Subject: Prospect 3 Hydroelectric Project (FERC ) Comments on Preliminary Application Document and Scoping Document; and Study Requests

Size: px
Start display at page:

Download "Subject: Prospect 3 Hydroelectric Project (FERC 2337-076) Comments on Preliminary Application Document and Scoping Document; and Study Requests"

Transcription

1 Oregon John A. Kitzhaber, MD, Governor November, 14, 2013 Department of Fish and Wildlife Umpqua Watershed District Office 4192 North Umpqua Highway Roseburg, OR (541) FAX (541) Kimberly Bose, Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C VIA ELECTRONIC FILING Subject: Prospect 3 Hydroelectric Project (FERC ) Comments on Preliminary Application Document and Scoping Document; and Study Requests Dear Secretary Bose: The Oregon Department of Fish and Wildlife is filing the attached comments on the Preliminary Application Document, comments on the Scoping Document, and study requests in response to the Federal Energy Regulatory Commission s Notice of Intent to File License Application, Filing of Pre-application Document (PAD), Commencement of Pre-filing Process, and Scoping: Request for Comments on the PAD and Scoping Document, and Identification of Issues and Study Requests, dated August 30, 2013 for the above reference project. Sincerely, David A. Harris Southwest Hydropower Coordinator Service List (P-308) C (electronic mail): Kristen Bonanno-USFS Ken Homolka-ODFW Salem Dan Van Dyke-ODFW Central Point Mark Vargas-ODFW Central Point Chris Stine- ODEQ Rob Burns- FWS Mary Grainey- OWRD

2 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PacifiCorp Energy ) FERC Project ) Notice of Intent to File License Application, ) Filing of Pre-application Document (PAD), ) Commencement of Pre-filing Process, and ) Prospect 3 Scoping: Request for Comments on the PAD ) Hydroelectric Project and Scoping Document, and Identification ) of Issues and Study Requests OREGON DEPARTMENT OF FISH AND WILDLIFE COMMENTS ON PRE-APPLICATION DOCUMENT, COMMENTS ON SCOPING DOCUMENT 1, AND STUDY REQUESTS INTRODUCTION PacifiCorp Energy ( PacifiCorp or Applicant ) plans to file an application for a new license to continue operating the Prospect No. 3 Hydroelectric Project (Project) FERC No P-2337, on the South Fork Rogue River in Jackson County, Oregon. The current license will expire on December 13, The Project has a generation capacity of 7,200 kilowatts (kw) and is located on both private lands owned by PacifiCorp and federal lands managed by the Rogue River-Siskiyou National Forest. The project consists of: (1) a 172-foot-long, 24-foot-high concrete diversion dam with a 98-foot-long uncontrolled ogee on the South Fork Rogue River, (2) a 1-acre impoundment at elevation 3,375 feet with a gross capacity of 10-acre-feet, (3) a fish passage facility, including (a) an 86-foot long, 14-pool concrete ladder for upstream fish passage over the diversion dam; and (b) a 0.25-inch wedge-wire, inclined-plane fish screen with a surface area of 199 square feet located with the Project diversion facilities, which transitions to a bypass pipe to return fish to the ladder and facilitate downstream passage: (4) a 15,894-footlong conduit system consisting of, in order, (a) foot-long concrete-lined canal section; (b) a 66-inch-diameter, 5,448-foot-long woodstave pipe; (c) a 5,805-foot-long concrete-lined canal 1

3 section; (d) a 5-foot-wide by 6.5-foot high, 698-foot-long, concrete-lined, horseshoe type tunnel; (e) a 416-foot-long canal to penstock transition (i.e. forebay) with a 2,486-foot-long side channel spillway; and (f) a 66-inch to 68-inch diameter, 3,254-foot-long, riveted steel penstock; (5) a powerhouse containing one generating unit with a rated capacity of 7,200 kw operating under a static head of 740 feet and producing an average annual energy output of 37,125 megawatt hours (mw h); (6) a concrete tailrace structure approximately 20 feet by 20 feet by 5 feet with a 172-foot-long concrete lined overflow spillway; (7) a 66-inch, 887-foot-long woodstove siphon that routes flows from the tailrace to the Middle Fork Canal of the Prospect Nos. 1,2 and 4 Project (FERC No. P-2630): and (8) a 6.97-mile-long, 69-kilovolt (kv) transmission line that connects to Prospect Central substation. The Oregon Department of Fish and Wildlife (ODFW) exercises statutory oversight and possesses management expertise regarding the natural resources in the Rogue River Basin that may be affected by this relicensing. ODFW is extensively involved in a variety of fish and wildlife management issues in the Rogue watershed, including big game management, fish and fishery management, and nongame protection at hydroelectric projects. The Applicant filed its Notice of Intent to File License Application for a New License and Commencing Pre-filing Process on August 30, Staff from ODFW attended the Project site visit held on September 24, 2013 and the Commission s Daytime Scoping Meeting held on September 24, 2013 in Medford, Oregon. 2

4 COMMENTS ON PRE-APPLICATION DOCUMENT The Pre-Application Document (PAD) provides the basic information that is relevant to the Project proposal that is currently available, and it will assist ODFW to identify issues and additional information needs. ODFW s main interest in Project relicensing is to ensure that any ongoing impacts are identified and mitigated, new impacts are avoided, and to ensure the Project is consistent with Oregon s Wildlife Policy (ORS ) and other statutes, rules, guidelines, and plans. Section 2.4 explains that the project is not operated with any specific daily or seasonal ramping rates. ODFW believes it is important to understand the frequency and magnitude of ramping in the tailrace and bypass reach from planned and unplanned project shutdowns. The frequency of past shutdown events should be readily available for analysis. Information on the magnitude of current ramping will need to be collected during relicensing when maintenance shutdowns or other events are initiated. This information will assist in evaluating the effects of current project operations on trout spawning, incubation, and rearing. Section 2.5 describes the Project operations and existing license. Generating unit trips or operational balancing infrequently (approximately 5 times per year) results in Project waters discharging to the Middle Fork Rogue via the forebay spillway and tailrace overflow channel, respectively. ODFW believes it is important to determine the month(s) these water discharges are occurring. Information will assist in the evaluation of impacts (ramping and turbidity) to spawning native trout in the Middle Fork Rogue below Daniel Creek. Egg incubation, fry emergence and fry stranding all may be impacted by these events. 3

5 Section 2.6 The Applicant indicates in Section 2.6 that it is not planning to install new facilities or implement capital upgrades; however, based on ODFW s observations during the scoping site visit it is likely that some fish and wildlife facilities will need to be modified or replaced; such as: (1) upgrading the fish ladder to meet current upstream passage criteria, (2) upgrading the fish bypass screen to meet current ODFW fish screening criteria, and 3) widening the existing big game crossings. Section is a summary of the available habitat information from The summary states that the 3.5 miles of the South Fork immediately below the dam represents the portion of the bypass reach directly influenced by project operations. Of course, project influence is not limited to the first 3.5 miles below the facility, and likely extends to the confluence with the North Fork Rogue. ODFW feels that the distance analyzed in the current relicensing effort should at a minimum include 6.3 miles (diversion dam downstream to the confluence of the Middle Fork of Rogue River. Field work should confirm that accretion rates have not changed in amount per month since the 1986 study. ODFW agrees that there is minimal habitat data available between River Mile (RM) zero to RM 7.5. Ideally physical habitat data should be collected all the way to the mouth in order to fully assess the potential native trout population. Native trout in the South Fork Rogue River are migratory and must make lengthy instream movements in order to fulfill life history phases. This additional information will be necessary to evaluate instream minimum flows that provide both protection and enhancement. This section refers to barriers to fish passage in the 3.5 miles below the dam, but ODFW has records of anadromous fish in the vicinity of the projects (see below). It is important to note that 4

6 while debris jams and boulders reported in the habitat survey create jumps, they rarely create barriers to fish migration because of gaps and even movement over time. In addition, the habitat survey conducted in 1986 was conducted when flows below the dam were approximately 4 cfs (see graph below). Flows this August were 13 cfs, and ambient flows even in August would be around 100 cfs upstream of the project (according to the 1986 report). High flows mean higher water levels and reduced jump heights. Fish passage should be expected through this area. ODFW agrees with FERC s request for PacifiCorp to conduct a fish and aquatic habitat survey; however, we disagree that the survey should only be conducted in the upper 3.5 miles of the bypass reach. ODFW recommends that the fish and aquatic habitat survey cover a total of at least the upper 6.3 miles of the bypass reach, and as part of this survey accretion rates be assessed. Section the PAD refers to a statement from a watershed analysis in stating that the project area is outside the historic range of anadromous fish species. The geologic landform barriers near Prospect actually refers to the Avenue of the Boulders, which is believed to have blocked anadromous fish from entering the mainstem (or North Fork) of the Rogue River. The South and Middle Forks are known to have been used by anadromous species. 5

