AUDIT REPORT INTERNAL AUDIT DIVISION. Vendor payment process in MONUSCO



Similar documents
AUDIT REPORT INTERNAL AUDIT DIVISION. Invoice Processing in UNAMID. Internal controls over invoice processing were inadequate and ineffective

AUDIT REPORT INTERNAL AUDIT DIVISION. Asset management at the UNHCR operations in Georgia

AUDIT REPORT. Services provided by the United Nations International Computing Centre to the UN Secretariat - Department of Field Support

AUDIT REPORT Audit of contracts management in UNMIS

REPORT 2016/035 INTERNAL AUDIT DIVISION

EXECUTIVE SUMMARY Audit of vendor database management in UNOG

REPORT 2016/045 INTERNAL AUDIT DIVISION. Audit of contracts management in the African Union-United Nations Hybrid Operation in Darfur

REPORT 2016/057 INTERNAL AUDIT DIVISION

EXECUTIVE SUMMARY Audit of information and communications technology governance and security management in MINUSTAH

REPORT 2016/061 INTERNAL AUDIT DIVISION. Audit of inventory management in the United Nations Interim Force in Lebanon

REPORT 2016/047 INTERNAL AUDIT DIVISION. Audit of the operations in Egypt for the Office of the United Nations High Commissioner for Refugees

AUDIT REPORT 2013/024

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/064. Audit of air transportation management in the United Nations Mission in South Sudan

REPORT 2016/066 INTERNAL AUDIT DIVISION. Audit of management of technical cooperation projects in the Economic Commission for Africa

EXECUTIVE SUMMARY Horizontal audit of data privacy in the United Nations Secretariat

AUDIT REPORT INTERNAL AUDIT DIVISION. UNJSPF Disability Benefits

AUDIT REPORT INTERNAL AUDIT DIVISION. UNHCR's relationship with implementing partners

AUDIT REPORT INTERNAL AUDIT DIVISION. Audit of non-expendable property at Headquarters

OVERALL RATING: PARTIALLY SATISFACTORY

AUDIT REPORT INTERNAL AUDIT DIVISION. Medical stores and equipment in UNMIS

AUDIT REPORT INTERNAL AUDIT DIVISION. Audit of UNCTAD Technical Cooperation Project Strengthening the Debt Management Capacity of Developing Countries

REPORT 2014/078 INTERNAL AUDIT DIVISION

AUDIT REPORT. Audit of the UNOG contracts for furniture supplies FINAL OVERALL RATING: PARTIALLY SATISFACTORY

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/073

SCOPE OF WORK FOR PERFORMING INTERNAL CONTROL AND STATUTORY/REGULATORY COMPLIANCE AUDITS FOR RECIPIENTS OF SPECIAL MUNICIPAL AID

A. Khiam Rehabilitation Center for Victims of Torture AUDIT OBJECTIVES

INTERNAL AUDIT DIVISION AUDIT REPORT 2013/020. Audit of the Umoja software system (SAP) implementation

REPORT 2014/001 INTERNAL AUDIT DIVISION. Audit of information and communications technology help desk operations at United Nations Headquarters

INTERNAL AUDIT DIVISION AUDIT REPORT. Audit of disbursements in UNAMI. Generally internal controls were in placer but could be further strengthened

New Jersey Commerce and Economic Growth Commission

June 2008 Report No An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers

4.06 Consulting Services

Software Licenses Managing the Asset and Related Risks

FMCF certification checklist (incorporating the detailed procedures) certification period. Updated May 2015

Request for Quotation (RFQ) for Adjustable Sit to Stand Desk Reference No.: UNWHQRFQ31. [Insert Title of Goods]

AUDIT REPORT INTERNAL AUDIT DIVISION. Audit of United Nations Archives and Records Management

How To Ensure That Non-Peoplesoft Applications Can Withstand Adverse Events

REPORT 2015/182 INTERNAL AUDIT DIVISION. Audit of the operations in Iran for the Office of the United Nations High Commissioner for Refugees

REPORT 2015/112 INTERNAL AUDIT DIVISION

Table of Contents. 1 P a g e

REPORT 2016/049 INTERNAL AUDIT DIVISION. Audit of the operations in South Sudan for the Office of the United Nations High Commissioner for Refugees

a) To achieve an effective Quality Assurance System complying with International Standard ISO9001 (Quality Systems).

