Investment & Performance Board (IPB)

Size: px
Start display at page:

Download "Investment & Performance Board (IPB)"

Transcription

1 Investment & Performance Board (IPB) Date of meeting: 19 January 2016 Title of paper: Developing a New Junior Electricity Supply Licence - Progress Report To be presented by: Cleared by: Classification: Patrick Feehily, Assistant Director, Environment Matthew Pencharz, Deputy Mayor, Environment and Energy Fiona Fletcher-Smith, Executive Director, Development, Enterprise and Environment Public with appendix 2 reserved from publication (as it contains commercially sensitive information) 1 Executive Summary 1.1 This is an update report requested by the IPB on the licence lite project. The purpose of the project is to enable existing and new decentralised energy providers who generate low and zero carbon electricity in London, to sell their electricity at proper market prices, rather than be impeded from taking full advantage of the market because of its risks and complexities. 1.2 Formal application for the junior electricity supply licence (known as licence lite ) was made to the electricity regulator Ofgem on 1 March During 2014 and 2015 specialised market services required were procured under a public procurement exercise, the successful tenderer being RWE npower. A public procurement process has also been carried out (and now completed to the evaluation stage) to obtain sources of low and zero carbon electricity for the GLA to supply to consumers under its licence lite operations. The initial consumer is planned to be Transport for London (TfL). 1.3 No new barriers to completion of the project have arisen, nor have the risks materially altered and the prospects of delivering licence lite remain positive. However, there have been very substantial delays in implementing the project caused by the time taken in completing the two public procurement processes involved, particularly the procurement of the electricity generating capacity. 1.4 It is apparent from the responses to the Invitation to Negotiate issued to electricity generators that a quantity of solar generated electricity is likely to be available which will be useful in servicing continuous day time electricity demand and assist in maintaining the balance between the generators output and the electricity demand the GLA is serving. 1.5 Providing price negotiations with the electricity generators and TfL as the first consumer proceed in accordance with current estimates of market prices, the objective is for an application for a Mayoral Decision to be made during February 2016.

2 1.6 Expenditure on the project remains within budget, although there may be a need for some final commercial and financial due diligence which has not been budgeted for. 2 Recommendation 2.1 That the Board notes the report. 3 Introduction and Background 3.1 The licence lite model involves the GLA obtaining a junior electricity supply licence whereby, with the support of a fully licensed electricity supplier, it can purchase the output from low and zero carbon electricity generators in London and supply the electricity produced to public and commercial electricity users in London, whose volumes and timing of electricity consumption offer the optimal income to the generators, relative to their costs. The GLA in effect acts as a facilitator, securing the best market for the electricity at the best available price, in return for taking a margin on the income received to cover its costs and retain a surplus. Appendix 1 illustrates the principles of the GLA licence lite model. 3.2 The financial efficacy of the model has been tested recurrently, in the light of fluctuating market conditions, during the currency of the project and remains positive. It should be noted that the accuracy of the financial model in assessing the feasibility of the project remains subject to some assumptions on current pricing in the market remaining broadly correct. These assumptions will be tested during the course of negotiations with the electricity generators appointed to the GLA s framework. These negotiations will be taking place during the next month and the Board will be given an oral update. 3.3 The risks of the project being unviable have diminished since the last progress report to the Board in December That is because the third party fully licensed electricity supplier required to provide the specialised market services has now been appointed under the tendering exercise and the GLA has received a sufficient number of responses from low and zero carbon electricity generators to its Invitation to Negotiate. Those responses are currently under formal evaluation. However, as stated above, until successful negotiation with generators on actual prices has been completed during January 2016, there remains the risk of assumptions made regarding prices attainable by generators being inaccurate. 3.4 In addition to maintaining an updated financial model for the project, a risk matrix of the risks associated with operating the licence lite model has been maintained and developed as the project has progressed. A high level summary of the prospective operational risks is contained in Appendix 2 and is commented upon below (Risks arising / mitigation). A full risks register is in course of preparation and will form part of the GLA s operational manual for licence lite (see paragraph 6 below).the risks are seen as manageable within the GLA s capacity and skills. That is because the functions requiring

3 specialised market knowledge and management capacity are carried out by the third part fully licensed supplier (RWE npower) under a market services agreement. 3.5 The major unexpected factor in the progress of the project has been timing, caused by the length of time involved in the public procurement processes, most notably in respect of the electricity generating capacity needed. Those process are however now complete, apart from the final evaluation stage of the generators tenders which is currently in progress. 3.6 The spend to date on licence lite is as follows DEPDU (Arup) - 192,323 Cornwall Energy (electricity market advisers) - 30,500 Legal advice (Nabarro and then Temple Bright) - 38,157 4 Progress since the last report and steps to completion 4.1 The principal steps completed since the last report to the Board in December 2014 are as follows appointment of RWE npower as market services provider; planning with npower of operation requirements for licence lite, notably invoicing / data collection processing /metering / service level arrangements; public procurement of electricity generating capacity. This is complete, subject to evaluation of tenders received. 8 tenders have been received, including 5 from London boroughs, one major housing association and 2 national providers and operators of low and zero carbon energy generating schemes, with investments in London; preparation of a form of power purchase agreement with generators and supply agreement with GLA licence lite customers; recurrent updating of financial model and risk matrix, in the light of how the project has developed and changes in market conditions; resolution with Ofgem of outstanding regulatory issues and operational requirements. 4.2 The principal steps required to be completed prior to application for a Mayoral Decision to approve the project / start of operations are as follows completion of evaluation of tenders from the electricity generators; settlement of pricing terms with generators and TfL (as the GLA s supply customer) and of the forms of power purchase agreement with the generators and supply agreement with TfL; completion of service level and operational arrangements with npower, concurrent with agreeing operational /invoicing arrangements with the generators and TfL; finalisation of financial model and risk matrix; completion of business plan and GLA operational handbook; grant of electricity (licence lite) supply licence by Ofgem.

