RESETTLEMENT POLICY FRAMEWORK (RPF)

Size: px
Start display at page:

Download "RESETTLEMENT POLICY FRAMEWORK (RPF)"

Transcription

1 Public Disclosure Authorized Road Asset Management Project (RAMP) Works and Highways (MPWH) Republic of Yemen Road Maintenance Fund Implementation Unit(RMFIU) Ministry of Public Public Disclosure Authorized Ministry of Public Works and Highways (MPWH) Road Maintenance Fund Implementation Unit (RMFIU) Public Disclosure Authorized Public Disclosure Authorized RESETTLEMENT POLICY FRAMEWORK (RPF) Road Asset Management Project (RAMP) 12/5/2012

2 Republic of Yemen Ministry of Public Works and Highways (MPWH) Road Maintenance Fund Implementation Unit (RMFIU) Road Asset Management Project (RAMP) RESETTLEMENT POLICY FRAMEWORK (RPF) Draft Final 05 December

3 TABLE OF CONTENTS List of Abbreviations 3 Purpose and Structure of RAMP 4 I: RESETTLEMENT POLICY FRAMEWORK Project Specific Information Key Elements of RPF... 6 Policy Principles.6 Policy Objectives...7 Policy Coverage.7 Process for Determining and Preparing Resettlement Plans.7 Determining Impacts and Sequencing 7 Resettlement Instruments...9 Resettlement Plans Preparation Considerations.9 Steps for Preparing and Processing ARP/RAP 10 Estimated Population and Categories of PAPs 11 Land Ownership Houses and Other Structures 12 Establishing Procedures and Eligibility Criteria..13 Asset Valuation Method and Compensation 13 Organizational Responsibilities and Arrangements.14 Implementation Process and Linkage to Civil Works.18 Grievance Redress Mechanisms..19 Sources of Financing for Resettlement 21 Consultation and Participation.21 Monitoring and Evaluation Arrangements..22 ANNEX A YEMENI LEGAL AND INSTITUTIONAL FRAMEWORK Main National Legislation Regulating Lands and Land Acquisition..24 Land Acquisition Procedures 30 Institutional Arrangements...30 ANNEX B GAPS BETWEEN YEMENI LEGISLATION AND THE WORLD BANK OP ANNEX C SUMMARY OF COMMUNITY CONSULTATIONS. 41 Gaps between Yemeni Laws and OP

4 LIST OF ABBREVIATIONS ARP BC DP EC IR LRC PAP RAP ROW RP SFA ABBREVIATED RESETTLEMENT PLAN BENEFICIARY COMMITTEE DISPLACED PERSONS ESTIMATION COMMITTEE INVOLUNTARY RESETTLEMENT LOCAL RESETTLEMENT COMMITTEE PROJECT AFFECTED PEOPLES RESETTLEMENT ACTION PLAN RIGHT OF WAY RESETTLEMENT PLAN SOCIAL FRAMEWORK AGREEMENT ******** 3

5 Purpose and Structure of RAMP The purpose of this policy framework is to clarify resettlement principles, organizational arrangements, and design criteria to be applied to subprojects to be prepared during the Road Asset Maintenance Project (RAMP) implementation. This RPF provides the framework for the implementation of the Operational Policy. Annexes A and B provide information which is important as reference in the formulation of any documents related to OP These are: the Yemeni legal framework and institutions for land and property exploration and, possible gaps between OP 4.12 and Yemen laws. The discussion of OP 4.12 and the RPF cover the following: a brief description of the project and components for which land acquisition and resettlement might be required, and an explanation of why a resettlement plan or an abbreviated plan as described cannot be prepared by project appraisal; principles and objectives governing resettlement preparation and implementation; a description of the process for preparing and approving resettlement plan, estimated population displacement and likely categories of displaced persons, to the extent possible; eligibility criteria for defining various categories of displaced persons; methods of valuing affected assets; organizational procedures for delivery of entitlements, a description of the implementation process- linking resettlement implementation to RAMP civil works; a description of grievance redress mechanisms; a description of the arrangements for funding resettlement, including the preparation and review of cost estimate, the flow of fund and, contingency arrangements; a description of mechanisms for consultations with, and participation of, displaced persons in planning, implementing, and monitoring; arrangements for monitoring by implementing agency and, if required, by independent monitors; Annex A focuses on Yemeni legal and institutional frameworks for land acquisition and property expropriation. Annex B identifies gaps between the two systems and points to practical project specific actions that may be considered by the Bank team and the RMF staff. 4

6 5 RESETTLEMENT POLICY FRAMEWORK 1.1 PROJECT SPECIFIC INFORMATION Project Background The main thrust of the Road Asset Maintenance Project (RAMP) is the financing of regular road maintenance through several network-wide term maintenance contracts. The project will bring about a considerable expansion of the road network in Yemen under annual regular maintenance and would build on experience from the Second Rural Access Project (RAP2) currently financed by the World Bank, and will mainstream the contracting out of maintenance of paved roads in Yemen in four governorates: Hodeidah, Ibb, Taiz and Lahj. The project will seek to ensure sustainability of these efforts through broad involvement of the private contracting industry in maintenance management, while creating local employment through small-scale labor-intensive maintenance activities Project Components Component 1: Road Maintenance Works (US$34.7 million equivalent). This component would finance the improvement of the road condition ( about 2,300 km total) in the Governorates of Al-Hodeidah, Ibb, Taiz, and Lahj in the form of regular and emergency road maintenance works through multi-year, fixed-term contracts with private contractors. The works would include repairs and routine maintenance of road networks including repairs to road surfacing and pavements, drainage improvements, restoration of shoulders and road furniture such as guardrails, road signs and marking. This component would also improve traffic safety by financing engineering improvements such as better road markings and signage, better and more appropriately positioned speed control measures in built-up areas, better crash barriers and the removal of other deficiencies that cause an accumulation of fatal and serious accidents. Component 2: Institutional Support and Capacity Building (US$3.1 million equivalent). This component would finance activities to strengthen the RMF s and MPWH s capacity for road asset management, including axle load controls and installation of Information and Communication Technology (ICT) equipment and software. In addition, the component will finance a road sector public expenditure review and introduce a medium term budget framework to improve the road expenditure policies generally and efficiency of maintenance related expenditures in particular. Road safety training, strengthening of the planning and supervision units in MPWH, updating of the Road Master Plan, studying options for commercializing GCRB s operations and limited road laboratory testing equipment would also be provide. This would be achieved through consultancy services and supply of computerized equipment and installation contracts. Necessary limited supply of vehicles to facilitate the strengthened role of these two entities as caretakers of the national road network would be financed by the RMF under its local budget. In addition, this component would support the establishment of a Public Private Partnership (PPP) unit in MPWH directly under the Minister to explore the potential for private-public partnerships in financing, operation and maintenance of new transport corridors.

7 Component 3 Transport Sector Studies (US$2.20 million equivalent). This component would finance technical assistance to address deficiencies and inefficiencies in transport infrastructure provision, maintenance and operation, at the same time support preparation of investments with potentials for other donors financial support. This would include technical studies including feasibility and preliminary engineering as well as O&M studies to assess potentials of PPP in the transport sector in Yemen, including public transport and operation of Sana a airport. The scope of this RPF document is limited primarily to Component Project Development Objectives The Project Development Objective is to improve road conditions in four governorates (Al- Hodeidah, Ibb, Taiz, and Lahj) and to strengthen the RMF capacity in road asset management. The proposed RAMP consists of three Components Project Location and Potential Impacts The proposed project will cover Hodeidah, Ibb, Taiz and Lahj governorates. Its roads maintenance works will stretch over considerable distances in the four governorates and run hundreds of kilometers and will involve many areas, villages and communities. The exact road alignments and impacts on livelihoods are not determined at this stage of project preparation. Exact alignments and project s impacts on livelihoods can only be known when final engineering design is made available. However, it is important to note that the project is planning to undertake its maintenance works on existing roads which already have an established right-of-way (ROW). Although its civil work will mainly focus on road maintenance work, it is also anticipated that new land may need to be acquired for bypasses, curve straightening, or roadside improvements. The acquisition of new land is likely to be modest, but this may still affect some livelihoods. The project s resettlement impacts are generally expected to be confined within a fairly narrow corridor of impact. Mainly areas that are unsafe, where people are not permitted to occupy structures, carry out business activities, or cultivate land. The width of this corridor/alignment is not yet known. For purposes of resettlement planning, the corridor of impact includes the immediate safety zone and any areas that impact directly on people s livelihoods The Purpose of the RPF The exact roads alignment and project s impact on livelihoods is unknown. In the absence of this information, it is not possible to prepare an Abbreviated Resettlement Plan (ARP) or Resettlement Action Plan (RAP). Because of this the purpose of the is to provide the guidelines for the formulation of either ARPs or RAPs as needed. During project implementation and when subprojects final engineering designs are made available and, when it is determined that civil works will necessitate involuntary resettlement or involuntary land taking, the Road Maintenance Fund (RMF) in 6

