OUR ASSURANCE PLAN 2016/17 MARCH Our Assurance Plan 2016/17

Size: px
Start display at page:

Download "OUR ASSURANCE PLAN 2016/17 MARCH 2016. 1 Our Assurance Plan 2016/17"

Transcription

1 OUR ASSURANCE PLAN 2016/17 MARCH Our Assurance Plan 2016/17

2 ABOUT THIS DOCUMENT We publish a range of information about our services and performance. This helps to provide our customers and stakeholders with assurance that we are delivering what they have told us they need and want from their water and sewerage company. It is important that we have robust governance and assurance arrangements in place to ensure that this information is accurate, clear and transparent. In doing so we will continue to provide stakeholders with trust and confidence. These arrangements have been developed in line with Ofwat s company monitoring framework (published in June 2015) which describes how it intends to oversee the information water companies provide to customers over the period The company monitoring framework allows Ofwat to assign each water company to one of three categories of assurance: Self-assurance. Companies that, apart from the base requirements that apply to all companies, have discretion to deliver self-assurance in relation to the additional assurance arrangements they put in place. Targeted assurance. Companies that have not consistently met the high standards that customers and other stakeholders expect are subject to targeted assurance requirements, to ensure that the assurance arrangements they put in place are sufficient to protect customers. Prescribed assurance. Companies that have not provided Ofwat with sufficient confidence about their ability to deliver, monitor and report performance, will have assurance requirements that are prescribed for all information that the company is required to publish, in order to protect customers. Most companies including Northumbrian Water Group (NWG) have initially been assessed for targeted assurance. This means we need to engage closely with our customers and stakeholders to identify key risks and areas of weakness and to consult on our draft assurance plans before publishing final assurance plans. In November 2015, we published our consultation on our risks, strengths and weaknesses and draft assurance plan. This consultation ended on 15 January 2016 and based on the feedback received we committed to publish our assurance plan by the end of March This document sets out NWG s assurance plan for 2016/17. Our assurance plan will be reviewed and updated on an annual basis. 2 Our Assurance Plan 2016/17

3 CONTENTS Who we are 4 of our assurance approach 5 Assurance Framework 7 of our risks, strengths and weaknesses 10 Our Assurance Plan for 2016/ Our Assurance Plan 2016/17

4 WHO WE ARE Northumbrian Water Group provides; Water and sewerage services to 2.7 million people in the north east of England trading as Northumbrian Water. Water services to 1.8 million people in the south east of England trading as Essex & Suffolk Water. Our vision Our vision is to be the national leader in the provision of sustainable water and wastewater services. Our values As important as what we do, is doing it the right way. This is driven by our company values which are: Customer focused. We aim to exceed the expectations of our internal and external customers. Results driven. We take personal responsibility for achieving excellent business results. Ethical. We are open and honest and meet our commitments with a responsible approach to the environment and our communities. Creative. We continuously strive for innovative and better ways to deliver our business. One Team. We work together consistently, promoting co-operation, to achieve our corporate objectives. These values underpin our approach to delivering assurance. 4 Our Assurance Plan 2016/17

5 SUMMARY OF OUR ASSURANCE APPROACH 5 Our Assurance Plan 2016/17

6 SUMMARY OF OUR ASSURANCE APPROACH We have well established governance and assurance arrangements, in the form of an assurance framework, which we use to ensure that our information is of appropriate quality. The diagram overleaf illustrates the tiers of assurance in place at Northumbrian Water, including: Board Oversight. The Board has ownership of the arrangements for governance and assurance of regulatory submissions and reporting. This is monitored and controlled through the Board s Audit Committee and Risk & Compliance Committee with regular reporting by the committees to the Board. Risk Management. We use a data risk assessment, and a risks, strengths and weaknesses review as part of our regulatory reporting processes, to determine levels of risk and target assurance activity. This is a robust and mature process and is embedded within the company s mature risk management processes. The Board sets the tone for risk management, determines the appropriate risk appetite, monitors the management of fundamental risk and approves major decisions affecting the company s risk profile. Management Assurance. Our Management Team implements the Board s strategies and closely monitors performance. This includes ensuring that sufficient and suitable resources (human and financial) are applied to scrutinise performance and identify and manage risk. The Management Team ensure there is appropriate assignment of responsibilities, corporate structures and reporting lines and accountabilities, supported by annual positive assurances on systems and controls. Business Assurance. We have many teams who are separate from the operational activities which monitor, capture and manage the data we report. Specifically this includes our Internal Audit Team. Accountable directly to the Audit Committee, this team provides strong, independent assurance. As such their remit sits across this tier and the following one. Independent Assurance. Our business assurance teams are supplemented with external specialist providers where we require technical and/or external assurance. 6 Our Assurance Plan 2016/17

7 ASSURANCE FRAMEWORK BUSINESS ASSURANCE TEAMS Health, Safety, Environment and Quality Performance and Information Economic Regulation Wastewater Compliance Water Quality Business Continuity Scientific Services Accreditation Team Information Systems Security Internal Audit INDEPENDENT ASSURANCE Numerous external assurance providers including the likes of: Deloitte (financial auditor) AFNOR (external accreditation) KPMG (internal audit co-source partner) External technical auditor (business continuity and regulatory reporting) INDEPENDENT ASSURANCE BUSINESS ASSURANCE TEAMS MANAGEMENT ASSURANCE RISK MANAGEMENT RISK MANAGEMENT BOARD OVERSIGHT ACTIVITIES BOARD OVERSIGHT Board Remuneration Committee Risk and Compliance Committee Audit Committee RISK MANAGEMENT Strategic Risk Model Corporate Risk Model (supported by a strong risk management framework) Detailed Risk Model Data Risk Model Risk Champions Assurance Forum MANAGEMENT ASSURANCE Departmental Compliance Programmes Management Team and its sub-groups Systems Controls 7 Our Assurance Plan 2016/17

8 This assurance framework was applied to our business plan and enabled our Board to satisfy itself that the information associated with the development of our performance commitments was robust. The same framework will apply to the information needed to report our performance against these commitments. A critical part of this framework is our approach to risk management which includes the following steps: Understanding how data for each measure of success is managed from the point at which it is collected in the field, through the way it is collated in order to appear on a final report; Applying a formal risk assessment to each measure of success. This reviews: The likelihood of a reporting error due to the complexity of a performance measure and the manner in which the data is collected. The impact should an error occur, particularly with regard to customers trust and confidence, financial incentives and our reputation. Checks and balances, in the form of data quality controls are used to mitigate risks. These controls may be procedural, audit based, or built into our IT systems. We review the effectiveness of these controls as part of our risk assessment and they are rated as good, acceptable or ineffective. We have also conducted a wider assessment of the risks, strengths and weaknesses exercise associated with providing robust information, taking account of: A review of our assurance arrangements by KPMG, including a deep dive into information relating to three measures of success. Our business as usual conversations with our key stakeholders. The relationship we have with our key stakeholders is important to Northumbrian Water. We actively engage with stakeholders to ensure that we maintain trust and confidence. Our key stakeholders in this context are: Our Water Forums (Customer Challenge Groups). The Consumer Council for Water (CCWater). Ofwat. The Drinking Water Inspectorate (DWI). The Environment Agency (EA). This engagement is achieved via regular conversations and performance review meetings with these stakeholders, understanding their expectations relating to data reporting and communications, whilst being open to constructive feedback. The results of KPMG s review, along with our stakeholder conversations, have been used to inform our draft Assurance Plan. Based on the feedback received from our consultation we have extended the scope of our assurance plan to include by exception key delivery risks in addition to consideration of data quality and integrity. An internal review of our corporate risk register has identified significant risks associated with either the delivery of our performance commitments or with meeting new or emerging requirements. 8 Our Assurance Plan 2016/17

