/03. QP Code 46 as of 9/22/03. QP Codes 4, 11 and 36 as of 12/19/03 QP Codes 1, 4, 5, 54 and 55 as of 7/26/04 QP Codes 5 and 11 as of 10/4/04 QP Code 33 as of 3/4/05 QP Codes 7 and 11 as of the document release date. QP Codes 4, 5 & 45 as of the document release date. QP Codes 10, 20, 37, 38, 42, 49 & 50 as of the document release date. QP5 Codes 2, 3, 5, 33, 56 and 57 as of the document release date. Added Appendix B with all R codes as of the document release date. QP Codes 11, 37 as of the document release date QP Codes 41 and 58 as of the document release date QP Code 59 as of the document release date Page 4 of 13

5 Extensively revised to incorporate the SPOC manual; all changes are effective with the document release date QP Code 07 updated to refer to SPOC 165 as of 4/24/08. Removed links to SPOC Manual in all applicable QP Codes. QP Code 08 updated to refer to SPOC 140 Table 3. QP 11 updated to SPOC only. QP Code 60 added, as of the document release date. QP Codes 1, 2, 3, 4, 11, 19, 45 and 48 changed, as of the document release date. QP55 obsoleted. QP Codes 7 and 60 updated, as of the document release date QP Codes 52 and 59 obsoleted as of the document release date QP Codes 1, 2 and 11 updated and QP61 and QP62 added, as of the document release date. QP Codes 1, 2, 3, 8, 13, 45, 46, 52 and 58 have been edited. Added SPOC 420 and QP63 are new. Note: All modifications will only show on orders placed after the document release date. Page 5 of 13

6 7.0 Appendices Appendix A Standard Variable Quality Provision (VQP) Codes QP01 QMS 2 Quality System Requirements. See the General Section of the SPOC Manual, paragraph Suppliers that do not meet the noted requirements may contact the Olathe Quality Manager for consideration of approval to an alternate Standard or assessment. The following SPOC codes will also apply: The general section of the SPOC manual, SPOC 100, 106, 239, 418 and 419 QP02 QMS 3 Quality System Requirements. See the General Section of the SPOC Manual, paragraph Suppliers that do not meet the noted requirements may contact the Olathe Quality Manager for consideration of approval to an alternate Standard or assessment. The following SPOC codes will also apply: The general section of the SPOC manual, SPOC 100, 106,127, 128.5, 149, 239, 418 and 419. Exception for supplier held FAA/EASA approval: SPOC 127 and 149 do not apply. QP03 QMS 4 Quality System Requirements. See the General Section of the SPOC Manual, paragraph Suppliers at this level shall maintain a quality system in accordance with AS9100. The following SPOC codes will also apply: The general section of the SPOC manual, SPOC 100, 106, 127, 128.5, 149, 239, 418 and 419. Exception for supplier held FAA/EASA approval: SPOC 127 and 149 do not apply. QP04 Key Characteristics Control Refer to SPOC QP05 QP07 Certificate of Compliance (COC). For QP01 parts the requirements outlined in SPOC 140 Group SPOC 003 apply. For QP2 & 3 parts the requirements outlined in SPOC 140 Group SPOC 002 apply. Special Processes Certification. Refer to SPOC 165 for technical requirements. And see SPOC 140 Table 3 for certification requirements. QP08 Raw Material Certification. Refer to SPOC 140, Table 3 Copies of the necessary documentation shall be submitted with product for verification and validation. QP09 Test Data. Copies of quantitative test data required by the purchase order or drawing shall accompany each shipment. QP10 Shelf Life (Honeywell Handling Code 10 ). Refer to SPOC 142 QP11 First Article Inspection Report (FAIR) Refer to SPOC 124. Page 6 of 13

7 QP13 QP14 Static Shielding (Honeywell Handling Code S ). Reference for Electrostatic Sensitive Devices Packaging Requirements. Supplier must operate with an Electrostatic Discharge program that complies with Mil-Std-1686 or ANSI/ESD S Static Shielding (Honeywell Handling Code S ). Components shall be delivered in anti-static conductive tubes in accordance with JEDEC specifications. QP15 Cosmetic Value (Honeywell Handling Code B ). Refer to SPOC 532 QP16 Delegation of Inspection Authority. Refer to SPOC 503 QP17 Delegation of MRB Authority. Refer to SPOC 529 Page 7 of 13

8 QP18 Delegation of Direct Ship Authority. Refer to SPOC QP19 Source Inspection is a requirement of this order. Refer to SPOC QP21 Leads shall be solderable when tested in accordance with MIL-STD-202, Method 208, Test Condition A. Refer to SPOC 325 (All Other Parts) QP22 Parts to be Tape and Reel per EIA STD RS-296 Class 1 Refer to SPOC 335 QP23 Parts to be Tape and Reel per EIA STD RS-296 Class II Refer to SPOC 335 QP24 Parts to be Tape and Reel per EIA STD RS-296 Class III Refer to SPOC 335 QP25 Parts to be Tape and Reel per EIA STD RS-468 H/HO=0.9 inch. Min. Refer to SPOC 335 QP26 Parts to be Tape and Reel per EIA STD RS-468-A Refer to SPOC 335 QP27 Parts to be Tape and Reel per EIA or 2 as applicable Refer to SPOC 335 QP28 Components to be double lead taped with spacing Refer to SPOC 335 QP29 QP30 QP31 QP32 QP33 QP34 QP35 QP36 Unique Packaging (Honeywell Handling Code A ). Parts require individual or special packaging to avoid damage due to corrosion, pin damage, contamination, impact, and/or handling damage. Supplier packaging (or equivalent) shall be maintained until assembly at Honeywell. Bending or Folding Damage (Honeywell Handling Code C ). Bending or folding can damage parts. Package in a manner to keep the parts flat. Temperature Sensitive (Honeywell Handling Code 31 ). Part is temperature sensitive. Package, store or re-package per drawing requirements. Magnetic Material (Honeywell Handling Code 32 ). Part is made from Magnetic material or contains magnetic parts. Package and store to prevent damage to these or other parts that could be affected by magnetic fields. Assembly at Honeywell (Honeywell Handling Code 33 ). Parts required hardware to be considered complete. Solderable Component (Honeywell Handling Code 34 ). Part solderability is susceptible to contamination. DO NOT TOUCH LEADS OR WEAR STATIC-SHIELDING FINGER COTS WHEN HANDLING. Vacuum Transfer Material (Honeywell Handling Code 35 ). Parts are extremely sensitive to handling damage. DO NOT TOUCH. Parts must be transferred from the package with a vacuum pickup tool (vacuum pen). Battery Storage and Shelf Life (Honeywell Handling Code 36 ). Do not store batteries on metallic shelving or in conductive anti-static material. Do not allow batteries to contact each other. Rechargeable batteries require re-charging every 6-months and are excess after 2-years. Primary Li batteries have 10-year shelf life. Page 8 of 13

