2007 Follow-Up Report on the Audit of Information Technology January 2005

Size: px
Start display at page:

Download "2007 Follow-Up Report on the Audit of Information Technology January 2005"

Transcription

1 2007 Follow-Up Report on the Audit of Information Technology January 2005 Natural Sciences & Engineering Research Council of Canada & Social Sciences & Humanities Research Council of Canada October 2007

2 Follow-up Report on the Audit of Information Technology Introduction In accordance with NSERC SSHRC s annual plan for internal audit, a follow-up audit of the 2005 Audit of Information Technology occurred. This report presents the observations and findings of the follow-up audit. Being a follow-up audit, the focus was the actions taken in response to recommendations made in Objectives and Scope The primary objective and scope of the follow-up audit were to report on the status of the approved management action plans related to the recommendations in the 2005 Audit of Information Technology. Governance was a significant issue raised in the 2005 Audit. In response, management introduced the IM/IT Bi-Council Steering Committee to oversee and provide direction to the IT function. Given the importance of this change, we took the opportunity to observe two meetings of the committee, as a means to comment on and, if appropriate, offer suggestions to improve its operations. Accordingly, the follow-up audit was completed in two phases, coinciding with two meetings of the committee. The first phase commenced in June 2007 and was completed in July 2007, focusing on the status of management responses to audit recommendations. The second phase commenced in September 2007 and was completed in October 2007, allowing us to observe a second meeting of the committee. Approach The follow-up audit was conducted in accordance with the internal auditing standards for the Government of Canada. The approach included: Reviewing the information technology audit report; Reviewing the management action plans related to the recommendations in the audit report; Developing an audit approach for these issues; Interviewing responsible managers and examining pertinent documentation related to the action plan; Observing two meetings of the NSERC - SSHRC IM/IT Bi-Council Steering Committee; Page 2

3 Interviewing or requesting input from executive members of NSERC and SSHRC and the Vice President, CASD; Conducting such tests, as necessary, to assess the effectiveness of current practices; and, Discussing preliminary audit findings, with the Corporate Internal Auditor and the responsible management. Background to the Follow-up Audit The Natural Sciences and Engineering Research Council of Canada (NSERC) and the Social Sciences and Humanities Research Council of Canada (SSHRC) share administrative services through the Common Administrative Services Directorate (CASD). Included in the shared directorate is an Information Services Division (ISD). During 2004, an audit was conducted of Information Technology in the two councils. An audit report, which contained 22 recommendations for the strengthening of the information technology function, was released in January In February 2005, management provided their action plan in response to the recommendations contained in the audit report. Notice to Reader: Since the time of the audit, organizational changes occurred, such that the organization responsible for information services is now the Information Management and Technology Services Division (IMTS). While recommendations and management responses in the original audit report referred to ISD or ITSS, such references have been amended to IMTS in line with current structure. Overall Conclusions Positive progress was observed in response to all recommendations made in the 2005 Audit. As of September 2007, fifteen of the twenty-two 2005 recommendations have been implemented and seven recommendations remain in progress. Our tests confirmed the implementation of management actions, reported as completed, and the accuracy of the status reports for the seven recommendations remaining in-progress. Two recommendations have been made regarding the operations of the IM/IT Bi-Council Steering Committee, as result of the follow-up audit. 1. The Committee should re-instate semi-annual monitoring and reporting of the seven recommendations remaining in-progress, until all are resolved. 2. The Committee should review its terms of reference ensure it complements those of other committees with particular attention to approval of IT Plan and reporting and resolution of non-compliance and risk issues. No further follow-up activity is recommended for Internal Audit regarding the Audit of Information Technology. Page 3

4 Detailed Observations 1. Organizational and Operating Changes In an effort to increase efficiency, the information technology functions for both councils have been centralized under CASD. In mid-2007, an Executive Director, IMTS was hired to oversee the management of the information technology (IT) function. In addition to the organizational changes, information technology has been striving to better focus their resources by reducing and consolidating the number of projects they are committed to delivering. Approximately two years ago, annual project lists included over 200 projects. This number has been significantly reduced and is now less than half that number. To better address users needs, further consolidation of IT projects and increased use of commercial off-the-shelf products are planned. 2. Monitoring of Implementation of Recommendations For the first two years subsequent to the release of the January 2005 audit report, IMTS regularly monitored progress on the implementation of the audit recommendations. Progress updates were recorded as of June 2005, October 2005, February 2006 and October 2006, (the last update performed). 3. Accuracy of Progress Monitoring During the follow-up audit, documentary evidence was requested to support the progress reported for each recommendation in the October 2006 progress update. The reporting of progress was found to be accurate. The evidence obtained, relative to the current status of the implementation of each recommendation, supported the information provided in the October 2006 progress update. 4. Current Status of Recommendations As of September 2007, fifteen of the twenty-two 2005 recommendations have been implemented and seven recommendations remain in progress. Some of the key initiatives which have been implemented include: The establishment of the IM/IT Bi-Council Steering Committee; The production of a multi-year Bi-Council technological vision; The development of a comprehensive Threat and Risk Assessment of the IT infrastructure environment; The implementation of a template which requires the completion of Threat and Risk Assessments for each new system initiative; and, Page 4

