1 Directorate of Estates and Campus Services Estates Development Projects A client guide to Estates Services project management

2 Version 1, December 2013

3 Contents Introduction... 2 The Project Lifecycle... 3 Project Stakeholders... 5 Project Team: Roles and Responsibilities... 6 Stakeholder Engagement... 9 Communication, Dissemination and Feedback...11 Change Control Stage A: Works Request Stage B: Preparing the Strategic Brief Stage C: Outline Proposals Stages D-F: Detailed Design Development...19 Stages G-H: Tender Stages J-K: Mobilisations and Delivery Stage L: Practical Completion and Handover Stage M: Defect Period and Feedback Glossary of Terms Page 1

4 Introduction This guide has been developed to provide project Clients and Stakeholders with a detailed insight into how Estates Services development projects are delivered and the roles and responsibilities of the various stakeholder groups who have an interest in project delivery. Explanation is given of the project lifecycle including what can be expected at each stage of project delivery and critical points within the process. A glossary of common project terms is also included. Involvement in a development project can be an incredibly exciting and rewarding experience; at the same time it can also be an extremely daunting and stressful experience especially where it takes the individual outside their usual role and expertise. The main aim of this publication is therefore to help you to become an informed project stakeholder, reduce uncertainties, clarify expectations and improve the project experience for all those involved. We hope that the following pages demonstrate our commitment to delivering a professional, quality driven project service and provide you with reassurance of our overriding intent to ensure full stakeholder inclusivity throughout the entire project lifecycle. If you have any further questions, feedback or suggestions on this publication, please contact the Estates Development Team via estatesdevelopment@york.ac.uk or via our website. 2 Page

5 The Project Lifecycle Based on the RIBA (Royal Institute of British Architects) industry standards, the development project lifecycle is divided into eight sequential stages: Stage A: Works request Submitting an initial request to Estates for works to be carried out. Stage C: outline proposals Initial design concepts capturing high level requirements. Stages G-H: tender Invitation to tender, tender evaluation & contracting. Stage B: preparing strategic brief Scoping works, feasibility study, impact & risk assessments. Data collation to inform briefing pack. Stages D-F: detailed design development Working up of detail of chosen design solution. Stages J-K: mobilisation & delivery Stage L: practical completion & handover Works practically complete, commissioning & testing complete and defects rectification. Site set up and works on site. Stage M: defect period & feedback Close out of defects and postproject review. Whether a Client, User Representative or other project stakeholder you will be expected to be involved in some, if not all, of the above stages to varying degrees. For minor works projects, the early stages of the lifecycle may be condensed into one and/ or the project may go out to tender on outline proposals only. Page 3

6 The level of detail and duration of each of these stages will depend on the scope and scale of the works involved in the project. A table of example project timescales is shown below however, it should be noted that these are for indicative purposes only and projects will be assessed on a case by case basis. Indicative time periods The following gives examples of the likely timescales for typical project types. Please note that these are indicative timescales only and each project will need to be programmed according to its own requirements and complexity. Please also note that if planning permission is required for a projct, this can take 12 weeks following submission of the planning application. Project type Small works Minor works revenue Minor works capital Major capital Example Office redecoration 20m 2, paint, carpet, lights Re-order 50m 2-100m 2 : partitions, lab benching, mechanical vent, paint, flooring, lights Full refurbishment and change of use of a floor of a building including partitioning, new toilets, all internal finishes, 800m 2 Full refurbishment of listed building Typical value From request to RIBA stage D (detailed design) From RIBA stage D to tender complete Construct Total 5-40k 3 weeks 6 weeks 5 weeks 14 weeks k 8 weeks 8 weeks 10 weeks 26 weeks 250k- 2m 15 weeks 20 weeks 20 weeks 55 weeks 9m 30 weeks 30 weeks 60 weeks 120 weeks Progressing between stages At the end of each of the lifecycle stages, is an authorisation gateway or sign-off process which must be completed by the Project Manager before authorisation is given to proceed to the next stage. The purpose of the sign-off is two-fold: i) to ensure that all the necessary elements have been completed in a stage and client, stakeholder and management approvals received; ii) to ensure that all parties are clear on what has been agreed, amended, updated, etc prior to works progressing to the next stage. If a Stakeholder has any concerns on signing-off project documentation, they should alert the Project Manager as soon as possible. Sign-offs are only expected to the level of an individual s expertise and area of specialisation, and can always be accompanied by a written copy of any concerns, conditions or clarifications that individual may have relating to the approval and which will need to be considered at the next stage. Raising concerns at the earliest possible opportunity is key to maintaining project momentum and ensuring that the end product meets everyone s expectations. 4 Page

7 Project Stakeholders A project Stakeholder is defined as anyone who either has an interest in, or is impacted by, the works/outputs of a project. The following diagram gives a non-exhaustive list of typical stakeholders that could be involved in a project to a greater or lesser extent. Not all of a project s stakeholders will have a direct interest in the scoping, design or outputs/deliverables of a project. Their interest may be solely in the impact of the works whilst on site on their day to day operations for example noise, dirt, diversions, service isolations, temporary unavailability of spaces or facilities etc. Other stakeholders however, may have a very keen interest and direct involvement in the scoping, design and delivery of the project such as IT Services, Telephony and Security. Whilst preparing the Strategic Brief, the Project Manager will make an informed assessment of which Stakeholders need to be actively consulted and involved in the project and which only need to be made aware that the project is happening and provided with details of any disruptions during works on site. Involvement of too many stakeholders can result in conflicting requirements, aims and possible delays to the project. Page 5

8 Project Team Roles and Responsibilities The typical composition of a project team and its roles on a large strategic project are shown below. This will vary on a project by project basis and for many of our minor projects the stakeholder group will be very small indeed. Project Sponsor Responsible for the business case for the project and for ensuring the anticipated benefits outlined therein are realised by the project (for example improved student experience, reduced complaints, etc). Has the authority to influence/regulate and adjudicate between conflicting stakeholder requirements at University level. Usually a member of the University s Senior Management Team and reports progress to the Campus Development Steering Group. Makes recommendations for budget increases to University management if required. 6 Page