9 This approach has identified the following areas for inclusion in our final assurance plan: Outcome performance reporting. How we intend to meet our challenging performance commitments for pollution and sewer flooding. Assurance for meeting market readiness which comes into force in April next year. The implementation of a new consolidated customer information and billing system. Meeting our commitments in relation to new reporting requirements for developer services. The diagram below provides an overview of the approach we have undertaken in developing our risk assessment. EXTERNAL ENGAGEMENT AREAS OF RISK INTERNAL REVIEW Continuous stakeholder engagement Consultation on risks, strengths and weaknesses Regulatory guidance and feedback Consequence Outcome performance reporting Pollution and sewer flooding commitments New obligations for the retail market New consolidated customer information and billing system New obligations for developer services Identification of risks associated with: Quality of information Achievement of our performance commitments New obligations Likelihood 9 Our Assurance Plan 2016/17

10 SUMMARY OF OUR RISKS, STRENGTHS AND WEAKNESSES 10 Our Assurance Plan 2016/17

11 SUMMARY OF OUR RISKS, STRENGTHS AND WEAKNESSES Strengths Our well established, mature and well understood Governance and Assurance Framework has been applied to the reporting of our performance commitments. This includes a data risk assessment which has been used to target the nature and level of assurance activity in the most appropriate way. The framework has been assessed by KPMG as consistent with regulatory expectations and deep dives conducted by KPMG into three areas of performance have all resulted in a green assessment: Robust methodology and robust controls in place. No major issues expected. This framework also builds upon our integrated management system and commitment to quality assurance. We have companywide accreditation to the following standards which has been in place for a number of years: ISO A quality management system ISO An environmental management system OHSAS An occupational health & safety management system In addition our sampling and laboratory analysis are accredited to the demanding ISO standard, and from 2015 we also have companywide accreditation to IS for Asset Management A further strength is our excellent, strong and mutually beneficial relationships with our key stakeholders. Risks Outcome performance reporting Many of our performance commitments for have financial incentives associated with them in the form of penalties and rewards. This is a new arrangement, and we are very aware of the adverse impact that miscalculating incentives could have on our reputation and stakeholder trust and confidence, along with the potential for associated fines. These impacts are likely to be more significant than the actual monetary value of any penalty or reward being incorrect. This risk has been reflected in our data risk assessment exercise, the results of which have enabled us to target assurance and mitigation activities in the most effective way. Pollution and sewer flooding commitments Based on recent performance our pollution performance commitment is challenging and there is a need to focus on maintaining recent improvements in our sewer flooding performance. Our strategy, operational and delivery teams will continue to focus on developing a pollution action plan and embedding our sewer flooding action plan to ensure that targets are achieved. New obligations for the retail market From April 2017, non-household customers across England and Wales will be able to choose their supplier for water and wastewater services. In readiness for the market opening, we will need to provide assurance that we have met the requirements of these new arrangements which includes confirmation of hitting key milestones. New consolidated customer information and billing system We rely on our IT systems for the majority of information required to monitor our performance. Consistent with our business plan, we are planning substantial improvements to these systems during the 2015 to 2020 period. Most significantly this includes a new customer information and billing system and systems to support retail separation. It is important that we retain a strong focus on data quality when we make these changes, in order to avoid any adverse impact on performance commitment reporting. 11 Our Assurance Plan 2016/17

12 New obligations for developer services Water and sewerage companies provide a range of developer services to enable new connections to the network. We already offer developers a high quality service and our approach of early collaboration with them and local planning authorities is very supportive and ensures that our water and sewerage infrastructure planning is closely aligned to future housing and economic development plans. We, along with other water and sewerage companies, now report our performance so that customers can compare the standard of service they receive from the industry. This is an area that we want to focus assurance activity on in order to meet statutory obligations and improve services to developers. Weaknesses In future, in addition to reporting on our performance in the previous year, we will need to share forecasts of likely outcomes on penalties and rewards. We have a forecasting methodology which we use for internal purposes, but the processes and controls for producing reliable forecasts are fundamentally different to those used in recording and reporting on actual information and data as are the assurance requirements. We will need to consider whether additional assurance may be required to support the new requirement to publish these forecasts externally. Within the context that each area received an overall assessment of green, there are a limited number of recommendations from KPMG in relation to their deep dive exercise which we have incorporated into our draft assurance plan. 12 Our Assurance Plan 2016/17

13 OUR ASSURANCE PLAN FOR 2016/17 13 Our Assurance Plan 2016/17

14 OUR ASSURANCE PLAN FOR 2016/17 The following tables contain our assurance plan for 2016/17. This details how the outcome from the data risk assessment exercise, and the wider assessment of risks, strengths and weaknesses, has been used to target our planned assurance activity. PERFORMANCE COMMITMENTS Interruptions to water supply DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES This measure is calculated using the total duration of all water supply interruptions of more than three hours divided by the number of properties the company supplies to give an average interruption time in minutes and seconds per year. The measure includes planned interruptions, unplanned interruptions and interruptions caused by the actions of third parties, for example resulting from a power cut The measure will be assessed on the company s regulatory year performance. The risk assessment found a mature process with regular data quality monitoring along with senior manager scrutiny throughout the year. Performance is also monitored monthly by Management Team and Board. Previous audits have found some minor inaccuracy in time recording (with a non-material effect on overall performance). A re-organisation of our water service team is underway. We need to ensure that responsibilities for the provision of data are considered as part of this. We have separate IT systems (Northumbrian and Essex & Suffolk) which are being aligned. Overall the assessment of data quality controls for this measure is acceptable. This is a high priority for assurance, it is important that all data quality controls are working effectively. Areas to target The risk based review identified that highest risk to quality of data lies in areas of manual data collection. Our external technical auditor will carry out an audit of our methodology, processes, data quality and final numbers. The audit will also include sampling of data from report back to source paying special attention to data which is collected manually. Our internal audit team will conduct system audits during the year. KPMG observations from deep dive exercise: Risks The main area of potential risk comes from manual collection of data prior to entering into our IT systems. Strengths Processes have been carefully mapped and relevant controls identified. There is a robust challenge and review process, and a high awareness of the team on the relevance of data quality that translates into regular challenges on data accuracy before it is entered into our IT systems. This is a complex measure with financial incentives attached and as such is a high priority for assurance. 14 Our Assurance Plan 2016/17