FINAL AUDIT REPORT. Audit of the information and communications technology (ICT) governance and security management in peacekeeping missions

Internal Audit of the Georgia Country Office

February 15, The Honorable Joshua B. Bolten Director Office of Management and Budget th Street, NW Washington, DC 20503

Final Report Audit of Vendor Performance and Corrective Measures. September 18, Office of Audit and Evaluation

CONTROL AND COMPLIANCE AUDITS

FINAL. Internal Audit Report. Employees Travel and Subsistence Expenses 2014/15

Terms of Reference for the external audit of project accounts at the contract partner's head office

CHAPTER 23. Contract Management and Administration

INTERNAL AUDIT REPORT

Contracting for Services

Contract for Provision of Services - Terms of Reference (Services of Technical or intellectual nature)

DNDi PROCUREMENT POLICY 2.4

UNIVERSITY OF NAIROBI

Department of Health and Mental Hygiene Community and Public Health Administration

Stated below are the SCIRE activity level control objectives for purchasing and accounts payable.

Audit of Community Futures Program

HOWARD UNIVERSITY POLICY

FINAL AUDIT REPORT. Audit of Arrangements for Global Banking and Investment Management in OPPBA

CREDIT CARDS CALIFORNIA STATE UNIVERSITY, EAST BAY. Audit Report June 28, 2013

Report on. Office of the Superintendent of Financial Institutions. Corporate Services Sector Human Resources Payroll. April 2010

Audit of Procurement Practices

Financial Regulations and Rules of the United Nations

ULSTER COUNTY COMPTROLLER S OFFICE Elliott Auerbach, Comptroller

AUDIT REPORT INTERNAL AUDIT DIVISION. Audit of OCHA s management of the Haiti Emergency Relief and Response Fund

Working Party on Control of Medicines and Inspections. Final Version of Annex 16 to the EU Guide to Good Manufacturing Practice

LEGAL SERVICES CORPORATION OFFICE OF INSPECTOR GENERAL FINAL REPORT ON SELECTED INTERNAL CONTROLS RHODE ISLAND LEGAL SERVICES, INC.

Project Implementation: Procurement & Contract Management. April 2012

INTERNAL CONTROL POLICIES

INVITATION TO BID: ITB

Purchases from $750 $1,500 requires 3 Verbal Quotes. Purchases from $1,501 $24,999 requires 3 Written Quotes

State and District Monitoring of School Improvement Grant Contractors in California FINAL AUDIT REPORT

AUDIT REPORT INTERNAL AUDIT DIVISION. ICT governance, security, business continuity and disaster recovery in UNIFIL

Internal Audit Terms of Reference

SUPPLIER PAYMENT GUIDE

AUDIT REPORT INTERNAL AUDIT DIVISION. Enterprise Resource Planning project at the United Nations Secretariat

Herscher Community Unit School District #2. PURCHASE ORDER POLICIES and PROCEDURES

The Education Fellowship Trust. Review of financial management and governance

September Claims Guideline

File Classification Scheme for Administrative Functions Common to all UN Offices

Invitation to Quote for consultancy services: a review of business planning arrangements

MONITORING PERFORMANCE

One source. One amazing service. Procurement Process and the Sarbanes-Oxley Act

U.S. Department of Energy Office of Inspector General Office of Audits and Inspections

Florida A & M University

City of Berkeley. Prepared by:

AUDIT OF READINESS FOR THE IMPLEMENTATION OF THE POLICY ON INTERNAL CONTROL

Navy s Contract/Vendor Pay Process Was Not Auditable

Internal Audit. Audit of the Inventory Control Framework

Review of the Veterans Health Administration s Use of Reverse Auction Acquisitions

NEW YORK CITY HOUSING DEVELOPMENT CORPORATION PURCHASING PROCEDURES. Updated as of December 23, 2014

U.S. Department of Agriculture Office of Inspector General Midwest Region Audit Report

PROCUREMENT TECHNICIAN

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Prepared by: Audit and Assurance Services Branch.