8 consultation with the Bank would proceed and prepare ARP/RAP consistent with this RPF. 1.2 KEY ELEMENTS OF RPF Principles and Objectives Governing Resettlement Preparation and Implementation Policy Principles The policy principle of OP 4.12 is to avoid involuntary resettlement where feasible by exploring alternatives. Involuntary Resettlement (IR) resulting from development projects will, if unmitigated, give rise to difficult economic, social, and environmental risks that may lead to a variety of unacceptable impacts including dismantling of production systems, impoverishment of people, relocation of displaced persons to environments that do not suit their skills, weakening of community institutions and social networks, dispersion of extended families and kin groups and loss of cultural identity. OP 4.12 is a road map for the identification, preparation, and implementation of Bank-funded programs with a focus on minimizing negative social and economic impacts on individuals and communities. If IR is unavoidable, resettlement activities should be conceived and executed as sustainable development programs where displaced persons should be meaningfully considered. Resettlement programs should work to improve the livelihoods of the Project Affected Persons (PAPs). A well-designed resettlement programs may present good development opportunities. By providing proactive mitigation measures that will lead to sound resettlement planning, OP 4.12 is designed to ensure that PAPs are not negatively affected by World Bank-financed projects Policy Objectives The overall objectives of the Bank s policy on involuntary resettlement are: Involuntary resettlement should be avoided where feasible, or minimized, exploring all viable alternative project designs; Where it cannot be feasibly avoided, resettlement activities should be conceived and executed as sustainable development program, providing sufficient investment resources to enable PAPs to share the project benefits. PAPs should be meaningfully consulted and should have opportunities to participate in planning and implementing resettlement programs and compensation measures; and PAPs should be assisted in improving their livelihoods and standards of living or at least in restoring them, in real terms, to pre-displacement levels or to levels prevailing prior to project implementation, whichever is higher Policy Coverage The Bank policy on involuntary resettlement covers the direct economic and social impacts that both result from WB financed projects operation and are caused by: 7

9 The involuntary taking of land resulting in relocation or loss of shelter, or loss of access to productive assets, or loss of sources of income or means of livelihood, whether or not the affected persons must move to another location; or, The involuntary restriction of access to legally designated parks and protected areas resulting in adverse impacts on the livelihoods of the displaced persons. This policy applies to all RAMP subproject(s) component(s) that may result in involuntary resettlement, regardless of the source of financing Process for Determining and Preparing Resettlement Plan Determining Resettlement Impact and Sequencing When a sub-project s final engineering design is made available, the scale and severity of its impact on livelihoods will be assessed and determined by the RMF s Environmental and Social Specialists. It is possible that access to natural resources might be restricted, land may be acquired and, livelihoods might be affected negatively. When these possibilities are apparent, the RMF will gather information on potential PAPs and their assets. The information will be used to: (i) determine the applicability of Operational Policy (OP) 4.12, (ii) identify potential PAPs and vulnerable groups in the project areas, (iii) establish baselines for evaluating income restoration measures and, (iv) design technically feasible and socially acceptable alternatives and resettlement plans. This requires the RMF s Environmental and Social Specialists to conduct studies to document existing conditions in the early stages of each subproject preparation, in consultation with the PAPs. These studies will include the following depending on specific situations and local contexts. (a) (b) Conduct a census survey covering: current occupants of the affected area by subproject to establish a basis for the design of the resettlement program and to exclude subsequent inflows of people from eligibility for compensation and resettlement assistance; standard characteristics of displaced households, including a description of production systems, labor, and household organization; baseline information on livelihoods (including, as relevant, production levels and income derived from both formal and informal economic activities) and standards of living (including health status) of the displaced population; the magnitude of the expected loss total or partial of assets, and the extent of displacement, physical or economic; information on vulnerable groups or persons; provisions to update information on the displaced people s livelihoods and standards of living at regular intervals so that the latest information is available at the time of their displacement; Other studies may be required to better inform the reasons for specific actions: such as inventory of land assets and their categories, public infrastructure and social services etc. 8

10 It is very likely that subprojects final engineering designs may not be available at project start-up and may be completed in stages. This may prove difficult to conduct the study and determine subprojects impact on livelihoods. Given these challenges, the RMF in consultation with the Bank, will determine either to deliberately extend the census and surveys to: include the maximum envelope of project impact zone or; estimate the resettlement impact in the areas where the road maintenance may have impacts and conduct the census and socioeconomic survey subprojectby-subproject at a later date. If the RMF chooses to present an initial ARP/RAP at appraisal on the basis of one of the above options, the initial ARP/RAP will likely to cover both the known and the unknown road alignments. In this case, the RMF will be required to update the initial ARP/RAP), presented at appraisal, and revise them at a later date. If final engineering designs of subprojects are to be completed in stages, different activities related to planning and implementation of subprojects physical work and resettlement 1 need to take place sequentially for any given stretch of corridor. RMF will carefully examine and coordinate these activities to avoid delays in subprojects resettlement activities that will hold up civil works or to prevent civil works from taking place on a stretch of corridor before appropriate resettlement activities are completed Resettlement Instruments While this project does not anticipate works outside the existing right-of-way, however, if it is determined land acquisition is unavoidable option and OP 4.12 is applicable to RAMP subproject(s), the RMF will prepare Land Acquisition Plan (LAP) for each subproject and inform the Bank of the project intention to acquire land. Upon receiving this information the Bank team will weigh the scale and magnitude of subproject(s) impact on livelihood, advice the RMF on next action to be taken and, recommend the resettlement planning instruments to be used from the followings: Resettlement Action Plan (RAP): The preparation of this planning instrument is dependent upon the scale and severity of impacts on livelihoods. A full RAP is required when: a) more than 200 individuals are affected; b) all of the PAPs lose more than 10 percent of any of their holdings; c) the remainder of their land is economically unviable; and (c) they have need for physical relocation. Abbreviated Resettlement Action Plan (ARP): This planning instrument is prepared if the resettlement impacts are minor, Resettlement impacts are considered minor if: (a) RAMP displaces fewer than 200 people, (b) all of the PAPs lose less than 10 percent of their land, regardless of the number of PAPs; (c) the remainder of their land is economically viable; and (d) they have no need for physical relocation. An abbreviated plan covers the following minimum elements: 1. a census survey of displaced persons and valuation of assets; 2. description of compensation and other resettlement assistance to be provided; 2. Rapid screening, land and assets inventory and consultation must be started upon receiving final design 9

11 3. consultations with displaced people about acceptable alternatives; 4. institutional responsibility for implementation and procedures for grievance redress; 5. arrangements for monitoring and implementation; and 6. a timetable and budget; Process Framework (PF): The Process Framework is prepared if the operation of RAMP imposes restriction of access to legally designated parks or protected areas. If the project restricts access to common property or natural resources as a result of its activities, it is then imperative that the project prepare and submit a process framework as a condition for appraisal Resettlement Plans Preparation Considerations If land acquisition becomes an unavoidable reality, the RMF will prepare ARP/ RAP 2 that must be consistent with this RPF as well as the social context of the subproject(s) area(s). The followings are key resettlement preparation considerations: RAMP subprojects with known corridor of impact: If there are subprojects with known corridors of impact at the time of project appraisal, it is imperative that RMF prepared ARP/RAP with full population census and an inventory of the assets to be acquired. RAMP subprojects with corridor impact only partly known: If there are subprojects with corridors that can only partly be known at appraisal, the RMF is required to have an approved Resettlement Policy Framework for the entire project and ARP/RAP for those sections where the corridor is known. ARP/RAP must be presented later for sections where the corridor is unknown at the time of project appraisal. RAMP impact corridor and alignment is not know: If the project s preliminary design identified only general corridors of impact by the time of project appraisal, precise identification and enumeration of potential PAPs and their assets cannot be undertaken by appraisal. In such circumstances: A RPF (this document as accepted by both the GoY and the Bank) will establish categories of entitlements to apply after precise identification and enumeration of potential PAPs. For segments of the project for which engineering specifications are available (and for all land to be acquired in the first year of the project), a full census of all potential PAPs and a detailed and complete inventory of land and assets to be acquired will be carried out and documented. For segments of the project for which engineering specifications are not fully known, a corridor of maximum impact to serve as the basis for a full census of all people possibly affected will be used, The ARP/RAP for subsequent subprojects involving resettlement must be presented before the respective subprojects are approved for Bank financing. The RMF is responsible for preparing a resettlement plans in accordance with this framework, for each sub-project giving rise to displacement, and furnishing it to the Bank for approval prior to implementation of the sub-project. 2 Detailed guidelines for preparing a RAP are available one the World Bank's website 11

12 Initial social and environmental. screening, Initial multi-stakeholder consultations Decision on choices of corridor RPF Census and baseline survey Agreement on categories of impacts and appropriate entitlements Preparation of RPs: time-bound implementation plan for entitlements Final designs, on corridor of impact Detailed overview of DPs within corridor of impact Consultations with DPs about the project; presentation on entitlements and options Registration and preparation of identity cards Revisit DPs to discuss and finalize options Issuance of identity cards Updating of resettlement action plan Implementation of resettlement action plan within relevant corridor segments Relocation and assistance to DP s is completed Road Asset Management Project Steps for Preparing and Processing ARP/RAP Preparing ARP/RAP entails systematic planning and coordination. It will involve screening and on the spot verification exercises, consulting people, reviewing documents, assessing and identifying capacities of implementing agencies, and building their capacities. The below diagram provides steps to be followed by RMF while preparing and processing its subprojects ARP/RAP. Road Asset Maintenance Project (RAMP) Resettlement Planning and Processing Steps STEP IV STEP I STEP II STEP III STEP V STEP VI STEP VII STEP VIII Sub projects civil woks started Estimated Population of PAPs and Categories of PAPs At this time it is not possible to estimate the probable extent of PAPS. However this RPF recommends that PAPs are categorized as: (a) (b) (c) Individual persons affected by RAMP: an individual is affected when he/she is subject to loss of goods, property and or access to natural resources resulting from the project. For example, an individual who is cultivating land or owns a commercial or housing structure which is removed as a result of the project. Household affected by RAMP: a household is affected when one or several of its members are subject to loss of property, land or access to land or other income-generating activity as a result of the project Vulnerable households affected RAMP: a vulnerable household may have needs affected by the project which are different from most other households. They may concern (although it is unlikely in the Yemeni cultural context) such segments of the population as self-supporting women and elderly people 11