15 PERFORMANCE COMMITMENTS Sewer flooding - includes internal and external flooding and repeat flooding DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES These measures track the number of properties which have been affected by an escape of sewage from the company s network. We have separate performance commitments for properties which are affected internally and externally. We also report separately on flooding incidents caused by assets which transferred into water company ownership in October There is a further performance commitment for repeat flooding incidents. Previous audits have found year on year improvement in data and no recent material issues. The risk assessment found a mature process with regular internal data quality monitoring along with senior manager scrutiny throughout the year. Performance is also monitored monthly by Management Team and Board. The risk assessment found good data quality controls in place. Our historic performance has been challenging, there is a need to focus on maintaining recent improvements in service. KPMG observations from deep dive exercise: Risks The main area of potential risk is assessing and categorising flooding incidents correctly on the ground followed by collating and aggregating the data to report performance. The former is conducted by our sewerage teams, the latter by our performance and information team. These two teams have the appropriate expertise to carry out these functions. Interaction between these teams is crucial for this approach to work. This is a high priority for assurance, it is important that all data quality controls are working effectively. Areas to target The risk based review identified that the highest risk to data quality lies in assessing flooding incidents and categorising them correctly. Our internal audit team will conduct system and data quality audit. The audit will also include sampling of data from report back to source during the year and reporting of final numbers. In addition given the performance challenge, our strategy, operational and delivery teams will continue to focus on our action plan to maintain recent improvements in performance levels. Strengths The process has been carefully developed and documented with data quality controls in the main areas of risk. One of the main focuses of our new sewer flooding team is to ensure data relating to our performance commitments is robust and carefully checked. These are complex measures with financial incentives attached and as such are a high priority for assurance. 15 Our Assurance Plan 2016/17

16 PERFORMANCE COMMITMENTS Customer surveys includes surveys undertaken by CCWater and other independent bodies DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES There are various surveys conducted that ask customers independently about their overall satisfaction with the service the company provides. Overall customer satisfaction. Keeping customers informed. Domestic customer satisfaction (Net Promoter Score). Value for money (water). Value for money (sewerage). These surveys are carried out by accredited external organisations (e.g. Explain) and recognised industry bodies (e.g. CCWater). The risk assessment found good data quality controls in place. KPMG observations from deep dive exercise: (Based on one parameter - Net Promoter Score) Risks Reputational measures are not always under the full control of the company and may be influenced by external factors. This is a low priority for assurance. No additional assurance required. Service Incentive Mechanism (SIM) The SIM measure indicates the level of customer satisfaction with company service. It comprises a combined score of quantitative (volumes of complaints) and qualitative (survey) figures. There is an associated penalty and reward set by Ofwat. Strengths When performing surveys, Explain uses a robust sampling methodology based on best practices in the industry. The company regularly reviews the quality of the data collection process. This is a low priority for assurance. Previous audits have found no material issues. The risk assessment found a mature process which is carefully controlled with procedures in place for regular data quality monitoring. Performance is also monitored monthly by Management Team and Board. The risk assessment found good data quality controls in place. This is a complex measure with financial incentives attached and as such is a high priority for assurance. This is a high priority for assurance, it is important that all data quality controls are working effectively. Our internal audit team will conduct a system and data quality audit. The audit will also include sampling of data from report back to source during the year and reporting of final numbers. Overall drinking water quality This is our overall drinking water quality compliance based on 39 water quality parameters determined by the Drinking Water Inspectorate. Previous audits have found a mature process with no material issues. The risk assessment found water quality sampling, analysis and data recording covered by a rigorous quality system assured by UKAS (the UK Accreditation Service). Reporting is performed directly from our Laboratory Information Management System and is also monitored monthly by Management Team and Board. The risk assessment found good data quality controls in place. This is a high priority for assurance, it is important that all data quality controls are working effectively. Continuing UKAS certification, which covers sampling, laboratory and data audits. Our external technical auditor will audit data extraction, interpretation and reporting. This is a complex measure with financial incentives attached and as such is a high priority for assurance. 16 Our Assurance Plan 2016/17

17 PERFORMANCE COMMITMENTS Pollution incidents DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES This measure is the number of category 3 pollution attributable to our operations. It includes the total number of category 3 pollution events from a discharge or escape of a pollutant from the company s water and sewerage assets affecting rivers or coastal waters. A portion of the reported number relies on self reporting to the Environment Agency (EA) by the company. The EA then store pollution data in their database and are responsible for reporting performance. Previous audits have found no material issues. The risk assessment found a well established self reporting process and detailed and comprehensive records. Performance is also monitored monthly by Management Team and Board. The found good data quality controls in place. Based on recent performance this is a challenging commitment to achieve. This is a high priority for assurance. Our external technical auditor will review our methodology and data quality. This will include sampling of data from source to final report and cross checking of the final numbers with the EA s list. In addition given the performance challenge, our strategy, operational and delivery teams will focus on the development and implementation of an action plan to ensure targets are achieved. This measure has financial incentives attached and is a challenging performance commitment to achieve, so is a high priority for assurance. Satisfaction with taste and odour of tap water This is the number of complaints received from customers because they are dissatisfied with the taste or odour of their tap water. The measure matches Drinking Water Inspectorate reporting guidance. Previous audits have found no material issues. The risk assessment found a mature process with data entered into corporate systems and extracted directly from systems to provide performance reports. Performance is also monitored monthly by Management Team and Board. The risk assessment found good data quality controls in place. This is a medium priority for assurance. Our internal audit team will conduct a system and data quality audit. The audit will also include sampling of data from report back to source during the year and reporting of final numbers. This measure has financial incentives attached and so even though controls were found to be robust it remains a medium priority for assurance. Discoloured water complaints This is the number of complaints received from customers because they are dissatisfied with the appearance of their water because it is discoloured; described as black, orange or brown. Previous audits have found no material issues. The risk assessment found a mature process with data captured and recorded directly into corporate systems. The data is then stored and reported directly out of corporate systems with senior manager scrutiny throughout the year. Performance is monitored monthly by Management Team and Board. The risk assessment found good data quality controls in place. This is a medium priority for assurance. Our internal audit team will conduct a system and data quality audit. The audit will also include sampling of data from report back to source during the year and reporting of final numbers. This measure has financial incentives attached and so even though controls were found to be robust it remains a medium priority for assurance. 17 Our Assurance Plan 2016/17

18 PERFORMANCE COMMITMENTS Sewer collapses DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES This measure counts the number of collapsed sewers that we experience. We report separately on collapses relating to assets which transferred into water company ownership in October Previous audits found no material issues. The risk assessment found complex definitions, with reliance on information from 3rd parties. The number of collapses experienced, however, is low. This means that occurrences can, and do, receive a high level of individual scrutiny. Monitoring and reporting responsibility was changed to a different team from July This change reduces the control assessment in the risk model to acceptable. This is a medium priority for assurance. Our external technical auditor will carry out a review of our methodology, data quality and final numbers. The audit will also include sampling of data from report back to source. This measure has financial incentives attached and so even though controls were found to be robust it remains a medium priority for assurance. Sewage treatment works discharge compliance This is a measure of the effectiveness of our Sewage Treatment Works to treat waste water to an appropriate standard before it is returned to the environment, as stipulated in Environment Agency consents. Previous audits found no material issues. The risk assessment found sampling, analysis and data recording covered by a rigorous quality system assured by UKAS. Reporting is performed directly from our Laboratory Information Management System and is also monitored monthly by our Management Team and Board. Reports are also subject to Environment Agency scrutiny. The risk assessment found good controls in place. This is a high priority for assurance, it is important that all data quality controls are working effectively. Continuing UKAS certification, which covers sampling, laboratory and data audits. Our external technical auditor will audit data extraction, interpretation and reporting. This is a complex measure with financial incentives attached and as such is a high priority for assurance. Bathing water compliance This is the number of designated bathing waters that meet the regulatory sufficient standard based on the results of the independent testing of seawater by the Environment Agency during the bathing water season. Sampling and monitoring is carried out independently by the Environment Agency. Previous audits have found no material issues. This remains a low priority for assurance despite now having financial incentives attached. This is a low priority for assurance. No additional assurance required. 18 Our Assurance Plan 2016/17