ESM Management Comments on Board of Auditors Annual Report to the Board of Governors for the period ended 31 December 2014

KAREN E. RUSHING. Audit of Purchasing Card Program

Item 10 Appendix 1d Final Internal Audit Report Performance Management Greater London Authority April 2010

Office of Consumer Credit Commissioner

Florida Department of Highway Safety and Motor Vehicles Office of Inspector General

Transcription:

INTERNAL AUDIT DIVISION AUDIT REPORT Vendor payment process in MONUSCO Monitoring controls over the vendor payment process should be strengthened to mitigate risks of financial loss 6 June 2011 Assignment No. AP2010/620/09

INTERNAL AUDIT DIVISION FUNCTION The Office shall, in accordance with the relevant provisions of the Financial Regulations and Rules of the United Nations examine, review and appraise the use of financial resources of the United Nations in order to guarantee the implementation of programmes and legislative mandates, ascertain compliance of programme managers with the financial and administrative regulations and rules, as well as with the approved recommendations of external oversight bodies, undertake management audits, reviews and surveys to improve the structure of the Organization and its responsiveness to the requirements of programmes and legislative mandates, and monitor the effectiveness of the systems of internal control of the Organization (General Assembly Resolution 48/218 B). CONTACT INFORMATION DIRECTOR: Fatoumata Ndiaye: Tel: +1.212.963.5648, Fax: +1.212.963.3388, e-mail: ndiaye@un.org DEPUTY DIRECTOR: Gurpur Kumar: Tel: +1.212.963.5920, Fax: +1.212.963.3388, e-mail: kumarg@un.org CHIEF, PEACEKEEPING AUDIT SERVICE: Eleanor T. Burns: Tel: +1.917.367.2792, Fax: +1.212.963.3388, e-mail: burnse@un.org

EXECUTIVE SUMMARY Audit of vendor payment process in MONUSCO The Office of Internal Oversight Services (OIOS) conducted an audit of the vendor payment process in the United Nations Organization Stabilization Mission in the Democratic Republic of the Congo (MONUSCO). The overall objective of the audit was to assess the adequacy and effectiveness of internal controls over the vendor payment process. The audit was conducted in accordance with the International Standards for the Professional Practice of Internal Auditing. Monitoring controls over the vendor payment process should be strengthened to mitigate risks of financial loss. The audit noted the following irregularities and inefficiencies: Contrary to Financial Rule 105.6, payments totaling $2.8 million made to two freight forwarding vendors were not based on valid commitments. The Movement Control officers who requested and purchased the services were not authorized to enter into financial commitments and approving officers in the Finance Section processed the payments without questioning the validity of the supporting documents. The Mission did not adhere to systems contract prices for pharmaceutical items which increased the risk of overpricing and that vendors may not be qualified to supply the procured goods. The Procurement Section did not implement a systematic procedure for dealing with short deliveries. This resulted in delays in resolving discrepancies and increased the risk of financial loss, especially for goods that were paid in advance under the International Commercial Terms. The Mission lacked a proper invoice processing system, hindering its ability to monitor the processing of invoices and resulting in the unmitigated risk of delays in paying vendors and loss of early payment discounts. OIOS has made five recommendations to address the issues identified during this audit and to improve internal controls over the vendor payment process.

