1 EAST AYRSHIRE COUNCIL CABINET 19 MARCH 2014 HOUSING INVESTMENT PROGRAMME 2014/ /19 Report by the Acting Executive Director of Neighbourhood Services and the Executive Director of Finance and Corporate Support 1. PURPOSE OF REPORT 2. To update the previously agreed Housing Investment Programme as presented to Cabinet on the 27 March 2013 and propose a revised Housing Investment Programme Strategy for 2014/15 to 2018/19 to ensure continuing support for the Council s commitments in terms of the Standard Delivery Plan until April 2015 and ongoing maintenance of the housing stock thereafter. 3. BACKGROUND 4. In 2004, the then Minister for Communities introduced the new Scottish Housing Quality Standard (SHQS) and set a target date of April 2015 by which date all local authorities and registered social landlords are required to achieve compliance. In order to deliver on these aims the Council developed a Standard Delivery Plan which was submitted and accepted by the Scottish Executive in May Works on the Housing Investment Programme until April 2015 require to be tailored towards achievement of the SHQS in any non-compliant housing and continued thereafter to ensure that currently compliant housing is maintained at a level that will avoid future failure. 6. Allocations to fund the works required in terms of the Housing Investment Programme allow the reallocation of programme slippages between financial years. This approach has been agreed and adopted to provide some certainty for forward planning assumptions whilst maintaining the required flexibility to redress slippage or increased progress within elements of the programme. To inform Cabinet of progress, a revised and proposed 5 year rolling Housing Investment Programme will be submitted annually for approval. 7. CURRENT POSITION 8. Stock condition surveys were originally carried out for 4600 properties following the stock options appraisal in 2005 and the result of this sample was extrapolated across the overall housing stock. The sample was spread both geographically and by house type to provide balanced information. This survey information was augmented by works that had been carried out since the date of the survey to reflect the position with regards to compliance with the Standard.
2 9. Stock condition surveying has been ongoing since July 2012 to ensure that the Council have a robust survey sample to evidence its position with regard to SHQS compliance. The position at 31 st January 2014 with regard to completed surveys is that 99.7% of properties have been surveyed externally and 61% of properties fully surveyed. Work is ongoing with regard to completing the partial surveys and it is anticipated that we will have approximately 90% of our stock fully surveyed by April Properties for inclusion in the Housing Investment Programme are identified through a combination of stock information, technical knowledge and life expectancy of the main components. Previous component renewal projects provide information with regard to compliance with the relevant criteria of the Standard. For example, where kitchen upgrade projects have been carried out, the specification used meets the requirements set out within the Standard. All properties (with the exception of refusals) will have had this upgrade work carried out prior to March The Council will require to apply for exemptions and abeyances with regard to compliance with the Scottish Housing Quality Standard. Exemptions/abeyances may be required in a number of situations. 12. Where work is not technically feasible 13. An example of this would be where the installation of cavity wall insulation is not appropriate due to the form of construction. East Ayrshire Council also have flatted blocks where it is not technically feasible to install secure entry doors due to the construction of entrance to the building. 14. Where work cannot be undertaken in mixed tenure blocks due to owner refusal 15. Abeyances will be sought where work is unable to be undertaken in common properties due to the refusal of owners within the block. This may apply where the Council is unable to obtain a majority agreement to carry out the installation of a new door entry system to a mixed tenure block. 16. Tenant refusal 17. Where tenants have refused to allow certain works such as kitchen, bathroom and electrical upgrading to be undertaken due to personal reasons, health reasons etc, abeyances may be required to satisfy the requirements of the Standard. 18. Disproportionate Cost prior to Exemptions will be sought for properties that require major investment beyond 2015 or are identified to be removed from stock and the investment required is disproportionate. Where these properties are vacant, they will not be considered for social let until the proposed work is completed.
3 20. PROPOSED HOUSING INVESTMENT PROGRAMMES 2013/ / Asbestos Significant progress continues to be made to identify and remove asbestos from the Council s housing stock to protect the occupants and any workers employed in repairs and improvements. However, the proposed demolition works and ongoing major improvement works of replacing heating systems and renewing kitchens and bathrooms involves gaining access to previously untested areas of Council houses where asbestos products may still be encountered. 22. Prior to carrying out these major works, location specific Refurbishment/Demolition Asbestos Surveys are being undertaken in addition to carrying out Asbestos Management Surveys in each property as required. It is, therefore, proposed to set aside a provisional sum of 2.05m over the period of the plan to deal with identification, sampling and asbestos removal and to safely facilitate the ongoing works programmes. 23. Energy Efficiency The replacement of doors and screens with UPVC double glazed units in recent years continues to reduce the need for demand repairs and improves the energy efficiency of the Council housing stock. The new units have an anticipated lifespan of 40 years. Provision of these improvements will reduce the Council s annual maintenance costs and will significantly extend the period before replacement is again required. 24. The Council has committed to an accelerated programme of both window and door installations to enhance the thermal properties of its homes. A total estimated provision of 6.65M over the period of the plan has therefore been set aside in the Housing Investment Programme to ensure the Council meets all SHQS commitments and agreed commitments regards thermal improvements. It is planned to carry out the replacement of 600 doors and screens and 400 window replacements during 2014/ East Ayrshire Council continues to explore all potential funding streams with regard to energy efficiency with particular focus on reducing fuel poverty. 26. The Scottish Government launched the Home Energy Efficiency Programme Scotland: Area Based Schemes (HEEPS: ABS) in 2013 with a key focus on assisting home owners within mixed tenure properties to participate in certain qualifying projects. This scheme was anticipated to work in direct association with Energy Company Obligation Funding (ECO) which was to be provided by the energy utility companies. 27. Recent Government changes relating to levies applied to energy utility companies have had an immediate effect on the amount of ECO funding available and have reduced the opportunities to attract this. The current position with regard to ECO is unclear and further guidance is awaited.
