FATMA COLASAN. Past President, ATCEA Former EC Member, FIDIC Member of Business Practice Committee, FIDIC

Size: px
Start display at page:

Download "FATMA COLASAN. Past President, ATCEA Former EC Member, FIDIC Member of Business Practice Committee, FIDIC"

Transcription

1 FATMA COLASAN Past President, ATCEA Former EC Member, FIDIC Member of Business Practice Committee, FIDIC

2 CASE STUDY DISPUTE ADJUDICATION Construction Works of the Potable Water Supply Facility of the city of XXX -TURKEY

3 Contents of the DAB DECISION REPORT 1. Definitions 2. General information 3. Appointment of the DAB 4. Disputes to be resolved 5. Examinations of the DAB 6. Developments 7. Explanations of the DAB 8. DAB Decision

4 Definitions Employer (Client): Municipality of XXX Contractor: A national firm Engineer: An international firm PWSF: Potable Water Supply Facility GCC: General Conditions of Contract (FIDIC Yellow Book,1999) FCG: FIDIC Contracts Guide (2000) SC: Sub-Clause EoT: Extension of Time for Completion etc.

5 General information Project: Construction Works of the Potable water Supply Facility of the City of XXX inturkey (Design-Build project) Conditions of Contract for Design-Build (Yellow Book) Contract Date: Dec. 18, 2014, Base Date: Nov.20, 2014 Reference day: 28 days before Base Date: Oct.23, 2014 Accepted Contract Amount= , 75 Time for Completion: 480 days DAB (Dispute Adjudication Board) Ad-hoc, one sole member DAB Appointing Entity : ATCEA, Association of Turkish Consulting Engineers and Architects

6 Appointment of the DAB Because the Engineer did not answer the Contractor and did not nominate a candidate to act as the DAB member; after waiting for a reasonable time, the Contactor applied to ATCEA, the Appointing Entity, to name a DAB member. ATCEA appointed the DAB, as one sole member in conformance with the Contract.

7 Disputes to be resolved Claim No: 1 (Dispute 1) Time extension of 24 days days and payment of 47,500,00 arising from unpaid extra works Claim No: 2 (Dispute 2) Time extension of 28 days and payment of cost plus profit, arising from two consecutive floods at the construction site Claim No: 5 (Dispute 3) (Ongoing Claim) Time extension of 213 days and payment of 1.560,500,00 arising from Interference With Tests on Completion Claim No: 8 (Dispute 4) Payment of ,27 arising from Unjustified Deductions in the IPC s

8 Examinations of the DAB All submitted documents by the Parties, namely the Contract (including FIDIC Conditions of Contract for Plant and Design-Build, Employer s Requirements, Technical Specifications, addenda, appendices, drawings etc.), written correspondences between the Parties, minutes of monthly meetings, progress reports, relevant payment certificates, third body statements/comments (user, municipality etc.), DAB s notes taken during two Hearings, and the similar.

9 Developments Two consecutive floods occurred at the construction site on Oct , 2015 and Nov , 2015, which brought mud and debris to the site, causing the Contractor to lose time and costs of remedial works. The Contractor gave Notice to the Engineer for both of the two floods on Nov.03, 2015 under GCC-SC 19.2 (Notice of Force Majeure) and 20.1 (Contractor s Claims). The Contractor sent his relevant Claim to the Engineer on Dec.07, 2015 supported by photos of the consequences of the flood at the site and claimed 28 days of Extension of Time for the two floods, plus cost and profit. He emphasized that the situation, referring to flood, exactly fitted in the conditions of Force Majeure, Clause 19 of the Yellow Book.

10 Developments (cont.) Precipitation recordings in the city of XXX for the first flood was missing owing to the mis-functioning of the State Meteorology Institution s (DMI) equipment at that time, which was testified by DMI as well. The Engineer replied on Jan. 18,2016 and said that, in the absence of required substantiation/documentary evidence, he cannot accept the notice for any agreement or Determination. In his reply, instead of Force Majeure, he referred to GCC-SCs 4.10, 4.11, 4.12 (Unforeseeable Physical Conditions), 17.2 and 17.3 (Contactor s Care of the Works). He emphasized that according to GCC-SC 17.2, the Contractor was responsible for the care of the Works and Goods at the site. The Contractor made a full claim for the second time on May 18, 2016 for Extension of Time 28 days and cost plus profit, but this time he refered to GCC-SC 8.4.c (Exceptionally Adverse Climatic Conditions) upon the Engineer s ignoring the Contractor s reference to Force Majeure and instead, referring to Unforeseeable Physical Conditions.

11 Developments (cont.) Engineer replied that it was the Contractor s responsibility to take precautions against such events. Contractor argueed that he was not responsible for preventing the flood which started a kilometer away from the construction site owing to overflowing of an open drainage channel after the heavy rain and storm. The second flood s precipitation recordings, as taken from DMI showed that in the city of XXX, the rainfall amount was 29.6 kg/m2 on Nov.01, 2015 and 44.0 kg/m2 on Nov.02,2015. On August 18,2016 the Engineer gave his Determination and rejected the Claim totally; provided an Evaluation Report connected to his Determination. In his report he statedthat the rainfalls in October and November cannot be considered as Exceptionally Adverse Climatic Conditions. The Contractor gave a final Notice on June 10,2017 to the Engineer stating that he intends to refer the dispute to DAB.

