Resource efficiency through BIM: A Guide for BIM Managers

Size: px
Start display at page:

Download "Resource efficiency through BIM: A Guide for BIM Managers"

Transcription

1 Guidance on resource efficient construction Resource efficiency through BIM: A Guide for BIM Managers Shared model and data Design development and optimisation Rapid analysis and quantification Guidance for BIM Managers on systems and processes to enable resource efficiency to be considered through design, construction and asset management February 2013 Issue 1.0

2 WRAP s vision is a world without waste, where resources are used sustainably. We work with businesses, individuals and communities to help them reap the benefits of reducing waste, developing sustainable products and using resources in an efficient way. Find out more at Written by: Adam Mactavish and Nahim Iqbal Document reference: [e.g. WRAP, 2006, Report Name (WRAP Project TYR Report prepared by..banbury, WRAP] Edited by: Dave Marsh, WRAP WRAP and Sweett Group believe the content of this report to be correct as at the date of writing. However, factors such as prices, levels of recycled content and regulatory requirements are subject to change and users of the report should check with their suppliers to confirm the current situation. In addition, care should be taken in using any of the cost information provided as it is based upon numerous project-specific assumptions (such as scale, location, tender context, etc.). The report does not claim to be exhaustive, nor does it claim to cover all relevant products and specifications available on the market. While steps have been taken to ensure accuracy, WRAP cannot accept responsibility or be held liable to any person for any loss or damage arising out of or in connection with this information being inaccurate, incomplete or misleading. It is the responsibility of the potential user of a material or product to consult with the supplier or manufacturer and ascertain whether a particular product will satisfy their specific requirements. The listing or featuring of a particular product or company does not constitute an endorsement by WRAP and WRAP cannot guarantee the performance of individual products or materials. This material is copyrighted. It may be reproduced free of charge subject to the material being accurate and not used in a misleading context. The source of the material must be identified and the copyright status acknowledged. This material must not be used to endorse or used to suggest WRAP s endorsement of a commercial product or service. For more detail, please refer to WRAP s Terms & Conditions on its web site:

3 Contents 1.0 Introduction Resource Efficiency in Construction Overview Opportunities to improve resource efficiency Why focus on resource efficiency? Measuring performance Resource Management Plans (RMP) The approach for addressing resource efficiency through BIM, and the role of the BIM Manager Key actions and steps Important considerations Defining resource efficiency objectives Embedding the approach within the BIM Execution Plan Structure of a typical BIM Execution Plan Incorporating resource efficiency information Applying resource efficiency information to BIM objects Internal data association External data association Practical considerations Data requirements Adding data to BIM objects Managing project data to benchmark and improve performance Benchmarking resource efficiency performance Tracking performance over time WRAP tools to help track project performance Defining and communicating your approach Appendix A: Example of BIM Execution Plan incorporating resource efficiency elements Appendix B: Partial proforma for assessing design team competency and approach to BIM implementation Resource efficiency through BIM: A Guide for BIM Managers

4 1.0 Introduction The adoption of Building Information Modelling and Management (BIM) is a major evolution in the ways in which information on construction projects is generated, shared and managed. BIM brings the potential for widespread efficiencies in project delivery. This Guide considers just one of these: the more efficient use of natural resources, and specifically focuses on the role of the BIM manager in helping deliver these benefits. Resource efficiency involves achieving the required project outcomes using fewer resources (carbon, energy, materials, and water) resulting in reduced impacts (climate change, resource depletion, carbon emissions, water scarcity, and project costs). Ultimately, successful organisations will be able to closely manage their use of increasingly scarce and expensive resources; demonstrating greater value for money by reducing costs and meeting environmental objectives. BIM is not essential to improving a project s resource efficiency. However, incorporating resource efficiency into BIM implementation makes sense because BIM processes and data can be used directly to achieve efficiencies and also to help estimate performance and identify the biggest opportunities to save money and carbon. This Guide is part of a series of complementary guidance on using BIM effectively to improve resource efficiency in construction projects. Information Note A succinct summary for senior decision makers in projects and construction companies so they can buy-in to the process. BIM Manager s Guide (this Guide) Shows how resource efficiency can be incorporated into an organisation s BIM processes, datasets and methods. BIM User s Guide Explains practical approaches for using the BIM design workflow to help identify opportunities for improve resource efficiency, and to help estimate the environmental and cost impacts and benefits. This Guide does not focus in detail on BIM itself and assumes that the reader is suitably familiar with BIM tools and delivery processes; rather it considers how they can be applied to the challenge of making better use of construction resources. Other WRAP publications provide further detailed information on resource efficiency. Throughout the Guide key sources of further information are indicated in the format below. Further information on resource efficiency Background information and articles on BIM Resource efficiency through BIM: A Guide for BIM Managers 4

5 2.0 Resource Efficiency in Construction 2.1 Overview What? Resource efficient construction makes best use of materials, water and energy over the lifecycle of built assets to minimise embodied and operational carbon. This prioritises consideration of: reducing materials use and wastage; increasing reuse and recycled content, and enabling reuse and recyclability at end of life; matching the durability and lifespan of assets to proposed service life; using resources with no scarcity and source security issues; using products with lower embodied carbon and embodied water; reducing energy and water use during construction; and enabling energy efficiency and water efficiency in use. When? Resource efficiency opportunities exist throughout the construction lifecycle including product manufacture, design, construction, operation, refurbishment, and at end of life. Why? Business benefits, including: reducing costs and project risk; stimulating innovation; demonstrating compliance with regulations, standards and planning requirements; supporting industry objectives; and improving reputation. Environmental benefits, including: helping to achieve climate change targets; reducing depletion of natural resources; and helping to tackle water scarcity. How? Best results will be achieved where there is a strong client lead together with coordinated action from the supply chain utilising effective Resource Management Planning Process and technical innovations can support resource efficiency in construction, including BIM, Lean, offsite construction and logistics solutions. 2.2 Opportunities to improve resource efficiency Whilst much of this Guide focuses on efficiencies in the design and construction process, consideration must also be given to the impact of design decisions on operational performance, the longevity and flexibility of the asset and its end of life management. For a new or refurbished building, the key opportunities include: Prepare Understand the site and the opportunities and constraints it presents. Target the project s resource efficiency objectives to reflect site specific considerations. Resource efficiency through BIM: A Guide for BIM Managers 5

6 Design Develop the minimum amount of space that will fully achieve the functional requirements (e.g. reducing the overall space requirement by improving the net to gross ratios or creating flexible multiuse spaces). Design an operationally efficient (including energy, water and facilities management) building that is flexible to accommodate future changes in use. Use as few materials as necessary. Choose materials with low lifecycle impacts (e.g. embodied energy, water and carbon) and a durability that reflects their life span within the building. Source products that make good use of resources by using recycled content, sustainably sourced renewable materials and energy, material and water efficient manufacturing and supply. Construct Manage materials to minimise costs and wastage during transport, delivery and installation. Maximise the recovery and reuse of surplus material and wastes from construction and if removed at demolition / refurbishment. Use energy and water efficiently on site. Operate Enable efficient operations by encouraging responsible use, careful management and maintenance of equipment and facilitating investment in new more efficient technologies. For any given project the priorities and opportunities will vary considerably. Successfully reducing resource use on a project requires the input and collaboration of many parties and the ongoing sharing of information. BIM tools and processes have an important role in this process by helping project teams identify, investigate and implement these opportunities in a co-ordinated way. BIM data also provide a powerful resource for helping to estimate resource efficiency, benchmark and identify improvement opportunities thereby informing decision making, and monitoring and reporting outcomes. 2.3 Why focus on resource efficiency? The Government s Low Carbon Construction Action Plan, and the subsequent establishment of the Green Construction Board all signify that the UK construction sector is critical to the growth and decarbonisation of the economy. To meet this challenge it is imperative that the industry is able to work more efficiently, getting better value for the cost and carbon involved in project delivery. Resource efficiency delivers powerful benefits by: reducing project costs; demanding a focus on quality and co-ordination throughout the design and construction process; encouraging innovation and a creative approach; and reducing the environmental impacts of construction. Resource efficiency through BIM: A Guide for BIM Managers 6

7 The importance of making efficient use of all resources will continue to grow as global demand for materials, energy and water increases and it becomes harder to dispose of waste. Those organisations taking proactive steps to be more resource efficient will be more cost competitive and better able to meet their stakeholders requirements, be they customers, policy makers, employees or regulators. BIM is a key tool helping the industry achieve these efficiencies; making better and wider use of information to co-ordinate, test and improve decision making from the outset of a project to its completion and use. However, the adoption of 3D modelling and other BIM tools will not in itself change behaviours and performance. BIM Managers are responsible for helping their organisation maximise the benefits of adopting BIM. This includes making good use of the data in each model by setting up processes for timely provision of robust and accessible information. The Low Carbon Construction Action Plan Green Construction Board Measuring performance Measuring the impact of any resource efficiency actions is important in assessing their value for money. BIM is a useful tool to support measurement but nonetheless it is important to take a proportionate approach and ensure that time spent on measuring performance is justifiable in the context of overall project and the potential savings. A wide range of metrics could be used to measure the different elements of resource efficiency, however it is recommended that the initial focus is on few priority metrics. The following metrics are considered to generally represent current priorities of resource efficient construction: Embodied carbon, including emissions associated with manufacture, supply and installation of construction products (tco 2e ). Non-renewable energy use from onsite activities (MJ GCV or kwh, split by energy type). Waste produced (tonnes, split by hazardous, non-hazardous and inert and whether this is construction, demolition or excavation waste). Recycled content of materials used (% by value). Water use onsite (m 3, split by water source). These metrics do not address all response efficiency elements, however they enable practical action through design and construction, and provide a robust starting point to inform decision making and performance benchmarking. The above metrics can also be used to report performance indicators by dividing by an appropriate measure of either the spatial area developed (e.g. m 2 gross internal floor area), the function delivered (e.g. per pupil, bedspace, patient, etc) or for specific project elements (e.g. per m 2 of external wall area). In combination, these Resource efficiency through BIM: A Guide for BIM Managers 7