19 PERFORMANCE COMMITMENTS Leakage DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES The measure is based on the volume of water leaking from the company s water supply assets. The annual average is applied to give a figure for mega litres per day (Ml/d). It includes any uncontrolled losses between water treatment works and customers internal stop taps. It does not include customers internal plumbing losses. Previous audits found no material issues. The risk assessment found data held in multiple separate company corporate systems and manipulated in spreadsheets. These are technical and complex processes, however leakage is calculated using a recognised industry standard and follows a clearly documented methodology. The risk assessment found good controls in place. This is a high priority for assurance, it is important that all data quality controls are working effectively. Our external technical auditor will examine the application of reporting requirements, our methodology, data quality, the leakage calculation and final numbers. Other strengths noted Leakage was subject to a full system audit in This was a combined audit, carried out by Internal Audit and an external technical auditor. This audit found no material issues. This is a complex measure with financial incentives attached and as such is a high priority for assurance. Properties experiencing poor water pressure This measure is the number of properties regularly experiencing water pressure below the minimum standard. Previous audits found no material issues. The risk assessment found extensive validation controls in place with systems and processes fully documented and data quality controls fully evaluated and assessed. The risk assessment found good controls in place. This is a medium priority for assurance. Our internal audit team will conduct a system and data quality audit. The audit will also include sampling of data from report back to source during the year and reporting of final numbers. Other strengths noted This measure was subject to a full system audit in This was a combined audit, carried out by Internal Audit and an external technical auditor. This audit found no material issues. This measure has financial incentives attached and so even though controls were found to be robust it remains a medium priority for assurance. No material issues identified in previous audits. The risk assessment found there is regular internal data quality monitoring. Data from company operatives is captured and recorded directly into corporate systems. Data from contractors is captured on data sheets and input into company systems. Data is then reported directly out of corporate systems and is subject to senior manager scrutiny throughout the year. The risk assessment found good controls in place. Water mains bursts This is the number of water mains bursts and is determined by the number of completed repairs. The impact of bursts on our customers is measured via other performance commitments such as poor pressure, interruptions to supply and leakage. This is a medium priority for assurance. Our internal audit team will conduct a system and data quality audit. The audit will also include sampling of data from report back to source during the year and reporting of final numbers. 19 Our Assurance Plan 2016/17 This measure has financial incentives attached and so even though controls were found to be robust it remains a medium priority for assurance.

20 PERFORMANCE COMMITMENTS Greenhouse gas emissions DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES This is a measure of the greenhouse gases produced by our operations and assets. No material issues identified in previous audits. The risk assessment found extensive validation controls in place. The reported numbers are based in part on certain assumptions, however this only relates to a small proportion of the total reported number. This is a medium/low priority for assurance. Internal Audit will carry out a systems and final numbers audit, paying particular attention to documentation. Other strengths noted Our greenhouse gas data was subject to a full system audit in This was a combined audit, carried out by Internal Audit and an external technical auditor. This audit found no material issues, although in some cases documentation relating to roles and responsibilities could be improved. The numbers are produced using the latest version of the Carbon Accounting Workbook. This is an industry wide approach developed by the Water Research Council and endorsed by Ofwat. The risk assessment found good controls in place and the priority for assurance score is medium/low. Asset health determinations, water and wastewater A number of our performance commitments are aggregated to understand the effectiveness and sustainability of our long term stewardship of our assets. Our performance against the resulting Asset Health measures has a very significant impact on penalties and rewards. Previous audits (of serviceability and asset health) have found no material issues. The risk assessment found this is technical and complex area, however it is non-judgemental and based on a fixed methodology. The Management Team and Board monitor performance throughout the year. The risk assessment found good controls in place for water measures and acceptable controls in place for wastewater. This is a high priority for assurance, it is important that all data quality controls are working effectively. Our external technical auditor will examine our methodology, its application, and the outcome of the determination of asset health for water and wastewater. This is a complex measure and has a direct impact on significant financial incentives so is a high priority for assurance. 20 Our Assurance Plan 2016/17

21 PERFORMANCE COMMITMENTS Outcome delivery incentive calculation DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES Calculation of rewards or penalties for performance commitments which have financial incentives attached. The calculation is carried out using a pre-audited model with formal methodology and guidance. The risk assessment found good controls in place. This has a direct impact on any penalties and rewards so the priority for assurance is high. This is a high priority for assurance, it is important that all data quality controls are working effectively. Our internal audit team will audit the calculation inputs and outputs and controls over the model. Annual Environment Report The company is committed to publishing an independent annual review of its environmental performance undertaken by the Corporate Responsibility Groups (CRAGs). In future years this will be covered within the remit of the Water Forums. Our risk assessment found good controls in place. This is an external independent review of NWL environmental performance. Any environmental performance commitments referred to in the publication will be covered individually elsewhere in this plan. Ascertaining whether or not the report is published is a straightforward matter. This is a low priority for assurance. No additional assurance required. This is a low priority for assurance. Whitburn combined sewer overflow (CSO) project This project is needed to improve the way in which wastewater is discharged to the environment at Whitburn. Delivery of this commitment has a financial incentive attached which compensates customers if the project is not completed on time - by 31 December Our risk assessment found good controls in place. While this is a complex project, ascertaining whether it is delivered on time is a straightforward matter. This is a low priority for assurance. This is a low priority for assurance. No additional assurance required. Delivering a consolidated customer information & billing (CIB) system As part of our improvements to IT systems during , we plan to implement a new customer information and billing (CIB) system. Delivery of this commitment has financial incentives attached which encourage us to deliver this project efficiently, sharing any savings with customers. The incentive arrangement also compensates customers if the system is not implemented on time - by 31 March Our risk assessment found good controls in place. This is a complex and high profile project which is closely monitored and contains a great deal of assurance to ensure that excellent customer service is maintained during and after implementation. From a performance commitment perspective, however, ascertaining whether the new system is implemented on time and to budget is more straightforward and is supported by a documented definition of what constitutes implemented as set out in our 2014 Ofwat Final Determination. This is a high priority for assurance. Our programme team have compiled a detailed plan with regular reporting against key milestones. External assurance will be provided by Deloitte to provide regular checks on the suitability of the programme to proceed to the next stage. The priority for assurance is ensuring customer service and data quality are maintained during and after implementation. This is a high priority for assurance. 21 Our Assurance Plan 2016/17

22 NEW OBLIGATIONS Ready for Retail (Market reform) DESCRIPTION RISK BASED REVIEW PLANNED ASSURANCE ACTIVITIES From April 2017, non-household customers in England will be able to choose their supplier for water and wastewater services. A comprehensive programme is required to be in place in readiness of the market opening and several new obligations will be introduced. Most notably a level playing field where wholesale companies must provide the same level of service to all retail companies. : Until April 2017, the focus will be on confirming readiness for market opening and certainty to Market Operator Services Limited (MOSL) and Ofwat that we will be ready. Post April 2017, focus concentrates on: Legal separation. Level playing field. This is a complex area with high importance. It is therefore a high priority for assurance. It should however be noted that a high level of assurance is already in place and required to meet external assurance requirements. This is a high priority for assurance. Our internal audit team will review the programme. External consultant will provide assurance of overall programme plan and mitigation of risks. We will conduct formal milestone reporting to MOSL and Ofwat. Developer Services Based on existing obligations, companies are now requested to formally submit performance information in relation to Developer services. : The risk assessment identified complex reporting systems, with manual intervention. Performance information will be published in set of industry league tables by Water UK. This is a new reporting requirement involving a degree of complexity. It is therefore a high priority for assurance. This is a high priority for assurance. Our internal audit team will conduct an audit of systems and processes used to produce data. We will conduct a formal review of March 2016 results. Further review will occur throughout 2016/ Our Assurance Plan 2016/17

