COLLECTING YOUR MONEY THROUGH MECHANIC S LIENS, STOP NOTICES & BONDS
|
|
- Miles Henry
- 8 years ago
- Views:
Transcription
1 COLLECTING YOUR MONEY THROUGH MECHANIC S LIENS, STOP NOTICES & BONDS A Presentation for THE HUMBOLDT BUILDERS EXCHANGE, INC. April 22, 2015 By: Kenneth S. Grossbart Abdulaziz, Grossbart & Rudman P.O. Box North Hollywood, CA (818) info@agrlaw.com website: Abdulaziz, Grossbart & Rudman has been practicing construction law for 30 years. The California Construction Law book is published and updated annually. They represent numerous construction trade associations and contractors. Abdulaziz, Grossbart & Rudman appears at Contractors State License Board meetings and has argued a number of cases before the appellate courts, including the California Supreme Court dealing with the "Pay-If-Paid Clause." Abdulaziz, Grossbart & Rudman provides this information as a service to its friends & clients. The documents are of a general nature and are intended to highlight areas of the subject matter and should not be used as a substitute for specific legal advice. You should seek the aid and advice of a competent attorney and/or accountant instead of relying on the presentation and/or documents. Abdulaziz, Grossbart & Rudman can be reached at, P.O. Box 15458, North Hollywood, CA ; (818) , Facsimile (818) ; or by at info@agrlaw.com. On the Internet, visit our Website at
2 Collecting Your Money -- Mechanic s Liens, PRIVATE WORKS MECHANIC S LIEN, STOP PAYMENT NOTICE AND BOND CHECKLIST I. WHAT IS A MECHANIC S LIEN? A. A Mechanic s Lien is a lien on real estate that has been improved. B. It is fairly well accepted that the right to a Mechanic s Lien is protected by the California Constitution. The California Law Revision Commission completed an extensive study where the right to a lien was left untouched, but the procedural requirements were all streamlined. SB 189 addressed these minimal changes. C. A Mechanic s Lien cannot be used on public works of improvement, and as a result, the Legislature created Stop Payment Notice and Bond rights. II. WHO IS ENTITLED TO A LIEN? A. Essentially, anyone who contributes to a private work of improvement is entitled to a lien. For example, licensed contractors, subcontractors, workers working for contractors or subcontractors, people who supply material to a contractor or subcontractor, as well as people who rent equipment. B. There are times where there may be no entitlement to a Mechanic s Lien. For instance, supplied materials that were not consumed on the project or do not become a part of the permanent structure cannot be included in a Mechanic s Lien. A contractor who was required to be licensed but was unlicensed at any time during the project, may not be able to collect utilizing the Mechanic s Lien process. Others not entitled to record a Mechanic s Lien include suppliers to material suppliers, but even there, the courts have created limited exceptions. III. WHAT IS A STOP PAYMENT NOTICE ON PRIVATE WORKS? A. While a Mechanic s Lien is a lien on real estate, a Stop Payment Notice is a lien on construction funds. A Stop Payment Notice is also called a Notice to Withhold. Instead of encumbering real property, it ties up the construction funds for a project. Page 1
3 Collecting Your Money -- Mechanic s Liens, B. One court has held that a Stop Payment Notice is a substitute for a Mechanic s Lien and therefore also constitutionally protected. IV. BENEFITS AND DETRIMENTS OF A STOP PAYMENT NOTICE: A. While a Mechanic s Lien attaches to real estate, it does not physically affect the work of improvement. A Stop Payment Notice has an immediate effect in that it keeps money designated for construction from being paid to anyone. This is even before a suit is filed. B. A bonded Stop Payment Notice allows for attorneys fees to the prevailing party. A Mechanic s Lien does not. C. A Stop Payment Notice will survive a foreclosure and is an important tool in a tough economy. D. If the holder of the construction funds is a lender, you will have to put up a bond with the lender. A construction lender on private works may ignore an unbonded Stop Payment Notice. E. Any person who fails to serve a Stop Payment Notice after the owner makes a written demand therefore will forfeit its right to a Mechanic s Lien. V. WHO IS ENTITLED TO A STOP PAYMENT NOTICE? A. If the holder of the construction funds is a construction lender, which includes an escrow and others as set forth in the statutes defining a construction lender, then everyone who is entitled to enforce a Mechanic s Lien is also entitled to enforce a Bonded Stop Payment Notice. B. If the holder of the construction funds is the owner, then everyone who is entitled to enforce a Mechanic s Lien, other than the direct contractor, is entitled to enforce a Stop Payment Notice. C. There are instances where there may be no entitlement to a Stop Payment Notice. For instance, supplied materials that were not consumed on the project or become a part of the permanent structure cannot be included in a Stop Payment Notice. A contractor who was required to be licensed but was unlicensed at any time during the project, may not be able to collect utilizing a Stop Payment Notice. Others not entitled to enforce a Stop Payment Notice usually include suppliers to material suppliers. Page 2
4 Collecting Your Money -- Mechanic s Liens, VI. PRELIMINARY TO STARTING: Get as much information as possible!!! These determinations will save you money in the long run, should a dispute arise. A. Obtain the address, legal description of the property (map book and page number, etc.) and assessor s parcel number. B. Obtain the home and business address of the owner and the customer if the customer is not the owner. C. Determine the name of the owner and the extent of the owner s interest in the property. D. Determine whether the owner is the one who is requesting the improvement. If not, what is the interest of the person requesting it and are there any others who claim an interest in the property (lenders, etc.)? E. Determine whether you are a direct contractor, subcontractor, laborer or material supplier. F. Ascertain the name of the construction lender, holder of construction funds, and payment bond surety (if any). Do a public records check if told there is no lender on a larger project, or to confirm the identity on a larger project. G. Consider the effect of a bond or joint control. H. When entering into a Home Improvement Contract or a New Residential Contract, a Mechanic s Lien Warning is required to be either a part of the contract or incorporated into the contract as an attachment. Make sure you include this as well as comply with other contract requirements so that you do not lose your rights. VII. ONCE WORK STARTS: A. Within twenty (20) days of first furnishing labor or materials: 1. Preliminary Notice: A Preliminary Notice is intended to notify owners, lenders, and contractors that someone has a right to enforce a Mechanic s Lien or Stop Payment Notice and allows the owner to protect itself from the possible collection remedy. Subcontractors and material suppliers need to send out a Preliminary Notice to the owner, direct contractor, and construction lender or holder of construction funds (if any). Contractors working for an owner/builder shall send out a Preliminary Notice to the construction lender or holder of construction funds (if any). This is so important that if Page 3
5 Collecting Your Money -- Mechanic s Liens, you are told there is no lender, you should check public records and the building permit for the existence of a lender. For purposes of collecting on a payment bond, all parties should serve the bonding company as well. No matter how many deliveries you make, or the time span over which you furnish labor or materials, only one Preliminary Notice is required, unless the project is suspended. However, if you furnish materials or services under separate contracts or with more than one contractor or subcontractor, you must furnish a separate Notice for each subcontractor. Please note that SB 189 made changes to the Preliminary Notice form, specifically to the Notice To Owner language that is required on the Preliminary Notice of private works of improvements. For the specific text of the new language required in the Notice To Owner please see the sample Preliminary Notices at the back of your handout. We have also included some other forms that may be of interest to you. If a preliminary notice is given by a subcontractor that has not paid all compensation due to a laborer, the notice shall include the name and address of the laborer and any person or entity described in Civil Code Section 8202(b) to which payments are due. 2. Service: The most common method of service is by first-class certified or registered mail, return receipt requested, postage prepaid, addressed to the residence or place of business of the person being served, or at the address shown by the building permit, or at an address contained on a recorded mortgage or trust deed. Be sure to keep post office receipts for later use if you need to file a claim and prove it in court. A Preliminary Notice also may be served by personal delivery or by leaving it with some person in charge at the residence or place of business of the person you wish to serve (must be an adult). We strongly recommend serving a Preliminary Notice at the time that the contract for work on a project is entered into. There can never be an argument that a Preliminary Notice was served too early. On the other hand, a Preliminary Notice never relates back more than twenty (20) days and due to the changes in the legislation of SB 189 (effective July 1, 2012), there are some fears with respect to Civil Code section 8116(b), which refers to a Code of Civil Procedure section pertaining to service by mail. At least one recognized source believes the Code section suggests that you must give an additional five (5) days notice due to the fact that the notice is being served by mail. The section in question pertains to litigation matters and gives additional time for a response when something is mailed rather than hand delivered. At least one other commentator has suggested that the effect of the legislation including a reference to Section 1013 of the Code of Civil Procedure, means that a Preliminary Notice must be served no more than fifteen (15) days after material is first delivered, or else it will only relate back fifteen (15) days when served by mail. While we are not sure that this necessarily applies, good business practice is to serve the Notice as quickly as possible to avoid any such argument. Page 4