13 1.2.4 Eligibility Criteria Since RAMP impacts are not yet known it is not possible to determine who is qualified or not qualified for compensation or assistance. Nonetheless, all PAPs who suffer complete or partial losses of assets or access to assets shall be eligible for some kind of assistance, according to their legal rights to the land, if it can be proven that they occupied the land before the claim cut-off date. The Bank OP 4.12 specifically proposes the following three general categories for eligibility: a) Those who have formal, legal rights to land, including customary and traditional rights, recognized under the laws of the country; b) Those who have no formal legal rights to land at the time the census begins but have a claim to such land or assets, provided such claims are recognized under the laws of the country or become recognized through a process identified in the resettlement plan; and c) Those who have no recognizable legal right or claim to the land they occupy. Persons covered under (a), (b) and (c) above will be provided assistance under this Policy Framework if they occupy land or buildings prior to the cut-off date (which is the date the detailed census to identify affected persons begins.) Persons who encroach on the area after the cut-off date are not entitled to consideration or any form of resettlement assistance under this policy. Eligibility for compensations will recognize private, customary or traditional rights as well as formal and informal contractual rights. 12

14 Land Ownership As final engineering design and planning information becomes available, land ownership and severity of impact shall be used to determine compensations for resettlement entitlements. The type of ownership or claim, in combination with the severity of impact, determines the relevant resettlement entitlements, which are generally defined in proportion to the impact on PAPs Ownership of Houses and other Structures Owners of affected houses or other structures will be compensated in-kind at replacement cost, which is defined as the cost of the work required to replace the asset in its existing condition. The basic parameters generally used to determine the replacement cost shall be the size, standard and condition of existing asset. This, in addition to arrangements for providing the land on which the replacement structure will be built, will be stated in mutually signed Social Framework Agreement (SFA) that would be signed by the asset owner(s), the Chair of the Beneficiary Committee (BC) and the RAMPIU. The SFA documents all land and property expropriations or donations made to the RAMP and its effect on livelihoods. The document states the exact amount of land taken, the value of the property and, the purpose for which the land and the property has been used by the owner. The SFA will clearly state the terms and conditions of agreement and would be signed prior to the start of any subproject(s) civil works. The role and responsibilities of the Beneficiary Committee is described under section of this RPF. The committee will be composed of: (i) representative of PAPs, (ii) project engineer, (iii) SDO, (iv) a representative of land authority and, (v) a representative of local government. The qualities, specifications and estimated cost for the new structure(s) shall be assessed by the design consultant and will be incorporated into the bidding documents Establishing Procedures and Eligibility Criteria If RAMP requires resettlement planning to address adverse impact on livelihoods, the Road Maintenance Fund (RMF) will develop a procedure satisfactory to the Bank for establishing the criteria by which PAPs will be deemed eligible for compensation and other resettlement assistance. The procedure includes provisions for meaningful multi-stakeholders consultations with PAPs and PAP-communities, local authorities and relevant NGOs, and government agencies Asset Valuation Method and Compensations Asset Valuation Method Tangible assets: The valuation of losses in physical assets will be carried out by assessing the market value of the assets, if known, and estimating the replacement cost. Replacement cost is simply calculated as the cost of replacing the lost assets plus any transaction costs associated with bringing the asset to pre-displacement value. 13

15 Replacement cost will differ depending on the type of asset, as illustrated in Table below. Asset Agricultural Land Houses / Other Structures Source: WB OP 4.12 Replacement Cost for Tangible Assets Replacement Cost Equals the pre-project or pre-displacement, whichever is higher, market value of land of equal productive potential or use located in the vicinity of the affected land, plus the cost of preparing the land to levels similar to those of the affected land, plus the cost of any registration and transfer taxes. Equals the market cost of the materials to build a replacement structure with an area and quality similar to or better than those of the affected structure, or to repair a partially affected structure, plus the cost of transporting building materials to the construction site, plus the cost of any labor and contractors fees, plus the cost of any registration and transfer taxes. Intangible assets: For intangible loses that cannot easily be valued in monetary terms (i.e. access to employment opportunities, public services, natural resources, social capital), the RAMP will attempt to establish access to equivalent resources and earning opportunities that are acceptable to the PAPs Compensations If OP 4.12 becomes applicable to the project, compensation will be provided to all individuals whose assets or access to assets is severely affected or damaged. The compensation for the loss of physical and non-physical assets will vary depending on the type of loss, severity of the loss, and eligibility of the PAPs. When land is acquired for a public interest project, fair compensation to the affected people is guaranteed in the constitution for urban areas. The compensation level is determined by a Beneficiary Committee. All PAPs will be entitled to compensation at replacement cost, at market value (at the entitlement cut-off date), for affected tangible assets. In accordance to local practice in-kind compensation can be considered as an option where the affected assets would be replaced with an asset of similar size, value, and quality. In the rural areas the customary system of donating land for public interest projects is still being applied. No formal legislation exists with regard to land acquired for public interest projects in rural areas, and the process followed is based upon wellestablished traditional community-level systems where project affected persons donate land. Rural communities in Yemen have traditionally been solving land acquisition issues through consultation and internal dispute resolution arrangements. In many cases, the affected lands owners are expected to voluntarily donate the land needed for a public benefit project. However, the voluntary donation of land will have to take place within the context of a mutually accepted understanding and within the framework of the SFA. No cash compensation is involved. However, in-kind replacement for buildings and physical structures will be negotiated with the property owner. 14

16 To the extent possible the SFA should list the exact amount of land that is being taken or donated from each property owner. The document requires the signature by the landowner prior to project implementation. This provides documentation of the awareness and consent of landowners of the amount of his or her land used for the RAMP. The SFA specifies the terms under which the voluntary donation of land is made. The terms in the SFA will be based on local traditional practices concerning private land donation for RAMP operation and specify any special terms or conditions related to the particular case, which are to be settled internally by community. Generally, these terms can include one of the following options: a) The affected person freely donates the land to the community, or b) The community may allocate part of its land to the affected person. The decision as to which type of compensation is used should be jointly agreed upon between the RAMP and the PAPs and shall be subject to the availability of replaceable assets. Moreover, development and resettlement transitional assistance needed to restore the livelihood and standard of living of PAPs to pre-project levels shall also be part of the compensation component of any resettlement plan (i.e. shortterm jobs, subsistence support, moving allowance, salary maintenance, food assistance, etc). Where compensation is paid which is not the case of land donated for a project in the public interest then compensation is paid just before the land is actually acquired. In the case of the RAMP implementation with phased sub-projects, the actual compensation and resettlement should not take place several years ahead of the construction phase of each segment of its subproject. The RMF will exercise care so that premature resettlement is avoided and construction works have started immediately after resettlement compensation is paid. These actions by RMF will help to avoid: Acquiring land and properties long before the land is actually required, People reoccupying the space required if too much time passes between resettlement and construction, Paying compensation or assistance several years before people actually moved or their land is acquired, Compensation for losses in communal property shall only be in-kind for the community as a whole, and shall take the form of reconstruction of the affected or damaged facility (i.e. public school buildings, markets, etc.) to at least the same standard prior to the project s implementation. As part of the resettlement process, a compensation matrix will be prepared that identifies the expected negative impacts, the eligible persons for compensation, and the compensation policy that is to be applied. 15

17 1.2.6 Organizational Responsibilities and Arrangements The Road Maintenance Fund (RMF) Compliance to OP 4.12: The primary responsibility of RMF is to ensure resettlement planning is taking place for each sub project and make sure that that no civil works are undertaken on any stretch of the alignment before land acquisition for the respective stretch has been completed and compensation or assistance has been delivered according to an agreed RP/SFA. Administrative Coordination: As project executing agency, RMF will be responsible for addressing issues of multijurisdictional planning and coordination, such as any public and private agencies in the four governorates. The RMF will establish suitable mechanisms to allocate responsibilities, including financial responsibilities and other measures needed for timely delivery of compensation and other assistance to PAPs. The RMF will also be responsible for preparing separate RPs for each jurisdiction with specific implementation plans for each. The organizational responsibilities and financial arrangements of each jurisdiction will be defined and agreed. In addition to the overall responsibilities of planning and coordination, the RMF will also be responsible for conducting the following specific tasks: Screening the project activities to check if any activity will result in land acquisition and involuntary resettlement; Hiring resettlement consultant for the preparation of the RAP/ ARP; Preparing the ToRs for the Local Resettlement Committee; Following up on the formation of the different committees stated in this RPF; Ensuring the interest of PAPs, particularly the vulnerable groups, are well addressed by the RAP/ARP and the SFA; Preparing and submitting RAP/ARP for WB approval; Facilitating the different consultation activities; Participating in responding to the grievance and work toward solving related issues; Overseeing/monitoring the progress in resettlement policy, resettlement preparation and implementation through reviewing regular progress reports; Reporting regularly to the WB on compliance to OP 4.12 and when relevant on resettlement activities (RAP/ ARP implementation); Keeping records and documentation and ensure data compilation in a way that facilities the task of Bank s supervision and the external monitoring activities (e.g. grievance process and action taken); Participating in preparing the external monitoring consultant ToRs according to the WB standards; Reviewing the external monitoring report Local Authorities (Local Councils) The respective of Local Councils in the four governorates are the key governmental authorities of relevance to the execution of the resettlement programs. Their responsibilities in the RAP/ARP execution should involve: 16