9 Project Manager Responsible for delivering the project and its outputs: deliverables. Acts on behalf of and represents the University, has the duty of ensuring the Project is to the University s satisfaction, safeguarding its interest at all times, and giving consideration to the needs of the eventual user of the facility. Co-ordinates and manages different disciplines and expertise, to satisfy the objectives and provisions of the project brief from inception to completion. Performs the overall day-to-day management of the project to ensure that project deliverables are achieved within time/cost/quality constraints, whilst managing stakeholder expectations. Reports project progress to the Steering Group (depending on project size/ complexity) to ensure the project s overall direction and integrity is maintained. Alerts the Project Steering Group to emerging risks and potential means of mitigating them. Client(s) Usually the initiator of the project request. May be more than one, with conflicting requirements. Active stakeholders and funders often considered clients. Design Team Specialists in their respective fields responsible for designing a solution that will meet the agreed standards and specifications within the agreed budget and timeframe constraints. Typically includes Architect, Mechanical & Electrical Advisor, CDM Co-ordinator, Quantity Surveyor/Cost Consultant and Contract Administrator/Employer s Agent. Stakeholder(s) Anyone with an interest in, or impacted by, the works or deliverables of a project. Some stakeholders will be actively and directly involved in the project, others merely need to be kept informed of the project ( passive stakeholder ). Active stakeholders will usually include the following: Client Representative(s), Estates Operational Champion (representing Estates Electrical, Mechanical and Building Engineers), Facilities Manager, Maintenance Manager, University Fire Officer, IT Services and Telephony, Security, Asbestos Manager, BMS (Building Management Systems) Manager and User Representatives (if different from Client Representatives). Page 7

10 Steering Group Responsible for supporting the Project Sponsor in the delivery of the business case and anticipated benefits of the project. Monitors the project with regards quality, time and budget. Considers and rules on project issues that cannot be resolved at Working Group level. Typically includes Project Sponsor, Project Manager, Head of Client Department, Head of Estates Development and Head of Estates Operations. Provides direction and guidance on matters of policy. Approves all major plans and authorises any major deviation from the agreed plan. Negotiates a solution to any problems between the project and external bodies. Provides overall guidance and direction to the project, ensuring that it remains within specified constraints. Signs off the completion of each stage and authorises the start of the next stage. Ensures that the required resources are committed to the project. Arbitrates on any conflicts within the project. Can approve financial variations within an approved budget but must escalate budget variations to relevant University management. Working Group Responsible for supporting the Project Manager in the day-to-day delivery of the project to the agreed requirements, in time and on budget. Detailed design/usage issues are discussed at this level and those which cannot be resolved are referred to the Project Steering Group. Typically includes Design Team representation, Contractors, Client/User representatives and active Stakeholder representatives (listed above). 8 Page

11 Stakeholder Engagement Unsuccessful or unsatisfactory projects can often be traced back to poor stakeholder engagement and/or poor planning during the early stages of a project. In short, what comes out of a project is often a direct reflection of what is put in to it! The more information on and input to what the project is aiming to achieve that can be provided during the Preparing the Strategic Brief stage, the more realistic the project scope of works, and more robust the early risk, impact and financial assessments will be. This is not to say that Clients awill be expected to decide on small details such as colour of carpets and curtains at the outset, rather that if there is a critical piece of equipment or facilities that need specialist conditions that this is made known to the Project Manager as soon as possible in the project lifecycle. It is far easier to accommodate a specialist research laboratory need for a major load bearing floor in the outline design stage than after all the floor plans have been issued and construction is underway. Similarly, the likelihood of a project meeting client and stakeholder requirements significantly increases if we can specify those requirements from the outset. This does not preclude variations being proposed and agreed during the design process but it is far easier, and significantly more time and cost effective to tweak an already compliant design than it is to try to make a completely non-compliant design retrofit to requirements later in the process. The early information gathering and assessment stages are also critical to putting the project in context of a very busy and often crowded, publically accessible Campus. Mitigation measures (diversions, relocations, etc) can be dealt with far more easily with advance notice to those who will be affected, if the issue is identified early in the process. Stakeholders have a key role to play in helping Project Managers identify such issues by providing data on existing buildings, facilities and services; on events that are happening in those areas which may be affected by the works and any potential clashes with day-to-day University business. Page 9

12 Whilst Project Managers will endeavour to undertake as thorough data gathering and assessment exercise as possible, they often do not have direct access to locally held records, knowledge and expertise. Therefore, there is a responsibility on Stakeholders to provide information where available, to highlight where information is not available or out of date and if they are aware of any potential issues or clashes to bring these to the Project Manager s attention as soon as possible. There can never be too much information provided! 10 Page

13 Communication, Dissemination and Feedback Communication can make or break a project. Even the smallest of projects can go horribly wrong with poor project communications. The Project Manager is the linchpin for co-ordinating the Client, the Stakeholders, the Design Team, the Contractor(s) and any third party involvement. Client and Stakeholder representatives have a key role to play in relaying project communications to and from their respective teams: to disseminate information on the project so that the wider stakeholder audience is kept informed; to gather information and feedback from their teams on the project plans; and feed it back to the Project Manager accordingly. A good way of gathering input and feedback on project proposals is to consult the users at the coalface - those who use, maintain, run, repair the building, facility, space on a day-to-day basis. Their knowledge and experience of what works and any issues with existing facilities is often invaluable, together with practical suggestions for how improvements could be made. All communication MUST be channelled through the Project Manager. Consultants and Contractors should not contact Stakeholders directly and vice-versa, unless specific permissions has been given by the Project Manager. Failure to communicate through the Project Manager makes the project harder to manage and can lead to contractual and liability issues, escalating costs, increased risks and delays and potential project failure. Page 11

14 Change Control Change is an inevitable part of projects. Even with the most diligent of planning, it is more than likely that something will arise that will require a change during the course of a project. The consequences however, can vary considerably depending on the nature of the change and more importantly the stage at which the change is requested in the lifecycle process. The later in a project lifecycle that a change is requested and introduced the more expensive, time-consuming and difficult the change is to accommodate. Large-scale changes, whilst difficult or inconvenient, can often be accommodated during the early design phases without too much impact on the overall programme or budget. Request the same change later in the design process (Stages D-F) however, and abortive costs may be incurred as well as programme delays as detailed plans, service provisions and specifications all need to be revisited to assess the knock-on effect of the requested change. Once Contractors are on site abortive and redesign costs together with project delays can be considerable, but more likely, the change request will be rejected as impossible to accommodate at that late stage in the project. Seemingly minor changes can also cause considerable problems or be rejected if they are introduced too late in the process. The end result will be a project that does not deliver the required outcome. A request for change needs to be fully assessed for its impact/ knock-on effect on design, programme and budget before a decision can be made on whether the change is to be accepted. Therefore all changes requests must be made through the Project Manager and only the Project Manager (or Contract Administrator where one is appointed) can contractually issue a variation (an approved change request). 12 Page