4 28. Notwithstanding this, two main energy efficiency projects have been identified by Housing Asset Services to utilise current funding available for 2013/14 through HEEPS:ABS. These projects must be confirmed and owners fully signed up prior to 31 st March 2014 with work being carried out prior to October timber framed houses (68 EAC and 48 private owners) in Muirkirk, Cumnock, Logan and Dalrymple are proposed to receive external wall insulation and a render finish. Owners will receive significant grant funding for this work should they agree to participate hard to treat flatted 4 storey blocks in Kilmarnock (32 EAC tenants and 32 private owners) have been identified to benefit from external wall insulation and render finish. These properties have had ongoing structural failures in concrete sills and lintels and this proposed work will allow resolution of this along with the energy efficiency improvements. 31. The properties are 8, 10, 11, 15 Kirktonholm Place, 10, 12 Gallion Walk and 12, 15 St Andrews Walk, Kilmarnock. 32. Repair work was originally planned for these particular flatted blocks and owners were informed of the costs that would be apportioned to them. Due to the high cost of these repairs, the level of remedial work was limited to current failure only although future failure is inevitable. The visual result of this work would undoubtedly be a patchwork effect. 33. This external insulation and render proposal will allow owners within these 8 blocks to benefit from significant grant funding. They will still require to contribute to the initial identified repair costs but the shortfall will be met by the available grant funding (and discretionary grant assistance where required.) 34. Failure to gain approval or the consent of every owner within each block will prevent the progress of this project and the funding will be unable to be fully utilised. 35. While a large proportion of the cost of this work for the East Ayrshire Council properties within the above projects will be funded from the external envelope budget (the aspiration is that 100 EAC properties would benefit from external insulation and new render), an estimated provision of 0.64m has been allowed for, over the period of the plan to assist with both this work and also with ongoing energy efficiency projects. 36. Efficient Heating The Council is committed to addressing problems with obsolete and inefficient heating systems and to gradually standardise heating boiler types to reduce the variety of heating units currently installed across the housing stock. It is crucial to continue to invest in new efficient central heating systems sourced from a chosen manufacturer that can provide a high level of support and comprehensive spares provision. The proposed 5 Year Housing Investment Programme, therefore, allows for the renewal of heating systems
5 with gas fuelled grade A condensing combination systems where a mains gas supply is available. 37. These works, when allied to the provision of thermal insulation packages, will assist all homes where this work is undertaken, to achieve the National Energy Rating required by the Standard and will assist in the reduction of fuel poverty. It should be noted that where no mains gas is available and a replacement system is required, a wet electric heating system will be installed. 38. It is estimated that cyclic replacement of 850 units per annum is necessary to reach and maintain the necessary Standard and a total estimated provision of 12.5m has been set aside in the 5 Year Housing Investment Programme. 39. External Envelope Enhancement These works address the requirement to replace failing roof coverings, address failing roofs that require redesign to improve the longevity of the structure, and works to the external walls of properties to deal with water ingress and poor energy efficiency. It is recognised that the existing housing stock requires investment in these key areas over future years. 40. Stock condition data has been used to identify the estimated remaining life span of these major components and identify work requirements for compliance with the Standard. This information will continue to be used to inform and influence future programmes of work. 41. It is planned to renew roof coverings to 100 flatted properties and to carry out the redesign and renewal of the roof to a block of 11 flats during 2014/15. The properties identified for this work are all within mixed tenure blocks. 42. The current programme of properties receiving new external render and cavity insulation replacement is planned to continue in 2014/15. The Council acknowledged the need to invest in this particular area of work in coming years with a commitment in the HIP Cabinet Paper of 27 March 2012 to provide an additional 0.880m per year from the Repair and Renewal Fund to accelerate the programme. The aspiration of the Council is to continue to provide additional support but this will be subject to affordability and review relating to the final three years of this five year plan. Projected numbers within Appendix 1 for years 2016/17, 2017/18 and 2018/19 are therefore based on additional finance being available for these years. 43. A total of 300 properties have been identified to receive new rendering in 2014/15. Some of these properties will also receive external wall insulation as identified in paragraphs 29, 30 and The total required provision, including this proposed additional funding, is therefore estimated at 15.6m. 45. It should be highlighted that the rendering programme has had considerable issues with regard to mixed tenure ownership. Where East Ayrshire Council
6 do not factor the block in question, they require obtaining majority consent within each block to allow the work to proceed. 46. A decision was taken in 2013 to allow owners in these mixed tenure blocks to opt out of the rendering works even if East Ayrshire Council had the majority consent to progress with the full work to the common block. 47. While this has meant that private owners have not been forced to participate and to pay the associated costs of this project, it has resulted in a number of blocks having a partly rendered finish which is not aesthetically pleasing. 48. Unfortunately, there have also been situations in some mixed tenure blocks where East Ayrshire Council have not been able to gain a majority consent to either fully or partly render the property, meaning that some tenants were unable to benefit from the improvements. 49. There have also been technical concerns where a Council flat is below a private flat and consent has been obtained to render the area outside the Council property only. The potential for water ingress from the above flat causing future damage to the lower render is a risk that requires to be considered. 50. Given the above issues and concerns, the position will require to be closely monitored and may require to be reconsidered. 51. Modern Facilities and Services Modern facilities and services are a principal requirement of the Scottish Housing Quality Standard. The current co-ordinated renewal of all the major internal facilities and services through a single multi-work contract continues to provide economies of scale with regard to time and cost, whilst also ensuring that disruption to tenants is minimised and satisfaction enhanced. The current single multi-work contract includes electrical upgrading, kitchen and bathroom renewal and redesign, internal plumber work renewal, and replacement of any encountered lead piping feeds. 52. It is proposed to carry out these works to 820 properties during 2014/15 to ensure that we meet the requirements of the Standard by April A total estimated provision of 23.3m would be required during the period of the plan to continue to carry out this improvement work based on life cycles of 15 years for kitchens and 30 years for bathrooms. 54. While the current aspiration of the Council is to replace kitchens every 15 years, consideration could be given to extending this replacement cycle on a short term basis for a 5 year period (the last 4 years of this plan as well as the following year.) Based on current costs, this would reduce the proposed costs for the period of the current plan by 7.36m. 55. The net effect of this temporary reduction would be that properties improved following the 5 year period would have waited 17 years for the improvement
7 work as opposed to 15 years. A decision could then be taken as to whether to revert to a 15 year cycle for future years. 56. Timber Houses There are a number of timber properties within the Council area which have required annual external decoration and timber preservation works in previous years as part of a cyclic maintenance programme to maintain the exterior envelope in sound condition. 57. It is proposed that the funding for 2014/15 be used along with the other available funding to deliver the external wall insulation and render to timber framed houses identified in paragraph 29. This project requires the timber to be repaired and treated prior to the external insulation system being fitted. Once rendered, these properties will be removed from the cyclic preservation works programme for future years. This work would both improve energy efficiency and provide a long lasting external wall finish. 58. Decisions on years 2-5 of the plan would require taking account of the available energy efficiency funding at that time. It is proposed that if similar funding is available, further timber framed properties throughout the Authority should benefit from the improved energy efficiency and long lasting external wall finish that this work would bring. 59. A provision of 1.0m has been allowed for over the period of the plan to assist with this work. 60. Safe and Secure Neighbourhoods It is proposed to install door entry systems where no system presently exists and continue replacement of existing systems that have either failed due to obsolescence or remain inoperative for protracted periods due to ongoing vandalism or the difficulties in sourcing replacement components. The works include the provision of metal or timber security doors and screens dependent on the condition of the current units and the history of damages from forced entry. 61. It is currently estimated that an average 70 houses will be addressed per annum, with a total estimated overall cost of 0.5m during the period of the plan. 62. Stock Initiatives There are currently a number of properties within the housing stock where issues of low demand and/or significant disrepair have been identified. Some properties may give cause for concern for a variety of reasons and a considered, sensible and proportionate response is required to ensure that we maintain sustainable neighbourhoods whilst providing value for money. It is important to ensure that the properties that we own and manage are in good condition, in the right location, and of a design that is fit for purpose. 63. Where properties throughout the area are identified as difficult to let, have no registered waiting list demand and/or require significant investment,