4 4.3. As stated above, the timing of progress has hitherto been dictated and constrained by the public procurement exercises. However, subject to the completion of the evaluation of the tenders from generators, there are now no procurement exercises to constrain the timing. The remaining tasks listed above mainly have to be progressed and delivered in parallel, since they are interdependent. Substantial progress will have been made by the 19 January IPB meeting and an update of progress will be made then. An estimated timetable for completion of the remaining stages is as follows 7 January - completion of evaluation of generator tenders. This will mean that all the parties to operating licence lite will have been assembled, subject to agreeing pricing terms with the generators and TfL; 28 January pricing terms agreed in principle with TfL and the generators; February commercial / financial due diligence; - request for Mayoral Decision approving the project; 28 February forms of agreement settled with generators and TfL; 14 March - licence lite licence granted; 31 March - ready to commence operations 4.4 The actual date for commencement of operations will depend upon the timing of the availability of the electricity generating capacity contracted and arrangements for TfL premises being available to take the electricity supplies from the licence lite operation. The introduction of electricity generating capacity to the licence lite project and the making available of TfL s electricity consumption meters to be supplied under the project will need to be a phased process during the first year. For example, combined heat and power plants may be subject to existing export arrangements and only available when those arrangements expire. Conversely, some solar power may be available immediately and other new generating plant available immediately following its commissioning being completed. 5 Equality Comments 5.1 Equality issues have been considered. Most notably the project when complete will involve contracts with parties, all of whom have accepted responsibility for equality issues in terms acceptable to the GLA, in addition to which the GLA will be carrying out its electricity supply activities under regulated terms that include provisions regarding those with protected characteristics. The outcome is expected to be positive. 6 Key Risks and Issues 6.1 The risk of the project not proceeding has diminished, insofar as the procurement process for acquiring generating capacity has had a positive outcome. The principal risk remaining is that the assumptions made in the financial model regarding the pricing expectations of smaller electricity generators are inaccurate and assume lower prices than those actually attainable. The effect would be to reduce or remove the financial margin in the

5 model. The position will crystallise when the GLA negotiates prices with the generators appointed to the framework during January. 6.2 Now that we will be obtaining actual prices from the generators, the current financial model which has been used to monitor the financial feasibility of the project, will be converted into an operational model, within which all aspects of the day to day financial performance of the project can be assessed. 6.3 There are risk issues attached to operating the licence lite project, as distinct from the risks of the project not proceeding. The significant risks in this area revolve around two areas of exposure first, purchasing electricity from the generators and selling it to GLA consumers (notably TfL). This gives rise to the risk of the purchase price paid by the GLA rising, without the sale price to TfL doing so or doing so to the same extent; or falls in price similarly affecting the GLA s margin. This risk is contained by arranging for fixed terms for purchase of electricity from the generators and supply to TfL, so that market fluctuations only affect price when both sides of the arrangement come up for re-negotiation; second, generators failing to produce the electricity the GLA has contracted for on time and in the quantity required. This could cause the GLA to be short relative to its commitment to supply TfL and incur a high penalty price in the electricity market (passed through by npower) for replacement of the missing power, if it has not made other arrangements. This risk is managed and mitigated by an arrangement with npower to sell substitute power to the GLA if it is given due notice. Where due notice is not possible, the GLA regulates the position by passing all or part of the extra cost incurred back to the generator who is at fault. Also, the GLA will normally buy more electricity than it needs, so there is an excess available. 6.4 A GLA licence lite operational manual is in course of preparation to establish the risk register and specify the measures to manage those risks. 6.5 Appendix 2 contains a high level summary of the operational risks and the means of management and mitigation of them. 7 Financial comments of the Executive Director Resources 7.1 The spend detailed in paragraph 3.6 is expenditure since 2013 and has being funded as follows; Spend Amount Funding DEPDU (Arup) 192,323 European Local Energy Assistance (ELENA) EU funded Cornwall Energy (electricity market advisers) 30,500 Licence Lite and budget Legal advice 38,157 Licence Lite 2014-

6 (Nabarro and then Temple Bright) 15 and budget 7.2 Financial modelling for establishing financial feasibility is currently being developed to determine the expected income and expenditure. IPB will be informed of these figures once the financial model has being developed. 8 Legal Comments 8.1 No MD or DD is required 9 Next steps 9.1 The next steps following consideration/in-principle approval by IPB are summarised below: Activity Pricing agreed in principle between GLA /TfL /generators Announcement of construction of licence lite business MD approving project Forms of agreement settled between GLA/TfL/generators Grant of supply licence by Ofgem Ready to commence operations Timeline 20 January January February March March 31 March Appendices: Appendix 1 Diagram of Licence Lite Electricity and Payment Flows Appendix 2 Summary of Operational Risks (Reserved)

Investment & Performance Board (IPB)

Investment & Performance Board (IPB) Investment & Performance Board (IPB) Date of IPB meeting: 18 December 2014 Title of paper: To be presented by: Cleared by: (name Adviser & Director) Classification: Junior Electricity Supply Licence Update

More information

Investment & Performance Board (IPB)

Investment & Performance Board (IPB) Investment & Performance Board (IPB) Date of IPB meeting: 23 October 2012 Title of paper: To be presented by: Cleared by: (name Adviser & Director) Classification: Developing a new junior electricity supply

More information

Finance and Policy Committee. Date: 14 October 2014. Item 17: TfL Energy Purchasing 2017 to 2020. This paper will be considered in public.