15 Stage A Works Request The first stage in the project lifecycle is the submission of a Works Request indicating that a User has (or may have) some (future) works that they wish to be carried out. The Works Request is a downloadable online form accessed through the Development Team web pages. All requests for project work (refurbishments, space relocations, construction, etc) must now be made using the Works Request form. Requests for routine maintenance items or reporting day-to-day faults should continue to be made through the Estates Helpdesk on ext 5555 or estates@york.ac.uk. Why is this being introduced? Channelling all requests for estates projects through one portal allows: requests to be given equal and appropriate consideration; for checks to be carried out regarding time, funding and resource available to support the works; and for workload within the Estates Development Team to be managed and programmed to enable the appropriate level of support for projects going forward. When is the deadline for submission of Works Requests? As works on site are often restricted to vacation periods when access can be gained to teaching and residential spaces, these periods often get booked up very quickly in terms of resource available to support the works, both in terms of University project management support but also Contractors and Suppliers. Most of our Contractors and Suppliers also work for other Universities, Schools and Local Authorities whose peak demand period for works is also vacation periods. We have reached the situation where some Contractors can no longer respond to invitations to tender as they are fully booked on projects elsewhere. Similarly, Suppliers lead-times can double during vacation periods as some manufacturers close for a period during the Summer as well as at Easter and Christmas. Page 13

16 To prevent this situation from re-occurring the following deadlines are being introduced for the start of academic year 2013/2014: Works required in: Easter vacation Summer vacation Deadline for submissions of works request form Last day of Autumn Term Last day of Spring Term It is therefore strongly recommended that if a department thinks that they will require works that they submit a Works Request as soon as possible, even if the decision on whether the works are required does not come until later in the year. What happens next? The requests are reviewed by the Head of Development, Head of Operations and Senior Finance Officer and assessed for strategic and financial alignment with the University s strategic, capital and revenue plans. A decision is then reached: proceed to feasibility study (and Project Manager allocated) further information required (before the decision can be made) request put on hold (eg until funding or resource becomes available) reject. When will I get a decision? Works Requests are reviewed at regular Estates Senior Management Team meetings. Once a decision has been made, the original requestor will receive an response informing them of the decision. If the decision is negative, or further information is required before a decision can be made, this will be explained in the response. Please bear in mind that in peak periods, large numbers of requests are received and therefore there may be a slight delay in responding. What you can expect: acknowledgement of receipt of Works Request appropriate and equal consideration of requests confirmation of decision feedback on any rejected or delayed Works Requests. Expectations of you: submission of all requests for Estates project management supported works via the online Works Request form timely submission of Works Requests to allow sufficient time for scoping, planning and carrying out of the requested works if approved provision of basic data requested as part of the Works Request to allow an informed decision. 14 Page

17 Stage B Preparing Strategic Brief The success of a project is directly related to the quality of the information and planning that is put into the project in the early stages. The purpose of Stage B is to: establish the current condition of building/facilities where works have been requested; establish the full scope of the works that would need to be carried out to deliver the requested works for example identifying any asbestos works, enabling works, etc that would need to be completed as part of the works package; carry out a risk assessment and feasibility study to identify any potential risks, missing data and threats to the delivery of the project and to allow realistic programming and costing of the works to be carried out; to gather the latest University standard specifications that the works will need to adhere to and be designed to; identify any clashes or co-dependencies that impact on, or will be impacted by, the requested works. with the aim that 1) a complete package of information can be given to the Design Team allowing the works to be designed to meet the University s standards from the outset rather than trying to retrofit the design later in the process; and 2) an agreed starting status of the building/facility is established to allow configuration management to be implemented, tracking all the changes that are made to the building/facility as part of the project; and 3) agreement is established on the University standard specifications that the project is working to and delivering to (unless a variation is raised, agreed and recorded during the course of the project); and 4) all high level risks are identified, costed where appropriate and agreed; and 5) the full scope, risk and likely costs of the works are agreed and signed off by Estates Senior Management, before any works start on the project design or on site. Page 15

18 Sounds good, but what do I need to do? Technical Stakeholders (Estates Operations, Maintenance, Health & Safety, IT Services, Telephony, Security etc) will be expected to: supply existing data (such as existing building plans, service layouts, condition surveys, periodic test results and fire safety assessments etc) where it is available; inform the Project Manager where information is not available or out of date so that a risk can be flagged and costs included to obtaining the information if required; and confirm that the University standard specifications provided are the latest versions to be delivered to. Non-technical Stakeholders (Client and User representatives, Facilities Managers, Conference Office, Timetabling & Room Booking, etc) will be expected to: provide details of their respective high-level requirements of the project and help identify any clashes with other events or activities that may impact on, or be impacted by, the works being delivered, or affect when the works can be delivered, for example, if there is a conference happening in that building over the vacation period. Then what happens? The findings of the feasibility study, impact and risk assessments and scope of works will be submitted by the Project Manager, together with a covering report, to the Estates Senior Management Team for consideration and approval. If the works are approved, the project will be progressed to Stage C and the Stakeholders informed accordingly. Client and User requirements at this stage need only be outline but should capture all major aspects of the project, such as: type of facilities required how the facilities are to be used any co-location requirements any special access requirements proposed opening arrangements any special equipment needs approximate user numbers any special security needs any ancillary requirements. 16 Page

19 Stage C Outline Proposals Stage C is an iterative process of stakeholder consultation, the purpose of which is to develop the project sufficiently to determine a general approach to layout, design, construction and costs. Draft designs are produced for review by the project Working Group and an indicative programme and cost calculated. Design Team Consultants (Architects, Mechanical & Electrical Consultants, Quantity Surveyors, CDM Co-ordinator) may be appointed to assist in this phase, subject to the size and nature of the works involved. Stakeholder engagement and communication are key Client and Stakeholder representatives have a large role to play in this stage. Stakeholder consultation is a cyclical process and a project may go round this loop several times before it is ready for sign-off. Attendance at project meetings is key, as well as the dissemination of information to, and gathering information from, their respective stakeholder groups to feed back to the Project Manager. Steering Groups and Working Groups Any variations from the University s standard specifications (electrical, mechanical, building, lifts etc) must be agreed and signed off by the relevant Estates Operations representative before it can be incorporated into the plans. Some smaller projects will go out to tender at the end of Stage C so it is essential that the stage C plans accurately reflect the Client s and Stakeholders requirements. Projects requiring Local Authority approval may also be required to submit plans as part of this stage, so again it is essential that all requirements are captured so that the appropriate approval can be applied for. For large strategic projects a Steering Group and a Working Group are usually established, with Head of Department level representation on the Steering Group and User representatives on the Working Group. Smaller projects may have a Working Group or may function on individual consultation meetings with Stakeholder representatives depending on the nature of the works requested. Page 17