8 measures can enable project teams and clients to assess if their design and specification is resource efficient and if it has been delivered in an efficient way. See section 7 for further discussion on benchmarking and reporting performance. 2.5 Resource Management Plans (RMP) Resource management planning is an effective process for improving the resource efficiency of a project. The RMP defines the scope and priorities for resource efficiency for the project and provides a framework for recording actions, estimating their impacts, monitoring performance and reporting. Many of the actions within an RMP are routinely undertaken on many projects. For example, site waste management planning, design co-ordination and clash prevention, logistics strategies, etc. In addition, depending on the scope determined for the project, an RMP might include actions to reduce embodied carbon or increase recycled content during product selection. BIM data and tools can have a significant role in improving project resource efficiency, and these opportunities (see Section 3 for examples) should be recognised within the RMP and actions defined for ensuring that BIM activities support the project s resource efficiency objectives. Similarly, the project BIM Execution Plan should specify in more detail how BIM will be used to input to the RMP, for example by defining the processes, tools and data that will be used at different stages (see Section 4 for further information). Further information on Resource Management Plans Further information on materials logistics planning Resource efficiency through BIM: A Guide for BIM Managers 8

9 3.0 The approach for addressing resource efficiency through BIM, and the role of the BIM Manager 3.1 Key actions and steps A BIM Manager can help their organisation to improve and demonstrate resource efficiency through four key actions: Defining resource efficiency objectives Embedding resource efficiency actions within the approach to BIM Execution Planning. Developing or using an object library that contains industry standard classification (e.g. Uniclass) systems, and ideally contains embedded resource efficiency data. Managing project data to enable benchmarking and refinement of the resource management planning process. These are each considered in the following sections of this Guide. The BIM Manager should liaise closely with their organisation s environmental / sustainability manager (if there is one) to ensure coordination between the strategy for reducing resource use and the BIM processes, data and reporting outputs (e.g. COBie files) at key project stages. Figure 1 illustrates the key steps involved identification of the scope for the project followed by action planning and periodic estimation and monitoring of performance. Figure 1 Steps in building resource efficiency into a BIM based project process These steps are explained further in the BIM User s Guide. Resource efficiency through BIM: A Guide for BIM Managers 9

10 3.2 Important considerations The requirements of each organisation and the right approach to embedding resource efficiency within a BIM process will vary according to size, discipline (see Table 1), sector, experience and capability, and project or company priorities and objectives. It is vitally important that these are proportionate and practicable, and there should not be an aim to do everything. If the demands on the project team are unreasonable then they are likely to be unfulfilled, completed badly, or lead to loss of interest or enthusiasm for improving resource efficiency. For example, an engineer that already has well developed BIM design capabilities may find it reasonably straightforward to incorporate analysis of embodied carbon in materials by embedding this data within their library of BIM objects. Alternatively, an architects practice that is still establishing its BIM capabilities may not wish to undertake quantification of resource use within BIM, but may instead choose to use BIM tools to minimise wastage through effective clash prevention and design co-ordination. Then over time as experience is gained, this practice is likely to start incorporating analysis to draw on the additional benefits brought through measurement and benchmarking. Table 1 Examples of using BIM in delivering resource efficiency by different disciplines Discipline Resource efficiency opportunity Role of BIM (examples) Civil engineers Balancing cut and fill Building designers Sourcing low impact materials Effectively managing excavation materials Reducing materials use through evaluation of different design/structural options Selecting components with low embodied carbon Taking steps to minimise wastage through careful design co-ordination Site teams Avoiding rework/clashes onsite Planning logistics and management of deliveries Minimising wastes through establishment of management and installation methods for priority materials Reducing energy and water use on site Maintaining a record of actual performance (e.g. materials used and the associated embodied carbon) BIM can help in all of these areas by supporting cut and fill calculations helping to quantify excavation arisings and material requirements. BIM tools can be used to refine designs, co-ordinate designs and prevent clashes. Data can be extracted from the BIM model to calculate embodied carbon and other impacts, and can also be used as a basis for forecasting the mass/volume and cost of material wastage. BIM will help in minimising and managing design changes whilst supporting effective installation and clash prevention by providing clear visualisations and up to date design details. The work of different trade contractors and suppliers can be effectively integrated within the overall model. Sequencing tools will assist with logistics planning and can also inform estimates of site energy and water use. BIM is the ideal resource for maintaining an as-built model that demonstrates the resource efficiency of the project as delivered. Resource efficiency through BIM: A Guide for BIM Managers 10

11 4.0 Defining resource efficiency objectives If a resource efficiency strategy is already in place within the project or company then this should be the reference for determining the role of BIM tools and processes. If a formal strategy is not in place, then the following questions may help in identifying resource efficiency priorities and requirements. What are the key sources of resource use and potential savings for typical projects or activities undertaken? What internal policy objectives have been set? Which project requirements are frequently requested? Are these requirements likely to change in the future? The aim should be to develop a practical set of resource efficiency objectives that meet all internal and typical external requirements and address the key opportunities to reduce cost, carbon and other impacts. BIM Managers should consider the following questions when assessing how they can best to support their organisation s or project s key resource efficiency objectives. What level of detail is practical for estimating resource efficiency performance for different topics and at different project stages? What existing tools and systems can be developed or modified to support resource efficiency? For example, refinement of the BIM Execution Plan (see Section 5) What new tools 1, or systems, are needed to support this analysis? Are new schedule templates and or calculations required? What sources of resource efficiency data could be used to identify opportunities and quantify performance (see section 6)? How should resource efficiency data be managed? For example, by: o embedding resource efficiency data into BIM library objects; or o linking information from the model with external datasets (e.g. WRAP s resource efficiency benchmarks). Is the organisation and its suppliers competent to take the steps necessary to meet the resource efficiency objectives using BIM? If not, what training is required? How could resource efficiency be incorporated within the organisation s template approach to BIM execution planning? Consulting with colleagues (including the environmental / sustainability lead) will be helpful in gaining a detailed understanding of the potential benefits and existing capabilities of the organisation. Further information on setting and responding to resource efficiency objectives 1 A review of some of the resource efficiency potential of some of the more well known tools is included in the BIM Users Guide Resource efficiency through BIM: A Guide for BIM Managers 11

12 5.0 Embedding the approach within the BIM Execution Plan 5.1 Structure of a typical BIM Execution Plan A BIM Execution Plan is the core co-ordinating tool that defines how BIM will be implemented on a project. It is important that resource efficiency elements that are relevant to BIM are incorporated within the plan. This content should refer to, and need not repeat, detail within the project Resource Management Plan (if one exists). A UK standard BIM Execution Plan template does not currently exist, although examples are emerging. The need for its development and implementation on design projects has been emphasised by leading organisations i.e. HM Government, RICS, CPIC (Construction Project Information Committee) and Constructing Excellence. In this Guide a BIM Execution Plan template developed by BIM Academy 2 is used as the reference, although as BIM adoption escalates this template will be developed and refined. The BIM Execution Plan should define all BIM-related aspects that will be applied to the project (including the objectives, activities, data and design protocols), typically comprising the following components: 1.0 Executive summary 2.0 Introduction 3.0 Project Information 4.0 Key Project Contacts 5.0 Project Goals, BIM Uses and Capabilities 6.0 Roles and Responsibilities 7.0 BIM Process Design 8.0 Model Element LOD and Responsibility Worksheet 9.0 Facility and Asset Management Requirements 10.0 Collaboration Procedures 11.0 Quality Control 12.0 Technological Infrastructure Needs 13.0 Model Standards and Guidelines 14.0 Delivery Strategy Agreement 15.0 Appendices The detail of the templates in use by different organisations will vary. However, their purpose and overall structure is not likely be too dissimilar from that described above. Appendix A contains a model BIM Execution Plan, with information on resource efficiency added and highlighted; this is discussed further below. 5.2 Incorporating resource efficiency information To date, resource efficiency considerations have not typically been specified within BIM Execution Plans; however there is potential for including relevant information that will help deliver a co-ordinated approach. Key sections where information can be added include: 5.0 Project goals these relate to high level objectives e.g. improve design quality, support reliable decision making and enhance communication. Project goals are achieved through the deployment of one or more BIM uses and resource efficiency can be included in this section, ideally in the form of a specific goal with performance measures / targets. For individual projects the objectives, measures and targets should reflect 2 Based around an original template developed by Penn State University. Resource efficiency through BIM: A Guide for BIM Managers 12