Finance and Policy Committee. Date: 14 October 2014. Item 17: TfL Energy Purchasing 2017 to 2020. This paper will be considered in public. Finance and Policy Committee Date: 14 October 2014 Item 17: TfL Energy Purchasing 2017 to 2020 This paper will be considered in public 1 Summary 1.1 This paper: (a) reviews the current purchasing strategy

More information

Transaction Advice Corporate Finance

Transaction Advice Corporate Finance Transaction Advice Corporate Finance Introduction Transaction Advice Transaction Advice Our Corporate Finance Services Arup s Transaction Advice team integrates financial, technical and commercial expertise,

More information

Procurement of communications support for the launch of Healthy Schools London

Procurement of communications support for the launch of Healthy Schools London REQUEST FOR DIRECTOR DECISION DD923 Title: Procurement of communications support for the launch of Healthy Schools London Executive Summary: The Healthy Schools London programme ( HSL Programme ) is one

More information

The Mayor s London Housing Strategy includes a policy to create Housing Zones across London.

The Mayor s London Housing Strategy includes a policy to create Housing Zones across London. REQUEST FOR MAYORAL DECISION MD1438 Title: Housing Zone Consultancy Support Executive Summary: The Mayor s London Housing Strategy includes a policy to create Housing Zones across London. The Housing Zone

More information

Date: 26/01/2004. MEETING NAME Executive Delegation of award of energy supply contracts

Date: 26/01/2004. MEETING NAME Executive Delegation of award of energy supply contracts Item No. Classification: Open Report title: Ward(s) or groups affected: From: Date: 26/01/2004 MEETING NAME Executive Delegation of award of energy supply contracts ALL Assistant Chief Executive Strategy

More information

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA Appendix 2c DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA Review of Programme and Project Management Framework- Strategic Land and Property DISTRIBUTION LIST Audit Team David

More information

Government response to the CFD Counterparty and Electricity Settlements Company operational costs 2014/15 consultation

Government response to the CFD Counterparty and Electricity Settlements Company operational costs 2014/15 consultation Government response to the CFD Counterparty and Electricity Settlements Company operational costs 2014/15 consultation Consultation on the operational cost levies June 2014 Crown copyright 2014 URN 14D/182

More information

Introduction to the London Energy Efficiency Fund (LEEF)

Introduction to the London Energy Efficiency Fund (LEEF) Executive Summary Introduction to the London Energy Efficiency Fund (LEEF) 1. The London Green Fund (LGF) is a 100m Fund comprising of 50m from the London 2007-13 European Regional Development Fund (ERDF)

More information

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and

SCHEDULE 16. Exit Plan. sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and SCHEDULE 16 Exit Plan 1. Scope 1.1 This schedule: (A) sets out the strategy to be followed on the termination (including Partial Termination) or expiry of this Agreement; and requires the Service Provider

More information

Electricity Terminology. Simplifying energy management

Electricity Terminology. Simplifying energy management Simplifying energy management AMR Automated Meter Reading - automatic collection of data from meters which is transferred to a central database for billing and/or analysis. Balancing Mechanism The mechanism

More information

Piedmont Natural Gas Company, Inc. Tennessee Index of Tariff & Service Regulations

Piedmont Natural Gas Company, Inc. Tennessee Index of Tariff & Service Regulations Tennessee Index of Tariff & Service Regulations Rate Schedule 301 Rate Schedule 302 Rate Schedule 303 Rate Schedule 304 Rate Schedule 306 Rate Schedule 307 Rate Schedule 309 Rate Schedule 310 Rate Schedule

More information

Securing and using additional external resources to support Health Inequalities Strategy delivery

Securing and using additional external resources to support Health Inequalities Strategy delivery REQUEST FOR DIRECTOR DECISION DD537 Title: Securing and using additional external resources to support Health Inequalities Strategy delivery Executive Summary: The Greater London Authority Act 1999 requires

More information

Proposed debt assignment protocol for prepayment customers. A consultation document

Proposed debt assignment protocol for prepayment customers. A consultation document Proposed debt assignment protocol for prepayment customers A consultation document Summary Ofgem is committed to removing any unnecessary barriers preventing customers from switching suppliers. This document

More information

GENERAL CONDITIONS FOR SALE OF ELECTRICITY TO DOMESTIC CONSUMERS

GENERAL CONDITIONS FOR SALE OF ELECTRICITY TO DOMESTIC CONSUMERS 27 February 2015 1 (9) GENERAL CONDITIONS FOR SALE OF ELECTRICITY TO DOMESTIC CONSUMERS GENERAL CONDITIONS prepared by Svensk Energi following agreement with the Swedish Consumer Agency. 1. Introductory

More information

UK-London: IT services: consulting, software development, Internet and support 2011/S 165-273114 CONTRACT NOTICE. Services

UK-London: IT services: consulting, software development, Internet and support 2011/S 165-273114 CONTRACT NOTICE. Services 1/6 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:273114-2011:text:en:html UK-London: IT services: consulting, software development, Internet and support 2011/S 165-273114 CONTRACT

More information

Business Improvement Programme Framework

Business Improvement Programme Framework Finance and Policy Committee Date: 11 March 2015 Item 19: Business Improvement Programme Framework This paper will be considered in public 1 Summary 1.1 The Transport for London Business Improvement Programme