7 The dam on the South Fork was built around Unfortunately the first biological observations were not made until roughly ten years later. In his report History and Development of the Rogue River Basin as Related to its Fishery Prior to 1941, Cole Rivers (1963) wrote of the then Copco dams: Occasionally there are a few steelhead found at the base of the dams on the south and middle forks. ODFW observed large numbers of spawning spring chinook using the South Fork of the Rogue River in October A total of 997 chinook and 420 redds were observed from the mouth of the South Fork up to the confluence with the Middle Fork Rogue River. In October 1969, ODFW observed 13 spring chinook and 8 redds on the Middle Fork under the Prospect-Butte Falls Road Bridge. So while William Jess Dam (Lost Creek Reservoir) does block anadromous fish today, ODFW emphasizes that historically this area supported a variety of native migratory fish species. The presence of Chinook salmon implies that all other anadromous fish in the Rogue could have been present historically. Section is a summary of the available information for the fish community in the Project area. ODFW believes that native migratory fish species, primarily wild rainbow trout and potentially cutthroat trout, migrate out of Lost Creek Reservoir and enter the lower South Fork Rogue and the South Fork bypass reach, and must be able to pass the dam and diversion to use habitat upstream of the project. The Applicant states that since a 1986 study on downstream entrainment, considerable improvements and updates to fish passage and screen facilities have been completed and tested, so 1986 passage and entrainment figures are no longer applicable. ODFW agrees that fish passage conditions were improved during the last relicensing, but believes it is important for 6

8 the Applicant to conduct an analysis of the design and operation of these facilities during this relicensing to determine whether they meet current fish passage criteria, or can be upgraded to meet current criteria. The Applicant indicates that suitable spawning area in the bypass reach may be an important limiting factor to rainbow trout population. The PAD states that immigrant additions to the population from downstream rainbow trout communities are precluded by a number of natural passage barriers in the bypass reach preventing additions to the population by upstream movement. ODFW disagrees with this statement, and is not aware of any evidence that confirms that the fish are blocked by the reported barriers listed in the 1986 study. As stated above, anadromous fish were known historically in the project area. Flow reduction below the project likely makes passage more difficult, but fish passage should be expected. ODFW agrees with the Applicant that native trout in South Fork Rogue River are migratory and need to safe upstream passage in order to reach suitable spawning areas. Based on observations during the Scoping site visit ODFW is concerned that hydraulic conditions in the fish ladder blocks, partially blocks, or delays upstream passage for trout. Also fish produced above the South Fork Diversion dam, particularly young of the year, which migrate downstream to contribute to the population, may be injured at the screen facility and at the exit pool of the bypass pipe. Section describes that an environmental minimum flow of 10 cfs was established in the last relicensing pursuant to License Article 402. Current minimum flows address juvenile fry in the bypass reach. ODFW believes that fry survival in the bypass reach, although is important, is not as critical as juvenile to adult survival. Juvenile to adult survival rate is higher than the fry to 7

9 adult survival rate. Fry production above the diversion dam will continue to produce fry that can seed downstream bypass habitats, and improving the fish screen will likely provide a more balanced benefit than focusing the bypass flow to increase fry habitat. Section ODFW believes that new information has been collected since the 1986 relicensing that will affect the results of the instream flow study. The Applicant should incorporate updated habitat suitability criteria (HSC) to estimate weighted useable area at various stream flows. ODFW recommends that the 1986 data be analyzed using the same HSC used on the Prospect 1, 2, & 4 project. ODFW recommends that the Applicant provide electronic files of the original 1986 instream flow data to the agencies and collaborate in rerunning the flow analysis using the more recent HSC. Section ODFW agrees with the Applicant that the previous instream flow study was coarse and supports an updated model to re-examine usable fish habitats at various life stages. ODFW also believes that both upstream and downstream fish passage is outdated and needs to be studied to determine suitable upgrades. Section ODFW believes that current wildlife crossings should be widened. Although information suggest both small and big game animals are using the crossings, added width ensures safe timely passage of herd animals that stack up and are forced to cross single file. Section ODFW with aid from federal agencies has radio collared several wolves in the state of Oregon. Migration routes and locations of one particular wolf have been documented in the South fork Rogue basin and Project area. ODFW believes that wolves should be added to the survey and manage list. 8

10 Section ODFW agrees with the Applicant s proposed study to conduct a fine-scale habitat duration analysis on existing habitat flow relationships for native trout in the South Fork bypass reach, and ODFW recommends that the Applicant collaborate with the agencies to re-analyze the existing 1986 instream flow data using updated HSC. ODFW also suggests re-examination of the design and hydraulics of the fish ladder and screen facilities and development of a plan to ensure they meet current ODFW fish passage criteria. The Applicant should consider ramping study to assess impacts. Section ODFW has filed its Wolf Management Plan with the Commission to have it considered as a comprehensive plan pursuant to Section 10(a)(2)(A) of the Federal Power Act (FPA). We believe the Wolf Management Plan would be applicable to the Project area. Appendix A: ODFW recommends that the siphon be considered a feature of the Prospect 3 project because in the event of a catastrophic failure of the loss of the siphon the loss of water could damage the hillside under the powerhouse, and in the event of such a failure the project should not be allowed to restart without a thorough evaluation of the environmental damage to the Middle Fork Rogue River. COMMENTS ON SCOPING DOCUMENT 1 Section proposes to address effects of project operations and maintenance on soil erosion. ODFW recommends that this section include analysis of the effects of penstock failures, unit trips and maintenance outages on Daniels Creek and the Middle Fork Rogue River; and the timing of forebay maintenance sluicing. ODFW has collected information from statewide 9

11 trout surveys that show erosion and fine sediment has a negative association with trout presence. ODFW recommends that the siphon be considered a feature of the Prospect 3 project because in the event of a catastrophic failure of the loss of the siphon the loss of water could damage the hillside under the powerhouse, and in the event of such a failure the project should not be allowed to restart without a thorough evaluation of the environmental damage to the Middle Fork Rogue River. Section proposes to address effects of minimum flow releases, Project effects on upstream and downstream fish passage, and flow fluctuations in the bypassed reaches and Daniel Creek. ODFW suggests that PacifiCorp re-analysis the existing 1986 instream flow data using the same HSC used on the Prospect 1, 2, & 4 project. ODFW requests a copy of the existing 1986 instream flow data in electronic format and will collaborate with the Applicant in order to run flow analysis using the updated HSC. Effects on upstream passage should include fish ladder entrance jump heights and attraction flows, in-ladder flows (including the fish bypass pipe flow into the ladder), in-ladder jump heights, and flow though the submerged orifice at the ladder exit. Downstream passage should include screen size, approach and sweeping velocities, screen maintenance (cleaning), and bypass pipe flows. Section proposes to address effects of deer and elk movement and maintenance activities. ODFW recommends that any analysis of the width of animal crossings be examined. Other animal crossings in the Umpqua and Rogue watersheds have been increased in width to accommodate herd animals. ODFW would also recommend that all transmission lines on the Project be analyzed for risk of electrocution by avian species. 10

12 STUDY REQUEST ODFW s study requests are formatted to follow the requirements of 18 CFR Section 5.9(b) 1. Ramping Recommended Study and Basis for Request ODFW recommends that PacifiCorp perform ramping studies in Project bypass reaches to determine rates necessary to protect fish and aquatic resources from adverse effects resulting from upramping and downramping. Sudden flow changes in stream reaches due to Project operations can adversely impact fish and aquatic resources. Significant rapid flow reduction in bypass reaches can affect fish populations by dewatering redds and stranding fry or juvenile fish. Rapid flow increases in bypass reaches can wash out existing redds, displace fry, displace macroinvertebrates, or adversely impact amphibian populations in these reaches. One very significant ramping event at a very unusual time can cause a significant limiting condition for one or more age classes of fish, or a section of habitat to be impacted for a long period. The current FERC license does not include conditions requiring PacifiCorp to apply specific ramping rates to operations. ODFW believes that in order to form an adequate factual basis for complete analysis of the application, information needed to achieve the study objectives must be included. For these reasons, a ramp rate study at the South Fork Dam should be conducted. Study Participants ODFW does not take a position on who should conduct the study. We are confident that PacifiCorp can conduct the work in-house, though they may prefer to contract with a reputable 11

