1 Capital Project Closeout Construction Documentation Requirements Guidelines for Architects, Contractors, and Project Managers For further information about this document contact: HARVARD UNIVERSITY PROPERTY INFORMATION RESOURCE CENTER 1350 Massachusetts Ave., Holyoke Center Suite 550 Cambridge, MA t: f: e: 1
2 T ABLE OF C ONTENTS I. Introduction p. 3 A. Documentation Required B. Project Manager Responsibilities C. Templates and Standards II. Templates 1. Transmittal for Materials Required p Project Dossier p Capital Project Contact List p Electronic File Quality Assurance Checklist p Electronic File Index p. 11 2
3 I. Introduction This document is for the use of project managers, architects, and contractors working on Harvard University capital projects and provides a description of: 1) Architect Deliverables per Item #14 and Attachment #4 ( Materials Checklist ) in the Harvard Attachment to the B151 Agreement between Owner and Architect; and 2) Contractor Deliverables per Item #2 ( Materials Checklist ) and #9 ( Project Binder ) of Attachment 1 to the A201 General Conditions of the Contract for Construction (Agreement between Owner and Contractor); and 3) Contractor Deliverables per Items #24 and #25 and Attachment # 9 ( Materials Checklist ) to the Basic Information Sheet for the A107 Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope. A. Documentation Required Harvard University has specific requirements for capital project documentation which must be submitted to the Property Information Resource Center (PIRC) prior to project close. These requirements are specified in the attached Materials Checklist. Materials submitted to the PIRC should be coordinated with the Harvard Project Manager assigned to the project. Project documentation must be clear, consistent, and complete. The quality of the documentation will be reviewed by PIRC staff within two (2) weeks of receipt. Project documentation deliverables must be accompanied by the Materials Checklist & Transmittal for Materials (see Section II). AutoCAD Revit (and other BIM) requirements for deliverables must adhere to the BIM Execution Plan (BEP), if a plan was created for the project. The existence of a BEP does not supersede these closeout requirements; they are in addition to these requirements. If there is no BEP and there are AutoCAD Revit or other BIM files, they may be provided in addition to requirements outlined herein. B. Project Manager Responsibilities There are additional requirements for Project Managers in the Harvard University Project Delivery Guidelines (PDG). Project Managers should convey all requirements to the architect or contractor. All documents required as part of project close out must be submitted in the formats described in the Materials Checklist. To ensure consistency of data, the Project Manager should confirm that the following templates and standards are used (see Section III): 3
4 C. Templates and Standards Materials Checklist & Transmittal for Materials (Template 1) The architect or contractor should use this checklist as a transmittal, which lists all materials required at project close. The completed transmittal forms, including an official submission of close out materials letter on the submitting firm s letterhead should accompany the submission of deliverables to the PIRC. Project Dossier (Template 2) The Project Dossier serves to document various other types of information about the project. The Project Dossier is the responsibility of the lead architect or engineer. Capital Project Contact List (Template 3) The Project Manager should provide information for each person or firm (architects, contractors, sub contractors, etc.) involved in the project. Electronic File Quality Assurance Checklist (Template 4) The architect or contractor must sign and submit this checklist, which ensures that all electronic materials adhere to the standards and guidelines set forth in the Harvard Planning & Project Management s CAD Standards publication. Electronic Files Indices Guidelines (Template 5) Architects and contractors must supply indices that conform to the contents and formats presented in this guideline. CAD Standards (2009 Version) ( This document provides specifications for producing and delivering CAD drawings for project documentation. Survey Specifications ( This document describes the coordinate system used by Harvard University and the basic standards that need to be followed to insure compatibility with the University GIS. 4
5 II. TEMPLATES TEMPLATE 1 M ATERIALS C HECKLIST & T RANSMITTAL F OR M ATERIALS Project Name: Harvard Project Manager: Harvard Capital Project number: Building Number(s): Date: Submitted by: Consultant Project Number: Building Root Number(s): All materials submitted at close out must be accompanied by this form for submission to the PIRC. Effective February 10, 2014 Materials 1copy each item Transmittal Complete this Materials Checklist & Transmittal Template. If a required submission is not applicable to your project please indicate such with N/A Delivered to PIRC Initials of submitter Contact List Use Capital Project Contact List Template A. ADMIN DOCS Debarment Certification Signed debarment certification must be included for all capital level projects with contracts executed after February 10, Form to be supplied by your Harvard PM. Quality Assurance Checklist(s) Use Electronic File Quality Assurance Checklist Template¹ ; Refer to Surveying Standards and Recovery Notes 3 Indices of electronic files Use Electronic Files Indices Template¹ Project Dossier This information must be submitted by the lead architect or engineer on the project. If no architect or engineer was employed this requirement is not applicable. Drawings all drawings delivered at project close must be delivered in hardcopy, TIFF, PDF, and DWG formats (1:1:1:1 for each drawing) B. CONSTRUCTION DOCUMENTATION Hardcopy Drawings: All drawings should be printed on 20lb. bond paper. Acceptable sizes: 24 x36 or 30 x42. Drawings must be rolled, not folded. Drawings must not be stapled Architects: submit stamped and signed Record Drawings which incorporate all changes made in the field as the final record deliverable. 5