More information

Gravesham Borough Council. Leader of the Executive

Gravesham Borough Council. Leader of the Executive Classification: Key Decision: Part 1 Public Yes Gravesham Borough Council Report to: Leader of the Executive Date: 18 January 2013 Reporting officer: Subject: Kevin Burbidge, Director (Housing and Regeneration)

More information

2015 No. 1544 ELECTRICITY GAS. The Electricity and Gas (Standards of Performance) (Suppliers) Regulations 2015

2015 No. 1544 ELECTRICITY GAS. The Electricity and Gas (Standards of Performance) (Suppliers) Regulations 2015 S T A T U T O R Y I N S T R U M E N T S 2015 No. 1544 ELECTRICITY GAS The Electricity and Gas (Standards of Performance) (Suppliers) Regulations 2015 Made - - - - 11th July 2015 Coming into force - - 1st

More information

Cabinet Member for Business, Skills and Housing. Title: Purchase of Communal Electricity and Gas 2014/15

Cabinet Member for Business, Skills and Housing. Title: Purchase of Communal Electricity and Gas 2014/15 Decision Maker: Cabinet Member for Business, Skills and Housing Date: 13 January 2014 Classification: General Release Title: Purchase of Communal Electricity and Gas 2014/15 Wards Affected: Better City,

More information

LOCAL SUPPLY: OPTIONS FOR SELLING YOUR ENERGY LOCALLY STEPHENS SCOWN AND REGEN SW

LOCAL SUPPLY: OPTIONS FOR SELLING YOUR ENERGY LOCALLY STEPHENS SCOWN AND REGEN SW LOCAL SUPPLY: OPTIONS FOR SELLING YOUR ENERGY LOCALLY STEPHENS SCOWN AND REGEN SW June 2015 Page 2 1 INTRODUCTION Our energy system is changing. Communities across the UK are no longer satisfied with a

More information

How To Account For Construction Contracts In Indian Accounting Standard (Indas)

How To Account For Construction Contracts In Indian Accounting Standard (Indas) Contents Indian Accounting Standard (Ind AS) 11 Construction Contracts Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT

More information

Guidance for the instruction of experts in civil claims

Guidance for the instruction of experts in civil claims Guidance for the instruction of experts in civil claims Introduction 1. The purpose of this guidance is to assist litigants, those instructing experts and experts to understand best practice in complying

More information

Procurement of IT software and support for housingmoves service

Procurement of IT software and support for housingmoves service REQUEST FOR DIRECTOR DECISION DD447 Title: Procurement of IT software and support for housingmoves service Executive Summary: Housingmoves will transfer to the GLA on 1 st April 2011. The efficient running

More information

Capital Works Management Framework

Capital Works Management Framework POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset

More information

Date: 14.9.05. Classification: Open. Meeting Name: Council Assembly. Item No. 6.1. Adoption of powers to deal with Moving Traffic Offences All

Date: 14.9.05. Classification: Open. Meeting Name: Council Assembly. Item No. 6.1. Adoption of powers to deal with Moving Traffic Offences All Item No. 6.1 Classification: Open Date: 14.9.05 Meeting Name: Council Assembly Report title: Ward(s) or groups affected: From: Adoption of powers to deal with Moving Traffic Offences All Strategic Director

More information

Agreement for the provision of IT Management Services and IT Services

Agreement for the provision of IT Management Services and IT Services Board Date: 26 March 2015 Item 16: Agreement for the provision of IT Management Services and IT Services This paper will be considered in public 1 Summary 1.1 This paper asks the Board to approve extended

More information

Finance for the non-financial manager

Finance for the non-financial manager Finance for the non-financial manager A Guest Article by Paul Lower January 2010 How to control working capital and cash flow The banking crisis, credit crunch and global recession have provided the backdrop

More information

Mill Hill East Limited Liability Partnership and Co-operation Agreement. 18 March 2011

Mill Hill East Limited Liability Partnership and Co-operation Agreement. 18 March 2011 1271 DELEGATED POWERS REPORT NO. SUBJECT: Mill Hill East Limited Liability Partnership and Co-operation Agreement Control sheet All of the following actions MUST be completed at each stage of the process

More information

Most household services provide you with a fixed monthly bill: Broadband Internet service

Most household services provide you with a fixed monthly bill: Broadband Internet service Predict-a-Bill Natural Gas Most household services provide you with a fixed monthly bill: Cell phone service Broadband Internet service And now... your natural gas supply! Predict-a-Bill advantage: Developed

More information

Invitation to Tender

Invitation to Tender Invitation to Tender Provision of Training in Technology Transfer and Related Areas for The Southern Africa Innovation Support Programme 1. Drawing up the tender The tender must be submitted in writing

More information

Financial Settlement Strategy

Financial Settlement Strategy Financial Settlement Strategy We are seeking stakeholders views on the questions set out in this consultation document. If you have any comments on the paper please contact: feedback@open-water.org.uk

More information

GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses

GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses Office of Government Procurement Cost Control: Price Variation Clauses Document Reference GN 1.5.2 v1.0 22 January 2016 2016 Department of Public

More information

Standard conditions of electricity supply licence

Standard conditions of electricity supply licence Gas and Electricity Markets Authority ELECTRICITY ACT 1989 Standard conditions of electricity supply licence SECTION A: STANDARD CONDITIONS FOR ALL SUPPLIERS Standard conditions 1 to 6: General arrangements