23 23 Our Assurance Plan 2016/17

24 Northumbrian Water Limited Northumbria House Abbey Road Pity Me Durham DH1 5FG Designed by NWG Marketing Our Assurance Plan 2016/17

Consultation on United Utilities statement of risks, strengths and weaknesses 2015/16 Our 2015-20 annual performance reporting

Consultation on United Utilities statement of risks, strengths and weaknesses 2015/16 Our 2015-20 annual performance reporting Consultation on United Utilities statement of risks, strengths and weaknesses 2015/16 Our 2015-20 annual performance reporting United Utilities performance reporting Consultation on our statement of risks,

More information

Delivering for our customers Our 2015 to 2020 business plan

Delivering for our customers Our 2015 to 2020 business plan Delivering for our customers Our 2015 to 2020 business plan 2nd December 2013 South East Water Delivering for our customers Our 2015 to 2020 business plan Priorities Service Outcomes Performance Incentives

More information

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers

7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4

More information

RISK MANAGEMENT POLICY (Revised October 2015)

RISK MANAGEMENT POLICY (Revised October 2015) UNIVERSITY OF LEICESTER RISK MANAGEMENT POLICY (Revised October 2015) 1. This risk management policy ( the policy ) forms part of the University s internal control and corporate governance arrangements.

More information

The Drinking Water Inspectorate s response to the Consultation on the Cave Review of competition and innovation in water markets

The Drinking Water Inspectorate s response to the Consultation on the Cave Review of competition and innovation in water markets The Drinking Water Inspectorate s response to the Consultation on the Cave Review of competition and innovation in water markets This is Drinking Water Inspectorate s (DWI) response to the UK and Welsh

More information

Staff Paper 6. Allowed for operating costs. 6.1 Introduction

Staff Paper 6. Allowed for operating costs. 6.1 Introduction Staff Paper 6 Allowed for operating costs This staff paper has been produced by our office to assist stakeholders in responding to the Draft Determination. The material reflected in this staff paper has

More information

Contents BUSINESS PLAN 2015-2020. Part A Business Plan Summary

Contents BUSINESS PLAN 2015-2020. Part A Business Plan Summary Contents Executive summary... 4 A1 Introduction... 13 A1.1 Building the plan... 13 A1.2 Overall Business Plan structure... 14 A1.3 Structure of this document... 16 A2 The right outcomes for customers...

More information

Regulatory Information and Data Quality Assurance Policy

Regulatory Information and Data Quality Assurance Policy ISSUE 1.0 Page 1 of 7 Regulatory Information and Data Quality Assurance Policy Contents Policy Scope Responsibility for Data Quality and Assurance Reference Documents The Data Quality Assurance Process

More information

Achieve. Performance objectives

Achieve. Performance objectives Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.

More information

Corporate Risk Management Policy

Corporate Risk Management Policy Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction

More information

Bridgend County Borough Council. Corporate Risk Management Policy

Bridgend County Borough Council. Corporate Risk Management Policy Bridgend County Borough Council Corporate Risk Management Policy December 2014 Index Section Page No Introduction 3 Definition of risk 3 Aims and objectives 4 Strategy 4 Accountabilities and roles 5 Risk

More information

Confident in our Future, Risk Management Policy Statement and Strategy

Confident in our Future, Risk Management Policy Statement and Strategy Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents

More information

HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK

HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK July 2013 1 P age Contents Page 1.0 Definition 3 2.0 Context 3 3.0 Purpose and aim of the policy 4 4.0 Policy Statement 4 5.0 Framework for Performance Management

More information

Audit Quality Thematic Review

Audit Quality Thematic Review Thematic Review Professional discipline Financial Reporting Council January 2014 Audit Quality Thematic Review Fraud risks and laws and regulations The FRC is responsible for promoting high quality corporate

More information

Appendix 10: Improving the customer experience

Appendix 10: Improving the customer experience Appendix 10: Improving the customer experience Scottish Water is committed to delivering leading customer service to all of our customers. This means we deliver the following activities: We will ensure

More information

V1.0 - Eurojuris ISO 9001:2008 Certified

V1.0 - Eurojuris ISO 9001:2008 Certified Risk Management Manual V1.0 - Eurojuris ISO 9001:2008 Certified Section Page No 1 An Introduction to Risk Management 1-2 2 The Framework of Risk Management 3-6 3 Identification of Risks 7-8 4 Evaluation

More information

Risk and Compliance Statement 2013/14

Risk and Compliance Statement 2013/14 Risk and Compliance Statement 2013/14 June 2014 Purpose of this statement The purpose of this statement is: To confirm that we have complied with all our relevant statutory, licence and regulatory obligations;

More information

Central bank corporate governance, financial management, and transparency

Central bank corporate governance, financial management, and transparency Central bank corporate governance, financial management, and transparency By Richard Perry, 1 Financial Services Group This article discusses the Reserve Bank of New Zealand s corporate governance, financial

More information

APPENDIX 50. Enterprise risk management - Risk management overview

APPENDIX 50. Enterprise risk management - Risk management overview APPENDIX 50 Enterprise risk management - Risk management overview Energex regulatory proposal October 2014 ENTERPRISE RISK MANAGEMENT Risk Management Overview (RMO) 06 11 2013 Table of Contents 1. INTRODUCTION...

More information

Improving information to support decision making: standards for better quality data

Improving information to support decision making: standards for better quality data Public sector November 2007 Improving information to support decision making: standards for better quality data A framework to support improvement in data quality in the public sector Improving information

More information

Housing Association Regulatory Assessment

Housing Association Regulatory Assessment Welsh Government Housing Directorate - Regulation Housing Association Regulatory Assessment Melin Homes Limited Registration number: L110 Date of publication: 20 December 2013 Welsh Government Housing

More information

How To Manage The Council

How To Manage The Council Mole Valley District Council Corporate Communications Strategy 2002-2005 CONTENTS Content Section 1: Introduction Section 2: Stakeholders Section 3: Objectives Section 4: Targets Section 5: Principles

More information

Government Communication Professional Competency Framework

Government Communication Professional Competency Framework Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their

More information

Risk and Compliance Statement 2015

Risk and Compliance Statement 2015 Risk and Compliance Statement 2015 Yorkshire Water Risk and Compliance Statement 2015 2 Endorsement of the Risk and Compliance Statement The Board has confirmed that it has sufficient processes and internal

More information

Governance, Risk and Best Value Committee

Governance, Risk and Best Value Committee Governance, Risk and Best Value Committee 2.00pm, Wednesday 23 September 2015 Internal Audit Report: Integrated Health & Social Care Item number Report number Executive/routine Wards Executive summary

More information

Business Continuity Management

Business Continuity Management Business Continuity Management Policy Statement & Strategy July 2009 Basildon District Council Business Continuity Management Policy Statement The Council is committed to ensuring robust and effective

More information

Relationship Manager (Banking) Assessment Plan

Relationship Manager (Banking) Assessment Plan Relationship Manager (Banking) Assessment Plan ST0184/AP03 1. Introduction and Overview The Relationship Manager (Banking) is an apprenticeship that takes 3-4 years to complete and is at a Level 6. It

More information

ARB's overarching goals The Board has identified two objectives from the Act which underpin all of our work:

ARB's overarching goals The Board has identified two objectives from the Act which underpin all of our work: Architects Registration Board Communications Strategy Introduction Effective communication is key to the work of the Architects Registration Board (ARB), enabling the organisation to build and maintain

More information

Water today, water tomorrow Involving customers in price setting Ofwat s customer engagement policy statement

Water today, water tomorrow Involving customers in price setting Ofwat s customer engagement policy statement Water today, water tomorrow Involving customers in price setting Ofwat s customer engagement policy statement About this document This document sets out our approach to customer engagement during the price-setting

More information

Risk Management Policy

Risk Management Policy Risk Management Policy Responsible Officer Author Ben Bennett, Business Planning & Resources Director Julian Lewis, Governance Manager Date effective from December 2008 Date last amended December 2012

More information

Communications Strategy

Communications Strategy Communications Communications July 2013 Version 1.1 1 Communications River Clyde Homes Vision Our vision is to provide quality, affordable homes, in neighbourhoods we can be proud of and to deliver excellent

More information

The Levy Control Framework

The Levy Control Framework Report by the Comptroller and Auditor General Department of Energy & Climate Change The Levy Control Framework HC 815 SESSION 2013-14 27 NOVEMBER 2013 4 Key facts The Levy Control Framework Key facts 2bn

More information

Water Mains Rehabilitation Framework (NI) Northern Ireland Water

Water Mains Rehabilitation Framework (NI) Northern Ireland Water PROJECT: CLIENT: MAIN CONTRACTOR: Water Mains Rehabilitation Framework (NI) Northern Ireland Water Farrans Background Northern Ireland Water manages a water mains infrastructure that supplies 625 million

More information

DELVING INTO WATER. Performance of the water companies in England and Wales. 2010-11 to 2013-14

DELVING INTO WATER. Performance of the water companies in England and Wales. 2010-11 to 2013-14 DELVING INTO WATER Performance of the water companies in England and Wales 2010-11 to 2013-14 Consumer Council for Water January 2015 Contents Section Page 1. Executive Summary 3 2. Introduction 9 3. Dealing

More information

Solihull Clinical Commissioning Group

Solihull Clinical Commissioning Group Solihull Clinical Commissioning Group Business Continuity Policy Version v1 Ratified by SMT Date ratified 24 February 2014 Name of originator / author CSU Corporate Services Review date Annual Target audience

More information

Thames Water s Thames Tunnel Consultation

Thames Water s Thames Tunnel Consultation Thames Water s Thames Tunnel Consultation Consumer Council for Water response January 2011 Introduction 1. The Consumer Council for Water (CCWater) is the independent body that represents water and sewerage

More information

Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02) 8270 2218

Sector Development Ageing, Disability and Home Care Department of Family and Community Services (02) 8270 2218 Copyright in the material is owned by the State of New South Wales. Apart from any use as permitted under the Copyright Act 1968 and/or as explicitly permitted below, all other rights are reserved. You

More information

The Compliance Universe

The Compliance Universe The Compliance Universe Principle 6.1 The board should ensure that the company complies with applicable laws and considers adherence to non-binding rules, codes and standards This practice note is intended

More information

the role of the head of internal audit in public service organisations 2010

the role of the head of internal audit in public service organisations 2010 the role of the head of internal audit in public service organisations 2010 CIPFA Statement on the role of the Head of Internal Audit in public service organisations The Head of Internal Audit in a public

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

CORPORATE PERFORMANCE MANAGEMENT GUIDELINE

CORPORATE PERFORMANCE MANAGEMENT GUIDELINE -001 CORPORATE PERFORMANCE MANAGEMENT GUIDELINE -001 TABLE OF CONTENTS 1 Introduction... 3 1.1 Scope... 3 1.2 Purpose... 3 2 Performance Management Framework Overview... 4 3 Performance Management Framework...

More information

From our review of the experience at PR14 we have identified five key lessons for the next price review. These are summarised in Figure 1 below.

From our review of the experience at PR14 we have identified five key lessons for the next price review. These are summarised in Figure 1 below. Water 2020 Customer engagement: lessons and opportunities Executive summary Most stakeholders would agree that the PR14 process was a huge success in terms of ensuring that business plans reflected customer

More information

Assessment Policy. 1 Introduction. 2 Background

Assessment Policy. 1 Introduction. 2 Background Assessment Policy 1 Introduction This document has been written by the National Foundation for Educational Research (NFER) to provide policy makers, researchers, teacher educators and practitioners with

More information

DATA QUALITY STRATEGY

DATA QUALITY STRATEGY DATA QUALITY STRATEGY June 2008 G:\Performance Management\data quality\data Quality Strategy08.doc 1 CONTENTS CONTENTS 2 1. INTRODUCTION 3 2. BACKGROUND INFORMATION 3 3. THE PRINCIPLES OF DATA QUALITY

More information

How To Be Accountable To The Health Department

How To Be Accountable To The Health Department CQC Corporate Governance Framework Introduction This document describes the components of CQC s Corporate Governance Framework: what it is intended to achieve, what the components of the Framework are

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

Monitoring Highways England The monitoring framework

Monitoring Highways England The monitoring framework Monitoring Highways England The monitoring framework October 2015 Contents Executive summary 4 Roads reform 4 ORR s role in monitoring Highways England 5 What we will do next 10 1. Overview of this document

More information

Asset Management Strategy (2013-2017) Doing things Differently A New Approach for a sustainable future

Asset Management Strategy (2013-2017) Doing things Differently A New Approach for a sustainable future Asset Management Strategy (2013-2017) A New Approach for a sustainable future Contents Introduction... 2 The Asset Management Vision, Policy Statement & Strategic Themes... 5 Part B The Asset Management

More information

A Risk Management Standard

A Risk Management Standard A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management

More information

SUSTAINABILITY TRENDS

SUSTAINABILITY TRENDS 213 SUSTAINABILITY TRENDS 213 Our Vision To be the national leader in the provision of sustainable water and waste water services. Northumbrian Water Limited (NWL) is one of the ten regulated water and

More information

Capital Maintenance Planning From a historical and future perspective

Capital Maintenance Planning From a historical and future perspective Capital Maintenance Planning From a historical and future perspective This paper has been written by Anglian Water as a contribution to Water 2020, Ofwat s programme for determining the form of the 2019

More information

Final Draft Guidance on Audit Committees

Final Draft Guidance on Audit Committees Guidance Corporate Governance April 2016 Final Draft Guidance on Audit Committees The FRC is responsible for promoting high quality corporate governance and reporting to foster investment. We set the UK

More information

RE Quality First Principles for Content and Data

RE Quality First Principles for Content and Data RE Quality First Principles for Content and Data RE Group Risk Management and Corporate Responsibility June 2014 Introduction Reed Elsevier s strategy is to: Deliver improved outcomes to professional customers

More information

RISK MANAGEMENT GUIDANCE FOR GOVERNMENT DEPARTMENTS AND OFFICES

RISK MANAGEMENT GUIDANCE FOR GOVERNMENT DEPARTMENTS AND OFFICES RISK MANAGEMENT GUIDANCE FOR GOVERNMENT DEPARTMENTS AND OFFICES GOVERNMENT ACCOUNTING SECTION DEPARTMENT OF FINANCE MARCH 2004 Risk Management Guidance CONTENTS Pages List of guidelines on risk management