8 consideration must be given to the long term sustainability of these buildings. This will involve the need for a whole organisation approach to ensure that well informed decisions are taken. 64. Consideration has been given to determine the most cost - effective solution in each case and this has informed the proposals for action as set out below: Proposed Demolition 9-15, 17-23, 18-24, Mason Avenue, New Cumnock 9-15 Somerville Street, Catrine 17-19, 21-27, 29-35, Greenbraes Drive, New Cumnock Holmhead, Logan 1-6 Girvan Crescent, Newmilns Barshare Road, Cumnock Knockinlaw Road, Kilmarnock Church Street, Auchinleck 65. Lock-up Garages A number of lock-up garages have been identified as low demand and in need of investment. It is recommended that consideration be given for the following units to be demolished and the sites cleared. Rigghead North, Stewarton 13 units Kirkton Road, Kilmarnock 12 units Bellsland Place, Kilmarnock 24 units Boyd Street, Kilmarnock 27 units Witch Road, Kilmarnock 9 units Keith Place, Kilmarnock 40 units Mackellar Place, Kilmarnock 22 units Henderson Drive, Muirkirk 5 units Lovedale Crescent, Muirkirk 11 units Burnbank Street, Darvel 7 units Kilnholm Street, Newmilns 8 units 66. Any further proposals for action will be submitted for elected member consideration at the appropriate time 67. A provisional sum of 1.4m has been included within the period of this plan to take these proposals forward. 68. At the meeting of the Council on 12 December 2013, it was agreed that 0.80M should be invested in housing environmental improvements. Work is ongoing at present to compile a programme of common entry painting. 69. The table below shows the aspirational lifecycle for main renewal programmes. These figures are notional and for guidance purposes only.
9 Gas Central Heating Installations Kitchens Bathrooms Render Windows and Doors Concrete Tiled Roofs Slated Roofs Flat roofs 15 years 15 years 30 years years years 40 years 80 years years 70. SCHEME OF ASSISTANCE 71. The Council have previously been able to assist adjacent owners within mixed tenure blocks with advice and in some cases financial grant assistance where the block was included in the investment programme through the Council s Scheme of Assistance. Any financial assistance is discretionary, subject to available resources and is subject to means testing. Grant assistance is only considered where the parts that is subject to improvement works are owned in common with East Ayrshire Council s own housing stock. 72. This assistance is intended to help the Council to obtain consent from adjacent owners and encourage owners to be involved in the programmed works. East Ayrshire Council are not currently in a position to offer a formal loan in respect of the payment for common works. 73. The increase in planned external fabric works to mixed tenure blocks has placed a greater strain on the funding available for this purpose and it is important that any financial assistance that is available is provided to the most appropriate cases. 74. It is proposed that the current arrangements and eligibility criteria be reviewed with a view to optimising opportunities for progressing with the Housing Improvement Programme where multi-tenure issues present potential impediments. 75. STRATEGIC LOCAL PROGRAMME 76. Further to the award of additional resources to Councils Resource Planning Assumptions by the Scottish Government, a report was submitted to Cabinet in April 2013 to increase the proposed number of units of affordable housing to be developed in response to the additional allocation. A total of 200 houses across 12 sites are currently being developed for Council housing. Site start has been achieved on 7 sites to date, following receipt of competitive tenders, with the balance all due to commence works by April A separate report to this Cabinet provides an update on the progress of the Strategic Local Programme as well as the Strategic Housing Investment Plan 2013/ /2018.
10 77. Progress on taking matters forward continues to be managed by a Project Board comprising senior officers from relevant services across the Council led by the Acting Executive Director of Neighbourhood Services. Progress on delivering the programme will be reported to elected members through East Ayrshire Performs. 78. FINANCIAL IMPLICATIONS 79. The Housing Investment Programme for 2013/14 is currently projected to outturn 1.427m less than budget. This is due to render and roofing projects being delayed due to weather and procurement issues. These works will be carried out in 2014/ Phased allocations have also been provided for all further financial years to 2018/19, however, it should be noted that the contract figures given in the tables appended to this report are based on known historic costs and should be regarded as provisional only at this time pending completion of the usual procurement and tendering exercises. Therefore where the work programme is under or over committed in any future years, there may be a compensatory increase or decrease, but the programme will be maintained to achieve the Scottish Housing Quality Standard by 2015, and an ongoing sustainable housing stock within the approved maximum allocation. 81. The estimated increase in the debt financing costs in the financial years up to 2018/19 arising from the proposed increase in the level of capital investment is 1.885M based on Appendix 1. It is expected that this will be met through increased budget provision within the Housing Revenue Account. This approach will be subject to annual review to ensure that the longer-term affordability and sustainability of the investment programme is maintained 82. Details of the source of finance for the plan are shown on Appendix LEGAL IMPLICATIONS 84. Any private properties that within the scope of the Council s stock initiative proposals as identified in Paragraph 64 of this report will require to be repurchased to allow the demolition to proceed. 85. The remaining Scottish Secure tenants, the private owners and any private tenants within the blocks may be entitled to receive home loss and disturbance payment under the terms of the Land Compensation (Scotland) Act In addition, any private owner or private tenant entitled to a disturbance payment is entitled in terms of the 1973 Act, in an identical manner to the remaining Scottish Secure tenants, to be re-housed by the Council
11 86. COMMUNITY PLANNING IMPLICATIONS 87. The annual Housing Investment Programme improves the condition of the council housing stock towards achievement of the Scottish Housing Quality Standard by 2015 and supports the East Ayrshire Community Plan themes of Delivering Community Regeneration and Improving Health and Wellbeing. 88. ASSET MANAGEMENT IMPLICATIONS 89. The ongoing investment programme improves and maintains individual properties and supports the long term sustainability of the council housing stock in East Ayrshire. 90. RISK MANAGEMENT IMPLICATIONS 91. Due to the currently experienced and future predicted falls in receipts from house and land disposals, greater reliance on borrowing and support from the Housing Revenue Account is anticipated. Any further reduction in funding is likely to prejudice the achievement of the Standard by 2015 and affect future sustainability of the housing stock thereafter. 92. The Housing Investment Programme and Standard Delivery Plan is based on the present Scottish Housing Quality Standard in terms of affordability. Any future additions to the Standard would require the overall Standard Delivery Plan to be reappraised and a new Delivery Plan would require to be produced to address the requirements after the present 2015 deadline. 93. Any reduction in cyclic replacement based on the life expectancy of components, such as heating systems, would result in future increased costs for the Council through increased failures and obsolescence of parts. Tenant satisfaction levels would likely reduce as a result of increased waiting times for replacement, lower heating efficiency and increased fuel costs, in turn leading to increased fuel poverty. 94. Any significant slippage would result in a general extension of timescales over which improvements are delivered. Any significant extension of timescales would require the revision of the currently published 5 year plan and would mean that the 2015 target may not be achieved or, in later years, sustainability would be compromised. 95. The removal or reduction of Private Sector Housing Grant may have a significant impact on the ability of East Ayrshire Council to encourage private owners within mixed tenure blocks to participate in planned works.