6 Collecting Your Money -- Mechanic s Liens, 3. County Recorder: You may file/record a copy of the Preliminary Notice with the County Recorder so that they will notify you if a Notice of Completion or Notice of Cessation is recorded. Note that the County has no liability if they fail to notify you, which is highly possible since many County Recorders are very backlogged. VIII. IF YOU ARE A SUBCONTRACTOR OR MATERIAL SUPPLIER: If you are a contractor working for an owner/builder go to the section below called IF YOU ARE A DIRECT CONTRACTOR, otherwise follow the procedure below. A. After work is completed or work ceases: 1. Notice of Completion: a. The Notice of Completion shortens the time limit for recording a Mechanic s Lien and Stop Payment Notice to thirty (30) days after recordation of the Notice of Completion (for subcontractors and material suppliers). b. After completion of the work of improvement you should not do additional work under the contract. Warranty and punch list work can be performed. c. Within fifteen (15) days after completion an owner can record a Notice of Completion. (This changed on July 1, 2012, from 10 days). d. A Notice of Completion must be signed and verified by the owner or the owner s agent as well as be served per Civil Code sections and then be recorded. e. While this Notice provision is designed to primarily protect the owner, it might serve to increase the funds accessible to satisfy your claim, and indicate that you performed your contractual obligations. f. Except for residential home owners of dwellings fewer than five units, when an owner records a Notice of Completion, the owner must serve the direct contractor and all subcontractors or material suppliers who provided a Preliminary Notice, with Notice that it has recorded a Notice of Completion. Service of the owner s Notice must include a Proof of Service Affidavit in accordance with Civil Code section 8118 and be sent within ten (10) days of recordation, by registered or certified mail, return receipt requested, or by express mail, overnight delivery by an express service carrier, personally delivering copies or by leaving the notice and mailing a copy per Code of Civil Procedures section for the service of a Summons and Complaint in a civil action. If the owner fails to send the Notice to the lien claimants, then the normal 90-day period of time in which a Mechanic s Lien may be recorded will apply as discussed below. Again, this mailing requirement does not apply on typical residential projects. Page 5
7 Collecting Your Money -- Mechanic s Liens, 2. Notice of Cessation of Labor: a. Note that labor must have ceased for at least thirty (30) days before the owner is entitled to record the Notice of Cessation. b. The Notice of Cessation shortens the time limit for recording a Mechanic s Lien and Stop Payment Notice to thirty (30) days after recordation of the Notice of Cessation for subcontractors and material suppliers. c. A Notice of Cessation must be signed and verified by the owner or the owners agent as well as be served per Civil Code sections and then be recorded. d. While this Notice provision is designed to primarily protect the owner, it might serve to increase the funds accessible to satisfy your claim. e. Except for residential home owners of dwellings fewer than five units, when an owner records a Notice of Cessation of Labor, the owner must serve the direct contractor and all subcontractors or material suppliers who provided a Preliminary Notice, with Notice that it has recorded a Notice of Cessation of Labor. Service of the owner s Notice must include a Proof of Service Affidavit in accordance with Civil Code section 8118 and be sent within ten (10) days of recordation, by registered or certified mail, return receipt requested, or by express mail, overnight delivery by an express service carrier, personally delivering copies or by leaving the notice and mailing a copy per Code of Civil Procedures section for the service of a Summons and Complaint in a civil action. If the owner fails to send the Notice to the lien claimants, then the normal 90-day period of time in which a Mechanic s Lien may be recorded will apply as discussed below. Again, this mailing requirement does not apply on typical residential projects. 3. If the owner records either the Notice of Cessation or a Notice of Completion, the subcontractor or material supplier must: a. Within thirty (30) days of recording the Notices that shorten time: i. Record a Mechanic s Lien (or Claim of Lien) in the office of the County Recorder. (1) Make sure that your Mechanic s Lien form complies with the law. A Mechanic s Lien must include: (a) The amount demanded (the amount that is owed after all credits, off-sets, etc.). If the amount is a good faith demand, the exact accurateness will not invalidate the lien. However, an excessive lien (one that is not in good faith), will invalidate the lien. (b) The name of the owner or reputed owner. (c) A general statement of the labor, services, equipment, etc., furnished. Page 6
8 Collecting Your Money -- Mechanic s Liens, (d) A description of the property sufficient for identification. This is very important since it will not bind the property if it is not described specifically. (e) Signature and verification by the claimant. (f) Proof of service affidavit (described below). (g) As of January 1, 2011, a Mechanics Lien is required to have a Notice of Mechanic s Lien. The language of this Notice changed due to AB 456 and the language which is effective as of January 1, 2012, is as follows: NOTICE OF MECHANICS LIEN ATTENTION! Upon the recording of the enclosed MECHANICS LIEN with the county recorder s office of the county where the property is located, your property is subject to the filing of a legal action seeking a courtordered foreclosure sale of the real property on which the lien has been recorded. That legal action must be filed with the court no later than 90 days after the date the mechanics lien is recorded. The party identified in the mechanics lien may have provided labor or materials for improvements to your property and may not have been paid for these items. You are receiving this notice because it is a required step in filing a mechanics lien foreclosure action against your property. The foreclosure action will seek a sale of your property in order to pay for unpaid labor, materials, or improvements provided to your property. This may affect your ability to borrow against, refinance, or sell the property until the mechanics lien is released. BECAUSE THE LIEN AFFECTS YOUR PROPERTY, YOU MAY WISH TO SPEAK WITH YOUR CONTRACTOR IMMEDIATELY, OR CONTACT AN ATTORNEY, OR FOR MORE INFORMATION ON MECHANICS LIENS GO TO THE CONTRACTORS STATE LICENSE BOARD WEB SITE AT ii. Serve the owner: The Mechanic s Lien is also required to include a proof of service affidavit showing that the Mechanic s Lien has been mailed, by registered, certified, or first-class mail, with proof of mailing to: (1) The owner s residence or place of business; Page 7
9 Collecting Your Money -- Mechanic s Liens, (2) The address shown on the building permit on file with the building department; or (3) At any other address allowed under the Preliminary Notice statutes. This affidavit should indicate the name of the owner or reputed owner that is being served. If the owner cannot be served in this manner, then the construction lender or direct contractor can be served. If the lien is not served as required, it will be unenforceable as a matter of law. iii.serve Stop Payment Notices (see the section called STOP PAYMENT NOTICES for more information on Stop Payment Notices and bond requirements). b. File Lien Foreclosure action i. Within ninety (90) days of recording the Mechanic s Lien (Claim of Lien) a lien foreclosure action must be filed. If no suit is filed within that 90 day time period, the lien is void. (1) If you want more than ninety (90) days in which to foreclose, then after recording a lien, but before ninety (90) days elapses, give credit to the owner and record a notice of the fact and terms of credit, usually called a Notice of Extension of Credit. The statute that describes the Notice of Extension of Credit was not clear as to who must execute the Notice of Extension of Credit. At least one prominent construction commentator was of the opinion that a contractor could unilaterally extend credit by recording the Notice. However, effective July 1, 2012, when the revised Civil Code enacted by SB 189 went into effect, Civil Code section 8460 provides explicitly that both the contractor and owner must sign the Notice of Extension of Credit. This makes perfect sense how can one extend credit without agreeing to it? The Notice of Extension of Credit must specify exactly how much additional time to file suit to foreclose is being granted, and all of the signatures of the owner and contractor must be notarized before recording the document. Per Civil Code section 8460, a Notice of Extension of Credit must either be recorded within 90 days of the recording of the original Mechanic s Lien (when that lien would expire), or if recorded later than that time, it must be recorded before any purchaser or encumbrancer for value acquires rights (i.e., the property is transferred or sold, or a loan is recorded against the property). Page 8