5 The completion of a TBS required, Management of IT Security (MITS) compliance assessment. Appendix A provides detailed information on the in-progress audit recommendations. 5. Governance and Risk Management At the current time, governance structures at NSERC-SSHRC are under review. This review of governance structures may present opportunities to increase the effectiveness of information technology through strengthened oversight arrangements. It was noted that several committees appear to have an advisory capacity with regards to information technology. What was not as clear is how the information technology plans and objectives directly relate to the NSERC- SSHRC multi-year strategic plans and who approves the information technology project plan. Another element which was not clearly enunciated in committee terms of reference was who is accountable for monitoring and managing IT risks in the Councils. With regards to risk, two core information technology documents were completed in 2007, a comprehensive Threat and Risk Assessment of Information Technology Infrastructure and a required Treasury Board Secretariat questionnaire on the Management of IT Security (this information is used by TBS to monitor departmental and government-wide compliance with government IT security requirements). The Threat and Risk Assessment identified six areas of medium risk to be addressed and the Management of IT Security (MITS) questionnaire identified fourteen points of non-compliance within the Councils. 6. Cost /Benefit Assessments During the conduct of the follow-up audit, full costs for information technology projects were not available. IMTS is working towards this goal by assigning salary and other than salary costs to IT projects. Page 5

6 Follow-up Audit Recommendations & Management Responses 1. Continued Monitoring It is recommended that the IM/IT Bi-Council Steering Committee re-instate semi-annual monitoring and reporting of the seven recommendations, which are still in progress until all are resolved. Management Response Response: Action: Management agrees with recommendations as stated. The IM/IT Bi-Council Steering Committee will add an IT Audit Update item to its agenda for the first and third meeting of each fiscal year until all recommendations are completely resolved. 2. Governance and Risk Management In conjunction with the internal reviews of governance, it is recommended that the IM/IT Bi- Council Steering Committee review the various committees terms of reference to ensure that respective roles relative to information technology of the various executive and management committees are clear and complement those of the IM/IT Bi-Council Steering Committee, particularly as they relate to: A. Approving the IT Plan and its revision (the list of projects that IT resources can be devoted to and the process to be followed to add or remove projects). B. Identifying and agreeing on which committee(s) is to be informed of the existence and disposition of non-compliance and risk issues. Management Response Response: Action A: Action B: Management agrees with recommendations as stated. The IM/IT Bi-Council Steering Committee will ensure that the responsibility and accountability for approving and maintaining the annual IT Plan is appropriately referenced within its Terms of Reference. The IM/IT Bi-Council Steering Committee will ensure that the responsibility and accountability for addressing IT non-compliance and risk issues are communicated to and acted upon by the appropriate committee(s) subsequent to the completion of the internal reviews of governance. Page 6

7 ORIGINAL RECOMMENDATIONS IT Policies In collaboration with the Administration Division, IMTS should identify the IT areas to be covered by IT policies, assign a priority and a development schedule to each new policy, develop each one according to the established timeline, present them to the IM/IT steering committee for approval, and develop a roll out strategy to cover the communication to staff and posting on the Intranet Service Level Agreements IMTS should review its SLA (Service Level Agreement) and identify performance targets for Network Administration, System Development, Helpdesk Services, Internet and Intranet. These performance targets need to be negotiated with the clients, included in a revised SLA, monitored for compliance, reported on a regular basis, and communicated to the IT Steering Committee. Appendix A FOLLOW-UP AUDIT Information on In-Progress Recommendations STATUS OF IN-PROGRESS RECOMMENDATIONS As of October 2005, IMTS had established an ongoing process for identifying and documenting new IT policies which included: Identifying new IT policy requirements at the IMTS Managers annual planning retreat; In collaboration with the Administration Division, identifying potential overlap between IT and Administration policies, assigning priorities, preparing development schedules and documenting the policies; and Developing a rollout strategy. At that time, the need for an Information Management Policy, requiring collaboration between IT and Administration was been identified. Prior to the creation of the IM/IT Steering Committee, there did not appear to be a governance body in the Bi-Council with a mandate to review and approve IM/IT polices for NSERC-SSHRC. However, a committee governance review is currently underway within both Councils. The results of these reviews are expected to set clear roles and responsibilities that will account for the IM/IT related policy review and approvals. IMTS indicate that their existing Service Level Agreement (SLA) has required updating since They are in the process of subdividing this generic agreement into more specific service SLA's. Throughout IMTS plan to create 2 new specific SLA's - one for Corporate Application Support services, and another for Electronic Business Solution Development services. The existing SLA would then be updated to remove reference to those services that will have their own more specific client SLA. An IMTS Corporate System Development SLA was drafted in July 2007 and IMTS plans to complete both new SLA s by the end of 07/08. In the interim, the ebusiness Support for External Clients document, while not a formal SLA, does serve as a service commitment by the On-line Service Helpdesk to the external user community. This document will be rolled into the Electronic Business Solution Development services SLA. Page 7

8 ORIGINAL RECOMMENDATIONS Tracking Incidents and Requests IMTS should investigate the advantages of endorsing a more comprehensive incident tracking system and maintaining a single database for all service requests. Appendix A FOLLOW-UP AUDIT Information on In-Progress Recommendations STATUS OF IN-PROGRESS RECOMMENDATIONS This project is to provide a common, single ITIL (Information Technology Infrastructure Library) compliant tool to assist in performing incident, problem, configuration, change, release and service level management and associated reporting. This tool will replace the in-house built inventory management system and will also be made available to divisions outside of Information Technology and Support Services Division as required, for example within Admin at their own helpdesk, at IM and for the purchasing section in Admin. This is a multi-year project with 3 phases. Phase 1 is the deployment of incident and request management and is complete. Phase 2 is the deployment of Change, Release and Configuration management modules started in September Phase 3 will complete the project with Service Level management, Problem management and basic financial management modules Escalation Process IMTS should institute a formal escalation process to solve more complex problems. This project involves defining and revising the internal processes associated with each module in order to apply industry best practices. ITIL is the IT Infrastructure Library and it is a framework of best practice approaches intended to facilitate the delivery of high quality IT services. Same as 8.2 Page 8