12 Explanations of the DAB Claim: Time extension of 28 days and cost plus profit, arising from two consecutive floods at the construction site Contractor s original claim for two consecutive floods refers to GCC-SCs 19.1, 19.4 Force Majeure. Engineer in his reply rejects the claim by referring to GCC-SCs 4.10, 4.11, Unforeseeable Physical Conditions - and not to Force Majeure, also refers to 17.2 and 17.3 Contactor s Care of the Works. Contractor repeats his claim but upon Engineer s reply, this time refers to GCC-SC 8.4.c - Exceptionally Adverse Climatic Conditions.

13 Explanations of the DAB (cont.) Engineers s response on Jan.18,2016 refers to Sub-clause 4.12 which explains Unforeseeable Physical Conditions excluding climatic conditions. Therefore the Engineer s reference to Unforeseeable Physical Conditions at the site and his determination have no grounds with respect to the mentioned Sub-clause of the Yellow Book. Although the Contractor s first Notice and Claim refers to flood and to the Force Majeure Clause; upon the Engineer s response, the Contractor changed his Claim and submitted it for the second time, but this time based the claim on Exceptionally Adverse Climatic Conditions (GCC-SC 8.4.c), instead of Force Majeure.

14 Explanations of the DAB (cont.) GCC Sub-Clause 19.1 (Definition of Force Majeure) reads as follows: Force Majeure means an exceptinal event or cicumstance: (a) which is beyond a Party's control, (b) which such Party could not reasonably have provided against before entering into the Contract, (c) which, having arisen, such Party could not reasonably have avoided or overcome, and (d) which is not substantially attributable to the other Party. Force Majeure may include, but is not limited to, exceptional events or circumstances of the kind listed below, so long as conditions (a) to (d) above are satisfied:.. (v) natural catastrophes such as earthquake, hurricane, typhoon or volcanic activity.

15 Explanations of the DAB (cont.) SC-19.2 Notice of Force Majeure The notice shall be given within 14 days after the Party became aware, or should have become aware, of the relevant event or circumstance constituting Force Majeure. SC-19.4 Consequences of Force Majeure If the Contractor is prevented from performing any of his obligations of which Notice has been given under SC-19.2, and suffers delay and/or incurs Cost by reason of such Force Majeure, Contractor shall be entitled to EoT

16 Explanations of the DAB (cont.) The DAB considers that the Claim fits into GCC Clause 19 (Force Majeure) in general; because it is not the precipitation itself at the site which created a Force Majeure situation, but the flood which caused the flow of mud and debris to the site from the open drainage channel which is close to the site. Therefore flood caused by rainfall elsewhere (not the rainfall itself at the site), being considered a catastrophe fits in the definition of Force Majeure, as flood also might have been listed by FIDIC in addition to the ones given, following the words such as. Force Majeure is not caused by the precipitation itself at the site, but the flood coming from elsewhere. On the other hand, having not given the Notice of Force Majeure in 14 days (GCC-SC 19.2), makes the Contractor lose his rights for the October flood. Since the Contractor gave Notice on Nov.03,2015, 20 days after the October flood, he was late by = 6 days. But his Notice is valid for the November flood with respect to the Force Majeure clause.

17 Explanations of the DAB (cont.) On the other hand, if one considers the repeated Claim No: 2, which this time is given with respect to Exceptionally Adverse Climatic Conditions (GCC SC-8.4.c), it is observed that GCC-SC 17.3 item (h), explaining Employer s Risks reads as: any operation of the forces of nature which is unforeseeable or against which an experienced Contractor could not reasonably have been expected to have taken adequate preventive precautions.

18 Explanations of the DAB (cont.) Also, Questions & Answers contained in the Tender Dossier reveals that the short listed Contractors, before the Tender, asked the Employer for the confirmation of unnecessity for a flood protection requirement, and the Employer in his answer confirmed. FCG 8.4.c (FIDIC Contracts Guide) FIDIC Contracts Guide refers to Exceptionally Adverse Climatic Conditions as one of the causes of Extension of Time. The relevant paragraph reads as: In order to establish whether such climatic conditions occurred, it may be appropriate to compare the adverse climatic conditions with the frequency with which events of similar adversity have previously occurred at or near the site. An exceptional degree of adversity might, for example, be regarded as one which has a probability of occurrence of four to five times the Time for Completion of the Works (for example, once every eight to ten years for a two-year contract).

19 Explanations of the DAB (cont.) Base Date of the project is Nov.20, 2014 and, 28 days before Base Date is Oct.23, 2014 which is the date after which the Contractor should be aware of all relevant existing legislation according to the Yellow Book and should investigate the climaic conditions etc. beforehand. Time for Completion is 480 days with regard to the Contract. If 5 times Time For Completion is taken as the investigation period, it corresponds to 480 days x 5= 2400 days before the reference day, reference day being 28 days before the Base Date. DMI recordings show that max. precipitation in this period occurred in October 2012 as 91.3 mm of rainfall in the city of XXX. This date falls into the investigation period. When the average of the rainfall amounts of the closest four towns to the city of XXX is evaluated with regard to DMI records on Oct. 5, 2015, the average of 42.9 mm rainfall can be considered as valid for the city of XXX as well, since no measurement could be done by DMI in XXX.

20 Explanations of the DAB (cont.) Since the average precipitation of the neighborhood towns is estimated to be 42.9 mm, which is considered by the DAB to be taken as similar to the precipitation in the city of XXX, the rainfall on October 5, 2015 in XXX cannot be considered as Exceptionally Adverse Climatic Condition when compared to the precipitation of 91.3 mm of October The tables prepared by the DMI showing rain precipitations in the city of XXX in November during the years 2008 to 2014 are submitted by the Contractor. The tables show that during the month November from 2008 through 2014, the max precipitation which occurred in XXX on Oct.23,2009 and is recorded as 38.9 mm., whereas the DMI table indicates that XXX received 44 mm of rainfall on Nov.02,2015 (which is the subject of Claim 2, part two for November). Therefore this proves that the rain precipitation of 44 mm can be considered as Exceptionally Adverse Climatic Condition in the city of XXX in November.