6 MEP: submit stamped and signed As Built Drawings reflecting as built conditions which incorporate all changes made in the field as the final record deliverable. Electronic Drawings Drawings should exactly match hard copy documents submitted on CD/DVD/USB2.0 labeled with project name, project number, drawings included, date, company name, contact name and telephone number. Drawing names should be identical to hard copy drawing sheet number, (i.e., A 1.DWG, E 1.DWG). Special characters should be limited to dashes. TIFF Produced at 300ppi resolution at hard copy dimensions; file names must follow conventions in CAD Standards. Each drawing should be one TIF PDF Produced at 300ppi resolution at hard copy dimensions; file names must follow conventions in CAD Standards. Each drawing should be one PDF CAD file drawings Must comply with all requirements in CAD and Image Standards. All external references must be bound; file names must follow conventions in CAD and Image Standards Specifications all specifications delivered at project close must be delivered in hardcopy and PDF formats. PDF version must reproduce 100% of the information in the original documents. PDF specifications must be submitted with a TOC The specifications shall be annotated to show the actual selected products that are incorporated into the project, particularly where a choice of two or more products was permitted. Follow the Construction Specifications Institute (CSI) format and indexing The first page of each division shall be in the index to that section Operation and maintenance manuals all project manuals delivered at project close must be delivered in hardcopy and PDF formats. PDF version must reproduce 100% of the information in the original documents. PDF manual must be submitted with a TOC All manuals should contain: Phone Lists of subcontractors, suppliers, manufacturers representatives, Manuals of Systems Components to be specified by Architect, and Warranties/Guarantees. This manual must include, as applicable, the Manufacturer s printed installation and operating instructions: technical specifications and instructions (not sales brochures/promotional material). Instructions shall include all modes of operation in sufficient detail to be readily understood by maintenance personnel. Complete information on actual equipment installed as described in the manufacturers instructions, including dimensional drawings, model, type, size, capacity, performance parameters such as curves, efficiencies, power requirements, operating ranges, etc. (Only one manual is needed for multiple, identical equipment. Serial numbers for all equipment Detailed Parts List showing manufacturers parts numbers and such other identification as necessary to facilitate procurement of spare or renewal parts and Owner Manufacturer communications. Schedules showing proper time intervals for lubrication, adjustment, calibration or checking. Contractor shall consolidate manufacturers schedules with a single master schedule of required maintenance. This requirement is for the 6
7 Contractor s as well as the Owner s protection to insure proper early maintenance during the warranty period. Final Commissioning Report / Systems Manual all projects which engage a Commissioning Authority (CxA) must deliver a hardcopy and PDF version of the report. The final Commissioning Report/Systems Manual must be formatted in accordance with the Harvard University Office for Sustainability and ASHRAE requirements. Regulatory Approvals all copies of permits and certificates should be delivered in hardcopy format Building permit application (submitted by project team) Building permit (issued by City) Occupancy permit application (submitted by project team) Occupancy permit (issued by City) Final cost affidavit for building permit Certificate of inspection Contracts copies of executed contracts should be signed by all parties and delivered in hardcopy format. Information relating to payment amounts may be redacted. Include all contracts with Architects, Engineers, Consultants, Contractors and Construction Managers, if applicable. Land Survey if a survey was completed it must be submitted in hard copy and electronic formats Soil or Environmental Reports if testing or remediation was performed all geotechnical and geochemical reports should be submitted in hardcopy and electronic format Arc Flash Study and Hazard Analysis A hard copy format of the report must be included in the close out package if an Arc Flash Study was produced for NEC/NFPA compliance on the project. 7
8 TEMPLATE 2 P ROJECT D OSSIER P LEASE COPY AND SUBMIT THIS ON F IRM L ETTERHEAD Project Name: Harvard Capital Project number: Contract Type / Delivery Method: LEED Project? Project Start Date: Project Location and Address: Consultant Project Number: Extent (gsf/nasf): Building Systems Impacted: Project End Date: Project Description: 8
9 TEMPLATE 3 C APITAL P ROJECT C ONTACT L IST Information must be provided for each person or firm (architects, contractors, sub contractors, etc.) involved in the project. Project Name: Harvard Project Manager: Harvard Capital Project number: Building Number(s): Date: Submitted by: Consultant Project Number: Building Root Number(s): Role Organization Contact Name Company Company Project Number Phone E Mail 9