13 client or other project requirements and ideally be those stated within the project Resource management plan (if one exists). 6.0 Roles and responsibilities following the identification of project goals, the responsibility of individual team members for delivery of the required information, analysis or decisions is specified. Teams are often assessed through an interview process to identify level of capability for each BIM use. Resource efficiency can be incorporated into the assessment process thereby identifying capacity and training requirements. Appendix B provides a proforma for assessing design team competency and approach to BIM implementation. 7.0 BIM Process Design this is a technique used to summarise the BIM uses that will be deployed at different project stages and to identify those responsible for delivery. Various outputs from BIM uses e.g. 3D models, schedules and visualisations, are defined. Activities to enhance resource efficiency should be incorporated into this workflow together with relevant outputs such as a Resource Management Plan report. 9.0 Facility and Asset Management Requirements this section of the plan specifies the reporting deliverables that will be provided detailing the facility and its intended management regime. For public sector projects this will take the form of COBie data files (see section 6 of this Guide) delivered at key stages in the project. The COBie files can include information on resource efficiency performance, although this information can also be reported separately (e.g. within a Resource Management Plan) Collaboration Procedures these identify the basic requirements for collaborative working practices and communication e.g. s, video conferencing and meetings. In addition meeting requirements are specified in reference to type, project stage, frequency, participants and location. Resource efficiency specific procedures should be detailed e.g. workshops and review periods Technological Infrastructure Needs in this section all members of the project team are required to specify the technologies to be deployed to support the delivery of each BIM use. The data, methods and tools required to meet the project s resource efficiency objectives should be specified Model Standards and Guidelines this section sets out the approach to data management and the data systems that will be used across the project team. The relevant set of resource efficiency data parameters and sources (see Section 6) should be specified here. Figure 2 illustrates key resource efficiency activities and how these map into the BIM Execution Plan. Other sections of the BIM Execution Plan, e.g. Quality Control (which focuses on design coordination and clash prevention) are highly relevant to the overall performance of the project, but it is not necessary to specifically mention resource efficiency in relation to these activities. The BIM Execution Plan is ideally initiated at a workshop session involving the client and wider project team. This is the best time to highlight and agree the approach to incorporating resource efficiency aspects into the BIM workflow. Resource efficiency through BIM: A Guide for BIM Managers 13

14 It is important to remember that the BIM Execution Plan is not a BIM manual and should not include detailed processes for undertaking different studies. Instead it is a vehicle for clearly stating the protocols that will be followed when undertaking the project. As such resource efficiency requirements should be incorporated clearly, but concisely, with appropriate reference to other more detailed information sources such as WRAP guidance and tools. Resource efficiency through BIM: A Guide for BIM Managers 14

15 Figure 2 Incorporating resource efficiency within the BIM Execution Plan BIM Execution Plan element Resource efficiency activity Resource efficiency through BIM: A Guide for BIM Managers 15

16 6.0 Applying resource efficiency information to BIM objects Whilst many of the steps in a BIM delivery process will help improve resource efficiency, the greatest insights into performance and opportunities for improvement come from making use of data associated with the objects in the model to estimate the resource efficiency benefits and impacts of the design. There are two main ways of associating and using resource efficiency data: Internal data association Adding resource efficiency data directly to the objects used in the model and undertaking calculations within the BIM package. External data association Extracting quantity and specification information from the BIM model and combining this with resource efficiency data in external software packages to undertake calculations outside the BIM design package. 6.1 Internal data association This is most effectively done by adding resource efficiency data to objects in the BIM object library. Until recently, organisations have focussed on the creation of object libraries in an evolutionary way as projects are undertaken. These often have no standardised data structure and a bias towards basic property reporting rather than analysis and downstream management processes. If resource efficiency data is to be associated with the objects within the BIM package then a clearly structured library is required the BIM Manager needs to ensure that object data fields are defined to hold each resource efficiency parameter, reports/schedules are set up to enable data to be extracted, and possibly sub-routines/macros written to perform calculations. This approach can therefore be time intensive to set up, but once done it enables the BIM Users to very quickly and easily estimate the resource efficiency benefits and impacts of design decisions. For example, an embodied carbon analysis of the modelled design can be produced by the BIM package as easily as it produces a cost plan. This approach also ensures that all BIM Users work in a consistent and auditable way particularly important when producing results required to demonstrate contractual compliance and gives controlled future-proofing and updating of the systems. But it requires the data to be maintained within the source BIM library and increases the quantity of data held within the system. Resource efficiency through BIM: A Guide for BIM Managers 16

17 6.2 External data association This approach makes use of export functions and template schedules readily available in most BIM packages and therefore requires little, if any, additional setting up of the system by the BIM Manager. For example, it might involve exporting a schedule from the BIM model into a spreadsheet and then adding resource efficiency data to the schedule manually, or by matching objects within the BIM schedule to those held in a separate database using common referencing such as a Uniclass code. As there is reliance on external software and datasets they should of course be stated in the BIM Execution Plan. These external resources required will vary depending on the complexity of the exported model data and the types of analysis required. For simple scenarios spreadsheet calculations may be sufficient; otherwise, specialist software may be required 3. Many BIM Users should however be familiar with this approach as it is often used for assessing thermal performance, daylight, and acoustics for example. Several software developers are in the process of developing tools for taking BIM data and analysing resource efficiency aspects such as embodied carbon, but as yet these are not commercially available. When creating schedules of information for studying resource efficiency, it is important to export all of the necessary information. For example, to assess embodied carbon it will be necessary to have sufficient information about the material to be able to apply an embodied carbon emission factor (typically kg CO 2 or kgco 2 e per kg). This would require information on material type(s), quantity, and density of material per unit of quantity. However, where the object is relatively generic (e.g. an external wall or ground floor system) then it may only be necessary to know the area of the system as the benchmark information will also be area based. 6.3 Practical considerations Analysing performance outside the BIM package requires less ongoing maintenance than embedding resource efficiency data within the BIM objects. If studies are only being undertaken infrequently this approach could be more effective than having to maintain and update a further set of object parameters within the library. However, if analyses are being undertaken on a routine basis (e.g. on every project, perhaps several times) then it is worth considering adding resource efficiency information directly into the BIM object library. In practice, it is likely that a hybrid approach will be most suitable where resource efficiency data is added to some BIM objects, e.g. those that represent proprietary products or frequently used components, and third party data is used for other project elements / components, particularly where the data is likely to change over time. Whichever method is used, it is important that the base datasets and model information can be available to enable all of the analysis studies required. This again highlights the importance of ensuring the resource efficiency objectives are realistically set, are recorded in the BIM Execution Plan, and are coordinated with other BIM considerations such as software availability and user capability. Furthermore, for either approach to work successfully it is imperative that good modelling practices are applied. For example, there should be no gaps in geometry and projects should be 3 Examples of BIM compatible software for specialist analysis is given in the BIM Users Guide. Resource efficiency through BIM: A Guide for BIM Managers 17

18 built from appropriately classified objects/families. If the base model is of insufficient quality then subsequent analysis will be compromised. BS8541-1:2012 Library objects for architecture, engineering and construction identification and classification Code of practice provides guidance on suitable classification systems that can be applied and recommends that at least one of the UK specific systems 4 is used to define all of the objects in a model. The COBie data schema uses the Uniclass classification system and will be required for government projects (see Box 1). Box 1: The COBie data format COBie (Construction Operations Building information exchange) is a file format for holding information on a facility. Many BIM design tools can export a tabular representation of the construction project into a COBie excel spreadsheet. The data in this sheet can then be analysed directly or imported into other compatible tools. The COBie format is based on unique types, these entities may be components or groups of components (called systems). Components and/or systems are assigned to spaces (which may be grouped into zones) and floors within the facility. The COBie file will provide information on each type and then specify where different types are used within the facility. Information on the cost and environmental impacts of can be assigned at any level (from specific types or at the level of the whole facility). Impact information includes its: cost and environmental impacts (primary energy consumption, water consumption, climate change (t CO 2 e) and hazardous and non-hazardous wastes) 5 at different stages in its lifecycle (e.g. production, installation, maintenance, replacement, use and reuse); and the duration and repetition of these impacts. A COBie file structure therefore a suitable means of storing resource efficiency information within a BIM library and also provides a framework for exporting this information for use in estimation or other forms of analysis. Further information on COBie Data requirements Table 2 illustrates the key reference data required to estimate resource efficiency performance. This data can be held within the COBie 6 data structure using existing COBie parameters although new parameters would be required to report specifically on material mass and recycled and reused content. 4 I.e. Uniclass, BCIS Standard forms of Cost Analysis or the RICS New Rules of Measurement. 5 This initial list can be extended to include other impact areas such a recycled content. 6 Version 2 release 4. See Resource efficiency through BIM: A Guide for BIM Managers 18

19 Table 2 Reference data required to estimate the impact of resource use Resource aspect Data required Comments Relevant COBie parameter for reporting result (shown as impact stage: impact category ) Materials use volume / area / unit to mass conversions Waste wastage rates for each component element Likely to be included within many proprietary BIM objects. Generic reference data is available at an elemental level for many typical elements (see Appendix A). Generic reference data is available at an elemental level for many typical elements (see Appendix A). No COBie impact category in default set but Mass (kg) could be added, e.g. Installation: Mass Installation: HazardousWaste / NonHazardousWaste / InertWaste / RadioactiveWaste Reused and recycled content Embodied carbon in materials Energy and water use in construction recycled content benchmarks showing achievable recycled content levels embodied carbon (kg CO 2 e) per unit of resource use, e.g. Nr, m 2, m 3 or tonnes site energy and water use for high, medium and low intensity site work. source of energy and water, i.e. fuel, grid, electricity, etc. Generic reference data is available at an elemental level for many typical elements. More detailed information at a component level and / or for specific products can be sourced from published datasets 7 or manufacturers. Generic reference data is available at an elemental level for many typical elements. More detailed information at a component level and / or for specific products can be sourced from published datasets 8 or manufacturers. Generic benchmarks for energy and water use on site and for transportation of materials to site (kwh or litres per person per day). To estimate carbon emissions these benchmarks need to be combined with impact factors for the specific type of energy or water use. No COBie impact category in default set but Recycled Content (%) could be added, e.g. Installation: RecycledContent Production: ClimateChange Installation: NonRenewableEnergyConsumption Installation: RenewableEnergyConsumption Installation: ClimateChange Installation: WaterConsumption 7 See WRAP Recycled Products Guide 8 Such as the Inventory of Carbon and Energy, created by Bath University Resource efficiency through BIM: A Guide for BIM Managers 19