21 Summary with regard to Exceptioanally Adverse Climatic Conditions N/A = not applicable Validity of Claim Incident Precipitation in the city of XXX N/A Avg. Prec. of Neighborhood Towns Max. Prec. in XXX during days before the Base Date NO Precipitation in October N/A 42.9 mm 91.3 mm YES Precipitation in November 44.0 mm N/A 38.9 mm

22 DAB Decision With regard to the evaluations given above, the Contractor s CLAIM IS FOUND PARTLY REASONABLE and the Contractor is entitled to 14 days of Extension of Time either with regard to GCC-SC 8.4.c (owing to Exceptionally Adverse Climatic Conditions which occurred in November 2015) or with regard to GCC-SC 19.1 (Definition of Force Majeure), SC 19.2 (Notice of Force Majeure), and SC 19.4 (Consequences of Force Majeure) owing to the flood which occurred again in November The Contractor is also entitled to payment of the costs, but not the profit.

23 Thank you...

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Distribution Restriction Statement Approved for public release; distribution is unlimited. CEMP-CP Regulation No. 415-1-15 Department of the Army U.S. Army Corps of Engineers Washington, DC 20314-1000 Construction CONSTRUCTION TIME EXTENSIONS FOR WEATHER ER 415-1-15 Distribution Restriction

More information

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE

More information

Scheduling Best Practices

Scheduling Best Practices The eighth article in the Scheduling Best Practices series is How to Handle the Weather. Our colleague Beth Blair, a managing consultant in Warner s Disputes Resolution Group, has over 20 years of experience

More information

MDB Harmonised Particular Conditions

MDB Harmonised Particular Conditions FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st

More information

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts

AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff. Risk Allocation in Construction Contracts 11 AfDB New Procurement Policy: Training Program for the Bank s Procurement Staff Risk Allocation in Construction Contracts Risks 2 In the absence of a contract, all risks are the owner's Contracting is

More information

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee

Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman of FIDIC Contracts Committee FIDIC Conditions of Contract IBC Conference 2003 Presentation Notes on: OVERVIEW OF THE NEW MAJOR CONTRACTS Speaker: CHRISTOPHER WADE, Chief Engineer, SWECO International, Stockholm, Sweden l, and Chairman

More information

Peter D Aeberli. Barrister - Arbitrator - Mediator Adjudicator. The Waiting Game: Extensions of Time

Peter D Aeberli. Barrister - Arbitrator - Mediator Adjudicator. The Waiting Game: Extensions of Time Peter D Aeberli Barrister - Arbitrator - Mediator Adjudicator The Waiting Game: Extensions of Time Determining extensions of time can be as sophisticated an art as designing a building in the first place.

More information

STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS

STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS STRATEGIC DATA FOR EMPLOYERS CONSTRUCTION CLAIMS KONGKOON TOCHAIWAT and VISUTH CHOVICHIEN Department of Civil Engineering, Chulalongkorn University, 254 Phyathai Road, Patumwan, Bangkok 10330, Thailand.

More information

ST HELENA TELECOMMUNICATIONS ORDINANCE, CAP 106 LICENCE TO OPERATE BROADCASTING STATIONS AND TO BROADCAST SERVICES (TELEVISION BROADCASTING LICENCE)

ST HELENA TELECOMMUNICATIONS ORDINANCE, CAP 106 LICENCE TO OPERATE BROADCASTING STATIONS AND TO BROADCAST SERVICES (TELEVISION BROADCASTING LICENCE) ST HELENA TELECOMMUNICATIONS ORDINANCE, CAP 106 LICENCE TO OPERATE BROADCASTING STATIONS AND TO BROADCAST SERVICES (TELEVISION BROADCASTING LICENCE) 1. I, the Governor, acting in accordance with section

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

Introduction to SOP. Background. Background. Principles of SOP Act. Objectives of SOP Act

Introduction to SOP. Background. Background. Principles of SOP Act. Objectives of SOP Act Introduction to SOP Background Building and Construction Industry Security of Payment (SOP) Act Objectives of Act Principles of Act Key Provisions of Act by Lim Jue Meng Jennifer Leong Ng Cher Cheng Feedback

More information

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004) Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament

More information

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS International Trade Centre, August 2010 Contents Foreword Acknowledgements Introduction Chapter 1 International Contractual

More information

The FOS Approach Mortgagee sales

The FOS Approach Mortgagee sales 1 At a glance 2 1.1 Scope 2 1.2 Summary 2 2 In detail 3 2.1 Taking reasonable care 3 2.2 Valuing the property 4 2.3 Marketing the property 4 2.4 Maintaining or improving the property 6 2.5 Selling the

More information

Queen Margaret University, Musselburgh, Edinburgh, EH21 6UU APPENDIX A: CONFERENCING & EVENTS GENERAL TERMS & CONDITIONS

Queen Margaret University, Musselburgh, Edinburgh, EH21 6UU APPENDIX A: CONFERENCING & EVENTS GENERAL TERMS & CONDITIONS Queen Margaret University, Musselburgh, Edinburgh, EH21 6UU APPENDIX A: CONFERENCING & EVENTS GENERAL TERMS & CONDITIONS THIS IS APPENDIX A REFERRED TO IN THE FOREGOING BOOKING BETWEEN QUEEN MARGARET UNIVERSITY