9 ORIGINAL RECOMMENDATIONS Help Desk Accountability IMTS should review the accountability of the IMTS internal Help Desk and the ebusiness ESD Help Desk (On-Line Service Help Desk) groups to ensure that each group becomes accountable to track and monitor the escalated problems until full resolution Monitor Performance Appendix A FOLLOW-UP AUDIT Information on In-Progress Recommendations STATUS OF IN-PROGRESS RECOMMENDATIONS Same as 8.2 IMTS should monitor the performance targets specified in the SLA Performance Reports IMTS should ensure that performance reports are produced to measure the attainments of objectives stated in the SLA. Same as 8.2 Same as 8.2 Page 9

AUDIT OF INFORMATION TECHNOLOGY Management (Action Plan) Responses February 2005 # PRIORITY DESCRIPTION MANAGEMENT RESPONSE

AUDIT OF INFORMATION TECHNOLOGY Management (Action Plan) Responses February 2005 # PRIORITY DESCRIPTION MANAGEMENT RESPONSE AUDIT OF INFORMATION TECHNOLOGY Management (Action Plan) Responses February 2005 # PRIORITY DESCRIPTION MANAGEMENT RESPONSE Ref: Chapter 3.1 GOVERNANCE FRAMEWORK Information Technology Steering Committee

More information

NSERC SSHRC AUDIT OF IT SECURITY Corporate Internal Audit Division

NSERC SSHRC AUDIT OF IT SECURITY Corporate Internal Audit Division AUDIT OF IT SECURITY Corporate Internal Audit Division Natural Sciences and Engineering Research Council of Canada Social Sciences and Humanities Research Council of Canada September 20, 2012 Corporate

More information

Internal Audit Manual

Internal Audit Manual Internal Audit Manual Version 1.0 AUDIT AND EVALUATION SECTOR AUDIT AND ASSURANCE SERVICES BRANCH INDIAN AND NORTHERN AFFAIRS CANADA April 25, 2008 #933907 Acknowledgements The Institute of Internal Auditors

More information

AUDIT OF INFORMATION TECHNOLOGY FINAL REPORT. Addressed to:

AUDIT OF INFORMATION TECHNOLOGY FINAL REPORT. Addressed to: AUDIT OF INFORMATION TECHNOLOGY FINAL REPORT Addressed to: Natural Sciences and Engineering Research Council of Canada (NSERC) Social Sciences and Humanities Research Council of Canada (SSHRC) Presented

More information

SSHRC Management Response to Review of AMIS

SSHRC Management Response to Review of AMIS SSHRC Management Response to Review of AMIS The attached table provides a detailed management response to Deloitte s April 2006 review of the Awards Management Information System (AMIS). Background and

More information

EXECUTIVE SUMMARY...5

EXECUTIVE SUMMARY...5 Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9

More information

Audit of the Management of Projects within Employment and Social Development Canada

Audit of the Management of Projects within Employment and Social Development Canada Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can

More information

Audit of Contract Management Practices in the Common Administrative Services Directorate (CASD)

Audit of Contract Management Practices in the Common Administrative Services Directorate (CASD) Audit of Contract Management Practices in the Common Administrative Services Directorate (CASD) AUDIT REPORT Prepared for NSERC (Natural Sciences and Engineering Research Council) and SSHRC (Social Science

More information

august09 tpp 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

august09 tpp 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper august09 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface Corporate governance - which refers broadly to the processes

More information

ISO 20000-1:2005 Requirements Summary

ISO 20000-1:2005 Requirements Summary Contents 3. Requirements for a Management System... 3 3.1 Management Responsibility... 3 3.2 Documentation Requirements... 3 3.3 Competence, Awareness, and Training... 4 4. Planning and Implementing Service

More information

Final Audit Report. Audit of the Human Resources Management Information System. December 2013. Canada

Final Audit Report. Audit of the Human Resources Management Information System. December 2013. Canada Final Audit Report Audit of the Human Resources Management Information System December 2013 Canada Table of Contents Executive summary... i A - Introduction... 1 1. Background... 1 2. Audit objective...

More information

Office of the Chief Information Officer

Office of the Chief Information Officer Office of the Chief Information Officer Business Plan: 2012 2015 Department / Ministère: Executive Council Date: November 15, 2012 1 P a g e This Page Left Intentionally Blank 2 P a g e Contents The Business

More information

Audit of Physical Security Management

Audit of Physical Security Management Audit of Physical Security Management Natural Sciences and Engineering Research Council of Canada Social Sciences and Humanities Research Council Approved by the President on March 18, 2015 1 Her Majesty

More information

REPORT 2014/001 INTERNAL AUDIT DIVISION. Audit of information and communications technology help desk operations at United Nations Headquarters

REPORT 2014/001 INTERNAL AUDIT DIVISION. Audit of information and communications technology help desk operations at United Nations Headquarters INTERNAL AUDIT DIVISION REPORT 2014/001 Audit of information and communications technology help desk operations at United Nations Headquarters Overall results relating to the adequacy and effectiveness

More information

A&CS Assurance Review. Accounting Policy Division Rule Making Participation in Standard Setting. Report

A&CS Assurance Review. Accounting Policy Division Rule Making Participation in Standard Setting. Report A&CS Assurance Review Accounting Policy Division Rule Making Participation in Standard Setting Report April 2010 Table of Contents Background... 1 Engagement Objectives, Scope and Approach... 1 Overall

More information

Audit of IT Asset Management Report

Audit of IT Asset Management Report Audit of IT Asset Management Report Recommended by the Departmental Audit Committee for approval by the President on Approved by the President on September 4, 2012 e-doc : 3854899 1 Table of Contents EXECUTIVE

More information

Audit of the Test of Design of Entity-Level Controls

Audit of the Test of Design of Entity-Level Controls Audit of the Test of Design of Entity-Level Controls Canadian Grain Commission Audit & Evaluation Services Final Report March 2012 Canadian Grain Commission 0 Entity Level Controls 2011 Table of Contents

More information

Audit of Financial Management Governance. Audit Report

Audit of Financial Management Governance. Audit Report Audit of Financial Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 2 What we examined... 2 Why it is important... 2 What we found... 2 Background... 4 Objective...