9 QP37 QP38 QP39 QP40 QP41 QP42 QP43 QP44 Container Marking. Mark container (bag, box, etc.) of parts with the Honeywell part number. Non-static Generating Packaging for Non-ESD Products. Parts shall be packaged in non-static generating material. Painted parts or Bare Printed Wire Boards shall also be wrapped in tissue or Kraft paper to prevent contamination from anti-static package lubricants or treatments before placing them in the non-static generating packaging. Gyroscopic Instrument (Honeywell Handling Code GY ). Part is sensitive to frequent and abrupt movement. Store in a manner that minimizes the need to move often. Avoid Distortion of Proper Convergence (Honeywell Handling Code CV ). Do not store, package, or deliver this product with or near magnetic materials. Shock Sensitive Material (Honeywell Handling Code XL-Package parts to prevent damage from shock. Humidity Sensitive (Honeywell Handling Code HU ). Part is humidity sensitive. Storing, Packaging, and Re-Packaging this material in an airtight sealed container is required. Reference JEDEC STD 033. Category 1 Standard Product (Honeywell Internal Requirement only) Category 1 Non-Standard Product (Honeywell Internal Requirement only) QP45 ELECTRONIC ASSEMBLIES WORKMANSHIP REQUIREMENTS as applicable: HPS1007 APPLICATION OF CONFORMAL COATING HPS1008 CABLE AND WIRE HARNESS ASSEMBLIES HPS1009 SOLDERED ELECTRICAL AND ELECTRONIC ASSY. HPS1011 REQUIREMENTS FOR RIGID PRINTED BOARDS (PB) HPS1017 REQUIREMENTS FOR FLEXIBLE / RIGID-FLEX PRINTED BOARDS (PB) QP46 For Purchased End Items with TSO/PMA Tags Refer to SPOC 535 Tag shall indicate NEW status unless otherwise agreed to. QP47 For Purchased Circuit Card Assemblies with Software. Refer to QMS QP48 QP50 For Purchased Kits Refer to SPOC 239, with an additional requirement that interior plastic or ESD bags shall be permanently sealed Workmanship Standard, Specification is a requirement of this order. QP51 Workmanship Standard Refer to SPOC 558 QP52 Purchased Circuit Card Assemblies SPOC 544 QP53 QP54 QP55 Test Data Requirements for Olathe TSO/PMA Products, supplier shall submit test data and other inspection data that shows evidence that the product meets the approved design data requirements for each serial number submitted to the Buyer. Test Data Requirements for Nonconforming Products, when the supplier fails to consistently deliver product that meets the drawing and/or specification requirements, the supplier shall provide evidence of process control (1.33 CpK or greater) on the product features identified below that lead to the poor performance and initiation of this process control requirement: Purchased End Items with Supplier Held TSO/PMA Obsolete Page 9 of 13

10 QP56 QP57 Electrolytic Device, This part contains an electrolyte that must be recharged or reformed after 5-years from the date of manufacture. Leakage current testing is to be done as required by the drawing. Parts shall be scrapped after 10-years from the date of manufacture. Bag and Tag Parts, Parts must be individually bagged, permanently sealed and marked with the Honeywell part number on the bag. Parts with hardware shall be kitted together with its corresponding hardware to form a complete unit and permanently sealed in a bag with the Honeywell part number labeled on the bag. QP58 GRESS Assessments: Refer to SPOC 537. The requirements flowed via this SPOC are accomplished through the SPRA (Supplier Product Realization Assessment). SPRA is a product-oriented process assessment performed at the Supplier site with the aim of verifying that methodologies / policies / processes, based on best practices, are formalized, implemented and proven effective (ref. SPRA Procedure AP-1614). QP59 Key Characteristic: Bare board plated through-hole thickness Obsolete See QP04. QP60 Interdivision Order Requirements: See SPOC 008 QP61 Contract Manufacturers: See Section 3 Group SPOC 009 QP62 Application of Thread Locker: For all Honeywell - Olathe products, sub assemblies and end items the supplier shall apply liquid stake to all threaded fasteners per Honeywell specification unless otherwise specified by the Engineering Drawing or Specification. Page 10 of 13

11 SPOC 562 SPOC 562 COMPONENT TRACEABILITY ** THE SUPPLIER OF ANY COMPONENT ASSEMBLY SHALL BE ABLE TO, UPON REQUEST, PROVIDE A LIST OF ALL MATERIAL UTILIZED IN THE CREATION OF SAID ASSEMBLY. MATERIAL REQUIRING TRACEABILITY INCLUDES ELECTRICAL COMPONENTS, THE ACTIVE AND PASSIVE PARTS AND ITEMS IN THE SCHEMATIC. IT DOES NOT INCLUDE NON CRITICAL PARTS SUCH AS HARDWARE AND OTHER MECHANICAL PARTS. THE LIST SHALL CONTAIN AS APPLICABLE: * THE COMPONENT NAME * COMPONENT OEM MANUFACTURER * HONEYWELL PART NUMBER * MANUFACTURER PART NUMBER * QUANTITY * REFERENCE DESIGNATOR WHERE USED * SERIAL NUMBER * LOT NUMBER AND / OR MANUFACTURING DATE * ANY DISTINGUISHING MARKINGS THAT WOULD AID IN TRACEABILITY * ALSO REQUIRED TO BE PROVIDED, UPON REQUEST, IS THE COMPONENT DISTRIBUTOR AND PROCUREMENT DATE OF EACH COMPONENT LISTED. SPOC 420 H01 H02 H03 H04 H05 H06 THE SYSTEM MUST ACCOUNT FOR ANY / ALL COMPONENTS THAT REQUIRE REPLACEMENT PAST INITIAL INSTALLATION. THE TRACEABILITY MUST BE MAINTAINED THROUGHOUT THE MANUFACTURING PROCESS FROM WORK ORDER LAUNCH TO SHIPPING TO HONEYWELL. IN ADDITION TO THE COMPONENT TRACEABILITY, THE SUPPLIER SHALL, UPON REQUEST, PROVIDE ALL NECESSARY PROCESSING HISTORY FOR THE ASSEMBLY IN QUESTION. THIS SHALL INCLUDE PROCESS NAME, DATE AND TIME, LOCATION, AND OPERATOR ID OF THE PERSONNEL PERFORMING THE FUNCTION. SPOC 420 Advanced Product Quality Planning. Advanced Product Quality Planning (APQP) is a structured method of defining and establishing the necessary activities to ensure that all product will satisfy the requirements of Honeywell. The goal of APQP is to establish mature product quality and program launch. Honeywell Handling code M Matched set. Parts need to be packaged and kept as a set Honeywell Handling Code R. These parts will be sent out to be reconditioned per the part requirements. Sealed bearing No shelf life requirement. Radioactive Material. Take precautions with material. If breach should occur contact HS&E immediately. Not moisture sensitive. H07 Battery shelf life must be no less than 90% at time of shipment. SR01 Special Requirement % inspect rotor diameter at 22 C per drawing. ( tolerance). Parts must stabilize at this temperature for at least 4 hours before measurement. You must avoid handling the part as much as possible before measurement. Page 11 of 13