20 Therefore, where an organisation s BIM library includes COBie 2.4 based parameters it should be possible to embed resource efficiency information directly to the systems (e.g. elements), components and types used to build the model and then to export this data within the COBie format for analysis. Other resource efficiency dimensions such as embodied water, materials scarcity and use of hazardous substances are currently difficult to quantify using impact factors. A suitable approach for considering these issues would be to add risk flags (with comments) to objects where these issues are of particular significance, this would, as a minimum, act as a prompt to the BIM user to further understand the issue and manage it appropriately. 6.5 Adding data to BIM objects BIM objects can store a wide range of information about the properties of the object, its source, physical characteristics, parametric interactions with other objects, etc. As shown in Table 2, COBie impact parameters are the most suitable means of storing most resource efficiency information within a BIM object file. The base COBie parameters can be supplemented with data on various resource efficiency aspects such as recycled content. Objects held in many BIM libraries, such as the National BIM Library (from NBS 9 ) and BIMStore 10, contain COBie parameters by default, but it is unlikely that all the object parameters will be detailed and those relating to resource efficiency may be blank. If COBie parameters are absent from required object(s), the easiest way of adding these parameters is to apply a COBie template to the relevant object(s) which will add the necessary parameters to the file(s). COBie templates can be downloaded from various sources 11. Resource efficiency data can be gathered from a range of sources and at different levels of detail. For generic objects (e.g. in situ concrete or a brick wall) it should be possible to source the necessary resource efficiency information from publically available datasets, such as those from WRAP, albeit that the base data may need to be adapted to ensure the units are compatible with the units of quantification used within the modelling tool 12. Where an object represents a proprietary product then resource efficiency data should be sought from the manufacturer. Where resource efficiency data is being embedded within the BIM objects in a BIM library (at either a project or corporate level), it is important that a nominated member of staff has responsibility for ensuring that the data is maintained and kept current. 9 The National BIM Library is a free to use web-based resource of BIM objects and systems in standardised data format, based on recognised industry data classification systems (Uniclass) delivered in IFC platform neutral format as well as native file formats for the commonly used BIM software programmes including BIM managers that want to work extensively in generating, modifying and managing BIM objects should consider tools such as xbim ( or Ideate BIMlink ( 12 These calculations could be embedded within the modelling tool (e.g. taking volume and density to determine mass and then applying a mass based emission factor to determine embodied carbon). Resource efficiency through BIM: A Guide for BIM Managers 20

21 7.0 Managing project data to benchmark and improve performance To take full advantage of the opportunities for quantification presented by BIM tools it is important to store and manage project data so that it can be used to track progress and inform future projects. Benefits include: benchmarking project and element level performance to provide an indication of the likely performance of a project at an early design stage and also helping demonstrate improvements in performance over time; and tracking resource efficiency throughout the design and construction phases to ensure project targets are achieved and to understand how performance evolves between the concept and as built stages, thereby improving forecasting for future projects. 7.1 Benchmarking resource efficiency performance In line with the recommended approach to cost benchmarking for Government Construction 13 project benchmarks can be classified into: Type 1: Spatial measures e.g. per m, m 2, etc. Type 2: Functional measures e.g. per pupil, place, bedspace, etc. Type 3: Bespoke measures e.g. key ratios or other measures that illustrate the efficiency of the project. Type 4: Elemental quantity measures e.g. per m of foundation or per m 2 of window area, etc. Of these it is recommended that resource efficiency data be generated for Type 1, 2 and 4 benchmarks against priority metrics from those described in Section 2.3. If resource efficiency data is being stored within the COBie format then data exported into the Impacts section of a COBie workbook can be used to derive Type 1,2 or 4 benchmarks derived by filtering the impact data to show only the desired objects and impacts (e.g. embodied carbon in manufacture, or water use on site). To enable consistency within the benchmarks it would be sensible to adopt a common approach to classifying the various Spaces and Zones within the project and the level of elemental detail that will be used in Type 4 benchmarks. The level of detail in benchmarking might vary with project type but should be agreed corporately and with the relevant project teams to ensure data is presented in a useable format to meet internal and client requirements. 7.2 Tracking performance over time Five data drops are recommended at key stages of public projects (see Figure 1). These stages provide suitable points to consider resource efficiency performance and to assess whether the project is on track to meet its targets, or is performing favourably against sector benchmarks. 13 Government Construction: Cost Benchmarking Principles and Expectations, February Cabinet Office, Resource efficiency through BIM: A Guide for BIM Managers 21

22 As the project progresses, data on targeted (or actual) performance will become increasingly detailed, e.g. as data for generic elements or components is replaced with more specific information. The aim should be to continue to move towards the Good end of the spectrum by taking decisions that reduce resource use or its associated impacts. Also as the project progresses, and particularly when recording actual information from onsite activities, it may become apparent that the original benchmarks used in the study were not sufficiently accurate or were not wholly applicable to the project context. In these instances the benchmarks can be refined or, if appropriate, a new benchmark can be created for the specific application. 7.3 WRAP tools to help track project performance WRAP s forthcoming Resource Efficiency Reporting Portal will be able to store and report benchmark data on a wide range of projects. Users will be able to upload COBie workbooks directly in to the online resource and then track project performance as the project progresses. They will also be able to generate average performance benchmarks for different project types and track how the performance of their completed projects has changed over time. WRAP has published benchmarks for waste and recycled content and is developing ones covering a wider set of resource efficiency aspects Defining and communicating your approach Given BIM s emerging status in the UK construction industry and the wide variety of tools and options being developed, it is important that organisations clearly set out their systems and default approaches so that their BIM Users are clear about the tools and guidance available and what is expected of them. This is an important role of the BIM Manager. The BIM Execution Plan template is a key resource because it describes the approach to using BIM processes and tools in project delivery. However, supplementing the template with a clear Practice Note will ensure project teams understand the available tools, data and resources and use them correctly and consistently. The content of a Practice Note, or equivalent, will vary according to the approach taken but could include the following: Position statement covering: o resource efficiency objectives or link to resource efficiency policy; and o role of BIM in delivering these objectives and the default approaches to be applied to projects. Approach to incorporating resource efficiency within BIM processes. This would include reference to the BIM Execution Plan and other relevant method statements. Resource efficiency data held within BIM libraries and how this is used. Process for reporting and reviewing performance at key project stages. In many instances a project team will need to adapt the organisation s standard approach to fit with other members of the project team or client requirements; however this will be easier if a clear default position is established. Resource efficiency through BIM: A Guide for BIM Managers 22

23 Appendix A: Example of BIM Execution Plan incorporating resource efficiency elements Resource efficiency through BIM: A Guide for BIM Managers 23

24 BIM Project Execution Plan Template Document details Project name Project code Client Document date Prepared by Version control Author Checked by Workstage Revision number Revision date Purpose Resource efficiency through BIM: A Guide for BIM Managers 24

25 Contents 1.0 Executive summary 2.0 Introduction 3.0 Project Information 4.0 Key Project Contacts 5.0 Project Goals, BIM Uses and Capabilities 6.0 Roles and Responsibilities 7.0 BIM Process Design 8.0 Model Element LOD and Responsibility Worksheet 9.0 Facility and Asset Management Requirements 10.0 Collaboration Procedures 11.0 Quality Control 12.0 Technological Infrastructure Needs 13.0 Model Standards and Guidelines 14.0 Delivery Strategy Agreement 15.0 Appendices Resource efficiency through BIM: A Guide for BIM Managers 25

26 1.0 Executive summary Add text summarising purpose of BEP, methodology for its creation and structure and ongoing development Resource efficiency through BIM: A Guide for BIM Managers 26

27 2.0 Introduction 2.1 Overview Building Information Modelling (BIM) is an integrated digital process providing coordinated, reliable information about a project throughout all phases, from design through construction and into operation. BIM represents a major change to the tools and processes used to design, construct and manage buildings and infrastructure. The use of BIM is increasing and is likely to accelerate in the near future following the UK Government s announcement to mandate its use on public sector projects valued at 5 million or more. Drivers for implementation include improved quality of information, lifecycle programme efficiency, enhanced operational workflows and achievement of sustainability objectives. BIM provides a multitude of benefits, derived from the use of accurate and consistent datasets, graphically representing design and construction information. Ultimately improving communication and engagement between stakeholders and eliminating errors to support better informed decision making through design development, construction and handover. Data is created, managed and coordinated by teams through collaborative working and integration of operational processes. Intelligent virtual technologies are deployed thorough the lifecycle to support the efficient creation, exchange and re-use of data, without loss or misinterpretation. Building owners can realise cost efficiency through streamlining design, construction and operations processes. Examples of BIM deployment to achieve this benefit include use of technologies enabling automated quantity takeoff, building performance analysis, Design for Manufacture and Design for Assembly, systematic clash detection and construction sequencing in the virtual environment. In addition owners are able to seamlessly integrate building information with life cycle costing tools, to monitor and reduce whole life and operating costs. Facilities Management is also optimised through the deployment of the Resource efficiency through BIM: A Guide for BIM Managers 27

