1 Capital Works Management Framework Guidance Note Planning and Control of Capital Costs GN 2.2

2 Planning and Control of Capital Costs Document Reference GN 2.2. V September Department of Public Expenditure and Reform Published by: Department of Public Expenditure and Reform Government Buildings Upper Merrion Street Dublin 2 This document is not to be taken as a legal interpretation of the provisions governing public procurement. All parties must rely exclusively on their own skills and judgement or upon those of their advisors when making use of this document. The Government Construction Contracts Committee (GCCC), the National Public Procurement Policy Unit (NPPPU) and the Department of Public Expenditure and Reform and any other contributor to this guidance note do not assume any liability to anyone for any loss or damage caused by any error or omission, whether such error or omission is the result of negligence or any other cause. Any and all such liability is disclaimed. GN 2.2 v1.1 29/09/2011 2

3 Contents Capital Works Management Framework Guidance Note Planning and Control of Capital Costs...1 GN Contents...3 Foreword...4 1: Introduction to Cost Control Overview Project Reviews and Capital Cost Planning and Control Critical Success Factors Managing Value and Complexity Cost Control in Design Development Roles and Responsibilities : Cost Control in Design Development Overview Cost Control in Design Development Roles and Responsibilities The Outline Cost Plan and Related Activities Developed Cost Plan / Outline Cost Plan (revised) and Related Activities Review of Developed Cost Plan / Outline Cost Plan (revised) Detailed Cost Check and Pre-Tender Cost Check Whole Life Cost Appraisal Integrating Whole Life Cost Management with Cost Plans Managing Corrective Action and Change Control Overview Change Management during the Planning Developed Stage Recording Change in the Budget Change Record Risk Management Tasks Risk Management and Cost Control in Design...60 Appendix: Standard Templates for Cost Planning and Control...64 GN 2.2 v1.1 29/09/2011 3

4 Foreword Purpose of this document This document deals with the planning and control of capital budgets for public works projects, both building and civil engineering, through all stages in the design process. It is one of a number of guidance notes aimed at facilitating the implementation of the measures in the Capital Works Management Framework (CWMF) introduced to achieve greater cost certainty and better value for money on publicly funded projects. See Design Development Process (GN 2.1) for more information on how design is progressed. Traditional and design-and-build projects This guidance note deals with design conducted by Clients in both traditional (Employer-designed) projects and in design-and-build (Contractor-designed) projects. In the case of the latter, however, much or all of the design and the accompanying cost control is carried out by the Contractor; so for that reason, this guidance note is only relevant to cost management and design work carried out by the Client before the design risk is transferred to the Contractor under a design and build contract. Audience This document is intended primarily for the guidance of Sponsoring Agencies embarking on capital works projects. However, the role of the Sanctioning Authorities and any external consultants appointed in relation to the capital works projects is also considered. Terminology in this guidance note The Sponsoring Agency becomes the Contracting Authority for a project once it becomes a party to any contract relating to the project. And from the time the Works Contract is signed, the Sponsoring Agency is referred to as the Employer. The term Client is used throughout this guidance note as a generic term to cover the Sponsoring Agency / Contracting Authority / Employer. References in this document Throughout this document references are made to other documents, including other guidance notes. These references should be understood as referring to the most up to date version in each case. GN 2.2 v1.1 29/09/2011 4

5 Foreword, Continued What is the Capital Works Framework The Capital Works Management Framework (CWMF) is a structure that has been developed to deliver the Government s objectives in relation to public sector construction procurement reform. It consists of a suite of best practice guidance, standard contracts and generic template documents that form four pillars that support the Framework; the pillars are: 1. A suite of standard forms of construction contracts and associated model forms, dispute resolution rules, model invitations to tender, forms of tender and schedules; 2. The standard conditions of engagement for consultants, dispute resolution rules, model invitations to tender, forms of tender and schedules; 3. Standard templates to record cost planning and control information; and for suitability assessment; and 4. Extensive guidance notes covering the various activities in a project delivery process. Capital Works Management Framework Public Works Contracts Contracts, Model Forms, Arbitration Rules, Invitations to Tender (works), Forms of Tender & Schedules (works) Standard Conditions of Engagement Standard Conditions, Arbitration Rules, Invitations to Tender (services), Forms of Tender & Schedules (services) Cost Planning & Control / Suitability Assessment Cost Control & Planning Forms, and Suitability Assessment Questionnaires Guidance Notes GN 2.2 v1.1 29/09/2011 5

6 Foreword, Continued What is the Capital Works Framework (continued) The content of the four pillars is outlined below. The constituent documents are coded according to the following scheme: Code Description Code Description PW- CF Public Works Contract Form COE Standard Conditions of Engagement MF Model Form GN Guidance Note AR Arbitration Rules CO Cost Planning / Control Form ITTS Invitation To Tender, Services ITTW Invitation To Tender, Works QC Questionnaire: Suitability Assessment for Service Provider QW FTS Form of Tender and Schedule GL Glossary WE Data on Weather Events Questionnaire: Suitability Assessment for Works Contractor CWMF Pillar 1 Public Works Contracts Contracts, Model Forms, Arbitration Rules, Invitations to Tender (works), and Forms of Tender & Schedules (works) Contracts PW-CF1 PW-CF2 PW-CF3 PW-CF4 PW-CF5 PW-CF6 PW-CF7 PW-CF8 PW-CF9 WE 1.0 Public Works Contract for Building Works designed by the Employer Public Works Contract for Building Works designed by the Contractor Public Works Contract for Civil Engineering Works designed by the Employer Public Works Contract for Civil Engineering Works designed by the Contractor Public Works Contract for Minor Building and Civil Engineering works designed by the Employer Public Works Short Form of Contract Public Works Investigation Contract Public Works Short Form of Investigation Contract Public Works Framework Agreement Weather Events Met Éireann s calculations of Weather Events GN 2.2 v1.1 29/09/2011 6

7 Foreword, Continued CWMF Pillar 1 (continued) MF 1.0 MF 1.1 MF 1.2 MF 1.3 MF 1.4 MF 1.5 MF 1.6 MF 1.7 MF 1.8 MF 1.9 MF 1.10 MF 1.11 MF 1.12 MF 1.13 MF 1.14 MF 1.15 MF 1.16 MF 1.17 AR 1.0 ITTW 1 ITTW 2 ITTW 3 FTS 1 FTS 2 FTS 3 FTS 4 FTS 5 FTS 6 FTS 7 FTS 8 Model Forms Model Forms (compendium of all model forms) Bid Bond Letter to Apparently Unsuccessful Tenderer Letter of Intent Letter of Acceptance Letter to Tenderers Notifying Award Performance Bond Parent Company Guarantee Novation and Guarantee Agreement Novation Agreement Appointment of Project Supervisor Professional Indemnity Insurance Certificate Collateral Warranty Rates of Pay and Conditions of Employment Certificate Bond Unfixed Works Items Retention Bond Appointment of Conciliator Bond Conciliator s Recommendation Arbitration Rules Arbitration Rules Invitations to Tender (works) Invitation to Tender for Works, Restricted Procedure Invitation to Tender for Works, Open Procedure Invitation to Tender, Investigation Contract under an Open Procedure Forms of Tender and Schedules Form of Tender and Schedule: Public Works Contract for Building Works designed by the Employer Form of Tender and Schedule: Public Works Contract for Building Works designed by the Contractor Form of Tender and Schedule: Public Works Contract for Civil Engineering Works designed by the Employer Form of Tender and Schedule: Public Works Contract for Civil Engineering Works designed by the Contractor Form of Tender and Schedule: Public Works Contract for Minor Building and Civil Engineering Works designed by the Employer Form of Tender and Schedule: Public Works Short Form of Contract Form of Tender and Schedule: Public Works Investigation Contract Form of Tender and Schedule: Public Works Short Form of Investigation Contract GN 2.2 v1.1 29/09/2011 7