12 8.0 Revision History Revision Revision Date Release Date Description of Change - 4/29/98 XX/XX/XX Original release; document revised and replaces MQ0030, Rev. 4 A 10/9/98 10/13/98 Updated document to add effectivity statement in para. 1.0, added Forms, and modified QP codes 1, 5, and 29. Revised Para. 1.0 to indicate updated QP codes, updated QP Codes 04, 07, 16, 19 & 39. B 1/22/99 2/4/99 Added QP Code 47; changed Code 45 was IPC-RB-267, and modified wording of QP 42. Also, added QMS to Reference Section and QMS to the Forms Section of this document. C 4/12/99 4/13/99 Obsoleted QP Code 12 (replaced by QP13) and added Code 48. D 6/15/99 7/22/99 Added For order quantities... statement to QP Codes 22 through 28 modified QP 18 and added clarification to DTS program in para E 8/3/00 8/11/2000 Modified QP11 to allow for a different set of guidelines established by ATR & B&GA. Modified QP 38, 43 and 44. Added Codes 49 & 50. Changed AlliedSignal to Honeywell throughout document. F 3/15/02 3/15/02 Updated Process Coordinator and Leader, changed Commodity to Supplier Quality throughout document, moved effectivity from Section 1.0 to new Section 6.0, added paragraph 5.2, added QP51 and updated QP07 and 38. G 11/1/02 11/4/02 Added Operations Engineer in appropriate location throughout document. Modified QP Codes 2, 3 and 36. H 4/28/03 5/7/03 Added QP Code 52. Clarified OE/SQE roles in paragraph 5.1 I 7/8/03 7/21/03 Added QP Code 53 updated QP19 and updated associated paragraph 6.1. and J 9/16/03 9/16/03 Updated QP46 and paragraph 6.1 K 12/12/03 1/7/04 Updated QP codes 4, 11 and 36 and paragraph 6.1 L 7/22/04 7/22/04 Updated codes 1, 4 and 5; added codes 54 and 55. M 10/1/04 10/1/04 Updated codes 5 and 11 and replaced QMS with the Mail Survey in Section 4.0. Removed ML designator from document number. N 3/1/05 3/1/05 Updated QP code 33 and paragraph 6.1. O 5/3/05 5/6/05 Updated QP codes 7 & 11 and paragraph 6.1 P 9/20/05 9/27/05 Updated QP codes 4, 5, corrected typo in QP 45 and updated paragraph 6.1. Added QMS Purchase Order Standard Quality Provisions to Section 3.0. Removed obsolete QMS and from document. Q 6/20/06 6/29/06 Removed QMS from Reference Section, Removed OE from the document, Removed PFC requirement (see QMS ), Updated QP10, 37, 38, 42, 49 & 50 and Obsoleted QP20. R 7/24/06 8/4/06 Updated QP2, 3, 5 and 33; added QP 56 and 57 and some minor changes S 11/8/06 11/8/06 Added Appendix B for Redmond Codes, Renamed Section 7 to Appendices and first appendix to Appendix A. Corrected the URL in QP11. Changed the title of QP37 to Container Marking from Individual Marking. Page 12 of 13

13 Revision Revision Date Release Date Description of Change T 5/10/07 5/14/07 Update QP41 to remove individual added QP58 Changed reference from to QMS U 10/15/07 10/15/07 Added QP59 V 4/24/08 4/24/08 Extensively revised to incorporate the SPOC manual; all changes are effective with the document release date W 4/23/08 4/29/2008 QP07 updated to refer to SPOC 165. Updated Revision date of Rev V to show correct date. Updated 6.0 Change History and Applicability. X 5/8/08 5/9/08 Removed reference to QMS as it is obsolete. Removed links to SPOC Manual in flowdown text. Y 6/18/08 6/26/08 Requisition Approval Process (Quality Flow down Provisions), Rev X to Rev Y, Owner: Noel Betow, Campus: Olathe, Update required to change QP08 to refer to SPOC 140, Table 3 and QP11 to FAIR Refer to SPOC only with ) Z 1/14/09 1/20/09 Removed Redmond codes, added QP60, updated paragraphs 5.2 and 6.1 AA 1/21/09 2/3/2009 Revised QP1, 2, 3, 4, 11, 19, 45 and 48 to reflect changes in Revision H of the SPOC manual. Obsoleted QP55 (consolidated with QP46). And update 6.1 AB 9/4/09 9/07/2009 Updated QP07 to add certification requirements and updated QP60 to address new guidelines for Interdivisional Orders AC 11/10/09 11/19/09 Obsoleted QP52 and QP59. No longer needed with updates to SPOC Replaced references from Supplier Quality Engineer to PE throughout the document. AD 4/22/10 06/04/10 Updated QP01, 02 and QP11 and added QP61 and 62 AE 06/15/11 06/29/11 Updated QP11, QP47 and added SPOC 562. AF 12/12/13 03/13/14 QP Codes 1, 2, 3, 8, 13, 45, 46, 52 and 58 have been edited. Added SPOC 420, H01-06 and SR01. Other minor text changes. END OF DOCUMENT Page 13 of 13

Unincorporated changes to Revision J of the SPOC Manual UPDATED November 22, 2011

Unincorporated changes to Revision J of the SPOC Manual UPDATED November 22, 2011 Aerospace Unincorporated changes to Revision J of the SPOC Manual UPDATED November 22, 2011 The SPOC Manual is controlled in Electronic format as presented on the Supplier Portal and Honeywell Intranet.

More information

Quality Assurance Provisions

Quality Assurance Provisions Page 1 of 5 1. Purpose and Scope. The purpose of this document is to define the Quality Assurance Provisions FLIR Systems Inc. requires for inventory material received from Suppliers. This document applies

More information

Supplier Quality Requirements and Clauses

Supplier Quality Requirements and Clauses Supplier Quality Requirements and Clauses Supplier Quality Requirements General The following Quality Notes (QN01 through QN19) apply to and form a part of all Purchase Orders issued by Advanced Conversion

More information

L-3 Communications Corporation AMI Purchase Order Supplement No. 3 Quality Assurance

L-3 Communications Corporation AMI Purchase Order Supplement No. 3 Quality Assurance Q10 QUALITY SYSTEM REQUIREMENTS Q10A Q10B ISO 9001:2008 Seller s quality system shall be in compliance with the requirements of ISO 9001, Model for in Design, Development, Production, Installation and