10 TEMPLATE 4 E LECTRONIC F ILE Q UALITY A SSURANCE C HECKLIST CAD drawings delivered at closeout of a capital project must be accompanied by this checklist and a signed letter on firm letterhead stating that all materials adhere to the standards and guidelines set forth in the Harvard Planning & Project Management s CAD Standards publication found at FILE FORMAT AND SETUP Electronic File Format Scale, Units, & Tolerances Fonts and Text Styles Blocks Title Blocks Policy on Model Space and Paper Space Policy on External Reference Files (XREFs) LAYERING Standard Layer List Layer Name Formatting General Rules about Naming and Uses Layer Attributes (Colors, Pens, Linetypes) CAD & TIFF FILE NAME CONVENTIONS Building and Floor Identification Codes ipline Identification Codes Drawing Type Codes Drawing Numbers POLICY ON CAD FILE TRANSLATION Full AutoCAD Compliance Translation Testing Procedures (if applicable) POLICY ON TIFF FILE TRANSLATION Scan at 300 ppi at hard copy dimensions (24 x36 or 30 x42 ) Files must be uncompressed POLICY ON PDF FILE TRANSLATION Scan at 300 ppi at hard copy dimensions (24 x36 or 30 x42 ) Files must be uncompressed Name of Accountable Vendor Representative (please print) Phone number: Date: Signature of Accountable Vendor Representative 10
11 E LECTRONIC F ILE I NDEX TEMPLATE 5 All electronic materials (CAD files, TIFF scans, index table files, etc.) must be delivered on CD/DVD/USB2.0 formatted using Windows 2000 or higher. Indices for scans must be submitted in paper format and electronically in Microsoft Excel (version 5.0 or later). A blank template of this form is available on the PIRC website at Scans must be done at a resolution of 300ppi at hard copy dimensions. Indices must contain the following information: 1. File Name 2. Title of Drawing DO NOT ALL CAPS title block attributes 3. Horizontal Paper Size measured in inches, indicate the width of the original paper drawing at its widest horizontal dimension 4. Vertical Paper Size measured in inches, indicate the length of the original paper drawing at its widest vertical dimension 5. Scale indicate the scale of the original drawing (examples: 1 =20 or NTS) 6. Pixel Depth indicate color, grayscale, bi tonal Sample Electronic File Index PROJECT INFORMATION Firm Name: CAPS Project Name: Oxford Garage/52 Oxford St. CAPS Project No: UOS INDEX OF MATERIAL SAMPLE ONLY: DELETE CONTENT AND FILL IN WITH YOUR OWN DATA Harvard Scan Item No. Building Number Sheet # Title V x H size Scale Scan File name PPI resolution Scan # CAD File name CAD Version CAD # Record Documents on Paper.HC.TIFF.DWG T 1 Title sheet drawing list 24 x 36 NTS 01395_T1 300 # _T # C1 Site preparation plan 24 x 36 3/16 in. : 1 ft _C1 300 # _C # C2 Site layout plan 24 x 36 3/16 in. : 1 ft _C2 300 # _C # C3 Site utility plan C4 Site grading plan 24 x 36 3/16 in. : 1 ft. 24 x 36 3/16 in. : 1 ft _C _C4 300 #1 # _C _C #2 #2 11
CAD Standards Guideline For Facility Documentation and Construction Projects
CAD Standards Guideline For Facility Documentation and Construction Projects Implemented March 2010 Page 1 of 9 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4.
More informationCAD Standards Guideline For Facility Documentation and Construction Projects
CAD Standards Guideline For Facility Documentation and Construction Projects Page 1 of 12 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4. External References 5.
More informationUniversity of Northern Iowa Design Documents Standards. October 2014
University of Northern Iowa Design Documents Standards October 2014 2014 UNI BUILDING AND DESIGN STANDARDS 1.1 CONTRACT DOCUMENT FORMAT 1.1.1 The Electronic Word Programs used for the Project manual shall
More informationLANSING COMMUNITY COLLEGE 14205.00 TLC BUILDING SERVER ROOM UPGRADES SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.
SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings,
More informationDesigner Quality Control Plan Guidelines
Designer Quality Control Plan Guidelines Guidelines, as defined for this manual, are detailed minimum requirement to implement a Designer Quality Control Plan 7/9/2014 Quality Control Plan Acknowledgement
More informationDesign Deliverables Checklist
S a n i tary Sewer Overflow (SSO) Control a n d Wastewater Facilities Program Deliverables Checklist City of Baton Rouge/Parish of East Baton Rouge Department of Public Works Submitted by Prepared by:
More informationHP Smart Document Scan Software compression schemes and file sizes
Technical white paper HP Smart Document Scan Software compression schemes and file s Table of contents Introduction 2 schemes supported in HP Smart Document Scan Software 2 Scheme Types 2 2 PNG 3 LZW 3
More informationCAD Standards. Design Guidelines and Standards. June 2004. Office of the University Architect
Design Guidelines and Standards CAD Standards June 2004 Office of the University Architect Construction Management P.O. Box 210181 Cincinnati, Ohio 45221-0181 Table of Contents Contents CAD STANDARDS Introduction...
More informationTHIS PAGE INTENTIONALLY LEFT BLANK
Facilities Management June 29, 2015 THIS PAGE INTENTIONALLY LEFT BLANK Page 2 of 31 CAD Guidelines and Standards Table of Contents SECTION 1: THE PURPOSE OF USING CAD DATA STANDARDS... 5 1.1 Industry Standards...
More information5.2 Drawing Information. 0400 Consultants Procedure Manual. 5.2 Drawing Information: 5.2.2 Large Format Document Standards: Page 1 of 5
Page 1 of 5 5.2 : 5.2.1 General Information:.1 Final drawings for all projects shall be one of the following sizes: 11" x 17", 24" x 36" or 30" x 42". The dimensions refer to the outside edge or cut line.