12 96. RECOMMENDATIONS 97. It is recommended that the Cabinet: i) Approve the reduced number of modern facilities and services improvements as specified at paragraphs 54 and 55 and Appendix 1; ii) Approve the clearance and demolition of properties identified in paragraphs 64 and 65. iii) Note the issues with regard to mixed tenure properties within the render programme identified in paragraphs iv) Approve all other proposals for the 5 Year Housing Investment Programme for the period 2014/15 to 2018/19; v) Note that regular reports on progress in delivering the programme will be submitted to members through the budget scrutiny arrangements throughout the year; vi) Otherwise note the contents of the report. Chris McAleavey Acting Executive Director of Neighbourhood Services Alex McPhee Executive Director of Finance and Corporate Support LIST OF BACKGROUND PAPERS Any person wishing further information should contact Gary Craig, Housing Improvement Manager, Housing Asset Services Implementation Officer: gerry.darroch@east-ayrshire.gov.uk
13 APPENDIX 1 Housing Improvement Programme 2014/15 TO 2018/ / / / / /19 Cost Cost Cost Cost Cost Contract Type No. K No. K No. K No. K No. K K Door and Screen replacement ,650 Efficient Central Heating 850 2, , , , ,500 12,500 Re-roofing (inc. chimneys/gutters etc) , , ,100 4,900 Specialist re-roofing Modern Facilities and Services 820 4, , , , ,860 15,940 External envelope enhancement 300 2, , , , ,100 10,500 Energy Efficiency n/a 170 n/a 170 n/a 100 n/a 100 n/a Door Entry Systems Window Renewals (initially of single glazed) 400 1, , , , ,000 5,000 Asbestos Testing/Removal n/a 410 n/a 410 n/a 410 n/a 410 n/a 410 2,050 Stock Initiatives / Demolition ,400 Timber House Investment ,000 Total 12,710 10,720 10,950 10,950 10,950 56,280 Council House Build Programme House Building SLP 26,134 House Building SHIP 3, , ,844 13,932 10,950 19,438 10,950 94,114 Financed by Capital Funded from Current Revenue (CFCR) 9,811 9,811 9,811 9,811 9,811 Capital Receipts Drawdown from Repairs and Renewals Scottish Government Grant (SLP) 9, Scottish Government SHIP ,116 0 Borrowing 17,823 1, ,511 1,139 28,179 Total 38,844 13,932 10,950 19,438 10,950 94,114
Title: Corporate Asset Management Strategy
Title: Corporate Asset Management Strategy Date of issue: January 2015 Date of next review: January 2016 Author: V Thornton Service area applies to: Operations/Development Link to the Corporate Plane:
More informationHOUSING REVENUE ACCOUNT KEY ISSUES CAPITAL OUTTURN 2014/15
APPENDIX 4 HOUSING REVENUE ACCOUNT KEY ISSUES CAPITAL OUTTURN 2014/15 The spend for the year is 30,225,000. This can be compared with the budgeted figure for 2014/15 of 34,929,000 resulting in an under
More informationEAST AYRSHIRE COUNCIL. CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME
EAST AYRSHIRE COUNCIL CABINET 24 April 2013 2013-14 BRIDGE AND CULVERT STRENGTHENING PROGRAMME Report by the Depute Chief Executive/Executive Director of Neighbourhood Services PURPOSE OF REPORT 1 The
More informationHILLCREST HOUSING ASSOCIATION LIMITED MAINTENANCE POLICY
HILLCREST HOUSING ASSOCIATION LIMITED POLICY NO. AM14 MAINTENANCE POLICY 1.0 INTRODUCTION 1.1 This policy describes our arrangements for ensuring that our properties are well maintained and kept in good
More informationHow To Manage Property In Tower Hamlets
2015 2020 Page 1 of 15 Contents 1 Introduction 2 What is Asset Management 3 Limitations 4 THCH Asset Profile 5 How the Asset Management Strategy Supports THCH s Strategic Priorities 6 How The Asset Management
More informationEAST AYRSHIRE COUNCIL GOVERNANCE AND SCRUTINY COMMITTEE - 14 AUGUST 2014 AWARDING OF CONTRACTS - PERIOD FROM 15 MAY TO 30 JULY 2014
EAST AYRSHIRE COUNCIL GOVERNANCE AND SCRUTINY COMMITTEE - 14 AUGUST 2014 AWARDING OF S - PERIOD FROM 15 MAY TO 30 JULY 2014 Report by the Executive Director of Finance and Corporate Support 1. PURPOSE
More informationApproved by Management Committee 24/03/11 Strategy Document
ELHA POLICY Date Issued May 2007 Last Revised March 2011 Department Asset Management Title Asset Management Strategy Objective To outline the Association s strategy for managing its assets Responsible
More informationREACTIVE REPAIRS, CYCLICAL & PLANNED MAINTENANCE POLICY
POLICY REF : AM05 Version No. 4.0 August 2012 REACTIVE REPAIRS, CYCLICAL & PLANNED MAINTENANCE POLICY 1.0 INTRODUCTION 1.1 This policy describes our arrangements for ensuring that our properties are well
More informationNORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013
APPENDIX 1 NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 Page 1 of 10 1. INTRODUCTION It is widely recognised that asset management is a core component of effective
More informationWaltham Forest 2009-2011. Private Sector Housing. Renewal Assistance. Policy. Author: nigel.thornton@walthamforest.gov.uk
Waltham Forest Private Sector Housing Renewal Assistance Policy 2009-2011 Author: nigel.thornton@walthamforest.gov.uk 1 Contents Page 1. Introduction and background 3 1.1 Tenure Mix in The Borough 3 1.2
More informationAGENDA ITEM: 8 SUMMARY
AGENDA ITEM: 8 SUMMARY Report for: Housing and Community Overview and Scrutiny Committee Date of meeting: 28th January 2015 PART: 1 If Part II, reason: Title of report: Contact: Purpose of report: Recommendations
More information1.1 CHISEL's main activity is providing homes for our tenants to rent.