8 Foreword, Continued CWMF Pillar 2 Standard Conditions Standard Conditions of Engagement, Arbitration Rules, Invitations to Tender (services), and Forms of Tender & Schedules (services). Standard Conditions COE 1 COE 2 AR 1.0 ITTS 1 ITTS 2 FTS 9 FTS 10 Standard Conditions of Engagement for Consultancy Services (Technical) Standard Conditions of Engagement for Archaeology Services Arbitration Rules Arbitration Rules Invitations to Tender (services) Invitation to Tender for Services, Restricted Procedure Invitation to Tender for Services, Open Procedure Forms of Tender & Schedule (services) Form of Tender and Schedule, Consultancy Services (Technical) Form of Tender and Schedule, Archaeology Services GN 2.2 v1.1 29/09/2011 8

9 Foreword, Continued CWMF Pillar 3 Cost Planning & Control/ Suitability Assessment Cost Control & Planning Forms; and Suitability Assessment Forms for works and services. Cost Planning & Control Forms CO 1 CO 1.1 CO 2 CO 2.1 CO 2.2 CO 2.3 QW 1 QW 2 QW 3 QC 1 QC 2 QC 3 QC 4 How to Use the Costing Document (Building Works) Template Costing Document (Building Works) How to Use the Costing Document (Civil Engineering Works) Template Costing Document (Civil Engineering Works, Roads) Costing Document (Civil Engineering Works, Water Sector) Costing Document (Civil Engineering Works, Marine) Suitability Questionnaires (works) Questionnaire: Suitability Assessment for Works Contractor, Restricted Procedure Questionnaire: Suitability Assessment for Works Contractor, Open Procedure Questionnaire: Suitability Assessment for Works Specialist for specialist area Suitability Questionnaires (services) Questionnaire: Suitability Assessment for Service Provider, Restricted Procedure Questionnaire: Suitability Assessment for Service Provider, Open Procedure Questionnaire: Suitability Assessment for Service Provider, Independent PSDP Questionnaire: Suitability Assessment for Service Provider, Independent PSCS GN 2.2 v1.1 29/09/2011 9

10 Foreword, Continued CWMF Pillar 4 Guidance Notes GN 1.0 GN 1.1 GN 1.2 GN 1.3 GN 1.4 GN 1.5 GN 1.6 GN GN GN 1.7 GN 2.1 GN 2.2 GN 2.3 GN GN GN 2.4 GN 3.1 GN 4.1 GL 1.0 Guidance Notes Introduction to the Capital Works Management Framework Project Management Project Definition and Development of the Definitive Project Brief Budget Development Procurement and Contract Strategy for Public Works Contracts Public Works Contracts Procurement Strategy for Consultancy Services (Technical) Assessment of Construction Service Providers, Restricted Procedure Assessment of Construction Service Providers, Open Procedure Standard Conditions of Engagement, Guidance Note and Sample Schedules Design Development Process Planning and Control of Capital Costs Procurement of Works Contractors Assessment of Works Contractors, Restricted Procedure Assessment of Works Contractors, Open Procedure Tender Process Implementation Process Project Review Glossary Glossary GN 2.2 v1.1 29/09/

11 Foreword, Continued Strategic Objectives of the CWMF The strategic objectives of the Government s Capital Works Management Framework are to ensure: Greater cost certainty at contract award stage; Better value for money at all stages during project delivery, particularly at handover stage; and More efficient end-user delivery. Provided there is a comprehensive definition of the Client s requirements in terms of output specifications, and adequate pre-tender detail design input (in the cast of traditional contracts), the new public works contracts will enable the key objectives outlined above be achieved. The degree to which output specifications and the pre-tender detailed design input is developed is determined by the following guiding principles which underpin the new contracts: To ensure as far as practicable that the accepted tender prices and the final outturn costs are the same; and To allocate risk so that there is optimal transfer of risk to the Contractor. The public sector Client or is called the Employer in the new public works contracts. The achievement of optimal risk transfer is dependent on the Employer providing complete and detailed information in the tender documentation: For design-and-build projects, the Employer must provide detailed output specifications; and For traditional projects, the Employer must provide comprehensive input designs and specifications Then in responding to an invitation to tender, prospective contractors can assess the impact of the risks being transferred and build the costs of such risks into their tender price. Content The topics dealt with in this document are as follows: Chapter 1: Introduction to Cost Control Deals with principles of capital cost planning and controlling costs. 2: Cost Control in Design Development Deals with capital cost planning and control in the design development phase See Page GN 2.2 v1.1 29/09/

12 Foreword, Continued Content (continued) Chapter 3. Whole Life Cost Appraisal Deals with tasks in whole life cost appraisal 4. Managing Corrective Action and Change Control Deals with procedure for budget change 5. Risk Management Tasks Deals with risk management tasks relating to cost control Appendix: Standard Templates for Cost Planning and Control Deals with the use of standard templates for the main cost report activities and their output documents. See Page GN 2.2 v1.1 29/09/

13 Appraisal Project Stages Capital Works Management Framework Main Project Processes Approval in Principle Project Management Design Activities (Building) Design Activities (Civil Eng.) Cost Control Activities Risk and Value Management Documents for Approval Stage 1 Planning Initial Stage I Feasibility Study / Preliminary Report Stage II Design Manage outputs: Project Definition (through 16 N o overall parameters) Manage technical experts appointment (if required) Conduct Feasibility Studies Develop Definitive Project Brief Appoint technical experts (if required) Appoint PSDP (if required) Conduct Preliminary Report Conduct design studies Develop Definitive Project Brief Appoint technical experts (if required) Appoint PSDP (if required) Conduct cost assessment of Feasibility Studies / Preliminary Report (capital and maintenance costs) Project Review 1: Confirm approval for design expenditure (Report to Sanctioning Authority and await approval prior to proceeding) VM: Confirm strategic functional performance Review Feasibility Studies / Preliminary Report options Identify VM strategies Develop functional performance model RM: Identify and assess risk relating to the Project Execution Plan Develop high-level Risk Management Plan Project Management Structure Preliminary Project Brief Preliminary Output Specification Feasibility Study and Cost Plan Design Brief Final Output Specification Definitive Project Brief Project Execution Plan Risk Management Plan Stage 2 Planning Developed Capital Appraisal Standard Conditions of Engagement Manage procurement strategy Manage design consultant appointment Manage assessment of output requirements Appoint Design Team / Design Team Leader Assess output requirements Appoint Design Team / Lead Consultant Develop design standards Assess output requirements Check / assess budget VM: Consider VM in relation to procurement strategy RM: Identify risk in relation to procurement Agree risk allocation Definitive Procurement Strategy Contract Type Proposal Project Team Selection Report Project Review 2: Confirm requirements; review procurement strategy ( C ertify compliance to Sanctioning Authority; and proceed after agreed period provided no queries / hold from Sanctioning Authority) Manage Outline Design process Develop Outline Sketch Scheme Appoint PSDP (if not appointed earlier) Develop Preliminary Planning Appoint PSDP (if not appointed earlier) Develop Outline Cost Plan VM: Consider VM in relation to Outline Sketch Scheme / Preliminary Planning Outline Sketch Scheme (Building) Preliminary Planning drawings RM: Consider RM in (C. Eng.) relation to Outline Sketch Scheme Outline Cost Plan Project Review 3: Assess project design and Outline Cost Plan ( Certify compliance to Sanctioning Authority; and proceed after agreed period provided no queries / hold from Sanctioning Authority) Manage Developed Design process Manage procurement process Develop Developed Sketch Scheme Prepare submission for statutory approval Continue Preliminary Planning Prepare submission for statutory approval Develop Developed Cost Plan Develop Whole Life Cost Appraisal VM: Carry out value engineering Assess buildability of the design Consider VM in relation to Detailed Sketch Scheme RM: Identify residual risks Consider RM in relation to Detailed Sketch Scheme Suitability assessment of contractors Developed Sketch Scheme Developed Cost Plan Statutory Approval Submission Design and Build Project Review 4: Assess project prior to statutory approval (Report to Sanctioning Authority and await approval prior to proceeding) Manage statutory submission process Submit for statutory approval Review statutory approval outcome Submit for statutory approval Review statutory approval outcome Review Developed Cost Plan VM: Review any planning conditions for value management impact. RM: Review any planning conditions for risk impact. Developed Cost Plan (reviewed) Project Review 5: Assess outcome from statutory approval ( Certify compliance to Sanctioning Authority; and proceed after agreed period provided no queries / hold from Sanctioning Authority) Stage 3 Implemention Stage 4 Review Stage III Tender Stages IV and V Construction and Handover Manage the Detailed Design Process Develop Detailed Design (not designand-build) Prepare tender documents Develop Detailed Planning (Design) (not design-and-build) Prepare tender documents Conduct Detailed and Pre-Tender Cost Checks and Whole Life Cost Update in advance of preparing tender documents VM: Review suitability assessment of Tender Documentation contractors for VM potential Detailed Pre-tender Cost Check RM: Review suitability Whole Life Cost Update assessment of contractors for risk Contractor List Selection impact Project Review 6: Approve detailed design solution; review pre-tender cost check; review risk (Report to Sanctioning Authority and await approval prior to proceeding) Manage the Tender Process Issue tender documents Issue tender documents Develop Tender Cost Analysis VM: Assess tender Tender Assessment Criteria Assess tender returns Assess tender returns Develop Tender Report returns for VM potential Tender Analysis And Report Recommend successful tenderer Recommend successful tenderer RM: Assess tender Contractor Recommendation returns for risk impact Project Review 7: Review tender returns in advance of awarding the contract (Report to Sanctioning Authority and await approval prior to proceeding) Manage the implementation / Develop Detailed Design (Design and Develop Detailed Planning (Design Manage change control for costs VM: Carry out value Various contract management construction process Build) and Build) Prepare final account engineering (for design and build reports Manage change control Implement design Implement design projects only) Manage contract RM: Manage residual risk Manage construction risk Manage th Project Review Conduct design review Conduct design review Develop Analysis of Outturn Cost VM: Evaluate value achieved Project Outturn Review RM: Evaluate the risk management and risk mitigation process Consider operational risk reviews

