Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011

Similar documents
Bills of Quantity. D. Atkinson December Nature of Bills

PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS

[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices

Appendix 18 NEC3 Options

JCT Standard Building Contract SBC/Q

Schedule of Prices. Project Name Contract No. Contract Number

KITCHEN CONTRACT FOR WORK OVER $5000 COMPANY NAME: ADDRESS: DATE: CONTRACT PRICE: Please read all attached information and terms.

INSURANCE PROVISIONS

Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)

IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer

How To Write New Government Construction Contracts

The New Standard Construction Contracts: NZS3910, 3916 and 3917

How To Write A Contract

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES

means the period during which the Contractor is engaged by the Employment Business to render services to the Client.

TERMS OF ENGAGEMENT FOR LIMITED COMPANY CONTRACTOR

The amount to be included in any such application shall be the amount due to the Sub-Contractor from Cardy which shall be:

IRAINHAM STEEL I. Company Registration No...

CAPITAL & INFRASTRUCTURE BUILDING CONTRACT DIRECTIVE Copyright Reserved BCD.1 DATE: March 2014

Drain unblocking terms and conditions.

New-Gen Electrical (ABN ) Terms & Conditions

CLIENT / PROJECT MANAGER AGREEMENT

REQUEST FOR QUOTATION/ PURCHASE ORDER

General Terms and Conditions of the Association of Dutch Designers (BNO) February 2013

This innovative Scheme has been developed to resolve small claims disputes within the maritime industry.

Government of the Kingdom of Lesotho. Ministry of Public Works and Transport. Principal Building Agreement

BROOKFIELD GLOBAL INTEGRATED SOLUTIONS STANDARD PURCHASE ORDER TERMS FOR SUPPLIES

Schedule of 01 May 2015

NAB CONNECT MERCHANT TRANSACTION REPORTING SERVICE

Essex Recruitment Services: Terms of Engagement of Limited Company Contractors to Supply Workers to Clients (Opted Out) 1. Definitions 1.


TERMS AND CONDITIONS MAINTENANCE SERVICES. Value Added Asset Management Pty Ltd shall hereinafter be referred to as "Value Added Asset Management".

Borderland Fencing Centre - Credit Account Application Form

RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS

TERMS & CONDITIONS CONTRACTOR SERVICES

General Conditions of Contract for the Provision of Design and other Professional Services

GENERAL PURCHASING TERMS AND CONDITIONS

Conditions of Contract for CONSTRUCTION

Hong Kong Institute of Surveyors. Seminar on Conditions of Building Contract Questions and Answers Conducted by Mr. Colin B. Lee

Combar/CLLS Guidance note on the Agreement for the Supply of Services by a Barrister in a Commercial Case

What is a Standard of Booking

A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components

Activity Schedules in the NEC3 Engineering and Construction Contract

Standard Terms & Conditions for Supply of Software Development Services

Terms and Conditions of Sale

Lenovo Service Parts Sales Terms and Conditions New Zealand

JRI S STANDARD TERMS OF PURCHASE. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.

General Government Terms and Conditions for Public Service Contracts 2011 (ARVODI 2011)

Practice Note Deciding on the appropriate JCT contract

ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS)

3.0 ACCEPTANCE OF WORK

Standard forms: JCT 2005, NEC3 and the Virtual Contract

Breed Communications Limited - limited company consultancy agreement

General Terms and Conditions of the Association of Dutch Designers (BNO) January 2005

Baqqa Limited. Terms and Conditions

General Conditions Of Contract for Use in the Procurement and Erection of Plant at Site in the United Kingdom

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES

Module 5 Software Support Services TABLE OF CONTENTS. Version 3.1

TERMS AND CONDITIONS OF PURCHASE

Explaining an architect s services. General information on the usual tasks undertaken by an architect

Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer

BMT Tax Depreciation Pty Ltd - Terms of Engagement

Nominated Subcontractors on International Projects: Approaches to Risk Allocation

QUOTATION DOCUMENTS TERMS AND CONDITIONS OF AGREEMENT

Public Lecture at Engineers Ireland. How the Public Works Contracts might be used in the Private Sector