28 CoBIE data format, which enables direct linking with intelligent 3D BIM models and design information. The use of 3D visualisation improves communication, engagement and understanding of space, supporting strategy development and carbon footprint reduction. Design consultants are able to concurrently consider multiple design options and design coordination is more effective and accurate through the use of a single multi-disciplinary model. The stated capabilities enable enhanced control/dissemination of data throughout the project. In addition constructors are able to rapidly establish construction sequences by working with subcontractors to identify health and safety risks earlier on, optimise resource efficiency and conduct what if scenario planning to streamline build sequences in line with time, cost and resource requirements. 2.2 BIM execution planning Add text summarising BEP process 2.3 BIM mission statement Add text explaining client vision for BIM implementation and outcomes for the project Resource efficiency through BIM: A Guide for BIM Managers 28

29 3.0 Project information 3.1 Project owner Add text 3.2 Project name Add text 3.3 Project location and address Add text 3.4 Contract type / delivery method Add text 3.5 Brief project description Scheme Type eg residential Add text 3.6 Project schedule / phases / milestones (Example) Project Phase / Milestone Proposed Start Date Proposed Completion Date Consultant Appointments Stage B Stage C Stage D Planning Application Submission Committee Conditional Approval Planning to Site Start Construction Start on-site Resource efficiency through BIM: A Guide for BIM Managers 29

30 4.0 Key project contacts 4.1 Contacts for each organisation on the project. For role definitions refer to section 5. (Example) Role Organisation Contact Name Phone Client and Project Manager Design Team BIM Leader(s) BIM Manager(s) BIM Modellers / Technicians Resource efficiency through BIM: A Guide for BIM Managers 30

31 5.0 Project goals, BIM uses and capabilities 5.1 BIM specific This section defines how BIM will be used to maximise project value (e.g. design alternatives, cost estimating, pre-fabrication opportunities, construction planning, etc). In addition, project team capabilities have been assessed (refer to Appendix 5 for interview response form template) in reference to each BIM use and will be updated according to progress made in corresponding project stages. BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Design Authoring Description E.g. High Development of information rich 3D model(s) using parametric tools with powerful automated functionalities ie quantity takeoff and schedules. Team Member Capability Level Goal(s) Support reliable decision making Better quality of design Improve understanding of design intent Inform resource efficiency through improved optimisation of materials and components Resource efficiency through BIM: A Guide for BIM Managers 31

32 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Spatial Validation Description Assess design performance in regards to spatial requirements ie analyse space and understand complexity of space standards and regulations. Goal(s) Area scheduling, tracking and validation Identify deviations from space requirements Improve speed and accuracy of cost analysis Team Member Capability Level Library of Assemblies / Systems / Components Description Comprehensive library of generic objects embedded with intelligent parametric relationships and a rich dataset eg material, supplier and specification information. Team Member Capability Level Goal(s) Time saving through optimisation and standardisation Improve integration between design and manufacturing Inform resource efficiency through improved optimisation of materials and components Enable estimation of resource efficiency performance through relevant data applied to the model objects Resource efficiency through BIM: A Guide for BIM Managers 32

33 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Building Environmental Analysis Description Measure building performance using analysis tools ie solar analysis, wind analysis and energy usage. Ensure the building is operating to specified design and sustainable standard. Team Member Capability Level Goal(s) Analyse and optimise building environmental performance Inform resource efficiency by optimising energy and water usage Reduce carbon emissions Engineering Analysis Description Determine effective engineering methods based on design specifications eg structural analysis. Additional examples include CFD analysis and planning of emergency evacuation using pedestrian flow modelling. Team Member Capability Level Goal(s) Analyse, test and optimise performance of design elements Support more reliable decision making Optimise structural elements to minimise materials use and overall building mass Resource efficiency through BIM: A Guide for BIM Managers 33

34 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) 3D Coordination Description Use of clash detection software during the coordination process to determine field conflicts by comparing 3D models of building systems. Goal(s) Elimination of site conflicts Reduce RFI s Increase site productivity Improve resource efficiency by reducing material waste Team Member Capability Level Design Reviews Description Use of 3D models to showcase and review the design in the virtual environment. Goal(s) Informed decision making Improve understanding of design intent and explore options for improving resource efficiency Enhanced communication Reduce RFI s Team Member Capability Level Resource efficiency through BIM: A Guide for BIM Managers 34

35 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Digital Fabrication Description Considering opportunities for future fabrication, i.e. communicating information in a format that enables prefabrication of objects directly from a 3D model. Goal(s) Improve integration between design and manufacturing Improve speed and accuracy of fabrication Improve resource efficiency by optimising use of materials and reducing construction waste on site Team Member Capability Level Rapid Prototyping Description Integration of 3D models with Rapid Prototyping processes to create and test physical models under controlled conditions eg wind tunnel testing. Goal(s) Analyse, test and optimise building performance Support reliable decision making Improve resource efficiency by minimising resource use and waste arising from trials and rework on site Team Member Capability Level Resource efficiency through BIM: A Guide for BIM Managers 35

36 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Visualisation Description Use of visualisation technologies to develop high quality renders and animations. Team Member Capability Level Goal(s) Support marketing initiatives Improve resource efficiency by ensuring usability and client acceptance in a virtual space, so minimising resource use and waste arising from late stage changes and rework on site Phase Planning (4D Modelling) Description Linking 3D model elements with a construction programme enabling real time visualisation of build sequence. Team Member Capability Level Goal(s) Improve materials logistics to reduce wastage from damage in site storage Coordination of trades to reduce rework and damage of installations Increase site productivity and minimise material, water and energy consumption Support health and safety planning Resource efficiency through BIM: A Guide for BIM Managers 36

37 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Support more reliable decision making Identify and reduce risk Cost Estimation (5D Modelling) Description Generate accurate quantity take-offs and cost estimates. Providing what if analysis capabilities to assess modifications to design or programme. Goals Improve speed and accuracy of cost analysis Team Member Capability Level Resource efficiency through BIM: A Guide for BIM Managers 37

38 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Space Management and Tracking Description Effectively allocate, manage and track assigned workspaces and related resources. Goals Informed decision making Deliver accurate record information Team Member Capability Level Asset Management Description 3D model based system that will efficiently aid in the maintenance and operation of a facility and its assets. QED will be provided with structured information (user manuals, equipment schedules etc) aligned with the CoBIE format. Goal(s) Informed decision making Deliver accurate record information Support resource efficient RMI Optimise building performance in operation to minimise energy and water use Team Member Capability Level Resource efficiency through BIM: A Guide for BIM Managers 38

39 BIM use (images are indicative) BIM goal(s) Priority (High / Med / Low) Resource efficiency Description Analysis of materials use, onsite energy and water consumption and waste arisings. Analysis based around the quantity and type of materials included in the design and associated construction activities. Resource efficiency should include consideration of materials quantity, materials wastage, recycled content, embodied carbon, water use, embodied water, life span (e.g. durability), end of life potential (e.g. reuse; recyclability), resource scarcity & security Outputs will be exported in CoBIE format. Goal(s) Minimise resource use (carbon, energy, materials, and water) and associated impacts (climate change, resource depletion and water scarcity) Team Member Capability Level Resource efficiency through BIM: A Guide for BIM Managers 39

40 5.2 Project objectives The project has the following stated objectives and targets: Insert project objectives and targets to which use of BIM can have a direct role or influence in delivery. Resource efficiency Embodied carbon (tco 2 e per m 2 ) = Water use on site (m 3 per m 2 ) = Energy use on site (kwh per m 2 ) = Recycled content (% by value) = Etc. Resource efficiency through BIM: A Guide for BIM Managers 40

41 6.0 Roles and responsibilities 6.1 General project responsibilities (Example) Role Client and Project Manager Design Team BIM Leader BIM Manager(s) BIM Modellers / Technicians Responsibilities High level responsibility for the overall project and associated workstreams. Supporting the creation of clear and attainable project objectives, building the project requirements, and managing cost, time, and quality through various stages, in line with client requirements. Delivery of discipline specific output required to support the successful completion of the overall project. Providing strategic direction and support to clients, project managers, discipline leaders, BIM managers, technicians and BIM modellers. Key focus is supporting the development and implementation of the BEP and associated workstreams according to client requirements. Company specific BIM champions leading implementation of BIM uses. Individuals are required to attend BIM workgroup meetings and provide input to support development of BEP. Implementation of BIM workstreams e.g. clash detection, design reviews, 4D/5D modelling 6.2 BIM responsibilities Add text describing BIM project specific responsibilities 6.2.x Resource efficiency analysis and reporting to be led by xxx with support from xxx and xxx. Resource efficiency through BIM: A Guide for BIM Managers 41

42 7.0 BIM process design 7.1 Level One process map The Level One process map provides: a detailed plan for execution of each BIM use aligned with project stages; identification of responsible stakeholders for each use; and corresponding information output. This process map is detailed in Appendix 1 Example Resource efficiency through BIM: A Guide for BIM Managers 42

43 7.2 Level Two process map The Level Two process map is detailed in Appendix 2. Following discussion with the project team there is no current requirement for process maps for each BIM use. Opportunity for development in Stage C will be agreed collectively with the project team. Example Resource efficiency through BIM: A Guide for BIM Managers 43

