1 SOUTHERN PARTNERSHIP GROUP Dunedin Hospital Redevelopment Overview and Stage 1 Project Brief Sign Off This document requires the following approvals: Southern Partnership Group Approved SPG 10 Nov 2015> Author Document Location Status Kieran Reilly Lotus Notes Capital and Operating/ Capital Project Dunedin/ Key Documents Final

2 Version History Version Date Summary of Changes /11/2015 Approved by SPG at their 10 Nov 2015 meeting Document Consultation The following stakeholders (internal or external) have been consulted with regarding the content of this document. Name Organisation/ Role Date Southern Steering Group MoH and Southern DHB joint group 3 Nov 2015 Southern Partnership Group Governance 10 Nov 2015 Confidentiality The information contained in this document is proprietary to the Southern Partnership Group. This document must not be used, reproduced, or disclosed to others except employees of the recipient of this document who have the need to know for the purposes of this assignment. Prior to such disclosure, the recipient of this document must obtain the agreement of such employees or other parties to receive and use such information as proprietary and confidential and subject to non-disclosure on the same conditions as set out above. The recipient by retaining and using this document agrees to the above restrictions and shall protect the document and information contained in it from loss, theft and misuse.

3 1) Purpose of this Document The purpose of this project brief is to provide an overview of Stage 1 of the project and seeks agreement, at a high level, on how the work will be managed. 2) Project Overview a) Project objectives The main objective for Stage One is to prepare a Strategic Assessment and Indicative Business Case that will provide an early indication of the best way forward to address issues with the facilities at the Dunedin Hospital campus. b) Context and Background A number of buildings on the Southern District Health Board s 1 Dunedin Hospital Campus site are not considered economically viable for relifing including the Children s Pavilion Building (built 1945), the Psychiatric Services Building (built 1935), the Fraser Building (built 1940) and the Clinical Services Building (built 1960s). Recent urgent maintenance issues with the existing facilities include the water tightness of the Clinical Services Building and a required roof replacement for the Fraser Building. For instance the Clinical Service Building s does not meet the standards for electrical wiring and protection of patient treatment areas (cardiac Protected Status ASNZ 3003:2011), nor for infection control and management of dirty laundry. In 2014, Dunedin Hospital lost its College of Intensive Care Medicine accreditation for specialist training. And in October 2015 the pathology lab and mortuary were closed due to asbestos with a cleanup also required in other areas of the building. Southern DHB commissioned Chow Hill & Sapere to develop a Service and Facilities Strategy for Dunedin Hospital facilities which it completed in March Southern DHB also recently completed development of a whole of health, system-wide Southern Strategic Health Plan It is mandatory that all major capital projects follow the standards and processes required by the Better Business Cases Model 2 (BBC). The Southern Partnership Group (SPG) has been commissioned to govern the redevelopment of hospital facilities for Southern District Health Board Dunedin including $11.5M of urgent interim works at the Dunedin and Wakari hospital campuses that was recently approved. The interim works include changes to the Gastroenterology and Audiology facilities as well as a programme of deferred maintenance. A further xxxx has been reserved in the Health Capital Envelope for redevelopment of the Dunedin Hospital Intensive Care Unit subject to 1 Southern DHB was created in 2010 as the result of a merger of Southland DHB and Otago DHB and employs approximately 4,500 staff. The DHB provides health services to a population of over 313,000 people (2015/16 estimate) who live in their catchment area which includes Invercargill City, Queenstown - Lakes District, Gore, rural Southland, Clutha, Central Otago, Maniototo, Waitaki District and Dunedin City. 2 BBC guidance is mandatory for all capital expenditure, lease and asset disposal proposal undertaken by Government Departments or Crown entities that require Cabinet approval (Cabinet Office Circular CO (10) 2:Capital Asset Management in Departments and Crown Entities Redevelopment of Dunedin Hospital Project Brief Stage 1 3

4 Southern DHB developing an Implementation Business Case that is approved by the Capital Investment Committee. Southern DHB will not be able to fund any of the capital development. A $300M potential capital cost has been signalled in the DHB s capital intentions for this project. Based on other rebuilds this project is expected to take 7-10 years to complete. 3) Reasons for this Project a) Mandate The Ministers of Health and Finance have approved the formation of the Southern Partnership Group to oversee the redevelopment of Dunedin Hospital (HR ). The Ministers of Health and Finance (HR ) also approved the urgent interim works including the redevelopment of the Gastroenterology and Audiology facilities and a programme of deferred maintenance. 3 These works and any additional approved capital projects for Southern DHB in Dunedin will be subject to the oversight of the Southern Partnership Group to ensure they align with the overall redevelopment. For Stage 1 of the project the Ministry of Health holds legal authority for any contracts. b) Project Drivers and Rational The Better Business Case process is focused on being smarter about how we invest for change as well as deliver better services and better outcomes for New Zealanders. It is based on robust planning, analysis, decision making, implementation and review. Strategies to manage expected growth, service changes, whole of service alignment and financial viability will need to be fully explored and agreed prior to approval of any capital works. The health partnership group model has elsewhere proved to be an effective and successful mechanism for ensuring that the business cases developed are robust, the outcomes are appropriate to the needs of the local population and that the options being put forward provide best value for public money. c) Key Benefits The key outcomes and benefits of this project will be covered in detail as part of producing the Strategic Assessment and Initial Business Case. 3 Gastroenterology - a redevelopment on Level 8 of the south wing of the Ward Block. The Audiology service will relocate to the Wakari campus. Redevelopment of Dunedin Hospital Project Brief Stage 1 4

5 4) Project Deliverables and Approach a) Project Scope The following table delineates the scope of this project. In Scope Determining the pathway forward to address issues with the facilities at the Dunedin Hospital campus. Progress reports to SPG on the approved urgent interim works at the Dunedin and Wakari campuses and any other relevant capital works Review of an Implementation Business Case for the Dunedin Hospital ICU and any subsequent progress reports Completing the requirements for Health Capital Approvals (based on the Better Business Case Model) and production of key documentation Development of a financial model for Southern DHB with a focus on hospital services RFPs for undertaking the Strategic Assessment and Indicative Business Cases Project Assurance Out of Scope (but has linkages to) Implementation of the Southern Strategic Health Plan The University of Otago s master site plan Health Reports and Cabinet papers (MoH/ Treasury) Southern DHB operational arrangements for the urgent interim works and ICU redevelopment (e.g. projects and internal steering groups) Processes related to CIC and the signoff processes required by Cabinet and the Ministers of Health and Finance. Regional Service Planning b) Project Approach The project approach is based on the requirements of the Better Business Cases Model. Appendix One summarises how the Better Business Case Model is applied to Health Capital Business Cases. A core team of Southern DHB and Ministry of Health staff will work in partnership to support the project. Consultants will be used, either where suitable expertise is not available or as required as part of the business case process. Redevelopment of Dunedin Hospital Project Brief Stage 1 5