14 1: Introduction to Cost Control 1.1 Overview Stages in capital works management The four major stages in the delivery life cycle of a public works project are set out in the Department of Finance s Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector (February 2005). The four stages are: Capital Works Management Framework Stage What happens 1. Appraisal The needs are identified, the broad parameters of a solution are agreed, and a decision-in-principle is made to proceed. 2. Planning The needs are quantified and assumptions verified, the desired outputs are specified, and the solution is designed. 3. Implementation The solution is constructed. 4. Post-project review An assessment is carried out of how successfully the delivered solution addresses the needs. The planning and control of capital costs activities described in this guidance note take place during the Planning stage. Purpose of capital cost planning and control The planning and control of capital costs is a key requirement of good governance and should be a priority for all capital works projects. The primary aim of implementing cost planning and cost control procedures in the management of capital projects is to ensure that cost certainty and value for money are achieved. By adopting best practice procedures in the management of capital expenditure through the use of cost planning and cost control, the Project Coordinator can minimise the financial risks involved in undertaking capital works projects. GN 2.2 v1.1 29/09/

15 1.1 Overview, Continued Definitions of cost control and cost planning Cost planning For the purposes of this document, the planning of capital costs or cost planning as it is more commonly known can be defined as a system of integrating cost-based intelligence into the design process. To maximise its value, cost planning should be based on a series of cost holding categories appropriate for a particular project design. Each cost holding category should be allocated a value (a target cost) that represents a reasonable proportion of the budget and also represents value for money. The aggregate value of the target costs should not exceed the overall approved budget for the project. Once an Outline Cost Plan is established, the cost holding categories should be continually assessed to ensure that the integrity of the project budget continues to hold true. Cost control For the purposes of this document cost control can be defined as the management of the costs associated with the design process (in each cost holding category) to achieve a predefined approved capital budget. Continuous assessment of the cost holding categories during the Planning Developed stage (including preparation of tender documentation) will test the robustness of the costs in these categories that make up the approved budget. Cost control is dependent on two key factors: information and action. In order to have successful cost control, it is essential to have the necessary information and to take appropriate action based on that information. If the relevant information is not available or if the required action is inefficiently executed, then the risk to cost control on a project is raised considerably. GN 2.2 v1.1 29/09/

16 1.1 Overview, Continued Scope of costs for inclusion The costs covered by this guidance document are those capital costs properly accruing to the Sponsoring Agency and /or the Sanctioning Authority in connection with public works projects. The costs can be divided into two distinct categories: Category Description 1. Capital costs Capital costs are those costs that are necessarily incurred in providing and equipping a construction facility. They do not include any costs properly chargeable to current expenditure for example, expense costs such as rent for temporary accommodation. 2. Whole life costs For a more detailed, although not exhaustive, listing of project costs, see Budget Development (GN 1.3). In addition to all capital costs as outlined above, whole life cost includes all costs incurred with a planned maintenance programme and operational costs over the functional life of a facility. Whole life cost is expressed in terms of net present value. See Chapter 3 below for more information on whole life costs. Contents This chapter covers four topics as follows: Topic 1.2 Project Reviews and Capital Cost Planning and Control Describes how capital cost planning and control integrates with the project review cycle. 1.3 Critical Success Factors Outlines some of the critical success factors relating to cost planning and control on a project. 1.4 Managing Value and Complexity Deals with managing projects with different profiles in relation to risk, value and whole life cost. 1.5 Cost Control in Design Development Roles and Responsibilities Outlines the roles and responsibilities of the Sanctioning Authority, the Sponsoring Agency and the Design Team in relation to cost planning and control. See Page GN 2.2 v1.1 29/09/

17 1.2 Project Reviews and Capital Cost Planning and Control Overview Project Reviews are a means to allow Sponsoring Agencies ensure their projects remain on track to deliver their objectives (see Process Map). There is a direct correlation between Project Reviews 3 to 7 and the cost planning and cost control activities that are carried out in the Planning Initial and Developed stages in the delivery life cycle of a public works project. Cost planning and control is an activity that takes place between project reviews, and its overall output is a key determining factor at review stage in deciding whether or not a project proceeds to the next stage or is sent back for reassessment. The Cost Planning and Control Activity..... is aligned with: Outline Cost Plan Project Review 3 Developed Cost Plan/Outline Cost Plan (revised) Project Review 4 Building: Developed Cost Plan Building: Pre-Tender Cost Check Price Pricing Document and update Developed Cost Plan [revised] Civil Engineering: Outline Cost Plan (revised) amended following statutory approval Civil Engineering: Pre-Tender Cost Check Price Pricing Document and update Outline Cost Plan [revised]) Project Review 5 Project Review 6 Tender Cost Analysis Project Review 7 Project reviews and procurement strategy Project reviews 1 to 7 are all appropriate to traditional, Employer-designed projects. For design-and-build projects, Project reviews 1, 2 and 7 are always appropriate. Project Reviews 3, 4, 5 and 6 are appropriate only while the Client continues to retain the design risk. Traditional / Employer-designed Project Review 1 Project Review 2 Project Review 3 Project Review 4 Project Review 5 Project Review 6 Design and-build / Contractor-designed Appropriate only while the Client retains the design risk. Project Review 7 GN 2.2 v1.1 29/09/

18 1.2 Project Reviews and Capital Cost Planning and Control, Continued Project Review 1 Project Review 1 is a mandatory red light review that takes place after the Definitive Project Brief (and design standards, in the case of civil engineering projects) has been developed when approval for design expenditure is needed. Its function is to confirm that the project is in line with the Approval in Principle, that the preferred design option is capable of being further developed through the design and statutory process, and that delivery of the project is realistic relative to the detailed budget set when the Approval in principal was granted. If Project Review 1 reveals a conflict with the project appraisal or the assumptions underlying the Approval in Principle, or if support for the preferred project solution cannot be obtained, then project work should be suspended and the project should be referred back to the Appraisal stage for reassessment.. Project Review 2 Project review 2 is an amber light review which takes place after the procurement strategy is agreed and the Design Team has been appointed. The purpose of this review is for the Design Team to check that the requirements (as specified in the Definitive Project Brief and after design standards have been established [civil engineering]) and the approved budget are adequate and to review the procurement strategy. Conducting Project Review 2 is one of the first tasks undertaken by the Design Team after their appointment. It takes place before the commencement of any design work and before any formal planning and cost control activities associated with such work are initiated. During the review, the budget might be found to be inadequate or excessive: Inadequate budget Excessive budget If the Design Team finds that the budget is inadequate, they should quantify the deficit and seek an increase in the budget from any contingency monies that the Sponsoring Agency might have. (See Chapter 4 for details of the change control mechanisms that are appropriate in such a situation.) Alternatively, the project should be referred back to the Appraisal stage for reassessment. If the Design Team finds that the capital budget is in excess of what is required, they should quantify and report the excess to the Sponsoring Agency who should remove it from the budget. GN 2.2 v1.1 29/09/