More information

Informing the audit risk assessment for Cannock Chase District Council

Informing the audit risk assessment for Cannock Chase District Council ITEM NO. 9.1 Informing the audit risk assessment for Cannock Chase District Council Year ended 31 March 2016 March 2016 James Cook Engagement Lead T 0121 232 5343 E james.c.cook@uk.gt.com Laura Hinsley

More information

25 NOVEMBER 2011. Assessing the Value for Money of Regulation of Infrastructure Networks

25 NOVEMBER 2011. Assessing the Value for Money of Regulation of Infrastructure Networks FOURTH ANNUAL CONFERENCE ON COMPETITION AND REGULATION IN NETWORK INDUSTRIES 25 NOVEMBER 2011 RESIDENCE PALACE, BRUSSELS, BELGIUM Assessing the Value for Money of Regulation of Infrastructure Networks

More information

PERFORMANCE DATA QUALITY STRATEGY 2010-11

PERFORMANCE DATA QUALITY STRATEGY 2010-11 a PERFORMANCE DATA QUALITY STRATEGY 2010-11 LEICESTERSHIRE COUNTY COUNCIL PERFORMANCE DATA QUALITY STRATEGY 2010-11 Status: Final Approved by Corporate Performance & Improvement Board, 23 March 2010 Date

More information

Extra help where it is needed: a new Energy Company Obligation

Extra help where it is needed: a new Energy Company Obligation Extra help where it is needed: a new Energy Company Obligation May 2011 The content of this paper is subject to the consultation outcome Contents 1 Our objectives for the ECO 1.1 Householder support: Lower

More information

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY

DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY VERSION 1.0 ISSUED JULY 2015 CONTENTS Page CONTENTS VERSION CONTROL FOREWORD i ii iii POLICY 1 Scope 1 Aim and Objectives 1 Methods and Standards 1

More information

Smart Meter Wide Area Network DCC Assurance Strategy

Smart Meter Wide Area Network DCC Assurance Strategy Smart Meter Wide Area Network DCC Describing the means by which DCC seeks to ensure that Communication Service Providers meet their connectivity and coverage service commitments Version: v1.0 Date: 2016-03-07

More information

Strategic Plan 2011 2012 to 2014 2015. Working Together for Australian Sport

Strategic Plan 2011 2012 to 2014 2015. Working Together for Australian Sport Strategic Plan 2011 2012 to 2014 2015 Working Together for Australian Sport Strategic Plan 2011 2012 to 2014 2015 Working Together for Australian Sport Australian Sports Commission 2011 Ownership of intellectual

More information

DATA QUALITY STRATEGY

DATA QUALITY STRATEGY DATA QUALITY STRATEGY If you or anybody you know requires this or any other council information in another language, please contact us and we will do our best to provide this for you. Braille, Audio tape

More information

Water Industry Alternative Dispute Resolution (ADR) scheme

Water Industry Alternative Dispute Resolution (ADR) scheme Water Industry Alternative Dispute Resolution (ADR) scheme For England and Wales System / process specification 1 Contents Introduction... 4 Background and rationale... 4 ADR scheme principles... 6 Process

More information

Quality Assurance. Policy P7

Quality Assurance. Policy P7 Quality Assurance Policy P7 Table of Content Quality assurance... 3 IIA Australia quality assurance and professional standards... 3 Quality assurance and professional qualifications... 4 Quality assurance

More information

Role Description Director ICT Governance, Security and Risk

Role Description Director ICT Governance, Security and Risk Role Description Director ICT Governance, Security and Risk Classification/Grade/Band Band 1 Senior Executive Work Level Standards ANZSCO Code 262112 PCAT Code 1226892 Date of Approval 03 March 2014 Work

More information

NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY

NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY NHS ISLE OF WIGHT CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY POLICY AUTHOR/ APPROVAL DETAILS Document Author Written By: Human Resources Authorised Signature Authorised By: Helen Shields Date: 20

More information

Securing safe, clean drinking water for all

Securing safe, clean drinking water for all Securing safe, clean drinking water for all Enforcement policy Introduction The Drinking Water Inspectorate (DWI) is the independent regulator of drinking water in England and Wales set up in 1990 by Parliament

More information

United Kingdom Competition Network (UKCN) Statement of Intent

United Kingdom Competition Network (UKCN) Statement of Intent United Kingdom Competition Network (UKCN) Statement of Intent 1. The statutory basis for the UKCN The Enterprise and Regulatory Reform Act 2013 (ERRA13) was enacted in April 2013. The Act creates the Competition

More information

A guide to our company and our services. www.phjones.co.uk

A guide to our company and our services. www.phjones.co.uk A guide to our company and our services www.phjones.co.uk NATIONWIDE COVERAGE local expertise Introduction Since it s formation in 1963, PH Jones has continued to grow through the provision of excellent

More information

APPENDIX C. Internal Audit Report South Holland District Council Project Management

APPENDIX C. Internal Audit Report South Holland District Council Project Management APPENDIX C Internal Audit Report South Holland District Council Project Management Date: 20th December 2012 Contents Introduction and Scope 1 Executive Summary Assurance Opinion Key Messages 2 3 Management

More information

EPA Victoria Engagement Policy ENVIRONMENT PROTECTION AUTHORITY

EPA Victoria Engagement Policy ENVIRONMENT PROTECTION AUTHORITY EPA Victoria Engagement Policy ENVIRONMENT PROTECTION AUTHORITY The aspirations of the people of Victoria for environmental quality shall drive environmental improvement Environment Protection Act 1970

More information

Queensland Government Human Services Quality Framework. Quality Pathway Kit for Service Providers

Queensland Government Human Services Quality Framework. Quality Pathway Kit for Service Providers Queensland Government Human Services Quality Framework Quality Pathway Kit for Service Providers July 2015 Introduction The Human Services Quality Framework (HSQF) The Human Services Quality Framework

More information

Quantifying the energy and carbon effects of water saving summary report

Quantifying the energy and carbon effects of water saving summary report Quantifying the energy and carbon effects of water saving summary report Domestic water use in the UK is around 150 litres per person per day. Taking water from the environment, treating it, distributing

More information

Anglian Water Customer Engagement Forum Supplementary Report FINAL

Anglian Water Customer Engagement Forum Supplementary Report FINAL Supplementary Report by the Chair and members of the Anglian Water Customer Engagement Forum (CEF) Note This is a supplementary report prepared by the CEF for Ofwat and the assurances provided are. The

More information

South Northamptonshire Council Contract Assurance: Leisure Contract

South Northamptonshire Council Contract Assurance: Leisure Contract South Northamptonshire Council Contract Assurance: Leisure Contract FINAL Internal Audit Report 2012/2013 January 2013 Contents 1. Executive summary 4 2. Background and scope 5 3. Detailed current year

More information

Investors in People Assessment Report. Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited

Investors in People Assessment Report. Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited Investors in People Assessment Report for Bradstow School Presented by Alli Gibbons Investors in People Specialist On behalf of Inspiring Business Performance Limited 30 August 2013 Project Reference Number

More information

Quality Governance Strategy 2011-2013

Quality Governance Strategy 2011-2013 Quality Governance Strategy 2011-2013 - 1 - Index Content Page Number Key Messages and context of the Strategy 3 Introduction What is Quality governance? What do we want to achieve? Trust Objectives Key

More information

QUALITY ASSURANCE POLICY

QUALITY ASSURANCE POLICY QUALITY ASSURANCE POLICY ACADEMIC DEVELOPMENT & QUALITY ASSURANCE OFFICE ALPHA UNIVERSITY COLLEGE 1. BACKGROUND The Strategic Plan of 2003-2005 E.C of Alpha University s defines the direction Alpha University

More information

Statistics on E-commerce and Information and Communication Technology Activity

Statistics on E-commerce and Information and Communication Technology Activity Assessment of compliance with the Code of Practice for Official Statistics Statistics on E-commerce and Information and Communication Technology Activity (produced by the Office for National Statistics)

More information

ANNEX 27: CORPORATE GOVERNANCE, COMPLIANCE AND DATA ASSURANCE BUSINESS PLAN ANNEX

ANNEX 27: CORPORATE GOVERNANCE, COMPLIANCE AND DATA ASSURANCE BUSINESS PLAN ANNEX ANNEX 27: CORPORATE GOVERNANCE, COMPLIANCE AND DATA ASSURANCE BUSINESS PLAN ANNEX Electricity North West Limited Registered Office: 304 Bridgewater Place, Birchwood Park, Warrington, Cheshire. WA3 6XG.