6 c) High-Level Milestones and Deliverables Within the above scope, the initial timelines for the Stage 1 are listed. A more detailed project schedule will be developed as the RFPs are completed. # High-Level Milestone or Deliverable Target Date A Stage 1 Strategic Planning Phase 1. Completing a Risk Profile Assessment RPA (BBC) December Review the current site Masterplan December RFP for health planners and business case writers to support development of the Strategic Service Plan, Strategic Assessment and Service Plan 4. Appoint contractor to develop a financial model for Southern DHB December 2015 February Complete financial model for Southern DHB April Draft Strategic Service Plan for Southern DHB April Finalise the Strategic Assessment document covering the case for change June Finalise the Strategic Service Plan June Produce a Detailed Services Plan June 2016 B Proposal phase 10. RFP for Health Design Team to work on Indicative Business Case (commencing June 2016) April Finalise the Detailed Service Plan 4 March Update the Masterplan April Draft Indicative Business Case document produced for review April Define the Models of Care May Feasibility Study (Facility options) June Finalise the Indicative Business Case document June 2017 The timeframes for the remaining steps of the project have yet to be confirmed and will be detailed in project plans for Stage 2 and 3. The steps are: a) Developing the Detailed Business Case b) Developing an Implementation Business Case c) The Delivery Phase Design, Procurement, Construction 4 Refining the preferred service of models of care in detailed consultation with Departments, staff and the community. Redevelopment of Dunedin Hospital Project Brief Stage 1 6

7 d) Post Implementation Review Refer to Appendix for further information on the Health Business Cases. d) Assurance Assurance requirements are built into the Better Business Cases model. 1) A Risk Profile Assessment (RPA) will need to be completed at the commencement of the project. 2) Subject to the outcome of the RPA, Gateway Reviews 5 will need to be completed and the outcome discussed with SPG in December. These are independent and confidential peer review process that examine projects and programmes at key points in their lifecycles to assess their progress and to rate the likelihood of successful delivery of their outcomes. The key decision points (or gates ) are: Gate 0: Strategic Assessment Gate 1: Business Justification & Options - Indicative Business Case Gate 2: Delivery Strategy - Detailed Business Case Gate 3: Investment Approach Gate 4: Readiness for Service Gate 5: Operational Review & Benefits Realisation It is likely the project will be deemed of sufficient risk that it will be required to complete Gates 0 and 1 as part of Stage 1 of the project. The Southern Partnership Group will determine what other peer reviews of work are required. The Capital Investment Committee will review the Strategic Assessment and Indicative Business Case produced by the project. They will provide their independent advice to the Ministers of Health and Finance on these documents as part of the sign-off process. 5) Stakeholders, Organisational Implications and Handover a) Key Stakeholders The following stakeholders (internal and external) have been identified as playing a key role in the success of this project. This will be expanded on in a formal communications plan. Stakeholder Relationship to Project Initial Engagement Approach Cabinet Will formally sign off on each stage of the Better Business Officials will provide reports and attendance at meetings 5 Gateway is Cabinet-mandated for high risk capital projects and programmes run by Government departments and Crown Agents refer Redevelopment of Dunedin Hospital Project Brief Stage 1 7

8 Ministers of Health and Finance Capital Investment Committee (CIC) Southern Partnership Group (SPG) Southern DHB (including the Executive, Clinical Council and clinical leaders) Treasury Ministry of Health University of Otago (occupy 20% of the Dunedin campus) Case Model and any additional capital works Will provide to recommendations to Cabinet on each stage of the Better Business Case Model and any additional capital works Will review and provide the Ministers of Health and Finance with independent advice on the key business case documents produced by the project. Governance role for the project Partner to the project. Owner and end user of any completed capital works. Oversee the assurance requirements for the project and will provide official advice to joint Ministers Partner to the project. Will oversee the initial contract arrangements. Responsible for supporting both SPG and CIC and providing advice to joint Ministers. Share staff and students with Southern DHB. The Dunedin School of Medicine has its offices on the Dunedin Hospital Campus in the Ward Block. The University has its own Master Site Plan that includes a Health Precinct as required. Quarterly Reports are required from SPG to the joint Ministers. Reports and meetings with officials as required. This project is a high priority for CIC and the Ministry of Health. 6 CIC will also need progress reports on any approved capital work funded from the Health Capital Budget.. Orientation meeting and arrange meetings with key stakeholders in Dunedin. DHB management and staff need to be fully involved in all processes run by the project team. Southern DHB will be a joint sponsor of the project team, provide communications support for Southern DHB. Will attend the Southern Partnership Group and Steering Group This project is a high priority for CIC and the Ministry of Health. Will be a joint sponsor of the project team and provide communications support for SPG. Arrange meeting between SPG and University of Otago representatives to discuss ongoing input. Otago Polytechnic Provides clinical training Cover in communications plan Staff and Professional Associations DHB staff will raise issues and concerns with their own professional associations Cover in communication plan Staff and patients are the end users. Good staff involvement 6 One of the SPG members is also a member of CIC Redevelopment of Dunedin Hospital Project Brief Stage 1 8