More information

PROPERTY OWNERS INSURANCE PROPOSAL

PROPERTY OWNERS INSURANCE PROPOSAL PROPERTY OWNERS INSURANCE PROPOSAL Please use BLOCK CAPITALS and tick boxes where applicable. Where requested enter further details in the space provided. If there is insufficient space please continue

More information

CONFORMITY MARKINGING FOR THE GCC COUNTRIES. Issue No.: (5) Date: (2/21/2008) Committee Draft No. 5

CONFORMITY MARKINGING FOR THE GCC COUNTRIES. Issue No.: (5) Date: (2/21/2008) Committee Draft No. 5 The Gulf Cooperation CONFORMITY MARKINGING FOR THE GCC COUNTRIES Committee Draft No. 5 Hint This Translation is informative and is not binding. List of Issue No.: (5) 1/9 Contents Clause 1: Purpose 3 Clause

More information

CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT

CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal

More information

Contractor s Claims Under The FIDIC Contracts For Major Works

Contractor s Claims Under The FIDIC Contracts For Major Works March 17, 2005 [This paper is to be published in the Construction Law Journal, London, in 2005]] International Construction Contracts and Dispute Resolution Co-Hosted by ICC and FIDIC In partnership with

More information

AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES

AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES AGREEMENT FOR THE PROVISION OF CONSULTANCY ENGINEERING SERVICES This agreement is made and entered into, on day the. of, 1991 by and between: Mr/. of P.O. Box.. hereinafter refereed to as the "Owner" on

More information

The FIDIC Suite of Contracts

The FIDIC Suite of Contracts Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October

More information

7.4.1 Be required to make exhaustive or continuous on-site reviews;

7.4.1 Be required to make exhaustive or continuous on-site reviews; SUPPLEMENTARY CONDITIONS TO THE CANADIAN STANDARD FORM OF CONTRACT FOR ARCHITECTURAL SERVICES DOCUMENT SIX 2006 EDITION RAIC 6 2006 FRASER HEALTH PROJECTS The following Supplementary Conditions are specific

More information

Hong Kong Institute of Surveyors

Hong Kong Institute of Surveyors Prolongation and Loss and Expense Claims For the Hong Kong Institute of Surveyors Mike Allen BSc FRICS MHKIS MCI Arb FA Cost E FAE CEDR Accredited Mediator 13 th February 2012 Contents Introduction The

More information

CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK

CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK SUMMARY The FIDIC Conditions are used extensively on international

More information

CONTRACT CONDITIONS FOR LOGISTICS (2014)

CONTRACT CONDITIONS FOR LOGISTICS (2014) CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member

More information

GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses

GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses Office of Government Procurement Cost Control: Price Variation Clauses Document Reference GN 1.5.2 v1.0 22 January 2016 2016 Department of Public

More information

Invitation to Tender

Invitation to Tender Invitation to Tender Provision of Training in Technology Transfer and Related Areas for The Southern Africa Innovation Support Programme 1. Drawing up the tender The tender must be submitted in writing

More information

RTI Statement for New Starters Please tick the relevant box below:

RTI Statement for New Starters Please tick the relevant box below: EXTERNAL ID Application to become a HYDRA PAYE Operative First Name: Address: Middle Name(s): Surname: Date of Birth: Town: N.I Number: Postcode: Nationality: Mobile Number: Email: Bank Details Bank Name

More information

Dated 29 February 2016. Flood Re Limited. Payments Dispute Process. Version 1.0

Dated 29 February 2016. Flood Re Limited. Payments Dispute Process. Version 1.0 Dated 29 February 2016 Flood Re Limited Payments Dispute Process Version 1.0 1. General 1.1 The following provisions will apply to all disputes referred to and conducted under this Payments Dispute Resolution

More information

3 February 2010 Millbank Tower, Millbank, London SW1P 4QP

3 February 2010 Millbank Tower, Millbank, London SW1P 4QP Report on an investigation into complaint no against Thurrock Council 3 February 2010 Millbank Tower, Millbank, London SW1P 4QP Investigation into complaint no against Thurrock Council Table of Contents

More information

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS International Trade Centre, August 2010 Contents Foreword Acknowledgements Chapter 1 International Contractual Alliance ITC

More information

Understanding Workers Compensation Rights and How to Protect Them

Understanding Workers Compensation Rights and How to Protect Them Understanding Workers Compensation Rights and How to Protect Them Jennifer M. Zupp Norelius, Nelson, Zupp, Zupp, P.C. 1317 Broadway POB 278 Denison, IA 51442 Ph. 1-712-263-4245 Fax. 1-712-263-8773 e-mail:

More information

CONTRACT FOR CONSULTANCY SERVICES. Section 1 Form of Contract

CONTRACT FOR CONSULTANCY SERVICES. Section 1 Form of Contract CONTRACT FOR CONSULTANCY SERVICES Equatorial Fidelity Centre 2 nd Floor, Off Waiyaki Way P.O Box 313-00606 Nairobi, Kenya. Tel +254 20 423 5000 Section 1 Form of Contract CONTRACT FOR: [Insert Title here]

More information

Consultant s Services Small Assignments, Lump-Sum Payments

Consultant s Services Small Assignments, Lump-Sum Payments STANDARD AND SAMPLE CONTRACT FOR Consultant s Services Small Assignments, Lump-Sum Payments Public Procurement Authority Accra, Ghana April, 2014 Table of Contents SECTION I: CONTRACT FORM... 1 Services...