18 Coordinating with other governmental organizations of relevance to the resettlement program; Following up on the resettlement process; Following up on the on compensations and the provision of the development assistance; Ensuring that PAPs are consulted and their concerns and interests are considered; and Through participation in the grievance resolution process, play a role in facilitating responsiveness to the PAPs concerns Beneficiary Committee Based on the census information, the Beneficiary Committee will: determine the terms and procedures of land donation/acquisition or in-kind replacement of structures; ensure that these terms and procedures are specified in Resettlement Plans (ARP/RAP), are consistent with OP 4.12, and appended to the SFA; Ensure that the SFA are negotiated consistent with OP 4.12 and the applicable customary practices; signed by the owner, witness and BC and; approved by the governor; Ensure implementation of terms of the donation as stated by SFA; Ensure that in-kind asset replacement are in accordance with customary law, OP 4.12 policy principles and as per agreement stated in the SFA; Work with RAMP to ensure that in-kind asset replacement cost are captured as project cost, Ensure and coordinate with RMF that the contractor rebuild the affected structure or asset according to a specified standard and at the agreed location; The World Bank The Bank may, at GOY s request, support RMF by providing assistance to: Assess and strengthen resettlement policies, strategies, legal frameworks, and specific plans; Prepare and review and Resettlement Planning; Strengthen the capacities of agencies responsible for resettlement, or of affected people to participate more effectively in resettlement operations; Develop resettlement policies, strategies, and specific plans, and for implementation, monitoring, and evaluation of resettlement activities; and Finance the investment cost of resettlement. Along the RAP/ARP cycle, the Bank is also responsible for: Screening and verifying findings and advice on the need for RAP/ARP and whether or not other remedial actions need to be taken; Approving the RAP/ARP prior to the execution of sub-projects or expropriation activities; Contracting the external monitoring consultant; and Reviewing monitoring reports and sending feedback to the RMF. 17

19 Non Governmental Organizations (NGOs) NGOs are key players that should be involved to ensure the efficiency of the resettlement activities. NGOs are also recommended to participate in: Coordination for the provision of supporting facilities/loans/ employment/capacity building programs, etc. based on the PAPs needs; Facilitation of access to the most vulnerable groups and ensuring fair representation of different social subgroups (e.g. women, youth, children, etc.); and External Consultant(s) The input of an external consultant will be required if the need arises for the preparation of a full RAP/ARP. The consultant will be needed to assist in the following issues: Resettlement and Capacity Building Assist RMF in the preparation of the RAP/ARP, particularly designing and applying the socio-economic survey; and Prepare training materials and provide the training to BC members on legislative issues related to resettlement (particularly OP 4.12) as well as methods for engaging and consulting stakeholders (particularly PAPs) and monitoring techniques, and evaluate the training outcome. Monitoring and Evaluation (M&E) Verify that project activities have been effectively completed with respect to quantity, quality and timeliness; Assess whether and how well these activities are achieving the stated goals and purpose of the project; Design monitoring tools; Carry out all the field surveys, investigation activities and stakeholders consultations as part of the monitoring process; and Review monthly and quarterly monitoring reports and other secondary data Implementation Process and Linkage to Civil Works Linking Resettlement Implementation to Civil Works PAPs will need to be compensated or their assets replaced before civil work can begin. The compensation shall be done in accordance with this Resettlement Policy Framework and subsequent resettlement and compensation plan(s). For activities involving land acquisition or loss, denial or restriction to access of resources, the RMF will make adequate provisions for compensation and for other assistance prior to the actual displacement and relocation. Assistance includes provision and preparation of resettlement sites with adequate facilities. In particular, land and related assets for RAMP activities may be taken only after compensation has been made and resettlement sites and moving allowances have been provided to the PAPs. For activities requiring relocation or resulting in loss of shelter, the project will take measures to ensure that the PAPs are assisted and the resettlement program is implemented in accordance with the ARP or RAP. 18

20 In the Implementation Schedule of the ARP or RAP, details on resettlement and compensations must be provided. The schedule for the implementation of activities, as agreed by SFA between the RMF and PAPs must include: Size and type of land and property acquired by the project from each PAP; Target dates for start and completion of civil works; Timetables for transfers of completed civil works to PAPs; Dates of possession of land that PAPs are using (this date must be after transfer date for completed civil works to PAPs and for payments of all compensations); and The link between RAP activities to the implementation of the overall RAMP. When approving recommendation for resettlement during screening, in compliance with this policy framework, the PAPs must confirm that the resettlement plans contain acceptable measures that link resettlement activities to the project s civil works. Proper timing and coordination measures will ensure that no affected persons will be displaced (economically or physically) due to civil works activity. Compensation is made in full before any of the RAMP activity can begin Cut-off Date, General Information and, Phased Action If land and asset acquisition are required, the RMF will: a) Establish the cut-off date and carry out a census to identify PAPs; b) Generate information about the PAPs, their entitlements regarding compensation, resettlement and rehabilitation assistance as required; c) Identify disturbances, especially those affecting income-earning activities, and properly recording compensation or asset replacement; and d) Prepare a time phased action plan with a budget and making provision of compensation, resettlement, and other assistance as required, based on the census and inventory of losses, and in consultation with the PAPs. The RMF and its Social Development Officer (SDO) shall ensure that following the census, ARP or RAP is prepared for RAMP activity that requires resettlement. The RMF may employ a private consultant to provide valuation services required for the ARP or RAP. This assignment shall be financed by the project. In case the project operation requires major involuntary resettlement planning, approval of the new pieces of land to be used for resettlement shall be sought from the Government of Yemen in consultation with local communities and affected individuals. To ensure transparency of procedures, the PAPs shall be informed of the method of valuation used to assess their assets. All compensation, resettlement assistance and rehabilitation assistance, as the case may be, shall be made in the presence of the PAPs in question and the local leaders Timeframes No civil work starts unless all compensations are made in full. The following key timeframes shall apply unless otherwise agreed between the RMF, BC and local government, the Resettlement Committee and the PAPs: 19

21 Site screening will have to be conducted at early stage of project identification; In a case of major involuntary resettlement, asset inventory shall be completed at most four months prior to the commencement of civil work; The resettlement plan shall be submitted to RMF and the WB for approval immediately after completion of asset inventory; and That civil works shall commence after compensation, resettlement and rehabilitation activities have been affected. Timeframes shall be drawn up and agreed upon by all parties including the PAPs. Compensations or asset replacement for acquired land, affected assets and resettlement of households must be completed as a condition for the taking away of land and before commencement of the civil works. Where relevant and in the case of full resettlement, adequate time and attention shall be allowed for consultation of both the PAPs and host communities before bringing in the newcomers. The actual length of time will depend on the extent of the resettlement and compensation and will have to be agreed upon by all parties Mechanisms to address Grievances Objective of Grievance Redress The objective of the mechanism to address grievances is to solve disputes at the earliest possible time, which will be in the interest of all parties concerned. The mechanism should discourage referring matters to a court for resolution. Grievances should be addressed by traditional and tribal institutions or special committees might be formed as an independent mechanism for the purpose of receiving and responding to grievance in order to ensure that PAPs grievances are treated fairly and timely. Minutes of the grievances and their proposed solutions should document the process. PAPs can file complaints in case of: (i) non-fulfillment of contracts or agreements, (ii) compensation entitlement, (iii) types and levels of compensation, (iv) compensation policy, acquisition / destruction of land or assets, and (v) resettlement, or development or transitional assistance. If the grievances or other disputes cannot be resolved through customary arrangements and administrative actions, the PAPs can initiate legal proceedings in accordance with provincial and national law (Article 51 of the Yemeni Constitution 3 ) and have recourse to the Appellate Courts and the Supreme Court and the processes depicted by the below diagram can be adopted by the RMF within the context of local practices. 3 A citizen may resort to the court for the protection of his right and legitimate interests. He/she shall be entitled to lodge complaints, criticisms, and suggestions to state entities and organizations in a direct or indirect manner. 21