More information

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S Hamdi Mramori Street, No 1 Prishtina 10000 Kosovo Tel: +381 (0) 38 247 615 ext. 103 Fax: +381 (0) 38 247 620 e-mail: info@ero-ks.org www.ero-ks.org ELECTRICITY SUPPLY/ TRADE LICENSE GRANTED TO: KORLEA

More information

DIRECTORATE OF AUDIT, RISK AND ASSURANCE

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Appendix 2 DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA DRAFT Review of Millennium Mills Grant Declaration 2014/15 DISTRIBUTION LIST Audit Team David Esling, Head of Audit

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

TERMS OF ELECTRICITY SALES 2010. as recommended by Finnish Energy Industries

TERMS OF ELECTRICITY SALES 2010. as recommended by Finnish Energy Industries TERMS OF ELECTRICITY SALES 2010 as recommended by Finnish Energy Industries Content: A. General, concluding an electricity sale contract, the prerequisites for electricity sales, commencement of electricity

More information

Page 7. London Borough of Sutton

Page 7. London Borough of Sutton Page 7 Agenda Item 3 London Borough of Sutton The Executive - 5 July 2011 Joint Report of the Strategic Director Resources and Executive Head of Policy and Customer Services BUSINESS AND FINANCIAL PLANNING

More information

NERA Analysis of Energy Supplier Margins

NERA Analysis of Energy Supplier Margins 7 December 2009 NERA Analysis of Energy Supplier Margins By Graham Shuttleworth Even though wholesale energy prices have fallen recently, gas and electricity suppliers are earning very little margin on

More information

RECOMMENDATIONS ON BUSINESS PLAN PREPARATION

RECOMMENDATIONS ON BUSINESS PLAN PREPARATION RECOMMENDATIONS ON BUSINESS PLAN PREPARATION 1. General provisions Business plan must contain: name of the investment project, as well description of its essence and feasibility; substantiation of the

More information

Transport for London. INVITATION TO TENDER FOR BRIDGE DESIGN CONSULTANCY SERVICES ITT REF: TfL/90711 PUBLICATION DATE: 13 FEBRUARY 2013

Transport for London. INVITATION TO TENDER FOR BRIDGE DESIGN CONSULTANCY SERVICES ITT REF: TfL/90711 PUBLICATION DATE: 13 FEBRUARY 2013 Transport for London INVITATION TO TENDER FOR BRIDGE DESIGN CONSULTANCY SERVICES ITT REF: TfL/90711 PUBLICATION DATE: 13 FEBRUARY 2013 Invitation to Tender TfL/90711 Bridge Design Consultancy Services

More information

INVITATION TO TENDER FOR SO16649 DEBT MANAGEMENT FUNCTIONAL DESIGN PRINCIPLES, STANDARDS AND MEASURES, AND DEBT LANDSCAPE

INVITATION TO TENDER FOR SO16649 DEBT MANAGEMENT FUNCTIONAL DESIGN PRINCIPLES, STANDARDS AND MEASURES, AND DEBT LANDSCAPE INVITATION TO TENDER FOR SO16649 DEBT MANAGEMENT FUNCTIONAL DESIGN PRINCIPLES, STANDARDS AND MEASURES, AND DEBT LANDSCAPE Version 1.0 Date: 8 th February 2016 Author: Harbinder Manku CONTENTS 1. INTRODUCTION...

More information

CONSULTATION PAPER MARCH 2010. Corporate Actions Processing on the International Order Book

CONSULTATION PAPER MARCH 2010. Corporate Actions Processing on the International Order Book CONSULTATION PAPER MARCH 2010 Corporate Actions Processing on the International Order Book Contents 1 Introduction... 3 1.1 Purpose of this document...3 1.2 Readership...4 1.3 Contact details...4 2 Corporate

More information

FINANCIAL SUPPORT PROGRAMS

FINANCIAL SUPPORT PROGRAMS 9 FINANCIAL SUPPORT PROGRAMS 108 9 FINANCIAL SUPPORT PROGRAMS 9 FINANCIAL SUPPORT PROGRAMS There are a number of Government support mechanisms to help reduce the barriers to undertaking action on energy

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

Review of Low Carbon Network Fund proposals

Review of Low Carbon Network Fund proposals Review of Low Carbon Network Fund proposals Report to Expert Panel Western Power Distribution WPDT2001: LV Network Templates 8 th October 2010 Report prepared by TNEI and Arthur D. Little for project commissioned

More information

STELLENBOSCH MUNICIPALITY

STELLENBOSCH MUNICIPALITY STELLENBOSCH MUNICIPALITY APPENDIX 9 BORROWING POLICY 203/204 TABLE OF CONTENTS. PURPOSE... 3 2. OBJECTIVES... 3 3. DEFINITIONS... 3 4. SCOPE OF THE POLICY... 4 5. LEGISLATIVE FRAMEWORK AND DELEGATION

More information

GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES

GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES 1 (6) GENERAL CONDITIONS FOR THE SALE OF ELECTRICITY USED IN BUSINESS OPERATIONS OR OTHER SIMILAR ACTIVITIES GENERAL CONDITIONS prepared by Svensk Energi 1. Introductory provisions 1.1 These general conditions

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

SETTING UP A LONDON ENERGY COMPANY

SETTING UP A LONDON ENERGY COMPANY February 2016 SETTING UP A LONDON ENERGY COMPANY SUMMARY: London is ready for a renewable energy revolution, and could supply 20 per cent of its electricity from solar power alone. A Green Mayor will set