More information

GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE. Section 1: Lost property and lost earnings are treated separately

GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE. Section 1: Lost property and lost earnings are treated separately GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE Section 1: Lost property and lost earnings are treated separately Business interruption insurance (also known as business income protection, profit protection,

More information

Smart Meters Programme Schedule 2.5. (Security Management Plan) (CSP South version)

Smart Meters Programme Schedule 2.5. (Security Management Plan) (CSP South version) Smart Meters Programme Schedule 2.5 (Security Management Plan) (CSP South version) Schedule 2.5 (Security Management Plan) (CSP South version) Amendment History Version Date Author Status v.1 Signature

More information

Terms and Conditions for Purchase Orders for Recycling Materials

Terms and Conditions for Purchase Orders for Recycling Materials Terms and Conditions for Purchase Orders for Recycling Materials This Agreement is made by and between AEROJET-GENERAL CORPORATION, an Ohio corporation with a place of business at Rancho Cordova, California

More information

INCOME TAX : INCOME TAX ACT, 1962 (the Act) : SECTION 10(1)(o)(ii) : EXEMPTION FROM INCOME TAX: FOREIGN EMPLOYMENT INCOME

INCOME TAX : INCOME TAX ACT, 1962 (the Act) : SECTION 10(1)(o)(ii) : EXEMPTION FROM INCOME TAX: FOREIGN EMPLOYMENT INCOME SOUTH AFRICAN REVENUE SERVICE INCOME TAX INTERPRETATION NOTE NO. 16 DATE: 27 March 2003 INCOME TAX ACT SECTION SUBJECT : INCOME TAX ACT, 1962 (the Act) : SECTION 10(1)(o)(ii) : EXEMPTION FROM INCOME TAX:

More information

General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage

General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage Determination Case number: 227307 General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage 4 April 2011 Background 1. The Applicants insured their home contents

More information

Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011

Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011 Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee 21 March 2011 & 23 March 2011 Introduction Jonathan Brooks osborneclarke.com osborneclarke.com

More information

USING THE ROAD MAINTENANCE AGREEMENT TEMPLATE

USING THE ROAD MAINTENANCE AGREEMENT TEMPLATE USING THE ROAD MAINTENANCE AGREEMENT TEMPLATE The Ministry of Government Relations has created a draft Road Maintenance Agreement template for municipalities and industry to use cooperatively. The primary

More information

Delay, Disruption and Acceleration Costs

Delay, Disruption and Acceleration Costs Project Services Pty Ltd Delay, Disruption and Acceleration Costs Patrick Weaver FAICD, MCIOB, PMP Introduction Delay and disruption costs are common in the construction and engineering industries and

More information

PROFESSIONAL PRACTICE EXAM MARCH 2009 PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS A PRACTITIONER AND ARCHITECTURAL SERVICE TO THE CLIENT

PROFESSIONAL PRACTICE EXAM MARCH 2009 PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS A PRACTITIONER AND ARCHITECTURAL SERVICE TO THE CLIENT PROFESSIONAL PRACTICE EXAM MARCH 2009 Instructions to Candidates: 1 All questions are to be answered Where a question is in sections, each answer is to be clearly separated strictly in accordance with

More information

American College of Real Estate Lawyers Tucson, Arizona March 18, 2005. FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W.

American College of Real Estate Lawyers Tucson, Arizona March 18, 2005. FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W. American College of Real Estate Lawyers Tucson, Arizona March 18, 2005 FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W. Trainor An excusable delay, or force majeure, clause is an important element

More information

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES

General Terms of Public Procurement in service contracts JYSE 2009 SERVICES General Terms of Public Procurement in service contracts November 2009 Contents Introduction........................................................................................................................................3

More information

Climate Change Adaptation - Risk Assessment. Melbourne, Australia

Climate Change Adaptation - Risk Assessment. Melbourne, Australia Climate Change Adaptation - Risk Assessment Melbourne, Australia The City of Melbourne Capital City of Victoria Second largest city in Australia Covers 37.6 square kilometres 100,611 residential population

More information

HOMESELLERS/HOMEBUYERS DISPUTE RESOLUTION MEDIATION PROGRAM

HOMESELLERS/HOMEBUYERS DISPUTE RESOLUTION MEDIATION PROGRAM HOMESELLERS/HOMEBUYERS DISPUTE RESOLUTION MEDIATION PROGRAM ---------------- A FAST, EASY, AND INEXPENSIVE ALTERNATIVE TO LITIGATION --------------- 5300 International Blvd.,Suite C-105 Charleston, SC

More information

FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY

FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY London Rd. WATERLOOVILE FOR McCarthy & Stone Ltd. July 2010 Such Salinger Peters Ltd 30558-1- Flood Risk Assessment & Drainage Strategy Contents Paragraph Page

More information

Consumer Code. for Home Builders. This document contains the Rules that govern the behaviour of Home Builders and Home Warranty Bodies

Consumer Code. for Home Builders. This document contains the Rules that govern the behaviour of Home Builders and Home Warranty Bodies Consumer Code for Home Builders This document contains the Rules that govern the behaviour of Home Builders and Home Warranty Bodies First Edition January 2010 Contents Meaning of words... 3 Introduction...