10 Collecting Your Money -- Mechanic s Liens, Within ninety (90) days after your Notice of Extension of Credit expires, but no later than one (1) year from completion, you must file suit to foreclose. You can keep granting extensions by the above procedure, but you must file suit to foreclose within one (1) year after work is completed. ii. Record a Lis Pendens within twenty (20) days of filing the action. iii.file an action on the Stop Payment Notice at this time if applicable. (See the section called STOP PAYMENT NOTICES for more information). iv.a Mechanic s Lien action should be brought to trial within two (2) years after commencement or the court may dismiss the action. 4. If no Notice of Completion or Cessation is recorded and: a. The project is actually completed; or, b. Labor ceases and owner or agent uses work of improvement; or, c. Labor ceases for a continuous period of sixty (60) days; Then: i. Within ninety (90) days of any of the above acts, record a Mechanic s Lien (Claim of Lien) and serve Notice as required of the lien. ii. Also, within ninety (90) days of any of the above acts, serve a Stop Payment Notice (see the section called STOP PAYMENT NOTICES for more information). iii. Within ninety (90) days of recording the lien, file a lien foreclosure action. iv. Record a Lis Pendens within twenty (20) days of filing the lien foreclosure action. v. If you want more than ninety (90) days in which to foreclose, then after recording a lien, but before ninety (90) days elapses, give credit to the owner and record a Notice of the fact and terms of credit, usually called a Notice of Extension of Credit. The statute that describes the Notice of Extension of Credit was not clear as to who must execute the Notice of Extension of Credit. At least one prominent construction commentator was of the opinion that a contractor could unilaterally extend credit by recording the Notice. However, effective July 1, 2012, when the revised Civil Code, enacted by SB 189 went into effect, Civil Page 9
11 Collecting Your Money -- Mechanic s Liens, Code section 8460 provides explicitly that both the contractor and owner must sign the Notice of Extension of Credit. This makes perfect sense how can one extend credit without agreeing to it? The Notice of Extension of Credit must specify exactly how much additional time to file suit to foreclose is being granted, and all of the signatures of the owner and contractor must be notarized before recording the document. Per Civil Code section 8460, a Notice of Extension of Credit must either be recorded within 90 days of the recording of the original Mechanic s Lien (when that lien would expire), or if recorded later than that time, it must be recorded before any purchaser or encumbrancer for value acquires rights (i.e., the property is transferred or sold, or a loan is recorded against the property). Within ninety (90) days after your Notice of Extension of Credit expires, but no later than one (1) year from completion, you must file suit to foreclose. You can keep granting extensions by the above procedure, but you must file suit to foreclose within one (1) year after work is completed. IX. IF YOU ARE A DIRECT CONTRACTOR: A. After work is completed or work ceases: 1. Notice of Completion: a. Within fifteen (15) days after completion you may wish to have a Notice of Completion recorded. (This changed on July 1, 2012, from 10 days). b. While this Notice provision is designed to primarily protect the owner, it might serve to increase the funds accessible to satisfy your claim and indicate that you have performed your contractual obligations. c. The Notice of Completion shortens the time limit for recording a Mechanic s Lien and Stop Payment Notice to sixty (60) days after recordation of the Notice of Completion (for direct contractors). d. A Notice of Completion must be signed and verified by the owner or the owner s agent as well as be recorded. e. Do not do additional work under the contract. f. If you are recording the Notice of Completion for the owner of residential housing of four units or less, you must serve a copy of the Notice of Completion on any lien claimants who served a Preliminary Notice by registered or certified first-class mail, return receipt requested. Page 10
12 Collecting Your Money -- Mechanic s Liens, g. If the owner is recording the Notice of Completion, the direct contractor as well as all subcontractors or material suppliers who provided a Preliminary Notice must provide notice that it has recorded a Notice of Completion. h. Except for residential home owners of dwellings fewer than five units, when an owner records a Notice of Completion, the owner must serve the direct contractor and all subcontractors or material suppliers who provided a Preliminary Notice, with Notice that it has recorded a Notice of Completion. Service of the owner s Notice must include a Proof of Service Affidavit in accordance with Civil Code section 8118 and be sent within ten (10) days of recordation, by registered or certified mail, return receipt requested, or by express mail, overnight delivery by an express service carrier, personally delivering copies or by leaving the notice and mailing a copy per Code of Civil Procedures section for the service of a Summons and Complaint in a civil action. If the owner fails to send the Notice to the lien claimants, then the normal 90-day period of time in which a Mechanic s Lien may be recorded will apply. However, it may be preferable to use the 60-day period so that you do not have to argue with the owner over the validity of their Notice of Completion. 2. Notice of Cessation of Labor: a. Note that labor must have ceased for at least thirty (30) days before the owner is entitled to record the Notice of Cessation. b. The Notice of Cessation shortens the time limit for recording a Mechanic s Lien and Stop Payment Notice to sixty (60) days after recordation of the Notice of Cessation for direct contractors. c. The Notice of Cessation must be signed and verified by the owner or the owner s agent as well as be served per Civil Code sections then be recorded. d. Except for residential home owners of dwellings fewer than five units, when an owner records a Notice of Cessation of Labor, the owner must serve the direct contractor and all subcontractors or material suppliers who provided a Preliminary Notice, with Notice that it has recorded a Notice of Cessation of Labor. Service of the owner s Notice must include a Proof of Service Affidavit in accordance with Civil Code section 8118 and be sent within ten (10) days of recordation, by registered or certified mail, return receipt requested, or by express mail, overnight delivery by an express service carrier, personally delivering copies or by leaving the notice and mailing a copy per Code of Civil Procedures section for the service of a Summons and Complaint in a civil action. If the owner fails to send the Notice to the lien claimants, then the normal 90-day period of time in which a Mechanic s Lien may be recorded will apply. However, it may be preferable to use the 60-day period so that you do not have to argue with the owner over the validity of their Notice of Cessation. Page 11
13 Collecting Your Money -- Mechanic s Liens, 3. If the owner records either the Notice of Cessation of Labor or a Notice of Completion, then: a. Within sixty (60) days of recording the Notices which shorten time: i. Record a Mechanic s Lien (or Claim of Lien) in the office of the County Recorder. (1) Make sure that your Mechanic s Lien form complies with the law. A Mechanic s Lien must include: (a) The amount demanded (the amount that is owed after all credits, off-sets, etc.). If the amount is a good faith demand, the exact accurateness will not invalidate the lien. However, an excessive lien (one that is not in good faith), will invalidate the lien. (b) The name of the owner or reputed owner. (c) A general statement of the labor, services, equipment, etc., furnished. (d) A description of the property sufficient for identification. This is very important since it will not bind the property if it is not described specifically. (e) Signature and verification by the claimant. (f) Proof of service affidavit (described below). (g) As of January 1, 2011, a Mechanic s Lien is required to have a Notice of Mechanics Lien. The language of this Notice changed due to AB 456 and the language which is effective as of January 1, 2012, is as follows: NOTICE OF MECHANICS LIEN ATTENTION! Upon the recording of the enclosed MECHANICS LIEN with the county recorder s office of the county where the property is located, your property is subject to the filing of a legal action seeking a courtordered foreclosure sale of the real property on which the lien has been recorded. That legal action must be filed with the court no later than 90 days after the date the mechanics lien is recorded. The party identified in the mechanics lien may have provided labor or materials for improvements to your property and may not have been paid for these items. You are receiving this notice because it is a required step in filing a mechanics lien foreclosure action against your property. The foreclosure action will seek a sale of your Page 12
14 Collecting Your Money -- Mechanic s Liens, property in order to pay for unpaid labor, materials, or improvements provided to your property. This may affect your ability to borrow against, refinance, or sell the property until the mechanics lien is released. BECAUSE THE LIEN AFFECTS YOUR PROPERTY, YOU MAY WISH TO SPEAK WITH YOUR CONTRACTOR IMMEDIATELY, OR CONTACT AN ATTORNEY, OR FOR MORE INFORMATION ON MECHANICS LIENS GO TO THE CONTRACTORS STATE LICENSE BOARD WEB SITE AT ii. Serve the owner: The Mechanic s Lien is also required to include a proof of service affidavit showing that the Mechanic s Lien has been mailed, by registered, certified, or first-class mail, with proof of mailing to: (1) The owner s residence or place of business; (2) The address shown on the building permit on file with the building department; or (3) At any other address allowed under the Preliminary Notice statutes. This affidavit should indicate the name of the owner or reputed owner that is being served. If the owner cannot be served in this manner, then the construction lender or direct contractor can be served. If the lien is not served as required, it will be unenforceable as a matter of law. iii.serve Bonded Stop Payment Notices if there is a construction lender (see the section called STOP PAYMENT NOTICES for more information). iv.file Lien Foreclosure action: (1) Within ninety (90) days of recording the Mechanic s Lien or Claim of Lien, a lien foreclosure action must be filed. If no suit is filed within that 90 day time period, the lien is void. (a) If you want more than ninety (90) days in which to foreclose, then after recording a lien, but before ninety (90) days elapses, give credit to the owner and record a Notice of the fact and terms of credit, usually called a Notice of Extension of Credit. Page 13