19 1.2 Project Reviews and Capital Cost Planning and Control, Continued Start of Cost Planning and Cost Control Activities Following a positive outcome to Project Review 2, the Sponsoring Agency certifies compliance to the Sanctioning Authority. After a period of time (agreed beforehand with the Sanctioning Authority), the Sponsoring Agency instructs the Design Team Leader / Lead Consultant in writing to proceed with the project in accordance with Stage (ii) Design in Schedule B of the Conditions of Engagement, (including cost planning and control activities) provided the Sanctioning Authority has no queries and does not issue an instruction to put the project on hold. The detailed project budget has already been developed, checked and verified by the Design Team as part of Project Review 2, and a framework for cost planning and control can now be established this is the first formal step in cost planning and control activities as described in this guidance note. The framework is based on best practice, as outlined in the guidance note Budget Development (GN 1.3) and extends to the start of the tendering process. Note: In some projects the detailed budget may have been developed to an advanced stage earlier during the Appraisal stage this is to facilitate the making of the approval in principal decision. Project Reviews 3 6 The Cost Planning and Control elements of Project Reviews 3 6 are described in more detail below: For Project Review 3, see 2.3 The Outline Cost Plan and Related Activities on page 36; For Project Review 4, see 2.4 Developed Cost Plan / Outline Cost Plan (revised) and Related Activities on page 42; For Project Review 5, see 2.5 Review of Developed Cost Plan / Outline Cost Plan (revised)on page 46; and For Project Review 6, see 2.6 Detailed Cost Check and Pre-Tender Cost Check on page 48. Project Review 7 takes place after the tender returns have been reviewed and in advance of the contract award. Discussion of Project Review 7 is not germane to this guidance note. For more information, see Tender Process (GN 2.4). GN 2.2 v1.1 29/09/

20 1.2 Project Reviews and Capital Cost Planning and Control, Continued Design-andbuild: transferring risk to the Contractor For design-and-build projects, the Sponsoring Agency may decide to cease design work after Project Review 2 and to transfer complete design and statutory approval risk to the successful design-and-build Contractor who emerges from the tender process. In this case, the management and establishment of project costs transfer initially to the design-and-build tenderers and ultimately to the successful Contractor that emerges at the end of the tender process. The Design Team will continue to remain in place to: Prepare tender documents (based on the Sponsoring Agency s output requirements, and pricing templates) for design-and-build tenderers; Evaluate tender designs and prices when they come in; and Monitor construction, administer the contract and settle the final account (where they have not been novated to the design and build contractor). The Sponsoring Agency will also be required to appoint a Project Supervisor for the Design Process (PSDP) to address Health and Safety design issues in the tender documents for more information see Design Development Process (GN 2.2). GN 2.2 v1.1 29/09/

21 1.3 Critical Success Factors Introduction Robust cost planning and strong cost control are dependent on a wide range of factors that can change in importance throughout the design life cycle of a project. However, there are a number of critical success factors that have a determining role; these include: The quality of the Definitive Project Brief and the detailed budget; Deciding on a clear procurement strategy; Appointing skilled Cost Advisers; Identifying a detailed and clear list of assumptions and exclusions; Clear procedures for risk management and change management Project Programme (design and tender process stages) Each of these factors is described below. Detailed budget and Definitive Project Brief The detailed budget is formulated at Definitive Project Brief stage within the approved budget limits for which the approval in principle was granted. If the budget has already been broken down to a level of detail at Appraisal stage (in advance of the approval in principle), then it must be reassessed at the Definitive Project Brief stage to confirm that all cost conclusions arrived at earlier continue to hold true. The detailed budget acts as the foundation stone for costs on a capital project. For a number of reasons, it is very important to get the detailed budget right before design work starts. To avoid project delays / abandonment that might arise from lack of funding To preempt the risk of good value for money not being achieved; and To ensure that quality standards do not suffer. The guidance document Budget Development (GN 1.3) sets out procedures for establishing the overall budget. In addition to establishing a detailed budget, the Definitive Project Brief should also be a clear, comprehensive and explicit statement of the user requirements, function, specification and physical output which form the basis of a project design. GN 2.2 v1.1 29/09/

22 1.3 Critical Success Factors, Continued Procurement Strategy The procurement strategy appropriate to a project is decided after Project Review 1, during the Planning Initial stage. The choice of procurement strategy is the key determinant of who is to be responsible for design: Employer An Employer-designed (or traditional ) project is one where the Contractor is responsible for providing the construction services to deliver a facility designed by (or on behalf of) the Client (Employer). Contractor A Contractor-designed (or design-and-build ) project is one where the Contractor is responsible (subject to the terms of contract) for the design, management and delivery of the project, on time and within the contract sum, taking into account whole-life costs and fitness for purpose in accordance with a predefined output specification provided by the Client (Employer) The Definitive Project Brief (and design standards, in the case of civil engineering projects) is the basis for project design irrespective of whether the design is to be performed by the Employer or by the successful Contractor who emerges from the tender process. For more information on the criteria on which the choice of procurement strategy for a particular project might be based, see Procurement Strategy for Public Works Contracts (GN 1.4). Skill base of Cost Advisers To carry out proper cost planning and cost control on a project it is essential that expert Cost Advisers are appointed to carry out this work either from within the Client body or externally. These advisers should be appointed at the earliest possible stage (preferably at the same time as the appointment of the Design Team) and their responsibilities should be clearly assigned. Cost Advisers must be skilled in the areas of cost management; value management; and risk management, including whole life cost analysis. Ideally, they should have experience of projects of a similar size, nature and complexity to that proposed. Assumptions and exclusions At all stages in the design process it is essential that costs are reported comprehensively, with a clear list of assumptions on which the budgetary figures are based, and any items that are excluded. Such assumptions and exclusions should normally be standard for the project type and they should be acceptable in relation to the context of the project. Sanctioning Authorities and Sponsoring Agencies should maintain a central list of acceptable items that may be excluded from cost reports. GN 2.2 v1.1 29/09/

23 1.3 Critical Success Factors, Continued Risk and contingency management The management of risk is critical to the success of any cost planning and control exercise. Risk management requires a high level of skill in the identification, quantification, mitigation and financial assessment of project risks. In the case of traditional contracts, the combination of mitigation measures and financial assessment will play an important management role throughout the life cycle of the project design. Contingency management and risk management on a traditional project are inextricably linked to each other and the refinement and resolution of both these elements is also linked to the Project Programme (design and tender processes). Both contingency and risk must be managed in tandem to ensure the smooth and orderly transition of a project through its various design stages. See chapter 6 of Project Management (GN 1.1) for details of the role of risk management in the life cycle of a project. Change management There should be no major change in scope to a project once the user requirements, function, specification and physical output which forms the basis of a project design are established in the Definitive Project Brief. In a situation where a necessary change in project scope is identified during the design process, it should first be approved by the Sanctioning Authority and then managed in such a way so as to minimise the extent of the design work that has to be redone. If a change in project scope becomes necessary during the construction stage, it is essential that this is managed within a rigorous verification procedure that is fully compliant with the contract conditions. Any major changes to a project must be approved by the Sanctioning Authority before the project may proceed. See Chapter 4 for details relating to change management. GN 2.2 v1.1 29/09/

24 1.3 Critical Success Factors, Continued Project Programme There are two factors that require consideration in relation to cost and time during the design and tender processes. The first is the ongoing refinement of the design and specifications leading to greater cost certainty and less reliance on the contingency allowance as the project moves through the design process. The second is the clear correlation between the cost of a project and the time it takes to complete the design and tender processes. For that reason it is essential that the Project Programme for the design and tender processes is properly managed with appropriate project management tools to ensure that deadlines are strictly adhered to. The total performance period for the project is established at the time the Design Team is appointed, along with the individual performance periods for each service stage of the project (including the design and tender processes). For each project, these are set out in Schedules A and B of the Standard Conditions of Engagement for Consultancy Services (Technical) (COE 1). GN 2.2 v1.1 29/09/