22 Procedures Road Asset Management Project ROAD ASSET MAINTENANCE PROJECT (RAMP) PRPOSED GRIEVANCE REDRESS MECHANISMS & PROCEDURES RMF in collaboration with District Administration will attempt to resolve the issue LA will attempt to resolve the problem within 14 days Court of Law RMF Local Administration If not resolved at LA level the case moves to RMF and District Administration. Should grievance remain unresolved it is referred to the Court of Law In not satisfied with LL, the affected person files his grievance to RMF Local leader respond to grievance with 14 days Local/Community Leader In not satisfied with BC, the affected person files his grievance to local leader and seeks remedy through customary law PMU Or Contractor Beneficiary Committee: inform, negotiate and, decide Land/ property owner If agreement is reached between the two parties, the SFA/ARP is signed and civil work proceed It is strongly recommended that in order to minimize the cases that are taken to the court and avoid long and tiring litigation, the local social context is carefully considered and Yemeni customary law consistent with OP 4.12 is followed. The role of traditional institutions in resolving disputes through mediation, customary tribal arbitration, and mutual accord is important in Yemen. Customary laws in tribal areas are strong and effective in resolving rural land disputes. It is anticipated that the traditional structure in the four governorates will play similar role in resolving land issues that might arise between the RAMP and beneficiary communities. It is also important to keep in mind that the RAMP collects and review status of grievances (in coordination with the representative local public official) monthly and the RMF should also play a role in facilitating the response to these grievances. Particular attention will be paid to vulnerable groups Sources of Financing for Funding Resettlement If OP 4.12 becomes applicable to RAMP, realistic cost estimates shall be calculated based on the data collected from the socio-economic survey on the estimated number of PAPs that are likely to be affected by the subprojects and the quantity and types of affected assets. 21

Performance Standard 8:

Performance Standard 8: Overview of Performance Standards on Environmental and Social Sustainability 1. IFC s Sustainability Framework articulates the Corporation s strategic commitment to sustainable development, and is an integral

More information

PR 5: Land Acquisition, Involuntary Resettlement and Economic Displacement

PR 5: Land Acquisition, Involuntary Resettlement and Economic Displacement 34 Environmental and Social Policy PR 5: Land Acquisition, Involuntary Resettlement and Economic Displacement Introduction 1. Involuntary resettlement refers both to physical displacement (relocation or

More information

Environmental & Social Assessment Procedures Basics

Environmental & Social Assessment Procedures Basics African Development Bank Group Environmental & Social Assessment Procedures Basics For public sector operations Compliance & Safeguards Division (ORQR.3) safeguards@afdb.org AFRICAN DEVELOPMENT BANK GROUP

More information

Resettlement Policy Framework

Resettlement Policy Framework Wuhan Intelligent Transportation Demonstration Project, a subproject of the World Bank-funded Wuhan Urban Circle Transportation Integration Demonstration Project Resettlement Policy Framework Wuhan Municipal

More information

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK

JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized JAMAICA SOCIAL INVESTMENT FUND LAND ACQUISITION AND RESETTLEMENT POLICY FRAMEWORK I.

More information

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE RESETTLEMENT ACTION PLAN

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE RESETTLEMENT ACTION PLAN NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT COMPLETION AUDIT TERMS OF REFERENCE RESETTLEMENT ACTION PLAN November 2009 BACKGROUND Newmont Ghana Gold Ltd. (NGGL) has developed gold reserves at the Ahafo

More information

EBRD Performance Requirement 7

EBRD Performance Requirement 7 EBRD Performance Requirement 7 Indigenous Peoples Introduction 1. This Performance Requirement (PR) recognises that projects can create opportunities for Indigenous Peoples to participate in and benefit

More information

Grievance Management Guidance Note

Grievance Management Guidance Note May 2012 1 Grievance Management Guidance Note 1 EBRD S REQUIREMENTS 1.1 PERFORMANCE REQUIREMENT (PR) 10 INFORMATION DISCLOSURE AND STAKEHOLDER ENGAGEMENT Key Bank requirements relating to grievance management

More information

ANNEX 7.1 Guide to Land Acquisition and Compensation (GLAC) LAND ACQUISITION

ANNEX 7.1 Guide to Land Acquisition and Compensation (GLAC) LAND ACQUISITION ANNEX 7.1 Guide to Land Acquisition and Compensation (GLAC) LAND ACQUISITION Overview Expropriation is a legal way to enable the government or a public legal entity to use immovable assets owned by natural

More information

VIE: Second Upper Secondary Education Development Project (USEDP II) - Ha Giang Province

VIE: Second Upper Secondary Education Development Project (USEDP II) - Ha Giang Province Due Diligence Report November 2014 VIE: Second Upper Secondary Education Development Project (USEDP II) - Ha Giang Province Quyet Tien Upper Secondary School Prepared by the Ministry of Education and Training,

More information

Environmental Assessment

Environmental Assessment OP 4.01 Page 1 of 5 Environmental Assessment Note: OP 4.01 replaces the policy elements of IFC s Environmental Analysis and Review of International Finance Corporation Projects (Washington, D.C.: IFC,

More information

TRANSPORT SECTOR SUPPORT PROJECT: BASE-GICUMBI-NYAGATARE ROAD (SECTION BASE - GICUMBI-RUKOMO: 51.5KM) SUMMARY OF THE RESETLEMENT ACTION PLAN

TRANSPORT SECTOR SUPPORT PROJECT: BASE-GICUMBI-NYAGATARE ROAD (SECTION BASE - GICUMBI-RUKOMO: 51.5KM) SUMMARY OF THE RESETLEMENT ACTION PLAN PROJECT: COUNTRY: TRANSPORT SECTOR SUPPORT PROJECT: BASE-GICUMBI-NYAGATARE ROAD (SECTION BASE - GICUMBI-RUKOMO: 51.5KM) REPUBLIQUE DU RWANDA SUMMARY OF THE RESETLEMENT ACTION PLAN Project Team Philippe

More information

Baker Hughes pays 100% of the cost of your coverage. No premium contributions are required from you for this coverage.

Baker Hughes pays 100% of the cost of your coverage. No premium contributions are required from you for this coverage. Basic Life Insurance Basic Life At-A-Glance Type of Plan Premium Contributions Employee Eligibility Eligible Dependents When Coverage Begins Enrollment Period* Coverage Options Contact Welfare Plan Providing

More information

Objective Oriented Planning Module 1. Stakeholder Analysis

Objective Oriented Planning Module 1. Stakeholder Analysis III. Stakeholder Analysis Stakeholders are people, groups, or institutions, which are likely to be affected by a proposed project (either negatively or positively), or those which can affect the outcome

More information

COMPONENT 2 - TKB DRAFT

COMPONENT 2 - TKB DRAFT 2015 Resettlement Policy Framework for the Turkey Geothermal Development Project COMPONENT 2 - TKB DRAFT Contents 1. Project Description & Background... 2 2. Principles & Objectives... 3 3. Process for

More information

Semi Annual Environmental Monitoring Report. July 2013 L2557/2558. SRI: Greater Colombo Wastewater Management Project

Semi Annual Environmental Monitoring Report. July 2013 L2557/2558. SRI: Greater Colombo Wastewater Management Project Semi Annual Environmental Monitoring Report July 2013 L2557/2558 SRI: Greater Colombo Wastewater Management Project This environmental monitoring report is a document of the borrower. The views expressed

More information

Seed Fund Proposal Application Form Template

Seed Fund Proposal Application Form Template Seed Fund Proposal Application Form Template Cover Page JSF Seed Fund Proposal Title: Name of implementing agency(s): Proposal location: Implementation Period : Start ---------- Completion----------------

More information

Operational Directive

Operational Directive Page 1 of 9 Involuntary Resettlement Introduction 1. This directive describes Bank 1 policy and procedures on involuntary resettlement, as well as the conditions that borrowers are expected to meet in

More information

PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS

PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS PROCEDURES FOR ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING OF INVESTMENT PROJECTS Approved 10 July 2015 CONTENTS 1. INTRODUCTION 1 2. OVERVIEW OF THE ENVIRONMENTAL AND SOCIAL APPRAISAL AND MONITORING

More information

ABI CODE OF PRACTICE: THIRD PARTY ASSISTANCE

ABI CODE OF PRACTICE: THIRD PARTY ASSISTANCE ABI CODE OF PRACTICE: THIRD PARTY ASSISTANCE Purpose Scope Status of code Contents of this code This code provides guidance for the procedures to be adopted by an insurer when they provide, or offer to

More information

These guidelines can help you in taking the first step and adopt a sustainability policy as well as plan your further sustainability communication.