More information

Service Level Agreement

Service Level Agreement Template SDSU-TPL-11085 v2 20/1/11 IT Services Service Level Agreement HR Management System -SAP (HRMS) Document Ref: DSLAHRMS Version: 0.3 24/03/2011 Contents 1 INTRODUCTION... 4 1.1 Service Outline...

More information

Status Report of the Auditor General of Canada to the House of Commons

Status Report of the Auditor General of Canada to the House of Commons 2011 Status Report of the Auditor General of Canada to the House of Commons Chapter 1 Financial Management and Control and Risk Management Office of the Auditor General of Canada The 2011 Status Report

More information

Chapter 5. Planning the Audit Engagement

Chapter 5. Planning the Audit Engagement Chapter 5 Planning the Audit Engagement A. Purpose for Planning the Engagement Engagement planning is performed to provide a means for developing an understanding of the business objectives of the auditee,

More information

Migration Planning Guidance (Draft)

Migration Planning Guidance (Draft) Financial Management Line of Business Migration Planning Guidance (Draft) Section 1.1 Overview The purpose of the Migration Planning Guidance document is to help agencies prepare for, and manage, a migration

More information

Identifying & Implementing Quick Wins

Identifying & Implementing Quick Wins Identifying & Implementing Quick Wins 1 Executive Summary........3 2 Introduction....... 5 3 Key Steps to Quick Wins....... 7 4 Sample Quick Wins...8 4.1 People Quick Wins... 8 4.2 Process Quick Wins......9

More information

RISK MANAGEMENT POLICY (Revised October 2015)

RISK MANAGEMENT POLICY (Revised October 2015) UNIVERSITY OF LEICESTER RISK MANAGEMENT POLICY (Revised October 2015) 1. This risk management policy ( the policy ) forms part of the University s internal control and corporate governance arrangements.

More information

PUBLIC SERVICE COMMISSION AUDIT REPORTS 2012

PUBLIC SERVICE COMMISSION AUDIT REPORTS 2012 PUBLIC SERVICE COMMISSION AUDIT REPORTS 2012 All of the audit work in this publication was conducted in accordance with the legislative mandate and audit policies of the Public Service Commission of Canada.

More information

ACTION PLAN IMPLEMENTATION STATUS UPDATE REPORT TO THE AUDIT COMMITTEE - AS OF SEPTEMBER 30, 2011

ACTION PLAN IMPLEMENTATION STATUS UPDATE REPORT TO THE AUDIT COMMITTEE - AS OF SEPTEMBER 30, 2011 APPROVAL : 24/09/10 1. The CFO, in collaboration with the ADMs responsible for regional operations and staff, should develop and implement a program that ensures sufficient resources are allocated to providing

More information

IT Infrastructure Audit

IT Infrastructure Audit IT Infrastructure Audit Office of the Chief Audit and Evaluation Executive Audit and Assurance Services Directorate June 2011 Cette publication est également disponible en français. This publication is

More information

Version 1.0. IT Service Management & IT Asset Management Services (ITSM & ITAM Services) Governance Process

Version 1.0. IT Service Management & IT Asset Management Services (ITSM & ITAM Services) Governance Process Version 1.0 IT Service Management & IT Asset Management Services (ITSM & ITAM Services) Governance Process Table of Contents 1 Planning and Organization... 6 1.1 Executive Overview... 6 1.1.1 ITSM & ITAM

More information

Why are PMO s are Needed on Large Projects?

Why are PMO s are Needed on Large Projects? Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects

More information

STATE OF ARIZONA OFFICE OF THE AUDITOR GENERAL. April 1, 2008

STATE OF ARIZONA OFFICE OF THE AUDITOR GENERAL. April 1, 2008 DEBRA K. DAVENPORT, CPA AUDITOR GENERAL STATE OF ARIZONA OFFICE OF THE AUDITOR GENERAL WILLIAM THOMSON DEPUTY AUDITOR GENERAL April 1, 2008 The Honorable John Nelson, Chair Joint Legislative Audit Committee

More information

GUIDELINES FOR ACADEMIC PROGRAM REVIEW For self-studies due to the Office of the Provost on October 1, 2015 CENTERS

GUIDELINES FOR ACADEMIC PROGRAM REVIEW For self-studies due to the Office of the Provost on October 1, 2015 CENTERS GUIDELINES FOR ACADEMIC PROGRAM REVIEW For self-studies due to the Office of the Provost on October 1, 2015 CENTERS OVERVIEW OF PROGRAM REVIEW At Illinois State University, primary responsibility for maintaining

More information

Health Information Management Module. Annual Review. Internal Audit Branch 378-1-233. Approved by Audit Committee

Health Information Management Module. Annual Review. Internal Audit Branch 378-1-233. Approved by Audit Committee Health Information Management Module Annual Review Internal Audit Branch 378-1-233 Approved by Audit Committee September 25 th, 2007 Table of Contents Executive Summary... i 1.0 Background...1 2.0 Objective

More information

Major IT Projects: Continue Expanding Oversight and Strengthen Accountability

Major IT Projects: Continue Expanding Oversight and Strengthen Accountability Secretary of State Audit Report Jeanne P. Atkins, Secretary of State Gary Blackmer, Director, Audits Division Major IT Projects: Continue Expanding Oversight and Strengthen Accountability Summary Information

More information

Guidance on the Governance and Management of Evaluations of Horizontal Initiatives

Guidance on the Governance and Management of Evaluations of Horizontal Initiatives Guidance on the Governance and Management of Evaluations of Horizontal Initiatives Centre of Excellence for Evaluation Expenditure Management Sector Treasury Board of Canada Secretariat Her Majesty the

More information

Audit of Community Futures Program

Audit of Community Futures Program Audit of Community Futures Program WESTERN ECONOMIC DIVERSIFICATION CANADA Audit, Evaluation & Disclosure Branch April 2009 Table of Contents 1.0 EXECUTIVE SUMMARY 1 2.0 STATEMENT OF ASSURANCE 2 3. 0 INTRODUCTION

More information

Audit of Procurement Practices

Audit of Procurement Practices Audit Report Audit of Procurement Practices Audit and Evaluation Directorate April 2014 TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 INTRODUCTION... 5 Background... 5 Risk Assessment... 5 Objective and Criteria...