13 consultant. PacifiCorp needs to consult with the resource agencies during development of study designs and analysis of data collected. Study Methods and Objectives All the information below will need to be collected for the reach below the South Fork Dam. 1) Magnitude of ramping event (inches/hr); 2) Duration the event occurred (time in minutes); 3) Frequency of events (completed by reviewing production log books)*; 4) Ramp rate as measured on staff gages (nearest 0.01 inches); 5) Ramp rate estimates for maintenance activities (planned outages) based on mechanical constraints. ODFW recommends employing the methods proposed and implemented for relicensing studies on the Prospect 1, 2, & 4 project. Use the same methods used at the Middle Fork and Red Blanket bypass reaches) to obtain the information. Study Objectives All objectives need to be achieved for the reach below the South Fork Dam. 1) Document the frequency and duration of scheduled and unscheduled ramping events*; 2) Categorize ramping events by month or hydrologically similar periods*; 3) Document magnitude and rate of ramping using current operational procedures*; 4) Assess the level of control Project works can impart on ramp rate measured at sites where effects of changing flows on aquatic resources would be pronounced; and, 5) Determine the physical capabilities of the Project structures in controlling ramp rates. 12

14 How the Study will be useful in Furthering ODFW Resource Management Goals ODFW s request is to ensure proposed studies are completed, that PacifiCorp collects all the information that they have proposed, and that the information is made available for analysis. ODFW will use the study results to assess the aquatic impacts of project ramping. This information will also serve as the evidentiary basis to support recommendations for project ramping rates that will avoid or minimize impacts to aquatic organisms. ODFW s overarching goal is to prevent or minimize project-caused flow fluctuations to protect fish, wildlife, and other aquatic resources. The study results will further ODFW s resource management goals by providing information regarding the effect of the project on aquatic habitat in the upper Rogue and what kinds and levels of mitigation measures would be most appropriate to include in the new license to support protection and restoration of aquatic organisms and their habitat. Time Required for Study PacifiCorp should be able to conduct the field data collection as proposed for the areas below the South Fork Dam with several weeks of effort. Field data collection should occur when spill over the dam is minimal, but diversion into the South Fork power canal is near capacity. Several weeks of effort will be needed to 1) collect records from log books to document the frequency and duration of scheduled and unscheduled ramping events, 2) categorize ramping events by month or hydrologically similar time periods, and 3) organize and analyze the data. Existing Information and the Need for Additional Information PacifiCorp has conducted the field phase of a ramp rate study for bypass reaches below the Middle Fork and Red Blanket Diversions, and the South Fork bypass below the confluence with 13

15 the Middle Fork as related to operation of the Prospect 1, 2, and 4 project, but areas affected by the Prospect 3 project have not been assessed. Additional information is needed to: 1) Document the frequency and duration of scheduled and unscheduled ramping events for the bypass reach. 2) Categorize ramping events by month or hydrologically similar periods for all of the bypass reach. 3) Document magnitude and rate of ramping using current operational procedures for all bypass reach. 4) Assess the level of control Project works can impart on ramp rate measured at sites where the effects of changing flows on aquatic resources would be pronounced in the South Fork reach. 5) Determine the physical capabilities of the Project structures in controlling ramp rates in the North Fork reach. 2. Wildlife Connectivity Recommended Study and Basis for Request ODFW recommends that studies be conducted to determine the movements of animals in the vicinity of Project facilities, entrapment into canals, and evaluation of the existing wildlife crossings to determine whether the Project adversely impacts habitat connectivity for big game and small animals. ODFW is interested in determining the effects of the existing canals on the small vertebrates. While the fencing that surrounds the canals probably protects large mammals from becoming entrapped, small animals are probably able to pass through the fence mesh and become vulnerable to entrapment. Seasonal movements of reptiles and amphibians 14

16 are a well-documented aspect of their life history. The canals could represent an important cause of mortality or block dispersion and genetic flow for some species. ODFW feels that the current wildlife crossings are probably too narrow to provide adequate passage for big game and may not be strategically located. ODFW recommends the use of the crossings by wildlife be quantified and documented by monitoring with video cameras. In addition, PacifiCorp has proposed a major maintenance event by replacing the wood stave flowline. Wildlife underpass locations should be identified and implemented during replacement to ensure wildlife connectivity. The information gained from this study is essential for assessing wildlife connectivity in the Project area and determining whether adverse impacts are occurring. ODFW s basis for obtaining this information is to assist in identifying project impacts on wildlife populations, determine whether the project is consistent with ODFW s resource goals, and provide evidentiary fact for recommending measures for protection, mitigation, and enhancement. Study Participants ODFW does not take a position on who should conduct the study. We are confident that PacifiCorp can conduct the work in-house, though they may prefer to contract with a reputable wildlife consultant. PacifiCorp needs to consult with the resource agencies during development of study designs and analysis of data collected. Study Methods and Objectives Study methods should follow those described in Corn and Bury (1990). ODFW, other agencies, and researchers have employed video cameras, still cameras, radio telemetry, and capture and release methodology to monitor animal movements and behavior. Remote sensing with video 15

17 cameras can be used with bait stations to observe pine marten and fisher. Video cameras can be used to record animal behavior at canal crossings. Radio telemetry and capture/release/observation methods can be used to assess habitat connectivity, the avoidance of canals to crossing, and an animal s ability to cross canals to other Project features. The objective of the study would be to provide information on the movements of large and small animals near Project canals, to estimate the extent of entrainment mortality, and to determine the efficiency of the existing canal crossings. How the Study will be useful in Furthering ODFW Resource Management Goals Study information would be used to determine if the movements of small and large animals are being restricted by Project facilities and whether project facilities or operations have affected habitat conditions or connectivity. ODFW s overarching goal for relicensing the Project is to maintain terrestrial habitat connectivity so that dispersal, migration, and interbreeding among subpopulations can occur and to create a waterway system that has insignificant effects on populations. The study will further ODFW s resource management goals by providing information regarding the effect of the project on wildlife populations in the upper Rogue and help to identify what kinds and levels of mitigation measures would be most appropriate to include in the new license to support protection and restoration of wildlife populations. ODFW s goals and objectives for the fish and wildlife populations in the upper Rogue River basin are found in the following statutes (ORS) and rules (OAR) Wildlife Policy (ORS ) Establishes wildlife management policy to prevent serious depletion of any indigenous species and maintain all species of fish and wildlife at optimum levels. 16

18 Fish and Wildlife Habitat Mitigation Policy (OAR ) Require or recommend mitigation for losses of fish and wildlife habitat. Oregon s Elk Management Plan Protect and enhance elk populations in Oregon to provide optimum recreational benefits to the public and to be compatible with habitat capability and primary land uses. Oregon s Black Bear Management Plan Maintain healthy populations of black bear consistent with public desires and state law. Oregon s Cougar Management Plan Maintain healthy populations of cougar consistent with public desires and state law. Wildlife Diversity Plan (OARs through 0030) Maintain Oregon s wildlife diversity by protecting and enhancing populations and habitats of native wildlife at self-sustaining levels throughout natural geographic ranges. Oregon Wolf Conservation and Management Plan (OAR ) Ensure the conservation of gray wolves as required by Oregon law while protecting the social and economic interests of all Oregonians. Black-tailed Deer Management Plan Maintain healthy populations of Black-tailed Deer consistent with public desires and state law. Time Required for Study The time required for collecting sufficient data on these species is not known. ODFW recommends that the study schedule be prepared by PacifiCorp in cooperation with researchers familiar with studies of these species. Existing Information and the Need for Additional Information PacifiCorp conducted surveys on canals for the Prospect 1, 2, & 4 project relicensing. PacifiCorp widened 6 foot wide crossings to 12 foot wide and observed usage by a number of animal species. PacifiCorp s North Umpqua Hydropower Project widened animal crossings from 6 feet to 36 feet in width with small animal cover constructed on the edges. Information collected by PacifiCorp suggests heavy usage of these larger width crossings by both large and small animals. 17

19 ODFW has collected evidence to suggest that deer and other animals migrate from areas of the Cascades above the Project to areas below the Project. There is uncertainty as to the extent the canals and fencing effect migration, and whether the crossings are ameliorating possible negative effects. ODFW again recommends evaluating use/non-use of the crossings by monitoring animal behavior with video cameras. Some data were collected at existing wildlife crossing structures. However, minimal information was collected to examine the success of animal movement or the effects of canals and other structures on dispersion of small animals. 3 Minimum Flows in Bypass Reaches Recommended Study and Basis for Request The current minimum flow requirement was established during the last Project relicensing in The current relicensing provides the opportunity to reassess the adequacy of the existing mitigation measures for meeting the current and updated standards and criteria for fish and wildlife mitigation and protection. Under the current license the minimum flow requirement in the Project bypass reach is 10 cfs (License Article 402). Relicensing should result in ensuring that minimum flows in the project bypass reach are consistent with fish management goals and objectives to provide adequate stream habitat for fish production. ODFW s goals and objectives for the Prospect area fish populations of the Rogue River are found in the following statutes (ORS) and rules (OAR): Wildlife Policy (ORS ) Policy to Restore Native Stocks (ORS General Fish Management Goals (OAR ) 18