20 Whether at Steering Group, Working Group or individual consultation level, it is vitally important that the representatives: have sufficient time to be able to commit to the project are empowered to make decisions on their respective elements of the project on behalf of their respective group are able to accurately represent and communicate the requirements of their respective groups. Sign-off of Stage C plans and design proposals At the end of the stage, each of the Stakeholder representatives will be asked to signoff the plans and proposals. In signing-off the plans and proposals, the representatives are only signing to say that to the best of their knowledge and in their opinion, the plans and proposals presented will meet the requirements of their section. If a Stakeholder s approval is conditional, or they wish to have their views recorded as part of the signoff, there is a section on the reverse of the form for comments to be recorded. Timely sign-off and return of the form is required to avoid any delays to the project. 18 Page

21 Stages D-F Detailed Design Development The detailed design development phase is probably the most intensive phase of Stakeholder input, as the initial plans are further developed and finalised ready for pricing by the Contractor(s). In essence, this is a repeat of the iterative stakeholder consultation carried out in Stage C but at a much more detailed level. Service drawings are finalised, equipment and fit-out schedules produced and furniture layouts agreed. On large construction projects detailed room data sheets may also be produced for each area. The plans and specifications that result from this phase will form the basis of both the invitation to tender and the subsequent contract, It is therefore important that they are as accurate as possible with regards to meeting Client and Stakeholder requirements. Whilst amendments are possible after this stage, they are usually extremely costly or have the potential to significantly impact the programme of delivery. All handover and commissioning requirements should be provided at this stage so that they can also be included in the tender package, and priced and programmed by the Contractor accordingly. Future-proofing All technical variations need to be approved by Estates Operations and the Project Manager prior to being incorporated into the plans. Approved variations will be recorded in the Technical Variations Record, which remains a live document throughout the project lifecycle and which will provide a complete list of agreed variations at handover. Parallel project activities include the updating of the project s cost profile, risk register and impact assessment. From a sustainability perspective, future-proofing of a design is recommended where possible. This is not to say that reams of additional services and facilities are added on the off-chance that numbers may increase substantially in the future. Rather, that facilities are not made unnecessarily bespoke so as to cause significant cost should its function be required to change in the future. Projects are usually constrained by budgets and therefore cannot cater for all future scenarios, but sensible consideration should be given to likely near future variations when providing user numbers. Page 19

22 Jargon-busting Discussions at some project meetings may inevitably become very technically based. Whilst the Project Manager will endeavour to ensure technical issues are explained for the understanding of all those present at the meeting, if a Stakeholder is unsure of what is being discussed or agreed, they should inform the Project Manager. A key purpose of stakeholder consultation is to ensure that all Stakeholders clearly understand what will, and will not, be delivered as part of the project. Sign-off At the end of the stage, all Stakeholder representatives will again be asked to sign-off the proposals. The documents for sign-off may be either in the form of a formal report or a series of plans and room data sheets, depending on the nature and scale of the works to be undertaken. Once approved, the project can progress to tender. 20 Page

23 Stages G-H Tender The procurement strategy and contract type selected for a project will be determined by the Project Manager and the Head of Estates Development based on the scale and nature of the works. Should the value of the works exceed European Union procurement thresholds (shown below), then the works will need to be tendered through the Official Journal of the European Union (OJEU) process. The nature of the procurement process will determine how long the process will take. Public Contracts Regulations 2006 from 1 January 2012 Supplies Services Works Entities listed in Schedule (1) 113,057 ( 130,00) Other public sector contracting authorities 173,934 ( 200,000) 113,057 (2) ( 130,00) 173,934 ( 200,000) 4,348,350 ( 5,000,000) 4,348,350 ( 5,000,000) Indicative Notices To be confirmed To be confirmed 4,348,350 ( 5,000,000) Small lots To be confirmed To be confirmed To be confirmed Figures are net of VAT Stakeholders have very little involvement in the tender process phase. For large strategic projects, the Head of the Client Department may be included on the tender review panel, but otherwise, the tender process is carried out by the Project Manager, Head of Estates Development and either the University s Procurement Manager or the project s appointed Quantity Surveyor/Contract Administrator. Value engineering As part of their tender submission, the successful Contractor may have suggested alternative products or identify areas where savings may potentially be made. The value engineering need to be treated as proposed variations, and be evaluated for their impact on quality, cost, function and programme before any decision is made as to their acceptance. In doing this, these post-tender variations also need to be signedoff by the relevant Stakeholders before they are approved for implementation on site. This ensures that all parties are agreed as to exactly what is being delivered by the project before the Contractor starts on site. Page 21

24 Stages J-K Mobilisation and Delivery Most projects will hold a pre-start meeting prior to any works starting on site. This allows the Project Manager to run through all the house-keeping requirements with the Contractor such as access to site, parking, signing-in, security, permitted working hours, emergency contact details whilst on site, service isolations etc. Technical Stakeholders are usually invited to attend this meeting. Once the Contractor starts on the site, access to the site for any Stakeholders is through the Project Manager in the first instance. Under no circumstances should Stakeholders access the site unaccompanied. Change control and communications Progress on site is reviewed through regular site progress meetings. Depending on the size of the project there may be several monthly meetings, or only a couple of fortnightly meetings if the works are minor and relatively short-term. Where project Steering Groups are in place, the Project Manager provides a written report on progress to each meeting, detailing any issues that have arisen. Once a site, the pace and sequencing of works means the potential for issues to escalate very quickly is significantly increased. It is therefore essential that all communications, particularly any requests for changes, are sent via the Project Manager. If the Project Manager is not kept in the loop, they cannot be expected to know all the issues and any requests made. Should a Stakeholder wish to request a change to a design or specification, they should raise it via a Project Change Request form which is available from the Project Manager. Similarly, if a University standard technical specification changes during the course of a project, the Estates Operations representative should inform the Project Manager accordingly so that a variation can be raised if the changes are to be incorporated into the project. Commissioning and snagging As the works near completion, the Contractor(s) will begin snagging identifying defects and rectifying them, and commissioning any equipment and services installed. Services (fire alarms, electrics etc) and any equipment installed all need to 22 Page