More information

Audit of the Post-Secondary Education Program

Audit of the Post-Secondary Education Program #1729764 Indian and Northern Affairs Canada Audit of the Post-Secondary Education Program Prepared by: Audit and Assurance Services Branch Project #07/20 January 23, 2009 Table of Contents Initialisms

More information

Fermilab Computing Division Service Level Management Process & Procedures Document

Fermilab Computing Division Service Level Management Process & Procedures Document BMC Software Consulting Services Fermilab Computing Division Process & Procedures Document Client: Fermilab Date : 07/07/2009 Version : 1.0 1. GENERAL Description Purpose Applicable to Supersedes This

More information

OFFICE OF THE PRIVACY COMMISSIONER OF CANADA. Audit of Human Resource Management

OFFICE OF THE PRIVACY COMMISSIONER OF CANADA. Audit of Human Resource Management OFFICE OF THE PRIVACY COMMISSIONER OF CANADA Audit of Human Resource Management May 13, 2010 Prepared by the Centre for Public Management Inc. TABLE OF CONTENTS 1.0 Executive Summary... 2 2.0 Background...

More information

OF CPAB INSPECTION FINDINGS

OF CPAB INSPECTION FINDINGS PROTOCOL FOR AUDIT FIRM COMMUNICATION OF CPAB INSPECTION FINDINGS WITH AUDIT COMMITTEES CONSULTATION PAPER NOVEMBER 2013 The Canadian Public Accountability Board ( CPAB ) is requesting comments on the

More information

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope Activity Code 24010 B-1 Planning Considerations Estimating System Survey (ICR) Purpose and Scope The major objectives of this audit are to: Evaluate the adequacy of and the contractor s compliance with

More information

Social Sciences and Humanities Research Council of Canada

Social Sciences and Humanities Research Council of Canada Social Sciences and Humanities Research Council of Canada Annex to the Statement of Management Responsibility including Internal Control over Financial Reporting (Unaudited) Fiscal year 2014-15 Table of

More information

Internal Audit Report ITS CHANGE MANAGEMENT PROCESS. Report No. SC-11-11

Internal Audit Report ITS CHANGE MANAGEMENT PROCESS. Report No. SC-11-11 Internal Audit Report ITS CHANGE MANAGEMENT PROCESS Report No. SC-11-11 March 2011 SANTA CRUZ: INTERNAL AUDIT March 31, 2011 MARY DOYLE Vice Chancellor Information Technology Re: Internal Audit Report

More information

This page was intentionally left blank.

This page was intentionally left blank. This page was intentionally left blank. Summary of Significant Changes SUMMARY OF SIGNIFICANT CHANGES The Business Systems Review (BSR) Guide has been revised to reflect recent significant changes and

More information

J u n e 2 0 1 0. N a t i o n a l R e s e a r c h C o u n c i l C a n a d a. I n t e r n a l A u d i t, N R C. Audit of Risk Management.

J u n e 2 0 1 0. N a t i o n a l R e s e a r c h C o u n c i l C a n a d a. I n t e r n a l A u d i t, N R C. Audit of Risk Management. N a t i o n a l R e s e a r c h C o u n c i l C a n a d a Audit of Risk Management I n t e r n a l A u d i t, N R C J u n e 2 0 1 0 June 2010 i 1.0 Executive Summary and Conclusion Background This audit

More information

Audit Report: Most Contracts Executed Timely but Contract Project Managers Could Use Better Tools and Guidance

Audit Report: Most Contracts Executed Timely but Contract Project Managers Could Use Better Tools and Guidance Office of the City Auditor CONSENT CALENDAR October 6, 2015 To: From: Honorable Mayor and Members of the City Council Ann-Marie Hogan, City Auditor Submitted by: Ann-Marie Hogan, City Auditor Subject:

More information

ITIL Roles Descriptions

ITIL Roles Descriptions ITIL Roles s Role Process Liaison Incident Analyst Operations Assurance Analyst Infrastructure Solution Architect Problem Manager Problem Owner Change Manager Change Owner CAB Member Release Analyst Test

More information

Internal Audit Quality Assessment. Presented To: World Intellectual Property Organization

Internal Audit Quality Assessment. Presented To: World Intellectual Property Organization Internal Audit Quality Assessment Presented To: World Intellectual Property Organization April 2014 Table of Contents List of Acronyms 3 Page Executive Summary Opinion as to Conformance to the Standards,

More information

Audit Report. Effectiveness of IT Controls at the Global Fund Follow-up report. GF-OIG-15-20b 26 November 2015 Geneva, Switzerland

Audit Report. Effectiveness of IT Controls at the Global Fund Follow-up report. GF-OIG-15-20b 26 November 2015 Geneva, Switzerland Audit Report Effectiveness of IT Controls at the Global Fund Follow-up report GF-OIG-15-20b Geneva, Switzerland Table of Contents I. Background and scope... 3 II. Executive Summary... 4 III. Status of

More information

Final Audit Report. Follow-up Audit of Information Technology Asset Management. January 2013. Canada

Final Audit Report. Follow-up Audit of Information Technology Asset Management. January 2013. Canada Final Audit Report Follow-up Audit of Information Technology Asset Management January 2013 Canada Table of Contents Executive summary... i A - Introduction... 1 1. Background... 1 2. Audit objective...