More information

MynxNet Broadband Terms and Conditions

MynxNet Broadband Terms and Conditions MynxNet Broadband Terms and Conditions Updated 10/12/15 Introduction These terms form the basis of the services provided by MynxNet (referred to as Mynx, Mynxnet, we, us, or our ) to yourself and your

More information

A Guide to Small Works. A brief explanation

A Guide to Small Works. A brief explanation A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here

More information

CGU & UIP CLAIMS PROCEDURES

CGU & UIP CLAIMS PROCEDURES CGU & UIP CLAIMS PROCEDURES INDUSTRIAL SPECIAL RISKS (DAMAGE TO OWNED PROPERTY & LOSS OF REVENUE Typically this policy covers claims arising from loss or damage involving such events as: Fire, including

More information

AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder

AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,

More information

SEO Agreement SEARCH ENGINE OPTIMIZATION AND REPORTING AGREEMENT

SEO Agreement SEARCH ENGINE OPTIMIZATION AND REPORTING AGREEMENT SEO Agreement SEARCH ENGINE OPTIMIZATION AND REPORTING AGREEMENT This Search Engine Optimization and Reporting Agreement ("Agreement") is hereby entered into between India Market Softech (P)Ltd. (hereinafter

More information

عقد العمل الخاص بالعمالة الهندية المغادرة للمملكة العربية السعودية

عقد العمل الخاص بالعمالة الهندية المغادرة للمملكة العربية السعودية STANDARD EMPLOYMENT CONTRACT FOR INDIAN DOMESTIC SERVICE WORKERS (DSW) BOUND FOR THE KINGDOM OF SAUDI ARABIA UNDER ARTICLE 3(IV) OF AGREEMENT ON LABOUR COOPERATION ON DOMESTIC SERVICE WORKERS SIGNED BETWEEN

More information

Consumer ID Theft Total Costs

Consumer ID Theft Total Costs Billions Consumer and Business Identity Theft Statistics Business identity (ID) theft is a growing crime and is a growing concern for state filing offices. Similar to consumer ID theft, after initially

More information

Consultants Services, Lump-Sum Remuneration

Consultants Services, Lump-Sum Remuneration 1 S T A N D A R D F O R M O F C O N T R A C T FOR Consultants Services, Lump-Sum Remuneration CONTRACT FOR CONSULTANTS SERVICES Lump-Sum Remuneration Between [name of the Procuring Entity] and 2 [name

More information

NAB CONNECT MERCHANT TRANSACTION REPORTING SERVICE

NAB CONNECT MERCHANT TRANSACTION REPORTING SERVICE NAB CONNECT MERCHANT TRANSACTION REPORTING SERVICE Terms and Conditions effective 21.05.07 30091_merch_transact (05/07) Contents Meaning of Words 2 Conditions of Use 2 Liability 3 Fees and Charges 4 Termination

More information

General Terms and Conditions BB Remessa

General Terms and Conditions BB Remessa General Terms and Conditions BB Remessa Your agreement with us consists of these General Terms and Conditions ( General Terms ) and any Additional Conditions (the General Terms and the Additional Conditions

More information

Capital Works Management Framework Document No. GN 1.7. Standard Conditions of Engagement for Consultancy Services (Technical)

Capital Works Management Framework Document No. GN 1.7. Standard Conditions of Engagement for Consultancy Services (Technical) Capital Works Management Framework Document No. GN 1.7 Standard Conditions of Engagement for Consultancy Services (Technical) Guidance Note and Sample Schedules GN 1.7 090708 1 About This Document Background

More information

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland

More information

Penalties for failure to file returns on time the Construction Industry Scheme (CIS)

Penalties for failure to file returns on time the Construction Industry Scheme (CIS) Compliance checks series CC/FS18b Penalties for failure to file returns on time the Construction Industry Scheme (CIS) This factsheet contains information about the penalty or penalties we will charge

More information

GRANT AGREEMENT FOR STUDIES ERASMUS+ 2016-2017

GRANT AGREEMENT FOR STUDIES ERASMUS+ 2016-2017 GRANT AGREEMENT FOR STUDIES ERASMUS+ 2016-2017 Linköping University (S LINKOPI01), SE-581 83 LINKÖPING, SWEDEN, and the student 1 Name Address (Street and postal address) Date of birth Number of completed

More information

Thames Water Utilities Limited. Settlement deed

Thames Water Utilities Limited. Settlement deed Thames Water Utilities Limited Settlement deed DATED [ ] THAMES WATER UTILITIES LIMITED the Undertaker [ ] the Owner DEED relating to the mitigation of the effects of settlement arising from the construction

More information

FIDIC AND. DISPUTE ADJUDICATION BOARDS (DAB(s))

FIDIC AND. DISPUTE ADJUDICATION BOARDS (DAB(s)) FIDIC AND DISPUTE ADJUDICATION BOARDS (DAB(s)) Christopher R. Seppälä Partner, White and Case LLP, Paris Legal Advisor, FIDIC Contracts Committee Vice-President Emeritus, ICC International Court of Arbitration

More information

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill

FIDIC users guide A practical guide to the 1999 Red and Yellow Books. Brian W. Totterdill FIDIC users guide A practical guide to the 1999 Red and Yellow Books Brian W. Totterdill Published by Thomas Telford Publishing, Thomas Telford Ltd, 1 Heron Quay, London E14 4JD. URL: www.thomastelford.com

More information

H o w t o W r i t e a J u d g e m e n t

H o w t o W r i t e a J u d g e m e n t H o w t o W r i t e a J u d g e m e n t A) Function of a Judgement: Being the final result of a legal procedure a judgement shall provide a balanced conflict solution. An ideal judgement enables both conflict

More information

ELECTRONIC FUND TRANSFER AGREEMENT AND DISCLOSURE PERSONAL CHECK and/or ATM CARD

ELECTRONIC FUND TRANSFER AGREEMENT AND DISCLOSURE PERSONAL CHECK and/or ATM CARD ELECTRONIC FUND TRANSFER AGREEMENT AND DISCLOSURE PERSONAL CHECK and/or ATM CARD This agreement and disclosure applies to payment orders and funds transfers governed by the Electronic Fund Transfer Act.