25 be tested and certified as fully working, compliant and safe, so a suitable period of the Contractor s programme for time on site should be dedicated to commissioning. A snagging list is usually produced which identifies defects or items requiring attention and tracks their resolution prior to handover of the building/facility. Stakeholder involvement Technical Stakeholders may be invited to attend site progress meetings if required during this phase, and would be required to review any change requests that are received. Non-technical Stakeholders are not usually involved during this phase other than receiving updates on progress through Steering Group or Working Group meetings. If particular issues arise that require Stakeholder sign-off then the Project Manager will raise the issue with the Stakeholder directly. Page 23

26 Stage L Practical Completion and Handover Once physical works on site and commissioning are complete and all the necessary lifesafety and handover checks have been passed, an assessment is made as to whether the facility is practically complete and safe to handover to the University. The facility does not go straight to the Departmental Client. Instead there is a staged handover process (see below) which is followed before the handover to the Client. There is a period in which Estates Operations colleagues may need to carry out statutory approvals, asset coding, etc all of which needs to be completed before the facility can safely be handed over to the Clients and the Users move in. Beneficial access may sometimes be granted (with agreement from Estates Operations) during this period to allow furniture installation if required. Orientation visits to familiarise the Users with their new facilities can also be arranged during this period through the Estates Operations representative. Sub- Contractor(s) Self- snag for quality assurance Commissioning witnessed by UoY Clerk of Works Provide commissioning cer<fica<on, O&M manual and H&S manual informa<on Principal Contractor Self- snag for quality assurance Responsible for quality assurance of Sub- contractor works Commissioning witnessed by UoY Clerk of Works Provide commissioning cer<fica<on, O&M manual and H&S manual and completed handover checklists Provide user training to UoY maintenance staff on new plant installa<ons Project Manager Receive confirma<on of Prac<cal Comple<on Confirm comple<on and receipt of required handover documenta<on Confirm arrangements for defect handling going forward Estates Opera<ons Carry out any statutory approvals required Complete asset coding where required Confirm any maintenance and opera<onal issues Confirm key and access arrangements with Security Client & Users Report any defects or issues arising via the Estates Services Helpdesk (x5555) 24 Page

27 Stage M Defect Period and Feedback The final phase of the project lifecycle is two-fold: i) closing out any remaining snags or defects that arise post-occupation ii) reviewing the project, its deliverables and benefits to identify good practice and identify any lessons to be learned. Defects and issues arising 5555 facilities helpdesk As part of the handover process, the arrangements for the reporting, handling and rectification of any defects that occur once the users have moved in are agreed with the Contractor(s) and communicated to the Stakeholders. Users are requested to report any defects or issues that arise through the Estates Facilities Helpdesk on ext 5555 or via the website at ac.uk/admin/estates/operations/business/helpdesk/index.html. The duration of the defect period (the time through which the Contractor is contractually liable to return to site and rectify the defects) varies depending on the type of the contract under which the works were delivered. Post-project review Following the completion of the project, we are keen to receive feedback on how the project has gone, on the Client s and Stakeholders experiences and whether the envisaged deliverables and benefits have been achieved. The type of post-project review depends on the scope of works that have been carried out, but we are proactively seeking feedback and identification of good practice and lessons learned. Project close Once the defect period has passed and the final account agreed (and any retention monies released), the project will be closed and the facility becomes maintained as part of the University s normal operations. Page 25

28 Glossary A Abortive Costs B Benefits Costs incurred if a design is changed significantly to warrant the existing design to be redone. The improvements (for example in service delivery, environment, facilities, etc) that are expected to arise from the successful completion of the project. C CDM Construction Design & Management Regulations 2007, issued by the Health & Safety Executive CDM Co-ordinator Professional appointed to be responsible for ensuring that all parties involved in a project adhere to CDM Regulations Change Control Change Request Client Clerk of Works Commissioning Condition Survey Configuration Management The process by which changes to project designs and/or specifications are requested, assessed for their impact, decided upon and recorded A request for an amendment to the existing/proposed design and/or specification The requestor of the works Member of Estates Services who oversees works on site The testing of services and equipment that are either newly installed or have been isolated during the works to ensure that they are fully working and compliant following the works Report detailing the current state of an asset The tracking, control and recording of any changes made to a building, its facilities or services as part of a project D Defect Defect Period Deliverables Design Team A fault requiring rectification The period in which the contractor is responsible for rectifying defects in the project deliverables The physical outputs of a project Specialists in their fields contracted to design a solution that will 26 Page

29 meet the client and stakeholder needs within the defined budget and timescales (eg architect, electrical & mechanical engineers, quantity surveyor, etc) F Feasibility Study Future-proofing I Impact Assessment Instruction M Mobilisation O OJEU Operational Champion Assessment of whether proposed works are possible practically, financially, operationally, strategically and from a health and safety perspective Adding a degree of flexibility into a design or not making a design so bespoke as to be very costly to amend should the future function of a space/facility change Identification of items, areas, people, facilities and services that are likely to be affected by the project works on site; assessment of the likely impact and identification of mitigation measures where appropriate The formal issues of an agreed change request to the Contractor for implentations on site. The setting up of the contractor s site including the area of works and any compound and waste areas required The Official Journal of the European Union the publication through which European tenders above a certain threshold are published and administered Representative from Estates Operations who attends project meetings with the role of feeding back to the various Operational & Maintenance sections within Estates Operations and feeding their requirements into the project P Practical When all the works described in the contract have been carried out Completion Pre-start meeting Meeting held before the appointed contractor starts work on site, to confirm all the necessary arrangements for the works on site Project Manager Project Sponsor Q Member of the Estates Services Development Team appointed to manage the project (and ensure it deliverables) in the interests of the University Responsible for the business case for a project and for ensuring the required benefits are delivered. Usually a member of the University s Senior Management Team Page 27

30 Quantity Surveyor R Retention RIBA Risk Assessment Risk Register Risk Owner Room Data Sheet S Scope of Works Snagging Stakeholder Steering Group V Value Engineering Variations W Works Request Qualified professional appointed to manage all costs relating to building and civil engineering projects, from the initial calculations to the final figures Monies held back from the Contractor for the duration of the defect period to cover any additional defect costs not met in the contract The Royal Institute of British Architects Identification of risks that may impact on a project, and assessment of the likelihood of the risk occurring and the impact that it would have on the project. Typical risk categories include: quality, health & safety, financial, delivery, resources and schedule. A tracking document that records all risks identified, their likelihood of occurrence, likely impact, mitigation measures and risk owner The person responsible for monitoring and managing a risk (through mitigation measures where applicable) A schedule detailing all the requirements of a room: services, function, number of users, layout, size, power, data, security, furnishings etc. The extent and detail of the works to be carried out including any enabling works and surveys Checking of works carried out to identify any defects requiring rectification Anyone with an interest in, or impacted by, a project and its works Head of Department level group which oversees the project with regards quality, time and budget; and provides overall guidance and direction to ensure the project remains within specified constraints Review of the designs and specifications to see where alternatives could be used and identifying where savings could be made Changes to designs, plans or specifications that have been agreed by the Project Manager and formally instructed to the Design Team/Contractor to be implemented Request submitted by a department to Estates Services Development for project work to be carried out. 28 Page

