DCMA EVMS COMPLIANCE REPORT I LOCKHEED MARTIN AERONAUTICS CO.



Similar documents
IT Baseline Management Policy. Table of Contents

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC

Supplier Risk Management. Presented By Bill Gibson, DCMA HQ Date: May 2001

July 6, (1) CHAPTER 11

Defense Logistics Agency INSTRUCTION

DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule

Achieving Desired Results with Less: Supply Chain Management. Vincent Feck, Colonel, USAF Commander DCMA Lockheed Martin Fort Worth

The Program Managers Guide to the Integrated Baseline Review Process

Government Contracting and Earned Value Management (EVM)

DEPARTMENT OF DEFENSE Defense Contract Management Agency INSTRUCTION. Defense Acquisition Executive Summary (DAES)

Scheduling Process Maturity Level Self Assessment Questionnaire

Recognizing and Mitigating Risk in Acquisition Programs

Click to edit Master title style

Report No. DoDIG April 27, Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support

DCAA Perspective: Key Subcontracting Practices for Maintaining Approved Business Systems Accounting System and Estimating System

Validating Third Party Software Erica M. Torres, CRCM

Status of Enterprise Resource Planning Systems Cost, Schedule, and Management Actions Taken to Address Prior Recommendations

Design and Development of Dallas/Fort Worth International Airport s [DFW s] Compliance-Focused Environmental Management System [EMS] 1

ROOT CAUSE ANALYSIS CONTRACT AND PROJECT MANAGEMENT APRIL 2008

The Changing Government Contractor Environment

Overview of SAE s AS6500 Manufacturing Management Program. David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM david.karr@us.af.

Evaluation of Defense Contract Management Agency Actions on Reported DoD Contractor Business System Deficiencies

Contractor Purchasing System Review (CPSR)

Earned Value Management Systems Application Guide

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

DOD BUSINESS SYSTEMS MODERNIZATION. Additional Action Needed to Achieve Intended Outcomes

F 35 Lightning II Program Quality Assurance and Corrective Action Evaluation

Systems Thinking in DoD Program Management

The following slides are not contractual in nature and are for information purposes only as of June 2015.

DCAA Initiatives/Current Issues

FOREWORD. Page 2 of 88

Earned Value Management Tutorial Module 1: Introduction to Earned Value Management. Prepared by:

Allegations of the Defense Contract Management Agency s Performance in Administrating Selected Weapon Systems Contracts (D )

GAO DEFENSE CONTRACT MANAGEMENT AGENCY. Amid Ongoing Efforts to Rebuild Capacity, Several Factors Present Challenges in Meeting Its Missions

Earned Value Management Systems Application Guide

STRENGTHENING DEPARTMENT OF DEFENSE LABORATORIES David Graham, Robert Leheny, and Susan Clark-Sestak

Strategic Implications of the New DFARS Business System Rule Co-presented by Venable LLP and Argy, Wiltse & Robinson June 12, 2012

Program Management Office Provided Adequate Oversight of Two Contracts Supporting the Defense Enterprise Accounting and Management System

GAO DEFENSE CONTRACT AUDITS. Actions Needed to Improve DCAA's Access to and Use of Defense Company Internal Audit Reports

Property Management System (GPMS)

Introduction to AS 9100

BETTER BUYING POWER 2.0 INITIATIVES DESCRIPTIONS

FEDERAL HOUSING FINANCE AGENCY ADVISORY BULLETIN AB OVERSIGHT OF SINGLE-FAMILY SELLER/SERVICER RELATIONSHIPS. Purpose

Review of Audits Issued by the Defense Contract Audit Agency in FY 2012 and FY 2013

GAO DCAA AUDITS. Allegations That Certain Audits at Three Locations Did Not Meet Professional Standards Were Substantiated

Government Contractor Business Systems and Overview of System Assessments

Department of Defense Fiscal Year (FY) 2016 President's Budget Submission

The Devil is in the Details Compliance with the Business Systems Rule

to Asset Management Policy and Guidance Draft Version July 2015

TOPIC NO TOPIC Supplies and Materials Inventory Table of Contents Overview...2 Policy...4 Procedures...8 Internal Control...

