1 STATE AGENCY REPORT WSKC Dialysis Services, Inc. Everest Healthcare Services Corp. West Side Health Authority d/b/a Austin Community Kidney Center Chicago, Illinois Project # I. The Proposed Project The applicants propose to establish a 16 station ESRD facility at the corner of Chicago Avenue and Cicero Avenue in Chicago, Illinois. The total estimated project cost is $3,261,393. II. Summary of Findings A. The State Agency finds that the proposed project does not appear to be in conformance with the provisions of Part B. The State Agency finds that the proposed project does not appear to be in conformance with the provisions of Part III. General Information The co-applicants are WSKC Dialysis Services, Inc., Everest Healthcare Services Corp., and West Side Health Authority. The facility will be located in HSA VI which is the planning area for ESRD services. There are 35 other facilities offering ESRD services in HSA VI, 28 of which are located within 30 minutes travel time of the proposed facility. This is a non-substantive project which is subject to both a Part 1110 and a Part 1120 review. The project has not been obligated and obligation is not requested upon permit issuance. The application states that the project should be completed in 6 months. An opportunity for public hearing was offered on this project; however, no request for a hearing was received.
2 Page 2 IV. The Proposed Project - Details The applicants are proposing to establish a 16 station ESRD facility in a new medical professional building to be constructed by West Side Health Authority in Chicago, Illinois. It will lease 7,555 square feet in the Austin Community Health and Education Center to be located on the corner of Chicago and Cicero Avenues in Chicago. As construction is being completed, the applicants will begin a tenant improvement build-out that includes treatment areas, plumbing, electrical, HVAC, life safety, and other improvements. V. Project Sources and Uses of Funds The applicant proposes to fund the project with $3,261,393 in cash and securities, leases, and a bank line of credit. The following table outlines the proposed use of funds: Table I Proposed Use of Funds Amount Preplanning Costs $ 5,000 New Construction Contracts 825,000 Contingencies 80,000 Architectural & Engineering Fees 65,000 Consulting and Other Fees 84,836 Movable or other Equipment 382,800 Net Interest Expense During Construction 75,957 Other Costs to be Capitalized 72,000 Acquisition of Leased Building (FMV) 1,670,800 Total $3,261,393 VI. Review Criteria - Chronic Renal Dialysis A. Criterion a., Data System
3 Page 3 The applicants state that an ESRD data system does not presently exist at the site. They do state that an ESRD data system will be established as is required by this criterion. B. Criterion b., Minimum Size of Renal Dialysis Facilities The applicant is proposing a facility with 16 stations. According to this criterion, the applicant must establish a facility with at least 6 stations in an MSA of more than 500,000 population. C. Criterion c., Variance to Station Need The April 15, 2000 update to the Inventory of Healthcare Facilities indicates a need for 66 stations in HSA VI. Therefore, this criterion is not applicable. D. Criterion d., Support Services The applicant will be supplying the following support services onsite: dietary counseling, rehabilitation, home/self training, social services and psychiatric services. Support services that will be provided by other entities are: tissue typing, isolation hemodialysis, and laboratory services. This criterion also specifies that blood bank services will be available. The applicants did not address the availability of this support service; therefore, a negative finding must be made. THE STATE AGENCY FINDS THAT THE PROPOSED PROJECT DOES NOT APPEAR TO BE IN CONFORMANCE WITH THE ABOVE REVIEW CRITERION. E. Criterion e., Affiliation Agreements The applicants have a signed affiliation agreement for hospital services with University of Chicago Hospital, 5841 South Maryland Avenue, Chicago. In addition, the applicants have a transplantation agreement with Rush Presbyterian Hospital, 1725 West Harrison Street, Chicago.
4 Page 4 F. Criterion f., Self-Care and Home Dialysis Training The applicants have certified that self care dialysis, self care instruction, home dialysis and home training services will be provided at West Metro Dialysis Center located at 1044 West Mozart Street, Chicago. G. Criterion g., Relocation of Facilities H. Criterion h., Addition of Stations These criteria are not applicable. I. Criterion i., Quality of Care The application states that in the 12 month period of 10/98-09/99, 79.3% of all WSKC Illinois patients had a Urea Reduction Rate of.65 or better. For the 8 month period of 10/98 to 5/99, 79.8% of WSKC Illinois patients had a hematocrit level 31% or better. These percentages surpass the State standard of 65% of the patients for both of these standards. An 8 month period was given for hematocrit since at that time WSKC started using a hemoglobin measure instead of Hematocrit. The application states that if the hematocrit and hemoglobin measures were combined to give a 12 month measure it would give a 81.7% level at 31% or better and would still be within state guidelines. VII. Review Criteria - General A. Criterion a., Location The applicants have provided a list of 69 patient referrals by zip code. The application states that these patients would come from present WSKC facilities that are running 100% or greater utilization rates. The table below lists the 28 facilities that are within a 30 minute travel time and the percent utilization they have. All but 3 show at least 80% utilization according to the 1998 Renal Network Report. There is a projected need for 66 stations in the planning area