These guidelines can help you in taking the first step and adopt a sustainability policy as well as plan your further sustainability communication. SUSTAINABILITY POLICY AND COMMUNICATION GUIDELINES Why communicate about sustainability? IFU encourages all our investments to be transparent and informative about business and sustainability performance

More information

National Standards for Disability Services. DSS 1504.02.15 Version 0.1. December 2013

National Standards for Disability Services. DSS 1504.02.15 Version 0.1. December 2013 National Standards for Disability Services DSS 1504.02.15 Version 0.1. December 2013 National Standards for Disability Services Copyright statement All material is provided under a Creative Commons Attribution-NonCommercial-

More information

GHANA S LAND ADMINISTRATION PROJECT: ACCOMPLISHMENTS, IMPACT, AND THE WAY AHEAD. W. ODAME LARBI (PhD, FGhIS) CHIEF EXECUTIVE OFFICER LANDS COMMISSION

GHANA S LAND ADMINISTRATION PROJECT: ACCOMPLISHMENTS, IMPACT, AND THE WAY AHEAD. W. ODAME LARBI (PhD, FGhIS) CHIEF EXECUTIVE OFFICER LANDS COMMISSION GHANA S LAND ADMINISTRATION PROJECT: ACCOMPLISHMENTS, IMPACT, AND THE WAY AHEAD W. ODAME LARBI (PhD, FGhIS) CHIEF EXECUTIVE OFFICER LANDS COMMISSION PRESENTATION OUTLINE Background The National Land Policy

More information

TERMS OF REFERENCE FOR STRATEGIC PLANNING & MANAGEMENT EXPERT

TERMS OF REFERENCE FOR STRATEGIC PLANNING & MANAGEMENT EXPERT TERMS OF REFERENCE FOR STRATEGIC PLANNING & MANAGEMENT EXPERT 1. Background The agency responsible for statistical information in Ghana is the Ghana Statistical Service (GSS) established in 1985 by PNDC

More information

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines

2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines 2010 MTEF: Budgeting for infrastructure and capital expenditure guidelines Introduction The guidelines below provide departments and entities with information to make budget submissions for capital projects

More information

Section 7. Terms of Reference

Section 7. Terms of Reference APPENDIX-A TERMS OF REFERENCE UNION-LEVEL TECHNICAL ASSISTANCE TO PROVIDE INSTITUTIONAL SUPPORT TO THE MYANMAR NATIONAL COMMUNITY DRIVEN DEVELOPMENT PROJECT I. INTRODUCTION IDA GRANT H814MM FY 2013-16

More information

Developing an Implementation Plan

Developing an Implementation Plan Initiative October 2013 / V1 Guidance Note: 3 Developing an Implementation Plan Introduction A key requirement of an application to join CoST is an implementation plan. The implementation plan should respond

More information

V-1 Reference Material for Social Analysis

V-1 Reference Material for Social Analysis Manual for PIP Project Management (Version 3.0, August 2010) Section V Technical Approached in PIP Management Manual for PIP Project Management Section V Technical Approaches in PIP Management Section

More information

Monitoring & Evaluation for Results. Reconstructing Baseline Data for Monitoring & Evaluation -Data Collection Methods-

Monitoring & Evaluation for Results. Reconstructing Baseline Data for Monitoring & Evaluation -Data Collection Methods- Monitoring & Evaluation for Results Reconstructing Baseline Data for Monitoring & Evaluation -Data Collection Methods- 2007. The World Bank Group. All rights reserved. Baseline Data Baseline data are initial

More information

Delivering Development Gains Through Partnerships. Insights for REDD+

Delivering Development Gains Through Partnerships. Insights for REDD+ Delivering Development Gains Through Partnerships. Insights for REDD+ Findings from ongoing research supported by TF-ESSD & PROFOR Diji Chandrasekharan Behr Natural Resource Economist,, World Bank Setting

More information

Forest Carbon Partnership Facility (FCPF)

Forest Carbon Partnership Facility (FCPF) Forest Carbon Partnership Facility (FCPF) Readiness Mechanism Review and Assessment of Readiness Preparation Proposals DRAFT September 4, 2009 This Program Document updates Program Document FMT 2009-1-Rev.2

More information

PROJECT : LAKE TURKANA WINDFARM ACCESS ROAD REHABILITATION COUNTRY : KENYA EXECUTIVE SUMMARY OF THE ABBREVIATED RESETTLEMENT ACTION PLAN

PROJECT : LAKE TURKANA WINDFARM ACCESS ROAD REHABILITATION COUNTRY : KENYA EXECUTIVE SUMMARY OF THE ABBREVIATED RESETTLEMENT ACTION PLAN PROJECT : LAKE TURKANA WINDFARM ACCESS ROAD REHABILITATION COUNTRY : KENYA Project reference: P-KE-FZ0-001 EXECUTIVE SUMMARY OF THE ABBREVIATED RESETTLEMENT ACTION PLAN Head of team: M. GABISCH Investment

More information

JOB DESCRIPTION PROCUREMENT DIRECTOR

JOB DESCRIPTION PROCUREMENT DIRECTOR JOB DESCRIPTION PROCUREMENT DIRECTOR Public Institution Millennium Challenge Account Moldova intends to recruit a Procurement Director for its Management unit to assist the implementation of the Compact

More information

Regulations for the Resettlement Process Resulting from Economic Activities. Decree 31/2012 of 8 August

Regulations for the Resettlement Process Resulting from Economic Activities. Decree 31/2012 of 8 August Regulations for the Resettlement Process Resulting from Economic Activities Decree 31/2012 of 8 August REPUBLIC OF MOZAMBIQUE COUNCIL OF MINISTERS ----------- Decree 31/2012 of 8 August The growing demand

More information

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION DISPUTE REVIEW BOARD THREE PARTY AGREEMENT (EFFECTIVE JULY 2011 LETTINGS)

STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION DISPUTE REVIEW BOARD THREE PARTY AGREEMENT (EFFECTIVE JULY 2011 LETTINGS) STATE OF FLORIDA DEPARTMENT OF TRANSPORTATION DISPUTE REVIEW BOARD THREE PARTY AGREEMENT (EFFECTIVE JULY 2011 LETTINGS) 700-011-02 Page 1 of 10 THIS THREE PARTY AGREEMENT, hereinafter called "AGREEMENT",

More information

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way

Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way Public Works Department Utility Coordination Procedures for Hillsborough County Construction Projects within County Rights-of-Way October 2015 HillsboroughCounty.org HILLSBOROUGH COUNTY Office of the County

More information

REAL ESTATE SPECIALIST CLASSIFICATION SERIES

REAL ESTATE SPECIALIST CLASSIFICATION SERIES Effective Date: May 18, 2003 Modified: December 14, 2003 Modified: April 15, 2007 Modified: November 20, 2011 STATE OF WISCONSIN CLASSIFICATION SPECIFICATION REAL ESTATE SPECIALIST CLASSIFICATION SERIES

More information

F i r s t N a t i o n a n d M é t i s Consultation Policy Framework. June 2010

F i r s t N a t i o n a n d M é t i s Consultation Policy Framework. June 2010 F i r s t N a t i o n a n d M é t i s Consultation Policy Framework June 2010 Table of Contents 1. Introduction.... 2 2. Duty to Consult Policy................................................. 3 1. Policy

More information

OECD RECOMMENDATION CONCERNING GUIDELINES ON EARTHQUAKE SAFETY IN SCHOOLS

OECD RECOMMENDATION CONCERNING GUIDELINES ON EARTHQUAKE SAFETY IN SCHOOLS OECD RECOMMENDATION CONCERNING GUIDELINES ON EARTHQUAKE SAFETY IN SCHOOLS THE COUNCIL Having regard to article 5b) of the Convention establishing the Organisation for Economic Co-operation and Development

More information

Community Development Block Grant Program APPLICATION FORM FOR CONSTRUCTION/ REHAB/ ACQUISITION/ DEMOLITION* PROGRAM YEAR 2015-2016

Community Development Block Grant Program APPLICATION FORM FOR CONSTRUCTION/ REHAB/ ACQUISITION/ DEMOLITION* PROGRAM YEAR 2015-2016 Community Development Block Grant Program APPLICATION FORM FOR CONSTRUCTION/ REHAB/ ACQUISITION/ DEMOLITION* PROGRAM YEAR 2015-2016 PLEASE DO NOT COMPLETE THIS APPLICATION FORM UNTIL YOU HAVE COMPLETED

More information

ii. Project Finance Specialist (national consultant; 9 person-months; intermittent).

ii. Project Finance Specialist (national consultant; 9 person-months; intermittent). 1 ADDITIONAL CONSULTANTS FOR THE PUBLIC PRIVATE PARTNERSHIP CENTER AND THE DEPARTMENT OF FINANCE 1. Expansion of the PPP Center s consultant pool is proposed to strengthen PPP Center s capacity in thematic

More information

5. GUIDELINES FOR PREPARING JOB DESCRIPTIONS

5. GUIDELINES FOR PREPARING JOB DESCRIPTIONS 5. GUIDELINES FOR PREPARING JOB DESCRIPTIONS 5-1 5. GUIDELINES FOR PREPARING JOB DESCRIPTIONS Introduction 1. This section provides information related to the preparation of job descriptions. It includes

More information

Instruction note for ECHO staff on Remote Management

Instruction note for ECHO staff on Remote Management Ref. Ares(2013)168580-08/02/2013 EUROPEAN COMMISSION DIRECTORATE-GENERAL HUMANITARIAN AID AND CIVIL PROTECTION ECHO Instruction note for ECHO staff on Remote Management Commission européenne/europese Commissie,

More information

INCOME MANAGEMENT POLICY

INCOME MANAGEMENT POLICY INCOME MANAGEMENT POLICY 1. Principles 2. Aims 3. Methods * Arrears Prevention * Debt Recovery * Rent Accounting 4. Statutory and Regulatory Requirements 5. Performance Monitoring 6. Review 7. Date of

More information

APB ETHICAL STANDARD 5 NON-AUDIT SERVICES PROVIDED TO AUDIT CLIENTS

APB ETHICAL STANDARD 5 NON-AUDIT SERVICES PROVIDED TO AUDIT CLIENTS APB ETHICAL STANDARD 5 NON-AUDIT SERVICES PROVIDED TO AUDIT CLIENTS (Re-issued December 2004) Contents paragraph Introduction 1-4 General approach to non-audit services 5-38 Identification and assessment