9 Dunedin City Council Southern DHB community/ patients Media Rural Hospital Trusts, PHO and Alliance South and unions. Dunedin Hospital is a significant asset to the city and the Dunedin campus site is centrally located on a constrained site that is also bound by State Highway 1 on Cumberland Street. Central to any service planning work and the consumer of services at any new facilities The local media already have a strong focus on reporting on Southern DHB matters including service issues, the formation of the Southern Partnership Group. Southern DHB s financial deficit and the work of the Commissioners. Need to be involved in the strategic planning phase and clinical leadership is recognised as critical to completing the BBC processes. Arrange meeting between SPG and key council representatives to discuss ongoing input. 7 NZTA may also need to be involved in the future. Staff and patients are the end users. They will need to be focused on in the communications plan. The project will look to set up a website with publicly accessible information on it Cover in the communications plan. The project will look to set up a website with publicly accessible information on it. The Chair of SPG is the designated contact for media communications. Meetings to be set up by the Health Planners being appointed by RFP b) Stakeholder Engagement & Comms Plan As per the terms of reference for SPG: a) The Southern Partnership Group is to provide the Minister of Health, the Southern DHB and the Ministry with reasonable advance notice and the content of any media statements or reports to be publicly published. b) Partnership Group members, including ex officio members and members of advisory committees, and staff supporting the Hospital Redevelopment Partnership Group may not comment on the developments, to external individuals or organisations, including the media, without the prior agreement of the Chair. c) The Southern DHB Commissioner (or Board Chair) is the spokesperson for Southern DHB. A communications plan and protocols for sharing information will be developed by MoH communications staff working with Southern DHB communications staff. The communication plan will become part of the overall Stage 1 project plan. It may not be finalised until after meetings between SPG and the University of Otago and DCC are held. 7 One of the SPG members is currently a Dunedin City Councillor Redevelopment of Dunedin Hospital Project Brief Stage 1 9

10 c) Handover Approach The main deliverables from Stage 1 are the key business case documents and service plan for Dunedin which will be inputs to subsequent stages of the project. 6) Risks a) Project Dependencies There will need to be a review by the health planners and business case writer of key reports already commissioned and produced by Southern DHB including the Service and Facilities Strategy document and Strategic Health Plan The RFPs associated with the Strategic Assessment and Indicative Business Case will invite respondents to outline the processes they will run with Southern DHB within the set timeframes. Minimum levels of engagement will be specified. It is currently assumed they can be completed within the indicative timeframes otherwise they will delay the work. b) Other Key Risks The following risks have been identified as having the potential to delay progress of the project and/or impact on the ability to achieve the deliverables. Risk Description (If X happens, there is a risk of Y, meaning Z impact) The initial timelines assume that the work already completed by Southern DHB will shorten the usual processes in the Stage 1 of the project. Not all resource has yet been appointed to support the project and planning for involving Southern DHB staff in the Strategic Assessment Phase needs to be worked through as part of the RFP process. There has been relatively little communication with key stakeholders to date as the project has worked through its establishment processes. Misinformation may already be in circulation. The Health Planners appointed by RFP to work on Stage 1 will need to keep up to date with the work to implement the Southern Strategic Health Plan Risk Rating Medium Medium Medium Medium How Risk Will Be Managed The consultants will commence their work with a review of all relevant documentation produced by Southern DHB. They will be asked to meet with the SPG in February. As part of the RFP respondents are to outline the process they propose to run with Southern DHB. The Steering Group will be able to focus on the arrangements for involving Southern DHB staff. SPG will be kept updated at its meetings. Cover in communications plan and develop material on the scope of the project and key dates for wider dissemination. Create a website with publicly accessible information to be managed by the MoH s communications resource with links to Southern DHB communications. Will be managed as part of monthly reports to steering group and communications plan. Redevelopment of Dunedin Hospital Project Brief Stage 1 10

11 Given the long timeframes involved in capital projects there is a risk that the scope of work and approvals given are relitigated in the future. Medium Manage through good documentation and full consultation processes 7) Funding and Resourcing a) Funding Arrangements On 29 October the project was granted $1.6M from the Health Capital Envelope until 30 June This budget will be used for project establishment, supporting the Southern Partnership Group (including travel and meetings), Ministry of Health staff costs, assurance processes like Gateway Reviews as well as funding for additional project team resources (refer overpage). A separate budget bid for 2016/17 will need to be prepared in April Strategic Planning Stage(June 2016) Funding ($) Item Consultants Health Planner plus team xxxxxxx Strategic Service Plan Service Plan Strategic Assessment Financial analyst xxxxxxx Financial model Sundry travel for consultants xxxxxx Project Support Project manager xxxxxx Admin xxxxxx Communications xxxxx Communication Plan Website access Assurance Peer review QS xxxxx Review RFP evaluation Gateway/Assurance xxxxxx Gateway 0 Legal fees xxxxxx RFP evaluation Probity costs xxxxxx RFP evaluation Governance costs Exec Communication travel PCG travel Additional meetings Contingency xxxxxx xxxx xxxxx xxxxxx HRPG costs xxxxxx Total 1,599,960 Redevelopment of Dunedin Hospital Project Brief Stage 1 11

12 b) Resource Requirements The core project team members for undertaking the planning stage are detailed below. Name Peter Beirne Kieran Reilly Karen Irving Role Executive Director, Southern DHB Senior Project Manager, MOH Senior Advisor Capital MOH Additional key roles still to be appointed into the project team include Communications Support for SPG Consultants for the Strategic Assessment Phase including a) Health planners b) Business case writer(s) A contractor to develop a financial model Health Design Team to work on Indicative Business Case Both MOH and SDHB need dedicated communications support RFP November 2015 TBC RFP to appoint early 2016 NB Treasury will assist contractor RFP April ) Project Structure a) Project governance Minister of Health Minister of Finance Capital Investment Committee Southern Partnership Group Southern Steering Group Project Control Group Working Groups (TBC) Southern Partnership Group Members: Andrew Blair (Chair) Mr Andrew Connolly Redevelopment of Dunedin Hospital Project Brief Stage 1 12

13 Dr Tony Lanigan Richard Thomson Dr Margaret Wilsher Ex Officio Other attendees Secretariat John Hazeldine (MOH) Davin Hall (Treasury) Kathy Grant (Southern DHB Commissioner) Carole Heatly (Southern DHB CEO) Kieran Reilly (MOH) The terms of reference for the Southern Partnership Group have been approved by the Ministers of Health and Finance and will be discussed at the first meeting. Southern Steering Group Sponsors: Mhairi McHugh (MOH) or delegate Carole Heatly (Southern DHB CEO) or delegate Other attendees Sandra Boardman (Southern DHB) Peter Beirne (Southern DHB) Leanne Samuel (Southern DHB) Lexie O Shea (Southern DHB) Karen Irving (Ministry of Health) Kieran Reilly (Ministry of Health) Davin Hall (Treasury) An additional clinical representative from Southern DHB will also join the group. The role of the steering group is to support the project team and to ensure the Southern Partnership Group receives timely and appropriate information. The Project Control Group will provide a regular monitoring and catch-up forum for key members of the project team. As different workstreams commence they will report on progress to the MoH Project Manager through the control group. b) Reporting Requirements The reporting requirements will be elaborated on as the project team is built up and the communications plan developed. Initial arrangements are: Who reports To whom What is reported When SPG Ministers of Health and Finance 1) Written Progress Report (Secretariat to prepare) 2) Business Case 1) Quarterly From February Redevelopment of Dunedin Hospital Project Brief Stage 1 13