5 Page 5 based on the April update to the Inventory of Health Care Facilites. It appears that the proposed project will not cause a maldistribution of services. Table II Facilities Within 30 Minutes Travel Time Facility 1998 Renal Network - % Utilization Neomedica North 95 Lincoln Park Dialysis Services 93 Edgewater Hospital 52 Northwestern Hospital 82 West Metro Dialysis Center* 85 Chicago Dialysis Center* 90 Logan Square 105 DCA Prairie 103 DCA Lakeshore 96 Neomedica - Southwest 99 Univ. of Chicago Hospitals 88 Rush Presbyterian 94 Neomedica Melrose Park 84 DCA Riverside 84 DCA Loop 94 Mt. Sinai 99 Neomedica West Belmont 80 West Suburban Dialysis Center* Oak Park Dialysis Center* 97 Foster McGaw Hospital of Loyola 133 University of Illinois Hospital 92 Neomedica Loop 82 Downers Grove Dialysis Center 106 Elmhurst Memorial Hospital 93 LaGrange Dialysis Center 117 Resurrection Medical Center 94 DCA Rodgers Park 93 Neomedica Niles 65 *owned by applicant
6 Page 6 B. Criterion b., Background of the Applicant The applicants have provided documentation showing that they are fit, willing and able, and have the qualifications, background and character to adequately provide a proper standard of health care services for the community. C. Criterion c., Alternatives The applicants investigated alternatives to the proposed project which are outlined in Attachment #GRC-3 of its application. Other alternatives were rejected due to high present utilization at WSKC facilities and the fact that there is a calculated need for dialysis facilities in the area. It appears that opening a new facility is a reasonable choice. D. Criterion d., Need for the Project There is a calculated need for 66 stations in the planing area according to the April 15, 2000 update to the Inventory of Health Care Facilities. E. Criterion e., Size of the Project The applicants state that they have projected their utilization rate for the new facility based on past experience in the area. The application states that they will start with 69 patients and grow by 8% a year. The 8% is stated to be a conservative estimate based on growth at nearby WSKC facilities of 17-23% for the year They project a utilization rate of 78% percent by the end of the first year and 84% at the end of the second year. This projection meets the State standard of 80% by the second year.
7 Page 7 The applicant is proposing to establish a 16 station facility in 7,555 GSF or GSF per station. This number is in excess of the State Agency guideline of 470 GSF/station. The application did not provide information as to the reasons for this excess; therefore, a negative finding must be made. THE STATE AGENCY FINDS THAT THE PROPOSED PROJECT DOES NOT APPEAR TO BE IN CONFORMANCE WITH THE ABOVE REVIEW CRITERION. VIII. Review Criteria - Financial Feasibility A. Criterion a., Financial Viability The State Agency has reviewed the latest three years financial statements that were provided. The applicants results in comparison to State standards are listed below: State WSKC Dialysis Services, Inc. Measure Standard Current Ratio 1.5 x or more NA Net Margin Percentage 3.5% or more 3.7% 2.5% 2.6% NA Debt Capitalization Ratio 80% or less 53% 65% 75% NA Debt Service Coverage 1.75 x or more NA Days Cash on Hand 90 days or more NA Cushion Ratio 5 or more NA The applicant s days cash on hand and cushion ratio did not meet State standards for the 3 years given. Net margin percentage was not met in 1998 or Also, projected ratios for 2002 were not supplied. State Everest Healthcare Services Corp. Measure Standard Current Ratio 1.5 x or more Net Margin Percentage 3.5% or more 3.7% 2.5% 3.6% 3.1% Debt Capitalization Ratio 80% or less 53% 65% 75% 71% Debt Service Coverage 1.75 x or more Days Cash on Hand 90 days or more Cushion Ratio 5 or more
8 Page 8 The applicant s days cash on hand and cushion ratio did not meet State standards for the 3 years given or the 2002 projection. Net margin percentage was not met in 1998 or State Westside Health Authority Measure Standard Current Ratio 1.5 x or more NA Net Margin Percentage 3.5% or more -3.30% 23.23% 1.06% NA Debt Capitalization Ratio 80% or less 59% 17% 14% NA Debt Service Coverage 1.75 x or more NA Days Cash on Hand 90 days or more NA Cushion Ratio 5 or more NA The applicant s net current ratio, net margin percent, debt capitalization ratio, debt service coverage, days cash on hand, and cushion ratio did not meet State standards for Net margin percentage was not met in 1999 and days cash on hand was not met in 1998 or Also, projected ratios for 2002 were not supplied. THE STATE AGENCY FINDS THAT THE PROPOSED PROJECT DOES NOT APPEAR TO BE IN CONFORMANCE WITH THE ABOVE REVIEW CRITERION. B. Criterion b., Availability of Funds The applicant proposes to fund the project with $75,957 in existing cash and securities, leases of $1670,800, and bank line of credit for $1,514,636. After reviewing Everest Healthcare Services Corporation s audited financials, it appears that there are sufficient financial resources to fund the project. C. Criterion c., Start-Up Costs The application did not contain information as to start-up costs; therefore, this criterion is negative. THE STATE AGENCY FINDS THAT THE PROPOSED PROJECT DOES NOT APPEARS TO BE IN CONFORMANCE WITH THE ABOVE REVIEW CRITERION.