15 Collecting Your Money -- Mechanic s Liens, The statute that describes the Notice of Extension of Credit was not clear as to who must execute the Notice of Extension of Credit. At least one prominent construction commentator was of the opinion that a contractor could unilaterally extend credit by recording the notice. However, effective July 1, 2012, when the revised Civil Code enacted by SB 189 went into effect, Civil Code section 8460 provides explicitly that both the contractor and owner must sign the Notice of Extension of Credit. This makes perfect sense how can one extend credit without agreeing to it? The Notice of Extension of Credit must specify exactly how much additional time to file suit to foreclose is being granted, and all of the signatures of the owner and contractor must be notarized before recording the document. Per Civil Code section 8460, a Notice of Extension of Credit must either be recorded within 90 days of the recording of the original Mechanic s Lien (when that lien would expire), or if recorded later than that time, it must be recorded before any purchaser or encumbrancer for value acquires rights (i.e., the property is transferred or sold, or a loan is recorded against the property). Within ninety (90) days after the Notice of Extension of Credit expires, but no later than one (1) year from completion, you must file suit to foreclose. You can keep granting extensions by the above procedure, but you must file suit to foreclose within one (1) year after work is completed. (b) Record a Lis Pendens within twenty (20) days of filing the action. (c) File an action on the Stop Payment Notice at this time, if applicable. (See the section called STOP PAYMENT NOTICES for more information). (d) A Mechanic s Lien action should be brought to trial within two (2) years after commencement or the court may dismiss the action. B. If no Notice of Completion or Cessation is recorded, and: Then: 1. The project is actually completed; or, 2. Labor ceases and owner or agent uses the work of improvement; or, 3. Labor ceases for a continuous period of sixty (60) days, a. Within ninety (90) days of any of the above acts, record a Mechanic s Lien (Claim of Lien) and serve Notice as required of the lien. You can also serve a bonded Stop Payment Notice on the construction lender at the same time, if applicable. Page 14
16 Collecting Your Money -- Mechanic s Liens, b. Within ninety (90) days of recording the lien, file a lien foreclosure action. c. Record a Lis Pendens within twenty (20) days of filing the action. d. You should also include an action to foreclose on the Stop Payment Notice, if applicable. e. If you want more than ninety (90) days in which to foreclose, then after recording a lien, but before ninety (90) days elapses, give credit to the owner and record a Notice of the fact and terms of credit, usually called a Notice of Extension of Credit. The statute that describes the Notice of Extension of Credit was not clear as to who must execute the Notice of Extension of Credit. At least one prominent construction commentator was of the opinion that a contractor could unilaterally extend credit by recording the Notice. However, effective July 1, 2012, when the revised Civil Code enacted by SB 189 went into effect, Civil Code section 8460 provides explicitly that both the contractor and owner must sign the Notice of Extension of Credit. This makes perfect sense how can one extend credit without agreeing to it? The Notice of Extension of Credit must specify exactly how much additional time to file suit to foreclose is being granted, and all of the signatures of the owner and contractor must be notarized before recording the document. Per Civil Code section 8460, a Notice of Extension of Credit must either be recorded within 90 days of the recording of the original Mechanic s Lien (when that lien would expire), or if recorded later than that time, it must be recorded before any purchaser or encumbrancer for value acquires rights (i.e., the property is transferred or sold, or a loan is recorded against the property). Within ninety (90) days after your Notice of Extension of Credit expires, but no later than one (1) year from completion, you must file suit to foreclose. You can keep granting extensions by the above procedure, but you must file suit to foreclose within one (1) year after work is completed. X. STOP PAYMENT NOTICES: A. Preliminary Notice 1. If not a direct contractor, serve the Preliminary Notice as described above in the subsection called Preliminary Notice. 2. In order to protect Stop Payment Notice rights it is a must to give a Preliminary Notice if your contract is with anyone other than the owner of the property and you must always serve a Preliminary Notice on a construction lender. Page 15
17 Collecting Your Money -- Mechanic s Liens, 3. The failure to give the notice on time will not preclude one from asserting Stop Payment Notice rights for the period of twenty (20) days prior to the service of the Preliminary Notice and forward. B. Contents 1. Must be addressed to the directing body of the public entity. 2. Claimant s name, address and capacity. 3. What was furnished. 4. Value of what was agreed to be furnished. 5. Location of public work. 6. Identification of work. 7. How much claimant wants withheld. 8. Verification. C. Serve Stop Payment Notice 1. On anyone who is holding construction funds; the owner, a lender, a fund control company, etc. 2. If it is a construction lender, you must also serve a bond (which makes it a Bonded Stop Payment Notice) in order for it to be effective. 3. If an unbonded Stop Payment Notice is served on the lender, the lender may not withhold the amount claimed and has no obligation to do so. D. If a payment bond was recorded, the owner or lender may refuse to withhold funds pursuant to the Stop Payment Notice. E. File suit on the Stop Payment Notice at the same time that you file a lien foreclosure action or within ninety (90) days after the end of the time when a Stop Payment Notice could be served. F. Any person who fails to serve a Stop Payment Notice after the owner makes a written demand therefore will forfeit its right to a Mechanic s Lien. Page 16
18 Collecting Your Money -- Mechanic s Liens, XI. FILING SUIT ON PAYMENT BOND, IF APPLICABLE: This is only applicable to subcontractors and material suppliers. direct contractors, under contract with the owner, cannot file suit to recover on a payment or performance bond. A. If the Preliminary Notice is served as indicated in the subsection called Preliminary Notice, this will be sufficient notice to the bonding company. With respect to a claim against the bond: The safest course of conduct would be to serve the bonding company with the appropriate Bond Notice regardless of whether you have already served the Preliminary Notice. You can never go wrong by providing too much notice, but you can certainly put yourself in potential harm for failure to give proper or timely notice. The statute that discusses the appropriate notices to be given on a private works project indicate that in order to enforce a claim upon any payment bond given in connection with a private work, a claimant needs to give the Private Works Preliminary Bond Notice as provided in Civil Code section Section 8200 does not list the payment bond surety as one of those to be served with the Preliminary Notice. B. If you did not give the Preliminary Notice indicated above, you may still have a possibility of a bond claim but recent legislation limits these claims. To be safe, you must serve written notice on the bonding company within fifteen (15) days after recordation of a Notice of Completion. If no Notice of Completion is recorded, this time is extended to seventy-five (75) days after completion. The Legislature passed another change in the Mechanic s Lien Law scheme at the urging of direct contractors and their sureties, which eliminates the second bite of the apple Bond Notice that applies when someone fails to serve a preliminary notice in certain cases. About twenty years ago, the Legislature created another notice that can be given to a bond surety where a Preliminary Notice was not given, which would allow a claimant to go forward on a bond claim. Indeed, in some cases, using this process, someone may have a bond claim even if they do not have a Stop Payment Notice claim and never served a Preliminary Notice. The 2012 legislation eliminates the ability to serve a Notice to Surety in the instance where the contractor that did not pay the claimant was paid. What is not clarified by the statute is what level of contractor needs to be paid. As an example, if the direct contractor pays the subcontractor, but the subcontractor does not pay its subsubcontractor, can the material supplier to the sub-subcontractor make a bond claim using this process? The direct contractor will certainly argue that he paid for the work. Since it is its bond surety, that argument would likely fly with some courts. The statute is vague, but it was intended to exclude the right where the direct contractor paid is subcontractor for the work in question. Page 17
19 Collecting Your Money -- Mechanic s Liens, C. You should then file your lawsuit on the surety before the expiration of six (6) months after the completion of the project. If you are filing suit on a Stop Payment Notice or Mechanic s Lien, you will likely sue on all claims within the shorter ninety (90) day period. XII. DESIGN PROFESSIONALS LIEN: A. This is a special type of lien for design professionals. The design professionals listed in the statute are, licensed architects, registered professional engineers and licensed land surveyors, and (per SB 189 effective 7/1/12), licensed landscape architects also have the design professional lien available to them. B. Must have a written contract with owner. C. Lien may not be recorded unless a building permit or other governmental approval in furtherance of the work of improvement has been obtained based on the particular design professional s work. D. In order for a design professional to be entitled to a lien, the following conditions must be met: 1. The work of improvement for which the design professional provided services has not commenced. 2. The landowner defaults in a payment required under the contract or refuses to pay the demand of the design professional made under the contract. 3. Not less than 10 days before recording a claim of lien, the design professional gives the landowner notice making a demand for payment, and stating that a default has occurred under the contract and the amount of the default. 4. The claim of lien shall include all of the following information: a. The name of the design professional. b. The amount of the claim of lien. c. The current owner of record of the site. d. A legal description of the site. e. Identification of the building permit or other governmental approval for the work of improvement. Page 18