More information

PROTECTED DISCLOSURES ACT 26 OF 2000

PROTECTED DISCLOSURES ACT 26 OF 2000 Page 1 of 7 PROTECTED DISCLOSURES ACT 26 OF 2000 [ASSENTED TO 1 AUGUST 2000] [DATE OF COMMENCEMENT: 16 FEBRUARY 2001] (English text signed by the President) ACT To make provision for procedures in terms

More information

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:

PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics: Supply Chain Management Document Number: SCM006 Document Title: Supply Contract Version: 01 Purpose: Standard contract for all supplies of goods PREFACE The Contract for the Supply and Delivery of Goods

More information

DIGITAL SUBSCRIBER LINE (DSL) SERVICE GUIDE

DIGITAL SUBSCRIBER LINE (DSL) SERVICE GUIDE Rural Telephone Service Company, Inc. dba Nex-Tech Title Page DIGITAL SUBSCRIBER LINE (DSL) SERVICE GUIDE REGULATIONS, RATES, AND CHARGES Applying to the Provision of DSL For Customers of Rural Telephone

More information

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9

More information

Property Insurance. Endorsement. Policy Period. Effective Date. Policy Number. Insured. Name of Company. Date Issued

Property Insurance. Endorsement. Policy Period. Effective Date. Policy Number. Insured. Name of Company. Date Issued Property Insurance Endorsement Policy Period Effective Date Policy Number Insured Name of Company Date Issued This Endorsement applies to the following forms: SCHEDULE Form 80-02-1428 (Rev. 7-03) Endorsement

More information

List 10 different words to describe the weather in the box, below.

List 10 different words to describe the weather in the box, below. Weather and Climate Lesson 1 Web Quest: What is the Weather? List 10 different words to describe the weather in the box, below. How do we measure the weather? Use this web link to help you: http://www.bbc.co.uk/weather/weatherwise/activities/weatherstation/

More information

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS

MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS International Trade Centre, August 2010 Model Contracts for Small Firms: International Commercial Sale of Goods Contents

More information

PROTECTED DISCLOSURES ACT NO 26 OF 2000

PROTECTED DISCLOSURES ACT NO 26 OF 2000 Date of commencement: 16 February 2001 REVISION No.: 0 Page 1 of 6 PROTECTED DISCLOSURES ACT NO 26 OF 2000 CONTENTS CLICK ON PAGE NUMBER TO GO TO SECTION OR REGULATION AND USE WEB TOOLBAR TO NAVIGATE Section

More information

Under the Farm Debt Mediation Act 1994 "mediation" means mediation by a mediator who has been accredited by the NSW Rural Assistance Authority.

Under the Farm Debt Mediation Act 1994 mediation means mediation by a mediator who has been accredited by the NSW Rural Assistance Authority. WHAT IS MEDIATION? MEDIATION IS DEFINED AS "The process by which the participants, together with the assistance of a neutral person or persons, systematically isolate disputed issues in order to develop

More information

0%- Shop Now Pay Later Program- Terms & Condition

0%- Shop Now Pay Later Program- Terms & Condition 0%- Shop Now Pay Later Program- Terms & Condition In consideration of First Gulf Bank PJSC (hereafter referred to as the Bank ) agreeing to make available the 0% Program ( as defined hereunder) to the

More information

DIGITAL SUBSCRIBER LINE (DSL)

DIGITAL SUBSCRIBER LINE (DSL) Title Page DIGITAL SUBSCRIBER LINE (DSL) SERVICE GUIDE REGULATIONS, RATES, AND CHARGES Applying to the Provision of DSL For Customers of This DSL Service Guide does not include Internet Access, Content

More information

SolarEdge Technologies Ltd.

SolarEdge Technologies Ltd. SolarEdge Technologies Ltd. GENERAL TERMS AND CONDITIONS 1. General. This document, entitled General Terms and Conditions (referred to herein as the Agreement ), forms an integral part of the quotation

More information

MIGHTY MIKE PLUMBING, INC. PLUMBING GENERAL CONTRACTOR SERVICES PROPOSAL

MIGHTY MIKE PLUMBING, INC. PLUMBING GENERAL CONTRACTOR SERVICES PROPOSAL MIGHTY MIKE PLUMBING, INC. PLUMBING GENERAL CONTRACTOR SERVICES PROPOSAL PROPOSAL: Proposal No./Date: Address of Property where Services are to be Performed: Name of Person on Whose Behalf Services are

More information

CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014

CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014 CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014 Schedule 1 Insurance provisions 1 1 INSURED RISKS AND OTHER DEFINITIONS 1.1

More information

DOCUMENT. General Purchase Conditions

DOCUMENT. General Purchase Conditions 1. Scope 1.1 These general purchase conditions (hereinafter the GPC ) shall apply to all kinds of materials, articles, products and services related to them, (hereinafter Products ), offered, sold or supplied

More information

How To Recover From A Flood In Bundaberg

How To Recover From A Flood In Bundaberg BUNDABERG FLOODS NOW THE MUD HAS DRIED FLOOD RECOVERY AT MILLBANK Paper Presented by: Kym Kneebone Author: Kym Kneebone, Assistant Coastal Treatment Co-ordinator, Bundaberg Regional Council 37th Annual

More information

What amount of damages is the plaintiff entitled to recover from the defendant? 1

What amount of damages is the plaintiff entitled to recover from the defendant? 1 Page 1 of 5 745.07 NEW MOTOR VEHICLES WARRANTIES ACT ( LEMON LAW ) DAMAGES WHEN NOTE WELL: Appendices contain worksheets that the Court may want to provide to the jury, but it is not mandatory to do so.

