This is the author s version of a work that was submitted/accepted for publication in the following source:



Similar documents
This is the author s version of a work that was submitted/accepted for publication in the following source:

This is the author s version of a work that was submitted/accepted for publication in the following source:

THE FIRTH V SUTTON DECISIONS

CONTRACTUAL INDEMNITY CLAUSES. Tony Kulukovski Thompson Cooper Lawyers 21 November 2011

THE SECOND HARBOUR TUNNEL. A case study illustrating recent issues in construction insurance

LAW REFORM (CONTRIBUTORY NEGLIGENCE) AMENDMENT BILL 2001

the defendant owed the plaintiff a duty of care; the plaintiff suffered damage as a result of the defendant's breach of duty (causation); and

Defective works: No duty of care decision

CASE EXAMPLES CONTRACTUAL INDEMNITIES & OBLIGATIONS TO INSURE

Summary Guide for Chapter 6. Foundations of Australian Law. Fourth Edition. Callie Harvey

How To Prove Negligence In A Fire Door Case

Supreme Court of New South Wales -- Court of Appeal Giles, Hodgson JJA and Handley AJA CA40313/ April, 15 May 2008

TIME LIMITS ON LOANS PAYABLE ON DEMAND SEMINAR FOR THE INNER WEST LAW SOCIETY 17 FEBRUARY 2010 EFFENDY RESTAURANT, BALMAIN BY EDMUND FINNANE 1

Erect Safe Scaffolding (Australia) Pty Limited v Sutton (6 June 2008)

IN THE SUPREME COURT OF TEXAS

Assessing Damages Under Section 151Z: An Interaction of Schemes

How To Sue An Employer For Negligence

Introduction Page to the Appellant s PDF Factum:

Case Note by Paul Ryan February 2014

HIGH COURT OF AUSTP.ALIA FILED 2 0 JAN 2012 THE REGISTRY SYDNEY APPELLANT'S SUBMISSIONS

Australian Proportionate Liability Regime

CASE COMMENT. by Craig Gillespie and Bottom Line Research

Section 54(1) of the Insurance Contracts Act 1984 (Cth)

HIGH COURT OF AUSTRALIA

Pay-When-Paid Clauses

NEGLIGENCE AND INTOXICATION HAS CIVIL LIABILITY REFORM GONE TOO

SPANDECK ENGINEERING V DEFENCE SCIENCE AND TECHNOLOGY AGENCY

Legal Practitioners Negligence Liability for Claim Investigation and Advice

SAFETY REVIEW NOT SPECIFIED IN CONTRACT

2014 IL App (1st) U No February 11, 2014 Modified Upon Rehearing April 30, 2014 IN THE APPELLATE COURT OF ILLINOIS FIRST DISTRICT

South Australia LAW REFORM (CONTRIBUTORY NEGLIGENCE AND APPORTIONMENT OF LIABILITY) ACT 2001

REPUBLIC OF SOUTH AFRICA

COMMON LAW PRACTICE UPDATE 46

FIRE ON THE ICE: RECENT DEVELOPMENTS IN THE LAW OF NEGLIGENCE REGARDING CAUSATION

Murrell v Healy [2001] ADR.L.R. 04/05

In Queensland and Western Australia, there is no qualification that the peer professional opinion must be widely accepted in Australia.

QUT Digital Repository:

State v. Stonington Insurance Co., No Wncv (Toor, J., June, 29, 2006)

Don t Be Lost: Different Conceptions of Loss in Insurance

COMMON LAW PRACTICE UPDATE 47

IN THE SUPREME COURT OF BRITISH COLUMBIA

Recent changes to the Home Building Act, 1989 and Home Warranty Insurance

EASTERN CARIBBEAN SUPREME COURT IN THE COURT OF APPEAL. and LUCA POZZONI. 2014: July 8; September 16.

JAMAICA THE HON MR JUSTICE MORRISON JA THE HON MR JUSTICE BROOKS JA THE HON MS JUSTICE LAWRENCE-BESWICK JA (AG) BETWEEN GODFREY THOMPSON APPELLANT

Defective Work Claims

FACT PATTERN ONE. The following facts are based on the case of Bedard v. Martyn [2009] A.J. No. 308

RE: ONTARIO LTD. c.o.b. as SHOELESS JOE S Plaintiff v. INSURANCE PORTFOLIO INC. and CHRISTOPHER CONIGLIO. Defendants v.