More information

2.1.1. Distributors In addition to the requirements noted herein, Distributors shall have a Quality System

2.1.1. Distributors In addition to the requirements noted herein, Distributors shall have a Quality System 1. Purpose This document defines requirements for suppliers providing aerospace and defense materials, products and services to Electromech Technologies. Supplier acceptance of a purchase order from Electromech

More information

Self-Audit Checklist

Self-Audit Checklist Page 1 Company Name: Date of audit: Date of last audit performed: Name of person performing self-audit: Signature: Name of person responsible for quality system: Signature: Number of non-compliances: Page

More information

Plan QAQ-82-001 Supplier Quality Requirements (Rev 10)

Plan QAQ-82-001 Supplier Quality Requirements (Rev 10) 1.0 Purpose To outline Insitu s quality management system requirements for suppliers. 2.0 Scope This document applies to suppliers and subcontractors that provide products and/or services that affect the

More information

PERFORMANCE EXCELLENCE Procurement Standards

PERFORMANCE EXCELLENCE Procurement Standards PERFORMANCE EXCELLENCE Procurement Standards AEROSPACE PRODUCTS Agile Revision: D Sparton Quality Policy: It is the goal of Sparton Corporation and it subsidiaries ( Sparton ) to deliver value through

More information

Copyright 2006 Quality Excellence for Suppliers of Telecommunications Forum

Copyright 2006 Quality Excellence for Suppliers of Telecommunications Forum Release 4.0 4.2.3 4.2.3.C.1 Control of Customer- Supplied Documents and Data The organization shall establish and maintain a documented procedure(s) to control all customer-supplied documents and data

More information

Product Order Quality Requirements Meggitt (Orange County), Inc.

Product Order Quality Requirements Meggitt (Orange County), Inc. Product Order Quality Requirements Meggitt (Orange County), Inc. Reference QP8-051, Purchase Order Quality Requirements QP8-055, Review/Control Supplier Documentation PP-401, Quality Assurance Codes 50-2-351,

More information

Supplier Quality. Assurance Provisions. Manual. SQAP-001 Rev. E

Supplier Quality. Assurance Provisions. Manual. SQAP-001 Rev. E 9060 WINNETKA AVENUE NORTHRIDGE, CA 91324 USA Supplier Quality Assurance Provisions Manual SQAP-001 Revision E Page 1 of 14 Table of Contents 1 General Requirements... 4 1.1 Supplier Control... 4 1.2 Supplier

More information

PPI/TZ Standard Quality Requirements for Suppliers -SQRS-

PPI/TZ Standard Quality Requirements for Suppliers -SQRS- PPI/TZ Standard Quality Requirements for Suppliers -SQRS- AS9100, ISO 13485 and ISO 9001 Revision: November 16, 2015 For questions concerning Standard Quality Requirements for Supplier (SQRS), please contact

More information

Quality Assurance Requirements. For. Pratt & Whitney/Space Propulsion, Chemical Systems Division

Quality Assurance Requirements. For. Pratt & Whitney/Space Propulsion, Chemical Systems Division Quality Assurance Requirements For Pratt & Whitney/Space Propulsion, FORM 06.13.02.02 (REV. 6) Page 1 of 14 Table of Contents SECTION I QUALITY SYSTEMS REQUIREMENTS... 5 1. QUALITY ASSURANCE PROGRAM...

More information

1) CERTIFICATE OF COMPLIANCE/CONFORMANCE

1) CERTIFICATE OF COMPLIANCE/CONFORMANCE Standard Supplier Quality Requirements This document defines restrictions and quality system requirements applicable when goods and services are procured to SMART ELECTRONICS part numbers or Military,

More information

Aviation Suppliers Association Quality System Standard. ASA-100 Revision 4.0

Aviation Suppliers Association Quality System Standard. ASA-100 Revision 4.0 Page 1 Aviation Suppliers Association Quality System Standard ASA-100 Revision 4.0 Original Issue: March 1994 Revision 4.0 Release Date: August 1, 2015 Effective Date: August 24, 2015 Copyright 1994-2015

More information

Purchase Order Clauses and Conditions

Purchase Order Clauses and Conditions Purchase Order Clauses and Conditions All purchase orders for materials, special processes, machining and fabrication services and end items are subject to the following requirements: General Requirements:

More information

Quality Supplier Requirements for Beckwith Electric Co., Inc.

Quality Supplier Requirements for Beckwith Electric Co., Inc. Quality Supplier Requirements for Beckwith Electric Co., Inc. This Page Left Intentionally Blank To Our Valued Suppliers: One of the primary goals of Beckwith Electric is to provide the highest Quality

More information

ATTACHMENT "Q" PURCHASE ORDER QUALITY CLAUSES

ATTACHMENT Q PURCHASE ORDER QUALITY CLAUSES 1 of 8 Q0. Instructions: Review your Purchase Order for any Q clauses listed below. Specific clauses other than Q0 apply only when listed on the PO. All certifications provided to CAI are to be complete,

More information

GE Power Electronics Business Total Quality Management for Suppliers

GE Power Electronics Business Total Quality Management for Suppliers GE Power Electronics Business Total Quality Author: Reviewers: Contributors: Alessandro A. Cervone Technical Manager Component & Reliability Engineering Alicia Scott Title Erika Nannis Title Robert Roessler

More information

MOUSER ELECTRONICS QUALITYMANUAL

MOUSER ELECTRONICS QUALITYMANUAL MOUSER ELECTRONICS QUALITYMANUAL QS-QM-001 REV L9/25/09 This page intentionally left blank. Page 2 of 27 TABLE OF CONTENTS 1.0 Forward...5 2.0 Introduction...5 3.0 Mission Statement...5 4.0 Quality Management

More information

KOLLMORGEN. Title: Standard Operating Procedure Counterfeit Parts

KOLLMORGEN. Title: Standard Operating Procedure Counterfeit Parts Approved By: Elliott Major Date: 11-19-09 Page 1 of 9 Rev ECO Date Approve Rev ECO Date Approve A R01_13541 07-23-10 DWL B R01_14787 12-15-11 DWL C R01_14910 03-07-12 DWL D R01_14964 04-16-12 DWL 1.0 Purpose

More information

Supplier Quality Assurance Requirements Manual

Supplier Quality Assurance Requirements Manual 12716 EAST PINE STREET TULSA, OK 74116 Supplier Quality Assurance Requirements Manual Approved: Mike Collins Quality Assurance Manager Precise Machining & Manufacturing 1 Record of Revisions Revision D

More information

QP-740. Supplier Management Handbook

QP-740. Supplier Management Handbook QP-740 Supplier Management Handbook Revision H Revision Date Reason Signature - 2/02/08 Initial Release Avis Rosenfield A 12/10/10 Complete update Ritchie Lacson B 4/14/11 Add sections: 6.4, 6.5, 9.9,