More information

Audit of Policy on Internal Control Information Technology General Controls (ITGCs) Audit

Audit of Policy on Internal Control Information Technology General Controls (ITGCs) Audit D.2.1D Audit of Policy on Internal Control Information Technology General Controls (ITGCs) Audit Office of the Chief Audit Executive Audit and Assurance Services Directorate March 2015 Cette publication

More information

Unifying IT How Dell Is Using BMC

Unifying IT How Dell Is Using BMC Unifying IT Management: How Dell Is Using BMC Software to Implement ITIL ABSTRACT Companies are looking for ways to maximize the efficiency with which they plan, deliver, and manage technology services.

More information

FORUM ON TAX ADMINISTRATION

FORUM ON TAX ADMINISTRATION ORGANISATION FOR ECONOMIC CO-OPERATION AND DEVELOPMENT FORUM ON TAX ADMINISTRATION Tax Administration Guidance & Information Series January 2008 CENTRE FOR TAX POLICY AND ADMINISTRATION Dear Colleagues,

More information

2012 Audit Plan. Finance, Audit and Facilities Committee Board of Regents. November 2011 ATTACHMENT

2012 Audit Plan. Finance, Audit and Facilities Committee Board of Regents. November 2011 ATTACHMENT 2012 Audit Plan Finance, Audit and Facilities Committee Board of Regents November 2011 ATTACHMENT Table of Contents Executive Summary...1 2012 Audit Plan...2 Analysis of Coverage of University Auditable

More information

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION Desktop and Laptop Software License Management June 25, 2013 Reference Number: 2013-20-025 This report has cleared the Treasury Inspector General for Tax

More information

Audit of Occupational Safety and Health (OSH)

Audit of Occupational Safety and Health (OSH) National Research Council Canada Audit of Occupational Safety and Health (OSH) Internal Audit, NRC SEPTEMBER 2010 1.0 Executive Summary and Conclusion Background This report presents the findings of the

More information

Grant Monitoring. Curriculum developed by the Office of Grants Management and Nonprofits Assistance Fund

Grant Monitoring. Curriculum developed by the Office of Grants Management and Nonprofits Assistance Fund Grant Monitoring Curriculum developed by the Office of Grants Management and Nonprofits Assistance Fund Who We Are The mission of Admin's Office of Grants Management is to standardize, streamline and improve

More information

Funds Management Governance Framework

Funds Management Governance Framework Funds Management Governance Framework DEPARTMENT OF FINANCE BANK OF CANADA October 2007 Table of Contents Purpose 2 CHAPTER 1 Funds Management Objectives 4 TABLE OF ANNEXES 32 - Financial Asset and Liability

More information

Kentucky IT Infrastructure Library (ITIL) Program

Kentucky IT Infrastructure Library (ITIL) Program 2006 NASCIO Recognition Awards Nomination Category: Enterprise IT Management Initiatives Kentucky IT Infrastructure Library (ITIL) Program Commonwealth Office of Technology. KentuckyUnbridledSpirit.com

More information

ASSISTANT PAYROLL ADMINISTRATOR (PS100952) This position is located at the San Rafael Administration Building

ASSISTANT PAYROLL ADMINISTRATOR (PS100952) This position is located at the San Rafael Administration Building POSITION: SALARY RANGE: ASSISTANT PAYROLL ADMINISTRATOR (PS100952) This position is located at the San Rafael Administration Building $69,673.50 to $84,201.00 plus excellent benefits (37.5 hour workweek)

More information

Organization. Project Name. Project Overview Plan Version # Date

Organization. Project Name. Project Overview Plan Version # Date Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents

More information

The ITIL v.3. Foundation Examination

The ITIL v.3. Foundation Examination The ITIL v.3. Foundation Examination ITIL v. 3 Foundation Examination: Sample Paper 3, version 3.0 Multiple Choice Instructions 1. All 40 questions should be attempted. 2. There are no trick questions.

More information

Superseded by T MU AM 04001 PL v2.0

Superseded by T MU AM 04001 PL v2.0 Plan T MU AM 04001 PL TfNSW Configuration Management Plan Important Warning This document is one of a set of standards developed solely and specifically for use on the rail network owned or managed by

More information

QUALITY MANAGEMENT POLICY & PROCEDURES

QUALITY MANAGEMENT POLICY & PROCEDURES QUALITY MANAGEMENT POLICY & PROCEDURES Policy Statement Cotleigh Engineering Co. Limited specialises in the recruitment of engineering & technical personnel in the oil & energy, rail, civil engineering,

More information

Office of the Auditor General of Canada. Internal Audit of Document Management Through PROxI Implementation. July 2014

Office of the Auditor General of Canada. Internal Audit of Document Management Through PROxI Implementation. July 2014 Office of the Auditor General of Canada Internal Audit of Document Management Through PROxI Implementation July 2014 Practice Review and Internal Audit Her Majesty the Queen in Right of Canada, represented

More information

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION

TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION Lack of Proper IRS Oversight of the Department of the Treasury HSPD-12 Initiative Resulted in Misuse of Federal Government December 14, 2007 Reference

More information

Audit of Project Management Governance. Audit Report

Audit of Project Management Governance. Audit Report Audit of Project Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 3 What we examined... 3 Why it is important... 3 What we found... 3 Background... 5 Objective... 6

More information

INFORMATION MANAGEMENT

INFORMATION MANAGEMENT United States Government Accountability Office Report to the Committee on Homeland Security and Governmental Affairs, U.S. Senate May 2015 INFORMATION MANAGEMENT Additional Actions Are Needed to Meet Requirements