9 Page 9 IX. Review Criteria - Economic Feasibility A. Criterion a., Reasonableness of Financing Arrangements The applicant has stated that the project will be funded with cash and securities of $75,957, with a lease with a FMV of $1,670,800, and a bank line of credit for $1,514,636. According to the applicant, all available cash and securities are being used to fund the project. This criterion states that the applicant must document that the project will be funded with cash and equivalents including investment securities, unrestricted funds, and funded depreciation as currently defined by the Medicare regulations (42 USC 1395) unless cash and equivalents must be retained for either of the following: 1) a portion or all of the cash and equivalents must be retained in the balance sheet asset accounts in order that the current ratio does not fall below 2.0 times; or 2) borrowing is less costly than the liquidation of existing investments. The applicant must provide documentation of the investment portfolio and evidence that supports retaining such investments. In the provided Everest financials, there appeared to be sufficient funds to fund the project without borrowing. Since the application did not address either of the two variances given above, the State Agency must make a negative finding. THE STATE AGENCY FINDS THAT THE PROPOSED PROJECT DOES NOT APPEAR TO BE IN CONFORMANCE WITH THE ABOVE REVIEW CRITERION. B. Criterion b., Terms of Debt Financing The building will be leased for $4.58 per GSF per annum in the first year with a rising rent described in attachment GRC-1. There is also a bank line of credit at the current Prime rate. The applicants state that they choose to lease rather than purchase real estate since this allows greater flexibility in expanding and relocating units and that the capital expenditures in leasing would be less than for purchasing. The terms of the debt financing appear to be at a reasonable level.
10 Page 10 C. Criterion c., Costs of Debt Financing The applicant stated that the projected total facility debt would be $1,687,949. The cost of debt financing, that is required by this criterion, was not supplied. Therefore, a negative finding must be made. D. Criterion d., Reasonableness of Project Cost Preplanning Costs - These costs amount to $5,000 or 0.39% of contracts, contingencies and equipment costs. This amount is reasonable when compared to the State standard of 1.8%. New Construction - Contracts and contingencies amount to $905,000. The area to be constructed consists of 7,555 GSF or $ per GSF. This amount appears reasonable when compared to the State standard of $ for Contingencies - These costs amount to $80,000 or 9.7% of construction contracts. This appears reasonable when compared to the State Agency standard of 10%. Architectural and Engineering Fees - These costs amount to $65,000 or 7.2% of construction and contingencies costs. This amount appears reasonable when compared to the State standard of 7.2%. Consulting and Other Fees - These costs amount to $84,836 and appear reasonable when compared to previously approved projects. Equipment - These costs amount to $382,800 or $23,925 per station. This amount appears reasonable when compared to the State adjusted standard of $26,228. Net Interest Expense During Construction - These costs amount to $75,957 or 2.3% of total project costs. Other Costs To Be Capitalized - These costs amount to $72,000 and are for a water treatment system. This is 2.2% of total project costs. Lease Of Building - The FMV of the lease amounts to $1,670,800 and appears to be reasonable when compared to previously approved projects.
11 Page 11 E. Criterion e., Reasonableness of Resultant Operating Costs The applicant has projected the following operating costs for 2001: Salaries $734,315 Benefits 94,490 Supplies 266,220 Total $1,095,025 Units of Service 11,981 Cost per Unit $91.40 The applicants have not stated if the cost of Epogen was included in the costs above. The cost shown is within the adjusted State standard of $102. F. Criterion f., Capital Costs G. Criterion g., Non-Patient Related Services These criteria are not applicable to this project.
PROJECT NO: 01-063 CITY: Highland Park
DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST: A-8 November 29, 2001 FACILITY NAME: Highland Park Hospital CITY: 01-063 Highland Park Original: $3,604,745 Current: $ TYPE OF PROJECT: Substantive HSA:
More informationPROJECT NO: Original: $13,258,843 FACILITY NAME: CITY: Current: $ Marklund at Mill Creek. Geneva
DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST: B-1 May 17, 2001 00-080 Original: $13,258,843 FACILITY NAME: CITY: Current: $ Marklund at Mill Creek Geneva TYPE OF PROJECT: Non-Substantive HSA: 8 PROJECT
More informationILLINOIS REGISTER HEALTH FACILITIES AND SERVICES REVIEW BOARD NOTICE OF ADOPTED AMENDMENTS
TITLE 77: PUBLIC HEALTH CHAPTER II: HEALTH FACILITIES AND SERVICES REVIEW PLANNING BOARD SUBCHAPTER b: OTHER BOARD RULES PART 1120 HEALTH FACILITIES AND SERVICESPLANNING FINANCIAL AND ECONOMIC FEASIBILITY
More informationChampaign TYPE OF PROJECT: Substantive HSA: IV
DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST: B - 1 January 15-16, 2008 07-004 Original: $4,498,500 FACILITY NAME: CITY: Current: $4,498,500 Olympian Surgical Suites Champaign TYPE OF PROJECT: Substantive
More informationOctober 26, 2010. Original: $0 FACILITY NAME: Central Illinois Endoscopy Center, LLC TYPE OF PROJECT: Non-Substantive
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 52525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST:
More informationOriginal: $4,010,058 FACILITY NAME: DaVita Markham Renal Center
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 52525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST:
More informationTYPE OF PROJECT: Non-Substantive
DOCKET NO: H-09 BOARD MEETING: July 23-24, 2012 FACILITY NAME: Alden Courts of Shorewood PROJECT NO: 12-032 CITY: Shorewood PROJECT COST: Original: $10,428,798 Current: $ TYPE OF PROJECT: Non-Substantive
More informationSTATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 52525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST:
More informationDIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT AUGUST 2014
DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT AUGUST 2014 CON REVIEW HR-RC-0514-006 THE MISSISSIPPI METHODIST HOSPITAL AND REHABILITATION CENTER, INC. D/B/A METHODIST REHABILITATION CENTER RENOVATION
More informationMay 20-21, 2008. Original: $50,325,000 FACILITY NAME:
DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST: A - May 2-21, 28 8-8 Original: $5,325, FACILITY NAME: Gottlieb Memorial Hospital TYPE OF PROJECT: Non-Substantive CITY: Melrose Park Current: HSA: VII
More informationSTATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD CITY: Joliet TYPE OF PROJECT: Substantive HSA: IX
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 52525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST:
More informationMarch 27-28, 2007. Moline TYPE OF PROJECT: Substantive HSA: X
DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST: A - 6 FACILITY NAME: March 27-28, 2007 06-071 CITY: Original: $0 Regional Surgicenter, Ltd. Moline TYPE OF PROJECT: Substantive HSA: X PROJECT DESCRIPTION:
More informationMISSISSIPPI STATE DEPARTMENT OF HEALTH DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT DECEMBER 2015
MISSISSIPPI STATE DEPARTMENT OF HEALTH DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT DECEMBER 2015 CON REVIEW HR-RC-1015-022 RENOVATION OF 6 th FLOOR, PATIENT AND NURSING AREA LOCATION: JACKSON,
More informationTYPE OF PROJECT: Substantive HSA: VII
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 5 525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: H-01 BOARD MEETING: November 5, 2013 PROJECT
More informationSTATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD
DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST: H-09 October 30-31, 2012 FACILITY NAME: Hispanic American Endoscopy Center 12-068 CITY: Chicago Original:$ 50,500 Current: $ TYPE OF PROJECT: Substantive
More informationMISSISSIPPI STATE DEPARTMENT OF HEALTH DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT JUNE 2016 STAFF ANALYSIS
MISSISSIPPI STATE DEPARTMENT OF HEALTH DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT JUNE 2016 CON REVIEW HG-RB-0416-009 JACKSON HMA, LLC, D/B/A MERIT HEALTH CENTRAL EXPANSION OF PSYCHIATRIC BEDS
More informationCALIFORNIA HEALTH FACILITIES FINANCING AUTHORITY THE HELP II PROGRAM EXECUTIVE SUMMARY
CALIFORNIA HEALTH FACILITIES FINANCING AUTHORITY THE HELP II PROGRAM EXECUTIVE SUMMARY Applicant: Bloss Memorial Healthcare District Amount Requested: $427,500 ( BMHCD ) Requested Loan Term: 5 years 3605
More informationDIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT AUGUST 2013
DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT AUGUST 2013 CON REVIEW MISSISSIPPI METHODIST HOSPITAL AND REHABILITATION CENTER, INC. d/b/a METHODIST OUTPATIENT REHABILITATION CONSTRUCTION OF CONSOLIDATED
More informationRevolving Loan Fund for Commercial Development Summary*
Owatonna Economic Development Authority (EDA) City of Owatonna Revolving Loan Fund for Commercial Development Summary* Program Purpose: How It Works: Project Eligibility: Minimum Requirements: Use of Funds:
More informationACCOUNTING FOR NON-ACCOUNTANTS
Deutsch and Chikarovski's ACCOUNTING FOR NON-ACCOUNTANTS A Question and Answer Handbook Robert Deutsch and Kris Chikarovski THE FEDERATION PRESS 2012 Preface - x Who is this book for? x What is in this
More informationDIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT AUGUST 2004
DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT AUGUST 2004 CON REVIEW INDEPENDENT HEALTHCARE MANAGEMENT, INC. DBA LACKEY MEMORIAL HOSPITAL CONSTRUCTION OF A REPLACEMENT HOSPITAL CAPITAL EXPENDITURE:
More informationRevolving Loan Fund for Industrial Development Summary *
Owatonna Economic Development Authority (EDA) City of Owatonna Revolving Loan Fund for Industrial Development Summary * Program Purpose: How It Works: Project Eligibility: Minimum Requirements: Use of
More informationVILLAGE OF ARLINGTON HEIGHTS
VILLAGE OF ARLINGTON HEIGHTS ENERGY EFFICIENCY & CONSERVATION BLOCK GRANT SMALL BUSINESS LOAN PROGRAM 0% INTEREST POLICY AND PROCEDURES Prepared by: Village of Arlington Heights Department of Planning
More informationSTATE BANK OF INDIA BRANCH. Interview Form For Loans above Rs.25,000/- (To be submitted to the Sanctioning Authority along with the Application Form)
Annexure-SBF/3 STATE BANK OF INDIA BRANCH SMALL BUSINESS FINANCE Interview Form For Loans above 25,000/- (To be submitted to the Sanctioning Authority along with the Application Form) To be used for :
More informationPSYCHIATRIC RESIDENTIAL TREATMENT FACILITY APPLICATION FORM ARKANSAS HEALTH SERVICES PERMIT COMMISSION
PSYCHIATRIC RESIDENTIAL TREATMENT FACILITY APPLICATION FORM ARKANSAS HEALTH SERVICES PERMIT COMMISSION ARKANSAS HEALTH SERVICES PERMIT AGENCY 5800 WEST 10TH STREET, SUITE 805 LITTLE ROCK, ARKANSAS 72204
More informationTOWN OF HAMDEN, CONNECTICUT Economic & Community Development Department 2750 Dixwell Avenue Hamden, Connecticut 06518
TOWN OF HAMDEN, CONNECTICUT Economic & Community Development Department 2750 Dixwell Avenue Hamden, Connecticut 06518 Dale Kroop, Director TO ALL INTERESTED LOAN APPLICANTS NOTICE OF AVAILABLE FUNDS SMALL
More informationMISSISSIPPI DEPARTMENT OF HEALTH Division of Health Planning and Resource Development May 2007. Staff Analysis
MISSISSIPPI DEPARTMENT OF HEALTH Division of Health Planning and Resource Development May 2007 CON Review: HG-RC-0407-007 Southwest Mississippi Regional Medical Center Capital Expenditure: $8,597,238 Location:
More informationDIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT JUNE 2003 STAFF ANALYSIS
DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT JUNE 2003 THE NICHOLS CENTER CONSTRUCTION OF A 60-BED NURSING HOME REPLACEMENT FACILITY CAPITAL EXPENDITURE: $1,820,000 LOCATION: SUMRALL, MISSISSIPPI
More informationDIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT JUNE 2003 STAFF ANALYSIS
DIVISION OF HEALTH PLANNING AND RESOURCE DEVELOPMENT JUNE 2003 CON REVIEW SOUTH CENTRAL REGIONAL MEDICAL CENTER DBA LAUREL SURGERY AND ENDOSCOPY CENTER, LLC AMENDMENT, COST OVERRUN, SITE CHANGE AND TRANSFER
More informationDialysis Patients' Bill of Rights and Responsibilities
Dialysis Patients' Bill of Rights and Responsibilities PATIENTS Rights Quality Care Information Individual Treatment Privacy and Confidentiality Services Without Discrimination Treatment Options Kidney
More informationA. To strategically utilize debt to fund mission critical projects;
Policy concerning: page 1 of 5 DEBT POLICY I. GOALS AND OBJECTIVES Teaching and learning form the core of Westfield State University s institutional mission. The university s strategic plan identifies
More informationDEBT MANAGEMENT POLICY
DEBT MANAGEMENT POLICY This policy sets forth the principles that will govern the use of debt to finance University capital projects and assigns responsibilities for the management of University debt.