Maintenance Policies 1. Introduction 1.1 CHISEL's main activity is providing homes for our tenants to rent. 1.2 These homes have been provided with the aid of loans and are the security against which the
More informationCHESTERFIELD BOROUGH COUNCIL PRIVATE SECTOR HOUSING RENEWAL STRATEGY DRAFT FOR CONSULTATION
CHESTERFIELD BOROUGH COUNCIL PRIVATE SECTOR HOUSING RENEWAL STRATEGY 2012 2015 DRAFT FOR CONSULTATION October 2011 CONTENTS 1. Introduction 2. Links to other corporate strategies and policies 3. Policy
More informationSubject: HRA Financial Business Plan Review and Rent Increase Consultation Process. Report by: Head of Housing & Community Safety
CLACKMANNANSHIRE COUNCIL THIS PAPER RELATES TO ITEM 5 ON THE AGENDA Report to: Housing Health and Care Committee Date of Meeting: 5 November 2015 Subject: HRA Financial Business Plan Review and Rent Increase
More informationEAST AYRSHIRE COUNCIL CABINET27 NOVEMBER 2013 STEP CHANGE 2015 PROJECT UPDATE. Report by the Acting Executive Director of Neighbourhood Services
PURPOSE EAST AYRSHIRE COUNCIL CABINET27 NOVEMBER 2013 STEP CHANGE 2015 PROJECT UPDATE Report by the Acting Executive Director of Neighbourhood Services 1 The purpose of this report is to provide an update
More informationEAST AYRSHIRE COUNCIL CABINET 21 OCTOBER 2009 TREASURY MANAGEMENT ANNUAL REPORT FOR 2008/2009 AND UPDATE ON 2009/10 STRATEGY
EAST AYRSHIRE COUNCIL CABINET 21 OCTOBER 2009 TREASURY MANAGEMENT ANNUAL REPORT FOR 2008/2009 AND UPDATE ON 2009/10 STRATEGY Report by Executive Head of Finance and Asset Management 1 PURPOSE OF REPORT
More informationEAST AYRSHIRE COUNCIL CABINET: WEDNESDAY 13 MARCH 2013 WELFARE REFORM UPDATE ON IMPLEMENTATION ARRANGEMENTS
EAST AYRSHIRE COUNCIL CABINET: WEDNESDAY 13 MARCH 2013 WELFARE REFORM UPDATE ON IMPLEMENTATION ARRANGEMENTS Report by the Executive Director of Finance and Corporate Support 1. PURPOSE OF THE REPORT 1.1
More informationHome Energy Efficiency Programmes for Scotland Benefit and Tax Credit Checks Evaluation March 2015
Home Energy Efficiency Programmes for Scotland Benefit and Tax Credit Checks Evaluation March 2015 Energy Saving Trust Benefits Check Evaluation Draft Report page 1 of 10 Executive summary In November
More informationLONDON BOROUGH OF HAVERING
LONDON BOROUGH OF HAVERING CORPORATE ASSET MANAGEMENT PLAN 2015-2019 Sections LONDON BOROUGH OF HAVERING CORPORATE ASSET MANAGEMENT PLAN CONTENTS 1 Introduction and Context 2 Corporate Vision 3 Policy
More informationCompensation Policy Including statutory compensation, service failure and loss of amenities
Compensation Policy Including statutory compensation, service failure and loss of amenities Version Final By: Watkin Morgan Senior Manager Maria McCarron BOM approved: 22 March 2010 CONTENTS Section Page
More informationMeeting the Decent Homes Standard
Meeting the Decent Homes Standard 1 What is the Council trying to achieve in relation to the Standard. Does the Council know the condition of their housing stock and their compliance with the decent homes
More informationThe report summarises the outturn position for 2013/14 and the consequential impact on the Medium Term Financial Plan 2014/17.
TRAFFORD BOROUGH COUNCIL Report to: Accounts & Audit Committee 26 June 2014 Executive - 28 July 2014 Report for: Decision Report of: The Executive Member for Finance and the Director of Finance Report
More informationLHT S ASSET MANAGEMENT STRATEGY 2015-20. It s My Home
LHT S ASSET MANAGEMENT STRATEGY 2015-20 It s My Home 0 ASSET MANAGEMENT STRATEGY 2015-20 It s My Home Contents Page No 1. WHAT DOES OUR ASSET MANAGEMENT STRATEGY AIM TO DO? 2 2. WHY IS ASSET MANAGEMENT
More informationSection 1: Our assessment of the importance of housing for wellbeing in Scotland
Commission on Housing and Wellbeing Consultation 2014 North Lanarkshire Council Response Section 1: Our assessment of the importance of housing for wellbeing in Scotland Q1 Has our assessment of housing
More informationEAST AYRSHIRE COUNCIL CABINET 21 MAY 2014 DECOMMISSIONING, RESTORATION, AFTERCARE AND MITIGATION FINANCIAL GUARANTEES
EAST AYRSHIRE COUNCIL CABINET 21 MAY 2014 DECOMMISSIONING, RESTORATION, AFTERCARE AND MITIGATION FINANCIAL GUARANTEES Report by the Depute Chief Executive 1. PURPOSE OF REPORT 2. The purpose of this report
More informationThis policy details Stonewater s approach to the payment of compensation.
Compensation Policy 1.0 Policy Summary This policy details Stonewater s approach to the payment of compensation. It applies to all tenants. Where differences in the contractual rights of these customers
More informationH 7. Factoring Policy. If you require this policy in a different format please ask a member of staff. Date of Approval Oct 12 Review Due Dec 15
H 7 Factoring Policy If you require this policy in a different format please ask a member of staff Date of Approval Oct 12 Review Due Dec 15 1.0 The Association s Objective 1.1 Elderpark Housing Association
More informationAuthor: Adrian Pengelly Role: Director of Assets. Recommendations: 1. That the review of the Assets Directorate budget pressures for 2014/15 is noted.
Cornwall Housing Limited Report Template for DLT Agenda No: 7 Report to: The Board Part 1 Date: 27 July 2015 Title: Assets Directorate Budget Pressures 2014/15 Author: Adrian Pengelly Role: Director of
More informationFinancial Business Plan for Clackmannanshire Council Housing 2013-2018. Rent Consultation
Financial Business Plan for Clackmannanshire Council Housing 2013-2018 Background Rent Consultation In 2006 and 2007 we talked to our tenants to ask them how they wanted us to spend the rent money we collect.