Jigsaw24 Support Contract Terms & Conditions

DATED 2016 [SURETY] and [CONTRACTOR] and SCHOOL OF ORIENTAL AND AFRICAN STUDIES PERFORMANCE BOND

Bendigo Rewards. Terms & Conditions. 21 December

Australian Standard. Amended from AS

Vocational Education and Training (VET) Pre-qualified Supplier (PQS) Agreement

TERMS & CONDITIONS 1. DEFINITIONS & INTERPRETATION DEFINITIONS

Guide to Procuring Construction Projects

PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED

ANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance

Terms & Conditions Verder B.V. ( ) Filed at the Chamber of Commerce on

MDB Harmonised Particular Conditions

AJM AUTOMATION LIMITED TERMS AND CONDITIONS OF TRADING. 1.1 Buyer means the person who buys or agrees to buy the Goods from the Seller

Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO

TERMS OF BUSINESS FOR THE SUPPLY OF TEMPORARY CONTRACTORS

Contract for Capital Purchase N [reference of the COMPANY]

DIRECTORATE OF ESTATES & FACILITIES

THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $ EDITION

GRTGAZ NETWORK TRANSMISSION CONTRACT

Construction Contracts

Request for Quote Number: PRC Baseball Diamond Backstop Re-Fence

Thames Water Utilities Limited. Settlement deed

RECOMMENDED MODEL AGREEMENTS BETWEEN HOUSING CONSUMERS AND HOME BUILDERS FOR THE CONSTRUCTION OF A HOME

GAS INDUSTRY ACT 2001 COST RECOVERY ORDER IN COUNCIL

Building Work Contractors Act 1995

NEC3: The Engineering and Construction Contract An overview

HONG KONG HOUSING AUTHORITY GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS 2013 EDITION

SPECIALIZED SEATING AND WINDOW EQUIPMENT FOR MODIFICATION OF PRISONER TRANSPORTATION VANS

NOTE: SERVICE AGREEMENTS WILL BE DRAFTED BY RISK SERVICES SERVICE AGREEMENT

Digital Web Company (UK) Ltd. Terms and Conditions

ANNEXURE TO Australian Standard Minor Works Contract Conditions (Superintendent Administered) AS Part A

REQUEST FOR PROPOSAL: GIS MANAGEMENT AND DESIGN SUPPORT: FOR UTILITY SERVICES OCTOBER 21, 2011 CITY OF ALEXANDRIA DIVISIONS OF FINANCE AND UTILITIES

Transcription:

Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee 21 March 2011 & 23 March 2011

Introduction Jonathan Brooks osborneclarke.com

osborneclarke.com Variations - introduction Obligations to comply Timing of notice before or after variation agreed? Notice condition precedent? Timing of assessment

Andrew Ash osborneclarke.com

osborneclarke.com What is a variation? What is a variation? The circumstances in which variations might arise: Instructions from the CA or Engineer Changes to drawings Changes in site/work management, methods and procedures e.g. changes in access or changes to site accommodation Employer requests Instructions to expend provisional sums Changes in Statutory Requirements and Regulations post formation of contract Contractor requests Discrepancies in and/or between contract documents Agreed tender assumptions proven to be incorrect Unforeseen ground conditions

osborneclarke.com Variation clauses Why do contracts need variation clauses? What happens if the additional work requested is outside the scope of the variation clause? Blue Circle Industries v Holland Dredging Co (1987) Contractor can refuse to carry out the work; or If the Contractor carries out the work separate contract - entitled to be paid reasonable remuneration not at contract rates

osborneclarke.com Conditions precedent instructions to carry out additional work to be "in writing" What if varied work has been carried out solely on the basis of an oral instruction but the contract stipulates that only orders in writing will be paid for? Any evidence of an instruction in writing? If not, who gave the oral instruction? Was the Employer aware the varied work was being carried out but said nothing at the time? Has there been any signal from the Employer or its authorised representative that strict compliance will not be required?

osborneclarke.com Time bar provisions Contactor's Notices (1) To encourage contemporaneous claim evaluation rather than post mortems Examples: FIDIC Clause 20.1 Contractor gives notice of claim within 28 days of becoming aware (or from when he/she should have been aware) of event or circumstances giving rise to claim NEC 3 rd Clause 61.3 Contractor notifies PM within 8 weeks of becoming aware of an event which has happened or which he expects to happen

osborneclarke.com Time bar provisions Contactor's Notices (2) Implications of failure to give notice on time: FIDIC extension of time or additional payment adjusted to take account of prejudice caused NEC 3 rd Contractor not entitled to a change in the Price, the Completion date or a Key Date (unless the Compensation event is one which the PM should have notified but did not)

osborneclarke.com The impact of notice provisions on the Contractor Need for close and urgent scrutiny of drawings for changes and discrepancies at the outset Observant and experienced site staff looking out for change plus more site visits Programmers now an essential and ongoing part of the team Need to increase size of dedicated project claims team Need to step notice provisions down into sub-contracts