More informationAdditional Revision to Brief Report of Settlement of Accounts for Full Fiscal Year Ending March 31, 2007
June 22, 2007 Company Name: ARUZE CORP. Name and Title of Representative: Kunihiko Yogo Representative Director and CEO (JASDAQ Code: 6425) Contact: Norihisa Kiriu General Manager Finance and Accounting
More informationBridges of America - The Jacksonville Bridge, Inc. Orlando, Florida
Bridges of America - The Jacksonville Bridge, Inc. Orlando, Florida Financial Statements and Supplemental Information Year Ended June 30, 2010 Contents Page Independent Auditor s Report 1 Financial Statements
More informationCommunity Christian Church and Affiliates
Community Christian Church and Affiliates Independent Auditor s Report and Consolidated Financial Statements September 30, 2014 Community Christian Church and Affiliates September 30, 2014 Contents Independent
More informationSTATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 52525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST:
More informationSBA LOAN APPLICATION
Please submit application to Mike Litton at mlitton@plainscapital.com. SBA LOAN APPLICATION PlainsCapital Bank is a Preferred SBA Lender. The following information is required for initial processing, however,
More informationCOMMUNITY BLOOD CENTERS OF FLORIDA, INC. AND AFFILIATE
CONSOLIDATED FINANCIAL STATEMENTS CONTENTS Independent Auditors Report...1 Consolidated Financial Statements Statement of Financial Position... 2-3 Statement of Activities and Changes in Net Assets...4
More informationCDFI Bond Guarantee Program Secondary Loan Requirements Underwriting Review Checklist
CDFI Bond Guarantee Program Secondary Loan Requirements Underwriting Review Checklist PART I: INSTITUTIONAL LENDING REQUIREMENTS Under the CDFI Bond Guarantee Program, the Eligible CDFI must maintain loan
More informationAnalyzing Cash Flows. April 2013
Analyzing Cash Flows April 2013 Overview Introductions Importance of cash flow in underwriting decisions Key attributes to calculating cash flow Where to obtain information to calculate cash flows Considerations
More informationMANAGEMENT S DISCUSSION OF FINANCIAL PERFORMANCE. As of March 31, 2016
MANAGEMENT S DISCUSSION OF FINANCIAL PERFORMANCE As of March 31, 2016 Management s Discussion of Financial Performance Introduction The consolidated financial statement information and other data for the
More informationRSL-2008-03 Attachment 1 Determination of Operating or Capital Lease Classification for Budget Scorekeeping Purposes
1. General. RSL-2008-03 a. This policy, jointly issued by the Assistant Commissioners for Real Property Asset Management and Real Estate Acquisition, provides mandatory instructions for determining appropriate
More informationFinancial Statement Analysis Paper
Financial Statement Analysis Paper Example 1: Dell Computer Dell Inc. Current Year Prior Year Income Statement 3 Years Ago $ Percent $ Percent $ Percent Revenue 61,494 100.0% 52,902 100.0% 61,101 100.0%
More informationICAP GROUP S.A. FINANCIAL RATIOS EXPLANATION
ICAP GROUP S.A. FINANCIAL RATIOS EXPLANATION OCTOBER 2006 Table of Contents 1. INTRODUCTION... 3 2. FINANCIAL RATIOS FOR COMPANIES (INDUSTRY - COMMERCE - SERVICES) 4 2.1 Profitability Ratios...4 2.2 Viability
More informationTrinitas Regional Medical Center Obligated Group Consolidated Balance Sheet At September 30, 2015 and December 31, 2014 (Unaudited)
Consolidated Balance Sheet At 3, 215 and December 31, 214 (Unaudited) Assets Current Assets: Cash and cash equivalents (includes certificates of deposit) Assets whose use is limited Patient accounts receivable
More informationCommercial Applicant Processing Checklist
Commercial Applicant Processing Checklist In order to properly and promptly process an application, please fill out the following forms legibly and in their entirety: Commercial Lease Application Financial
More informationLYON RURAL ELECTRIC COOPERATIVE ECONOMIC DEVELOPMENT REVOLVING LOAN FUND APPLICATION. Name of Business: Address: City: Business contact person:
LYON RURAL ELECTRIC COOPERATIVE ECONOMIC DEVELOPMENT REVOLVING LOAN FUND APPLICATION I. BASIC INFORMATION Name of Business: Address: City: Business contact person: Social Security #: Zip Code: (if business
More informationBUSINESS LOAN APPLICATION
BUSINESS LOAN APPLICATION Thank you for your decision in obtaining a commercial loan from our business service division. Please complete the following information as accurately as possible so we may better
More informationCity of Mt. Angel. Comprehensive Financial Management Policies
City of Mt. Angel Comprehensive Financial Management Policies May 2014 Table of Contents Section Description Page I. Purpose... 3 II. Objectives... 3 III. Management of Fiscal Policy... 4 IV. Accounting,
More informationPEF closes funding gaps growth businesses commonly face as they move from start-up to commercialization and fast growth.