More informationGuide to Funding a Major Adaptation
Guide to Funding a Major Adaptation August 2010 Contents Contents... 1 Introduction... 1 Chapter 1: Policy and funding framework... 2 The importance of tenure... 2 The policy framework... 2 Overview of
More informationHousing Asset Management Strategy 2010-14
Housing Asset Management Strategy 2010-14 Lead officer: David Hodgson EIA completed: March 2010 Date agreed: 25 March 2010 Review date: March 2012 Working Page together 1 of 30 to deliver quality homes
More informationASSET MANAGEMENT STRATEGY
ASSET MANAGEMENT STRATEGY 2012 2017 Proudly delivering excellent homes and services to our customers and communities Page 1 of 17 CONTENTS 1. INTRODUCTION 3 PAGE 2. AIMS OF THE STRATEGY 3-4 3. OPERATING
More informationThe Real Estate Loan and Equity Release Schemes
Housing Assistance Policy (Loans) 1 1.0 Introduction...3 2.0 Background...3 3.0. Research into the potential demand for equity release / loan schemes...4 4.0. The loan scheme...5 5.0 Eligibility for grant
More informationFife Council Scheme of Assistance from 2011/12 for Home Owners and Private Tenants
Fife Council Scheme of Assistance from 2011/12 for Home Owners and Private Tenants Approved 17 th May 2011 Contents 1. Introduction..1 2. Vision and Strategy 1 3. Priorities for Assistance...2 4. Access
More informationASSET MANAGEMENT STRATEGY 2014-2017
ASSET MANAGEMENT STRATEGY 2014-2017 EXECUTIVE SUMMARY Eight years after its creation, Stafford and Rural Homes (SARH) is at an exciting stage of its journey as a leading housing association in the Midlands.
More informationCustomer Compensation Policy
Date approved: 5 May 2014 Approved by: Chief Executive 1. Introduction 1.1 Southway Housing Trust (Southway) will provide high quality services to our customers and aim to get things right first time.
More informationAPPENDIX B - PL1 Homes that meet people s needs and aspirations
APPENDIX B - PL1 Homes that meet people s needs and aspirations Decent and accessible homes are vital to all. Our focus on providing affordable homes is being progressed primarily through the Affordable
More informationProperty Factors (Scotland) Act 2011
East Ayrshire Council Property Factors (Scotland) Act 2011 STATEMENT OF SERVICES Property Factors Registration Number: PF000382 2 Property Factors Registration Number: PF000382 1. Background The Property
More informationFACTORING AGREEMENT ARGYLL COMMUNITY HOUSING ASSOCIATION LIMITED
ARGYLL COMMUNITY HOUSING ASSOCIATION LIMITED This is a Factoring Agreement between Argyll Community Housing Association Limited, having our registered office at 63-65 Chalmers Street, Ardrishaig, Argyll,
More informationSection 1 Summary and Recommendations
REPORT FOR: CABINET Date of Meeting: 10 December 2015 Subject: Key Decision: Responsible Officer: Portfolio Holder: Exempt: Decision subject to Call-in: Wards affected: Homes for Harrow: Building homes
More informationA Guide to... Home Renovation Incentive (HRI)
A Guide to... Home Renovation Incentive (HRI) About this guide This guide will tell you what you need to know if you are organising to have construction work done on your house and would like to avail
More informationStatement of Services
Statement of Services Property Factors (Scotland) Act 2011 Property Factors (Scotland) Act 2011 Statement of Services What is the Property Factors Act? The Property Factors (Scotland) Act of 2011 is a
More informationCernach Housing Association Factoring Policy
1. INTRODUCTION Housing Association Limited Cernach Housing Association as a landlord and factor accepts the responsibility for providing a range of services for all of the properties under its control.
More informationEAST AYRSHIRE COUNCIL CABINET 7 MARCH 2012 TRAFFIC, TRANSPORTATION AND ROAD SAFETY PROGRAMMES 2012-13
EAST AYRSHIRE COUNCIL CABINET 7 MARCH 2012 TRAFFIC, TRANSPORTATION AND ROAD SAFETY PROGRAMMES 2012-13 Report by Depute Chief Executive/Executive Director of Neighbourhood Services 1. PURPOSE OF REPORT
More informationCompensation Policy. When we have failed to carry out emergency or urgent repairs
Compensation Policy Hexagon aims to give good standards of service in housing and care, but occasionally things do go wrong. If a tenant makes a complaint, we will investigate and put the matter right
More informationRight to Compensation For Improvements
Right to Compensation For Improvements ROSEHILL HOUSING CO-OPERATIVE LIMITED 250 Peat Road, Glasgow, G53 6SA 1. Introduction The Right to Compensation for Improvements The Housing (Scotland) Act 2001 (The
More informationRent to Buy 2015 to 2017
Rent to Buy 2015 to 2017 BIDDING PROSPECTUS September 2014 Rent to Buy Contents Page Number Ministerial Foreword 2 Chapter 1 Overview of the fund 3 Chapter 2 The funding model 4 Chapter 3 Bidding requirements
More informationCapital Expenditure. The common definition of capital expenditure is
Capital Expenditure Under standard accounting practices local authorities are required to account for revenue expenditure and capital expenditure differently. Capital expenditure is defined in the Local
More informationHousing Scrutiny Sub-Committee 27 March 2012
b Housing Scrutiny Sub-Committee 27 March 2012 Asbestos Commission Update All Wards Report authorised by: Executive Director Housing Regeneration and Environment Sue Foster Executive summary The Council
More informationFACTORING SERVICE BLOCKS AND COMMON PARTS
FACTORING SERVICE BLOCKS AND COMMON PARTS ABOUT OUR ORGANISATION Atrium Initiatives Atrium Initiatives was formed in 2005. Its parent company is Atrium Homes, a not for profit company. Atrium Initiatives
More informationHow We Review Rent, Management Fee & Service Charges
How We Review Rent, Management Fee & Service Charges Your views 2 CONTENTS Page 4 Rent, Management Fee & Service Charges Page 5 Our Approch to Rent Setting Page 6 Rent Increase Page 7 Close Cleaning Estate
More informationWRITTEN STATEMENT OF SERVICE /TERMS AND CONDITIONS OF SERVICE
WRITTEN STATEMENT OF SERVICE /TERMS AND CONDITIONS OF SERVICE Subjects covered by this written statement of service are These are the terms and conditions for the provision of a factoring service to owner
More informationFACTORING AGREEMENT ARGYLL COMMUNITY HOUSING ASSOCIATION LIMITED
ARGYLL COMMUNITY HOUSING ASSOCIATION LIMITED This is a FACTORING AGREEMENT between Argyll Community Housing Association Limited, having our registered office at 63-65 Chalmers Street, Ardrishaig, Argyll,
More informationState of Council - Local Area Development