25 1.4 Managing Value and Complexity Appropriate measures It is important to recognise that the time and money invested in cost planning and control exercises should be appropriate to the value and complexity of the project. Projects with a high value and a high complexity require different procedures to those with low value or low complexity. Value threshold For the purposes of this guidance note, the low value threshold is 5 million (ex. VAT) in line with the threshold for the use of the Public Works Contract for Minor Building and Civil Engineering works designed by the Employer (PW-CF 5) and the Public Works Short Form of Contract (PW-CF 6) see Traditional Contracts in Public Works Contracts (GN 1.5). Measuring complexity Project complexity is more difficult to quantify and differs from sector to sector. For this reason the general guidance would be that low complexity would involve a project with a simple low level design requirement and a clear, accessible, independent and vacant site whereas high complexity could involve intricate high level design input and/or a difficult site and/or interfacing with existing live facilities. It is envisaged that, other than in exceptional cases, projects under 1 million will fall into Category 1 Low Value / Low Complexity. Each Sanctioning Authority should set specific guidelines on project complexity within their sector as guidance to Sponsoring Agencies. Note: As with the forms of contract it is open to Sponsoring Agencies to adopt the procedures for high-value projects or low-value projects as they consider appropriate. GN 2.2 v1.1 29/09/

26 1.4 Managing Value and Complexity, Continued Value / complexity threshold The following diagram presents a value/complexity matrix, with indications of the different management levels that apply to each. Value CATEGORY 3 HIGH Value LOW Complexity CATEGORY 4 HIGH Value HIGH Complexity Level 2 Risk Management Level 3 Value Management Level 2 Whole Life Cost Analysis CATEGORY 1 LOW Value LOW Complexity Level 1 Risk Management Level 1 Value Management Level 1 Whole Life Cost Analysis Level 3 Risk Management Level 3 Value Management Level 3 Whole Life Cost Analysis CATEGORY 2 LOW Value HIGH Complexity Level 3 Risk Management Level 1 Value Management Level 1 Whole Life Cost Analysis Complexity Figure 1: Value / complexity matrix Details of levels that apply to risk management, value management and whole life costs analysis are listed below. Risk management levels The following is a summary of the levels appropriate for risk management. Level 1 Level 2 Level 3 Risk Management should be a constant agenda item at Design Team meetings. With the cooperation of the Design Team, the risks should be identified and discussed, and strategies should be developed to minimise, mitigate or manage the risk Level 1 procedures plus Establish a formal Risk Register with the nature of each risk defined, quantified and valued, and a strategy for dealing with each of them should be developed. Level 1 and 2 procedures plus Run Risk Workshops using an experienced risk management expert not directly involved in the project. GN 2.2 v1.1 29/09/

27 1.4 Managing Value and Complexity, Continued Value management levels The following is a summary of the levels appropriate for value management. Level 1 Level 2 Level 3 In addition to the cost/ m 2, cost/km, unit cost etc., benchmarks as a basis for estimation the benchmark should also be used as a tool for reviewing value for money compared to other updated similar projects. Level 1 procedures plus Other benchmarking tools should be used including Functional Analysis to understand the Sponsoring Agency s interpretation of Value. Value engineering option appraisal should also be carried out. Level 1 and 2 procedures plus Run Value Management Workshops that focus on value for money as part of an ongoing process. This involves a review of the design to identify areas of improvements. Whole life costs analysis levels The following is a summary of the levels appropriate for whole life costs analysis. Level 1 Level 2 Level 3 As a matter of best practice, ensure that affordable, sustainable design solutions are included. Level 1 procedures plus Develop a Schedule of Whole Life Cost options with indicative orders of costs and payback terms for review with the Sponsoring Agency. As Level 2 procedures with increased analysis proportionate to the project size.. GN 2.2 v1.1 29/09/

28 1.5 Cost Control in Design Development Roles and Responsibilities Overview The roles and responsibilities of the Sanctioning Authority, the Sponsoring Agency (including the Project Coordinator) and the Design Team in relation to cost control during the design development process are detailed below. See Design Process (GN 2.1) for details of roles and responsibilities in relation to design development. Sanctioning Authority: roles and responsibiliti es It is the Sanctioning Authority s role to determine the outcome of any issue which impacts on a project arising out of a change in any of the components or circumstances on which the Approval in Principle was based. The Sanctioning Authority s particular responsibilities in relation to Project Reviews are outlined below. Project Reviews and the Sanctioning Authority Project Reviews 1, 4, 6 and 7 are red reviews red light reviews. These require the Sponsoring Agency to prepare a report for the Sanctioning Authority to approve in order for the project to proceed further. The report enables the Sanctioning Authority to evaluate the business case and the project parameters, to confirm the budget, and to determine whether or not the project should proceed. Project Reviews 2, 3 and 5 are amber light reviews. These require formal collection and reporting of evidence within the Sponsoring Agency and the Design Team to confirm that the project is on track. At each amber light review, the Sponsoring Agency should provide the Sanctioning Authority with verification that the project continues to be achievable within the budget, programme and scope constraints previously approved. The Sanctioning Authority retains the right to request additional information from the Sponsoring Agency at any project review. In this regard, Sanctioning Authorities should give particular consideration to the submission prior to the application for statutory planning approvals. This is an important stage because once a project passes into the statutory planning process it becomes more difficult to make changes to the scheme and details of the project are made public. The Sanctioning Authority s assessment can include an examination of the Design Team s report and the Sponsoring Agency s review of that report. The assessment should focus on the key requirements in terms of quality (including function), programme and cost. GN 2.2 v1.1 29/09/

29 1.5 Cost Control in Design Development Roles and Responsibilities, Continued Sanctioning Authority: roles and responsibiliti es (continued) Due diligence on large projects For large projects (greater than 30m) a more formal due diligence assessment should be carried out, which should include the following: Cost Benefit analysis; Assessment of the achievement of the Definitive Project Brief objectives (and design standards in the case of civil engineering projects); Assessment of the completeness of the tender documentation; and Assessment of the project s risk profile. Risk Assessment: the role of the Sanctioning Authority The Sanctioning Authority should periodically assess the Sponsoring Agency s risk management approach and the sufficiency of any mitigation measures it has adopted. The Sanctioning Authority should also periodically assess the adequacy of the ongoing contingency. Arising from such assessment by the Sanctioning Authority, there may be a requirement to put in place change control systems and other procedures. When this occurs, it must be recorded using an agreed documentation and recording procedure. Sponsoring Agency: roles and responsibiliti es The Sponsoring Agency is the key Client body with responsibility for initiating and monitoring the delivery of a capital project. In fulfilling this function the Sponsoring Agency, and in particular the Project Coordinator (the person charged with the day-to-day monitoring and approvals) must have appropriate systems and procedures in place to monitor and approve designs and costs. See the Budget Template in Appendices A and B of the guidance note Budget Development (GN1.3) for a non-exhaustive list of the costs to be monitored. It is also the Sponsoring Agency s responsibility to seek the approval of the Sanctioning Authority for any material change or change in circumstance which impact on the project for which Approval in Principle was granted. Communications In relation to communications it is important to note the provisions in clause 7, [7] to [10] of the Standard Conditions of Engagement for Consultancy Services (Technical) (COE 1) which states: The Client may respond to Consultant s communications with comments, questions, objections, to which the Consultant shall reply. A Client s response or failure to respond to any communication from the Consultant does not constitute or imply any review or verification by the Client, or relieve the Consultant from any responsibility or liability. GN 2.2 v1.1 29/09/