More information

Job Description Strategic Projects Team Leader

Job Description Strategic Projects Team Leader Strategic Projects Team Leader Department: Group: Direct Line Manager: Responsible For: Planning & Community Relations Manager - & Community Relationships Three (3) Strategic Project Drivers Delegations:

More information

National Standards for Disability Services. DSS 1504.02.15 Version 0.1. December 2013

National Standards for Disability Services. DSS 1504.02.15 Version 0.1. December 2013 National Standards for Disability Services DSS 1504.02.15 Version 0.1. December 2013 National Standards for Disability Services Copyright statement All material is provided under a Creative Commons Attribution-NonCommercial-

More information

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS LEC (Company Audit) Guidance Notes Glossary of Terms Transport for London (TfL) London Low Emission

More information

Agency Board Meeting 28 July 2015

Agency Board Meeting 28 July 2015 SEPA 22/15 Agency Board Meeting 28 July 2015 Report Number: SEPA 22/15 Audit Committee Annual Performance Report 2014-2015 Summary: Risks: Resource and Staffing Implications Equalities: Environmental and

More information

DUTY STATEMENT SECTION A: GENERAL INFORMATION

DUTY STATEMENT SECTION A: GENERAL INFORMATION DUTY STATEMENT SECTION A: GENERAL INFORMATION Title: Team Leader Mineral Tenement Systems Group: Resources and Energy Division: Mineral Resources Branch: Mineral Tenements & Exploration Occupant: HRMS

More information

Corporate Governance Service Business Plan 2011-2016. Modernising Services

Corporate Governance Service Business Plan 2011-2016. Modernising Services Corporate Governance Service Business Plan 2011-2016 Modernising Services Index 1. Executive Summary 3 2. Vision and Strategy 4 3. Service Overview 3.1 What Services do we and Will we Deliver? 5 3.2 How

More information

Risk Management Strategy and Policy. The policy provides the framework for the management and control of risk within the GOC

Risk Management Strategy and Policy. The policy provides the framework for the management and control of risk within the GOC Annex 1 TITLE VERSION Version 2 Risk Management Strategy and Policy SUMMARY The policy provides the framework for the management and control of risk within the GOC DATE CREATED January 2013 REVIEW DATE

More information

Corporate Governance Report

Corporate Governance Report Corporate Governance Report Chairman s introduction From 1 January 2015 until 31 December 2015, the company applied the 2014 edition of the UK Corporate Governance Code (the Code ). 1. BOARD COMPOSITION

More information

The South Staffordshire and Shropshire Health Care NHS Foundation Trust Digital Strategy 2014 2019

The South Staffordshire and Shropshire Health Care NHS Foundation Trust Digital Strategy 2014 2019 The South Staffordshire and Shropshire Health Care NHS Foundation Trust Digital Strategy 2014 2019 Peter Kendal Associate Director for Information Management and Technology Development 01/12/2014 1 Page

More information

TAXREP 01/16 (ICAEW REP 02/16)

TAXREP 01/16 (ICAEW REP 02/16) TAXREP 01/16 (ICAEW REP 02/16) January 2016 ICAEW research survey: HMRC Customer Service Standards 2015 Results of the ICAEW 2015 research survey among ICAEW smaller agents about HMRC service standards.

More information

Future water and sewerage charges 2010-15: Final determinations

Future water and sewerage charges 2010-15: Final determinations Future water and sewerage charges 2010-15: Final determinations Protecting consumers, promoting value, safeguarding the future PR09 www.ofwat.gov.uk About this document This document has four key objectives.

More information

CHAPTER 24: ENVIRONMENTAL MANAGEMENT

CHAPTER 24: ENVIRONMENTAL MANAGEMENT Central Eyre Iron Project Environmental Impact Statement CHAPTER 24: ENVIRONMENTAL MANAGEMENT CHAPTER 24 ENVIRONMENTAL MANAGEMENT COPYRIGHT Copyright Iron Road Limited, 2015 All rights reserved This document

More information

The Regulatory Framework for Social Housing in England Governance and Financial Viability standard requirement: Governance Annual Assessment

The Regulatory Framework for Social Housing in England Governance and Financial Viability standard requirement: Governance Annual Assessment East Thames Group The Regulatory Framework for Social Housing in England Governance and Financial Viability standard requirement: Governance Annual Assessment 1 Context 1.1 Under the Regulatory Framework,

More information

Job Description. To lead and effectively manage the Empty Homes team which is responsible for:

Job Description. To lead and effectively manage the Empty Homes team which is responsible for: Job Description Post Title Post Number Service Area / Department SDU Accountable to (Line Manager) Responsible for (Direct Reports Post Title) Empty Homes Manager RT01008 Leasehold and Lettings Housing

More information

Responsibility Deal between Government and the waste and resource management sector. June 2011

Responsibility Deal between Government and the waste and resource management sector. June 2011 www.defra.gov.uk www.esauk.org Responsibility Deal between Government and the waste and resource management sector June 2011 Department for Environment, Food and Rural Affairs Nobel House 17 Smith Square

More information

Guidance for audit committees. The internal audit function

Guidance for audit committees. The internal audit function Guidance for audit committees The internal audit function March 2004 The Combined Code on Corporate Governance July 2003 C.3 Audit Committee and Auditors Main Principle: The board should establish formal

More information

System of Governance

System of Governance CEIOPS-DOC-29/09 CEIOPS Advice for Level 2 Implementing Measures on Solvency II: System of Governance (former Consultation Paper 33) October 2009 CEIOPS e.v. Westhafenplatz 1-60327 Frankfurt Germany Tel.

More information

The Risk Management strategy sets out the framework that the Council has established.

The Risk Management strategy sets out the framework that the Council has established. Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management

More information

Internal Audit Division

Internal Audit Division Internal Audit Division at the Financial Conduct Authority Information Pack April 2013 Contents of Information Pack A. Introduction B. Internal Audit Terms of Reference C. Organisation D. Skills and Competencies

More information

KENYA NATIONAL BUREAU OF STATISTICS RISK MANAGEMENT POLICY

KENYA NATIONAL BUREAU OF STATISTICS RISK MANAGEMENT POLICY KENYA NATIONAL BUREAU OF STATISTICS RISK MANAGEMENT POLICY SEPTEMBER 2009 Table of Contents Pg No. FOREWARD... ii PREFACE...iii CHAPTER ONE... 1 INTRODUCTION... 1 1.0 Background... 1 1.1 KNBS policy statement...

More information