Minutes Published: 26 March, 2013 Call-In Expires: 2 April, 2013 CANNOCK CHASE COUNCIL MINUTES OF THE MEETING OF THE CABINET HELD ON THURSDAY, 21 MARCH, 2013 AT 5.45 P.M. IN THE CIVIC CENTRE, BEECROFT
More informationFire Damage Reinstatement Works to Rollit House, Newington Barrow
Housing and Adult Social Services 7 Newington Barrow Way, London N7 7P Decision of Corporate Director of Housing and Adult Social Services Meeting of: Date Ward(s) Officer key decision 25 September 2015
More informationHome Improvement Insurance - UK Landlords
COMPENSATION POLICY LEAD OFFICER Bruce Johnson Director of Technical Services Board Approval: January 2011 Next Revieww Date: January 2013 CONTENTS 1.0 Introduction 2.0 Purpose 3.0 Right to Repair 4.0
More informationHousing Policy Repairs and Maintenance
Housing Policy Repairs and Maintenance This policy affects: Tenants X Leaseholders X Other: TMO Tenants X TMO Leaseholders X PFI1 Tenants PFI2 Leaseholders PFI2 Tenants PFI2 Leaseholders Author: Service
More informationTSA Standards Review: Home Standard
TSA Standards Review: Home Standard Guidance note: This document sets out, in pink, what is expected of a landlord to meet the TSA s national standards. We then explain: Heantun s existing service standards
More informationThe City of London Corporation Housing Asset Management Strategy. Karen Tarbox, Head of Property Services
The City of London Corporation Housing Asset Management Strategy 2015-2020 Lead author: Karen Tarbox, Head of Property Services Document owner: Director of Community and Children s Services Approved/agreed
More informationEAST AYRSHIRE COUNCIL PLANNING COMMITTEE: 16 MAY 2014 14/0237/PP REPLACEMENT WINDOWS AND INSTALLATION OF COMFORT COOLING CONDENSERS
EAST AYRSHIRE COUNCIL PLANNING COMMITTEE: 16 MAY 2014 14/0237/PP REPLACEMENT WINDOWS AND INSTALLATION OF COMFORT COOLING CONDENSERS AT: 2 THE CROSS, KILMARNOCK KA1 1LR BY: EAC CORPORATE INFRASTRUCTURE
More informationFalkirk Council Corporate & Neighbourhood Services HOUSING ASSET MANAGEMENT PLAN 2012-2017
Falkirk Council Corporate & Neighbourhood Services HOUSING ASSET MANAGEMENT PLAN 2012-2017 1 GLOSSARY ACRONYM AMP CNBP DFS EESSH FIR HAMP HNDA HRA ICT IHMS LHS OMSE RSL SCS SHQS OSA DESCRIPTION Asset Management
More informationBuilding Condition Assessment: 109-111 North Howard Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
More informationKnock Down Rebuild. Building Process Building process - knock down rebuild 1
Knock Down Rebuild Building Process Building process - knock down rebuild 1 Building Process Your action Our action REMINDER Pre site Step 1 New Home Selection Congratulations. This marks the start of
More informationCompensation Policy. 1. Aim of policy. Version Number: 2.0 UNCONTROLLED IF PRINTED
Compensation Policy Policy Ref: POL-BA-COMPEN Version Number: 2.0 Policy Owner Customer Insight Lead UNCONTROLLED IF PRINTED 1. Aim of policy 1.1. City West Housing Trust (City West) is constantly striving
More informationManchester City Council Report for Information. Communities and Neighbourhoods Overview and Scrutiny Committee 8 December 2009
Manchester City Council Report for Information Report To: Subject: Report of: Communities and Neighbourhoods Overview and Scrutiny Committee 8 December 2009 Boiler Repairs in Council Stock and in Northwards
More informationA Decent Home. The definition and guidance for implementation. February 2004. housing
A Decent Home The definition and guidance for implementation February 2004 housing A Decent Home The definition and guidance for implementation (Updates following the PSA Plus Review and extension of the
More informationOPTIONS. for. Replacing Boiler Plant. Sussex Lodge London W2 & 16 Stanhope Terrace London W2
OPTIONS for Replacing Boiler Plant Report to Tenants Sussex Lodge London W2 & 16 Stanhope Terrace London W2 BPME Consulting Engineers Tel: 01932 873 653 13 JULY 2003. Replacing Boiler Plant... 1 1. Existing
More informationA Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division
A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose
More informationFirst Fix Leak Repair Scheme
Irish Water First Fix Leak Repair Scheme For Domestic Water Customers CER Consultation Public Submissions: Irish Water Response Submission to the CER Reg_PP_IW_FFLRS_003 31/07/15 1 Introduction This document
More informationulletin Canada Mortgage and Housing Corporation
B ulletin Canada Mortgage and Housing Corporation Replacement Reserve Guide WHAT IS THE REPLACEMENT RESERVE? The replacement reserve is a fund kept by each housing sponsor under the terms of its operating
More informationPRIVATE SECTOR HOUSING RENEWAL POLICY
Background and Local Context PRIVATE SECTOR HOUSING RENEWAL POLICY This Policy is published in response to the New Regulatory Reform Order 2002. The overall picture presented by Woking Borough Council
More informationTenant & Leaseholder Compensation Policy
Tenant & Leaseholder Compensation Policy Housing Landlord July 202 Version Control Version 3 Status of Policy Sponsor Author/Reviewer Approved Review Date Draft Mark Gaynor, Corporate Director of Housing
More informationGOOD LANDLORD CODE OF PRACTICE FOR PRIVATE RENTED SECTOR MANAGEMENT
GOOD LANDLORD CODE OF PRACTICE FOR PRIVATE RENTED SECTOR MANAGEMENT GUIDANCE DOCUMENT Each section contains general information on why the standard was set (Yellow text boxes). In many cases, the standards
More informationThe Association offers a factoring service to homeowners whose properties
PARAGON HOUSING ASSOCIATION LIMITED POLICY: POLICY AREA: FACTORING POLICY FINANCE AND INVESTMENT DATE APPROVED: 21 ST AUGUST 2013 DATE NEXT REVIEW: AUGUST 2018 Contents 1. Introduction 2. Aims 3. Objectives
More informationAppendix 1 Atkins Close Garage Site and Play Area Project Appraisal
Appendix 1 Atkins Close Garage Site and Play Area Project Appraisal 1. Summary This garage site was identified for possible re-development via a citywide review of garages in 2010. Out of the 14 garages
More informationCabinet Sub Group - Performance Board
Cabinet Sub Group - Performance Board Part 1 1 November 2012 Item No 4 Subject Purpose Author Ward Summary Fuel Poverty To provide Performance Board with an outline of what constitutes Fuel Poverty and
More informationThe Types of Standard 2 Guidance on the Standards 2 Changes to Legislation 2
CONTENTS INTRODUCTION 2 The Types of Standard 2 Guidance on the Standards 2 Changes to Legislation 2 SCOTTISH CORE STANDARDS FOR ACCREDITED LANDLORDS 3 1 Communication with the Tenant 3 2 Equality Issues,