TABLE OF CONTENTS Chapter Paragraphs I. INTRODUCTION 1-4 II. AUDIT OBJECTIVES 5 III. AUDIT SCOPE AND METHODOLOGY 6-7 IV. AUDIT RESULTS A. Noncompliance with the United Nations Procurement Manual and Financial Rules in purchasing and paying for freight forwarding services 8-11 B. Short deliveries not resolved in a timely manner 12-14 C. Systems contracts were not fully used 15-18 D. Invoice tracking system was inadequate 19-20 V. ACKNOWLEDGEMENT 21 ANNEX 1 Status of audit recommendations

I. INTRODUCTION 1. The Office of Internal Oversight Services (OIOS) conducted an audit of the vendor payment process in the United Nations Organization Stabilization Mission in the Democratic Republic of the Congo (MONUSCO). The audit was conducted in accordance with the International Standards for the Professional Practice of Internal Auditing. 2. The Vendors Unit in the Finance Section is responsible for processing invoices for payment in accordance with the Financial Regulations and Rules of the United Nations, the Field Finance Procedure Guidelines and other applicable standard operating procedures (SOPs). The Unit has six authorized posts and all were filled at the time of the audit. 3. During the financial year 2009/2010, the Unit processed payments estimated at $286 million as shown in Table 1. These payments related to commitments made through contracts, purchase orders (POs), and miscellaneous obligation documents by MONUSCO but did not include payments such as reimbursement to troop contributing countries made at the United Nations Headquarters on behalf of the Mission, as well as the payment for staff salaries and entitlements. Table 1: Payments by object code during financial year 2009/2010 Description Budget $ Expenditure $ Facilities and infrastructure 86,547,169 87,963,031 Ground transportation 17,660,800 19,560,884 Air transportation 61,773,800 66,479,336 Naval transportation 1,380,200 1,117,480 Communications 20,296,400 17,639,787 Information technology 8,888,100 8,040,157 Medical 2,397,990 1,853,559 Other supplies, services and equipment 19,098,931 19,580,553 Quick impact projects 1,000,000 717,443 Rations 65,160,100 63,023,399 Total 284,203,490 285,975,629 4. Comments made by MONUSCO are shown in italics. II. AUDIT OBJECTIVES 5. The main objective of the audit was to assess the adequacy and effectiveness of internal controls over the vendor payment process. III. AUDIT SCOPE AND METHODOLOGY 6. The audit covered the period from 1 July 2009 to 30 June 2010 and reviewed the transactions and records of earlier periods where necessary. 7. The audit methodology included a review of relevant records, analysis of available data and interviews with key Mission personnel. A sample of 67 vendor invoices valued at $36.5 million out of a total vendor payment of $286 million

were tested to assess compliance with the United Nations Manual, Financial Regulations and Rules, Field Financial Procedures and Guidelines and SOPs. IV. AUDIT RESULTS A. Noncompliance with the United Nations Procurement Manual and Financial Rules in purchasing and paying for freight forwarding services 8. In response to a recommendation resulting from OIOS audit of procurement management in MONUSCO (AP2009/620/13), the Mission established a single contract for customs clearance and freight forwarding services for all destinations in February 2010. This effectively prevented the Movement Control Section (MovCon) from unilaterally inviting price quotations and entering into piecemeal freight forwarding arrangements with two freight vendors using task orders in violation of the United Nations Procurement Manual. 9. OIOS notes that prior to establishing the single contract, the Mission had paid $2.85 million to the two freight vendors during the period from 1 October 2007 to 31 March 2010 in respect of 247 invoices. Out of the 247 invoices, OIOS reviewed the supporting documents for 55 invoices valued at $1,369,527, being those with the largest individual amounts. The review showed that contrary to Financial Rule 105.6, the payments were made without valid contracts. Instead, the approving officers of the payments relied on task orders (TOs) which were issued by MovCon officers. 10. In accordance with the United Nations Financial Rules, the contracts used in processing payments (i.e. financial commitments) must be approved by the Controller or someone designated by him/her. In MONUSCO, only the Director of Mission Support and procurement officers designated by the Department of Management have the authority to commit the United Nations. However, the task orders used in processing the 247 invoices referred to above were approved by officers who did not have the authority to enter into financial commitments on behalf of the United Nations. Furthermore, these officers performed both requisitioning and purchasing functions, which should be segregated to minimize conflict of interest situations. Recommendation 1 (1) The MONUSCO Office of Mission Support should review and confirm the regularity of the payments estimated at $2.8 million made to two freight forwarders and, if the payments are considered as irregular, initiate appropriate action against the concerned staff in connection with the payments. 11. The MONUSCO Office of Mission Support accepted recommendation 1 and stated that the payments estimated at $2.8 million were being reviewed to 2