31

32 Development Team Estates Services Providence House University of York Heslington York YO10 5DD

Clients in Construction Best Practice Guidance

Clients in Construction Best Practice Guidance Clients in Construction Best Practice Guidance Published in 2009 by the, Metropolitan Building, James Joyce Street, Dublin 1. Copyright The January 2009 Clients in Construction: Best Practice Guidance

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to: HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned

More information

Contract Management. Brief 22. Public Procurement. September 2011

Contract Management. Brief 22. Public Procurement. September 2011 Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual.

Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company. Ref: Quality Manual. This manual is proprietary and no part thereof shall be copied without written authorisation from the company Ref: Quality Manual.ind Issue: June 2009 INDEX 1 Amendment Status 2 Controlled Distribution

More information

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.

RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012. RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as

More information

Guide to Procuring Construction Projects

Guide to Procuring Construction Projects Guide to Procuring Construction Projects Contents 1. Introduction... 3 2. The Construction Project... 4 Who s who? - The Client s Team... 4 Who s who? - Externals... 5 The Design Team... 6 The Suppliers...

More information

Project Management Handbook 2014. "To Understand the Causes of Things"

Project Management Handbook 2014. To Understand the Causes of Things Management Handbook 2014 "To Understand the Causes of Things" AMENDMENT RECORD This document has been issued and amended as follows: - Isu. Rev. Reason for Issue / revision Date Issued to Team Stakeholders

More information

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone 029 2031 5512

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Projects Portfolio Manager HERA Grade: 8 Responsible to: Director of IT Accountable for: Day to day leadership of team members and assigned workload Key Relationships: Management

More information

A guide to appointing an architect

A guide to appointing an architect A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the

More information

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type

More information

SMS0045 Construction Health and Safety Policy and Procedures

SMS0045 Construction Health and Safety Policy and Procedures SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

SPACE MANAGEMENT POLICY

SPACE MANAGEMENT POLICY SPACE MANAGEMENT POLICY Originated by Assistant Director, Management Services: October 2010 Impact Assessment: 11 November 2010 Recommended by Estates Committee: 1 November 2010 Approved by Council: 22

More information

The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy.

The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy. Senior Project Manager Job Description Reference: 102014/51 Job Title: Senior Project Manager Purpose of Role: The University is committed to providing an environment conducive to high quality teaching

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

Business Continuity Management Framework 2014 2017

Business Continuity Management Framework 2014 2017 Business Continuity Management Framework 2014 2017 Blackpool Council Business Continuity Framework V3.0 Page 1 of 13 CONTENTS 1.0 Forward 03 2.0 Administration 04 3.0 Policy 05 4.0 Business Continuity

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 2014 for Inspecting and Certifying Buildings and Works Building Control Regulations 2014 February, 2014 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1 1.3 Application

More information

RIBA Plan of Work 2013 Overview

RIBA Plan of Work 2013 Overview RIBA Plan of Work 2013 Overview Foreword First developed in 1963, for half a century the RIBA Plan of Work has been the definitive UK model for the building design and construction process, also exercising

More information

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party).

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party). CONTRACT MANAGEMENT PROCEDURE Section Risk Management Contact Risk Manager Last Review February 2013 Next Review February 2016 Approval Not required Procedures Contract Initiation Request Mandatory Guidance

More information

Involve-Project Manager

Involve-Project Manager Involve-Project Manager This article will describe: What is Project Management Why is Project Management so important to community and voluntary organisations The Key Phases of Project Management: o Initiation

More information

European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation. Joint procurement.

European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation. Joint procurement. European Commission Green Public Procurement (GPP) Training Toolkit - Module 1: Managing GPP Implementation Joint procurement Fact sheet Toolkit developed for the European Commission by ICLEI - Local Governments

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Chapter 6 Implementation Planning

Chapter 6 Implementation Planning Chapter 6 Planning Planning- Division into Work Packages The following are the recommended Work Packages Overall Change Programme Work Package 1 E-Cabinet Model Work Package 2 Security Policy Design Work

More information

SUMMER WORKS SCHEME (SWS) 2014

SUMMER WORKS SCHEME (SWS) 2014 Circular 0059/2013 To: The Managerial Authorities of Recognised Primary, Secondary, Community and Comprehensive Schools and The Chief Executive Officers of Education and Training Boards SUMMER WORKS SCHEME

More information

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS NORTH LONDON WASTE AUTHORITY Agenda Item No: REPORT TITLE: PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS REPORT OF: HEAD OF WASTE STRATEGY AND CONTRACTS FOR SUBMISSION TO: DATE: AUTHORITY MEETING 11

More information

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004

Code of Practice EST 01 Decommissioning arrangements prior to site hand over Oct 2004 Estates Division Imperial College London Room 503 Sherfield Building South Kensington Campus London SW7 2AZ, UK Tel: +44 (0)20 7594 9832 Fax: +44 (0)20 7594 9050 r.mayne@imperial.ac.uk www.imperial.ac.uk

More information

Royal Institute of British Architects. Procurement policy. Building teams achieving value

Royal Institute of British Architects. Procurement policy. Building teams achieving value Royal Institute of British Architects Procurement policy Building teams achieving value November 2001 RIBA Procurement Policy The RIBA is committed to construction procurement that: R provides the best

More information

Gateway review guidebook. for project owners and review teams

Gateway review guidebook. for project owners and review teams Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and

More information

Capital Works Management Framework

Capital Works Management Framework POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS

Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS Financial and Commercial Services HIRE OF MANAGEMENT IT/IS CONSULTANTS Table of Contents Contents INTRODUCTION... 2 1. DEFINING MANAGEMENT CONSULTANCY... 2 2. KEY SUCCESS FACTORS... 3 3. THE PROJECT APPROACH