20 Collecting Your Money -- Mechanic s Liens, E. The lien must be recorded no later than ninety (90) days after the design professional knows that the work of improvement will not commence, if applicable. F. This lien expires when work begins or within ninety (90) days after recording the claim of lien. In the case of commencement of work, the design professionals can then utilize the traditional lien. G. Such a lien is not allowed on single-family residences where construction costs are under $100, in value. H. A design professional may convert a recorded design professional lien to a Mechanic s Lien if all of the following requirements are met (per SB 424, effective 7/1/12): 1. The design professional lien expires according to Civil Code section 8306(b)(1) which states that the lien expires upon the commencement of the work of improvement for which the design professional provided services on. 2. The design professional lien remains fully or partially unpaid. 3. Within thirty (30) days of the expiration of the design professional lien the design professional records a Mechanic s Lien for the amount of the unpaid design professional lien. 4. The recorded Mechanic s Lien states that it is a converted design professional lien but shall be recorded and enforced as a Mechanic s Lien, except that the design professional need not provide a Preliminary Notice to enforce the Mechanic s Lien. 5. Note that this lien conversion will not apply if the design professional lien expires pursuant to Civil Code section 8306(b)(2) which states that the lien expires upon the expiration of ninety (90) days after recording the claim of lien, unless the design professional commences an action to enforce the lien with that ninety (90) day time period. As stated previously, you should become thoroughly familiar with procedures yourself and discuss them with a construction attorney prior to putting the checklist to work in your office. Abdulaziz, Grossbart & Rudman provides this information as a service to its friends & clients. It is of a general nature and should not be used as a substitute for specific research or consultation with construction counsel. The firm can be reached at Abdulaziz, Grossbart & Rudman. P.O. Box 15458, North Hollywood, CA ; (818) ; Facsimile (818) ; at info@agrlaw.com; Website Page 19
21 Collecting Your Money -- Mechanic s Liens, PUBLIC WORKS STOP PAYMENT NOTICE AND BOND CHECKLIST Direct contractors have no Stop Payment Notice or Bond Rights on California Public Works of Improvement. This checklist pertains only to material suppliers and subcontractors. I. PRELIMINARY TO STARTING: Get as much information as possible!!! These determinations will save you money in the long run, should a dispute arise. A. Obtain the address, legal description of the property (map book and page number, etc.) and assessor s parcel number. B. Determine the name of the contracting officer. C. Determine whether you are a direct contractor, subcontractor, laborer or material supplier. D. Get all information regarding the Payment Bond (name of bonding company, address of bonding company and bond number), get a copy of the bond if possible. II. PRELIMINARY NOTICE: A. Within twenty (20) days from first furnishing labor or materials: First tier subcontractors on Public Works do not have to send a Preliminary Notice. However, all other subcontractors and material suppliers shall send out a Preliminary Notice to the public entity and direct contractor. It is a good idea for all claimants to serve the bonding company as well. Remember first tier subcontractors are under contract with the direct contractor and therefore do not have to give a Preliminary Notice, except notice should be given to the payment bond surety by either a Preliminary Notice or by a Bond Notice within 15 days of the recording of a Notice of Completion or 75 days of actual completion. No matter how many deliveries you make, or the time span over which you furnish labor or materials, only one Preliminary Notice is required. If you furnish materials or services under separate contracts or with more than one contractor or subcontractor, you must furnish a separate Notice for each subcontractor. However, the amount stated on the Page 20
22 Collecting Your Money -- Mechanic s Liens, Preliminary Notice must have been a reasonable estimate of the labor or materials to be furnished, and must be based upon information provided to you. B. Service: The most common method of service is by first-class certified or registered mail, return receipt requested, postage prepaid, addressed to the residence or place of business of the person being served, or at the address shown by the building permit, or at an address contained on a recorded mortgage or trust deed. Be sure to keep post office receipts for later use if you need to file a claim and prove it in court. A Preliminary Notice also may be served by personal delivery or by leaving it with some person in charge at the residence or place of business of the person you wish to serve (must be an adult). We strongly recommend serving a Preliminary Notice at the time that the contract for work on a project is entered into. There can never be an argument that a Preliminary Notice was served too early. On the other hand, a Preliminary Notice never relates back more than twenty (20) days and due to the changes in the legislation of SB 189 (effective July 1, 2012), there are some fears with respect to Civil Code Section 8116(b), which refers to a Code of Civil Procedure section pertaining to service by mail. At least one recognized source believe the Code section suggests that you must give an additional five (5) days notice due to the fact that the notice is being served by mail. The section in question pertains to litigation matters and gives additional time for a response when something is mailed rather than hand delivered. At least one other commentator has suggested that the effect of the legislation including a reference to Section 1013 of the Code of Civil Procedure, means that a Preliminary Notice must be served no more than fifteen (15) days after material is first delivered, or else it will only relate back fifteen (15) days when served by mail. While we are not sure that this necessarily applies, good business practices are to serve the Notice as quickly as possible to avoid any such argument. The claimant can pay the governmental entity a fee ($10.00, increased by SB 189) at the time that the Stop Payment Notice is filed. This will cause the governmental entity to have to inform the claimant when a Notice of Completion or a Notice of Cessation is recorded. This is cheap insurance for the claimant to know when the Notices are recorded and collection rights begin. III. STOP PAYMENT NOTICE: A. Contents: 1. Must be addressed to the directing body of the public entity. 2. Claimants name, address and capacity. 3. What was furnished. Page 21
23 4. Value of what was agreed to be furnished. Collecting Your Money -- Mechanic s Liens, 5. Location of public work. 6. Identification of work. 7. How much claimant wants withheld. 8. Verification. B. If you are a subcontractor or material supplier: 1. If the owner files a Notice of Cessation of Labor, a Notice of Completion, or a Notice of Acceptance (NOTE: Labor must have ceased for at least thirty (30) days before the owner is entitled to record the Notice of Cessation), Then: Within thirty (30) days of recording of any of these notices, the subcontractor and material supplier must serve a Stop Payment Notice. 2. If no Notice of Completion, Notice of Acceptance, or Notice of Cessation is recorded and: a. The project is actually completed; or b. Labor ceases and owner or agent uses work of improvement; or c. Owner or agent accepts improvement; or d. Labor ceases for a continuous period of thirty (30) days, Then: Within ninety (90) days of any of the above acts, serve a Stop Payment Notice on the public agency. 3. You must file suit on the Stop Payment Notice within ninety (90) days of the time one would have to serve a Stop Payment Notice. 4. A Notice of Commencement of Action must be filed and served within five (5) days after filing the action. Page 22
MANAGING A BUSINESS California Mechanics Liens and Stop Notices Mechanics Liens. Stop Notices. Other Remedies. Procedure.
MANAGING A BUSINESS California Mechanics Liens and Stop Notices Mechanics Liens. In the State of California, mechanics liens are provided in the California Constitution. Article XIV, Section 3 of the California
More informationCALIFORNIA NEW MANDATORY NOTICE REQUIREMENTS FOR ENFORCEMENT OF MECHANIC S LIEN RIGHTS
CALIFORNIA NEW MANDATORY NOTICE REQUIREMENTS FOR ENFORCEMENT OF MECHANIC S LIEN RIGHTS Lisa Dal Gallo, Partner, LEED AP Hanson Bridgett, LLP John T. Lettieri, Managing Director Aon Construction Services
More informationA GUIDE TO MECHANIC'S LIENS IN MINNESOTA
MULLIGAN & BJORNNES PLLP Attorneys at Law 401 Groveland Avenue Minneapolis, MN 55403 (612) 871-1800 TABLE OF CONTENTS PAGE I. PRE-LIEN NOTICE REQUIREMENTS...3 A. CONTRACTOR PRE-LIEN NOTICE REQUIREMENTS...3
More informationSOUTH CAROLINA & NORTH CAROLINA, MECHANIC S LIEN AND PAYMENT BOND CLAIM MANUAL *
SOUTH CAROLINA & NORTH CAROLINA, MECHANIC S LIEN AND PAYMENT BOND CLAIM MANUAL * * This manual is for general reference only and should not be used without consultation with an attorney This manual is
More informationMechanic s Liens. Colorado Revised Statutes, Section 38-22-101
This handout is intended as general information only, and not as legal advice for any specific situation. If you have a legal problem, you may want to check with an attorney. What is a Mechanic s Lien?
More informationBy Donald A. Odell, Attorney at Law
All About Homes Light Commercial & Residential Inspection 24326 Mission Blvd., Suite 7 Hayward, CA 94544 www.allabouthomes.com Mechanic hanic s Liens Law and how it Applies to an Owner of Real Proper operty
More informationPe r f e c t i n g a. Ne va d a. Caryn S. Tijsseling. Prepared and Presented by. Lewis and Roca LLP 775-321-3426 CTijsseling@LRLaw.