44 8.0 Model element Level of Development (LOD) and responsibility worksheet 8.1 Model elements by discipline, Level of Detail (LOD), and any specific attributes important to the project are to be documented using the LOD and Responsibility worksheet (refer to Appendix 3). This needs to be reviewed in conjunction with appointment terms. 8.2 LOD refers to the five basic levels of development created by the American Institute of Architects (AIA), which do not reflect specific modelling guidelines for any particular software, rather a generic definition of model content. Full explanation of levels is provided in AIA E202 ( and is summarised below. Example Resource efficiency through BIM: A Guide for BIM Managers 44

45 LOD summary LOD Essentially the equivalent of conceptual design, the model would consist of overall building massing and the downstream users are authorized to perform whole building types of analysis (volume, building orientation, cost per square foot, etc.) LOD Similar to schematic design or design development, the model would consist of "generalized systems or assemblies with approximate quantities, size, shape, location and orientation." Authorized uses would include "analysis of selected systems by application of generalized performance criteria." LOD Model elements are suitable for the generation of traditional construction documents and shop drawings. As such, analysis and simulation is authorized for detailed elements and systems. LOD This level of development is considered to be suitable for fabrication and assembly. The MEA for this LOD is most likely to be the trade contractor or fabricator as it is usually outside the scope of the architect's or engineer's services or would constitute severe risk exposure if such parties are not adequately insured. LOD The final level of development represents the project as it has been constructed - the as-built conditions. The model is suitable for maintenance and operations of the facility. (LOD summary courtesy of Resource efficiency through BIM: A Guide for BIM Managers 45

46 9.0 Facility and asset management requirements 9.1 Add text describing the Client s requirements for the use of BIM models and associated data for future asset management. 9.2 Resource consumption and associated impacts are to be reported using the COBie file format. Example below includes embodied (embedded) carbon in sanitary ware. Resource efficiency through BIM: A Guide for BIM Managers 46

Procurement requirements for reducing waste and using resources efficiently

Procurement requirements for reducing waste and using resources efficiently Guidance for building and civil engineering projects Procurement requirements for reducing waste and using resources efficiently Model procurement wording for clients and contractors to cut waste on construction

More information

Manchester United Old Trafford Stadium

Manchester United Old Trafford Stadium WRAP Resource Management Plan Online Tool for Events Manchester United Old Trafford Stadium The WRAP Resource Management Plan (RMP) for events is a free online tool which can be used by event organisers

More information

Asset Management Strategy (2013-2017) Doing things Differently A New Approach for a sustainable future

Asset Management Strategy (2013-2017) Doing things Differently A New Approach for a sustainable future Asset Management Strategy (2013-2017) A New Approach for a sustainable future Contents Introduction... 2 The Asset Management Vision, Policy Statement & Strategic Themes... 5 Part B The Asset Management

More information

Strategic approach to the selection and procurement of construction materials and products

Strategic approach to the selection and procurement of construction materials and products www.breeam.com Briefing Paper Strategic approach to the selection and procurement of construction materials and products Alan Yates 02 The selection and procurement of construction materials makes a major

More information

Designing out Waste: a design team guide for buildings

Designing out Waste: a design team guide for buildings Uniclass A42: N462 CI/SfB (Ajp) (T6) Designing out Waste: a design team guide for buildings Less Waste, sharper design Halving Waste to Landfill Clients are making construction waste reduction a priority

More information

Material bulk densities

Material bulk densities Summary Report densities This document provides bulk data for commonly collected material streams, taking into account container types and how the materials are collected (vehicle types). It provides data

More information

Government Communication Professional Competency Framework

Government Communication Professional Competency Framework Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their

More information

The Designing out Waste Tool for Civil Engineering Projects

The Designing out Waste Tool for Civil Engineering Projects Reference guide August 2010 The Designing out Waste Tool for Civil Engineering Projects Guide to Reference Data, Version 1.0 WRAP s vision is a world without waste, where resources are used sustainably.

More information

Social Return on Investment

Social Return on Investment Social Return on Investment Case study - London Borough September 2014 Overview The Social Value Act is transforming public sector procurement. Business needs to embrace this opportunity and use it to

More information

BIM Strategy for NHSScotland

BIM Strategy for NHSScotland BIM Strategy for NHSScotland Professor Bimal Kumar and Graham Hayne GCU BIM Partnership School of Engineering and Built Environment Glasgow Caledonian University Agenda Introduction to BIM GCU BIM Partnership

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

FAM100-001: Review of current procurement. practice in the Facilities Management sector

FAM100-001: Review of current procurement. practice in the Facilities Management sector Executive Summary FAM100-001: Review of current procurement practice in the Facilities Management sector This report describes the procurement processes currently followed within the Facility Management

More information

EU Life+ Project: Combining Water and Energy Efficiency. A report by the Energy Saving Trust and Waterwise UK.

EU Life+ Project: Combining Water and Energy Efficiency. A report by the Energy Saving Trust and Waterwise UK. : Combining Water and Energy Efficiency A report by the Energy Saving Trust and Waterwise UK. Combining Water and Energy Effi ciency Water in the home External to household Overview The EU Life+ RENEW

More information

Recycling of Mineral Wool Composite Panels Into New Raw Materials

Recycling of Mineral Wool Composite Panels Into New Raw Materials Case Study: Mineral Wool/Steel Composite Panel Recycling Recycling of Mineral Wool Composite Panels Into New Raw Materials Eurobond have developed a method for recycling mineral wool composite panels.

More information

Resource review: UK Drinks sector. Reducing fill losses

Resource review: UK Drinks sector. Reducing fill losses Resource review: UK Drinks sector Reducing fill losses Ideally, every unit of production in the drinks sector would be filled exactly to the nominal volume. This review outlines ways of improving drinks

More information

Sustainable Development Strategy

Sustainable Development Strategy Sustainable Development Strategy Our vision and strategy: A railway fit for the future 2013 2024 Document Ref: SBPT204 Version 0.71 Executive summary Network Rail exists to generate outstanding value for

More information

BUILDING INFORMATION MODEL (BIM) PROTOCOL

BUILDING INFORMATION MODEL (BIM) PROTOCOL BUILDING INFORMATION MODEL (BIM) PROTOCOL 2013 Standard Protocol for use in projects using Building Information Models The CIC acknowledges the technical input and leadership provided by the BIM Task Group

More information

WHITE PAPER. From Building Information Management to Facilities Management

WHITE PAPER. From Building Information Management to Facilities Management October 2011 WHITE PAPER. Management to Facilities Management A look at the benefits to be found by fostering the links between Building Information Modelling (used by the construction industry) and Computer

More information

Employer s Information Requirements Version 07 28.02.13. Core Content and Guidance Notes

Employer s Information Requirements Version 07 28.02.13. Core Content and Guidance Notes Employer s Information Requirements Version 07 28.02.13 Core Content and Guidance Notes Employer s Information Requirements - Guidance notes version 07: 28.02.13 Contents 1.0 Employer s Information Requirements

More information

The Levy Control Framework

The Levy Control Framework Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn

More information

University of Brighton Sustainable Procurement Strategy 2011-2015

University of Brighton Sustainable Procurement Strategy 2011-2015 University of Brighton Sustainable Procurement Strategy 2011-2015 Sustainable procurement in a challenging environment Introduction There is widespread recognition that climate change and the use of dwindling

More information

Implementing a Security Management System: An Outline

Implementing a Security Management System: An Outline Implementing a Security Management System: An Outline CAP 1273 Civil Aviation Authority 2015 All rights reserved. Copies of this publication may be reproduced for personal use, or for use within a company

More information

DRAFT V5. PFSC 16/05/2014 Appendix 1. Outline Plan to deliver the County Council s investment property Strategy

DRAFT V5. PFSC 16/05/2014 Appendix 1. Outline Plan to deliver the County Council s investment property Strategy PFSC 16/05/2014 Appendix 1 Outline Plan to deliver the County Council s investment property Strategy 1. Strategic Drivers 1.1 The County Council s property investment strategy sets out how its property

More information

Choosing the right recycling collection system

Choosing the right recycling collection system Choosing the right recycling collection system WRAP s role in relation to the design of recycling systems is to help practitioners by gathering and sharing knowledge and understanding about the relevant

More information

Queen s University Belfast Carbon Management Programme. Carbon Management Plan (CMP 2013)

Queen s University Belfast Carbon Management Programme. Carbon Management Plan (CMP 2013) Queen s University Belfast Carbon Management Programme Carbon Management Plan (CMP 2013) 5 June 2013 1 Contents Management Summary 1. Introduction 7 2. Carbon Management Strategy 2.1 Context and Drivers

More information

Sustainable procurement of mobile phone service contract

Sustainable procurement of mobile phone service contract Sustainable procurement of mobile phone service contract Summary Key Facts WRAP delivered a programme of providing technical procurement support to public sector organisations on behalf of Defra during

More information

Asset Management Policy March 2014

Asset Management Policy March 2014 Asset Management Policy March 2014 In February 2011, we published our current Asset Management Policy. This is the first update incorporating further developments in our thinking on capacity planning and

More information

Responsibility Deal between Government and the waste and resource management sector. June 2011

Responsibility Deal between Government and the waste and resource management sector. June 2011 www.defra.gov.uk www.esauk.org Responsibility Deal between Government and the waste and resource management sector June 2011 Department for Environment, Food and Rural Affairs Nobel House 17 Smith Square

More information

Presentation Overview. Site Waste Management Plans: A missed opportunity?