PURCHASE ORDER TERMS AND CONDITIONS FOR MANUFACTURING MANAGEMENT PROGRAMS MIL-STD-1528A APPENDIX 2

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT Approval Date:

Training Seminars. Description. Core Courses: The core courses consist of the following:

PROJECT MANAGEMENT AND THE ACQUISITION OF MAJOR SYSTEMS

GUIDANCE FOR MANAGING THIRD-PARTY RISK

Audit Quality Thematic Review

GAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices

Change Control Management Guide

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

Master Document Audit Program. Version 7.4, dated November 2006 B-1 Planning Considerations. Purpose and Scope

Fundamentals of Measurements

What Exactly is an Acceptable Accounting System?

CONTACT: 1. Proposed rule BDO GOVERNMENT CONTRACTING PRACTICE GUIDANCE ON THE PROPOSED DOE BUSINESS SYSTEM RULE

How To Write Ansi/Eia Evm System Acceptanceance Guide

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I

FCPA 10 Hallmarks Self- Assessment

a GAO GAO DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting Issues Remain

PROJECT MANAGEMENT PLAN CHECKLIST

Risk Management. Software SIG. Alfred (Al) Florence. The MITRE. February 26, MITRE Corporation

ISO/IEC QUALITY MANUAL

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G A, Appendix A, )

GAO DEFENSE CONTRACTING. Contract Risk a Key Factor in Assessing Excessive Pass-Through Charges. Report to Congressional Committees

Quality Assurance Program Plan. July U.S. Department of Energy Office of Legacy Management

Risk Mitigation and Subcontract Management

PROGRAM MANAGEMENT IN DEFENSE SYSTEMS

Material Transfers and Material Management and Accounting System (MMAS)

Program and Project Management Practices in the Federal Civilian Agencies

DOD DIRECTIVE CLIMATE CHANGE ADAPTATION AND RESILIENCE

SUPERVISION GUIDELINE NO. 9 ISSUED UNDER THE AUTHORITY OF THE FINANCIAL INSTITUTIONS ACT 1995 (NO. 1 OF 1995) RISK MANAGEMENT

Transcription:

POST ACCEPTANCE REVIEW FOR CAUSE COMPLIANCE REPORT FOR THE LOCKHEED MARTIN AERONAUTICS COMPANY FORT WORTH, TEXAS PREPARED BY: DEFENSE CONTRACT MANAGEMENT AGENCY (DCMA) EARNED VALUE MANAGEMENT (EVM) CENTER REPORT NUMBER CTR-2007-002 ALEXANDRIA, VA I PATUXENT RIVER, MD PREPARED FOR: OFFICE OF THE UNDER SECRETARY FOR DEFENSE FOR ACQUISITION, TECHNOLOGY, & LOGISTICS NOVEMBER 19, 2007 >1

TABLE OF CONTENTS PREFACE EXECUTIVE SUMMARY RECOMMENDATIONS 3 4 5 SECTION A. INTRODUCTION BACKGROUND 7 TEAM ROSTER EVM POLICY 9 OBJECTIVES 10 SCOPE 10 METHODOLOGY GUIDELINE RATINGS SECTION B. MAJOR SUMMARY FINDINGS SECTION C. ANSI-748 GUIDELINE ASSESSMENT 10 11 13 20 >2

PREFACE Earned Value Management (EVM) plays an increasingly important role for successfully delivering acquisition programs at the desired cost, schedule, and technical performance levels. Since 1996, when the Defense Contract Management Agency (DCMA) was appointed DoD Executive Agent for Earned Value Management Systems (EVMS), the responsibility to oversee the Department's primary program management process has never been more vital than it is today. In its simplest form, EVM is the discipline of managing programs successfully by planning and controlling authorized work to achieve cost, schedule, and performance objectives. EVM places special emphasis on efficiently and effectively executing work through the development and operation of management control system that includes people, systematic processes, and innovative tools and techniques. The intent of EVM is to help program managers, and the teams who support them, be successful by allowing them to operate productively in the high-risk environments surrounding them. Input* Output >3