Pe r f e c t i n g a Mechanic s Lien in Ne va d a Prepared and Presented by Caryn S. Tijsseling Lewis and Roca LLP 775-321-3426 CTijsseling@LRLaw.com Overview of Construction Liens The Nevada Revised Statutes
More informationHow To Get A Construction Contract In The United States
SOUTH CAROLINA LIEN AND BOND CLAIMS William ( Trey ) W. Watkins, Jr. 145 King Street, Suite 300 Charleston, SC 29401 843-329-9500 1 Introduction to Surety 3 Main differences between Insurance and Bonds
More informationSUMMARY OF MECHANICS LIEN LAW FOR CONNECTICUT. Reviewed Through 2011
SUMMARY OF MECHANICS LIEN LAW FOR CONNECTICUT Reviewed Through 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents
More informationThe 2012 Cardinal Change Order to California s Works of Improvement Statutes
The 2012 Cardinal Change Order to California s Works of Improvement Statutes Presented by Edward Lodgen edlodgen@rkmc.com Robins, Kaplan, Miller & Ciresi L.L.P. and Marilyn Klinger marilyn.klinger@sedgwicklaw.com
More informationCLAUSES REQUIRED ON ALL HOME IMPROVEMENT CONTRACTS ($500.00 on up)
CLAUSES REQUIRED ON ALL HOME IMPROVEMENT CONTRACTS ($500.00 on up) 1. The name, address and license number of the contractor, and the name and registration number of any salesperson who solicited or negotiated
More informationThe Top 10 Misconceptions About Mechanic s Liens
Engineering General Contractor s Association (EGCA) Seminar on Construction Law The Top 10 Misconceptions About Mechanic s Liens Tuesday, February 24, 2004 / 8:00 a.m. to 9:30 a.m. This seminar was delivered
More informationAssembly Bill No. 284 Assemblymen Conklin, Horne; and Kirkpatrick
Assembly Bill No. 284 Assemblymen Conklin, Horne; and Kirkpatrick CHAPTER... AN ACT relating to real property; revising provisions governing the recording of assignments of mortgages and deeds of trust;
More information8132. [Operative July 1, 2012] Conditional Waiver and Release in Exchange for Progress Payment; Form. If a claimant is required to execute a waiver
8132. [Operative July 1, 2012] Conditional Waiver and Release in Exchange for Progress Payment; Form. If a claimant is required to execute a waiver and release in exchange for, or in order to induce payment
More informationSOUTH CAROLINA MECHANIC S LIEN LAW With Changes Made in 2010. Section Contents Pre-lien Notice(s)
SOUTH CAROLINA MECHANIC S LIEN LAW With Changes Made in 2010 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic
More informationNC General Statutes - Chapter 44A Article 2 1
Article 2. Statutory Liens on Real Property. Part 1. Liens of Mechanics, Laborers, and Materialmen Dealing with Owner. 44A-7. Definitions. Unless the context otherwise requires, the following definitions
More informationOKLAHOMA MECHANICS LIEN LAW. With Changes in 2011. Section Contents Pre-lien Notice(s)
OKLAHOMA MECHANICS LIEN LAW With Changes in 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic s Lien Who
More informationReal Estate Finance: Arizona Clare H. Abel, Burch & Cracchiolo, P.A.
Real Estate Finance: Arizona Clare H. Abel, Burch & Cracchiolo, P.A. This Article is published by Practical Law Company on its PLC Real Estate web service at http://us.practicallaw.com/3-500-5703. A Q&A
More informationlegality and Practice - Design & Construction Lien
MILLER & STARR REAL ESTATE NEWSALERT Reprinted in part from Volume 17, Number 6 July 2007 (Article starting on page 377 in the actual issue) ARTICLE MECHANICS LIENS: PROPERTY LAW S UNLOVED STEPCHILD By
More information388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com ADDENDUM NO. 1
388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com May 6, 2015 To: All Plan Holders From: Vicki Morris General Manager Subject: Water Serviceline Installation
More informationWORK ORDER AND CONTRACT
WORK ORDER AND CONTRACT RE: Foundation Repairs Work Order# P2 SUBMITTED TO: Date 06/07/12 Amazing Real Estate 999 Madison Avenue Berkeley, Ca 94709 Email @.com Wk Ph# Cell /HmPh# 510- Job Address: Oakland,
More informationCHAPTER 32-19 FORECLOSURE OF REAL ESTATE MORTGAGES BY ACTION
CHAPTER 32-19 FORECLOSURE OF REAL ESTATE MORTGAGES BY ACTION 32-19-01. Action to foreclose mortgage on real estate authorized. The plaintiff shall bring an action in district court for the foreclosure
More informationIC 24-4.5-7 Chapter 7. Small Loans
IC 24-4.5-7 Chapter 7. Small Loans IC 24-4.5-7-101 Citation Sec. 101. This chapter shall be known and may be cited as Uniform Consumer Credit Code Small Loans. As added by P.L.38-2002, SEC.1. IC 24-4.5-7-102
More informationMake sure your builder is registered.
Marylanders purchase more than 10,000 new homes each year. The purchase of a new home is protected by Maryland law. Understanding your rights and responsibilities as a new home buyer protects your investment
More informationSUMMARY OF MECHANICS LIEN LAW FOR ARIZONA. With Changes for 2013
SUMMARY OF MECHANICS LIEN LAW FOR ARIZONA With Changes for 2013 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic
More informationCHICAGO TITLE INSURANCE COMPANY
CHICAGO TITLE INSURANCE COMPANY TOPIC: Condominium and Planned Community Assessments- Lien Priority Issues By: Mark Griffith State Underwriting Counsel, Chicago Title Insurance Company Homeowner association
More information2015 ARIZONA LEGISLATIVE AMENDMENTS AFFECTING REAL ESTATE LENDING (May 12, 2015 ACMLA meeting)
2015 ARIZONA LEGISLATIVE AMENDMENTS AFFECTING REAL ESTATE LENDING (May 12, 2015 ACMLA meeting) Following is a summary of legislative amendments enacted during the most recent session (the First Regular
More informationSURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.)
Performance Bond Document A312 2010 CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal status and address) CONSTRUCTION CONTRACT
More informationMechanics Liens WORK SET # 2. Provided by The CLTA Education Committee June, 2005
Mechanics Liens WORK SET # 2 Provided by The CLTA Education Committee June, 2005 California Land Title Association A Non-Profit Service Organization of Title Companies 1110 K Street, Suite 100, Sacramento,
More informationAIA Document A310 TM 2010
AIA Document A310 TM 2010 Bid Bond CONTRACTOR: OWNER: «Lane County» «125 East Eighth Avenue BOND AMOUNT: $ PROJECT: (Name, location or address, and Project number, if any) «Lane County Adult Corrections
More informationhttp://www.skokomish.org/skokconstitution&codes/codes/stc4-09.htm
Page 1 of 9 SKOKOMISH MORTGAGE LENDING, FORECLOSURE, AND EVICTION ORDINANCE Adopted by Resolution No. 03-48(April 30, 2003) TABLE OF CONTENTS GENERAL PROVISIONS 4.09.001 Purpose LIEN PRIORITY 4.09.010
More informationConstruction Law for California Contractors
Construction Law for California Contractors The Green Law Group, LLP 1777 E. Los Angeles Avenue Simi Valley, CA 93065 Phone: 805-306-1100 Fax: 805-306-1300 www.thegreenlawgroup.com 1 Introduction Knowledge
More informationSB 588. Employment: nonpayment of wages: Labor Commissioner: judgment enforcement.
SB 588. Employment: nonpayment of wages: Labor Commissioner: judgment enforcement. (1) The Enforcement of Judgments Law provides for the enforcement of money judgments and other civil judgments. Under
More informationCHAPTER 2013-137. Committee Substitute for Committee Substitute for House Bill No. 87
CHAPTER 2013-137 Committee Substitute for Committee Substitute for House Bill No. 87 An act relating to mortgage foreclosures; amending s. 95.11, F.S.; revising the limitations period for commencing an
More informationWHO CAN PULL A BUILDING PERMIT?