determine their legality and considering ways of regularizing them. While OIOS recognizes the steps being taken to confirm the regularity of the payments, there is also the need for the Mission to initiate appropriate action against concerned MovCon officers for discharging procurement function without authority. The related accountability of approving officers who processed invoices in the absence of valid supporting documents including purchase orders should also be clarified. Therefore, recommendation 1 remains open. B. Short deliveries not resolved in a timely manner 12. Discrepancies between POs and the actual quantities of goods received from vendors needed to be resolved in a timely manner. Discrepancy reports shown in Table 3 as on 16 May 2011 relating to 204 goods valued at $344,310 delivered from 1 July 2006 to 30 April 2011 had not been resolved by the Mission. Of these goods, 58 per cent were short-delivered, 18 per cent were damaged and 6 per cent were not matching with the specifications given in the POs. Ideally, the Mission should have resolved these short deliveries and discrepancies within a reasonable timeframe. However, this was not done. OIOS noted that it was already too late for the Mission to recover payments from the vendors in respect of the short deliveries and discrepancies. Table 2: Unresolved discrepancies in MONUSCO Year Short Damaged Mismatch Over Not Incomplete Amount deliveries goods with PO supplied ordered (in US$) 2006 23 5 2 12 1 0 25,965 2007 51 11 0 9 0 0 19,489 2008 13 7 5 1 0 1 33,761 2009 16 4 2 0 0 1 52,939 2010 3 7 4 5 3 0 121,456 2011 12 3 0 3 0 0 90,700 TOTAL 118 37 13 30 4 2 344,310 13. The Procurement Section did not implement a systematic procedure for dealing with discrepancies and short deliveries. Delays in resolving discrepancies increased the risk of financial loss, especially for goods that were paid in advance under the International Commercial Terms. Recommendation 2 (2) The MONUSCO Office of Mission Support should implement appropriate procedures for resolving discrepancies and short deliveries in a timely manner to prevent financial loss to the Organization. 14. The MONUSCO Office of Mission Support accepted recommendation 2 and stated that SOPs delineating the roles of the Receipt and Inspection Unit, the Finance and Procurement Sections in resolving discrepancies would be issued. Recommendation 2 remains open pending receipt of the SOP on the resolution of discrepancies and short deliveries in a timely manner. 3

C. Systems contracts were not fully used 15. Paragraph 13.5(8) of the United Nations Procurement Manual provides that POs should be issued for the requested deliverable clearly referring to the systems contract and the prices contained therein. Article 20.1 of the systems contract (PD/C0043/07) provides that payment to the contractor shall be made in accordance with the terms of the contract, based on unit prices specified in Annex B. Article 20.2 provides that the unit price for the goods specified in the contract shall remain firm during the entire term of the contract. 16. There were instances where prices in the POs for medical supplies issued by MONUSCO did not match the price lists in the relevant systems contract. For example, in POs 10KIN 200679 and 10KIN 2001131, a pack of 1,000 capsules of Amoxicillin 500 milligram (mg) was priced at $45 each while the systems contract price for a pack of 1000 Amoxicillin 500 mg was $25. A pack of 250 tablets of paracetamol 500 mg (nevrine) was priced at $17.50 each while the approved price for 250 tablets of paracetamol 500 mg was $1.13. The $85 per pack of terbinafine hydrochloride 250 mg paid by the Mission was not covered by the systems contract. Further, paid vouchers relating to POs 10KIN 200679, 10KIN-201131 and 11KIN-200501 contained 212 pharmaceutical items valued at $272,020 of which 90 items valued at $151,517 (56 per cent of total value of the reviewed vouchers) were not covered by the systems contract. 17. The Mission s failure to use the prices in the systems contract meant that it was not mitigating risks of overpricing and that the vendor may not be qualified to supply procured medicines. Recommendation 3 (3) The MONUSCO Office of Mission Support should ensure that established systems contracts are used in procuring pharmaceutical items and the medicines not covered in the systems contract price lists are procured through a transparent process and in compliance with the United Nations Procurement Manual. 18. The MONUSCO Office of Mission Support accepted recommendation 3 and stated that it was seeking further clarification from the United Nations Headquarters on the interpretation of the contract regarding vendor s noncompliance with the initial contract terms due to disparity in prices of brand and generic pharmaceutical brands. Recommendation 3 remains open pending confirmation that clarification has been sought from Headquarters on the use of systems contract price list and assurance that the Mission has taken steps to ensure that medicines not covered in the systems contract price list are procured through competitive bidding. D. Invoice tracking system was inadequate 19. The information system used by the Finance Section for invoice processing should be capable of generating reports for effective monitoring of the vendor 4