EXECUTIVE SUMMARY The DCMA EVMS compliance review, conducted 20-31 August 2007, found that Lockheed Martin Aeronautics Company (LM-Aero), Fort Worth, Texas, is not following, nor consistently applying, the American National Standard Electronic Industries Alliance Earned Value Management Systems (ANSI/EIA-748-A) guidelines during the execution of Department Programs. The findings of the review indicate that, under LM-Aero stewardship, the utility of the EVMS has declined to a level where it does not serve its intended purpose and the government is not obtaining useful program performance data to anticipate and mitigate program risks. Key LM-Aero EVMS processes and procedures are below standard and do not provide the requisite definition and discipline to properly plan and control complex, multibillion dollar weapon systems acquisition programs. Documented findings indicate that a large percentage of LM-Aero Control Account Managers (CAM) are disconnected from basic LM-Aero EVMS functions and ran not satisf actorily demonstrate that they understand and use documented EVM processes, procedures and tools to manage their work. These weaknesses adversely impact the validity of the data used in internal and external decision-making processes and are fully discussed in this report. Specifically, LM-Aero was found to be non-compliant in 19 of 32 industry guidelines. Significant findings, resulting in lack of planning and control disciplines include: Using vague and confusing EVMS documentation; Lack of clearly delineated roles and responsibilities; Using management reserve to alter internal and subcontract performance levels and overruns; Work authorization and change control processes that do not extend to appropriate levels; Cost and schedule integration problems that undermine the validity of data; Inappropriate earned value techniques used for the assessment of material, subcontracts, and rework; and The inability of LM-Aero CAMs to demonstrate a working level understanding of key EVMS processes including the definition and use of a > 4

program critical path, situational awareness of cost and schedule variances for course correction, and the substantiation of completion cost estimates. These and the other identified deficiencies raise significant concerns regarding LM-Aero management processes and practices and the Company's ability to mitigate emerging cost and schedule issues in a timely manner. Because the accuracy and validity of LM-Aero performance measurement data is suspect, the Department's ability to use EVM data to determine product delivery dates and to develop timely and accurate estimates of program completion costs is adversely impacted. It was apparent during discussions with LM-Aero CAMs that their involvement in performing their EVM responsibilities was superficial at best. Most CAM functions are being performed, with little management control, by the business operations personnel assigned to Integrated Product Teams (IPT). The result is a serious deterioration of system discipline. This undisciplined approach to program management and towards the maintenance of the EVMS, will ultimately jeopardize the long-term stability of LM-Aero programs at Fort Worth, Texas facilities and diminishes the purchasing power of the Department. Given the nature of the risks involved in the achievement of programmatic objectives, the LM-Aero management systems and processes reviewed did not provide reasonable assurance that established Department objectives for supplier EVMS would be achieved. Therefore, we believe significant corrective actions are needed immediately to help ensure compliance with applicable regulations, policies and procedures, and good business practices. RECOMMENDATIONS We recommend that: 1. Under Secretary of Defense for Acquisition, Technology, and Logistics should establish incentives for implementing and maintaining EVM Systems. For all new contracts include a contract clause for withholding up to 5-10 percent from supplier payments for failure to adequately implement and maintain a validated EVM System. For existing contracts, add a provision within the program award fee plan to establish similar incentives; 2. Lockheed Martin should review each LM-Aero location to ensure that the LM-Aero EVMS is properly implemented and that LM-Aero Fort Worth, TX findings are not systemic throughout the LM-Aero division; >5

3. LM-Aero and the Program Management Office should jointly develop and provide to the DCMA, no later than February 8, 2008, a plan of corrective action plan and milestones to address all compliance and program application issues in order to retain EVMS certification. The corrective action plan should contain a root cause analysis of system deficiencies and include measurable steps to correct them. The action plan should conclude with a follow-on compliance review in 4Q CY2008; 4. DCMA CMO Fort Worth should notify relevant Department stakeholders, including service SAE and PEO of the results of the compliance review and next steps; and 5. DCMA CMO Fort Worth should develop and adopt a risk based staffing approach to ensure for the proper levels of oversight needed for supplier EVMS implementation. >6