14 Documentation 2016 Southern DHB SPG Updates on the approved urgent interim works and any other requests to CIC Southern DHB CIC Updates on the approved urgent interim works and any other requests to CIC Ongoing as per SPG s meeting schedule Quarterly via SPG Project Manager SPG (via Steering Group) Progress Report and Risk Register Ongoing as per SPG s meeting schedule Project team. Work stream leaders and consultants Project Manager Participate in weekly update meetings (additional meetings may be required during establishment) Ongoing Reports on request or as specified in agreements with contractors MoH CIC Monthly reports to CIC Ongoing Redevelopment of Dunedin Hospital Project Brief Stage 1 14

15 Appendix One: Health Business Case Early engagement A business case approach encourages early engagement with stakeholder to confirm: Fit with strategy and need to invest The way forward with short-listed options That the best value option is affordable and deliverable and that the risks are acceptable Benefits of using the business case approach The key benefits for our stakeholders include: Decision makers better strategic alignment, value for money and evidence based assurance. Project managers early engagement and influence on direction. Business case developers clear expectations with flexibility and permission to take a risk-based, right size approach. Reviews early engagement and common language Stakeholder and public early engagement and influence on direction. Private sector suppliers certainty of implementation. How the Health Business Case approach works The Health Business Case approach is an adaption of the NZ Treasury s Better Business Case (BBC) model, which provides a structured way to develop an investment case in an inclusive way. The HBC will follow the principles of Treasury s BBC process using the key deliverables; strategic case, indicative business case, detailed business case and implementation business case. These are structured into 5 case models being strategic, economic, and commercial, financial and management. Redevelopment of Dunedin Hospital Project Brief Stage 1 15

16 Strategic Planning Phase (approx.12 months) Strategic Service Plan Reviews whole of health service operations over the next 10 years, providing a foundation for strategic clinical service planning and site specific capital developments. Ensuring the needs of the community are met by the DHB as an integrated and self-sufficient health service with integrated clinical service streams across a DHB. Providing a strategic view of service configuration, models of care and key enablers, determine the need going forward and possible strategies to manage growth, service changes, whole of service alignment and financial viability. Strategic Assessment (Business Case) Determines the key problems. It also provides stakeholders with a high degree of confidence that the investment they are considering aligns with the organisations strategic priorities identified in the strategic Service Plan and responds to a true business need. Stakeholders can consider the rationale for a proposed investment at an early stage and determine if the proposal warrants further business case development. Informed by ILM Proposal Phase (approx.12 Months) Service Plan Service delivery models are an adaption of an organisation's model of care and describes 'where and how work is to be carried out. Service Delivery models suit the local environment and resources to best meet the overarching organisational requirements. Redevelopment of Dunedin Hospital Project Brief Stage 1 16

17 Masterplan The purpose of a Master Plan Study is to identify and evaluate all the project planning options for the facility with consideration of the services to be provided, demographics, future trends, existing facilities, capital and recurrent costs and implementation strategy. Model of Care A model of care outlines best practice patient care delivery through the application of a set of service principles across identified clinical streams and patient flow continuums Indicative Business Case Provides decision-makers with an early indication for the preferred way forward. It confirms the case for change and the need to invest, identifies a wide range of options and recommends a preferred way forward for further development of the investment proposal, supported by a preferred short-listed options for further analysis. Planning and Evaluation Phase (approx.12 months) Feasibility The feasibility study is a detailed analysis of a preferred facility development strategy as determined in the master plan study. It should enable a DHB to fully determine the outcome, which will provide the most, cost efficient and effective delivery of its services. The preferred options for developing facilities to accommodate service delivery can then be determined. Functional Brief A description of the function to be accommodated and the relationships between functions for a proposed capital project. It should identify how the project meets the objectives and policies of the organisation Detailed Business Case The primary purpose of the Detailed Business Case is to recommend a preferred solution that optimises value for money. Implementation (approx. 12 months) Procurement Study Design development Implementation Business Case Delivery (approx. 18months 3 years) Construction Redevelopment of Dunedin Hospital Project Brief Stage 1 17

18 Post Delivery Benefits Realisation Post implementation review Post occupancy review Approval process Each completed business case will then go through an approval process. Initial endorsement by Southern Partnership Group, then endorsement from the Capital Investment Committee and finally approval from joint Ministers of Health and Finance and Cabinet if required. Redevelopment of Dunedin Hospital Project Brief Stage 1 18

UNSOLICITED PROPOSALS

UNSOLICITED PROPOSALS UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY

More information

Gateway review guidebook. for project owners and review teams

Gateway review guidebook. for project owners and review teams Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and

More information

I N C O N F I D E N C E

I N C O N F I D E N C E I N C O N F I D E N C E Cabinet Office CO (10) 2 Circular 1 August 2010 Intended for All Ministers All Chief Executives Speaker of the House General Manager, Parliamentary Service Controller and Auditor-General

More information

Construction Procurement Policy Project Implementation Process

Construction Procurement Policy Project Implementation Process Construction Procurement Policy Project Implementation Process Government of South Australia Copyright. January 2015 ISBN 978-0-7590-0217-3 The text in this document may be reproduced free-of-charge in

More information

New Cabinet Expectations: Investment and Asset Management, and Financial Authorities

New Cabinet Expectations: Investment and Asset Management, and Financial Authorities Cabinet CAB Min (15) 11/7A Copy No: Minute of Decision This document contains information for the New Zealand Cabinet. It must be treated in confidence and handled in accordance with any security classification,

More information

Chair Cabinet Committee on State Sector Reform and Expenditure Control

Chair Cabinet Committee on State Sector Reform and Expenditure Control Office of the Minister of State Services Chair Cabinet Committee on State Sector Reform and Expenditure Control REPORT OF THE GOVERNMENT CHIEF INFORMATION OFFICER ON THE REVIEW OF PUBLICLY ACCESSIBLE INFORMATION

More information

Single Stage Light Business Case Template

Single Stage Light Business Case Template Better Business Cases Single Stage Light Business Case Template Prepared by: Prepared for: Date: Version: Status: Better Business Cases Single Stage Light Business Case Template Document Control Document

More information

All Ministers Speaker of the House All Chief Executives Controller and Auditor-General

All Ministers Speaker of the House All Chief Executives Controller and Auditor-General Cabinet Office CO (15) YY Circular Intended for All Ministers Speaker of the House All Chief Executives Controller and Auditor-General Copies to All Senior Private Secretaries All Private Secretaries This

More information

Managing ICT contracts in central government. An update

Managing ICT contracts in central government. An update Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

The Transport Business Cases

The Transport Business Cases Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Ministry Of Health Registration of Interest

Ministry Of Health Registration of Interest Ministry Of Health Registration of Interest Intermediaries Social Bond Pilot(s) Part 1 Instructions and Supporting Information What s inside? Introduction to Social Bonds Purpose of the ROI Instructions

More information

Which MPA Assurance Review?