More informationDIVIDER G U I D E L I N E S
3212 E. Hwy 30 P. O. Box 2110 Kearney, NE 68847 800-445-6621 Fax: 308-234-3969 web: www.morriscookbooks.com e-mail: cbart@morriscookbooks.com Press-Ready DIVIDER G U I D E L I N E S Accepted Software &
More informationCity of Mercer Island Request for Proposals for Document Scanning and Indexing
City of Mercer Island Request for Proposals for Document Scanning and Indexing PROJECT DESCRIPTION In 2008, the City of Mercer Island purchased and implemented an electronic document management system
More informationRevised Work Scope Dated April 23 rd, 2015
Revised Work Scope Dated April 23 rd, 2015 2.4 SCOPE OF SERVICES The following combines the Scope of Services included in RFQ No. 671 dated March 12, 2015 and the Invitation to Interview letter dated March
More informationATLANTA PUBLIC SCHOOLS
Procurement Services 130 Trinity Avenue, S.W. 5 th Floor Atlanta, Georgia 30303 Request for Qualifications For October 31, 2007 Solicitation Number: 112607-01 Due Date: November 26, 2007 ADVERTISEMENT
More informationPeriodontology. Digital Art Guidelines JOURNAL OF. Monochrome Combination Halftones (grayscale or color images with text and/or line art)
JOURNAL OF Periodontology Digital Art Guidelines In order to meet the Journal of Periodontology s quality standards for publication, it is important that authors submit digital art that conforms to the
More informationISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)
ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:
More informationIndiana University Agreement Between Owner and Architect for a Small Project
Indiana University Agreement Between Owner and Architect for a Small Project This AGREEMENT is made: (Date) BETWEEN the Owner: The Trustees of Indiana University 1800 N. Range Road Bloomington, IN 47408
More informationApplicant. User Guide. www.beverlyhills.org/electronicreview
Applicant User Guide Quick References Page 2 Table of Contents Page 3 How to submit eplans. Page 7 Preparing eplans. Page 9-10 eplan File Names. Page 18 Resubmit Plans. www.beverlyhills.org/electronicreview
More informationATTACHMENT B PROJECT DATA & DELIVERABLES STANDARDS
EASTERLY SECONDARY SYSTEMS IMPROVEMENTS WBS NO. TP.E. 1255 JANUARY 2011 ATTACHMENT B PROJECT DATA & DELIVERABLES STANDARDS Overview This Attachment, Project Standards & Requirements Data, Drawings & Deliverables,
More informationHow To Make A Logo For A Co-Op&Condoexpo
Sponsorship Logo Requirements Aisle Sign Sponsors, Food Court Sponsor, Badge Sponsor, Cyber Cafe Sponsor Minimum Requirements for Logos 300 dpi resolution at a size of 8 x 10 inches (higher resolution
More informationElectronic Health Record System (EHR) Project. Request for Information RFI-CDVA-200907-01. Attachment 5 Statement of Work 2 Maintenance & Operations
State of California DEPARTMENT OF VETERANS AFFAIRS Electronic Health Record System (EHR) Project Request for Information RFI-CDVA-200907-01 Attachment 5 Statement of Work 2 Maintenance & Operations STATEMENT
More informationPROJECT DELIVERABLES FORMAT
PROJECT DELIVERABLES FORMAT TABLE OF CONTENTS 1. PROJECT DELIVERABLES FORMAT... 2 1.1. ELECTRONIC DELIVERABLES... 2 1.2. PHOTOGRAPHS... 2 1.3. FORMAT OF THE DESIGN SUBMISSION DELIVERABLES... 2 2. PREPARATION
More informationUNIVERSITY OF WASHINGTON Facilities Services Design Guide. Civil. Topographical Survey. Design Evaluation. Construction Submittals
This section applies to design standards and procedures involved in the field location and plotting of all natural objects and surface improvements. This section also includes the requirements for submittal
More informationSECTION 01 78 29 AS-BUILT DOCUMENTATION
SECTION 01 78 29 AS-BUILT DOCUMENTATION PART 1: GENERAL 1.01 AS-BUILTS Where identified as a product of the Work, provide as-built drawings adhering to the criteria provided here and in the special conditions.
More informationPROJECT MANUAL INCLUDING SPECIFICATIONS FOR OXNARD SCHOOL DISTRICT EDUCATIONAL SERVICE CENTER DATA ROOM ALTERATION. Oxnard, CA
PROJECT MANUAL INCLUDING SPECIFICATIONS FOR OXNARD SCHOOL DISTRICT Oxnard, CA Client Project Number: ARCHITECT MVE INSTITUTIONAL, INC. 3 MacArthur Place, Suite 850 Santa Ana, CA 92707 Telephone: 949.809.3380
More informationSAMPLE REQUEST FOR PROPOSALS TEMPLATE
SAMPLE REQUEST FOR PROPOSALS TEMPLATE Request for Proposals (RFP) For: [Title of RFP Project] Note: This sample is for a fabrication type of RFP. [RFP ID #] Issued: [Date] Submission deadline: [Time/Date]
More informationEngineering Operations Services. Business Process Guideline for Project Documentation
Engineering Operations Services Business Process Guideline for Project Documentation Engineering Operations Services Business Process Guideline for Project Documentation October 2002 Version 1 Global Team
More informationTHE VALSPAR CORPORATION
THE VALSPAR CORPORATION LABELING REQUIREMENTS FOR RAW MATERIALS SENT TO ALL VALSPAR CORPORATION LOCATIONS IN NORTH AMERICA January 2004 TABLE OF CONTENTS 1 Introduction...4 2 Compliance...4 3 Rationale...4
More informationLayton Construction Co., Inc. Quality Management Manual
Layton Construction Co., Inc QUALITY MANAGEMENT PLAN 1 Layton Construction Co., Inc. Quality Management Manual [ 2015 ] PHOENIX PHOENIX BOISE BOISE IRVINE IRVINE SALT LAKE CITY SALT ORLANDO LAKE CITY HAWAII
More informationREQUEST FOR PROPOSAL FOR GENERAL CONTRACTOR FOR AFFORDABLE MULTI-FAMILY HOUSING BREVARD COUNTY, FLORIDA. Issue Date: March 10, 2015
REQUEST FOR PROPOSAL FOR GENERAL CONTRACTOR FOR AFFORDABLE MULTI-FAMILY HOUSING BREVARD COUNTY, FLORIDA Issue Date: March 10, 2015 CLOSING DATE: Tuesday, March 31st, 2015, 2:00 p.m. EST Housing Authority
More informationARTICLE 11. INSURANCE AND BONDS
Provide submittals to Architect / Engineer that are required by any governing body or other authorities. Upon receipt of the Contractor s list, the Architect will make an inspection to determine whether
More informationBy following these guidelines, the illustrator will help production proceed more efficiently.