More information

FOREIGN EXCHANGE ACT, 1992 ARRANGEMENT OF SECTIONS. Title PART I PRELIMINARY PROVISIONS

FOREIGN EXCHANGE ACT, 1992 ARRANGEMENT OF SECTIONS. Title PART I PRELIMINARY PROVISIONS FOREIGN EXCHANGE ACT, ARRANGEMENT OF SECTIONS Section Title PART I PRELIMINARY PROVISIONS 1. Short title. 2. Commencement. 3. Application. 4. Interpretation. PART II PROVISIONS FOR FOREIGN EXCHANGE ADMINISTRATION

More information

Authority to Award Contract for the Supply of ACD Call Centre Software for Customer Services

Authority to Award Contract for the Supply of ACD Call Centre Software for Customer Services Cabinet 29 June 2015 Report from the Chief Operating Officer Wards Affected: ALL Authority to Award Contract for the Supply of ACD Call Centre Software for Customer Services 1.0 Summary 1.1 This report

More information

The main points are: The Business Plan How To Write It. History of your Business

The main points are: The Business Plan How To Write It. History of your Business The Business Plan How To Write It A business plan has nine key sections. Within each of the following sections there is a list of points that should be covered fully backed up with detailed information

More information

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS LAW OF MONGOLIA 28 January 2010 State Palace, Ulaanbaatar city Article 1. Purpose of the law ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS 1.1. The purpose of this law is to regulate matters related to

More information

BGE/BE/TAC/0710. NQH Business electricity Terms and conditions

BGE/BE/TAC/0710. NQH Business electricity Terms and conditions BGE/BE/TAC/0710 NQH Business electricity Terms and conditions These are our standard terms and conditions of NQH business electricity supply. As a NQH business customer you will be deemed to have accepted

More information

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013. Department for Culture, Media & Sport. The rural broadband programme

REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013. Department for Culture, Media & Sport. The rural broadband programme REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 535 SESSION 2013-14 5 JULY 2013 Department for Culture, Media & Sport The rural broadband programme 4 Key facts The rural broadband programme Key facts

More information

Procurement of call-off contract from SASPAC s Framework Agreement.

Procurement of call-off contract from SASPAC s Framework Agreement. REQUEST FOR DIRECTOR DECISION DD383 Title: Procurement of call-off contract from SASPAC s Framework Agreement. Executive Summary: The GLA manages the support, maintenance and development of the SASPAC

More information

Supporting People Delivery of Assistive Technology Monitoring Services

Supporting People Delivery of Assistive Technology Monitoring Services Agenda Item No 13 Bolsover District Council Executive 1 December 2014 Supporting People Delivery of Assistive Technology Monitoring Services Report of the Cllr K Reid, Portfolio Holder for Housing This

More information

Business and technical conditions of electricity supply for customers connected to the public distribution of LV electricity valid for the year 2005

Business and technical conditions of electricity supply for customers connected to the public distribution of LV electricity valid for the year 2005 Business and technical conditions of electricity supply for customers connected to the public distribution of LV electricity valid for the year 2005 ARTICLE I GENERAL PROVISIONS 1. These business and technical

More information

Section 82. Australian Consumer Law. Cancellation notice Unsolicited consumer agreement. Right to cancel this agreement within 10

Section 82. Australian Consumer Law. Cancellation notice Unsolicited consumer agreement. Right to cancel this agreement within 10 Section 82 Australian Consumer Law Cancellation notice Unsolicited consumer agreement Right to cancel this agreement within 10 business day cooling off period You have a right to cancel this agreement

More information

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES

General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9

More information

Highlands and Islands Broadband Pathfinder Project - Background

Highlands and Islands Broadband Pathfinder Project - Background ITEM: 22(a) PAGE: 1 REPORT TO: The Moray Council on 5 July, 2006 SUBJECT: BY: Highlands and Islands Broadband Pathfinder Project - Background Chief Executive 1. Reason for Report 1.1 The Pathfinder Broadband

More information

BANKING UNIT POLICY DOCUMENTS

BANKING UNIT POLICY DOCUMENTS BANKING UNIT POLICY DOCUMENTS POLICY DOCUMENT ON THE REGULATORY PROVISIONS FOR THE UNDERTAKING OF LENDING ACTIVITIES BY INSTITUTIONS AUTHORISED UNDER THE FINANCIAL INSTITUTIONS ACT 1994 FACTORING FORFAITING

More information

QUARTERLY REPORT FOR THE PERIOD ENDING 31 MARCH 2015

QUARTERLY REPORT FOR THE PERIOD ENDING 31 MARCH 2015 QUARTERLY REPORT FOR THE PERIOD ENDING 31 MARCH 2015 HIGHLIGHTS Positive free cashflow (revenue less operating costs and CAPEX) of $191k for the month of March; a first in the history of Lynas Amended

More information

APPROVAL OF POWER AND WATER S NETWORK SERVICES CLASSIFICATION THIRD REGULATORY CONTROL PERIOD

APPROVAL OF POWER AND WATER S NETWORK SERVICES CLASSIFICATION THIRD REGULATORY CONTROL PERIOD Address all correspondence to: Telephone: (08) 8999 5480 The Utilities Commissioner, GPO Box 915, Darwin NT 0801 Facsimile: (08) 8999 6262 Location: 38 Cavenagh Street, Darwin Website:www.utilicom.nt.gov.au

More information

Standard conditions of the Electricity Distribution Licence

Standard conditions of the Electricity Distribution Licence Gas and Electricity Markets Authority ELECTRICITY ACT 1989 Standard conditions of the Electricity Distribution Licence Standard conditions of the Electricity Distribution Licence 30 October 2015 SECTION