Which MPA Assurance Review? Which MPA Assurance? A guide to choosing which MPA Assurance s to include in the Integrated Assurance and Approvals Plan for your Major Project Version 1.0 March 2012 Copyright and contacts Crown copyright

More information

Electricity Reform Project

Electricity Reform Project Electricity Reform Project Governance Arrangements July 2012 Department of Treasury and Finance Contents 1. Introduction... 2 2. Project Governance... 3 3. Work Streams... 4 4. Project Timeline... 5 5.

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

INTEGRATED PLANNING AND REPORTING

INTEGRATED PLANNING AND REPORTING Government of Western Australia Department of Local Government INTEGRATED PLANNING AND REPORTING Framework and Guidelines Integrated Planning and Reporting Framework and Guidelines p1. Contents Foreword

More information

Appendix 1 Business Case to Support the Relocation of Mental Health Inpatient Services in Manchester (Clinical Foreword and Executive Summary)

Appendix 1 Business Case to Support the Relocation of Mental Health Inpatient Services in Manchester (Clinical Foreword and Executive Summary) Appendix 1 Business Case to Support the Relocation of Mental Health Inpatient Services in Manchester (Clinical Foreword and Executive Summary) Together we are better Foreword by the Director of Nursing

More information

TRUST BOARD. Date of Meeting: 05/04/2011 Enclosure: 5

TRUST BOARD. Date of Meeting: 05/04/2011 Enclosure: 5 TRUST BOARD Date of Meeting: 05/04/2011 Enclosure: 5 Title of Report: Merger and Acquisition Update Agenda Item No: 7.1 Aims: This report informs and updates the Board on the development of the process

More information

Procurement, Contracting and Contract Management Policy

Procurement, Contracting and Contract Management Policy Procurement, Contracting and Contract Management Policy Corporate policy 8.4 Responsible Officer: Group Manager Accounting and Taxation Policy Custodian: Chief Finance Officer Division: Finance and Resources

More information

ANALYSIS FOR OUTCOMES BETTER USE OF DATA TO IMPROVE OUTCOMES

ANALYSIS FOR OUTCOMES BETTER USE OF DATA TO IMPROVE OUTCOMES Chair Cabinet Committee on State Sector Reform and Expenditure Control ANALYSIS FOR OUTCOMES BETTER USE OF DATA TO IMPROVE OUTCOMES Purpose 1. This paper reports back on business case work to develop a

More information

John A Manzoni Chief Executive of the Civil Service. Email chief.executive@cabinetoffice.gov.uk

John A Manzoni Chief Executive of the Civil Service. Email chief.executive@cabinetoffice.gov.uk John A Manzoni Chief Executive of the Civil Service Email chief.executive@cabinetoffice.gov.uk 70 Whitehall London SW1A 2AS Telephone +44 (0) 20 7271 8822 Web www.cabinetoffice.gov.uk Paul Chinn Cabinet

More information

Health Facilities Capital Program Manual. Version 1.0

Health Facilities Capital Program Manual. Version 1.0 Health Facilities Capital Program Manual Version 1.0 TABLE OF CONTENTS TABLE OF CONTENTS... 2 1.0 INTRODUCTION... 9 1.1 Health Facilities Capital Program... 9 1.1.1 Major Capital Projects Total Project

More information

Audit and Performance Committee Report

Audit and Performance Committee Report Audit and Performance Committee Report Date: 3 February 2016 Classification: Title: Wards Affected: Financial Summary: Report of: Author: General Release Maintaining High Ethical Standards at the City

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Project Scope. Background

Project Scope. Background Project Scope Project Name: Cancer Centre Collaboration Project Project Description: Project Leader: Robert Bull Project Code: Project End Date: May 2010 Version: 6 (Draft) Version Date: 19/01/10 Background

More information

Human Resources Strategic Plan

Human Resources Strategic Plan OTAGO & SOUTHLAND DISTRICT HEALTH BOARDS Human Resources Strategic Plan 2009-2012 March 2009 HUMAN RESOURCES STRATEGIC PLAN 2009 2012 Contents Executive Summary...2 1. Introduction...3 2. Human Resources

More information

Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development)

Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development) Meeting: Cabinet Date: 6 October 2005 Subject: Governance of the Business Transformation Partnership Responsible Officer: Executive Director (Business Development) Contact Officer: Portfolio Holder: Key

More information

Information Governance Strategy and Policy. OFFICIAL Ownership: Information Governance Group Date Issued: 15/01/2015 Version: 2.

Information Governance Strategy and Policy. OFFICIAL Ownership: Information Governance Group Date Issued: 15/01/2015 Version: 2. Information Governance Strategy and Policy Ownership: Information Governance Group Date Issued: 15/01/2015 Version: 2.0 Status: Final Revision and Signoff Sheet Change Record Date Author Version Comments

More information

Performance audit report. Ministry of Education: Management of the school property portfolio

Performance audit report. Ministry of Education: Management of the school property portfolio Performance audit report Ministry of Education: Management of the school property portfolio Office of the Auditor-General Private Box 3928, Wellington Telephone: (04) 917 1500 Facsimile: (04) 917 1549

More information

Request for Proposal. Supporting Document 3 of 4. Contract and Relationship Management for the Education Service Payroll

Request for Proposal. Supporting Document 3 of 4. Contract and Relationship Management for the Education Service Payroll Request for Proposal Supporting Document 3 of 4 Contract and Relationship December 2007 Table of Contents 1 Introduction 3 2 Governance 4 2.1 Education Governance Board 4 2.2 Education Capability Board

More information

Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles

Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles Department of Infrastructure and Planning: Governance Framework for Infrastructure Delivery Special Purpose Vehicles Governance Framework for Special Purpose Vehicles Table of Contents Executive Summary...3