More information

AS9100 Quality Manual

AS9100 Quality Manual Origination Date: August 14, 2009 Document Identifier: Quality Manual Revision Date: 8/5/2015 Revision Level: Q AS 9100 UNCONTROLLED IF PRINTED Page 1 of 17 1 Scope Advanced Companies (Advanced) has established

More information

Benchmark Phoenix and Tijuana Supplier Quality Control Requirements (PSQC)

Benchmark Phoenix and Tijuana Supplier Quality Control Requirements (PSQC) PURPOSE This document establishes basic Quality Control Requirements specific to Benchmark Phoenix and Tijuana Facilities, PO Special Provisions and any Required or Mandatory Contractual Flow-downs that

More information

INTRODUCTION: PURPOSE:

INTRODUCTION: PURPOSE: UMBRA CUSCINETTI, INC. 2916 100 th Street SW Everett, WA 98204-1340 USA 425-743-2577 FAX: 425-347-0682 Printed versions may not be the latest. Suppliers shall utilize the latest version which can be found

More information

ISO/IEC 17025 QUALITY MANUAL

ISO/IEC 17025 QUALITY MANUAL 1800 NW 169 th Pl, Beaverton, OR 97006 Revision F Date: 9/18/06 PAGE 1 OF 18 TABLE OF CONTENTS Quality Manual Section Applicable ISO/IEC 17025:2005 clause(s) Page Quality Policy 4.2.2 3 Introduction 4

More information

Supplier Quality Assurance Requirements Manual

Supplier Quality Assurance Requirements Manual 1701 West Tacoma Broken Arrow, Ok. 74012 Supplier Quality Assurance Requirements Manual Approved: Bryan Sanderlin President/COO/CEO OSECO, Inc. Darrel Bilke Quality Assurance Manager OSECO, Inc. 1 Record

More information

Helical Products Co., Inc.

Helical Products Co., Inc. Q01 GENERAL REQUIREMENTS 1. Supplier Responsibilities 1.1. Delivery Certification By delivering products or services on the Contract, the Supplier certifies that such products or services are in compliance

More information

Example ESD Control Program Document Based on ANSI/ESD S20.20-2007

Example ESD Control Program Document Based on ANSI/ESD S20.20-2007 PROFESSIONAL STATIC CONTROL SERVICES Example ESD Control Program Document Based on ANSI/ESD S20.20-2007 The following document demonstrates the structure for an ESD control program that is compliant to

More information

UNCONTROLLED COPY FOR REFERENCE ONLY

UNCONTROLLED COPY FOR REFERENCE ONLY CLOVER MACHINE AND MFG. 800 MATHEW ST. #101 SANTA CLARA, CA 95050 727-3380 727-7015 fax REVISION: DATE: PAGE 1 OF 45 QUALITY POLICY MANUAL DISTRIBUTION LIST: President Purchasing Manager Vice President

More information

Acceptability of Printed Circuit Board Assemblies

Acceptability of Printed Circuit Board Assemblies Section No.: 12I.2.3, Sheet 1 of 9 Rev Level: 16 Additional Distribution: PCB Assembly Subcontractors 1.0 Purpose 2.0 Scope Acceptability of Printed Circuit Board Assemblies 1.1 The purpose of this standard

More information

SUPPLIER Form #: 007 AUDIT QUESTIONNAIRE

SUPPLIER Form #: 007 AUDIT QUESTIONNAIRE 1.0 BACKGROUND INFORMATION Company Name: Company Address: Phone Number: Fax Number: Number of years in business: Number of employees: Annual Sales in Dollars: Size of Facility in Square Feet: Name of Senior

More information

Copies of this document shall be classified either as Controlled or Uncontrolled, and shall be identified as such on the cover sheet.

Copies of this document shall be classified either as Controlled or Uncontrolled, and shall be identified as such on the cover sheet. INTRODUCTION This document describes an inspection system broken down into four separate levels. When Inspection Level IV is invoked, this system meets the requirements of former MIL-I-45208A. The primary

More information

Q2A First Article Inspection (FAI) AS9102 * Revised ** Added

Q2A First Article Inspection (FAI) AS9102 * Revised ** Added Page 1 of 5 Q2A First Article Inspection (FAI) AS9102 * Revised ** Added NOTE: A hard copy of this document may not be the document currently in effect. The current version is always the version on the

More information

Packaging Information for Vendors

Packaging Information for Vendors Packaging Information for Vendors ngineer Approved This specification is provided to inform vendors of Raytheon Systems Company's minimum packaging requirements. This document is superseded by any special

More information

Cartel Electronics. AS 9100 Quality Systems Manual

Cartel Electronics. AS 9100 Quality Systems Manual Cartel Electronics AS 9100 Quality Systems Manual 1900 C Petra Lane Placentia, California 92870 Introduction Cartel Electronics, as a global supplier to the aviation, space, and space industries, has developed

More information

Gulfstream Production Certificate Operations

Gulfstream Production Certificate Operations SUPPLIER QUALITY ASSURANCE SYSTEM REQUIREMENTS SQAR 0001 REV D Supplier s Quality System David H. Trucksis Donald A. Strickland R. Christiansen PREPARED BY: REVIEWED BY: APPROVED BY: Robert W. Mullen Jr.

More information

This page intentionally left blank

This page intentionally left blank This page intentionally left blank Page 2 of 28 . TABLE OF CONTENTS 1.0 Forward... 5 2.0 Introduction... 5 3.0 Mission Statement... 6 4.0 Quality Management Systems... 6 4.1 General Requirements... 6 4.2

More information

Chandler-Arrow Division Arrow Supplier Quality Requirements

Chandler-Arrow Division Arrow Supplier Quality Requirements AQR-1 QUALITY SYSTEM Supplier must maintain a quality system that meets, as a minimum, the requirements of ISO9001-2008, unless otherwise directed by Chandler-Arrow Division QA organization. Immediate

More information

SOLDERING ELECTRICAL AND ELECTRONIC EQUIPMENT

SOLDERING ELECTRICAL AND ELECTRONIC EQUIPMENT Sheet 1 of 6 SOLDERING OF ELECTRICAL AND ELECTRONIC EQUIPMENT EXPORT CONTROLLED - WARNING This document may contain information that is subject to the International Traffic in Arms Regulations (ITAR) or

More information

SUPPLIER QUALITY MANAGEMENT SYSTEM QUESTIONNAIRE

SUPPLIER QUALITY MANAGEMENT SYSTEM QUESTIONNAIRE Company Name Street Address City, State, Zip code Phone Number Fax Company Website Email Address ORGANIZATION NAME PHONE NUMBER EMAIL ADDRESS President/CEO General Manager Engineering Manager Production

More information

Aviation Suppliers Association Quality System Standard. ASA-100 Revision 3.5

Aviation Suppliers Association Quality System Standard. ASA-100 Revision 3.5 Page 1 Aviation Suppliers Association Quality System Standard ASA-100 Revision 3.5 Original Issue: March 1994 Revision 3.5 Release Date: September 1, 2008 Effective Date: November 1, 2008 Copyright 1994-2008