30 1.5 Cost Control in Design Development Roles and Responsibilities, Continued Sponsoring Agency: roles and responsibiliti es (continued) Progressing a project The way the project progresses will depend on when the Client gives permission for a stage to start. Clause 4 [1] of the Standard Conditions of Engagement for Consultancy Services (Technical) (COE 1) states: The Consultant shall start its Services for each Stage when the Client gives permission, perform them regularly, meet each milestone within the Stage, and complete the Services for the Stage with the Performance Period scheduled for it. The timing of each permission to start is the Client s choice [but clause 5 gives the Consultant rights in respect of the Scheduled Total Performance Period]. Systems and procedures The Sponsoring Agency in fulfilling its responsibility during the design process should have systems and procedures that include the following steps: Steps 1 Cost Planning and Cost Control 2 Programme confirmation Systems and procedures This step follows confirmation by the Design Team that the key deliverables of Quality (including function), Programme and Cost are realistic and capable of delivery. The Sponsoring Agency should have decided the extent of cost planning and cost control it requires on a project before it appoints the Design Team. It is critical that the Cost Plans and Cost Check reports are reviewed at the appropriate time to confirm that the project is within budget. The Cost Plans and Cost Checks should state that they are based on the drawings and information issued by the Design Team and that the notes and exclusions are not lengthy, exclude too much or are unacceptably onerous for a Sponsoring Agency to accept. The Sponsoring Agency should regularly review project progress against the project master programme and identify any time lost or gained since the previous stage. In reviewing the programme the Design Team should offer practical suggestions as to how lost time might be made up in order to bring the project back on track. The Sponsoring Agency should include in their formal approval any programme adjustments necessary (accelerations / overlapping of tasks and so on) to maintain the master programme end date. GN 2.2 v1.1 29/09/

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities

GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities GUIDANCE NOTE 1.1.1 Building Control (Amendment) Regulations 2014 Procurement Implications for Contracting Authorities Office of Government Procurement Building Control (Amendment) Regulations 2014 Procurement

More information

Capital Works Management Framework Guidance Note for Public Works Contracts

Capital Works Management Framework Guidance Note for Public Works Contracts Capital Works Management Framework Guidance Note for Public Works Contracts Copyright 2006 Department of Finance 30 April 2007 Published in April 2007 by: The National Public Procurement Policy Unit of

More information

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY

PROJECT MANAGEMENT GUIDELINES NATIONAL TRANSPORT AUTHORITY PROJECT MANAGEMENT GUIDELINES FOR PROJECTS FUNDED BY THE NATIONAL TRANSPORT AUTHORITY (UP TO 20 MILLION IN VALUE) december 2011 Table of Contents Section A 1. Introduction 4 1.1 Purpose 4 1.2 Applicability

More information

Cost Management Guidelines for. 1 September 2010

Cost Management Guidelines for. 1 September 2010 Cost Management Guidelines for Public Transport Investment Projects 1 September 2010 Table of Contents Foreword iv 1. Introduction 1 1.1 Purpose Of The Guidelines 1 1.2 Applicability 1 1.2.1 Conventionally

More information

GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses

GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses Office of Government Procurement Cost Control: Price Variation Clauses Document Reference GN 1.5.2 v1.0 22 January 2016 2016 Department of Public

More information

GUIDELINES FOR THE MANAGEMENT OF PUBLIC TRANSPORT INVESTMENT PROJECTS DELIVERED BY CONVENTIONAL PROCUREMENT

GUIDELINES FOR THE MANAGEMENT OF PUBLIC TRANSPORT INVESTMENT PROJECTS DELIVERED BY CONVENTIONAL PROCUREMENT GUIDELINES FOR THE MANAGEMENT OF PUBLIC TRANSPORT INVESTMENT PROJECTS DELIVERED BY CONVENTIONAL PROCUREMENT Guidelines for the Management of Public Transport Investment Projects delivered by Conventional

More information

Clients in Construction Best Practice Guidance

Clients in Construction Best Practice Guidance Clients in Construction Best Practice Guidance Published in 2009 by the, Metropolitan Building, James Joyce Street, Dublin 1. Copyright The January 2009 Clients in Construction: Best Practice Guidance

More information

GUIDANCE NOTE 1.6.3 PREQUALIFICATION OF CONSULTANTS. Minimum Standards for Suitability Criteria

GUIDANCE NOTE 1.6.3 PREQUALIFICATION OF CONSULTANTS. Minimum Standards for Suitability Criteria GUIDANCE NOTE 1.6.3 PREQUALIFICATION OF CONSULTANTS using Minimum Standards for Suitability Criteria Department of Public Expenditure and Reform Minimum Standards for Selected Suitability Criteria for

More information

Procedure Notes For Management of Construction Projects

Procedure Notes For Management of Construction Projects Isle of Man Government Reiltys Ellan Vannin Procedure Notes For Management of Construction Projects Issued by the Treasury Government Office Douglas, Isle of Man IM1 3PX April 2012 Record of Amendments

More information

CONTRACT MANAGEMENT FRAMEWORK

CONTRACT MANAGEMENT FRAMEWORK CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED

CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact info@whe.wales.nhs.uk or telephone 029 2031 5512

More information

Chartered Architectural Technologists: Client information for domestic projects

Chartered Architectural Technologists: Client information for domestic projects Chartered Architectural Technologists: Client information for domestic projects 1 Contents Section 0. (Pg. 1) Section 1. (Pg. 2) Section 2. (Pg. 3) Section 3. (Pg. 5) Section 4. (Pg. 9) Section 5. (Pg.

More information

SUMMER WORKS SCHEME (SWS) 2014

SUMMER WORKS SCHEME (SWS) 2014 Circular 0059/2013 To: The Managerial Authorities of Recognised Primary, Secondary, Community and Comprehensive Schools and The Chief Executive Officers of Education and Training Boards SUMMER WORKS SCHEME

More information

Appendix 18 NEC3 Options

Appendix 18 NEC3 Options Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

Procurement Strategy and Contract Selection

Procurement Strategy and Contract Selection GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works

More information

DIRECTORATE OF ESTATES & FACILITIES

DIRECTORATE OF ESTATES & FACILITIES DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:

More information

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26

Part 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26 Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain

More information

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS

PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS PROJECT MANAGEMENT MANUAL PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS FOR ESTATE MANAGEMENT November 2012 PMM REV1.4 CONTENTS INTRODUCTION PROJECT MANAGEMENT PROCESS FLOWCHARTS STAGE ZERO 0.0

More information

1.20 Appendix A Generic Risk Management Process and Tasks

1.20 Appendix A Generic Risk Management Process and Tasks 1.20 Appendix A Generic Risk Management Process and Tasks The Project Manager shall undertake the following generic tasks during each stage of Project Development: A. Define the project context B. Identify

More information

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to: HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned

More information

Internal Audit Report. Chief Executive s Unit. Review of Contract Management

Internal Audit Report. Chief Executive s Unit. Review of Contract Management Internal Audit Report Chief Executive s Unit Review of Contract Management February 2010 CONTENTS 1. BACKGROUND 1 Page 2. AUDIT SCOPE AND OBJECTIVES 1 3. AUDIT APPROACH 1 4. AMENDED PROCESS 2 5. SUMMARY

More information

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution Reducing Bid Costs for Outcome-Based Procurements in NSW Infrastructure and Structured Finance Unit: Partnering to Create Partnerships December 2015 1. Evolution of infrastructure procurement in NSW 2.