Tim Tapper

Practical Issues Tim Basic Principles Provisional Sums Preliminaries Errors The Contractor s QS and the PQS Stuart Fair Rates Omissions Dayworks Presentation Variations after PC

Basic Principles JCT 5.1 alteration or modification of the design, quality or quantity of the Works 5.2 the imposition by the Employer of any obligation or restriction Valuation principles 5.9 impact on other work NEC List of 19 CEs wider than JCT

Provisional Sums JCT concept Two types Defined due allowance for programming, planning and pricing prelims. Undefined no allowance required What happens when it says its defined and it isn t? What happens when the BQ says all provisional sums are deemed to be defined?

Preliminaries in Variations Try to include as much as you can NEC all included anyway (no procedure for separate claims) JCT 5.6.3.3 allowance, where appropriate shall be made for any additions to or reduction of preliminary items of the type referred to in the SMM

Errors in BQ 1. Contractor has underpriced a rate and then receives a variation for more. 2. Extension of rate x quantity is incorrect. 3. Error in quantity in lump sum BQ.

The Contractor s QS and the PQS

Stuart McGee

Valuation at Fair Rates JCT 2005 Without Quantities Clause 5.6.1.2 where the work is not of similar character to work set out in the Contract Documents, it shall be valued at fair rates and prices. GC Works 1 Clause 42.5(c) if it is not possible to value as sub paragraph (b) then by measurement and valuation at fair rates and prices, having regard to current market prices NEC does not have an equivalent clause as adjustments are based on Defined Cost

Valuation at Fair Rates Henry Boot Construction Ltd v Alstom Combined Cycles Ltd [1999] ABC.L.R. 01/22 HHJ Humphrey Lloyd QC decided generally means a valuation which will not give the contractor more than his actual costs reasonably and necessarily incurred plus similar allowances for overheads and profit In Weldon Plant Ltd v The Commission for New Towns [2000] EWHC Technology 76 a fair valuation must, in the absence of special circumstances include an element on account of profit.

Valuation of Omissions JCT 2005 without Quantities Clause 5.6.2 To the extent that a Valuation relates to the omission of work set out in the Contract Documents and subject to clause 5.8 in the case of CDP works, the valuation of the work omitted shall be in accordance with the rates, prices or amounts in the Priced Documents. NEC 3 Core clause 63.2 If the effect of a compensation event is to reduce the total Defined Cost, the prices are not reduced except as stated in this contract. Omissions -JCT Valued at contract rates or prices Loss of profit is not recoverable Unless omitted work given to another Will also include adjustment of Preliminary type items NEC Omission based upon Defined Cost unless otherwise agreed

Dayworks - When should they be used? JCT 2005 Without Quantities Clause 5.7 Where the execution of additional or substituted work cannot be valued in accordance with clause 5.6 or 5.8 [CDP works] as applicable the Valuation shall comprise: 1 the prime cost of such work.. together with Percentage Additions to each section of the prime cost at the rates stated When Works are not of similar character to work included in the contract documents Works are not executed in similar conditions to work included in the contract documents There is a significant change in quantities A variation quotation has not been issued Varied work cannot be properly valued by measurement such as disruption, relocation of operatives, changed access provisions or unique works.

Presentation of variation account Timing JCT Asap after instruction issued or works completed NEC Within three weeks of being instructed to do so Methodology Comply with Contract procedures Common system with client QS Update on a regular basis not less than monthly Clearly schedule and reference all amendments Ensure QS has acknowledged receipt Be consistent in format and content

Presentation of variation account Evidence Prepare the variation assuming it will be disputed and will be referred to Adjudication. Minimum Requirements Narrative Instruction to vary the works Quantities (inc dimensions) Rates extracts of BoQ s, build up to star rates, invoices or quotations Drawings and specifications Preliminary costs Photographs Notices and correspondence

Variations after Practical Completion Architect/EA unable to instruct as contract is at an end Unless agreement between Employer/Contractor Preferable for Contractor for works to be a separate order/contract Should be Quoted by Contractor or Based on schedule of rates Consider implications on design liability, warranty s, insurances Generally increased risk for Contractor with very little reward

Questions www.cyrilsweett.com