More information

QUALITY MANUAL REVISION RECORD

QUALITY MANUAL REVISION RECORD Page 2 of 31 REVISION RECORD Date Rev Description Jun 18, 2007 N/C Original Issue Sep 16, 2009 A Update to ISO 9001:2008 Standard. Feb 04, 2010 B Revised exclusions, removed (Except 7.3.7 from the exclusion

More information

GLOBAL AEROSPACE PROCEDURE

GLOBAL AEROSPACE PROCEDURE 1 of 13 1. PURPOSE: This procedure establishes the minimum PPG Aerospace requirements for a Supplier's Quality Plan. These requirements pertain to the documentation and inspection/testing necessary to

More information

Appendix QX. Supplier Quality Requirements

Appendix QX. Supplier Quality Requirements Appendix Q Appendix Q Supplier Quality Requirements The latest issue to this document is the version that is available on the Lockheed Martin Aero website: http://www.lockheedmartin.com/us/aeronautics/materialmanagement.html

More information

Company Quality Manual Document No. QM Rev 0. 0 John Rickey Initial Release. Controlled Copy Stamp. authorized signature

Company Quality Manual Document No. QM Rev 0. 0 John Rickey Initial Release. Controlled Copy Stamp. authorized signature Far West Technology, Inc. ISO 9001 Quality Manual Document No.: QM Revision: 0 Issue Date: 27 August 1997 Approval Signatures President/CEO Executive Vice President Vice President/CFO Change Record Rev

More information

QUALITY ASSURANCE PROVISIONS OF PURCHASE ORDER

QUALITY ASSURANCE PROVISIONS OF PURCHASE ORDER QUALITY ASSURANCE PROVISIONS OF PURCHASE ORDER Lockheed Martin and LMC hereinafter shall mean Lockheed Martin Maritime Systems & Sensors, Maritime Security & Ship Systems (MS&SS), a Lockheed Martin Company.

More information

New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification

New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification Revision A New Program Quality Requirements for Suppliers Rev.

More information

Cessna - Interiors Manufacturing Facility (IMF) Supplier Quality System Requirements

Cessna - Interiors Manufacturing Facility (IMF) Supplier Quality System Requirements Cessna - Interiors Manufacturing Facility (IMF) Supplier Quality System Requirements Wichita KS Effective: 3-11-15 Rev. IR Page 1 of 6 1.0 Introduction This document establishes Cessna Interiors Manufacturing

More information

Installation. Smart-UPS VT MGE Galaxy 3500. Maintenance Bypass Panel. 10-40 kva 400 V

Installation. Smart-UPS VT MGE Galaxy 3500. Maintenance Bypass Panel. 10-40 kva 400 V Installation Smart-UPS VT MGE Galaxy 3500 Maintenance Bypass Panel 10-40 kva 400 V Contents Safety.................................................. 1 Save these instructions...................................

More information

Q2A First Article Inspection (FAI) AS9102

Q2A First Article Inspection (FAI) AS9102 Page 1 of 7 Q2A First Article Inspection (FAI) AS9102 A hard copy of this document may not be the document currently in effect. The current version is always the version on the Lockheed Martin network.

More information

Bogue Machine Company, Inc. Business Instruction

Bogue Machine Company, Inc. Business Instruction Bogue Machine Company, Inc. Business Instruction Document Title: Supplier Quality Control Requirements Document Number: Revision: Document Owner: Mark Bogue Backup Owner: Craig Bogue Parent Document: PURP-004,

More information

Quality System Manual

Quality System Manual Chalmers & Kubeck, Inc. Quality System Manual ISO 9001:2008 Control #:00 Rev. 4 (02-01-11) Chalmers & Kubeck, Inc. Quality System Manual Scope Chalmers & Kubeck Inc. is a job shop that performs new manufacturing

More information

AMETEK Airtechnology Group Ltd

AMETEK Airtechnology Group Ltd Page 1 of 16 AMETEK Airtechnology Group Ltd Locations: Airscrew Muirhead Aerospace Traxsys Input Products 111 Windmill Road, Sunbury on Thames, Middlesex, TW16 7EF Oakfield Road, Penge London SE20 8EW

More information

New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification

New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification New Program Quality Requirements for Suppliers (NPQR) For Limited Manufacturing of Components and/or Processes for Engineering Certification Revision - New Program Quality Requirements for Suppliers Rev.

More information

How To Manage A Plant

How To Manage A Plant MALAT 9100 QUALITY REQUIREMENTS For Suppliers of Category 12, 13 This Document is located in the Internet site http://www.iai.co.il/sip_storage/files/2/35782.pdf Date: March 2012 Prepared by : S. Migdal

More information

Quality Management Systems Manual

Quality Management Systems Manual Washington Division Quality Management Systems Manual ISO 13485:2003 DOCUMENT NUMBER 01-QM-MED REVISION LEVEL 01 PAGE 1 of 40 This manual describes the quality management systems structure at GM Nameplate

More information

webampl Training December 2015

webampl Training December 2015 webampl Training December 2015 Aerospace Approved Manufacturer Parts List (AMPL) What is it? The AMPL is a database that manages the approved relationship between Honeywell Part Numbers and Manufacturer

More information

2. CANCELLATION. AC 20-62D, Eligibility, Quality, and Identification of Approved Aeronautical Replacement Parts, dated May 24, 1996, is canceled.

2. CANCELLATION. AC 20-62D, Eligibility, Quality, and Identification of Approved Aeronautical Replacement Parts, dated May 24, 1996, is canceled. U.S. Department of Transportation Federal Aviation Administration Advisory Circular Subject: Eligibility, Quality, and Identification of Aeronautical Replacement Parts Date: 12/23/10 Initiated by: AFS-300

More information

ALL PRODUCTS MFG & SUPPLY

ALL PRODUCTS MFG & SUPPLY ALL PRODUCTS MFG & SUPPLY 618 ANDERSON DRIVE ROMEOVILLE, IL 60446 PHONE: 877-255-8700 FAX: 877-255-8701 WWW. APGASKET.COM QUALITY MANAGEMENT SYSTEM MANUAL DATE: 11/20/12 REVISION 9.1 UNCONTROLLED COPY

More information

SUPPLIER QUALITY PROGRAM, V (U)

SUPPLIER QUALITY PROGRAM, V (U) FEDERAL MANUFACTURING & TECHNOLOGIES PQR 1060 PAGE 1 OF 17 SUPPLIER QUALITY PROGRAM, V (U) CHANGE HISTORY ISSUE DESCRIPTION OF CHANGE AUTHOR DATE E CORRECTED CHANGE HISTORY S. L. HALTER 10/18/2000 F UPDATED

More information

Service Guide for AC Drives and Soft Starters Supplement to the Schneider Electric Conditions of Sale Class 8800

Service Guide for AC Drives and Soft Starters Supplement to the Schneider Electric Conditions of Sale Class 8800 Service Guide for AC Drives and Soft Starters Supplement to the Schneider Electric Conditions of Sale Class 8800 Data Bulletin 8800DB0101R12/12 12/2012 Retain for future use. 8800DB0101R12/12 Service

More information

Anti-Counterfeit Policy Mouser has adopted this Anti-Counterfeit Policy to eliminate the impact of counterfeit products on Mouser and its customers.