More information

Authorised by the Victorian Government 1 Treasury Place, Melbourne, 3002

Authorised by the Victorian Government 1 Treasury Place, Melbourne, 3002 Project Governance Project Governance The Secretary Department of Treasury and Finance 1 Treasury Place Melbourne Victoria 3002 Australia Telephone: +61 3 9651 5111 Facsimile: +61 3 9651 5298 www.dtf.vic.gov.au

More information

Standardised Job Descriptions for Infrastructure Development and Technical Services Units of Provincial Health Departments as funded through the

Standardised Job Descriptions for Infrastructure Development and Technical Services Units of Provincial Health Departments as funded through the Standardised Job Descriptions for Infrastructure Development and Technical Services Units of Provincial Health Departments as funded through the Division of Revenue Act March 2015 1 JOB DESCRIPTION JOB

More information

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1

DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1 DRAFT PLANNING THE OPENING OF A ROAD PROJECT GUIDELINE 1 Guideline: DRAFT Planning the opening of a road project guideline Version: 1.1 Issue: September 2009 Approved By: Phil Margison General Manager,

More information

Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans

Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans A guide to implementing integrated assurance and approvals Version 1.0 - May 2011 Contents Introduction 03 Integrated

More information

Common Student Information System for Schools and School Boards. Project Summary

Common Student Information System for Schools and School Boards. Project Summary for Schools and School Boards May 2007 Table of Contents 1. Executive Summary...... 3 2. Project Background, Rationale, Benefits and Scope... 4 3. Procurement Process... 8 4. The Final Agreement. 10 5.

More information

Approved by Management Committee 24/03/11 Strategy Document

Approved by Management Committee 24/03/11 Strategy Document ELHA POLICY Date Issued May 2007 Last Revised March 2011 Department Asset Management Title Asset Management Strategy Objective To outline the Association s strategy for managing its assets Responsible

More information

Consultancy spending controls: Initial Guidance to NHS Trusts

Consultancy spending controls: Initial Guidance to NHS Trusts Consultancy spending controls: Initial Guidance to NHS Trusts 1. Summary 1.1 The NHS Trust Development Authority (NHS TDA), Monitor and NHS England (NHSE) are jointly implementing a controls process over

More information

Auckland District Health Board Minutes

Auckland District Health Board Minutes Auckland District Health Board Minutes Minutes of the Auckland District Health Board meeting held on Wednesday, 12 September 2012 in the A+ Trust Room, Clinical Education Centre, Level 5, Auckland City

More information

Performance audit report. Progress with priorities for health information management and information technology

Performance audit report. Progress with priorities for health information management and information technology Performance audit report Progress with priorities for health information management and information technology Office of the Auditor-General Private Box 3928, Wellington Telephone: (04) 917 1500 Facsimile:

More information

Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change

Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change For Decision Member Champion(s): Cllr A Alford, Corporate - Director:

More information

Application of the Framework is relevant to clinical networks, units and health service teams within each service or organisation.

Application of the Framework is relevant to clinical networks, units and health service teams within each service or organisation. NSW Health Performance Framework The NSW Health Performance Framework, encompassing Service Agreements, Service Compacts Performance Review meetings and associated processes, is now well accepted across

More information

Consultation Document. Ashburton & Rural Leadership: Proposal for Change

Consultation Document. Ashburton & Rural Leadership: Proposal for Change Consultation Document Ashburton & Rural Leadership: Proposal for Change April 2015 For information on this paper, please contact: Name: Email: Michael Frampton, General Manager People and Capability Kelly

More information

Benefits realisation. Gate

Benefits realisation. Gate Benefits realisation Gate 5 The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and Planning, January 2010. The Queensland

More information

Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide

Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide Standard 1 Governance for Safety and Quality in Health Service Organisations Safety and Quality Improvement Guide 1 1 1October 1 2012 ISBN: Print: 978-1-921983-27-6 Electronic: 978-1-921983-28-3 Suggested

More information

for appointment as Skills Laboratory Clinical Director / DSM Undergraduate Medicine Clinical Skills Director (Part-time) DUNEDIN SCHOOL OF MEDICINE

for appointment as Skills Laboratory Clinical Director / DSM Undergraduate Medicine Clinical Skills Director (Part-time) DUNEDIN SCHOOL OF MEDICINE A07/46 INFORMATION FOR CANDIDATES for appointment as Skills Laboratory Clinical Director / DSM Undergraduate Medicine Clinical Skills Director (Part-time) DUNEDIN SCHOOL OF MEDICINE General Information

More information

FINANCIAL ADVISERS REGULATION: VOLUNTARY AUTHORISATION

FINANCIAL ADVISERS REGULATION: VOLUNTARY AUTHORISATION OFFICE OF THE MINISTER OF COMMERCE The Chair CABINET ECONOMIC GROWTH AND INFRASTRUCTURE COMMITTEE FINANCIAL ADVISERS REGULATION: VOLUNTARY AUTHORISATION PROPOSAL 1 I propose that regulations be promulgated

More information

Project Appraisal and Scrutiny Committee Recommendation STRATEGY & RESOURCES 23 MARCH 2015

Project Appraisal and Scrutiny Committee Recommendation STRATEGY & RESOURCES 23 MARCH 2015 Cambridge City Council Project Appraisal and Scrutiny Committee Recommendation Project Name: Telecommunications To: Report by: Scrutiny committee: Wards affected: Recommendation/s Executive Councillor

More information

Business continuity management policy

Business continuity management policy Business continuity management policy health.wa.gov.au Effective: XXX Title: Business continuity management policy 1. Purpose All public sector bodies are required to establish, maintain and review business

More information

Good practice Public Service Communications Unit Communications Function Review 2009

Good practice Public Service Communications Unit Communications Function Review 2009 Final text: 06/04/10 Good practice Public Service Unit Function Review 2009 Purpose The purpose of this paper is to outline recommendations on good practice communications unit models and guidelines for

More information

External Audit BV Performance Report: Delivering Change Management and Financial Sustainability

External Audit BV Performance Report: Delivering Change Management and Financial Sustainability CLACKMANNANSHIRE COUNCIL THIS PAPER RELATES TO ITEM 05 ON THE AGENDA Report to: Resources and Audit Committee Date of Meeting: 24 September 2015 Subject: External Audit BV Performance Report: Delivering