More information

Addressing the social impact of mining activities on communities for sustainability

Addressing the social impact of mining activities on communities for sustainability Addressing the social impact of mining activities on communities for sustainability John-Mark Kilian, Director Umsizi Sustainable Social Solutions (Pty) Ltd, johnmark@umsizi.co.za It is very important

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

MINISTRY OF TRANSPORT AND COMMUNICATIONS OF KYRGYZ REPUBLIC. CAREC Transport Corridor 1 (Bishkek-Torugart Road) Project 3

MINISTRY OF TRANSPORT AND COMMUNICATIONS OF KYRGYZ REPUBLIC. CAREC Transport Corridor 1 (Bishkek-Torugart Road) Project 3 MINISTRY OF TRANSPORT AND COMMUNICATIONS OF KYRGYZ REPUBLIC CAREC Transport Corridor 1 (Bishkek-Torugart Road) Project 3 financed by the Asian Development Bank under Loan 2755-KGZ (SF) TERMS OF REFERENCE

More information

Ex-Ante Evaluation (for Japanese ODA Loan)

Ex-Ante Evaluation (for Japanese ODA Loan) Japanese ODA Loan Ex-Ante Evaluation (for Japanese ODA Loan) 1. Name of the Project Country: The Democratic Socialist Republic of Sri Lanka Project: New Bridge Construction Project over the Kelani River

More information

FLINTSHIRE COUNTY COUNCIL COMMUNITY ASSET TRANSFER GUIDANCE NOTES

FLINTSHIRE COUNTY COUNCIL COMMUNITY ASSET TRANSFER GUIDANCE NOTES FLINTSHIRE COUNTY COUNCIL COMMUNITY ASSET TRANSFER GUIDANCE NOTES CONTENTS Page (s) 1. PURPOSE OF THE GUIDE 1 2. KEY STAGES OF CAT PROCESS Stage 1 Expression of Interest Stage 2 Business Modelling Stage

More information

STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION

STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION STATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION TITLE GRADE EEO-4 CODE RIGHT-OF-WAY SUPERVISOR 39 A 7.412 SERIES CONCEPT Right-of-Way Agents appraise,

More information

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Guidelines for State Agency Management of Volunteer Activity

Guidelines for State Agency Management of Volunteer Activity Guidelines for State Agency Management of Volunteer Activity June 2008 Department of Premier and Cabinet Contents Introduction... 3 Scope and Definitions... 4 Relationship between Agencies and Volunteers...

More information

COMPLAINTS MANAGEMENT PROCESS

COMPLAINTS MANAGEMENT PROCESS COMPLAINTS MANAGEMENT PROCESS December, 2012 1. INTRODUCTION COMPLAINTS MANAGEMENT PROCESS The Complaint Management Process has been developed to provide a single system through which complaints about

More information

IRS PROCEDURAL ISSUES

IRS PROCEDURAL ISSUES IRS PROCEDURAL ISSUES I. Introduction A. In general, IRS procedural issues involving organizations that are, are seeking to become, or claim to be exempt from Federal income tax are the same as those for

More information

Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY. Sacramento River Southport Early Implementation Project

Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY. Sacramento River Southport Early Implementation Project Real Estate Acquisition Guidelines For: WEST SACRAMENTO AREA FLOOD CONTROL AGENCY Sacramento River Southport Early Implementation Project TABLE OF CONTENTS Introduction... 1 Before the Acquisition Process

More information

Please see Section IX. for Additional Information:

Please see Section IX. for Additional Information: The Florida Senate BILL ANALYSIS AND FISCAL IMPACT STATEMENT (This document is based on the provisions contained in the legislation as of the latest date listed below.) BILL: CS/SB 1064 Prepared By: The

More information

Introduction to SOP. Background. Background. Principles of SOP Act. Objectives of SOP Act

Introduction to SOP. Background. Background. Principles of SOP Act. Objectives of SOP Act Introduction to SOP Background Building and Construction Industry Security of Payment (SOP) Act Objectives of Act Principles of Act Key Provisions of Act by Lim Jue Meng Jennifer Leong Ng Cher Cheng Feedback

More information

Motor Vehicle Insurance. and. Repair Industry. Code of Conduct

Motor Vehicle Insurance. and. Repair Industry. Code of Conduct . Motor Vehicle Insurance and Repair Industry Code of Conduct Revised March 2011 MOTOR VEHICLE INSURANCE AND REPAIR INDUSTRY CODE OF CONDUCT 1 TABLE OF CONTENTS PREAMBLE... 3 1. PRINCIPLES OF THE CODE...

More information

September 2008. Claims Guideline

September 2008. Claims Guideline September 2008 Claims Guideline CLAIMS GUIDELINE Table of Contents 1 INTRODUCTION... 1 2 PURPOSE OF THE GUIDELINE... 1 3 DEFINITIONS... 2 MARKET CONDUCT 4 GENERAL REQUIREMENTS... 3 5 CLAIMS NOTIFICATION...

More information

ENVIRONMENTAL MANAGEMENT STRATEGY

ENVIRONMENTAL MANAGEMENT STRATEGY Jos& M. Cabral 36 1 ENVIRONMENTAL MANAGEMENT STRATEGY FOR INFRASTRUCTURE AGENCIES IN DEVELOPING COUNTRIES Jose M. Cabral' INTRODUCTION This paper describes an environmental management strategy for agencies

More information

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery

Document Commentary. AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery Document AIA Document C191 2009, Standard Form Multi-Party Agreement for Integrated Project Delivery INTRODUCTION Current practice in the construction industry promotes inefficiency when the key project

More information

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR

CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector

More information

عقد العمل الخاص بالعمالة الهندية المغادرة للمملكة العربية السعودية

عقد العمل الخاص بالعمالة الهندية المغادرة للمملكة العربية السعودية STANDARD EMPLOYMENT CONTRACT FOR INDIAN DOMESTIC SERVICE WORKERS (DSW) BOUND FOR THE KINGDOM OF SAUDI ARABIA UNDER ARTICLE 3(IV) OF AGREEMENT ON LABOUR COOPERATION ON DOMESTIC SERVICE WORKERS SIGNED BETWEEN

More information

Bank on Human Rights. Key Human Rights Concerns and Recommendations regarding the World Bank s Proposed Social and Environmental Safeguards Framework

Bank on Human Rights. Key Human Rights Concerns and Recommendations regarding the World Bank s Proposed Social and Environmental Safeguards Framework Bank on Human Rights Key Human Rights Concerns and Recommendations regarding the World Bank s Proposed Social and Environmental Safeguards Framework March, 2015 I. Respect for human rights The World Bank

More information

Environment Sustainability and Highways

Environment Sustainability and Highways Job Title: Marketing Intelligence Officer Job Grade: Band 4 Directorate: Environment Sustainability and Highways Job Reference Number: P01851 The Role The Marketing Intelligence Officer will: Devise intelligence

More information

BYLAWS OF THE TOLEDO METROPOLITAN AREA COUNCIL OF GOVERNMENTS

BYLAWS OF THE TOLEDO METROPOLITAN AREA COUNCIL OF GOVERNMENTS BYLAWS OF THE TOLEDO METROPOLITAN AREA COUNCIL OF GOVERNMENTS PREAMBLE: It is hereby affirmed that: A. The local governments - counties, cities, villages, townships, public school districts, public universities

More information

Outline feasibility study for ORET application in the health care sector

Outline feasibility study for ORET application in the health care sector Outline feasibility study for ORET application in the health care sector In this section we outline the information needed for a proper assessment of your application for financing under the ORET program.

More information

Identification. Preparation and formulation. Evaluation. Review and approval. Implementation. A. Phase 1: Project identification

Identification. Preparation and formulation. Evaluation. Review and approval. Implementation. A. Phase 1: Project identification II. Figure 5: 6 The project cycle can be explained in terms of five phases: identification, preparation and formulation, review and approval, implementation, and evaluation. Distinctions among these phases,

More information

DISCIPLINARY POLICY AND PROCEDURE

DISCIPLINARY POLICY AND PROCEDURE DISCIPLINARY POLICY AND PROCEDURE Date of Publication: April 2013 Agreed by: Vice Chancellor s Executive March 2013 Page 1 of 13 Policy 1.0 Introduction The purpose of the disciplinary policy and procedure

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014 the European Economic Area (EEA) Financial Mechanism 2009-2014 adopted by the EEA Financial Mechanism Committee pursuant to Article 8.8 of Protocol 38b to the EEA Agreement on 13 January 2011 and confirmed

More information

Environmental Assessment

Environmental Assessment BP 4.01 January 1999 These procedures were prepared for use by World Bank staff and are not necessarily a complete treatment of the subject. Environmental Assessment (Archived August 2004) Note: OP and

More information

Adopted by the Security Council at its 4761st meeting, on 22 May 2003

Adopted by the Security Council at its 4761st meeting, on 22 May 2003 United Nations S/RES/1483 (2003) Security Council Distr.: General 22 May 2003 Resolution 1483 (2003) Adopted by the Security Council at its 4761st meeting, on 22 May 2003 The Security Council, Recalling

More information

Islamic Republic of Afghanistan, Post Disaster Need Assessment (PDNA) Training Manual

Islamic Republic of Afghanistan, Post Disaster Need Assessment (PDNA) Training Manual Islamic Republic of Afghanistan, Ministry of Rural Rehabilitation and Development (MRRD) Ministry of Rural Rehabilitation & Development Post Disaster Need Assessment (PDNA) Training Manual Social Protection

More information

Chapter 3 Office of Human Resources Absenteeism Management

Chapter 3 Office of Human Resources Absenteeism Management Office of Human Resources Absenteeism Management Contents Section A - Background, Objective and Scope............................ 24 Section B - Criterion 1 - Communicating Expectations.......................