Presentation Overview. Site Waste Management Plans: A missed opportunity? Site Waste Management Plans: A missed opportunity? Presenter: Derek Duckett (CEnv, MIEMA) Project Manager Company: Mabbett & Associates (EH&S Consultants & Engineers) duckett@mabbett.com Presentation Overview

More information

Queensland recordkeeping metadata standard and guideline

Queensland recordkeeping metadata standard and guideline Queensland recordkeeping metadata standard and guideline June 2012 Version 1.1 Queensland State Archives Department of Science, Information Technology, Innovation and the Arts Document details Security

More information

Business Continuity Management

Business Continuity Management Business Continuity Management Policy Statement & Strategy July 2009 Basildon District Council Business Continuity Management Policy Statement The Council is committed to ensuring robust and effective

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

Information Governance Management Framework

Information Governance Management Framework Information Governance Management Framework Responsible Officer Author Business Planning & Resources Director Governance Manager Date effective from October 2015 Date last amended October 2015 Review date

More information

Corporate Risk Management Policy

Corporate Risk Management Policy Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

Guidance on Mobile Asset Management Planning Tool: Cleaning Equipment

Guidance on Mobile Asset Management Planning Tool: Cleaning Equipment Guidance on Mobile Asset Management Planning Tool: Cleaning Equipment Project code: RBM500-002 Date: October 2014 WRAP's vision: Our vision is a world in which resources are used sustainably. WRAP's mission:

More information

Reducing waste through efficient procurement can help reduce the costs of civil engineering and infrastructure projects; this guidance provides

Reducing waste through efficient procurement can help reduce the costs of civil engineering and infrastructure projects; this guidance provides Implementation guidance for civil engineering and infrastructure projects Civil engineering projects: Waste less and save money Reducing waste through efficient procurement can help reduce the costs of

More information

Housing Association Regulatory Assessment

Housing Association Regulatory Assessment Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing

More information

in collaboration with: Maximising Where are my assets? Adding the Spatial Dimension

in collaboration with: Maximising Where are my assets? Adding the Spatial Dimension in collaboration with: Maximising ROI on your Assets Where are my assets? Adding the Spatial Dimension Maximising Your RoI The ability to share accurate and up-to-date information has become the defining

More information

Procurement Strategy 2013-2017 Delivering Social Value for our Community

Procurement Strategy 2013-2017 Delivering Social Value for our Community Procurement Strategy 2013-2017 Delivering Social Value for our Community Making Bath & North East Somerset an even better place to live, work and visit 1 Picture courtesy of Bath & News Media Group Our

More information

London Underground Environment Strategy

London Underground Environment Strategy London Underground Environment Strategy 2008 2013 mayor of london Transport for London Contents Introduction 3 London Underground Environment strategy 4 Managing environmental impacts 5 Embedding environment

More information

Construction & Demolition Waste Management in Green Star Discussion Paper

Construction & Demolition Waste Management in Green Star Discussion Paper Construction & Demolition Waste Management in Green Star Discussion Paper 1 Construction & Demolition Waste Management in Green Star - Discussion Paper Construction & Demolition Waste Management in Green

More information

The South Staffordshire and Shropshire Health Care NHS Foundation Trust Digital Strategy 2014 2019

The South Staffordshire and Shropshire Health Care NHS Foundation Trust Digital Strategy 2014 2019 The South Staffordshire and Shropshire Health Care NHS Foundation Trust Digital Strategy 2014 2019 Peter Kendal Associate Director for Information Management and Technology Development 01/12/2014 1 Page

More information

SC21 Manufacturing Excellence. Process Overview

SC21 Manufacturing Excellence. Process Overview SC21 Manufacturing Excellence Process Overview Prepared by:- The SC21 Performance, Development and Quality (PDQ) Special Interest Group (SIG) Acknowledgement The scoring methodology used in the Management

More information

Achieve. Performance objectives

Achieve. Performance objectives Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.

More information

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust

BREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust BREEAM Refurbishment and Fit-out 2014 Briefings Part of the BRE Trust BREEAM for Refurbishment and Fit-out Follows 2 years of development Draft scheme published and consultation from 19 th July 2014 Launched

More information

whole life costing (+ CO2) user guide

whole life costing (+ CO2) user guide 2009 Forum for the Future - the not-for-profit sustainable development organisation - works in partnership with more than 120 leading businesses and public sector bodies, helping them devise more sustainable

More information

Project Management Manual

Project Management Manual Project Management Manual PM01 Introduction to the Project Management Manual Ref: PM01 (V7.01) - Uncontrolled once Printed Issued on 20 th December 2006 Manual Owner: James Couper Head of Project Management

More information

CEN/BT/WG 215 N 045 4 th draft BUSINESS PLAN

CEN/BT/WG 215 N 045 4 th draft BUSINESS PLAN CEN/BT/WG 215 N 045 4 th draft BUSINESS PLAN CEN/TC XXX Building Information Modelling (BIM) CEN/TC XXX Business Plan Date:2014-09-16 Version: Draft #7 Page: 1 EXECUTIVE SUMMARY Business Environment [to

More information

How To Host An Incompany Project For An Msc Student At Cranfield

How To Host An Incompany Project For An Msc Student At Cranfield The Cranfield Project an opportunity for your business Applying learning to real business issues At Cranfield School of Management we believe that Logistics and Supply Chain excellence is both a desirable

More information

Digital Inclusion Programme Started. BL2a

Digital Inclusion Programme Started. BL2a PROJECT BRIEF Project Name Digital Inclusion Programme Status: Started Release 18.05.2011 Reference Number: BL2a Purpose This document provides a firm foundation for a project and defines all major aspects

More information

Procurement and Contract Management Strategy 2013-2017

Procurement and Contract Management Strategy 2013-2017 Procurement and Contract Management Strategy 2013-2017 Title Owner Version 1 Distribution Procurement and Contract Management Strategy 2013 2017 Procurement and Performance Manager Corporate Issue date

More information

The Role of the BIM Coordinator

The Role of the BIM Coordinator The Role of the BIM Coordinator The objectives of this webinar are to: Introduce and define the role of Information Manager Introduce and define the emerging role and responsibilities of the BIM Coordinator.

More information

Sustainable Supply Chain Policy

Sustainable Supply Chain Policy Sustainable Supply Chain Policy 1. Contents Page 2. Introduction & Purpose 1 3. Definitions 1 4. Benefits of a Sustainable approach to the Supply Chain 2 5. Operational Context 2 6. Elements & Principles

More information

Corporate Carbon Neutral Plan

Corporate Carbon Neutral Plan This Carbon Neutral Plan will guide the District of 100 Mile House decision making process in terms of reducing corporate energy consumption and greenhouse gas emissions and in achieving carbon neutrality.

More information

Overview of Future Purchasing s fundamental and advanced training workshops...

Overview of Future Purchasing s fundamental and advanced training workshops... Performance Learning Presented by: Anna Del Mar - Director, Performance Learning Future Purchasing Overview of Future Purchasing s fundamental and advanced training workshops... Tailored excellence.. Our

More information

ILM Level 3 Certificate in Using Active Operations Management in the Workplace (QCF)

ILM Level 3 Certificate in Using Active Operations Management in the Workplace (QCF) PAGE 1 ILM Level 3 Certificate in Using Active Operations Management in the Workplace (QCF) CONTENTS Qualification Overview: ILM Level 5 Award, Certificate and Diploma in Management APPENDICES Appendix

More information

Relationship Manager (Banking) Assessment Plan

Relationship Manager (Banking) Assessment Plan Relationship Manager (Banking) Assessment Plan ST0184/AP03 1. Introduction and Overview The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It

More information

Construction Resources and Waste Roadmap

Construction Resources and Waste Roadmap A short guide to the Construction Resources and Waste Roadmap A roadmap is a tool that helps us visualise... ... how to get from A In England, construction, demolition and refurbishment activities produce

More information

DATA QUALITY STRATEGY

DATA QUALITY STRATEGY DATA QUALITY STRATEGY June 2008 G:\Performance Management\data quality\data Quality Strategy08.doc 1 CONTENTS CONTENTS 2 1. INTRODUCTION 3 2. BACKGROUND INFORMATION 3 3. THE PRINCIPLES OF DATA QUALITY

More information

SUSTAINABLE DEVELOPMENT REPORTING CASE STUDY

SUSTAINABLE DEVELOPMENT REPORTING CASE STUDY SUSTAINABLE DEVELOPMENT REPORTING CASE STUDY THE WAREHOUSE GROUP Introduction The Warehouse Group, established in 1982, currently comprises three trading operations - 77 Warehouse Stores, selling general

More information

EXAM EXEMPLAR QUESTIONS

EXAM EXEMPLAR QUESTIONS Level 4 Diploma in Procurement and Supply D2 - Business needs in procurement and supply EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 7 QUALIFICATIONS 2013 QUESTIONS AND MARKING

More information

Outline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups

Outline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups Item 13 Strategic Estates Planning Outline Brief for Development of Strategic Estates Plan for Bristol, South Gloucester, North Somerset and Somerset Clinical Commissioning Groups Phase 1: Priorities and

More information

EMBEDDING BCM IN THE ORGANIZATION S CULTURE

EMBEDDING BCM IN THE ORGANIZATION S CULTURE EMBEDDING BCM IN THE ORGANIZATION S CULTURE Page 6 AUTHOR: Andy Mason, BSc, MBCS, CITP, MBCI, Head of Business Continuity, PricewaterhouseCoopers LLP ABSTRACT: The concept of embedding business continuity