More information

AUDIT OF READINESS FOR THE IMPLEMENTATION OF THE POLICY ON INTERNAL CONTROL

AUDIT OF READINESS FOR THE IMPLEMENTATION OF THE POLICY ON INTERNAL CONTROL AUDIT OF READINESS FOR THE IMPLEMENTATION OF THE POLICY ON INTERNAL CONTROL AUDIT REPORT JUNE 2010 TABLE OF CONTENTS EXCUTIVE SUMMARY... 3 1 INTRODUCTION... 5 1.1 AUDIT OBJECTIVE. 5 1.2 SCOPE...5 1.3 SUMMARY

More information

Baker Tilly simplifies Windows 7 deployment with CA Technologies solutions

Baker Tilly simplifies Windows 7 deployment with CA Technologies solutions Customer success story Baker Tilly simplifies Windows 7 deployment with CA Technologies solutions Customer profile Industry: Professional services Company: Baker Tilly Employees: 2,400 Revenue: 204 million

More information

Final Report. Audit of the Project Management Framework. December 2014

Final Report. Audit of the Project Management Framework. December 2014 Final Report Audit of the Project Management Framework December 2014 Audit of the Project Management Framework Table of Contents Executive summary... i A - Introduction... 1 1. Background... 1 2. Audit

More information

Saskatchewan. Provincial Budget. Performance Plan. Information Technology Office

Saskatchewan. Provincial Budget. Performance Plan. Information Technology Office 2006 2007 Saskatchewan Provincial Budget Performance Plan Information Technology Office Minister s Message As the Minister Responsible for Information Technology, it is my pleasure to present the Information

More information

Audit of the Data Center Consolidation Initiative at NARA. OIG Draft Audit Report No. 12-09. May 10, 2012

Audit of the Data Center Consolidation Initiative at NARA. OIG Draft Audit Report No. 12-09. May 10, 2012 Audit of the Data Center Consolidation Initiative at NARA OIG Draft Audit Report No. 12-09 May 10, 2012 Table of Contents Executive Summary... 3 Background... 4 Objectives, Scope, Methodology... 7 Audit

More information

Administrative Directive

Administrative Directive Administrative Directive Title: Grant Management Index Number: AD 1.05 Date of Adoption: 09/06/94 Date of Revision: 06/30/2006 Page: 1 of 8 1.0 Purpose and Need Grant funds from state, federal, or other

More information

Sales & Operations Planning Process Excellence Program

Sales & Operations Planning Process Excellence Program Chemical Sector We make it happen. Better. Sales & Operations Planning Process Excellence Program Engagement Summary November 2014 S&OP Excellence Robust discussions creating valuable ideas Engagement

More information

Audit of the Enterprise Awards Management System (EAMS) Project

Audit of the Enterprise Awards Management System (EAMS) Project Audit of the Enterprise Awards Management System (EAMS) Project (CIAD), NSERC/ August 31, 2010 1 TABLE OF CONTENTS TABLE OF CONTENTS...2 EXECUTIVE SUMMARY...3 1. PROJECT BACKGROUND... 6 2. AUDIT OBJECTIVE

More information

Service Improvement Plan. DRAFT v.0.1. Harrow IT Services

Service Improvement Plan. DRAFT v.0.1. Harrow IT Services Harrow IT Services Service Improvement Plan DRAFT v.0.1 Harrow IT Services October 20 Contents 1. Introduction... Error! Bookmark not defined. 2. The Vision for HITS... Error! Bookmark not defined. 3.

More information

John Keel, CPA State Auditor. An Audit Report on The Dam Safety Program at the Commission on Environmental Quality. May 2008 Report No.

John Keel, CPA State Auditor. An Audit Report on The Dam Safety Program at the Commission on Environmental Quality. May 2008 Report No. John Keel, CPA State Auditor An Audit Report on The Dam Safety Program at the Commission on Environmental Quality Report No. 08-032 An Audit Report on The Dam Safety Program at the Commission on Environmental

More information

Algonquin and Lakeshore Catholic District School Board

Algonquin and Lakeshore Catholic District School Board Ministry of Education Algonquin and Lakeshore Catholic District School Board Follow-up Report to the Operational Review January 2012 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. STATUS AND IMPLEMENTATION

More information

The Department for Business, Innovation and Skills IMA Action Plan PRIORITY RECOMMENDATIONS

The Department for Business, Innovation and Skills IMA Action Plan PRIORITY RECOMMENDATIONS PRIORITY RECOMMENDATIONS R1 BIS to elevate the profile of information risk in support of KIM strategy aims for the protection, management and exploitation of information. This would be supported by: Establishing

More information

York Catholic District School Board

York Catholic District School Board Ministry of Education York Catholic District School Board Follow-up Report to the Operational Review August 2012 TABLE OF CONTENTS 1. INTRODUCTION... 1 2. STATUS AND IMPLEMENTATION UPDATE... 3 3. GOVERNANCE

More information

Page 1 of 8. Any change, which meets the following criteria, will be managed using IM/IT Change Management Process.

Page 1 of 8. Any change, which meets the following criteria, will be managed using IM/IT Change Management Process. Page 1 of 8 1. Introduction This policy describes the Authority s Information Management/Information Technology (IM/IT) change management procedures. IM/IT manages changes to applications, infrastructure

More information

Internal Audit Checklist

Internal Audit Checklist Internal Audit Checklist 4.2 Policy Verify required elements Verify management commitment Verify available to the public Verify implementation by tracing links back to policy statement Check review/revisions

More information

Governance and Audit Committee 23 November 2015

Governance and Audit Committee 23 November 2015 Agenda Item 7 Governance and Audit Committee 23 November 2015 Welland Internal Audit Consortium Internal Audit Plan & Performance Update 2015/16 Purpose of report: To provide Members with information on

More information

Project Charter Updated

Project Charter Updated Enterprise IT Service Management Pilot Proof of Concept Project Charter Updated Prepared By: M. Riley & J. Foster Date of Publication: March 13, 2006 Date Last Revised: April 25, 2007 PMO CH1, 8/01 Document