20 Oregon Plan for Salmon and Watersheds (ORS ) Native Fish Conservation Policy (OAR ) Trout Management (OAR ) Fish and Wildlife Habitat Mitigation Policy (OAR ) Study Participants ODFW does not take a position on who should conduct the study. We are confident that PacifiCorp can conduct the work in-house, though they may prefer to contract with a qualified fisheries consultant. ODFW recommends that the Applicant consult with the resource agencies to accomplish the reanalysis of the 1986 transect data using the HSC from the Prospect 1, 2, and 4 relicensing. Study Methods and Objectives This study will require PacifiCorp to acquire and provide to the resource agencies the existing 1986 IFIM data in electronic format. The Applicant should re-run the 1986 transect data using the HSC for cutthroat and rainbow trout as agreed by the Applicant and the resource agencies for the Prospect 1, 2, and 4 relicensing. The reanalysis of the existing transect data with the more recent HSC will likely result in modification of the predicted weighted useable area and habitat duration. (See ODFW caveat on habitat duration on page 23) The Applicant should use stream hydrograph data from the last 20 years as available from USGS or a synthesized hydrograph if necessary. ODFW recommends that the Applicant conduct field work to reassess the contribution of accretion in the lower Project bypass reach to document any changes since the last assessment for the 1986 IFIM study. The Applicant should collaborate with the resource agencies on the IFIM/PHABSIM results to identify appropriate minimum bypass flows for the species and life stages identified by the fish management agencies. The methods are 19

21 intended to be consistent with conducting a complete new IFIM/PHABSIM, however in this case new transect data will not be collected. How the Study will be useful in Furthering ODFW Resource Management Goals Study information would be used to determine what minimum flows will provide the greatest life history stage protection and enhancement. Native trout life history stages include: spawning, egg, fry, juvenile, and adult. Based on habitat measurements over a wide variety of flows, a determination of monthly or seasonal minimum bypass flows will be recommended that may overlap several life history stages but provide an overall protective/enhancement flow. These minimum flow(s) will help maintain aquatic habitat connectivity so that dispersal, migration, and interbreeding among subpopulations can occur. The study will further ODFW s resource management goals by providing information regarding the effect of the project on native trout populations in the upper Rogue and help to identify what kinds and levels of mitigation measures would be most appropriate to include in the new license to support protection and restoration of trout populations. Time Required for Study The time required for collecting sufficient data on these species is not known because ODFW is uncertain of the availability of the 1986 IFIM/PHABSIM data files. If these are readily available the rerun of the existing data with the more recent HSC could occur over a few weeks. Obtaining the hydrograph information including documenting accretion, drafting a report of the results, and collaboration and negotiation could potentially be completed within one year. Existing Information and the Need for Additional Information Current license article allows PacifiCorp to divert up to 150 cfs and leave at least 10 cfs to the bypass reach using the fish ladder as the conduit 20

22 Establishing minimum flow in the project-affected reaches is related to ODFW s management goals and objectives in that adequate flow for juvenile and adult rearing and spawning must be provided to meet goals and objectives of ODFW s trout management. Evaluating the relationship between stream flow and habitat in project affected reaches is necessary to assist in developing minimum flow requirements in project bypass reaches. PacifiCorp s proposes a fine scale habitat duration analysis on existing habitat-flow relationships for native trout in the South Fork bypass reach (IFIM). ODFW will review habitat duration analysis, but with the following caveats: WUA often reaches a peak at some intermediate flow level, then decreases at higher flows. Habitat duration analysis generally counts flow removal at these higher flows as a habitat benefit, since WUA is increased. This computed benefit is then used to offset WUA losses that occur when flow is reduced during the lower-flow times of the year. ODFW will not accept this type of interpretation because: a) Flows above the peak WUA flow provide many other functions to a healthy stream ecosystem. The benefits of these elevated flows are not captured by standard WUA output, but have been abundantly documented in the scientific literature. b) Use of physical habitat space by fish at elevated flows is not well documented. Higher velocity and increased depth does not necessarily decrease fish populations, despite the WUA output. 21

23 Any flow study conducted as part of relicensing for the Prospect 3 project must incorporate all necessary life stages/needs of all species of concern in the project area. The species of primary concern to ODFW are cutthroat trout and rainbow trout and the life stages are juvenile and adult. Because IFIM involves a number of important subjective decisions, PacifiCorp should involve ODFW and the other agencies in the study team to make decisions on techniques of IFIM and interpretation of results. IFIM is a group decision-making process, not simply a computer model, which requires input from all stakeholders throughout the entire process. A final study plan needs to be developed and submitted to the agencies for review; comment and approval before initiating the bypass reach flow studies. The study plan will be necessary to document the agreed upon techniques and analytical procedures to be used. ODFW recommends the following be considered in developing and conducting the flow study: Modeling incorporates a number of assumptions and uncertainties. These assumptions and uncertainties should be addressed in the interpretation and report. In particular, the effects of these uncertainties in determining instream flow requirements should be discussed, and quantified if possible. 1. Develop WUA curves per individual transect to determine if a particular habitat type is more impacted. 22

24 2. Make accurate representations of habitat the highest priority in the hydraulic modeling 3. Use the same spatial resolution for hydraulic simulation, habitat suitability index development, and habitat criteria testing. 4. ODFW will provide additional comments when a detailed study plan is distributed for review. 4 Upstream Passage Recommended Study and Basis for Request PacifiCorp was required to design and implement safe upstream passage per Article 404 of the current license. In 1993 ODFW requested that PacifiCorp proceed with the design of the facility utilizing interim design criteria to be provided by ODFW in the future. PacifiCorp filed the final upstream and downstream fish passage designs along with monitoring plan on December 28, The plans and design were accepted by FERC order on May 21, The construction of the upstream and downstream fish passage facilities was completed in November According to ORS , a fishway is required for artificial obstructions across any body of water in the state. Fishways must be provided to maintain adequate upstream and downstream passage of game fish. In addition, the policy goals of the Native Fish Conservation include; prevent the serious depletion of any native fish species by protecting natural ecological communities, conserving genetic resources, managing consumptive and non consumptive fisheries; and maintain and restore naturally produced native fish species, taking full advantage of the productive capacity of natural habitats, in order to provide substantial ecological, economic, and cultural benefits. 23

25 ODFW s main concern regarding fish passage is to bring the project into compliance with present day statutes and standards for fish and wildlife mitigation measures. We will work with PacifiCorp to identify the required fish passage criteria for the existing fishway. PacifiCorp should include plans for evaluating the effectiveness of fish passage facilities. Study Participants ODFW does not take a position on who should conduct the study. We are confident that PacifiCorp can conduct the work in-house, though they may prefer to contract with a reputable fisheries consultant. PacifiCorp needs to consult with the resource agencies during development of study designs and analysis of data collected Study Methods and Objectives This study will require PacifiCorp conduct field sampling. Fish ladder hydraulics and steps will need to be determined and compared to existing ODFW fish passage criteria. Those criteria that do not meet current ODFW standards should be updated to ensure safe and timely upstream passage. The energy dissipation factor EDF should be one component of the hydraulic analysis, in addition to measuring operational flow, flow design range, jump heights, and pool dimensions. How the Study will be useful in Furthering ODFW Resource Management Goals Study information would be used to determine what flow will provide safe and timely upstream passage. Also, jump heights at each fish ladder weir may need to be adjusted to allow passage. Lastly, flows through the submerged orifice at the ladders exit may be preventing or delaying trout movement out of the ladder into the reservoir. The goal is to maintain aquatic habitat connectivity so that dispersal, migration, and an exchange of genetic material can occur. 24

26 The study will further ODFW s resource management goals by providing information regarding the effect of the project on native trout populations in the upper South Fork Rogue River. Time Required for Study The time required for collecting sufficient data on these species should be complete during the spring and fall months of 2015 and Two seasonal survey periods will cover migration periods of trout species present in the South Fork Rogue River and check for a possible second seasonal peak upstream migration. ODFW recommends that the study schedule be prepared by PacifiCorp in cooperation with researchers familiar with studies of these species. Existing Information and the Need for Additional Information Current ladder at the South Fork diversion dam was designed and constructed using interim design criteria. The ladder was evaluated with upstream fish passage observed, Since 1997, information pertaining to correct step heights (6 inches), proper cfs though the ladder, energy dissipation, and continued safe upstream passage has not be documented. ODFW recommends the following be considered: 1. Updated fish ladder measurements to determine jump height 2. Accurate in ladder flow measurements (cfs) to determine if trout criteria are being met 3. Updated fish evaluation plan that outlines a study to determine safe upstream fish passage 4. Updated information on the physical condition of the fish ladder (concrete cracks, vegetation growth on ladder, etc.), 25