More information

RIBA Plan of Work 2013 Overview

RIBA Plan of Work 2013 Overview RIBA Plan of Work 2013 Overview Foreword First developed in 1963, for half a century the RIBA Plan of Work has been the definitive UK model for the building design and construction process, also exercising

More information

CCG: IG06: Records Management Policy and Strategy

CCG: IG06: Records Management Policy and Strategy Corporate CCG: IG06: Records Management Policy and Strategy Version Number Date Issued Review Date V3 08/01/2016 01/01/2018 Prepared By: Consultation Process: Senior Governance Manager, NECS CCG Head of

More information

Role Description Vendor Relationship Manager ICT

Role Description Vendor Relationship Manager ICT Role Description Vendor Relationship Manager ICT Classification/Grade/Band Clerk Grade 9/10 ANZSCO Code PCAT Code Date of Approval Primary purpose of the role The Vendor Relationship Manager ICT is responsible

More information

Architecture Design Engineering Urbanism Sustainability Lighting Acoustics. Strategic Consultancy by BDP

Architecture Design Engineering Urbanism Sustainability Lighting Acoustics. Strategic Consultancy by BDP Architecture Design Engineering Urbanism Sustainability Lighting Acoustics Strategic Consultancy by BDP About BDP BDP is a major international, interdisciplinary practice of architects, designers, engineers

More information

Steel procurement in major projects: Guidance on the application of social issues. Purpose

Steel procurement in major projects: Guidance on the application of social issues. Purpose Steel procurement in major projects: Guidance on the application of social issues Purpose 1. This is a practical guide on how to incorporate social issues in major projects with a significant steel component.

More information

Slough Borough Council. Highway Asset Management Strategy

Slough Borough Council. Highway Asset Management Strategy Slough Borough Council Highway Asset Management Strategy OUR AMBITION USING RESOURCES WISELY By 2019 the Council s income and the value of its assets will be maximised 1 Key Priorities 1.1 We understand

More information

NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES

NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES NATIONAL E-PROCUREMENT PROJECT GUIDANCE NOTES PROCUREMENT SPEND ANALYSIS Title: Procurement Analysis Identification: Supports organisations in gathering and analysing procurement spend to highlight system

More information

CGAM022.1/12/10. Asset Management Improvement Strategy 2010

CGAM022.1/12/10. Asset Management Improvement Strategy 2010 Asset Management Improvement Strategy 2010 Version Control Version No. Date Details Author/s 1.0 July 2009 Adopted Strategy 2.0 October 2010 Update TABLE OF CONTENTS OF CONTENTS 4 OF THE ASSET MANAGEMENT

More information

Delivering Excellence in Insurance Claims Handling

Delivering Excellence in Insurance Claims Handling Delivering Excellence in Insurance Claims Handling Guide to Best Practice Delivering Excellence in Insurance Claims Handling Contents Page 1. Introduction 1 2. Executive Summary 2 3. Components of Best

More information

Solvency II Own Risk and Solvency Assessment (ORSA)

Solvency II Own Risk and Solvency Assessment (ORSA) Solvency II Own Risk and Solvency Assessment (ORSA) Guidance notes September 2011 Contents Introduction Purpose of this Document 3 Lloyd s ORSA framework 3 Guidance for Syndicate ORSAs Overview 7 December

More information

HUGO BOSS ENVIRONMENTAL COMMITMENT. Our claim. Our approach

HUGO BOSS ENVIRONMENTAL COMMITMENT. Our claim. Our approach HUGO BOSS ENVIRONMENTAL COMMITMENT HUGO BOSS assumes responsibility for future generations. This entails that we also pursue our high standards for quality and performance in environmental protection.

More information

THE BRITISH LIBRARY. Unlocking The Value. The British Library s Collection Metadata Strategy 2015-2018. Page 1 of 8

THE BRITISH LIBRARY. Unlocking The Value. The British Library s Collection Metadata Strategy 2015-2018. Page 1 of 8 THE BRITISH LIBRARY Unlocking The Value The British Library s Collection Metadata Strategy 2015-2018 Page 1 of 8 Summary Our vision is that by 2020 the Library s collection metadata assets will be comprehensive,

More information

Back to Basics. Managing the Audit Department: Resource Management

Back to Basics. Managing the Audit Department: Resource Management Back to Basics Managing the Audit Department: Resource Management In her article in the last newsletter, Bev Cole provided an overview and roadmap for managing the audit department and also provided more

More information

The role of integrated requirements management in software delivery.

The role of integrated requirements management in software delivery. Software development White paper October 2007 The role of integrated requirements Jim Heumann, requirements evangelist, IBM Rational 2 Contents 2 Introduction 2 What is integrated requirements management?

More information

Data Quality Management A Risk-Based Approach to Targeting Performance

Data Quality Management A Risk-Based Approach to Targeting Performance Data Quality Management A Risk-Based Approach to Targeting Performance On target data strategy The currency of today s e-economy is data. Information about customers, products, sales, business partners,

More information

Attached is the 2015-16 business plan for Transport Services for consideration by OPCC. (Please see attached)

Attached is the 2015-16 business plan for Transport Services for consideration by OPCC. (Please see attached) Financial Performance Programme 2014-15 Report to: the Office of the Police and Crime Commissioner for Essex Report from: Essex Police Meeting Date: 21 st May 2015 Topic: Transport Services 15-16 Business

More information

How to Become a Data Driven Business

How to Become a Data Driven Business January 2012 Executive summary Becoming a Data Driven Business, particularly from a Marketing perspective, presents significant benefits in helping your business to grow, develop and succeed, by working

More information

Scope 2 Accounting Guidance: What it means for corporate decisions to purchase environmental instruments

Scope 2 Accounting Guidance: What it means for corporate decisions to purchase environmental instruments Scope 2 Accounting Guidance: What it means for corporate decisions to purchase environmental instruments January 2015 Corporate Scope 2 accounting has traditionally been relatively straight forward. Common

More information

Sustainability and Carbon Footprint Reduction

Sustainability and Carbon Footprint Reduction Sustainability and Carbon Footprint Reduction PricewaterhouseCoopers September 2008 An estimate is made of a complete carbon footprint of greenhouse gas emissions arising from New Zealand Fire Service

More information

Technical Journal. Paper 142

Technical Journal. Paper 142 Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager

More information

Plymouth Council & Asset Management

Plymouth Council & Asset Management Plymouth Council & Asset Management Plymouth City Council is committed to improving the condition of its carriageways and has demonstrated this graphically by pledging to spend 20m over and above any DfT/central

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

RISK MANAGEMENT POLICY

RISK MANAGEMENT POLICY RISK MANAGEMENT POLICY Approved by Governing Authority February 2016 1. BACKGROUND 1.1 The focus on governance in corporate and public bodies continues to increase. It resulted in an expansion from the

More information

London Borough of Havering. Draft Planning Guidance Note on Affordable Housing. Commuted Sum Payments

London Borough of Havering. Draft Planning Guidance Note on Affordable Housing. Commuted Sum Payments London Borough of Havering Draft Planning Guidance Note on Affordable Housing Commuted Sum Payments May 2016 Affordable housing circumstances where Havering Council will use commuted sum payments to the

More information

A Changing Commission: How it affects you - Issue 1

A Changing Commission: How it affects you - Issue 1 A Changing Commission: How it affects you - Issue 1 Contents Overview... 3 Change Programme... 4 Introduction... 4 Reviewing how we regulate and engage... 4 What are the key changes... 5 What does it mean

More information

the role of the head of internal audit in public service organisations 2010

the role of the head of internal audit in public service organisations 2010 the role of the head of internal audit in public service organisations 2010 CIPFA Statement on the role of the Head of Internal Audit in public service organisations The Head of Internal Audit in a public

More information

Identifying Environmental Aspects

Identifying Environmental Aspects Identifying Environmental Aspects How an organization interfaces with the environment Environmental Aspect: Element of an organization s activities, products, or services that can interact with the environment.

More information

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam

44-76 mix 2. Exam Code:MB5-705. Exam Name: Managing Microsoft Dynamics Implementations Exam 44-76 mix 2 Number: MB5-705 Passing Score: 800 Time Limit: 120 min File Version: 22.5 http://www.gratisexam.com/ Exam Code:MB5-705 Exam Name: Managing Microsoft Dynamics Implementations Exam Exam A QUESTION

More information

An introduction to impact measurement

An introduction to impact measurement An introduction to impact measurement Contents 1 Introduction 2 Some definitions 3 Impact measurement at BIG 4 Setting impact measures for programmes APPENDICES A External Resources (separate document)

More information

Adapting to a changing climate and energy future

Adapting to a changing climate and energy future Adapting to a changing climate and energy future Our policy position: Yarra Ranges Council acknowledges scientific advice concerning climate change and the need to mitigate and adapt to its impacts. Council

More information

Migrating Lotus Notes Applications to Google Apps

Migrating Lotus Notes Applications to Google Apps Migrating Lotus Notes Applications to Google Apps Introduction.................................................... 3 Assessment..................................................... 3 Usage.........................................................

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012. RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as

More information

Document management concerns the whole board. Implementing document management - recommended practices and lessons learned

Document management concerns the whole board. Implementing document management - recommended practices and lessons learned Document management concerns the whole board Implementing document management - recommended practices and lessons learned Contents Introduction 03 Introducing a document management solution 04 where one

More information

CPIx on Line. Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Supporting the HMG Construction Strategy.

CPIx on Line. Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Supporting the HMG Construction Strategy. CPIx on Line Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Project Address: Project Number: Date: Document No: Date: March 2013 Revision: R1 Status: Published