Anti-Counterfeit Policy Mouser has adopted this Anti-Counterfeit Policy to eliminate the impact of counterfeit products on Mouser and its customers. QS-PR-024 Anti-Counterfeit Control Plan Approved by: Chuck Amsden Approved 1/19/15 This procedure is current and approved when viewed on-line. The procedure becomes uncontrolled when printed. Uncontrolled

More information

Quality Requirements for ADTRAN Hardware Repair Service Suppliers

Quality Requirements for ADTRAN Hardware Repair Service Suppliers Quality Requirements for ADTRAN Hardware Repair Service Suppliers Foreword ADTRAN designs and manufactures telecommunications equipment that has an enviable reputation for high reliability and quality

More information

Turbo Resources International Quality Procedure

Turbo Resources International Quality Procedure TURBO RESOURCES INTERNATIONAL QUALITY MANAGEMENT SYSTEM MANUAL APPROVALS: Revision : 46 Page : 1 of 53 TABLE OF CONTENTS INTRODUCTION 3 1. SCOPE 4 1.1 GENERAL 4 1.2 APPLICATION 5 2. NORMATIVE REFERENCE

More information

Supplier Quality Management Handbook

Supplier Quality Management Handbook Supplier Quality Management Handbook PREPARED BY: ORGANIZATION: DATE: Byron Murray SYS 05/20/2013 APPROVALS (Name): ORGANIZATION: APPROVAL DATE: Javier Marti CCB Chair 06/12/2013 Krista Laursen CCB Chair

More information

Table of Contents 1. SCOPE... 3 2. APPLICABLE DOCUMENTS... 4 3. TERMS AND DEFINITIONS... 4 4. QUALITY MANAGEMENT SYSTEM...4-8

Table of Contents 1. SCOPE... 3 2. APPLICABLE DOCUMENTS... 4 3. TERMS AND DEFINITIONS... 4 4. QUALITY MANAGEMENT SYSTEM...4-8 Table of Contents 1. SCOPE... 3 2. APPLICABLE DOCUMENTS... 4 3. TERMS AND DEFINITIONS... 4 4. QUALITY MANAGEMENT SYSTEM...4-8 5. MANAGEMENT RESPONSIBILITY...8-9 6. RESOURCE MANAGEMENT... 10 7. PRODUCT

More information

Quality Requirements for Suppliers

Quality Requirements for Suppliers ESC9100 Rev D Quality Requirements for Suppliers This document is the property of The United Technologies Aerospace Corporation and is loaned with the understanding that neither this document, nor any

More information

Quality Management System Manual ISO9001:2008

Quality Management System Manual ISO9001:2008 Quality Management System Manual ISO9001:2008 Controlled Copy Rev. 3 Page 1 of 21 7/1/13 Table of Contents Company Profile...5 Past...5 Present...5 Mission...5 Vision...5 Locations...6 1 Scope...6 1.1

More information

HP ProLiant DL380 G6 Carrier-Grade Server Read Before Install

HP ProLiant DL380 G6 Carrier-Grade Server Read Before Install HP ProLiant DL380 G6 Carrier-Grade Server Read Before Install Carrier-Grade Instructions HP Part Number: AM275-9001A Published: July 2012 Edition: 3 Copyright 2009, 2012 Hewlett-Packard Development Company,

More information

LMSC PACKAGING STANDARD

LMSC PACKAGING STANDARD LMSC PACKAGING STANDARD Page 1 of 11 PACKAGING OF NON ELECTROSTATIC DISCHARGE SENSITIVE (NON ESDS) DEVICES, PARTS AND COMPONENT ASSEMBLIES 1.0 SCOPE This standard provides methods for the protection of

More information

Supplier Quality Requirements F16 Program

Supplier Quality Requirements F16 Program ISRAEL AEROSPACE INDUSTRIES LTD. MILITARY AIRCRAFT GROUP, LAHAV DIVISION DOCUMENT IDENTIFIER : WF16Z/150901 Supplier Quality Requirements F16 Program RESTRICTION ON USE, DUPLICATION, OR DISCLOSURE OF PROPRIETARY

More information

IPC Certification Centre

IPC Certification Centre A DVANCED REWORK TECHNOLOGY LTD IPC Certification Centre IPC-A-610D Training and Certification Programme (Revision D Training) Certified Trainer Application Specialist IPC J-STD-001D Training and Certification

More information

RTP s NUCLEAR QUALITY ASSURANCE PROGRAM

RTP s NUCLEAR QUALITY ASSURANCE PROGRAM RTP s NUCLEAR QUALITY ASSURANCE PROGRAM RTP operates under one quality program, whether you purchase products that are commercial grade, nuclear safety-related or industrial safety compliant (IEC 61508).

More information

Quality Management System Manual

Quality Management System Manual Quality Management System Manual Assurance ISO / AS Manual Quality Management System EXCEEDING ALL EXPECTATIONS Since our inception in 1965, Swiss-Tech has supplied the medical, aerospace, hydraulic, electronic

More information

Supplier Quality Manual

Supplier Quality Manual Supplier Quality Manual INTRODUCTION Welcome to LG Chem Power, Inc.. LG Chem Power, Inc. (LGCPI) is bringing the power of Lithium-Ion Polymer Battery Technology to North America for Hybrid Electric Vehicle

More information

IEC Electronics Terms and Conditions

IEC Electronics Terms and Conditions IEC Electronics Terms and Conditions 1. General: This Purchase Order is placed subject to these terms and conditions including those within the Purchase Order. The terms of any proposal referred to in

More information

Material and Components Used for UL/C-UL/ULC Mark Follow-Up Services

Material and Components Used for UL/C-UL/ULC Mark Follow-Up Services MARK INTEGRITY PROGRAM UL Traceability Requirements Material and Components Used for UL/C-UL/ULC Mark Follow-Up Services UL defines minimum requirements for material and components used in UL certified

More information

00.037.701 Rigid Printed Circuit Board Requirements

00.037.701 Rigid Printed Circuit Board Requirements 00.037.701 Rigid Printed Circuit Board Requirements Issued by: Engineering Effective Date: 10/8/2015 Rev. D Pg. 1 of 9 Approved: 10/8/2015 8:10 AM - Christy King, Quality Engineer 2.0 OBJECTIVE & SCOPE:

More information

The following document contains information on Cypress products.