More information

SERVICE SPECIFICATION

SERVICE SPECIFICATION SERVICE SPECIFICATION Provision of a Service for Young Carers Wokingham Borough Council OFFICIAL - SENSITIVE Page 1 1. Introduction This is the service specification for the provision of a Young Carers

More information

SELF-DIRECTED INDIVIDUAL 401K ACCOUNT HOLDER DISCLOSURE AND HOLD HARMLESS

SELF-DIRECTED INDIVIDUAL 401K ACCOUNT HOLDER DISCLOSURE AND HOLD HARMLESS SELF-DIRECTED INDIVIDUAL 401K ACCOUNT HOLDER DISCLOSURE AND HOLD HARMLESS P.O. BO 30007 ALBUQUERQUE, NEW MEICO 87190 P: 888-205-6036 F: 505-288-3905 OPERATIONS@HORIZONTRUST.COM Important! This form contains

More information

Programme Manager/Procurement Specialist. Suva. Capital Works Manager. As soon as possible. As follows

Programme Manager/Procurement Specialist. Suva. Capital Works Manager. As soon as possible. As follows JOB DESCRIPTION Position: Location of position: Reporting to: Special functional relationships: Term of Appointment: Programme Manager/Procurement Specialist Suva Capital Works Manager Capital Works Programme

More information

No. 132. Land Use and Building Act (132/1999, amendment 222/2003 included) Chapter 1. General provisions. Section 1 General objective of the Act

No. 132. Land Use and Building Act (132/1999, amendment 222/2003 included) Chapter 1. General provisions. Section 1 General objective of the Act NB: UNOFFICIAL TRANSLATION FINLAND No. 132 Land Use and Building Act (132/1999, amendment 222/2003 included) In accordance with the decision of Parliament the following is enacted: Chapter 1 General provisions

More information

CHAPTER 3 - CUSTOMER RELATIONSHIP MANAGEMENT (CRM)

CHAPTER 3 - CUSTOMER RELATIONSHIP MANAGEMENT (CRM) CHAPTER 3 - CUSTOMER RELATIONSHIP MANAGEMENT (CRM) 3.1 INTRODUCTION The most important purpose of any service orientated organisation is to retain customers. It is critical for any organization to keep

More information

PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN

PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN PUBLIC RIGHT-OF-WAY ACCESSIBILITY TRANSITION PLAN FOR THE VILLAGE OF HUNTLEY, ILLINOIS 2015 Contents Introduction 1 Purpose 1 Officials Responsible for Implementation 2 Public Notice 2 Grievance Procedure

More information

Lawrence Heights Revitalization Corporate Implementation Actions and Social Development Plan

Lawrence Heights Revitalization Corporate Implementation Actions and Social Development Plan STAFF REPORT ACTION REQUIRED Lawrence Heights Revitalization Corporate Implementation Actions and Social Development Plan Date: June 8, 2010 To: From: Wards: Community Development and Recreation Committee

More information

PLEASE NOTE. For more information concerning the history of this Act, please see the Table of Public Acts.

PLEASE NOTE. For more information concerning the history of this Act, please see the Table of Public Acts. PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this Act, current to December 2, 2015. It is intended for information and reference purposes only. This

More information

North American Development Bank. Prequalification of Contractors

North American Development Bank. Prequalification of Contractors North American Development Bank Prequalification of Contractors PREQUALIFICATION NOTE This note is prepared for the exclusive use of the borrower (the purchaser in this document) and should not be included

More information

ASPIRE CHARTER ACADEMY, INC. A Charter School and Component Unit of the District School Board of Orange County, Florida

ASPIRE CHARTER ACADEMY, INC. A Charter School and Component Unit of the District School Board of Orange County, Florida Financial Statements with Independent Auditors Reports Thereon June 30, 2015 CONTENTS Page Management s Discussion and Analysis 1 6 Report of Independent Auditors on Basic Financial Statements and Supplementary

More information

Analysis of Strategic Management in Small and Medium Business Organizations in Graphic Industry

Analysis of Strategic Management in Small and Medium Business Organizations in Graphic Industry Review paper UDK: 655.005.21 Analysis of Strategic Management in Small and Medium Business Organizations in Graphic Industry Abstract Graphic industry as a field of work and a field of study offers ability

More information

Advisory Guidelines of the Financial Supervision Authority

Advisory Guidelines of the Financial Supervision Authority Advisory Guidelines of the Financial Supervision Authority General requirements to insurance contracts These Advisory Guidelines were established by Resolution No 89 of the Management Board of the Financial

More information

An Introduction to Conservation Covenants. A Guide For Developers and Planning Departments

An Introduction to Conservation Covenants. A Guide For Developers and Planning Departments An Introduction to Conservation Covenants A Guide For Developers and Planning Departments The Land Trust Alliance of BC Revised April 2007 Photo: Millard Piercy Watershed Courtenay, BC several conservation

More information

Guidelines on preparation for and management of a financial crisis

Guidelines on preparation for and management of a financial crisis CEIOPS-DOC-15/09 26 March 2009 Guidelines on preparation for and management of a financial crisis in the Context of Supplementary Supervision as defined by the Insurance Groups Directive (98/78/EC) and

More information

CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES

CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES CHAPTER 12 Revised January 1, 2013 SIGNING AND SEALIN OF PROFESSIONAL SURVEY DELIVERABLES Chapter Contents Sec. 12.01 Sec. 12.02 Sec. 12.03 Sec. 12.04 Sec. 12.05 Sec. 12.06 Introduction Business & Legal

More information

Setting the Expectation for Success: Performance Management & Appraisal System

Setting the Expectation for Success: Performance Management & Appraisal System HILLSBOROUGH COUNTY CIVIL SERVICE BOARD OFFICE Setting the Expectation for Success: Performance Management & Appraisal System Supervisor s Guide PROCESS OVERVIEW Setting the Expectation for Success: Performance

More information

Chapter 11 Housing Page 11-1

Chapter 11 Housing Page 11-1 Housing Page 11-1 11(1) Municipal Standards for Condominium Developments That the following minimum Municipal Standards for condominium developments be established: Minimum Municipal Standards Parking

More information

Grievance Management. What s in this section? Process is important. Scale the mechanism to project needs. Put it in writing and publicize it

Grievance Management. What s in this section? Process is important. Scale the mechanism to project needs. Put it in writing and publicize it Grievance Management What s in this section? GRIEVANCE MANAGEMENT 70 70 72 72 73 75 75 76 Process is important Scale the mechanism to project needs Put it in writing and publicize it Bring in third parties

More information

Reporting Service Performance Information

Reporting Service Performance Information AASB Exposure Draft ED 270 August 2015 Reporting Service Performance Information Comments to the AASB by 12 February 2016 PLEASE NOTE THIS DATE HAS BEEN EXTENDED TO 29 APRIL 2016 How to comment on this

More information

Tender Procedures for EU-funded Projects

Tender Procedures for EU-funded Projects Tender Procedures for EU-funded Projects Membership in the European Union opens up an opportunity for Bulgaria to utilize up to 7 billion EUR during the period 2007-2013. The economic and social areas

More information

GENERAL ELECTRIC COMPANY EMPLOYMENT DATA PROTECTION STANDARDS

GENERAL ELECTRIC COMPANY EMPLOYMENT DATA PROTECTION STANDARDS GENERAL ELECTRIC COMPANY EMPLOYMENT DATA PROTECTION STANDARDS December 2005 2 GENERAL ELECTRIC COMPANY EMPLOYMENT DATA PROTECTION STANDARDS I. OBJECTIVE... 1 II. SCOPE... 1 III. APPLICATION OF LOCAL LAWS...

More information

The dispute is about the sale of a payment protection insurance (PPI) policy in connection with a credit card account with the firm in April 2007.

The dispute is about the sale of a payment protection insurance (PPI) policy in connection with a credit card account with the firm in April 2007. FINAL DECISION complaint by: Mr E complaint about: the firm complaint reference: date of decision: April 2009 This final decision is issued by me, Robert Short, an ombudsman with the Financial Ombudsman

More information

4.4 Commissioning, Handover and Warranty

4.4 Commissioning, Handover and Warranty 4.4 Commissioning, Handover and Warranty 4.4.1 Building Commissioning and Manuals The Building Commissioning formalizes the review and integration of all project expectations during the planning and design,

More information

Procurement Performance Measurement System

Procurement Performance Measurement System Public Procurement and Disposal of Public Assets Authority Procurement Performance Measurement System User's Guide August 2008 Public Procurement and Disposal of Public Assets Authority Procurement Performance

More information