PITTSBURGH ENTREPRENEUR FUND Program Guidelines I. Statement of Purpose The Pittsburgh Entrepreneur Fund (PEF) will provide capital for new and growing businesses, including emerging technology-based firms,
More informationSTATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 5 525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST:
More informationDREAM OFFICE REIT REPORTS SOLID SECOND QUARTER 2015 RESULTS AND ROBUST LEASING ACTIVITY
DREAM OFFICE REIT REPORTS SOLID SECOND QUARTER 2015 RESULTS AND ROBUST LEASING ACTIVITY This news release contains forward-looking information that is based upon assumptions and is subject to risks and
More informationIMPLEMENTING GUIDELINES FOR THE GUARANTY PROGRAM FOR ABANDONED/UNFINISHED BUILDINGS
IMPLEMENTING GUIDELINES FOR THE GUARANTY PROGRAM FOR ABANDONED/UNFINISHED BUILDINGS I. Concept The guaranty program for abandoned/unfinished buildings is intended to encourage banks to extend construction
More informationPOLICY. Employees Covered All College financing activities.
THE RICHARD STOCKTON COLLEGE OF NEW JERSEY POLICY Debt Management Policy Policy Administrator: Associate Vice President for Administration and Finance Authority: N.J.S.A. 18A:64-6 Effective Date: February
More informationIf you have questions regarding these forms or requirements, please consult with your attorney. Office of the Chapter 13 Trustee Marilyn O.
This office has been appointed standing trustee in your Chapter 13 bankruptcy case. The documents that you filed indicate that at least one of the persons filing this case is engaged in business. Enclosed
More informationBridges of America - The Orlando Bridge, Inc. Orlando, Florida Financial Statements and Supplemental Information Year Ended June 30, 2011
Bridges of America - The Orlando Bridge, Inc. Orlando, Florida Financial Statements and Supplemental Information Year Ended June 30, 2011 Table of Contents Page Independent Auditor s Report 1 Financial
More informationWestern Avenue Special Service Area Number 20
Financial Statements Year Ended December 31, 2010 and 2009 Contents Page Independent Auditor's Report 1 Financial Statements Statement of Financial Position 2 Statement of Activities 3 Statement of Cash
More informationHeartland International Health Center. Financial Report June 30, 2013
Heartland International Health Center Financial Report June 30, 2013 Contents Independent Auditor's Report 1 2 Financial Statements Statements of Financial Position 3 Statements of Operations 4 Statements
More informationHealthy Food Access Fund
Healthy Food Access Fund Program Guidelines and Loan Application Form IFF, a nonprofit financial institution with 26 years of experience financing economicdevelopment projects in disinvested communities,
More informationBridges of America - The Turning Point Bridge, Inc. Orlando, Florida
Bridges of America - The Turning Point Bridge, Inc. Orlando, Florida Financial Statements and Supplementary Information Year Ended June 30, 2014 Table of Contents Page Independent Auditor s Report 1 Financial
More informationBOARD MEETING: August 13, 2013
STATE OF ILLINOIS HEALTH FACILITIES AND SERVICES REVIEW BOARD 52525 WEST JEFFERSON ST. SPRINGFIELD, ILLINOIS 62761 (217) 782-3516 FAX: (217) 785-4111 DOCKET NO: BOARD MEETING: PROJECT NO: PROJECT COST:
More informationFinancial Modeling & Forecasting. Jason MacMorran www.pncpa.com
Financial Modeling & Forecasting Jason MacMorran www.pncpa.com Presentation Outline I. Introduction and Learning Objectives II. Definitions and Standards Overview III. Uses for Financial Models IV. Basics
More informationRENT CONTROL BOARD SUBSTANTIAL REHABILITATION APPLICATION FOR ONE-TIME EXEMPTION OF ENTIRE BUILDING
RENT CONTROL BOARD SUBSTANTIAL REHABILITATION APPLICATION FOR ONE-TIME EXEMPTION OF ENTIRE BUILDING SUBSTANTIAL REHABILITATION APPLICATION FOR ONE-TIME EXEMPTION OF ENTIRE BUILDING EXPLICATION AND INSTRUCTIONS:
More informationTOWN of BRATTLEBORO, VERMONT SMALL BUSINESS ASSISTANCE PROGRM POLICIES AND PROCEDURES
TOWN of BRATTLEBORO, VERMONT SMALL BUSINESS ASSISTANCE PROGRM POLICIES AND PROCEDURES A. POLICIES I. Purpose: Conventional sources of funding for start-up or business expansion purposes are largely inaccessible
More informationAnalysis of the Financial Condition of the University of Illinois System
Analysis of the Financial Condition of the University of Illinois System Prepared by Howard Bunsis: PhD, MBA, J.D., B.S., CPA Professor of Accounting Eastern Michigan University 734 487 2519 hbunsis@emich.edu
More informationSchneps, Leila; Colmez, Coralie. Math on Trial : How Numbers Get Used and Abused in the Courtroom. New York, NY, USA: Basic Books, 2013. p i.