27 5 Fish Entrainment in the Power Canal Recommended Study and Basis for Request In 1993 ODFW requested that PacifiCorp proceed with the design of the facility utilizing interim design criteria to be provided by ODFW in the future. ODFW provided a Fish Screen Policy with interim design standards to PacifiCorp on September 7, PacifiCorp filed the final upstream and downstream fish passage designs along with monitoring plan on December 28, The plans and design were accepted by FERC order on May 21, The construction of the upstream and downstream fish passage facilities was completed in November ODFW has responsibility to protect downstream migrating fish through ORS and These statutes may require installation, operation, and maintenance of a fish screen on any diversion of water in the state and downstream passage for native migratory fish. ODFW will work with PacifiCorp to provide advice on conducting entrainment studies, to determine if an updated fish screen criterion is being met. ODFW will help develop new screening design and developing study plans for screen evaluation if determined that the existing screen does not meet criterion. Study Participants ODFW does not take a position on who should conduct the study. We are confident that PacifiCorp can conduct the work in-house, though they may prefer to contract with a reputable fisheries consultant. PacifiCorp needs to consult with the resource agencies during development of study designs and analysis of data collected Study Methods and Objectives This study will require PacifiCorp conduct field sampling, and re-use existing fish passage studies conducted in the 1980 and 1990 s. Fish screen hydraulics and bypass pipe will need to 26

28 be studied then compared to existing ODFW fish passage criteria. Those criteria that do not meet current ODFW standards should be updated or replaced to ensure safe and timely downstream stream passage. Trout of various sizes should be placed at the entrance of the fish screen (in the canal) to determine if: 1) screen approach and sweeping velocities meet criteria, 2) passage through the screen is safe and completed in a timely matter, and 3) passage through the bypass pipe and exit from the pipe does not delay or injure trout. How the Study will be useful in Furthering ODFW Resource Management Goals Study information would be used to determine what if the current screen facility meets ODFW criteria and provides safe and timely downstream passage. The goal is to maintain aquatic habitat connectivity so that dispersal, migration, and an exchange of genetic material can occur to downstream habitats below the diversion dam. The study will further ODFW s resource management goals by providing information regarding the effect of the project on native trout populations in the upper South Fork Rogue River. Time Required for Study The time required for collecting sufficient data on these species should be complete during the spring of 2015 and ODFW recommends that the study schedule be prepared by PacifiCorp in cooperation with researchers familiar with studies of these species. Existing Information and the Need for Additional Information Current fish screen at the South Fork diversion dam was designed and constructed using interim design criteria. The screens were evaluated in the late 1990 s and did not meet criteria. The screen was repaired and updated by PacifiCorp and met criteria standards for Since then no additional testing has been completed at the screening facility. 27

29 ODFW recommends the following be considered: 1. Updated approach and sweeping velocity studies 2. Updated screen spacing size 3. Updated fish screen evaluation plan that outlines a study to determine safe downstream fish passage 4. Updated information on the physical condition of the fish screen facility (concrete cracks, vegetation growth, screen condition, etc.), 6 Wildlife Species Composition Survey ODFW proposes a study to characterize the existing wildlife and amphibian communities of the project area in order to improve the understanding of the wildlife species currently inhabiting project landscape during different times of the year, including their distribution, and relative abundance. Study Participants ODFW does not take a position on who should conduct the study. We are confident that PacifiCorp can conduct the work in-house, though they may prefer to contract with a reputable wildlife consultant. PacifiCorp needs to consult with the resource agencies during development of study designs and analysis of data collected Study Methods and Objectives Study methods should be current acceptable to ODFW and other agencies. Studies may include the use of video cameras, still cameras, radio telemetry, and capture and release methodology to monitor animal movements and behavior. Remote sensing with video cameras can be used with bait stations to observe species such as pine marten and fisher. Video cameras can be 28

30 used to record animal behavior at canal crossings. Radio telemetry and capture/release/observation methods can be used to assess habitat connectivity, the avoidance of canals to crossing, and an animal s ability to cross canals to other Project features. The objective of the study would be to provide information on the species composition of large and small animals near Project. How the Study will be useful in Furthering ODFW Resource Management Goals Study information would be used to determine what current and future project impacts may have on wildlife resources in the area. The study will further ODFW s resource management goals by providing information regarding the effect of the project on native trout populations in the upper Time Required for Study The time required for collecting sufficient data on these species should be complete during the spring of 2015 and ODFW recommends that the study schedule be prepared by PacifiCorp in cooperation with researchers familiar with studies of these species. Existing Information and the Need for Additional Information Species information gathered by other agencies appears to cover large landscapes and are not specific to the Prospect 3 project area. In order to implement specific species management plans, a detailed wildlife species composition list is needed. 29

31 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PacifiCorp Energy ) FERC Project ) Notice of Intent to File License Application, ) Filing of Pre-application Document (PAD), ) Commencement of Pre-filing Process, and ) Prospect 3 Scoping: Request for Comments on the PAD ) Hydroelectric Project and Scoping Document, and Identification ) of Issues and Study Requests CERTIFICATE OF SERVICE I HEREBY CERTIFY that I have made service of the foregoing OREGON DEPARTMENT OF FISH AND WILDLIFE COMMENTS ON THE PREAPPLICATION DOCUMENT AND SCOPING DOCUMENT NO. 1, AND STUDY REQUESTS Prospect 3 Hydroelectric Project - Oregon - FERC Project No upon the parties designated on the official service list compiled by the Secretary in this proceeding: Dated November 14, 2013 David A. Harris Southwest Region Hydropower Coordinator 30

Black Canyon Hydroelectric Project FERC Project No. P-14110 Proposed Fish Passage Study Plan September 2012

Black Canyon Hydroelectric Project FERC Project No. P-14110 Proposed Fish Passage Study Plan September 2012 Black Canyon Hydroelectric Project FERC Project No. P-14110 Proposed Fish Passage Study Plan September 2012 Prepared for Black Canyon Hydro, LLC 3633 Alderwood Avenue Bellingham, WA 98225 Table of Contents

More information

121 FERC 62,167 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Public Utility District No. 1 of Project No. 637-044 Chelan County

121 FERC 62,167 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Public Utility District No. 1 of Project No. 637-044 Chelan County 121 FERC 62,167 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Public Utility District No. 1 of Project No. 637-044 Chelan County ORDER MODIFYING AND APPROVING LAKE CHELAN FISHERY PLAN,

More information

ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage

ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage DOEIID-10360 Distribution Category: UC-22S ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage M. J. Sale G. F. Cada

More information

Gold Ray Dam Interagency Technical Team Meeting

Gold Ray Dam Interagency Technical Team Meeting Gold Ray Dam Interagency Technical Team Meeting Agenda Public Outreach, Funding, Monitoring EA/BA/Permit Updates Deconstruction Plans Fish Passage & Salvage Plan Hydraulic Modeling Next Steps Public Outreach,

More information

Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant

Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant By Ginger Gillin, John Pizzimenti, and Doug Foss, GEI Consultants, Inc., USA, and Jon Jourdonnais, PPL Montana, USA. Abstract The

More information

Year 2 7-15-10 Post Restoration Monitoring Summary Rock Creek Project Monitoring and Analysis conducted by Bio-Surveys,LLC. Contact: strask@casco.

Year 2 7-15-10 Post Restoration Monitoring Summary Rock Creek Project Monitoring and Analysis conducted by Bio-Surveys,LLC. Contact: strask@casco. Year 2 7-15-10 Post Restoration Monitoring Summary Rock Creek Project Monitoring and Analysis conducted by Bio-Surveys,LLC. Contact: strask@casco.net Project Sponsors include: The City of Corvallis Oregon

More information

NID statement Agreement Disagreement Auburn Ravine: During irrigation and nonirrigation

NID statement Agreement Disagreement Auburn Ravine: During irrigation and nonirrigation NID statement Agreement Disagreement Auburn Ravine: 1. NID will not divert the natural flow during times when the flow as measured at NID s Highway 65 gage is less than 8 cfs provided that during those

More information

Walla Walla Bi state Stream Flow Enhancement Study Interim Progress Report. Department of Ecology Grant No. G1400656.