Recent Developments in Indemnities

Reports or Connecticut Appellate Reports, the

The Duty of Solicitors to Give Tax Advice - A Rebuttal of the Reply

Setting the Standards for Medical Negligence: The Bolam test post Rogers v Whitaker.

Indefeasibility, boxing, the apportionment of tortious loss, the rebels and a building in Enmore the Vella decisions

COMMON LAW CASE UPDATE 6 - THE NOMINAL DEFENDANT AND UNREGISTERED MOTOR VEHICLES

In The Court of Appeals Fifth District of Texas at Dallas. No CV

Chapter 4 Crimes (Review)

Barings v Coopers & Lybrand; Johnson v Gore Wood; Standard Chartered Bank v Pakistan National Shipping Corp: Some Temporary Relief for Auditors?

MEDICAL NEGLIGENCE ANNUAL CASE REVIEW MEDICAL NEGLIGENCE 2009/2010. Ian Butcher, barrister 1

THE SUPREME COURT OF APPEAL OF SOUTH AFRICA

2011 Television Education Network Pty Ltd and Wendy Kayler-Thomson, Forte Family Lawyers

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA FIRST APPELLATE DISTRICT DIVISION FOUR A136605

Duty of Care. Kung Fu Instructor in Training Program. Shaolin Guardian Network

2013 IL App (3d) U. Order filed September 23, 2013 IN THE APPELLATE COURT OF ILLINOIS THIRD DISTRICT A.D., 2013

(ii) Competitors to Spectators

EMPLOYEE OR CONTRACTOR?

Settlement of Claims without an Insurer's Consent. February 08, 2006

DAMAGES FOR DISAPPOINTMENT & DISTRESS: DAMAGES FOR BREACH OF CONTRACT OR PERSONAL INJURY DAMAGES THE IMPACT OF THE CLA SHARON MILTON

Case Comment: Hardie v Kamloops Towne Lodge Ltd 2014 BCSC 955

Professional Negligence

Chapter IV INTRODUCTION

ARE FUND MANAGEMENT APPLICATIONS STILL A GRAY AREA?

STATE OF MICHIGAN COURT OF APPEALS

Personal Injuries: A Practical Introduction

S.116 Of The Courts of Justice Act Can Defendants Impose A Structured Settlement on the Plaintiff? Robert Roth

Sample Tort Law Problem Question

WHAT=S THE DEAL WITH GENERAL AND SPECIAL DAMAGES? By William E. McNally and Barbara E. Cotton 1

Complaint - Walmart Substance on Floor in Frozen Food Dept.

Costs Payable in Personal Injury Claims under the Various Legislative Regimes by Paul Garrett

IN THE SUPREME COURT OF IOWA

2015 IL App (1st) U. No IN THE APPELLATE COURT OF ILLINOIS FIRST JUDICIAL DISTRICT

Citation: Sadler, Pauline and Guthrie, Rob Sports Injuries and the Right to Compensation. Legal Issues in Business 3: 9-14.

BUSINESS LAW GUIDEBOOK

STATE OF OHIO ) IN THE COURT OF APPEALS NINTH JUDICIAL DISTRICT COUNTY OF WAYNE ) DECISION AND JOURNAL ENTRY

An Introduction to Work Injury Damages

Global Guide to Competition Litigation Poland

Termination of Contract: A practical guide on when and how to terminate a contract and common mistakes

Case 2:09-cv JPH Document 23 Filed 02/02/10 Page 1 of 7 IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

Controlling Liability To Passive Sufferers Of Negligent Misstatements

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE December 02, 2014 Session

LOUISIANA PERSONAL INJURY ACCIDENT BASICS

Offers of Compromise and Calderbank offers in civil litigation

Andrew Thurlow & Suzanne Innocenzi v The Architect Studio Pty Ltd [2008] NTMC 005 THE ARCHITECT STUDIO PTY LTD

Transcription:

This is the author s version of a work that was submitted/accepted for publication in the following source: Stickley, Amanda P. (2010) Assessment of damages for property damage. Queensland Lawyer, 30(2), p. 68. This file was downloaded from: http://eprints.qut.edu.au/46784/ c Copyright 2010 Thomson Reuters (Australia/NZ) Notice: Changes introduced as a result of publishing processes such as copy-editing and formatting may not be reflected in this document. For a definitive version of this work, please refer to the published source:

QUT Digital Repository: http://eprints.qut.edu.au/ This is the author version published as: This is the accepted version of this article. To be published This is the author version published as: Assessment of damages for property damage Catalogue from Homo Faber 2007 In Gagner Pty t/as Indochine Café v Canturi Corporation Pty Ltd (2009) 262 ALR 691, the assessment of damages awarded for the rectification work to the premises of the respondent was in issue. The appellant operated a restaurant above the respondent s jewellery store in Sydney. When the kitchen of the restaurant flooded, water escaped causing damage to the jewellery store s fit-out. The escape of the water Abstract was held to be due to the negligence of persons for whom the appellant was vicariously liable. The trial judge awarded damages, measured by the amount required to return the premises as close as was possible to the condition prior to the flood damage as well as an allowance for interruption to the business for 10 days. The 10 day allowance reflected the number of days the store would have been closed for if it was to be B

ASSESSMENT OF DAMAGES FOR PROPERTY DAMAGE In Gagner Pty t/as Indochine Café v Canturi Corporation Pty Ltd (2009) 262 ALR 691, the assessment of damages awarded for the rectification work to the premises of the respondent was in issue. The appellant operated a restaurant above the respondent s jewellery store in Sydney. When the kitchen of the restaurant flooded, water escaped causing damage to the jewellery store s fit-out. The escape of the water was held to be due to the negligence of persons for whom the appellant was vicariously liable. The trial judge awarded damages, measured by the amount required to return the premises as close as was possible to the condition prior to the flood damage as well as an allowance for interruption to the business for 10 days. The 10 day allowance reflected the number of days the store would have been closed for if it was to be returned to its previous condition. The evidence was that the flooding has only affected approximately 10% of the floor area of the store. However, instead of having work carried out to bring the premises back to its condition as before the water damage, the respondent closed the business for 29 working days for a complete internal refurbishment at a cost substantially more than simple rectification. On appeal it was argued that the trial judge had assessed the damages incorrectly as by undertaking a complete refurbishment had the effect that the respondent did not suffer any loss as a consequence of the negligence in relation to the fit-out. It was asserted that the claim for damages was in the circumstances a claim for betterment. It was also argued that the damages should not include a component for GST. Campbell JA gave reasons, with Macfarlan JA and Sackville AJA agreeing. OVERCOMPENSATION? Before the Court of Appeal the appellant criticised the trial judge s assessment because the damages she had allowed were theoretical, the argument being that they were damages for work that never was carried out and for loss of trade for the completion of that work: at [32]. The court was referred to cases in which damages were claimed for breach of contract where the defendant (builder or architect) had carried out defective work. The appellant argued that these authorities established that if rectification of the property could not occur, no damages could be awarded on the basis that rectification work could be carried out. Campbell JA examined a number of these cases. 1 His Honour then noted that all of these cases were considering rectification work not being carried out because the plaintiff was unlikely to rectify the defects, in the sense that the property remained in the defective condition : at [88]. In the case before the court, this was not the scenario as the respondent had rectified the damaged property, just not to the same condition as prior to the flood. The flood caused the respondent to suffer damage and it was reasonable for the respondent to rectify the damage and claim the damages: at [88]. Campbell JA, noting that the cases examined were contractual cases, discussed cases which measured damage for tortious damage to property. 2 His Honour concluded: What counts as making good the damage, for the purpose of assessing damages for torts, needs to be understood bearing in mind what the purpose is for which one is asking what counts as making good. That purpose is ascertaining what the work is that is necessary to undo the 1 Bellgrove v Eldridge (1954) 90 CLR 613; Director of War Service Homes v Harris [1968] Qd R 275; De Cesare v Deluxe Motors Pty Ltd (1996) 67 SASR 28; Central Coast Leagues Club Ltd v Gosford City Council (unreported, NSWSC, Giles CJ Comm D, 9 June 1998, BC9802257); Hyder Consulting (Aust) Pty Ltd v Wilh Wilhelmsen Agency Pty Ltd [2001] NSWCA 313; Scott Carver Pty Ltd v SAS Trustee Corporation [2005] NSWCA 462; Westpoint Management Ltd v Chocolate Factory Apartments Ltd [2007] NSWCA 253; UI International Pty Ltd v Interworks Architects Pty Ltd [2007] QCA 402; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272. 2 Murphy v Brown (1985) 1 NSWLR 131; South Parklands Hockey & Tennis Centre Inc v Brown Falconer Group Pty Ltd (2004) 88 SASR 65; Kirkby v Coote [2006] QCA 61; Lodge Holes Colliery Co Ltd v Wednesbury Corporation [1908] AC 323; Minter v Eacott (1952) 69 WN (NSW) 93; Evans v Balog [1976] 1 NSWLR 36; Hollebone v Midhurst and Fernhurst Builders Ltd [1968] 1 Lloyd s Rep 38.