New York, NY, USA: Basic Books, 2013. p i. http://site.ebrary.com/lib/mcgill/doc?id=10665296&ppg=2 New York, NY, USA: Basic Books, 2013. p ii. http://site.ebrary.com/lib/mcgill/doc?id=10665296&ppg=3 New
More informationREGULATION NO. 30. Loans for Rural Economic Development
EASTERN ILLINI ELECTRIC COOPERATIVE REGULATION NO. 30 SUBJECT: Loans for Rural Economic Development OBJECTIVE: It is the objective of Eastern Illini Electric Cooperative (Cooperative) to provide an additional
More informationAPPLICATION FOR FINANCIAL ASSISTANCE Phone: 513.631.8292 Fax: 513.631.1192 1776 Mentor Ave. Suite 100 Cincinnati, OH 45212 www.hcdc.
APPLICATION FOR FINANCIAL ASSISTANCE Phone: 513.631.8292 Fax: 513.631.1192 1776 Mentor Ave. Suite 100 Cincinnati, OH 45212 www.hcdc.com COMPANY INFORMATION: (This is information about your operating business.)
More informationBorrowing 101. Resources. Are you ready to Borrow?
Borrowing 101 The BDC wants your business to succeed and in turn pay the BDC back. Our programs are revolving loan funds that require loans to be repaid so that we can lend our dollars to other businesses
More informationORGANIZATIONAL CHART FOR A TYPICAL LARGE REAL ESTATE COMPANY
ORGANIZATIONAL CHART FOR A TYPICAL LARGE REAL ESTATE COMPANY Senior Management At the senior management level, a large real estate development company is much like any other large corporation, with a chief
More informationEQUITY OFFICE ANNOUNCES FIRST QUARTER 2004 RESULTS
Two North Riverside Plaza, Suite 2100 Chicago, Illinois 60606 phone 312.466.3300 fax 312.454.0332 www.equityoffice.com Equity Office (Investors/Analysts): Diane Morefield 312.466.3286 Equity Office (Media):
More informationFederal Historic Rehabilitation Tax Credits. Cameron N. Cosby, Partner Hunton & Williams LLP
Federal Historic Rehabilitation Tax Credits Cameron N. Cosby, Partner Hunton & Williams LLP July 24, 2013 Topics Overview of Federal HTCs Application and Review Process Special Rules for Tax-Exempt Entities
More informationEnd Stage Renal Disease (ESRD)
End Stage Renal Disease (ESRD) AN OVERVIEW OF ESRD, TREATMENT COSTS & COVERAGE WSHIP Board Meeting January 14, 2015 Lisa Matthews and Sharon Becker 1 Kidney Disease Facts & Figures 1 in 10 people have
More informationDebt Service Analysis: Can I Repay?
Purdue Extension Knowledge to Go Debt Service Analysis: Can I Repay? Low prices and incomes have made many farmers and their lenders concerned about the farmers ability to fulfill debt obligations. Lenders
More informationDOWNTOWN BOND PROGRAM. Revolving Loan. Administered and Serviced by Eastern Savings Bank
DOWNTOWN BOND PROGRAM Revolving Loan Administered and Serviced by Eastern Savings Bank Revolving Loan Checklist Initial Meeting Date Application Personal Financial Statements Business Tax Returns Business
More informationRating Update: Moody's revises Rush University Medical Center Obligated Group's (IL) outlook to positive; A2 rating affirmed
Rating Update: Moody's revises Rush University Medical Center Obligated Group's (IL) outlook to positive; A2 rating affirmed Global Credit Research - 26 Aug 2013 Approximately $558M of rated debt outstanding
More informationHOSPITAL OF SAINT RAPHAEL
REPORT 20 - REPORT OF EACH JOINT VENTURE, PARTNERSHIP AND CORPORATION RELATED TO THE HOSPITAL (1) (2) (3) LINE DESCRIPTION AFFILIATE INFORMATION A. AFFILIATE NAME SAINT RAPHAEL HEALTHCARE SYSTEM, INC 1
More informationDebt Policy. I. Purpose of the Debt Policy
Debt Policy I. Purpose of the Debt Policy In support of its mission, (University) maintains a long term strategic plan. The strategic plan establishes University wide priorities as well as divisional programmatic
More informationECONOMIC DEVELOPMENT CORPORATION OF THE CITY OF FLINT
ECONOMIC DEVELOPMENT CORPORATION OF THE CITY OF FLINT Dear Applicant: Thank you for your interest in the Economic Development Corporation of the City of Flint loan program. Enclosed are the Commercial
More information15 th Annual Non Profit Health Care Investors Conference
15 th Annual Non Profit Health Care Investors Conference New York, New York May 21, 2014 William P. Santulli Executive Vice President, Chief Operating Officer Lee B. Sacks, M.D. Executive Vice President,
More informationFrom PLI s Course Handbook Private Equity Acquisition Financing Summit 2006 #10725. Get 40% off this title right now by clicking here.