Walla Walla Bi state Stream Flow Enhancement Study Interim Progress Report. Department of Ecology Grant No. G1400656. Walla Walla Bi state Stream Flow Enhancement Study Interim Progress Report Department of Ecology Grant No. G1400656 Submitted by: Walla Walla Watershed Management Partnership Walla Walla, WA Walla Walla

More information

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P-12686. Turbidity Monitoring Plan

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P-12686. Turbidity Monitoring Plan APPENDIX F Baker County Mason Dam Hydroelectric Project FERC No. P-12686 Turbidity Monitoring Plan April 2011 857 Table of Contents 1.0 Introduction 1 2.0 Purpose and Scope 2 3.0 Turbidity Monitoring and

More information

BIG CREEK Nos. 1 AND 2 (FERC Project No. 2175) VOLUME 1 (BOOK 1 OF 27 BOOKS) INITIAL STATEMENT, EXHIBITS A, B, C, D AND H (PUBLIC INFORMATION)

BIG CREEK Nos. 1 AND 2 (FERC Project No. 2175) VOLUME 1 (BOOK 1 OF 27 BOOKS) INITIAL STATEMENT, EXHIBITS A, B, C, D AND H (PUBLIC INFORMATION) BIG CREEK Nos. 1 AND 2 (FERC Project No. 2175) VOLUME 1 (BOOK 1 OF 27 BOOKS) INITIAL STATEMENT, EXHIBITS A, B, C, D AND H (PUBLIC INFORMATION) CD NO. 1 OF 19 CDS Initial Statement Exhibit A: Description

More information

ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN. Evaluation of spring Chinook salmon spawning in Big Butte Creek, 2008

ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN. Evaluation of spring Chinook salmon spawning in Big Butte Creek, 2008 ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN Evaluation of spring Chinook salmon spawning in Big Butte Creek, 28 Rogue Watershed District Oregon Department of Fish and Wildlife March 29 Introduction

More information

Determination of NEPA Adequacy (DNA)

Determination of NEPA Adequacy (DNA) DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT MEDFORD DISTRICT OFFICE GRANTS PASS RESOURCE AREA 2164 NE SPALDING AVENUE GRANTS PASS, OR 97526 Determination of NEPA Adequacy (DNA) Office: Grants

More information

STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208

STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208 STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208 RANGELAND HEALTH STANDARDS - ASSESSMENT SAGEHEN ALLOTMENT #0208 STANDARD 1 - UPLAND WATERSHED This standard is being met on the allotment.

More information

UTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION

UTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION UTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION Joshua A. Israel, Fish Biologist, U.S Bureau of Reclamation, Sacramento, CA. jaisrael@usbr.gov; Paul

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN Columbia River Project Water Use Plan LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN CLBMON-45 Lower Columbia River Fish Indexing Surveys 31 August 2007 1.0 OVERVIEW LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN

More information

1.7.0 Floodplain Modification Criteria

1.7.0 Floodplain Modification Criteria 1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:

More information

Skaguay Reservoir. FISH SURVEY AND MANAGEMENT DATA Greg A. Policky - Aquatic Biologist (Salida) greg.policky@state.co.

Skaguay Reservoir. FISH SURVEY AND MANAGEMENT DATA Greg A. Policky - Aquatic Biologist (Salida) greg.policky@state.co. FISH SURVEY AND MANAGEMENT DATA (Salida) greg.policky@state.co.us / 719-530-5525 General Information: Skaguay Reservoir, a 114 acre impoundment, offers good fishing for rainbow and brown trout with an

More information

Chapter 11. Costs and Funding

Chapter 11. Costs and Funding Chapter 11. 11.1 Financial Summary...11-1 11.2 Program Costs...11-2 11.2.1 Habitat Conservation Program Costs...11-2 Bull Run Habitat Conservation Measures...11-2 Offsite Sandy River Basin Habitat Conservation

More information

Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008

Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008 Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008 In partnership with Montana Department of Fish, Wildlife, and Parks (FWP), American Wildlands, and Wildlife Forever, the Madison

More information

STREAMFLOW RESTORATION PRIORITY AREAS

STREAMFLOW RESTORATION PRIORITY AREAS STREAMFLOW RESTORATION PRIORITY AREAS Synopsis The Water Resources Department and the Department of Fish and Wildlife jointly identified priority areas for streamflow restoration in basins throughout the

More information

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project September 12, 2013 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Preliminary Permit Application for the Dear Ms. Bose, Please find attached

More information

Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013

Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013 Chehalis River Basin Flood Damage Reduction 2013-2015 Capital Budget Approved by Legislature in June 2013 1. Design alternatives for large capital flood projects (basinlevel water retention and Interstate

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

LR 314 Working Group 5 Final Report

LR 314 Working Group 5 Final Report LR 314 Working Group 5 Final Report I. Nebraska Department of Natural Resources Table 1. NDNR and NATURAL RESOURCES COMMISSION WATER/INTEGRATED MANAGEMENT PLANNING RELATED RESEARCH, STUDIES AND RELATED

More information

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria

More information

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY

PIPELINE ROUTING PERMIT. For A NATURAL GAS PIPELINE DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PIPELINE ROUTING PERMIT For A NATURAL GAS PIPELINE IN DAKOTA AND RAMSEY COUNTIES ISSUED TO NORTHERN STATES POWER COMPANY D/B/A XCEL ENERGY PUC DOCKET No. G002/GP-05-1706 In accordance with the requirements

More information

COMPLIANCE REPORT MUDDY HOLLOW CULVERT REMOVAL FILE NUMBER 25358N

COMPLIANCE REPORT MUDDY HOLLOW CULVERT REMOVAL FILE NUMBER 25358N COMPLIANCE REPORT MUDDY HOLLOW CULVERT REMOVAL FILE NUMBER 25358N Submitted by the National Park Service Point Reyes National Seashore Point Reyes Station, California, 94956 Project Description: Muddy

More information

Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Water Quality May 2015

Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Water Quality May 2015 Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Water Quality May 2015 Prepared by: PacifiCorp Hydro Resources 925 South Grape Street Medford, OR 97501 For Public Review

More information

Monitoring the Benefits of Instream Habitat Diversity. Entiat River, Chelan County, Washington

Monitoring the Benefits of Instream Habitat Diversity. Entiat River, Chelan County, Washington Monitoring the Benefits of Instream Habitat Diversity Entiat River, Chelan County, Washington Bureau of Reclamation Bonneville Power Administration May 2013 This is an update of the report that first occurred

More information

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title]

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] Purpose These rules set forth the conditions under which a person may, without an individual removal-fill permit

More information

5.14 Floodplains and Drainage/Hydrology

5.14 Floodplains and Drainage/Hydrology I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important

More information

Wildlife Habitat Conservation and Management Program

Wildlife Habitat Conservation and Management Program Wildlife Habitat Conservation and Management Program Manual for Counties and Cities Oregon Department of Fish and Wildlife 2015 Table of Contents 1. Introduction Purpose of the habitat program Objective

More information

May 29, 2015. Mr. Tom Howard Executive Director State Water Resources Control Board P.O. Box 100 Sacramento, CA 95812-0100

May 29, 2015. Mr. Tom Howard Executive Director State Water Resources Control Board P.O. Box 100 Sacramento, CA 95812-0100 May 29, 2015 Mr. Tom Howard Executive Director State Water Resources Control Board P.O. Box 100 Sacramento, CA 95812-0100 Mr. Ron Milligan Operations Manager, Central Valley Project U.S. Bureau of Reclamation

More information

Rhode Island NRCS received approximately $2.4 million in ARRA funds to implement four floodplain easement projects.

Rhode Island NRCS received approximately $2.4 million in ARRA funds to implement four floodplain easement projects. American Recovery and Reinvestment Act (ARRA) Emergency Watershed Protection Program Floodplain Easements Rhode Island Natural Resources Conservation Service Rhode Island NRCS received approximately $2.4

More information

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

TENNESSEE GAS PIPELINE COMPANY, L.L.C. TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC & HYDRAULIC CALCULATIONS FOR WATERBODIES CROSSED BY CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,

More information

WATER STORAGE, TRANSPORT, AND DISTRIBUTION Multi-Dam Systems and their Operation - J.J. Cassidy MULTI-DAM SYSTEMS AND THEIR OPERATION

WATER STORAGE, TRANSPORT, AND DISTRIBUTION Multi-Dam Systems and their Operation - J.J. Cassidy MULTI-DAM SYSTEMS AND THEIR OPERATION MULTI-DAM SYSTEMS AND THEIR OPERATION J.J. Cassidy Consulting Hydraulic and Hydrologic Engineer, Concord, California, USA Keywords: Dams, reservoirs, rivers, water storage, dam safety, floods, environment,

More information

Summary of the Klamath Basin Settlement Agreements

Summary of the Klamath Basin Settlement Agreements Summary Summary of the Klamath Basin Settlement Agreements May 2010 Representatives of 45 organizations, including Federal agencies, California and Oregon, Indian tribes, counties, irrigators and conservation

More information

CHAPTER I: INTRODUCTION. Background

CHAPTER I: INTRODUCTION. Background CHAPTER I: INTRODUCTION Background California State Law requires each county to adopt a General Plan for the physical development of the county and any land outside its boundaries which bears relation

More information

Frequently Asked Questions (FAQs) on Hydropower

Frequently Asked Questions (FAQs) on Hydropower Frequently Asked Questions (FAQs) on Hydropower What are the advantages of Hydropower? A renewable source of energy - saves scarce fuel reserves. Non-polluting and hence environment friendly. Long life

More information

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN

3.4 DRAINAGE PLAN. 3.4.1 Characteristics of Existing Drainages. 3.4.2 Master Drainage System. Section 3: Development Plan BUTTERFIELD SPECIFIC PLAN 3.4 DRAINAGE PLAN This section describes the existing onsite drainage characteristics and improvements proposed within this Specific Plan. Following this description, drainage plan development standards