More information

June 2008 Supplement to Characteristics and Risks of Standardized Options

June 2008 Supplement to Characteristics and Risks of Standardized Options June 2008 Supplement to Characteristics and Risks of Standardized Options This supplement supersedes and replaces the April 2008 Supplement to the booklet entitled Characteristics and Risks of Standardized

More information

PUBLIC Calculation of Supplier Demand for EMR Charging. EMRS Guidance

PUBLIC Calculation of Supplier Demand for EMR Charging. EMRS Guidance PUBLIC Calculation of Supplier Demand for EMR Charging EMR Settlement Ltd Version 1.0 06 August 2015 CONTENTS Change Amendment Record 3 1. Introduction 4 2. Purpose 4 3. Why is this important? 4 4. What

More information

How To Read The Unitholders Of The Kukon Island Power Station

How To Read The Unitholders Of The Kukon Island Power Station E.ON s UK Consolidated Segmental Report for the year ended 31 December 2012 Introduction In accordance with the Electricity Generation Licence Condition 16 - Financial Information Reporting, and the Electricity

More information

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to:

2. Subject to any special rules applied by the College's funding bodies, the tendering procedures will be applicable to: HARPER ADAMS UNIVERSITY COLLEGE Code of Tendering Practice Introduction 1. The following guidelines are to be used in the conduct of tendering and contracting of major services and supplies commissioned

More information

ELECTRICITY MARKET ACT

ELECTRICITY MARKET ACT 1 NB: Unofficial translation Ministry of Trade and Industry, Finland ELECTRICITY MARKET ACT (386/1995; amendments up to 1172/2004 included) In accordance with a decision by Parliament, the following is

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

MEDIA STATEMENT Electronic Trading Platform for RSA Government Bonds

MEDIA STATEMENT Electronic Trading Platform for RSA Government Bonds MEDIA STATEMENT Electronic Trading Platform for RSA Government Bonds The National Treasury will implement an electronic trading platform ( ETP ) for the Primary Dealers ( PDs ) where the secondary market

More information

By email to smartermarkets@ofgem.gov.uk. Andrew Wallace Smarter Markets Ofgem 9 Millbank London. 11 August 2014. Dear Andrew,

By email to smartermarkets@ofgem.gov.uk. Andrew Wallace Smarter Markets Ofgem 9 Millbank London. 11 August 2014. Dear Andrew, By email to smartermarkets@ofgem.gov.uk Andrew Wallace Smarter Markets Ofgem 9 Millbank London 11 August 2014 Dear Andrew, We welcome the opportunity to provide ELEXON Limited s views on the above consultation

More information

Date: 7 March 2014. Dear Colleagues, White label providers Call for evidence

Date: 7 March 2014. Dear Colleagues, White label providers Call for evidence To: Domestic and non-domestic suppliers, white label providers, consumers, consumer organisations, academics and other interested parties Direct Dial: 0207 901 0533 Email: white.labels@ofgem.gov.uk Dear

More information

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010 Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010 This report has been prepared on the basis of the limitations set out on page 16. Contents Page

More information

PUBLIC G5 - Supplier CFD Credit Cover. EMRS Guidance

PUBLIC G5 - Supplier CFD Credit Cover. EMRS Guidance PUBLIC G5 - Supplier CFD Credit Cover EMR Settlement Ltd Version 2.0 25 November 2015 CONTENTS Amendment Record 3 1. Introduction 4 2. Purpose 4 3. Who is this document for? 4 4. Associated documents 4

More information

REQUEST FOR MAYORAL DECISION MD405. Title: Disaster Recovery Services

REQUEST FOR MAYORAL DECISION MD405. Title: Disaster Recovery Services REQUEST FOR MAYORAL DECISION MD405 Title: Disaster Recovery Services Executive Summary: In May 2006, the GLA entered into an agreement with a recovery partner to offer immediate replacement IT equipment

More information

Competition. Quick reference guides and checklists for: Retailers Wholesalers Currently Integrated Businesses

Competition. Quick reference guides and checklists for: Retailers Wholesalers Currently Integrated Businesses Quick reference guides and checklists for: Retailers Wholesalers Currently Integrated es About Ascendancy Water At Ascendancy we believe that the best way to develop a competitive advantage is to be totally

More information

Accessing finance. Developing a business case for your resource efficiency projects

Accessing finance. Developing a business case for your resource efficiency projects Accessing finance Developing a business case for your resource efficiency projects Developing a business case for your resource efficiency projects 2 Contents 1 Planning a resource efficiency project?

More information

Cabinet Member Finance and Resources. Procurement of Electricity and Gas Supplies

Cabinet Member Finance and Resources. Procurement of Electricity and Gas Supplies Cabinet Member Finance and Resources Procurement of Electricity and Gas Supplies Report by Executive Director Customers and Change Ref No. FR07(11/12) Key Decision Yes Part I Electoral Division N/A Executive

More information

CHESHIRE FIRE AUTHORITY SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM TERM FINANCIAL PLAN

CHESHIRE FIRE AUTHORITY SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM TERM FINANCIAL PLAN CHESHIRE FIRE AUTHORITY Item 2 ITEM: 2 MEETING OF : FIRE AUTHORITY DATE : 12 FEBRUARY 2014 REPORT OF : CHIEF FIRE OFFICER AUTHOR : HEAD OF FINANCE SUBJECT : 2014-15 DRAFT BUDGET, COUNCIL TAX AND MEDIUM