More information

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES

PROJECT PROCUREMENT PROCEDURES AND GUIDELINES CAPITAL ASSET MANAGEMENT PROJECT PROCUREMENT PROCEDURES AND GUIDELINES June 2003 Updated June 20, 2003 Ministry of Education Province of British Columbia TABLE OF CONTENTS EXECUTIVE SUMMARY... iii 1.0

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

(1) To approve the proposals set out in paragraphs 3.1-2 to ensure greater transparency of partnership board activity; and

(1) To approve the proposals set out in paragraphs 3.1-2 to ensure greater transparency of partnership board activity; and Agenda Item No. 7 Governance Committee 23 November 2015 Partnership Governance for Contract Management Report by Director of Law Assurance and Strategy Executive Summary This report sets out some areas

More information

Logan City Council. Strategic Planning and Performance Management Framework

Logan City Council. Strategic Planning and Performance Management Framework Logan City Council Strategic Planning and Performance Management Framework 1 Table of contents 1. Overview 3 a) Purpose 3 b) Key Features 3 2. Context 4 a) National Framework for Sustainability 4 b) Elements

More information

CRD Wastewater Treatment Project: Observations and Recommendations on Project Governance

CRD Wastewater Treatment Project: Observations and Recommendations on Project Governance Appendix A - Governance May 3, 2016 CRD Wastewater Treatment Project: Observations and Recommendations on Project Governance Background In early April 2016, the Minister of Communities, Sport and Cultural

More information

Frequently Asked Questions regarding European Innovation Partnerships

Frequently Asked Questions regarding European Innovation Partnerships May 2012 Frequently Asked Questions regarding European Innovation Partnerships 6 December 2010 FAQs 1. What are the objectives behind European innovation partnerships? 2. What concrete benefits can be

More information

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini)

THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) PAGE 1 THE APPLICATION OF A VALUE ASSURANCE SYSTEM TO OIL & GAS DEVELOPMENT PROJECTS (Guido Mattu, Franca Marini) Ing. Guido Mattu More than 25 years experience in Engineering and Project Management activities

More information

London Borough of Bromley COMMISSIONING - PROPOSED TOTAL FACILITY MANAGEMENT CONTRACT

London Borough of Bromley COMMISSIONING - PROPOSED TOTAL FACILITY MANAGEMENT CONTRACT Report No. DRR14/089 London Borough of Bromley PART 1 - PUBLIC Decision Maker: Executive Date: 15 th October 2014 Decision Type: Non-Urgent Executive Key Title: COMMISSIONING - PROPOSED TOTAL FACILITY

More information

JOINT CORE STRATEGY PROGRAMME MANAGEMENT FRAMEWORK GOVERNANCE PROCESSES AND PROCEDURES. Draft

JOINT CORE STRATEGY PROGRAMME MANAGEMENT FRAMEWORK GOVERNANCE PROCESSES AND PROCEDURES. Draft APPENDIX 1 JOINT CORE STRATEGY PROGRAMME MANAGEMENT FRAMEWORK GOVERNANCE PROCESSES AND PROCEDURES Draft CONTENTS 1. INTRODUCTION 2. SCOPE 3. PROGRAMME AND PROJECT MANAGEMENT GOVERNANCE 4. PROGRAMME MANAGEMENT

More information

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

More information

Stage. service. Procure a solution. management. communication

Stage. service. Procure a solution. management. communication Stage 4 communication management service Procure a solution Confi rm a procurement approach and select suppliers that offer best overall value for money (including risk and reward trade-offs). Key better

More information

Advisory Note - October 2005. Disclosure and management of conflict of interest for advisers

Advisory Note - October 2005. Disclosure and management of conflict of interest for advisers Advisory Note - October 2005 Disclosure and management of conflict of interest for advisers The Secretary Department of Treasury and Finance 1 Treasury Place, Melbourne Victoria 3002 Australia Telephone:

More information

TERMS OF REFERENCE - MAJOR EVENTS PANEL

TERMS OF REFERENCE - MAJOR EVENTS PANEL TERMS OF REFERENCE - MAJOR EVENTS PANEL OVERVIEW The Major Events Panel is a specialist advisory body to the UK Sport Board and its Major Events Team. Its main purpose is to represent the interests of

More information

Frequently asked questions

Frequently asked questions Frequently asked questions Frequently asked questions on the Procurement manual and procedures. Physical works, professional services and public transport How do you define value for money? The manual

More information

Project Managers Operations

Project Managers Operations Date: 15 December 2015 Job Title: Department: Location: Senior Project Manager Operations (Interim Projects & logistics) Project Team North Shore Hospital site, Takapuna, Auckland and Waitakere Hospital;

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

Public Records Review

Public Records Review Project Initiation Document (PID) PROJECT NAME: PROJECT REFERENCE: Public Records Review NAS5/B56 PRESENTED BY: Project Manager QUALITY REVIEWED BY: Project Board and Advisory Group (as required) DATE

More information

IT Infrastructure Outsourcing Helps Shell Lower Costs, Drive Increased Efficiency

IT Infrastructure Outsourcing Helps Shell Lower Costs, Drive Increased Efficiency IT Infrastructure Outsourcing Helps Shell Lower Costs, Drive Increased Efficiency With more than 104,000 employees in more than 110 countries, Shell plays a key role in helping to meet the world s growing

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

Procurement Functional Leadership Progress Report April 2015 to September 2015

Procurement Functional Leadership Progress Report April 2015 to September 2015 The Chair Cabinet State Sector Reform and Expenditure Control Committee Office of the Minister for Economic Development Procurement Functional Leadership Progress Report April 2015 to September 2015 Proposal

More information

A Question of Balance

A Question of Balance A Question of Balance Independent Assurance of Information Governance Returns Audit Requirement Sheets Contents Scope 4 How to use the audit requirement sheets 4 Evidence 5 Sources of assurance 5 What

More information

Project Management Fact Sheet:

Project Management Fact Sheet: Project Management Fact Sheet: Steering Committee nuts and bolts Version: 1.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It

More information

Health Purchasing Policy 2. Procurement Strategic Analysis

Health Purchasing Policy 2. Procurement Strategic Analysis Health Purchasing Policy 2. Procurement Strategic Analysis Determining the market dynamics, complexity of procurement and aligning capability 26 June 2014 1 Health Purchasing Policy 2. Procurement Strategic

More information

The STFC Project Management Framework

The STFC Project Management Framework The STFC Project Management Framework Version 4 April 2016 For further information contact: Tony Medland, Programmes Directorate (tony.medland@stfc.ac.uk) Matt Fletcher, National Laboratories Directorate

More information

IT1T Integrated Recruitment Systems 2015

IT1T Integrated Recruitment Systems 2015 UCD IT Services IT1T Integrated Recruitment Systems 2015 Project Initiation Document Version 1.0 2 December 2014 Version History Version Date Summary of Changes Changed by 1.0 02/12/2014 Initial Draft

More information

Note that the following document is copyright, details of which are provided on the next page.