More information

Arkansas River Corridor Vision & Master Plan

Arkansas River Corridor Vision & Master Plan A r k a n s a s R I v e r C o r r I d o r P l a n Arkansas River Corridor Vision & Master Plan July 2005 Indian Nations Council of Governments A r k a n s a s R I v e r C o r r I d o r P l a n Partnership

More information

Oregon. Climate Change Adaptation Framework

Oregon. Climate Change Adaptation Framework Oregon Climate Change Adaptation Framework Oregon Environmental Quality Commission Climate Change Adaptation Framework Presentation at a glance: Purposes of the framework Participating agencies Climate

More information

How To Decide If A Dam Removal Is Safe For Water Quality

How To Decide If A Dam Removal Is Safe For Water Quality Report Issue Paper: Water Quality Certification Procedures for Klamath River Restoration Project By: Steve Kirk and Debra Sturdevant March 2012 Last Updated: 3/14/12 DEQ 11-WQ-047 This report prepared

More information

PUBLIC NOTICE Application for Permit

PUBLIC NOTICE Application for Permit PUBLIC NOTICE Application for Permit 30-Day Notice Issue Date: June 20, 2016 Expiration Date: July 20, 2016 US Army Corps of Engineers No: NWP-2010-535 Oregon Department of State Lands No: 58311-RF Interested

More information

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA

The Basics of Chapter 105 Waterways and Wetlands Permitting in PA The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers

More information

Proposal to the Trinity Adaptive Management Working Group (TAMWG)

Proposal to the Trinity Adaptive Management Working Group (TAMWG) Proposal to the Trinity Adaptive Management Working Group (TAMWG) Request that the TAMWG recommend that the Trinity River Restoration Program fund BLM to purchase the Weigel parcel at Gold Bar (river mile

More information

Addendum. Use Attainability Analysis for Site Specific Selenium Criteria: Alkali Creek. February 23, 2009

Addendum. Use Attainability Analysis for Site Specific Selenium Criteria: Alkali Creek. February 23, 2009 Addendum Use Attainability Analysis for Site Specific Selenium Criteria: Alkali Creek February 23, 2009 Prepared by MWH Americas, Inc. Prepared for EnCana Oil and Gas (USA) Inc. Page 2 Responses to Comments

More information

Habitat Quality, Rainbow Trout Occurrence, and Steelhead Recovery Potential Upstream of Searsville Dam

Habitat Quality, Rainbow Trout Occurrence, and Steelhead Recovery Potential Upstream of Searsville Dam Habitat Quality, Rainbow Trout Occurrence, and Steelhead Recovery Potential Upstream of Searsville Dam Prepared by: Matt Stoecker Biologist Owner Stoecker Ecological December 19, 2014 Table of Contents

More information

Tie CornrnonweaGti of Massaciusetts Wecutive Ofiice of Energy andenvironmentacpfiairs 100 Cam6ndjge Street, Suite 900 Boston, NP 021 14

Tie CornrnonweaGti of Massaciusetts Wecutive Ofiice of Energy andenvironmentacpfiairs 100 Cam6ndjge Street, Suite 900 Boston, NP 021 14 Ocval I.. Palrick CiClVERNOll Ttrnothy P. Murray I IFUTENANl GOVERNOR Ian A. Rowles SECRETARY Tie CornrnonweaGti of Massaciusetts Wecutive Ofiice of Energy andenvironmentacpfiairs 100 Cam6ndjge Street,

More information

Steelhead Recovery in San Juan and Trabuco Creeks Watershed

Steelhead Recovery in San Juan and Trabuco Creeks Watershed Steelhead Recovery in San Juan and Trabuco Creeks Watershed Are there fish now? Overview Final San Juan and Trabuco Creeks Watershed Management Plan Fish & Game Implementation NOAA Steelhead Recovery and

More information

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference Columbia River Project Water Use Plan Revelstoke Flow Management Plan Monitoring Program Terms of Reference CLBMON-15a Middle Columbia River Physical Habitat Monitoring Revision January 29, 2015 Monitoring

More information

DRAFT SOUTH FORK SKYKOMISH RIVER

DRAFT SOUTH FORK SKYKOMISH RIVER DRAFT SOUTH FORK SKYKOMISH RIVER 9 levees and revetments / Approximately 1.1 miles of river bank are armored Revetments provide limited, localized erosion protection, but impact habitat Frequent and costly

More information

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure (December 2013) IUCN does not engage in projects which involve the design, construction or rehabilitation

More information

2008 Total Dissolved Gas Management Plan

2008 Total Dissolved Gas Management Plan 2008 Total Dissolved Gas Management Plan 1.0 Introduction High total dissolved gas (TDG) saturation levels are observed in various parts of the Columbia and Snake River systems where spill occurs, sometimes

More information

PANEL REVIEW OF THE DRAFT BAY DELTA CONSERVATION PLAN: PREPARED FOR THE NATURE CONSERVANCY

PANEL REVIEW OF THE DRAFT BAY DELTA CONSERVATION PLAN: PREPARED FOR THE NATURE CONSERVANCY PANEL REVIEW OF THE DRAFT BAY DELTA CONSERVATION PLAN: PREPARED FOR THE NATURE CONSERVANCY AND AMERICAN RIVERS Jeffrey Mount, Ph.D. (Chair) William Fleenor, Ph.D. Brian Gray, J.D. Bruce Herbold, Ph.D.

More information

LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN

LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN 1 AUGUST 2011 LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN KEY ELEMENTS OF THE PLAN: 1. Replace the existing unsafe Ragged Mountain dam with a new dam and raise the reservoir pool level initially

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library. For additional information about this document and the document conversion process, please contact

More information

Bull Run River. Water Temperature Evaluation. Prepared by: City of Portland Bureau of Water Works Portland, Oregon

Bull Run River. Water Temperature Evaluation. Prepared by: City of Portland Bureau of Water Works Portland, Oregon Bull Run River Water Temperature Evaluation Prepared by: City of Portland Bureau of Water Works Portland, Oregon June 2004 Contents Page Preface... 1 Report Purpose... 1 Report Organization... 1 Executive

More information

Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration

More information

Code of Practice for Pipelines and Telecommunication Lines Crossing a Water Body

Code of Practice for Pipelines and Telecommunication Lines Crossing a Water Body Code of Practice for Pipelines and Telecommunication Lines Crossing a Water Body Made under the Water Act and the Water (Ministerial) Regulation Consolidated to include amendments in force as of June 24,

More information

HCP Team Meeting. November 18, 2015. icfi.com

HCP Team Meeting. November 18, 2015. icfi.com HCP Team Meeting November 18, 2015 icfi.com 1 Welcome and Introductions Where are we in the HCP process Hydrology modeling update Native fish survey Fish translocation Finalize covered activities Next

More information

PROJECT STATUS REPORT. Development of microhabitat suitability criteria for fry and juvenile salmonids of the Trinity River

PROJECT STATUS REPORT. Development of microhabitat suitability criteria for fry and juvenile salmonids of the Trinity River PROJECT STATUS REPORT Development of microhabitat suitability criteria for fry and juvenile salmonids of the Trinity River Prepared for: Trinity River Restoration Program P.O. Box 13 1313 South Main St.

More information

Comment Invited on Proposal to Protect the Bristol Bay Watershed

Comment Invited on Proposal to Protect the Bristol Bay Watershed Region 10 Comment Invited on Proposal to Protect the Bristol Bay Watershed July 2014 U.S. Environmental Protection Agency Region 10 requests comment on a proposal to protect one of the world s most valuable

More information

Section 2. Mono Basin Operations

Section 2. Mono Basin Operations Section 2 Mono Basin Chapter 2 Mono Basin Compliance with State Water Resources Control Board Decision 1631 and Order Nos. 98-05 and 98-07 May 2008 Los Angeles Department of Water and Power Table of Contents

More information

HEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES

HEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES HEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES INTRODUCTION The Headwaters Control Structure at Gray's Bay is the outlet of Lake Minnetonka to Minnehaha Creek. It is an adjustable

More information

Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices

Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Post-Wildfire Clean-Up and Response in Houston Toad Habitat Best Management Practices Purpose The purpose of this document is to provide guidance and recommendations for minimizing potential impacts to

More information

Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002

Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002 Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed Summary Report 2002 DOE/BP-00005268-5 November 2002 This Document should be cited as follows: "Restoring Anadromous Fish Habitat in Big Canyon

More information

Request Number 11: Fish and Fish Habitat Compensation Plan

Request Number 11: Fish and Fish Habitat Compensation Plan Request Number 11: Fish and Fish Habitat Compensation Plan References: EIS Guidelines Section 16.8.4; EIS Guidelines Section 10; EIS, Vol. 2, Section 12.5.3.2 JRP Context: The EIS states that a Site C

More information

Assessment of the White Salmon Watershed Using the Ecosystem Diagnosis and Treatment Model

Assessment of the White Salmon Watershed Using the Ecosystem Diagnosis and Treatment Model Assessment of the White Salmon Watershed Using the Ecosystem Diagnosis and Treatment Model Draft Final Report For the Period: November 2003 to December 2004 May 2005 Brady Allen Fishery Biologist and Patrick

More information

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations

More information

DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014. Values Statements.

DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014. Values Statements. DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014 Values Statements. The Board opposes any new transfers of water from the

More information

How To Write A Watercourse Crossing

How To Write A Watercourse Crossing Code of Practice for Watercourse Crossings Made under the Water Act and the Water (Ministerial) Regulation Consolidated to include amendments in force as of June 24, 2013 Office Consolidation Published

More information

Definition of Tower from the Bradley County Zoning Resolution

Definition of Tower from the Bradley County Zoning Resolution Definition of Tower from the Bradley County Zoning Resolution 43. TOWER. Any outdoor structure designed and constructed to support one (1) or more transmitting or receiving devices for telephone, radio

More information

Request for Proposal. Request for Proposal for GreenLink Bellingham Technical Analysis and Community Engagement, Bellingham, WA

Request for Proposal. Request for Proposal for GreenLink Bellingham Technical Analysis and Community Engagement, Bellingham, WA Request for Proposal Request for Proposal for GreenLink Bellingham Technical Analysis and Community Engagement, Bellingham, WA 1 Table of Contents: Section A: Project Scope... 3 Section B: Background...

More information

18 voting members 44 stakeholders 114 email list. Senators: Wyden & Merkley Representative DeFazio

18 voting members 44 stakeholders 114 email list. Senators: Wyden & Merkley Representative DeFazio 18 voting members 44 stakeholders 114 email list Senators: Wyden & Merkley Representative DeFazio State Representative Krieger State Senators: Roblan, Johnson, and Kruse Governor Brown s office County

More information

How To Manage Water Resources In The Yakima Basin

How To Manage Water Resources In The Yakima Basin Yakima Basin Integrated Water Resource Management Plan October 23, 2014 Presented by Derek Sandison, Director Office of Columbia River Photo Courtesy of Tom Ring Basin size: 6,155 sq. miles Population:

More information

Kevin Kennedy Natural Gas and Special Projects Office

Kevin Kennedy Natural Gas and Special Projects Office PRELIMINARY ASSESSMENT OF ENERGY ISSUES ASSOCIATED WITH THE KLAMATH HYDROELECTRIC PROJECT Kevin Kennedy Natural Gas and Special Projects Office Jim Woodward Electricity Analysis Office Systems Assessment

More information

U.S. Fish and Wildlife Service Icicle Creek Fish Passage Evaluation for The Leavenworth National Fish Hatchery

U.S. Fish and Wildlife Service Icicle Creek Fish Passage Evaluation for The Leavenworth National Fish Hatchery U.S. Fish and Wildlife Service Icicle Creek Fish Passage Evaluation for The Leavenworth National Fish Hatchery U.S. Fish and Wildlife Service Columbia River Fisheries Program Office Vancouver, Washington

More information

Jackson Gulch Outlet Canal Rehabilitation Project

Jackson Gulch Outlet Canal Rehabilitation Project Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County

More information

King County Flood Hazard Management Plan Update Cedar/ Sammamish Rivers. Public Meeting December 5, 2012

King County Flood Hazard Management Plan Update Cedar/ Sammamish Rivers. Public Meeting December 5, 2012 King County Flood Hazard Management Plan Update Cedar/ Sammamish Rivers Public Meeting December 5, 2012 Goals of the Presentation Cedar and Sammamish R. Plan Update Context - Brief summary info about the

More information

The North State: Implementing the California Water Action Plan February 24, 2014

The North State: Implementing the California Water Action Plan February 24, 2014 The North State: Implementing the California Water Action Plan February 24, 2014 The North State Water Alliance applauds Governor Brown s California Water Action Plan (Action Plan) and his call for comprehensive

More information

CHAD R. GOURLEY SPECIALTY EMPLOYMENT

CHAD R. GOURLEY SPECIALTY EMPLOYMENT CHAD R. GOURLEY P.O. Box 919 Verdi, Nevada 89439 phone 775.345.9960 cell 775.250.8140 chad_gourley at att.net SPECIALTY Restoration of riverine, spring, and wetland ecosystems, specializing in a process

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

HYDROELECTRIC PERMITTING MANUAL FOR PENNSYLVANIA February 2015

HYDROELECTRIC PERMITTING MANUAL FOR PENNSYLVANIA February 2015 HYDROELECTRIC PERMITTING MANUAL FOR PENNSYLVANIA February 2015 Prepared by Pennsylvania Environmental Council Acknowledgements It is with gratitude that we acknowledge the many hours contributed by the

More information

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan

Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Throughout the Plan 1. There is a fundamental need for the revised plan to address how

More information

AN INITIATIVE TO IMPROVE

AN INITIATIVE TO IMPROVE L OW E R C A R M E L R I V E R A N D L AG O O N F L O O D P L A I N R E S TO R AT I O N A N D E N H A N C E M E N T P R O J E C T AN INITIATIVE TO IMPROVE FLOOD PROTECTION RESTORE AND PROTECT RIPARIAN

More information

Environmental Compliance Questionnaire for National Oceanic and Atmospheric Administration Federal Financial Assistance Applicants

Environmental Compliance Questionnaire for National Oceanic and Atmospheric Administration Federal Financial Assistance Applicants OMB Approval No.: 0648-0538 Environmental Compliance Questionnaire for National Oceanic and Atmospheric Administration Federal Financial Assistance Applicants Instructions The National Environmental Policy

More information

The NPS dam Safety and Security Program

The NPS dam Safety and Security Program United States Department of the Interior NATIONAL PARK SERVICE 1849 C Street, N.W. Washington, D.C. 20240 Director's Order #40: Dam Safety & Security Program Effective Date: ----------------- Duration:

More information

3. The submittal shall include a proposed scope of work to confirm the provided project description;

3. The submittal shall include a proposed scope of work to confirm the provided project description; QIN Shoreline Master Program Project Summary The Shoreline Master Program (SMP) development process for the Quinault Indian Nation (QIN) includes the completion of inventory and analysis report with corresponding

More information

Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE

Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE Miquon Creek STREAM RESTORATION PROJECT WHO WE ARE Introductions Brett Long, PE Project Permitting & Construction Oversight Chris Streb, PE Project Designer & Construction Oversight Assistance WHO WE ARE

More information

Develop and Implement a Pilot Status and Trend Monitoring Program for Salmonids and their Habitat in the Wenatchee and Grande Ronde River Basins.

Develop and Implement a Pilot Status and Trend Monitoring Program for Salmonids and their Habitat in the Wenatchee and Grande Ronde River Basins. Project ID: 35019 Title: Develop and Implement a Pilot Status and Trend Monitoring Program for Salmonids and their Habitat in the Wenatchee and Grande Ronde River Basins. Response to ISRP Comments A. This

More information

FLOOD PROTECTION BENEFITS

FLOOD PROTECTION BENEFITS IV. (340 points) Flood Protection Benefits A. Existing and potential urban development in the floodplain (50) 1. Describe the existing and potential urban development at the site and the nature of the

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

Resolving complex issues with large scale river restoration; a case study: the San Joaquin River in California

Resolving complex issues with large scale river restoration; a case study: the San Joaquin River in California IWA Publishing 2011 Water Practice & Technology Vol 6 No 4 doi:10.2166/wpt.2011.074 Resolving complex issues with large scale river restoration; a case study: the San Joaquin River in California William

More information

Federal Energy Regulatory Commission 5.1

Federal Energy Regulatory Commission 5.1 Federal Energy Regulatory Commission 5.1 period prescribed for making such payment, interest and penalty charges will be assessed. Interest and penalty charges will be computed in accordance with 31 U.S.C.

More information

Coastal Monitoring Program for Salmon and Steelhead

Coastal Monitoring Program for Salmon and Steelhead California California Department of Fish and Wildlife NOAA Fisheries Coastal Monitoring Program for Salmon and Steelhead California Department of Fish and Wildlife Fisheries Branch 830 S Street Sacramento,

More information

Run-of-River Hydropower in BC A Citizen s Guide to Understanding Approvals, Impacts and Sustainability of Independent Power Projects

Run-of-River Hydropower in BC A Citizen s Guide to Understanding Approvals, Impacts and Sustainability of Independent Power Projects Run-of-River Hydropower in BC A Citizen s Guide to Understanding Approvals, Impacts and Sustainability of Independent Power Projects Watching out for BC s Wild Salmon Watershed Watch Salmon Society Coquitlam,

More information