Exhibit A Picture Books for Children: Nefu Books Technical Guidelines Purpose Nefu Books staff will design and layout a picture book in Adobe InDesign using text submitted by the author(s) and illustrations
More informationExecutive Office for Administration & Finance. Request for Qualifications For Construction Management Services
Executive Office for Administration & Finance Request for Qualifications For Construction Management Services Massachusetts State Project (Project Number) (Full Project Name and Location), Massachusetts
More informationRequest for Proposal Permitting Software
Request for Proposal Permitting Software Date Issued: October 7, 2015 Proposals Due no later than: 2:00pm EST on November 10, 2015 Page 1 of 10 Revised 10/5/2015 TABLE OF CONTENTS Section I Introduction
More informationItems Required to Submit for Specialized Certificate of Occupancy for Operating a Sexually-Oriented Business City of Fort Worth, Texas
Items Required to Submit for Specialized Certificate of Occupancy for Operating a Sexually-Oriented Business City of Fort Worth, Texas Applicant should review Chapter 5, Article 2, Comprehensive Zoning
More informationCSC-DIVISION 1-MASTER SECTIONS Description
CSC-DIVISION 1-MASTER SECTIONS Description 01 11 00 Summary of Work by Consultant 01 12 00 Multiple Contract Summary by Consultant 01 14 00 Work Restrictions see below 01 21 00 Allowances by Consultant
More informationEffective Collaboration using Revit Structure and AutoCAD MEP
REVIT STRUCTURE Effective Collaboration using Revit Structure and AutoCAD MEP This white paper explains how structural engineers using Revit Structure software and mechanical/electrical/plumbing (MEP)
More informationBEST PRACTICES EMAIL DESIGN
BEST PRACTICES for EFFECTIVE EMAIL DESIGN July 2008 BEST PRACTICES for EFFECTIVE EMAIL DESIGN The number of professionals and businesses using email as part of their marketing campaign is growing. According
More informationREQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION
REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION
More informationSPECIFICATIONS FOR NW CONTROL CENTER, HURRICANE HARDENING - SARASOTA ISSUE FOR CONSTRUCTION
SPECIFICATIONS FOR NW CONTROL CENTER, ISSUE FOR CONSTRUCTION PREPARED FOR: FLORIDA POWER & LIGHT 700 UNIVERSE BLVD JUNO BEACH, FLORIDA 33408 PREPARED BY: ARCHITECTS ENGINEERS CONSTRUCTORS Board of Architecture
More informationGIS Spatial Data Standards
GIS Spatial Data Standards Manatee County, FL GIS Section, Information Services Department TABLE OF CONTENTS I. Introduction 2 A. Purpose 2 B. Reference 2 II. Spatial Reference Information 2 A. Projection:
More informationBASE CONSTRUCTION INC
BASE CONSTRUCTION INC 14252 CULVER DRIVE A-630 IRVINE,CA 92604-0326 OFFICE:949 387-3471 Shop 714 994 9563 CELL:949 735-5292 FAX:949 786-8753 QUALITY ASSURANCE and QUALITY CONTROL MANUAL 1 TABLE OF CONTENTS
More informationTransbay Transit Center Program. CADD Standards Manual. Revision 2. November 2010
Transbay Transit Center Program CADD Standards Manual Revision 2 November 2010 CADD Standards Manual Revision 2 November 2010 Issued by the Transbay Joint Powers Authority 1.0 INTRODUCTION TO... 1 1.1
More informationSUBMITTING A PRESS-READY COVER For Paperback Books with Perfect Binding, Plastic Comb, and Plastic Coil Binding
For Paperback Books with Perfect Binding, Plastic Comb, and Plastic Coil Binding Press-Ready Material We will only accept a digital file for a press-ready cover. The file must be print-ready with no typesetting
More informationATTACHMENT A1 SCOPE OF WORK
ATTACHMENT A1 SCOPE OF WORK Title-I Services June 6, 2016 Page 1 of 5 DISTRICT OF COLUMBIA DEPUTY MAYOR FOR PLANNING AND ECONOMIC DEVELOPMENT RENOVATION TO WILSON BUILDING 2 ND AND 3 RD FLOOR SUITES TITLE-I
More informationWake County Public School System Rogers Lane Elementary School (E40) Raleigh, North Carolina INSTRUCTIONS TO BIDDERS
Wake County Public School System Rogers Lane Elementary School (E40) Raleigh, North Carolina INSTRUCTIONS TO BIDDERS General Information: The work includes the construction of a new three story elementary
More information2014 yearbook. recognition. www.theyearbookcompany.com
204 the recognition ads(aka baby ads) CONGRATULATE Your Senior in their 204 postmarked by ON OR BEFORE: September 24 th (early bird), October 5 th (FINAL date) importantinformation - All materials (photos
More informationRegion 7 Education Service Center Request for Proposal (RFP) For Generator Installation
Region 7 Education Service Center Request for Proposal (RFP) For Generator Installation Purpose The purpose of this Request for Proposal (RFP) is to invite prospective vendors to submit a proposal to supply
More informationPROJECT CLOSEOUT PROCESS & PROCEDURES
PROJECT CLOSEOUT PROCESS & PROCEDURES MARY HENDERSON-REPS, CONTRACT ADMINISTRATOR DENVER INTERNATIONAL AIRPORT FEBRUARY, 2016 CLOSEOUT PROCESS - Closeout is defined as being The period that represents
More informationLIBERTY INDEPENDENT SCHOOL DISTRICT, LIBERTY,TEXAS REQUEST FOR PROPOSAL DELINQUENT TAX ATTORNEY RFP #13-01
LIBERTY INDEPENDENT SCHOOL DISTRICT, LIBERTY,TEXAS REQUEST FOR PROPOSAL DELINQUENT TAX ATTORNEY RFP #13-01 TABLE OF CONTENTS I. INSTRUCTIONS... 3 A. BID INFORMATION... 3 B. BID PROPOSAL FORMAT... 4 C.