More information

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes

TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS LEC (Company Audit) Guidance Notes Glossary of Terms Transport for London (TfL) London Low Emission

More information

Tendering to Public Sector Organisations

Tendering to Public Sector Organisations Tendering to Public Sector Organisations Introduction Authorities have to meet contract regulations and must ensure they provide equal opportunity and achieve the best value for money. Other factors include

More information

National Institute for Health Research Coordinated System for gaining NHS Permission (NIHR CSP)

National Institute for Health Research Coordinated System for gaining NHS Permission (NIHR CSP) National Institute for Health Research Coordinated System for gaining NHS Permission (NIHR CSP) Operating Manual Please check the CRN Website for the latest version. Version: 6.0 Status: Consultation in

More information

Project Management. Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services

Project Management. Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services January 2010 Contents Project Management Page Local Decontamination Units (LDUs) Construction Project Management...3

More information

White Paper. PPP Governance

White Paper. PPP Governance PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting

More information

Internal Audit Report. Chief Executive s Unit. Review of Contract Management

Internal Audit Report. Chief Executive s Unit. Review of Contract Management Internal Audit Report Chief Executive s Unit Review of Contract Management February 2010 CONTENTS 1. BACKGROUND 1 Page 2. AUDIT SCOPE AND OBJECTIVES 1 3. AUDIT APPROACH 1 4. AMENDED PROCESS 2 5. SUMMARY

More information

HOW TO RESPOND TO THE BASIC NEED CHALLENGE

HOW TO RESPOND TO THE BASIC NEED CHALLENGE HOW TO RESPOND TO THE BASIC NEED CHALLENGE The Situation: unprecedented demand Local Authorities have a statutory duty to provide school places for children of school age, but with recent unprecedented

More information

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 NCSA 01 Competency Based Assessment in Architecture THE

More information

Managing ICT contracts in central government. An update

Managing ICT contracts in central government. An update Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

Outsourcing. Knowledge Summary

Outsourcing. Knowledge Summary Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best

More information

One Government Contract Management Framework. September 2014

One Government Contract Management Framework. September 2014 One Government Contract Framework September 2014 One Government Contract Framework Table of contents 1 Introduction... 4 2 Purpose... 4 3 Scope... 5 3.1 Contract management planning starts before a contract

More information

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9

More information

PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS

PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS PROJECT MANAGEMENT MANUAL PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS FOR ESTATE MANAGEMENT November 2012 PMM REV1.4 CONTENTS INTRODUCTION PROJECT MANAGEMENT PROCESS FLOWCHARTS STAGE ZERO 0.0

More information

BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service

BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

ICT Service Desk Creation

ICT Service Desk Creation ICT Service Desk Creation Project Initiation Document Document: ICT Service desk Creation: PID Issue Date: 26 th November 2010 Version: 0.1 Draft Version Number: 1.0 Change Control Quality Assurance Document:

More information

UNSOLICITED PROPOSALS

UNSOLICITED PROPOSALS UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Reactive Maintenance Service Levels

Reactive Maintenance Service Levels Estates Office Reactive Maintenance Service Levels To report maintenance requests and items for repair go to: bristol.ac.uk/estates In an emergency, always call Ext: 89898 or (0117) 928 9898 Contents Executive

More information

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table

More information

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014

Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014 Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication

More information

NOS. Supply Chain Management Occupational Standards

NOS. Supply Chain Management Occupational Standards NOS National Supply Chain Management Occupational Standards Contents Unit Supply Chain Management National Occupational Standards - Technical T1 Maintain operational relationships within the supply chain

More information

Enterprise Architecture Governance Procedure

Enterprise Architecture Governance Procedure Governance Procedure Adrian Hollister Head of Strategy and Craig Douglas Architect 26 February 2014 Version Control Version Date Detail Contributor 0.1 26/2/2014 Initial Document CJD 0.2 14/3/2014 Amended

More information

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support Final Report Version 1.1 Oct 2009 Contents 1. Executive Summary...3 2. Context and Background...3 3. Deliverables and Value Added...

More information

Disciplinary Policy and Procedure

Disciplinary Policy and Procedure Disciplinary Policy and Procedure Policy The success of the University is dependent on its most important resource, its staff. It is therefore vital that all employees are encouraged to work to the best

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document

More information

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and SCHEDULE 16 Exit Plan 1. Scope 1.1 This schedule: (A) sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and requires the Service Provider

More information

2.6 Select a. procurement route. cabe. Contents

2.6 Select a. procurement route. cabe. Contents 2.6 Select a procurement route 2.6.1 Procurement routes Procurement is the purchasing of products, work and services. It is more important than its unglamorous name suggests and plays a major part in any

More information

TERMS & CONDITIONS FULLY MANAGED SERVICE

TERMS & CONDITIONS FULLY MANAGED SERVICE TERMS & CONDITIONS FULLY MANAGED SERVICE For the purpose of this agreement the following definitions will apply:- Keywest Estate Agents Ltd shall be known as The Agent... shall be known as The Owner..

More information

NFSA Project Management Guidelines

NFSA Project Management Guidelines NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and

More information

Departmental Business Continuity Framework. Part 2 Working Guides

Departmental Business Continuity Framework. Part 2 Working Guides Department for Work and Pensions Departmental Business Continuity Framework Part 2 Working Guides Page 1 of 60 CONTENTS Guide to business impact analysis...3 Guide to business continuity planning...7 Guide

More information

Chartered Architectural Technologists: Client information for domestic projects

Chartered Architectural Technologists: Client information for domestic projects Chartered Architectural Technologists: Client information for domestic projects 1 Contents Section 0. (Pg. 1) Section 1. (Pg. 2) Section 2. (Pg. 3) Section 3. (Pg. 5) Section 4. (Pg. 9) Section 5. (Pg.