More information

Department of Finance. Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector

Department of Finance. Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector Department of Finance Guidelines for the Appraisal and Management of Capital Expenditure Proposals in the Public Sector January 2005 Table of Contents Page Preface Role of Government and Ministers 4 Introduction

More information

How To Write New Government Construction Contracts

How To Write New Government Construction Contracts HUSSEY FRASER SOLICITORS 1. Objectives of new contracts 2. How objectives are to be achieved Risk Transfer Procedural / Information Burden 3. Termination Provisions 4. Collateral Warranties 5. Conclusion

More information

Standard Conditions of Appointment. Architect s Copy ONLINE VERSION ONLINE VERSION ONLINE VERSION. for an Architect (CA-S-07-A)

Standard Conditions of Appointment. Architect s Copy ONLINE VERSION ONLINE VERSION ONLINE VERSION. for an Architect (CA-S-07-A) Standard Conditions of Appointment for an Architect (CA-S-07-A) Architect s Copy Royal Institute of British Architects RIBA Agreements are produced in association with: the Royal Incorporation of Architects

More information

Contract Management Guideline

Contract Management Guideline www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract

More information

OPW HANDBOOK FOR THE CONSULTANTS DIRECT INVITATION LISTS (CDIL)

OPW HANDBOOK FOR THE CONSULTANTS DIRECT INVITATION LISTS (CDIL) OPW HANDBOOK FOR THE CONSULTANTS DIRECT INVITATION LISTS (CDIL) FOR CONSULTANCY CONTRACTS WITH AN ESTIMATED VALUE OF LESS THAN 50,000 (EXCLUSIVE OF VAT) Table of Contents 1.0 Introduction...3 1.1 CDIL

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Procurement of Goods, Services and Works Policy

Procurement of Goods, Services and Works Policy Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March

More information

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health

Page 5. The Adult Social Services and Health Committee. The Strategic Director of Adult Social Services, Housing and Health Page 5 Agenda Item 5 Report to: The Adult Social Services and Health Committee Date: 20 th November 2012 Report of: The Strategic Director of Adult Social Services, Housing and Health Ward Location: All

More information

Capital Works Management Framework Document No. GN 1.7. Standard Conditions of Engagement for Consultancy Services (Technical)

Capital Works Management Framework Document No. GN 1.7. Standard Conditions of Engagement for Consultancy Services (Technical) Capital Works Management Framework Document No. GN 1.7 Standard Conditions of Engagement for Consultancy Services (Technical) Guidance Note and Sample Schedules GN 1.7 090708 1 About This Document Background

More information

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS

CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS CONSTRUCTION PROJECT MANAGER TERMS OF REFERENCE CENTRAL BANK OF LESOTHO PROPOSED EXTENSION BUILDING AND DISASTER RECOVERY SITE CONSTRUCTION PROJECTS 1. GENERAL PROVISIONS. 1.2 DEFINITIONS Where the words

More information

Project Management Handbook 2014. "To Understand the Causes of Things"

Project Management Handbook 2014. To Understand the Causes of Things Management Handbook 2014 "To Understand the Causes of Things" AMENDMENT RECORD This document has been issued and amended as follows: - Isu. Rev. Reason for Issue / revision Date Issued to Team Stakeholders

More information

Code of Practice for Agents Undertaking Renovation Grants

Code of Practice for Agents Undertaking Renovation Grants Code of Practice for Agents Undertaking Renovation Grants July 1998 Contents Introduction Page 1 Approved List of Agents Page 1 Procurement Page 2 Approval Page 5 Works in Progress Page 6 Completion Page

More information

Royal Holloway University of London

Royal Holloway University of London Royal Holloway University of London Consultancy Policy December 2008 1.0 Introduction 1.1 Consultancy is defined as: The deployment of existing knowledge to meet the specific requirements of a client either

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

Capital Works Management Framework

Capital Works Management Framework POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset

More information

The Gateway Review Process

The Gateway Review Process The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

Appendix A. Call-off Terms and Conditions for the Provision of Services

Appendix A. Call-off Terms and Conditions for the Provision of Services Appendix A Call-off Terms and Conditions for the Provision of Services Where an Order Form is issued by the Authority that refers to the Framework Agreement, the Contract is made between the Authority

More information

Circular 10/14: Initiatives to assist SMEs in Public Procurement

Circular 10/14: Initiatives to assist SMEs in Public Procurement Ref: DPE108/001/2014 16 April 2014 To Heads of Departments 1 Circular 10/14: Initiatives to assist SMEs in Public Procurement A Dhuine Uasail, 1. In the context of the reform of the Public Service and

More information

The Transport Business Cases

The Transport Business Cases Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business

More information

North Middlesex University Hospital NHS Trust. Annual Audit Letter 2005/06. Report to the Directors of the Board

North Middlesex University Hospital NHS Trust. Annual Audit Letter 2005/06. Report to the Directors of the Board North Middlesex University Hospital NHS Trust Annual Audit Letter 2005/06 Report to the Directors of the Board 1 Introduction The Purpose of this Letter 1.1 The purpose of this Annual Audit Letter (letter)

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011

BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011 BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

Accounting for Infrastructure Projects within Enterprise Zones (EZ) and Tax Increment Financing (TIF) Funded Programmes.

Accounting for Infrastructure Projects within Enterprise Zones (EZ) and Tax Increment Financing (TIF) Funded Programmes. Accounting for Infrastructure Projects within Enterprise Zones (EZ) and Tax Increment Financing (TIF) Funded Programmes. Background 1 A number of initiatives are under way that involve local authorities

More information

A guide to appointing an architect

A guide to appointing an architect A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the

More information

Interim Guidelines for the Provision of Infrastructure and Capital Investments through Public Private Partnerships:

Interim Guidelines for the Provision of Infrastructure and Capital Investments through Public Private Partnerships: Interim Guidelines for the Provision of Infrastructure and Capital Investments through Public Private Partnerships: Procedures for the Assessment, Approval, Audit and Procurement of Projects Table of Contents

More information

Chapter 6A SPONSORS AND COMPLIANCE ADVISERS

Chapter 6A SPONSORS AND COMPLIANCE ADVISERS Chapter 6A SPONSORS AND COMPLIANCE ADVISERS Definitions and interpretation 6A.01 In this Chapter: (1) Compliance Adviser means any corporation or authorised financial institution licensed or registered

More information

Lexcel England and Wales v6 Guidance notes for in-house legal departments Excellence in practice management and client care. 2015 The Law Society.

Lexcel England and Wales v6 Guidance notes for in-house legal departments Excellence in practice management and client care. 2015 The Law Society. Excellence in practice management and client care 2015 The Law Society. Contents Introduction... 3 PART ONE - GUIDANCE AGAINST LEXCEL STANDARD REQUIREMENTS... 4 1 - Structure and strategy... 4 2 - Financial

More information

Risks in International Consultancy Appointments: The FIDIC White Book

Risks in International Consultancy Appointments: The FIDIC White Book Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction

More information

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and SCHEDULE 16 Exit Plan 1. Scope 1.1 This schedule: (A) sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and requires the Service Provider

More information

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 PAGE: 1 REPORT TO: SUBJECT: BY: AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 ASSET MANAGEMENT CHIEF FINANCIAL OFFICER 1. REASON FOR REPORT 1.1 To provide the Audit and Performance Review

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

LSB Procurement Framework

LSB Procurement Framework LSB Procurement Framework Introduction Procurement covers the typical purchase of services, supplies and works required to enable project delivery and to manage the infrastructure. The Services Board (LSB)

More information

PM Governance. Executive Team ADCA ADCA

PM Governance. Executive Team ADCA ADCA Item 6.5a Action Plan against the Recommendations Made in the Review of Risk Management Arrangements by PM Governance, November 2014 Key: PM Governance Paul Moore, Risk Consultant ADCA Associate Director

More information

Guide to Procedure for Competitive Tendering March 2003

Guide to Procedure for Competitive Tendering March 2003 Guide to Procedure for Competitive Tendering March 2003 The Landscape Institute 33 Great Portland Street London W1W 8QG Tel: +44 (0)20 7299 4500 Fax: +44 (0)20 72994501 Email: mail@landscapeinstitute.org

More information

REGULATORY AUDITS OF DISTRIBUTION BUSINESSES ELECTRICITY AND GAS INDUSTRIES

REGULATORY AUDITS OF DISTRIBUTION BUSINESSES ELECTRICITY AND GAS INDUSTRIES ESSENTIAL SERVICES COMMISSION '""- GUIDELINE No. 16 REGULATORY AUDITS OF DISTRIBUTION BUSINESSES ELECTRICITY AND GAS INDUSTRIES March 2004 ELECTRICITY AND GAS INDUSTRIES GUIDELINE No. 16 This guideline

More information

Project Consultant & Business Development Consultant (BDC) Guidelines

Project Consultant & Business Development Consultant (BDC) Guidelines Isle of Man Department of Economic Development s Business Support Scheme (BSS) Project Consultant & Business Development Consultant (BDC) Guidelines February 2012 Contact Details For further Information,

More information

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper

december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper december 08 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The NSW Government is committed to the ongoing improvement of public services by ensuring

More information

Ministry Of Health Registration of Interest

Ministry Of Health Registration of Interest Ministry Of Health Registration of Interest Intermediaries Social Bond Pilot(s) Part 1 Instructions and Supporting Information What s inside? Introduction to Social Bonds Purpose of the ROI Instructions

More information

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

Nominated Subcontractors on International Projects: Approaches to Risk Allocation Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.