1685 Main Street, Room 111 (310) 458-8355 FAX (310) 396-6473 WHO CAN PULL A BUILDING PERMIT? PROPERTY OWNERS, STATE OF CALIFORNIA LICENSED CONTRACTORS OR AGENT FOR PROPERTY OWNER/CONTRACTOR (with correct
More informationOwner Builder Information, Notice to Property Owner & Owner Authorization
Owner Builder Information, Notice to Property Owner & Owner Authorization CSS-026 Purpose: Assembly Bill 2335, 2008 amended California Health and Safety Code, Section 19825, regarding disclosures and verifications
More informationSUMMARY OF MECHANICS LIEN LAW FOR FLORIDA. With Changes for 2013
SUMMARY OF MECHANICS LIEN LAW FOR FLORIDA With Changes for 2013 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic
More informationDocument A312 TM SURETY. (Name, legal status and principal place of business)
Payment Bond Document A312 TM 2010 CONTRACTOR: (Name, legal status and address) OWNER: (Name, legal status and address) CONSTRUCTION CONTRACT Date: Amount: $ Description: (Name and location) Uninterruptible
More informationCODING: Words stricken are deletions; words underlined are additions. hb0087-00
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 A bill to be entitled An act relating to mortgage foreclosures; amending s. 95.11, F.S.; revising the limitations period for commencing
More informationEQUITY SHARING AGREEMENT
EQUITY SHARING AGREEMENT This Equity Sharing Agreement (the Agreement ) is entered into as of the date set forth below by and between a California nonprofit corporation (the Church ), and (the Occupant
More informationKentucky Department of Education Version of Document A312 2010
Kentucky Department of Education Version of Document A312 2010 Performance Bond CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal
More informationStep One: Determining Whether Lien Rights are Available
ALABAMA LIEN LAW CHECKLIST This paper presents general information regarding the law of mechanic's liens in Alabama. It should not be construed as legal advice or legal opinion on any specific facts or
More informationSUMMARY OF MECHANICS LIEN LAW FOR THE DISTRICT OF COLUMBIA
SUMMARY OF MECHANICS LIEN LAW FOR THE DISTRICT OF COLUMBIA Section Contents Pre-lien Notice(s) Introduction Section Contents Mechanic s Lien Who is Entitled to a Lien? When to File/Record Where to File/Record
More informationBUYER'S DISCLOSURE STATEMENT
BUYER'S DISCLOSURE STATEMENT CITY OF WALNUT CREEK INCLUSIONARY HOUSING PROGRAM ADMINISTRATIVE COVER SHEET (Remove Upon Completion) BLANK LINES: CHECKLIST Eligible Purchaser Income Level, p. 3, Section
More informationCA Home Repair I Page 1
Home Improvement Contract This agreement is made on the date written above our signatures between Contractor Name: (Contractor) and Owner Name: (Owner). Contractor Any Notice of Cancellation can be sent
More informationMIGHTY MIKE PLUMBING, INC. PLUMBING GENERAL CONTRACTOR SERVICES PROPOSAL
MIGHTY MIKE PLUMBING, INC. PLUMBING GENERAL CONTRACTOR SERVICES PROPOSAL PROPOSAL: Proposal No./Date: Address of Property where Services are to be Performed: Name of Person on Whose Behalf Services are
More informationCalifornia Senate Bill 474 Impact on Owners & Contractors
California Senate Bill 474 Impact on Owners & Contractors Beginning January 1, 2013, project owners, general contractors ( GC ), construction managers ( CM ) and any lower tier contractor who employs subcontractors
More informationA Guide To Understanding The Community Association Collection And Foreclosure Process
A Guide To Understanding The Community Association Collection And Foreclosure Process What is the initial demand letter? What is a Claim of Lien? What is a thirty (30) day letter? How do you foreclose
More informationNevada Lien Statutes
108.221. Definitions Nevada Lien Statutes As used in NRS 108.221 to 108.246, inclusive, unless the context otherwise requires, the words and terms defined in NRS 108.22104 to 108.22188, inclusive, have
More informationAIA Document A312 - Electronic Format. Performance Bond
AIA Document A312 - Electronic Format Performance Bond THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION. AUTHENTICATION
More informationMISSISSIPPI LEGISLATURE REGULAR SESSION 2015
MISSISSIPPI LEGISLATURE REGULAR SESSION 2015 By: Senator(s) Horhn To: Accountability, Efficiency, Transparency SENATE BILL NO. 2638 1 AN ACT TO AMEND SECTION 31-5-51, MISSISSIPPI CODE OF 1972, TO 2 PROVIDE
More informationLIEN PERFECTION SERVICES AGREEMENT
LEVY VON BECK & A S S O C I A T E S, P. S. SANFORD R. LEVY ATTORNEYS AT LAW OFFICE MANAGER DAVID VON BECK* 600 University Street, Suite 3300 DOLORES EVANS CHARLES P. MORTIMER* Seattle, WA 98101 LEGAL ASSISTANTS
More informationGLOSSARY OF COLLECTION LAW TERMINOLOGY
GLOSSARY OF COLLECTION LAW TERMINOLOGY The purpose of this glossary is to assist community association board members and property managers in better understanding legal terms and procedures that are frequently
More informationSAMPLE LAND CONTRACT
This material is provided to answer general questions about the law in New York State. The information and forms were created to assist readers with general issues and not specific situations, and, as
More informationNC General Statutes - Chapter 44A Article 3 1
Article 3. Model Payment and Performance Bond. 44A-25. Definitions. Unless the context otherwise requires in this Article: (1) "Claimant" includes any individual, firm, partnership, association or corporation
More informationSUMMARY OF MECHANICS LIEN LAW FOR WISCONSIN. Revised Through 2011
SUMMARY OF MECHANICS LIEN LAW FOR WISCONSIN Revised Through 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic
More informationv. VERIFIED ANSWER TO FORECLOSURE COMPLAINT
SUPREME COURT OF THE STATE OF NEW YORK COUNTY OF v. Plaintiff, Index No. VERIFIED ANSWER TO FORECLOSURE COMPLAINT Defendant(s). Defendant answers as follows: I generally deny each allegation of the Complaint,
More informationIN THE CIRCUIT COURT OF THE THIRTEENTH JUDICIAL CIRCUIT IN AND FOR HILLSBOROUGH COUNTY, FLORIDA GENERAL CIVIL DIVISION
IN THE CIRCUIT COURT OF THE THIRTEENTH JUDICIAL CIRCUIT IN AND FOR HILLSBOROUGH COUNTY, FLORIDA GENERAL CIVIL DIVISION Plaintiff(s), v. Defendant(s). / CASE NO.: GENERAL CIVIL DIVISION: UNIFORM FINAL JUDGMENT
More informationBROKER AGREEMENT. NOW THEREFORE, in consideration of promises, covenants and agreements hereinafter contain, the parties agree as follows:
THIS AGREEMENT is entered into in the State of California this day of 2006, between Crestline Funding Corporation, hereinafter referred to as Crestline Funding, and, hereinafter referred to as Broker.
More informationILLINOIS MECHANIC S LIEN LAW With Changes for 2013. Section Contents Pre-lien Notice(s)
ILLINOIS MECHANIC S LIEN LAW With Changes for 2013 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic s Lien
More informationTOP 20 TITLE ISSUES In no particular order, here are brief summaries of the top 20 title issues that can arise in a real estate transaction: 1. Trusts 2. Power of Attorney 3. Death 4. Divorce 5. Foreclosure
More informationUNIVERSITY OF MINNESOTA
UNIVERSITY OF MINNESOTA Bond Number CONTRACTOR: «Vendor_Name» «Address_1» «Address_2» 00620PAY PAYMENT BOND SURETY (Name and Address as listed in the current Federal Register): OWNER: Regents of the University
More informationCalifornia Civil Code 2782.05
California Civil Code 2782.05 (a) Except as provided in subdivision (b), provisions, clauses, covenants, and agreements contained in, collateral to, or affecting any construction contract and amendments
More informationMarion County Board of County Commissioners
BUILDING PERMIT APPLICATION Permit number: Project number: ARN number: Date: Rep: Code: FBC Parcel number: Project address: Sec: Twp: Rge: Subdivision: Lot: Block: Unit: Property owner of record: Daytime
More informationDELINQUENT ASSESSMENT COLLECTION
Salvatori, Wood, & Buckel ATTORNEYS AT LAW 9132 Strada Place, Fourth Floor, Naples, FL 34108-2683 John D. Humphreville Tel: 239.552.4100 Direct Dial: 239.552.4107 Fax: 239.649.1706 jdh@swbnaples.com Web:
More informationCHAPTER 7 PUBLIC WORKS LAW
7-1 CHAPTER 7 PUBLIC WORKS LAW GENERAL PROVISIONS The "Public Works Law" [IC 36-1-12] applies to all public work performed or contracted by political subdivisions and their agencies. Any public work performed
More informationUsing a Mechanic s Lien to Get Your Money in Texas
Using a Mechanic s Lien to Get Your Money in Texas Prepared by Brian W. Erikson Quilling, Selander, Cummiskey & Lownds, P.C. Attorneys and Counselors 2001 Bryan Street, Suite 1800 Dallas, Texas 75201 Telephone:
More informationNEW JERSEY MECHANIC S LIEN LAW With Changes Made in 2011. Section Contents Pre-lien Notice(s)
NEW JERSEY MECHANIC S LIEN LAW With Changes Made in 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic s
More informationCHAPTER 2013-159. Committee Substitute for House Bill No. 7025
CHAPTER 2013-159 Committee Substitute for House Bill No. 7025 An act relating to timeshares; amending s. 718.112, F.S.; specifying that certain provisions relating to condominium board elections do not
More information2015 -- S 0581 SUBSTITUTE A ======== LC001375/SUB A ======== S T A T E O F R H O D E I S L A N D
0 -- S 01 SUBSTITUTE A LC00/SUB A S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 0 A N A C T RELATING TO PROPERTY -- MORTGAGE FORECLOSURE AND SALE Introduced By: Senators
More informationDEFERRED LOAN CLOSING COST ASSISTANCE GRANT AND MORTGAGE CREDIT CERTIFICATE PROGRAMS LENDER PARTICIPATION AGREEMENT
THIS AGREEMENT ( Agreement ) is made and entered into this day of, 20, by and between the San Diego Housing Commission, a public agency, ( SDHC ), and a ( Lender ). RECITALS A. SDHC has implemented a Closing
More informationOFFICE OF THE CITY ATTORNEY J. DELGADILLO CITY ATTORNEY REPORT RE:
OFFICE OF THE CITY ATTORNEY ROCKARD J. DELGADILLO CITY ATTORNEY REPORT RE: REPORT NO. R 0 9-0 12 6 il\pr t e ~ DRAFT ORDINANCE ADDING ARTICLE 7.2 TO CHAPTER IV OF THE LOS ANGELES MUNICIPAL CODE TO REGULATE
More informationCOMPENDIUM OF NEW JERSEY CONSTRUCTION LAW
COMPENDIUM OF NEW JERSEY CONSTRUCTION LAW Prepared by Connell Foley LLP USLAW NETWORK 5905 NW 54 th Circle Coral Springs, FL 33067 Phone/Fax (800) 231-9110 www.uslaw.org COMPENDIUM OF NEW JERSEY CONSTRUCTION
More informationAN ACT RELATING TO PROPERTY; ENACTING THE MORTGAGE FORECLOSURE CONSULTANT FRAUD PREVENTION ACT; IMPOSING PENALTIES.