More information

Before starting it is worth considering what we mean by the term project - basically it can be defined as:

Before starting it is worth considering what we mean by the term project - basically it can be defined as: Delivering Successful Projects, Tom Moriarty, MDR Consulting This paper outlines the critical requirements of success in managing projects of all types from the definition of a business need to the delivery

More information

Government Communication Professional Competency Framework

Government Communication Professional Competency Framework Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their

More information

PROCUREMENT & LOGISTICS DEPARTMENT

PROCUREMENT & LOGISTICS DEPARTMENT PROCUREMENT & LOGISTICS DEPARTMENT Tender/OJEU Procedure Overview This procedure applies to all purchases over 50,000 not covered by existing contracts and should be followed in conjunction with the Tender/OJEU

More information

Code of Practice for Agents Undertaking Renovation Grants

Code of Practice for Agents Undertaking Renovation Grants Code of Practice for Agents Undertaking Renovation Grants July 1998 Contents Introduction Page 1 Approved List of Agents Page 1 Procurement Page 2 Approval Page 5 Works in Progress Page 6 Completion Page

More information

Imperial College of Science, Technology & Medicine

Imperial College of Science, Technology & Medicine Imperial College of Science, Technology & Medicine SERVICE LEVEL AGREEMENT Maintenance Support to Projects Agreement approved Director of Estates..date Revisions date.date 1.0 Introduction The following

More information

Capital Works Management Framework Guidance Note. Planning and Control of Capital Costs GN 2.2

Capital Works Management Framework Guidance Note. Planning and Control of Capital Costs GN 2.2 Capital Works Management Framework Guidance Note Planning and Control of Capital Costs GN 2.2 Planning and Control of Capital Costs Document Reference GN 2.2. V.1.1 29 September 2011 2011 Department of

More information

Procedure Notes For Management of Construction Projects

Procedure Notes For Management of Construction Projects Isle of Man Government Reiltys Ellan Vannin Procedure Notes For Management of Construction Projects Issued by the Treasury Government Office Douglas, Isle of Man IM1 3PX April 2012 Record of Amendments

More information

Consumer Code. for Home Builders

Consumer Code. for Home Builders Consumer Code for Home Builders This document contains the Consumer Code requirements together with non-mandatory good practice guidance for Home Builders Second Edition January 2010 Contents Meaning of

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

Procurement, Contracting and Contract Management Policy

Procurement, Contracting and Contract Management Policy Procurement, Contracting and Contract Management Policy Corporate policy 8.4 Responsible Officer: Group Manager Accounting and Taxation Policy Custodian: Chief Finance Officer Division: Finance and Resources

More information

Management Board. Business and Financial Planning and Performance Management

Management Board. Business and Financial Planning and Performance Management Management Board Business and Financial Planning and Performance Management A paper by the Office of the Chief Executive and the Department of Resources 1. Purpose 1.1 To establish the approach to be taken

More information

Insurer audit manual

Insurer audit manual Insurer audit manual Disclaimer This publication may contain work health and safety and workers compensation information. It may include some of your obligations under the various legislations that WorkCover

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Queensland Government Human Services Quality Framework. Quality Pathway Kit for Service Providers

Queensland Government Human Services Quality Framework. Quality Pathway Kit for Service Providers Queensland Government Human Services Quality Framework Quality Pathway Kit for Service Providers July 2015 Introduction The Human Services Quality Framework (HSQF) The Human Services Quality Framework

More information

Balancing the Hybrid Development Process. The role of the Business Analyst

Balancing the Hybrid Development Process. The role of the Business Analyst The role of the Business Analyst This document is intended as a guide only. Readers are advised that before acting on any matter arising from this document, they should consult FINNZ. 2013 FINNZ Limited.

More information

ARTWORK COMMISSION AGREEMENT

ARTWORK COMMISSION AGREEMENT ARTWORK COMMISSION AGREEMENT THIS AGREEMENT is made the day of in the year BETWEEN the Minister for Works of Level 6, 16 Parkland Road, Osborne Park, WA 6017 being the body corporate created under Section

More information

Resource Management. Determining and managing the people resources on projects can be complex as:

Resource Management. Determining and managing the people resources on projects can be complex as: Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish

More information

Revision: 3. Author: J McGuire Department: Company. Category: Contract Management. Appr. Signature: CONTENTS 1.0 PURPOSE... 1 2.0 SCOPE...

Revision: 3. Author: J McGuire Department: Company. Category: Contract Management. Appr. Signature: CONTENTS 1.0 PURPOSE... 1 2.0 SCOPE... POLICY Title: QAL Contract Management Policy Policy No: P801.001 Issue: 2 Revision: 3 Operative Date: 10/11/2009 Author: J McGuire Department: Company Sect./Classification: Company Category: Contract Management

More information

HILLCREST HOUSING ASSOCIATION LIMITED MAINTENANCE POLICY

HILLCREST HOUSING ASSOCIATION LIMITED MAINTENANCE POLICY HILLCREST HOUSING ASSOCIATION LIMITED POLICY NO. AM14 MAINTENANCE POLICY 1.0 INTRODUCTION 1.1 This policy describes our arrangements for ensuring that our properties are well maintained and kept in good

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

Wharton Construction Ltd. Quality Manual. Kellaw Road Yarm Road Business Park Darlington DL1 4YA

Wharton Construction Ltd. Quality Manual. Kellaw Road Yarm Road Business Park Darlington DL1 4YA Quality Manual Kellaw Road Yarm Road Business Park Darlington DL1 4YA MANUAL IDENTIFICATION This document is a controlled/uncontrolled copy. Copy Number:...of... Issued to... Title... Holders of controlled

More information

Construction (Design and Management) Regulations 2007

Construction (Design and Management) Regulations 2007 MEETING Finance, Procurement and Property Committee AGENDA ITEM 14 MEETING DATE 9 th July 2007 DOCUMENT NUMBER FEP 1052 SUBJECT REPORT Construction (Design and Management) Regulations 2007 (12/06/07) by

More information

Purpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed

Purpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed Key Learning Points The Swirl Logo is a trade mark of the AXELOS Limited. Is used by the Project Board throughout the project to verify its continued viability:- Is the investment in this project still

More information

MODULE 3: ONGOING MANAGEMENT

MODULE 3: ONGOING MANAGEMENT MODULE 3: ONGOING MANAGEMENT Purpose of module This module has the following objectives: To emphasise the importance of ongoing management of any contract, and of meeting the University s contractual obligations;

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

JOB DESCRIPTION Facilities Manager Soft Services. RESPONSIBLE FOR: Team Leaders and Contract Support staff

JOB DESCRIPTION Facilities Manager Soft Services. RESPONSIBLE FOR: Team Leaders and Contract Support staff JOB DESCRIPTION Facilities Manager Soft Services DIRECTORATE: Merlin Works DEPARTMENT: Facilities Management SALARY: 44,880 RESPONSIBLE TO: Head of Facilities Management RESPONSIBLE FOR: Team Leaders and

More information

Best Practice. Change Management. Guidelines

Best Practice. Change Management. Guidelines Best Practice Change Management Guidelines 1 Created by: Denise Phelan, Demand Management lead, (LPP) Reviewed by: Jonathan Porter, HR Workstream Lead, St George s Healthcare NHS Trust Approved by: Mick

More information