More information

The Context for Practice

The Context for Practice The Context for Practice 1a. Describe briefly the role of English Heritage. English Heritage works in partnership with the central government departments, local authorities, voluntary bodies and the private

More information

Explanatory Paper TPB(EP) 03/2010

Explanatory Paper TPB(EP) 03/2010 Explanatory Paper TPB(EP) 03/2010 Professional Indemnity Insurance This TPB explanatory paper (TPB(EP)) is intended as information only. It provides a detailed explanation of the Board s professional indemnity

More information

Project Management. Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services

Project Management. Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services Advice on the provision of Local Decontamination Units (LDUs) Decontamination Services January 2010 Contents Project Management Page Local Decontamination Units (LDUs) Construction Project Management...3

More information

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 PART 3G Contracts Standing Orders 2015/16 Definitions Aggregation is the combining together of the total contract value from separate contracts

More information

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES

APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES 1 PERFORMANCE PLANS 1.1 The key controls for performance plans are: (a) to ensure that all relevant plans are produced and that they are consistent

More information

Gateway review guidebook. for project owners and review teams

Gateway review guidebook. for project owners and review teams Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and

More information

Capital Adequacy: Advanced Measurement Approaches to Operational Risk

Capital Adequacy: Advanced Measurement Approaches to Operational Risk Prudential Standard APS 115 Capital Adequacy: Advanced Measurement Approaches to Operational Risk Objective and key requirements of this Prudential Standard This Prudential Standard sets out the requirements

More information

Project Assessment Framework Establish service capability

Project Assessment Framework Establish service capability Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.

More information

LEAD PROVIDER FRAMEWORK CALL OFF TERMS AND CONDITIONS

LEAD PROVIDER FRAMEWORK CALL OFF TERMS AND CONDITIONS LEAD PROVIDER FRAMEWORK CALL OFF TERMS AND CONDITIONS 1 LEAD PROVIDER FRAMEWORK - CALL OFF TERMS AND CONDITIONS - SUMMARY Where an Order Form is issued by the Authority that refers to the Framework Agreement,

More information

Managing Outsourcing Arrangements

Managing Outsourcing Arrangements Guidance Note GGN 221.1 Managing Outsourcing Arrangements 1. This Guidance Note provides further detail on the requirements for managing material outsourcing arrangements (refer Prudential Standard GPS

More information

Procurement requirements for reducing waste and using resources efficiently

Procurement requirements for reducing waste and using resources efficiently Guidance for building and civil engineering projects Procurement requirements for reducing waste and using resources efficiently Model procurement wording for clients and contractors to cut waste on construction

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

A GOOD PRACTICE GUIDE FOR EMPLOYERS

A GOOD PRACTICE GUIDE FOR EMPLOYERS MITIGATING SECURITY RISK IN THE NATIONAL INFRASTRUCTURE SUPPLY CHAIN A GOOD PRACTICE GUIDE FOR EMPLOYERS April 2015 Disclaimer: Reference to any specific commercial product, process or service by trade

More information

Procurement and contract strategies

Procurement and contract strategies Achieving Excellence in Construction Procurement Guide 06 Procurement and contract strategies 06 Contents 01 The Achieving Excellence Procurement Guides 02 Introduction 02 Principles 05 Process 18 Annex

More information

PROJECT PROCUREMENT MANAGEMENT

PROJECT PROCUREMENT MANAGEMENT 12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,

More information

Dated 2015 (1) THE HALL FOR CORNWALL TRUST. and (2) [ARCHITECT] Appointment of Architect

Dated 2015 (1) THE HALL FOR CORNWALL TRUST. and (2) [ARCHITECT] Appointment of Architect Dated 2015 (1) THE HALL FOR CORNWALL TRUST and (2) [ARCHITECT] Appointment of Architect to provide architectural and other multi-disciplinary services in relation to the design for the Hall for Cornwall,

More information

Project Management Manual Update 2006. Transportation Department City of Edmonton

Project Management Manual Update 2006. Transportation Department City of Edmonton Project Management Manual Update 2006 Transportation Department City of Edmonton Project Management Manual for Transportation Projects EXECUTIVE SUMMARY This document has been updated to fulfill the requirements

More information

ENGAGING A LANDSCAPE CONSULTANT GUIDANCE FOR CLIENTS ON FEES SEPTEMBER 2002

ENGAGING A LANDSCAPE CONSULTANT GUIDANCE FOR CLIENTS ON FEES SEPTEMBER 2002 ENGAGING A LANDSCAPE CONSULTANT GUIDANCE FOR CLIENTS ON FEES SEPTEMBER 2002 The Landscape Institute 33 Great Portland Street London W1W 8QG Tel: +44 (0)20 7299 4500 Fax: +44 (0)20 7299 4501 Email: mail@llandscapeinstitute.org

More information

International Construction Warranties Limited. Terms & Conditions. Version UK1

International Construction Warranties Limited. Terms & Conditions. Version UK1 International Construction Warranties Limited Terms & Conditions Version UK1 Rules of Registration Version 5 All Companies applying for or taking out a Warranty on a New Development with ICW shall comply

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

Internal Audit. Capital Projects. May 2015. Final Report

Internal Audit. Capital Projects. May 2015. Final Report Internal Audit TABLE OF CONTENTS Executive Summary...3 1 Introduction...3 2 Objectives...3 3 Scope...4 4 Summary of...4 5 Overall and Opinion...4 Audit Tests and...5 6.1 Management & Delivery of Projects...5

More information

Operational Parameters. for the. Review and Evaluation of. Construction Management Projects

Operational Parameters. for the. Review and Evaluation of. Construction Management Projects Operational Parameters for the Review and Evaluation of Construction Management Projects Operational Parameters for the Review and Evaluation of Construction Management Projects Table of Contents Introduction...

More information

QUEENSLAND CENTRE FOR PROFESSIONAL DEVELOPMENT (QCPD) TENDERING SERVICE: TENDER BID DECISION, PREPARATION AND SUBMISSION PROCEDURES

QUEENSLAND CENTRE FOR PROFESSIONAL DEVELOPMENT (QCPD) TENDERING SERVICE: TENDER BID DECISION, PREPARATION AND SUBMISSION PROCEDURES PROCEDURES QUEENSLAND CENTRE FOR PROFESSIONAL DEVELOPMENT (QCPD) TENDERING SERVICE: TENDER BID DECISION, PREPARATION AND SUBMISSION PROCEDURES PURPOSE These procedures provide guidance on the process of

More information

SPECIAL CONDITIONS OF EMPLOYMENT/CONTRACT AND NOTE TO TENDERERS/CONSULTANTS

SPECIAL CONDITIONS OF EMPLOYMENT/CONTRACT AND NOTE TO TENDERERS/CONSULTANTS Revised SCE( ) at App E to TCW 9/2007, page 1 of 3 SPECIAL CONDITIONS OF EMPLOYMENT/CONTRACT AND NOTE TO TENDERERS/CONSULTANTS SCE ( ) Professional Indemnity Insurance General Conditions of Employment

More information

SMS0045 Construction Health and Safety Policy and Procedures

SMS0045 Construction Health and Safety Policy and Procedures SMS0045 Construction Health and Safety Policy and Procedures March 2015 Version 8 Please note that for projects utilising a CDM Co-ordinator under the transitional arrangements of CDM 2015 (between 6 April

More information

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table

More information

Policy and Procedure for Claims Management

Policy and Procedure for Claims Management Policy and Procedure for Claims Management RESPONSIBLE DIRECTOR: COMMUNICATIONS, PUBLIC ENGAGEMENT AND HUMAN RESOURCES EFFECTIVE FROM: 08/07/10 REVIEW DATE: 01/04/11 To be read in conjunction with: Complaints

More information

Internal Audit Standards

Internal Audit Standards Internal Audit Standards Department of Public Expenditure & Reform November 2012 Copyright in material supplied by third parties remains with the authors. This includes: - the Definition of Internal Auditing

More information

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review

Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a

More information