consequences of the tort having been committed. The only interest of the defendant that bears upon the question of whether rectification work is reasonable is a financial one, sometimes expressed in the principle that a plaintiff must mitigate his damage. The cost of making good is merely one way of putting a dollar figure on the damage that the plaintiff has suffered, for the purpose of carrying through the compensatory principle. There are circumstances, of which the present is one, when the fact that money has not been spent on the precise items that would need to be acquired to restore property to its pre-damage condition does not prevent the cost of acquiring those items being the appropriate way of giving effect to the compensatory principle. Similarly, in circumstances where profits have been lost as a result of the shop being closed during the time it took to undertake the (loose sense) rectification that was carried out, and a lesser time would have involved in effecting a (precise sense) rectification, the appropriate quantum for loss of profits is the profits that would have been lost during the lesser of those times: at [105]-[106]. The appellant argues that the refurbishment of the shop was not an act of making good the damage but rather separate and distinct action, derived from the respondent s pre-existing intention to refurbish the ship premises. Campbell JA made an analogy with an injured plaintiff who voluntarily seeks medical treatment which is completely successful, stating that in that situation the plaintiff can still recover damages to the extent that they have been caused by the tort in the period up to the effecting of the successful cure, including the costs of obtaining that cure at [109]. The fact that the respondent took the opportunity to refurbish the shop did not mean that the premises had not been damaged by the flood water. The flood water was one of the causes of the refurbishment and Campbell JA stated: To the extent to which there were contributing causes besides the water damage, it was the judge s task to assess the compensation that would make good those consequences properly attributable to the flooding. This she did by allowing the amount that a precise rectification of the water damage alone would have cost, and leaving the respondent to bear any amount it had spent in excess of that: at [111]. The appellant also alleged that the trial judge had erred by not taking into account the benefits gained by the respondent from the refurbishment. The compensatory principle requires an account to be taken if an award of damages confers a benefit. 3 There was no evidence that the respondent s business was more profitable due to the refurbishment or in any other way more valuable than it would have been if the damage had never occurred: at [127]. Unlike the case of Hoad v Scone Motors Pty Ltd, the respondent s business was not about to close so that the refurbishment would add sale value, thereby conferring a benefit. Campbell JA upheld the trial judge s assessment, stating: to the extent that the installation of the new fitout was more than the respondent needed to do to make good the damage caused by the flooding, it cannot recover the full cost of the fitout, but it has not claimed the full cost of the fitout, and the judge has endeavoured to find the means of measuring the extent to which the respondent has suffered damage caused only by the flooding: at [127]. GST? The trial judge had included in her assessment of damages an amount to reflect GST. The appellant argued that there should not be an allowance for GST as at all times the respondent was a trading corporation registered for GST purposes. Therefore any payment of GST could be claimed back by the respondent as there would be no permanent loss. Campbell JA went through in detail the relevant provisions of the A New Tax System (Goods and Services Tax) Act 1999 (Cth) and held that any goods or services paid for the purpose of improving the respondent s shop s appearance or usability was a creditable purpose as under s 11-5 of the Act, allowing the GST to be claimed back: at [140]-[145]. Therefore even though the 3 Harbutt s Plasticine Ltd v Wayne Tank and Pump Co Ltd [1970] 1 QB 447; British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co Ltd [1912] AC 673; Hoad v Scone Motors Pty Ltd [1977] 1 NSWLR 88.

respondent may pay GST on the refurbishment, it was entitled to recover that amount and therefore, the amount of GST component of any payments it made for making good the premises would not ultimately be a loss that it suffered : at [147]. As such, GST should not have been included in the assessment of damages by the trial judge. Amanda Stickley