From PLI s Course Handbook Private Equity Acquisition Financing Summit 2006 #10725 Get 40% off this title right now by clicking here. 2 ASSET-BASED FINANCINGS FOR ACQUISITIONS COUNTING ON YOUR ASSETS Seth
More informationResearch in Your Backyard. Illinois
Research in Your Backyard Pharmaceutical Clinical Trials Illinois Since 1999, 5,115 clinical trials have been conducted by biopharmaceutical companies in collaboration with research institutions in Illinois,
More informationDirector s Guide to Credit
Federal Reserve Bank of Atlanta Director s Guide to Credit This guide was created by the Supervision and Regulation Division of the Federal Reserve Bank of Atlanta, 1000 Peachtree Street NE, Atlanta,
More informationCITY OF GLENDORA ECONOMIC DEVELOPMENT LOAN/GRANT PROGRAM
CITY OF GLENDORA ECONOMIC DEVELOPMENT LOAN/GRANT PROGRAM The City of Glendora provides federal Community Development Block Grant (CDBG) funds for eligible economic development projects. The Economic Development
More informationUniversity of Kentucky
University of Kentucky Debt Policy Purpose To fulfill its mission, the University of Kentucky must make ongoing strategic capital investments in academic, student life, healthcare, and other plant facilities
More informationHigher Education Loan Authority of the State of Missouri. Student Loan Asset-Backed Notes, Series 2012-1
Higher Education Loan Authority of the State of Missouri Student Loan AssetBacked Notes, Series 20121 Fluctuations were noted in the Student Loan AssetBacked Notes, Series 20121 (20121 Bond) parity rates
More informationHEALTHCARE EXPANSION LOAN PROGRAM II (HELP II)
CALIFORNIA HEALTH FACILITIES FINANCING AUTHORITY HEALTHCARE EXPANSION LOAN PROGRAM II (HELP II) OVERVIEW LOW FIXED INTEREST RATE LOANS FOR CALIFORNIA S NON-PROFIT SMALL AND RURAL HEALTH FACILITIES 915
More informationUNITED STATES. SECURITIES AND EXCHANGE COMMISSION Washington, DC 20549 FORM 8-K
UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, DC 20549 FORM 8-K CURRENT REPORT Pursuant to Section 13 or 15(d) of the Securities Exchange Act of 1934 Date of Report (Date of earliest event
More informationSo You Want to Borrow Money to Start a Business?
So You Want to Borrow Money to Start a Business? M any small business owners cannot understand why a lending institution would refuse to lend them money. Others have no trouble getting money, but they
More informationSelect Medical Holdings Corporation Announces Results for Second Quarter Ended June 30, 2015
R E L E A S E FOR IMMEDIATE RELEASE 4714 Gettysburg Road Mechanicsburg, PA 17055 Select Medical Holdings Corporation Announces Results for Second Quarter Ended June 30, 2015 NYSE Symbol: SEM MECHANICSBURG,
More informationTHE ED PINCKNEY ENTER-PRIZE LOAN PROGRAM
THE ED PINCKNEY ENTER-PRIZE LOAN PROGRAM PURPOSE The purpose of the program is to provide financing to economically disadvantaged business owners or potential business owners. The loan proceeds are to
More informationVillage of Paw Paw Policy and Plan For Revolving Loan Fund
Village of Paw Paw Policy and Plan For Revolving Loan Fund The Finance Administrator shall deposit such monies available in separate fund, hereby created, entitled ARevolving Loan Fund@ hereinafter ARLF@.
More informationhospital capital spending
NOVEMBER 2009 healthcare financial management FEATURE STORY Thomas M. Schuhmann AT A GLANCE A recent study of changes in U.S. hospitals capital spending and financing disclosed that between 2001 and 2007:
More informationPublicly Registered Non-Traded Real Estate Investment Trust* Fourth Quarter Investor Presentation
Healthcare Trust, Inc. Publicly Registered Non-Traded Real Estate Investment Trust* Fourth Quarter Investor Presentation Risk Factors Risk Factors Investing in our common stock involves a high degree of
More informationREVISED DISCLOSURE REPORT DATED MAY 27, 2016 THE NEW YORK AND PRESBYTERIAN HOSPITAL FOR THE QUARTER ENDED MARCH 31, 2016
REVISED DISCLOSURE REPORT DATED MAY 27, 2016 THE NEW YORK AND PRESBYTERIAN HOSPITAL FOR THE QUARTER ENDED MARCH 31, 2016 This Disclosure Report is a revised version of the initial Disclosure Report for
More informationDebt Management. Policy/Procedure. I. Purpose
Debt Management Policy/Procedure I. Purpose This Debt Management Policy is designed to provide a useful framework by which decisions will be made concerning the use and management of debt but is not intended
More informationCurrent Funding Programs
Current Funding Programs FHA-HUD (221 d4 / 223 f / 223 a7 / 232) For Apartments, Apartment Rehabs, and Senior Housing Purchase, Refinance, Construction 80 to 85% Financing Rates Start in low 4 s 35 Year
More informationReport of Independent Auditors and Consolidated Financial Statements. Kaweah Delta Health Care District
Report of Independent Auditors and Consolidated Financial Statements Kaweah Delta Health Care District June 30, 2014 and 2013 CONTENTS MANAGEMENT S DISCUSSION AND ANALYSIS 1 16 PAGE REPORT OF INDEPENDENT
More informationNYCIDA PROJECT COST/BENEFIT ANALYSIS June 5, 2014
NYCIDA PROJECT COST/BENEFIT ANALYSIS June 5, 2014 APPLICANT Skyline Restoration Inc. CGI Northeast, Inc. Spring Scaffolding LLC Metropolitan Northeast LLC 11-20 37 th Avenue Long Island City, NY 11101