Note that the following document is copyright, details of which are provided on the next page. Please note that the following document was created by the former Australian Council for Safety and Quality in Health Care. The former Council ceased its activities on 31 December 2005 and the Australian

More information

White Paper. PPP Governance

White Paper. PPP Governance PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting

More information

Governance, Risk and Best Value Committee

Governance, Risk and Best Value Committee Governance, Risk and Best Value Committee 2.00pm, Wednesday 23 September 2015 Internal Audit Report: Integrated Health & Social Care Item number Report number Executive/routine Wards Executive summary

More information

Information Governance Strategy & Policy

Information Governance Strategy & Policy Information Governance Strategy & Policy March 2014 CONTENT Page 1 Introduction 1 2 Strategic Aims 1 3 Policy 2 4 Responsibilities 3 5 Information Governance Reporting Structure 4 6 Managing Information

More information

Title: Funding London Business Plan 2014/15 and Governance Changes [Funding London is the new trading name of SME Wholesale Finance London Ltd]

Title: Funding London Business Plan 2014/15 and Governance Changes [Funding London is the new trading name of SME Wholesale Finance London Ltd] REQUEST FOR MAYORAL DECISION MD1447 Title: Funding London Business Plan 2014/15 and Governance Changes [Funding London is the new trading name of SME Wholesale Finance London Ltd] Executive Summary: In

More information

City of Cardiff Council Improving Scrutiny Project: Project Brief, January 2015

City of Cardiff Council Improving Scrutiny Project: Project Brief, January 2015 APPENDIX A City of Cardiff Council Improving Scrutiny Project: Project Brief, January 2015 Project Purpose Cardiff is proud of its scrutiny arrangements and the important part scrutiny plays in Council

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

Section 6. Strategic & Service Planning

Section 6. Strategic & Service Planning Section 6 Strategic & Service Planning 6 Strategic & Service Planning 6.1 Strategic Planning Responsibilities Section 6 Strategic & Service Planning 6.1.1 Role of Local Health Districts and Specialty

More information

Board Charter. HCF Life Insurance Company Pty Ltd (ACN 001 831 250) (the Company )

Board Charter. HCF Life Insurance Company Pty Ltd (ACN 001 831 250) (the Company ) Board Charter HCF Life Insurance Company Pty Ltd (ACN 001 831 250) (the Company ) Board approval date: 27 October 2015 Contents 1. Introduction and Purpose of this Charter...1 2. Role of the Board...1

More information

Interim Guidelines for the Provision of Infrastructure and Capital Investments through Public Private Partnerships:

Interim Guidelines for the Provision of Infrastructure and Capital Investments through Public Private Partnerships: Interim Guidelines for the Provision of Infrastructure and Capital Investments through Public Private Partnerships: Procedures for the Assessment, Approval, Audit and Procurement of Projects Table of Contents

More information

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper december 08 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The NSW Government is committed to the ongoing improvement of public services by ensuring

More information

Report on Archives New Zealand s line-by-line Review. February 2009 Version 1.2

Report on Archives New Zealand s line-by-line Review. February 2009 Version 1.2 Report on Archives New Zealand s line-by-line Review February 2009 Version 1.2 1. Background Formation of Archives New Zealand 1.1. The National Archive was formally established by the Archives Act 1957

More information

Risk Management Policy and Framework

Risk Management Policy and Framework Risk Management Policy and Framework December 2014 phone 1300 360 605 08 89589500 email info@centraldesert.nt.gov.au location 1Bagot Street Alice Springs NT 0870 post PO Box 2257 Alice Springs NT 0871

More information

Collaborative development of evaluation capacity and tools for natural resource management

Collaborative development of evaluation capacity and tools for natural resource management Collaborative development of evaluation capacity and tools for natural resource management Helen Watts (Adaptive Environmental Management, formerly NSW Department of Environment and Climate Change) Sandra

More information

(Cabinet 10 December 2014) The supply of Hard Facilities Management (Hard FM) maintenance services to the County Council estate

(Cabinet 10 December 2014) The supply of Hard Facilities Management (Hard FM) maintenance services to the County Council estate Somerset County Council Cabinet 10 th December 2014 (Cabinet 10 December 2014) Paper H Item No. 11 The supply of Hard Facilities Management (Hard FM) maintenance services to the County Council estate Cabinet

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Agenda Item No: 6.1 Enclosure: 3 17 January 2012 Intended Outcome:

Agenda Item No: 6.1 Enclosure: 3 17 January 2012 Intended Outcome: TRUST BOARD Date of Meeting: Agenda Item No: 6.1 Enclosure: 3 17 January 2012 Intended Outcome: For noting For information For decision Title of Report: Progress Report for the Acquisition of North Cumbria

More information

The overall aim for this project is To improve the way that the University currently manages its research publications data

The overall aim for this project is To improve the way that the University currently manages its research publications data Project Plan Overview of Project 1. Background The I-WIRE project will develop a workflow and toolset, integrated into a portal environment, for the submission, indexing, and re-purposing of research outputs

More information

BSC Implementation Plan Incorporating Organisational Structure Review; Community Satisfaction Survey; Development Application Processing Survey

BSC Implementation Plan Incorporating Organisational Structure Review; Community Satisfaction Survey; Development Application Processing Survey Develop an engagement Notify employees affected of program (which includes change Council's duty to notify) with Notify unions to which they key stakeholders regarding the belong introduction of structural

More information

AUDITOR-GENERAL S AUDITING STANDARD 4 (REVISED) THE AUDIT OF SERVICE PERFORMANCE REPORTS. Contents

AUDITOR-GENERAL S AUDITING STANDARD 4 (REVISED) THE AUDIT OF SERVICE PERFORMANCE REPORTS. Contents AUDITOR-GENERAL S AUDITING STANDARD 4 (REVISED) THE AUDIT OF SERVICE PERFORMANCE REPORTS Contents Page Introduction 3-8301 Scope of this Statement 3-8301 Application 3-8303 Objectives 3-8304 Definitions

More information