The following document contains information on Cypress products. The following document contains information on Cypress products. HANDLING PRECAUTIONS 1. Handling Precautions Any semiconductor devices have inherently a certain rate of failure. The possibility of failure

More information

ADVISORY CIRCULAR AC-05-004

ADVISORY CIRCULAR AC-05-004 THE BAHAMAS CIVIL AVIATION DEPARTMENT ADVISORY CIRCULAR AC-05-004 ELIGIBILITY & TRACEABILITY OF REPLACEMENT PARTS SECTION 1 POLICY & GENERAL INFORMATION 1.1 PURPOSE This advisory circular (AC) provides

More information

Packaging Information for Vendors Engineer Approved Hard Copies Uncontrolled. Verify Revision Prior to Use.

Packaging Information for Vendors Engineer Approved Hard Copies Uncontrolled. Verify Revision Prior to Use. General Vendor Packaging PIV-012 1 of 7 This specification is provided to inform vendors of Systems Company's minimum packaging requirements. This document is superseded by any special requirements listed

More information

How To Ensure Quality Assurance

How To Ensure Quality Assurance 1001 Robb Hill Road Oakdale, PA 15071-3200 412/923-2670 PROCUREMENT SPECIFICATION: SUPPLIER QUALITY MANAGEMENT SYSTEM REQUIREMENTS Specification Number: ATI-QA-703, Rev 4 Date: 11/12/13 Page: 1 of 7 Written

More information

Sargent Controls & Aerospace 5675 West Burlingame Rd. Tucson AZ 85743 PHONE: (520) 744-1000 FAX: (520) 744-8054

Sargent Controls & Aerospace 5675 West Burlingame Rd. Tucson AZ 85743 PHONE: (520) 744-1000 FAX: (520) 744-8054 Sargent Controls & Aerospace 5675 West Burlingame Rd. Tucson AZ 85743 PHONE: (520) 744-1000 FAX: (520) 744-8054 SUPPLIER EVALUATION CHECKLIST Date: Vendor: Address: City, State, Zip: Web Site: Prepared

More information

The Fulfillment of AS 9100 Rev C Requirements by EnterpriseIQ

The Fulfillment of AS 9100 Rev C Requirements by EnterpriseIQ The Fulfillment of AS 9100 Rev C Requirements by EnterpriseIQ Manufacturers have worked to meet the stringent requirements of AS9100 for decades; the recent introduction of Revision C has further expanded

More information

Quality Management System Manual Revision L

Quality Management System Manual Revision L This Page 1 of 35 of the Quality Management System Manual If issued as a controlled copy, the serial number of this copy is Quality Management System Manual Certified to AS9100 Revision C Printed copies

More information

Repair Station Training Suspected Unapproved Parts

Repair Station Training Suspected Unapproved Parts Title 14 CFR Part 1 Part 21 Part 43 Part 45 Part 91 Part 121 Part 135 Part 145 Information & References Advisory Circular AC 21-29-B AC 20-62 General FAA Info Suspected Unapproved Parts Program Plan (Report

More information

Camar Aircraft Parts Co. Procedures Manual

Camar Aircraft Parts Co. Procedures Manual QUALITY ASSURANCE PROCEDURES INDEX Procedure Number Approval Procedure Title 4.2.3 R.F. Control of Documents 4.2.4 R.F. Control of Records 6.2.2 R.F. Competence, Training and Awareness 6.4 R.F. Foreign

More information

AVNET Logistics & EM Americas. Quality Manual

AVNET Logistics & EM Americas. Quality Manual AVNET Logistics & EM Americas Quality Manual Avnet is committed to ensuring customer satisfaction while meeting all customer and applicable legal, statutory and regulatory requirements. This is accomplished

More information

QUALITY POLICY MANUAL Document: 01-090000 Revision: E Effective Date: January 15, 2010

QUALITY POLICY MANUAL Document: 01-090000 Revision: E Effective Date: January 15, 2010 Section i INTRODUCTION QUALITY POLICY STATEMENT: The purpose of our business is to provide continuity of electrical power to keep businesses in business. We do this by helping clients solve their power

More information

QUALITY MANAGEMENT SYSTEMS

QUALITY MANAGEMENT SYSTEMS QM-1 QUALITY MANAGEMENT SYSTEMS MANUAL Revision 7 Page: 1 of 57 This document contains proprietary information and is not lo be distributed to or copted for a third party without the express written permission

More information

INSPECTION IN-PROCESS AND FINAL QUALITY ASSURANCE

INSPECTION IN-PROCESS AND FINAL QUALITY ASSURANCE INSPECTION IN-PROCESS AND FINAL QUALITY ASSURANCE 1.0 SCOPE: The purpose of this procedure is to document mandatory to ensure compliance to Project Requirements. inspection points and 2.0 REFERENCE DOCUMENTS:

More information

Universal Vehicle Power Supply 9007AX01. Installation Instructions

Universal Vehicle Power Supply 9007AX01. Installation Instructions Universal Vehicle Power Supply 9007AX01 Installation Instructions Disclaimer Honeywell International Inc. ( HII ) reserves the right to make changes in specifications and other information contained in

More information

NORTH AMERICA OPERATIONS. (Fairmont and Montreal Facilities) QUALITY MANUAL. Prepared to comply with the requirements of ISO 9001:2008

NORTH AMERICA OPERATIONS. (Fairmont and Montreal Facilities) QUALITY MANUAL. Prepared to comply with the requirements of ISO 9001:2008 WEIGH-TRONIX CANADA ULC NORTH AMERICA OPERATIONS (Fairmont and Montreal Facilities) QUALITY MANUAL Prepared to comply with the requirements of ISO 9001:2008 Meets or exceeds the requirements for design,

More information

Appendix QX. Supplier Quality Requirements

Appendix QX. Supplier Quality Requirements Supplier Quality Requirements The latest issue to this document is the version that is available on the Lockheed Martin Aero website: http://www.lockheedmartin.com/us/aeronautics/materialmanagement.html

More information

CORPORATE QUALITY MANUAL

CORPORATE QUALITY MANUAL Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance

More information

For Components PIERBURG S.A.

For Components PIERBURG S.A. Procedure 04 1 / 29 Packaging Terms and Conditions For Components PIERBURG S.A. Modificaciones del documento Versión Capítulo Descripción Fecha Realizado por 00 Versión inicial 14.01.2015 J.M. Galiano

More information

Purchase Order Attachment 1600 Revision 02 June-2006. Raytheon Aircraft Company Supplier Quality Requirements Document

Purchase Order Attachment 1600 Revision 02 June-2006. Raytheon Aircraft Company Supplier Quality Requirements Document Purchase Order Attachment 1600 Revision 02 June-2006 Raytheon Aircraft Company Supplier Quality Requirements Document Issued by: Raytheon Aircraft Company Supply Chain Management Quality Assurance 101

More information