More informationSharePoint for Engineering Document Management & Control
SharePoint for Engineering Document Management & Control Managing and controlling engineering documents and drawings with SharePoint A white paper by Cadac Organice BV Date: 01-03-2012 Table of contents
More informationRequest for Proposal RFP #201501. Printing & Mailing Services
Request for Proposal Printing & Mailing Services Date of Issue: 03/24/2015 For period beginning: 05/01/2015 Due Date/Time for Receipt of Proposals: 04/06/2015 @ 2:00 p.m. (EDT) RFP Number: 201501 Date
More informationRequest for Qualifications. Owner s Project Manager. Design and Construction of a New School Facility. K~8 Charter School
Request for Qualifications Owner s Project Manager Design and Construction of a New School Facility K~8 Charter School 26 Madeira Avenue New Bedford, MA 02746 REQUEST FOR QUALIFICATIONS (RFQ) Issued: 4/16/2014
More informationArt Submission Guidelines
Art Submission Guidelines Organizing artwork for your manuscript may seem like a daunting task, but the following guidelines will walk you through our art submission process. Whether you have a large set
More informationCASE NO. 279 CIVIL ACTION APPLICABLE TO ALL CASES CASE MANAGEMENT ORDER NO.5
FILED 'JUL 18 2008 JUdge Jamie D. Happas IN RE: GADOLINIUM BASED CONTRAST AGENTS LITIGATION SLTPERIOR COLTRT OF NEW JERSEY LAW DIVISION: MIDDLESEX COUNTY CASE NO. 279 CIVIL ACTION APPLICABLE TO ALL CASES
More informationState of Ohio Model Bid/Quote Template for General Goods & Services (Non-IT)
State of Ohio Model Bid/Quote Template for General Goods & Services (Non-IT) Guidance Document Department of Administrative Services, Office of Procurement Services 6/4/2015 Contents Purpose... 2 Background...
More informationUNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 10 (February 2010) ----------------------------------- Preparing Activity: USACE Superseding UFGS-01 45 01.10 (January 2008) UNIFIED FACILITIES GUIDE SPECIFICATIONS
More informationREQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
More informationRequest for Qualifications (RFQ) Number 01-15 PUBLIC WORKS CONTINUING CONSTRUCTION AND ENGINEERING INSPECTION AND PROJECT MANAGEMENT SERVICES
City of DeBary Request for Qualifications (RFQ) Number 01-15 PUBLIC WORKS CONTINUING CONSTRUCTION AND ENGINEERING INSPECTION AND PROJECT MANAGEMENT SERVICES The City of DeBary, Florida is seeking standby
More informationDocument Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
More informationAGREEMENT FOR PROFESSIONAL DESIGN SERVICES
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES This Professional Design Services (this "Agreement"), made as of 20 by and between the University of Cincinnati (the "University") by the Division of Administration
More informationVENDOR INFORMATION. Company Name: Billing Address: Telephone #: Fax #: Contact Name: Cellphone #: Email Address: Secondary Contact:
VENDOR INFORMATION Company Name: Billing Address: Telephone #: Fax #: Contact Name: Cellphone #: Email Address: Secondary Contact: Cellphone #: Email Address: Please check the appropriate boxes for the
More informationREQUEST FOR QUALIFICATIONS For an AS-NEEDED CONSULTING PROJECT MANAGER(S) With Hospital, Clinical Care and Building Systems Renewal Experience
REQUEST FOR QUALIFICATIONS For an AS-NEEDED CONSULTING PROJECT MANAGER(S) With Hospital, Clinical Care and Building Systems Renewal Experience For the UNIVERSITY OF CALIFORNIA, SAN DIEGO On behalf of FACILITIES
More informationNEVADA IRRIGATION DISTRICT DEVELOPER REQUIREMENTS FOR TREATED WATER SYSTEM EXTENSIONS GENERAL
NEVADA IRRIGATION DISTRICT DEVELOPER REQUIREMENTS FOR TREATED WATER SYSTEM EXTENSIONS GENERAL An owner requesting treated water service to lands which do not otherwise have service available must comply
More informationCITY OF BELL PROFESSIONAL CONSULTING SERVICES FOR ROOF REPAIRS TO CITY OWNED FACILITIES
CITY OF BELL 6330 PINE AVENUE BELL, CA 90201 PH: (323) 588-6211 FAX: (323) 771-9473 CITY OF BELL PROFESSIONAL CONSULTING SERVICES FOR ROOF REPAIRS TO CITY OWNED FACILITIES I. INTRODUCTION City of Bell
More informationLAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application
Applicant shall indicate that the required information has been provided or is not applicable to the project by placing the appropriate mark in the first column of this checklist. Missing or incomplete
More informationQuestion(s): 4. Will color processing/scanning be required for photographs? If so, what is the estimated percentage? Answer(s): Yes, less than 2%.