More information

Code of practice for accurate bills

Code of practice for accurate bills Code of practice for accurate bills Version: January 2015 Contents Definitions 3 Introduction 4 Switching 6 Meter reading 7 Energy bills and statements 8 Payments and refunds 9 Back billing 10 2 Billing

More information

CABINET. 24 April 2012. Title: Term Contract for Maintenance, Repair and Minor Works on Security and Protection Systems

CABINET. 24 April 2012. Title: Term Contract for Maintenance, Repair and Minor Works on Security and Protection Systems CABINET 24 April 2012 Title: Term Contract for Maintenance, Repair and Minor Works on Security and Protection Systems Report of the Cabinet Member for Finance and Education Open Report Wards Affected:

More information

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS

PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS HEAD OF WASTE STRATEGY AND CONTRACTS NORTH LONDON WASTE AUTHORITY Agenda Item No: REPORT TITLE: PROCUREMENT PROGRAMME PROCUREMENT OF CONSULTANTS REPORT OF: HEAD OF WASTE STRATEGY AND CONTRACTS FOR SUBMISSION TO: DATE: AUTHORITY MEETING 11

More information

Operation of electricity meters when energy flowing in reverse

Operation of electricity meters when energy flowing in reverse Title: Operation of electricity meters when energy flowing in reverse Synopsis: To document the impact of reverse energy flow of whole current import electricity meters Date: 20 th August 2013 Prepared

More information

INFORMATION FOR OBSERVERS. Project: IAS 39 and Business Combinations (Agenda Paper 7E)

INFORMATION FOR OBSERVERS. Project: IAS 39 and Business Combinations (Agenda Paper 7E) 30 Cannon Street, London EC4M 6XH, United Kingdom Tel: +44 (0)20 7246 6410 Fax: +44 (0)20 7246 6411 E-mail: iasb@iasb.org Website: www.iasb.org International Accounting Standards Board This observer note

More information

Contract for Difference for non-uk Renewable Electricity Projects

Contract for Difference for non-uk Renewable Electricity Projects Contract for Difference for non-uk Renewable Electricity Projects August 2014 Crown copyright 2014 URN 14D/291 You may re-use this information (not including logos) free of charge in any format or medium,

More information

BANKING SUPERVISION UNIT

BANKING SUPERVISION UNIT BANKING SUPERVISION UNIT POLICY DOCUMENTS POLICY DOCUMENT ON THE REGULATORY PROVISIONS FOR THE UNDERTAKING OF FINANCIAL LEASING ACTIVITIES BY INSTITUTIONS AUTHORISED UNDER THE FINANCIAL INSTITUTIONS ACT

More information

Conditions means the standard terms and conditions set out in this document;

Conditions means the standard terms and conditions set out in this document; October 2014 Conditions of Supply for Electricity SME Business Customers These are our terms and conditions which are applicable to Commercial Customers with tariffs in Duos Group DG1, DG2, DG 5 or DG

More information

GUIDANCE ON PERFORMING AUDITS ON BEHALF OF THE AGSA

GUIDANCE ON PERFORMING AUDITS ON BEHALF OF THE AGSA Proposed Guide September 2013 Comments due: 31 October 2013 Proposed Guide for Registered Auditors GUIDANCE ON PERFORMING AUDITS ON BEHALF OF THE AGSA REQUEST FOR COMMENTS REQUEST FOR COMMENTS The Committee

More information

WATFORD BOROUGH COUNCIL PROCUREMENT RECOMMENDATION SUBMITTED BY: TRICIA TAYLOR - CORPORATE DIRECTOR

WATFORD BOROUGH COUNCIL PROCUREMENT RECOMMENDATION SUBMITTED BY: TRICIA TAYLOR - CORPORATE DIRECTOR WATFORD BOROUGH COUNCIL PROCUREMENT RECOMMENDATION TO: CORPORATE MANAGEMENT BOARD SUBMITTED BY: TRICIA TAYLOR - CORPORATE DIRECTOR REQUIREMENT: INTEGRATED HR SYSTEMS WITH PAYROLL DATE: 11 November 2008

More information

Electricity prices explained

Electricity prices explained e-guide Electricity prices explained For large business customers 2/5 Electricity prices explained Information for business customers Electricity suppliers are the public face of the electricity industry.

More information

Korea Electric Power Corporation

Korea Electric Power Corporation Korea Electric Power Corporation Response to Rate Regulation Standard Setting - Request for Information 2013. 5.31 [Question 1] For the types of rate regulation that you think would be useful for us to

More information

Ofgem s approach to smart metering

Ofgem s approach to smart metering Ofgem s approach to smart metering Philip Davies Director of Retail Markets and Environmental Policy Cambridge Conference Pg 1 Agenda Why smart metering? Experience to date with competition The smart meter

More information

Grant Programme Guidelines Community Development Grants Programme

Grant Programme Guidelines Community Development Grants Programme Grant Programme Guidelines Community Development Grants Programme Community Development Grants Programme Guidelines Contents Process Flowchart... 3 1. Introduction... 4 1.1. Programme Background... 4 1.2.

More information

Code of Conduct for Marketing Retail Energy in Victoria

Code of Conduct for Marketing Retail Energy in Victoria Code of Conduct for Marketing Retail Energy in Victoria January 2009 TABLE OF CONTENTS Page INTRODUCTION...1 1. MARKETING REPRESENTATIVES - TRAINING...3 2. CONTACT WITH CONSUMERS...4 2.1 Personal contact...4

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information