More informationproperty questionnaire
Property address Seller(s) Completion date of property questionnaire Note for sellers Please complete this form carefully. It is important that your answers are correct. The information in your answers
More informationLondon Borough of Merton Housing Renewal Policy January 2009
London Borough of Merton Housing Renewal Policy January 2009 Introduction This Policy sets out: What Council grants are available for improving private homes Who qualifies for the money How to release
More informationNorth Ayrshire Council Finance & Property Services. Property Factoring Service. Consultation Report
North Ayrshire Council Finance & Property Services Property Factoring Service Consultation Report September 2013 Introduction The North Ayrshire Property Factoring Service was developed in response to
More informationHousing Asset Management Strategy 2013-2043
Housing Asset Management Strategy 2013-2043 1 Introduction 1.1 The asset management strategy sets out the approach Islington takes when deciding what types of long term investment are needed in our homes
More informationHomes for Life Housing Partnership
Homes for Life Housing Partnership POLICY ON COMPENSATION FOR IMPROVEMENTS 1.1 This document sets out the Company's policy on "Compensation for Improvements". 1.2 Section 30 of the Housing (Scotland) Act
More informationRESPONSIBILITY FOR REPAIRS AND MAINTENANCE FAIR FUNDING: April 2002
RESPONSIBILITY FOR REPAIRS AND MAINTENANCE FAIR FUNDING: April 2002 INDEX New Build Flat and Pitched Roofs Rainwater Goods Porches to Existing Buildings / Covered Links etc, Between Buildings Floors /
More informationJOB DESCRIPTION Facilities Manager Soft Services. RESPONSIBLE FOR: Team Leaders and Contract Support staff
JOB DESCRIPTION Facilities Manager Soft Services DIRECTORATE: Merlin Works DEPARTMENT: Facilities Management SALARY: 44,880 RESPONSIBLE TO: Head of Facilities Management RESPONSIBLE FOR: Team Leaders and
More informationA Strategic Approach to Housing Asset Management
Housing A Strategic Approach to Housing Asset Management www.milton-keynes.gov.uk/housing-mkc 0 A Strategic Approach to Housing Asset Management Contents Page 1. Introduction 1 2. Developing a New Set
More informationBridgend County Borough Council
Bridgend County Borough Council Executive Summary December 2009 Page i Executive Summary Background S1 This document summarises the findings of a comprehensive Private Sector House Stock Condition survey
More informationPlanning & Building Control Division. Development. East Ayrshire Planning. Design Guidance
Planning & Building Control Division Design Guidance 1 East Ayrshire Planning Design Guidance Householder Development 1 EAST AYRSHIRE PLANNING: DESIGN GUIDANCE Design of the built environment can affect
More informationAgenda Item No: 2 Page Numbers: 1-6 EAST RIDING OF YORKSHIRE COUNCIL THE CABINET 1 FEBRUARY 2011
Report to: The Ca binet To appr ove as a correct record the Minutes of t he meeting of The Cabinet held on 1 Febr uary 2011 Contact Officer: 01 March 2011 Iain Edmiston Senior Committee Manager Telephone
More informationHAVEBURY HOUSING PARTNERSHIP
HS028 HAVEBURY HOUSING PARTNERSHIP POLICY ASBESTOS MANAGEMENT Controlling Authority Director of Resources Policy No. HS028 Issue No. 3 Status Final Date November 2013 Review Date: November 2016 Equality
More informationPost Inspection Improvement Plan
Post Inspection Improvement Plan Introduction GHA has developed this Improvement Plan in response to the Inspection Report issued by Communities Scotland (the Regulator) in September 2007. The Plan reflects
More informationHart s Older Persons Housing Strategy 2011-14
Hart s Older Persons Housing Strategy 2011-14 Helping local people find housing solutions Final Version Date: May 2011 Contents Introduction 3 Objective 1: Deliver a choice of good quality housing for
More informationCabinet Member for Business, Skills and Housing. Title: Purchase of Communal Electricity and Gas 2014/15
Decision Maker: Cabinet Member for Business, Skills and Housing Date: 13 January 2014 Classification: General Release Title: Purchase of Communal Electricity and Gas 2014/15 Wards Affected: Better City,
More information03 Your tenancy explained
03 Your tenancy explained Written Statement of Services Factored Owners Written Statement of Services under the Property Factors (Scotland) Act 2011 Revised version: April 2015 What is the Written Statement
More informationSCARBOROUGH BOROUGH COUNCIL
SCARBOROUGH BOROUGH COUNCIL CABINET 26 JULY 2005 AGENDA ITEM NO REPORT OF THE HEAD OF ENVIRONMENTAL HEALTH SERVICES HEHS/05/43 on THE NORTH YORKSHIRE 'WISH' PURPOSE OF REPORT This report outlines the progress
More informationFACTORING POLICY March 2007
FACTORING POLICY March 2007 SPIRE VIEW HOUSING ASSOCIATION FACTORING POLICY DATE APPROVED: March 2007 1.0 THE ASSOCIATION S OBJECTIVES To provide good quality affordable housing for those in need and to
More informationPROBIS SUPPORTING PUBLIC PROCUREMENT OF BUILDING INNOVATIVE SOLUTIONS
PROBIS SUPPORTING PUBLIC PROCUREMENT OF BUILDING INNOVATIVE SOLUTIONS Regione Lombardia ALER Bergamo Lecco Sondrio Treviglio via Dei Mulini n. 10/20 via Filzi n. 11/13 Prospectus Template provided by TEH-Ambrosetti.
More informationNick Sanderson, Head of Housing and Property. Reason for Report: To advise members of the new Compensation Policy.
DECENT & AFFORDABLE HOMES PDG 16 JUNE 2015 COMPENSATION POLICY Cabinet Member: Responsible Officer: Cllr Ray Stanley Nick Sanderson, Head of Housing and Property Reason for Report: To advise members of
More informationCABINET RESPONSE TO REPORT OF COMMITTEE TITLED THE IMPACT OF UNDER OCCUPATION OF SOCIAL HOUSING (BEDROOM TAX) WELFARE REFORM IN CARDIFF.
CITY OF CARDIFF COUNCIL CYNGOR DINAS CAERDYDD COMMUNITY & ADULT SERVICES SCRUTINY COMMITTEE AGENDA ITEM 2 nd July 2014 CABINET RESPONSE TO REPORT OF COMMITTEE TITLED THE IMPACT OF UNDER OCCUPATION OF SOCIAL
More informationPage 79. London Borough of Sutton. The Executive - 6 July 2010. Report of the Executive Head of Community Living
Page 79 Agenda Item 9 London Borough of Sutton The Executive - 6 July 2010 Report of the Executive Head of Community Living SUTTON S HOUSING REVENUE ACCOUNT BUSINESS PLAN 2010/11-2039/40 PROPOSED REFORM
More informationPRIVATE SECTOR HOUSING
PRIVATE SECTOR HOUSING FINANCIAL ASSISTANCE POLICY HOUSING SERVICES April 2014 Housing Services Private Sector Housing Renewal Hs168a 1 1.0 Objectives of the Policy HOUSING SERVICES Financial Assistance
More information