Letter of Clarification #1 TO: All Prospective Vendors FROM: Joycie Sheba, Buyer II CC: Nina Cook, Purchasing Manager DATE: May 21, 2014 SUBJECT: Final Response for Vendor Questions regarding-request for
More informationTutorial. IMPORTING AND EXPORTING AutoCAD FILES (DWG)
In addition to Canvas numerous import and export capabilities, you can also import AutoCAD 2007 files into Canvas 11, edit them, and export to PDF format. Objectives After this exercise you will be able
More informationRequest for Proposal Architectural/Engineering Services. Adapt/SouthRiver CHC. P a g e 1
P a g e 1 Request for Proposal Architectural/Engineering Services Adapt/SouthRiver CHC RFP for Architectural/Engineering Services P a g e 2 Introduction (SRCHC), a Federally Qualified Health Center, is
More informationGIS DATA SUBMITTAL SPECIFICATION
SJC-CM-IMS-2030 MINET SN JOSE INTERNTIONL IRPORT GIS DT SUBMITTL SPECIFICTION TBLE OF CONTENTS Section Title Page 1.0 INTRODUCTION 2 1.1 Purpose 2 1.2 Scope 2 1.3 Reference Documents 2 2.0 REQUIREMENTS
More informationMaterials information guide
Materials Information guide Contents 2 3 4-5 6 7 8 9 10 Deadlines Ad Delivery Color Material Production Specs Black & White Material Production Specs Digital File Setup and ICC Profiles Proofing Checklist
More informationTOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT
TOWN OF MILFORD REQUEST FOR QUALIFICATIONS DESIGNER SERVICES FOR LIBRARY ROOF REPLACEMENT The Milford Board of Library Trustees, as the Awarding Authority, invites the submission of qualifications by responsible
More informationREVISED JUNE 2011. PLEASE DISCARD ANY PREVIOUS VERSIONS OF THIS GUIDE. Graphic Style Guide
REVISED JUNE 2011. PLEASE DISCARD ANY PREVIOUS VERSIONS OF THIS GUIDE. Graphic Style Guide 1 Introduction 2 Logo Fonts 4 Logo Color 6 Logo Size & Clear Space 8 Logo Composition 10 Logo Application 16 Corporate
More informationBluebeam vs. Adobe. Bluebeam Vu vs. Adobe Reader X
Bluebeam vs. Adobe Bluebeam s PDF solutions are smart, so you don t have to be. Whether you are an engineer that needs to FTP complex CAD drawings or a project coordinator that wants to e-mail secure MS
More informationBrevard County Public Works Finance and Contracts Administration
Brevard County Public Works Finance and Contracts Administration Public Works Survey & Mapping Division Review Check Sheet for Land Acquisition, Drainage, Roadway and Pedway Expansion, Asbuilts, Maintenance
More informationSECTION 6 ELECTRONIC PATTERN FILE TRANSFERS
SECTION 6 ELECTRONIC PATTERN FILE TRANSFERS IMPORT PATTERN SUBMITTAL PROCEDURE SPECIFICATIONS DMC requires an electronic copy of all import TOP patterns. The pattern should be sent electronically to Tech
More informationSo you say you want something printed...
So you say you want something printed... Well, that s great! You ve come to the right place. Whether you re having us design and edit your work, or you fancy yourself a designer and plan to hand over your
More informationTHE TOWN OF NORTH SMITHFIELD
THE TOWN OF NORTH SMITHFIELD SPECIFICATIONS FOR REQUEST FOR PROPOSALS FOR EMERGENCY PLANNING, DISASTER RECOVERY, DEBRIS MANAGEMENT, AND HAZARD MITIGATION PROGRAM SERVICES SEPTEMBER 2014 FINANCE DIRECTOR
More informationWorkforce Solutions Brazos Valley Board P.O. Box 4128 Bryan, Texas 77805 (979) 595-2800 http://www.bvjobs.org/ Issue Date: May 2, 2013
REQUEST FOR PROPOSALS FOR Electronic Document Management System For the Workforce Solutions Brazos Valley Board Area Brazos, Burleson, Grimes, Leon, Madison, Robertson, and Washington Counties Issued by
More informationBRANDING STYLE GUIDE
BRANDING STYLE GUIDE THE GREEN WISE STORY Green Wise is a comprehensive program for paint manufacturers to test and market their environmentally responsible products to designers, specifiers, and retail
More informationCPIx on Line. Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Supporting the HMG Construction Strategy.
CPIx on Line Post Contract-Award Building Information Modelling (BIM) Execution Plan (BEP) Project Name: Project Address: Project Number: Date: Document No: Date: March 2013 Revision: R1 Status: Published
More informationAPPLICATION FOR CONDITIONAL USE PERMIT PROPOSED USES WITHIN EXISTING BUILDING
APPLICATION FOR CONDITIONAL USE PERMIT PROPOSED USES WITHIN EXISTING BUILDING City Use Only Planning Division 38250 Sierra Highway Palmdale, CA 93550 (661) 267-5200 planningdiv@cityofpalmdale.org Case
More informationUse this translator to save ArchiCAD layouts/views in DXF/DWG format if you plan to continue
Tip Sheet ArchiCAD 11 Mark Horrocks Graphisoft New Zealand May 2007 DWG Translator In Architectural practice you often send and receive content from co-working Structural, Mechanical or Electrical Engineers.