AN ACT RELATING TO PROPERTY; ENACTING THE MORTGAGE FORECLOSURE CONSULTANT FRAUD PREVENTION ACT; IMPOSING PENALTIES. BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF NEW MEXICO: Section 1. SHORT TITLE.--This
More informationBond Form Commentary and Comparison
Bond Form Commentary and Comparison AIA Document A310 2010, Bid Bond, and AIA Document A312 2010, Performance Bond and Payment Bond INTRODUCTION Since the first publication of The Standard Form of Bond
More informationTo all Interval Owners:
To all Interval Owners: In September and October of 2010, the Massachusetts legislature and Governor Patrick approved major changes to Chapter 183B of the Massachusetts General Laws which substantially
More informationWARM SPRINGS TRIBAL CODE CHAPTER 206 REAL PROPERTY SECURED TRANSACTIONS. Table of Contents
WARM SPRINGS TRIBAL CODE CHAPTER 206 REAL PROPERTY SECURED TRANSACTIONS Table of Contents Page 206.001 Legislative History... 1 206.010 Tribal Court Jurisdiction... 1 206.015 Security Interests Created
More informationMARYLAND MECHANIC S LIEN LAW With Changes Made in 2011. Section Contents Pre-lien Notice(s)
MARYLAND MECHANIC S LIEN LAW With Changes Made in 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic s Lien
More informationMemorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information
Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document
More informationLIEN AND BOND CLAIM MANUAL
LIEN AND BOND CLAIM MANUAL John P. Ahlers Paul R. Cressman, Jr. AHLERS & CRESSMAN PLLC 999 Third Avenue, Suite 3800 Seattle, Washington 98104-4023 (206) 287-9900 info@ac-lawyers.com www.ac-lawyers.com/blogs.php
More information11 LC 14 0449ER A BILL TO BE ENTITLED AN ACT
House Bill 338 By: Representative Bryant of the 160 th A BILL TO BE ENTITLED AN ACT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 To amend Title 44 of the Official Code of Georgia Annotated, relating to property,
More informationPUBLIC CHAPTER NO. 353
~tate of m:ennessee PUBLIC CHAPTER NO. 353 HOUSE BILL NO. 493 By Representative Sargent Substituted for: Senate Bill No. 601 By Senator Johnson AN ACT to amend Tennessee Code Annotated, Section 6-55-202
More informationINTRODUCTION TO SMALL CLAIMS COURT TABLE OF CONTENTS
INTRODUCTION TO SMALL CLAIMS COURT TABLE OF CONTENTS INTRODUCTION TO SUE OR NOT TO SUE? HOW TO FILE A SMALL CLAIMS CASE WHERE TO FILE FILING FEE NOTICE TO THE DEFENDANT COUNTERCLAIMS PREPARING FOR TRIAL
More informationSUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND ("Bond") SURETY Address
Bond # SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND ("Bond") KNOW ALL PERSONS BY THESE PRESENTS; that SUBCONTRACTOR as Principal (the "Subcontractor"), and SURETY as Surety or Co-sureties (hereinafter
More informationNON BORROWING SPOUSES AND REVERSE MORTGAGES OVERVIEW
WHAT IS A REVERSE MORTGAGE NON BORROWING SPOUSES AND REVERSE MORTGAGES OVERVIEW The Home Equity Conversion Mortgage Program, i.e. the reverse mortgage, was enacted by Congress in 1987 to meet the special
More informationSUMMARY OF MECHANICS LIEN LAW FOR MINNESOTA. As of 2013. Name of Notice Who Must Use This Notice When How to Serve Verified or notarized?
SUMMARY OF MECHANICS LIEN LAW FOR MINNESOTA As of 2013 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents Mechanic s Lien
More informationTo: Counsel, Agents, and Readers From: Michael J. Berey Dated: September 5, 2008 Re: Mortgages: Chapter 472, Laws of 2008
To: Counsel, Agents, and Readers From: Michael J. Berey Dated: September 5, 2008 Re: Mortgages: Chapter 472, Laws of 2008 Chapter 472 of the Laws of 2008 was signed into law on August 5, 2008. According
More informationHow BC s Builders Lien Act Applies to Contractors
How BC s Builders Lien Act Applies to Contractors The purpose of this summary is to give a general idea of the rights and liabilities which flow from the most important provisions in the Act. This summary
More informationCOMMENTARY. California s New Subcontractor Defense Regime for Non-Residential Projects: Creating Order or Chaos?
May 2013 JONES DAY COMMENTARY California s New Subcontractor Defense Regime for Non-Residential Projects: Creating Order or Chaos? As explained in a recent Commentary (available at http://www.jonesday.com/navigating_treacherous_
More informationOWNER-BUILDER ACKNOWLEDGEMENT & INFORMATION VERIFICATION
GEORGE CHAVEZ, City Building Official DAVID YELTON, Building Inspection Manager NESTOR OTAZU, Community Preservation Manager BUILDING & SAFETY DIVISION 455 North Rexford Drive, 1 st Floor Beverly Hills,
More informationCHAPTER 702 FORECLOSURE OF MORTGAGES, AGREEMENTS FOR DEEDS, AND STATUTORY LIENS. 702.06 Deficiency decree; common-law suit to recover deficiency.
Florida Foreclosure is Judicial. Notice of Foreclosure Florida foreclosure begins when the lender files a lawsuit (Lis Pendens) against the homeowner. The homeowners must be notified of the legal action
More informationUNITED STATES BANKRUPTCY COURT FOR THE WESTERN DISTRICT OF MICHIGAN ORIGINAL CHAPTER 13 PLAN
UNITED STATES BANKRUPTCY COURT FOR THE WESTERN DISTRICT OF MICHIGAN In Re: Debtor(s), / Case #: Chapter 13 Hon. Filed: ORIGINAL CHAPTER 13 PLAN Check this box if this plan deviates in any way from the
More informationPATHS OF A FORECLOSURE IN NEW YORK STATE
PATHS OF A FORECLOSURE IN NEW YORK STATE BORROWER DELINQUENT 2-3 months late with mortgage payments 90-DAY PRE-FORECLOSURE NOTICE Lender sends notices, bills, letters to borrower stating that he/she is
More informationHiring a Contractor. Federal Trade Commission consumer.ftc.gov
Hiring a Contractor Federal Trade Commission consumer.ftc.gov Adding a room, renovating a basement, or doing some much-needed repairs? Finding a good contractor is important a home improvement project
More informationWelcome to the Model Residential Construction Contract Lump Sum
Welcome to the Model Residential Construction Contract Lump Sum The Council for the Construction Law Section of the Washington State Bar Association prepared this Model Residential Construction Contract
More informationSUPREME COURT County of : State of New York VERIFIED ANSWER TO FORECLOSURE COMPLAINT. Defendant(s). Defendant answers as follows: General Denial.
SUPREME COURT County of : State of New York v. Plaintiff, Defendant(s). Index No.: VERIFIED ANSWER TO FORECLOSURE COMPLAINT Defendant answers as follows: General Denial. Plaintiff, upon information and
More informationBuilding a Good Construction Loan Agreement Presented by Laura S. Peck 608.283.6729 lpeck@axley.com
BUILDING A GOOD CONSTRUCTION LOAN AGREEMENT July 29, 2014 This document was drafted for presentation purposes only. Before relying on legal information of a general nature, please consult legal counsel
More informationSMALL CLAIMS COURT INFORMATION
Clark County District Court SMALL CLAIMS COURT INFORMATION INTRODUCTION The Small Claims Department of District Court allows a person or business with a legal dispute to sue without hiring an attorney.
More informationTo help you better understand the foreclosure process, these definitions are presented in a logical order, rather than alphabetical order.
FORECLOSURE GLOSSARY NOTICE: This glossary of legal words and phrases related to foreclosure is provided to you by the Clermont County Common Pleas Court to help you better understand your legal problem
More informationMechanic s Liens (Reprinted with permission from NACM s Manual of Credit and Commercial Laws, 104 th edition) INTRODUCTION
514 Mechanic s Liens (Reprinted with permission from NACM s Manual of Credit and Commercial Laws, 104 th edition) INTRODUCTION Mechanic s lien laws are the result of a policy intended to protect unpaid
More information