More information

Internal Quality Assurance Arrangements

Internal Quality Assurance Arrangements National Commission for Academic Accreditation & Assessment Handbook for Quality Assurance and Accreditation in Saudi Arabia PART 2 Internal Quality Assurance Arrangements Version 2.0 Internal Quality

More information

Network Resource Management Directive

Network Resource Management Directive Office of the Prime Minister Central Information Management Unit Directive document CIMU D 0036:2003 Network Resource Management Directive Version: 1.0 Effective date: 10.12.2003 Table of Contents 1. Purpose...3

More information

Audit of the Policy on Internal Control Implementation

Audit of the Policy on Internal Control Implementation Audit of the Policy on Internal Control Implementation Natural Sciences and Engineering Research Council of Canada Social Sciences and Humanities Research Council of Canada February 18, 2013 1 TABLE OF

More information

Manchester City Council Role Profile. Service Desk Analyst, Grade 6. ICT Service, Corporate Core Directorate Reports to: Team Lead (Service Support)

Manchester City Council Role Profile. Service Desk Analyst, Grade 6. ICT Service, Corporate Core Directorate Reports to: Team Lead (Service Support) Key Role Descriptors: Manchester City Council Role Profile Service Desk Analyst, Grade 6 ICT Service, Corporate Core Directorate Reports to: Team Lead (Service Support) Job Family: Technical The role holder

More information

How To Improve Mainframe Software Asset Management

How To Improve Mainframe Software Asset Management TREASURY INSPECTOR GENERAL FOR TAX ADMINISTRATION The Internal Revenue Service Should Improve Mainframe Software Asset Management February 20, 2014 Reference Number: 2014-20-002 This report has cleared

More information

NSSC Enterprise Service Desk Configuration Management Database (CMDB) Configuration Management Service Delivery Guide

NSSC Enterprise Service Desk Configuration Management Database (CMDB) Configuration Management Service Delivery Guide National Aeronautics and Space Administration NASA Shared Services Center Stennis Space Center, MS 39529-6000 www.nssc.nasa.gov NASA Shared Services Center Version 1.0 NSSC Enterprise Service Desk Configuration

More information

Passenger Protect Program Transport Canada

Passenger Protect Program Transport Canada AUDIT REPORT OF THE PRIVACY COMMISSIONER OF CANADA Passenger Protect Program Transport Canada Section 37 of the Privacy Act 2009 AUDIT OF PASSENGER PROTECT PROGRAM, TRANSPORT CANADA The audit work reported

More information

INTERNAL OVERSIGHT SERVICES INTERNAL OVERSIGHT AND ETHICS OFFICE

INTERNAL OVERSIGHT SERVICES INTERNAL OVERSIGHT AND ETHICS OFFICE INTERNAL OVERSIGHT SERVICES INTERNAL OVERSIGHT AND ETHICS OFFICE SUMMARY OF INTERNAL AUDIT ACTIVITIES AND REPORTS FOR THE REPORTING YEAR ENDING 31 DECEMBER 2014 MARCH 2015 SUMMARY OF INTERNAL AUDIT ACTIVITIES

More information

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting.

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting. Aboriginal Affairs and Northern Development Canada Internal Audit Report Audit of Internal Controls Over Financial Reporting Prepared by: Audit and Assurance Services Branch Project #: 14-05 November 2014

More information

Office of Internal Audit Status Report BOARD OF TRUSTEES

Office of Internal Audit Status Report BOARD OF TRUSTEES Office of Internal Audit Status Report BOARD OF TRUSTEES February 5, 2010 Office of Internal Audit Date: January 13, 2010 To: From: Subject: Board of Trustees and Finance and Audit Committee Allen Vann,

More information

Ministry of the Attorney General. Follow-up to VFM Section 3.02, 2012 Annual Report RECOMMENDATION STATUS OVERVIEW

Ministry of the Attorney General. Follow-up to VFM Section 3.02, 2012 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 4 Section 4.02 Ministry of the Attorney General Criminal Prosecutions Follow-up to VFM Section 3.02, 2012 Annual Report RECOMMENDATION STATUS OVERVIEW # of Status of Actions Recommended Actions

More information

Audit of Business Continuity Audit of Business Planning Continuity Planning

Audit of Business Continuity Audit of Business Planning Continuity Planning Reviewed by CRS in accordance with the Access to Information Act (AIA). Information UNCLASSIFIED Audit of Business Continuity Audit of Business Planning Continuity Planning October 2013 7050-61 (CRS) SECRET

More information

iso20000templates.com

iso20000templates.com iso20000templates.com Public IT Limited 2011 IT Service Policy Document Ref. ITSM01001 Version: 1.0 Draft 1 Document Author: Document Owner: V 1.0 Draft 1 Page 1 of 11 Revision History Version Date RFC

More information

FOLLOW-UP OF PERSONAL COMPUTER LICENSING REPORT NO. 08-04-107F. City of Albuquerque Office of Internal Audit and Investigations

FOLLOW-UP OF PERSONAL COMPUTER LICENSING REPORT NO. 08-04-107F. City of Albuquerque Office of Internal Audit and Investigations FOLLOW-UP OF PERSONAL COMPUTER LICENSING REPORT NO. City of Albuquerque Office of Internal Audit and Investigations City of Albuquerque Office of Internal Audit and Investigations P.O. BOX 1293 ALBUQUERQUE,

More information

Health Facilities Capital Program Manual. Version 1.0

Health Facilities Capital Program Manual. Version 1.0 Health Facilities Capital Program Manual Version 1.0 TABLE OF CONTENTS TABLE OF CONTENTS... 2 1.0 INTRODUCTION... 9 1.1 Health Facilities Capital Program... 9 1.1.1 Major Capital Projects Total Project

More information