More informationScanned Images: How Well Do They Depict the Subtle Features in Handwriting?
Scanned Images: How Well Do They Depict the Subtle Features in Handwriting? For Presentation at the Measurement Science and Standards in Forensic Handwriting Analysis Conference National Institute of Standards
More informationEngineering Procurement Construction Quality Plan
Engineering Procurement Construction Quality Plan Index 1 Introduction... 4 1.1 Project Background... 4 1.2 Document Purpose... 4 1.3 Change Control... 4 1.4 Contract... 4 1.5 Quality system... 4 1.6 Distribution...
More informationKIP 3000 Series MULTIFUNCTION SIMPLICITY
KIP 3000 Series MULTIFUNCTION SIMPLICITY KIP 3000 SERIES SYSTEMS The KIP 3000 is a highly hl advanced d wide format digital copy system that provides the ability to easily add network printing and scan-to-file
More informationSample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES
SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work
More informationStreet Acceptance Guidelines
Street Acceptance Guidelines Virginia Department of Transportation & Fairfax County Procedural Guidelines Flowcharts and June 6, 2005 These guidelines and forms are subject to change. Check for updates
More information1 OPPORTUNITY SUMMARY
REQUEST FOR PROPOSALS: SOFTWARE IMPLEMENTATION PROJECT MANAGEMENT SERVICES Posting Date: Wednesday, September 23, 2015 Due Date: Tuesday, October 13, 2015 1 OPPORTUNITY SUMMARY The Massachusetts Clean
More informationPRINT SPECIFICATIONS PRINT ADVERTISEMENT SPECIFICATIONS BLEED AD SPECIFICATIONS DIGITAL SPECIFICATIONS MEDIA GLOBAL
PRINT SPECIFICATIONS PRINT ADVERTISEMENT SPECIFICATIONS BLEED AD SPECIFICATIONS DIGITAL SPECIFICATIONS GLOBAL MEDIA PRINT SPECIFICATIONS Please provide ad materials in one of the following formats: Acrobat:.pdf
More informationWINDOW AND DOOR REPLACEMENT REQUIREMENTS
WINDOW AND DOOR REPLACEMENT REQUIREMENTS Should you have any questions after reading the following information, please call the Building Inspection Department at 651-439-4439 to discuss the topics of concern.
More informationSALEM STATE UNIVERSITY
SALEM STATE UNIVERSITY INVITATION TO BID THIS IS NOT AN ORDER 1. The university is an agency of the Commonwealth of Massachusetts and is exempt from any State tax or Federal excise tax 2. Unless otherwise
More informationRFP Milestones, Instructions, and Information
This Request for Proposal is being issued by the Lower Colorado River Authority (LCRA). LCRA is a conservation and reclamation district of the State of Texas created pursuant to Article XVI, Section 59,
More informationCAD and Drawing Style Procedure
CAD and Drawing Style Procedure 0.1.1.8 Rev. 4 Date: 2014-Nov-20 Copyright 2014, Canadian Light Source Inc. This document is the property of Canadian Light Source Inc. (CLSI). No exploitation or transfer
More informationOlilo's AEC Design Services. SrinSoft Inc, Partners of
Olilo's AEC Design Services SrinSoft Inc, Partners of Olilo provides design services that include design and analysis, cost estimation, 3D modeling, 2D drafting, conversion from 2D to 2D, quantity take-off,
More informationCITY OF BONITA SPRINGS, FLORIDA RFP # 14-019
CITY OF BONITA SPRINGS, FLORIDA RFP # 14-019 Pursuant to Florida Statutes, Chapter 287, The City of Bonita Springs hereinafter referred to as the City, will accept sealed Responses for Qualifications and
More informationIMPORTANT! - Please use the attached Application for Payment. All payment requests must be submitted on our form. Thank you!
` SUBCONTRACTOR: PHONE PROJECT: LOCATION: Page 1 of 6 SUBCONTRACT (SHORT FORM) JOB NO.: COST CODE: PRICE: This agreement is made and effective, by and between SUN CONSTRUCTION & FACILITY SERVICES, INC.
More informationCompany Quality Manual Document No. QM Rev 0. 0 John Rickey Initial Release. Controlled Copy Stamp. authorized signature
Far West Technology, Inc. ISO 9001 Quality Manual Document No.: QM Revision: 0 Issue Date: 27 August 1997 Approval Signatures President/CEO Executive Vice President Vice President/CFO Change Record Rev
More information14-ITN-001-KH Workforce Services IT Procurement Project Questions and Answers
Respondent Question Number ITN Page Number, Section Number, Subsection Reference 1. Attachment R, Page #1, REQ #9, REQ Section: General System 2. Attachment R, Page #5, REQ #41, REQ Section: Case 3. Attachment
More informationForms CS. Checks & Forms
Forms CS Take 25% off your first order (Applies to Checks, Forms and s) Checks & Forms Forms CS P.O. Box 681, Tarrytown, NY 10591 1-800-909-1850 1-914-592-8616 FAX: 1-800-261-1499 www.formscs.com Dear