More information

Injury Allowance Policy

Injury Allowance Policy Injury Allowance Policy Date: October 2014 Version number: 1 Authors: Lorraine Allinson, HR Service Manager Review Date: October 2017 If you would like this document in an alternative language or format,

More information

ARCHITECT'S APPOINTMENT - DOMESTIC PROJECT AGREEMENT FULL SERVICE. Mobile

ARCHITECT'S APPOINTMENT - DOMESTIC PROJECT AGREEMENT FULL SERVICE. Mobile ARCHITECT'S APPOINTMENT - DOMESTIC PROJECT AGREEMENT FULL SERVICE Reference N 1 CONTRACTING PARTIES Client Mr and Mrs/Ms or Mr and/or Mrs/Ms contracting in person. contracting in person. contracting in

More information

MORTGAGE PART 1 (This area for Land Title Office use) Page 1 of pages

MORTGAGE PART 1 (This area for Land Title Office use) Page 1 of pages LAND TITLE ACT FORM B (Section 225) Province of British Columbia MORTGAGE PART 1 (This area for Land Title Office use) Page 1 of pages 1. APPLICATION: (Name, address, phone number and signature of applicant,

More information

WINTERSHALL NORGE AS GENERAL TERMS & CONDITIONS I FOR ONSHORE GOODS. Table of Content

WINTERSHALL NORGE AS GENERAL TERMS & CONDITIONS I FOR ONSHORE GOODS. Table of Content WINTERSHALL NORGE AS GENERAL TERMS & CONDITIONS I FOR ONSHORE GOODS Table of Content Page 1. APPLICATION... 2 2. DEFINITIONS... 2 3. PURCHASE ORDER; ORDER CONFIRMATION... 2 4. THE GOODS... 2 5. QUALITY

More information

Ramah Navajo Chapter, Oglala Sioux Tribe & Pueblo of Zuni v. Jewell. Class Counsel Question and Answer Fact Sheet (revised Dec.

Ramah Navajo Chapter, Oglala Sioux Tribe & Pueblo of Zuni v. Jewell. Class Counsel Question and Answer Fact Sheet (revised Dec. Ramah Navajo Chapter, Oglala Sioux Tribe & Pueblo of Zuni v. Jewell Class Counsel Question and Answer Fact Sheet (revised Dec. 30, 2015) How much is the settlement amount? BASICS OF THE SETTLEMENT The

More information

CLAUSES REQUIRED ON ALL HOME IMPROVEMENT CONTRACTS ($500.00 on up)

CLAUSES REQUIRED ON ALL HOME IMPROVEMENT CONTRACTS ($500.00 on up) CLAUSES REQUIRED ON ALL HOME IMPROVEMENT CONTRACTS ($500.00 on up) 1. The name, address and license number of the contractor, and the name and registration number of any salesperson who solicited or negotiated

More information

Construction Claims in

Construction Claims in Construction Claims in the Gulf ICES CPD Event 12/2012 ADMC Auditorium 19 December 2012 DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Context» Aftermath of 2008 / 2009 financial

More information

ARMED SERVICES BOARD OF CONTRACT APPEALS

ARMED SERVICES BOARD OF CONTRACT APPEALS ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of -- ) ) Dehdari General Trading & Contracting EST. ) ASBCA No. 53987 ) Under Contract No. F38604-99-AJ016 ) APPEARANCE FOR THE APPELLANT: Mr. Mahmoud Dehdari

More information

Work Phone. Mobile / / Policy Number Date Issued Number of Travellers. Date of Booking Departure Date Return Date Total Days

Work Phone. Mobile / / Policy Number Date Issued Number of Travellers. Date of Booking Departure Date Return Date Total Days Travel Insurance Claim Form Cancellation You must register any claim within 30 days of completion of your travel. Please supply original documents of the evidence you intend to rely on for your claim,

More information

AN ACT...; relating to: the budget.

AN ACT...; relating to: the budget. 2013 2014 LEGISLATURE DOA:...Byrnes, BB0358 Expand flood damage aids appropriation to cover other disasters FOR 2013 2015 BUDGET NOT READY FOR INTRODUCTION AN ACT...; relating to: the budget. Analysis

More information

IKM-I-K-01E Standard conditions of purchase IKM Gruppen Side 1 av 6

IKM-I-K-01E Standard conditions of purchase IKM Gruppen Side 1 av 6 IKM-I-K-01E Standard conditions of purchase IKM Gruppen Side 1 av 6 Løvås Svein Firma/Company: IKM Gruppen AS 1. GENERAL 1.1 These conditions of purchase shall apply unless otherwise agreed in writing.

More information

These terms of business (the Terms ) explain the entire rights and obligations of You and Us regarding the provision of our Services.

These terms of business (the Terms ) explain the entire rights and obligations of You and Us regarding the provision of our Services. Investor Compensation (UK) Limited - Terms and Conditions PPI These terms of business (the Terms ) explain the entire rights and obligations of You and Us regarding the provision of our Services. You should

More information

Who pays the Money for the Time?

Who pays the Money for the Time? Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency

More information

Generali Worldwide Group Total & Permanent Disability Standard Terms and Conditions

Generali Worldwide Group Total & Permanent Disability Standard Terms and Conditions Generali Worldwide Group Total & Permanent Disability Standard Terms and Conditions generali-worldwide.com 2 of 7 Generali Worldwide Insurance Company Limited - Group Total & Permanent Disability Terms

More information

GRANT AGREEMENT FOR TRAINEES ERASMUS+ 2015-2016

GRANT AGREEMENT FOR TRAINEES ERASMUS+ 2015-2016 GRANT AGREEMENT FOR TRAINEES ERASMUS+ 2015-2016 Linköping University (S LINKOPI01), SE-581 83 LINKÖPING, SWEDEN, and the trainee 1 Name Address Date of birth Phone Number of completed higher education

More information