payment process. The Vendors Unit maintained a spreadsheet for recording the receipt of invoices and the actions taken on those invoices. However, the spreadsheet had significant gaps that undermined its usefulness. For example, it lacked adequate access controls, the Cashier s Office had no access to update the payment status, and it did not have a reporting capability. The lack of a proper invoice processing system hindered the monitoring of the processing activity in the Vendors Unit and contributed to loss of early payment discounts. For example, the Mission loss early payment discounts totaling $100,000 in respect of 48 of the 91 sample invoices (52 per cent) reviewed as these had been outstanding for more than 30 days. Recommendation 4 (4) The MONUSCO Office of Mission Support should ensure that it has an adequate tool to track and monitor the invoice payment process. 20. The MONUSCO Office of Mission Support accepted recommendation 4 and stated that it acknowledged the need for a better tool to track the invoice payment process and would write a business case to United Nations Headquarters on the viability of establishing an electronic monitoring tool. Recommendation 4 remains open pending confirmation of the establishment of a tool for tracking and monitoring the invoice payment process. V. ACKNOWLEDGEMENT 21. We wish to express our appreciation to the Management and staff of MONUSCO for the assistance and cooperation extended to the auditors during this assignment. 5

STATUS OF AUDIT RECOMMENDATIONS Recom. C/ Actions needed to close Recommendation Risk category Risk rating no. O 1 recommendation 1 The MONUSCO Office of Mission Support Compliance Medium O While OIOS recognizes the steps should review and confirm the regularity of being taken to confirm the regularity the payments estimated at $2.8 million made of the payments, there is also the to two freight forwarders and, if the need for the Mission to initiate payments are considered as irregular, initiate appropriate action against concerned appropriate action against the concerned MovCon officers for discharging staff in connection with the payments. procurement function without authority. The related accountability of approving officers who processed invoices in the absence of valid contracts should also be clarified. Therefore, this recommendation remains open. 2 The MONUSCO Office of Mission Support Financial Medium O Receipt of the SOP on the resolution should implement appropriate procedures for of discrepancies and short deliveries resolving discrepancies and short deliveries in a timely manner. in a timely manner to prevent financial loss to the Organization. 3 The MONUSCO Office of Mission Support should ensure that established systems contracts are used in procuring pharmaceutical items and the medicines not covered in the systems contract price lists are procured through a transparent process and in compliance with the United Nations Procurement Manual. 4 The MONUSCO Office of Mission Support should ensure that it has an adequate tool to track and monitor the invoice payment process. Financial Medium O Confirmation of the establishment of a tool for tracking and monitoring the invoice payment process. Operational Medium O Establishment of a tool for tracking and monitoring the invoice payment process. ANNEX 1 Implementation date 2 1 April 2011 31 March 2011 31 March 2011 31 July 2011 1. C = closed, O = open 2. Date provided by MONUSCO in response to recommendations.