COUNCIL AGENDA REPORT



Similar documents
COUNCIL AGENDA REPORT

Additional specific restrictions are laid out in the following bid packet. As a courtesy, we have provided the following summary of this bid.

CHARTER TOWNSHIP OF WASHINGTON PURCHASING & BID POLICY

Mission. City Manager s Office

CHAPTER 150: BUILDING REGULATIONS. Adoption of Regulatory Codes by Reference

Local Government Guide to Procurement with Federal Grant Funding

Solicitation Web Hosting Services for the Disaster Volunteer Network. State of California

Within the context of this policy, the following definitions apply:

TABLE OF CONTENTS I. PURPOSE... 3 II. GOALS...3 III. DEFINITIONS

ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects

How To Write A Contract In The European

PPSADOPTED: OCT BACKGROUND POLICY STATEMENT PHYSICAL FACILITIES. PROFESSIONAL PRACTICE STATEMENT Developing a Business Continuity Plan

Schneps, Leila; Colmez, Coralie. Math on Trial : How Numbers Get Used and Abused in the Courtroom. New York, NY, USA: Basic Books, p i.

REQUEST FOR PROPOSAL

Programs and Administration Committee. Pat Cabrera, Administrative Services Director. Uniform Public Construction Cost Accounting Act

CITY OF BLAINE REQUEST FOR PROPOSAL IP TELEPHONY SYSTEMS CONSULTANT

MANAGEMENT AUDIT REPORT DISASTER RECOVERY PLAN DEPARTMENT OF FINANCE AND ADMINISTRATIVE SERVICES INFORMATION TECHNOLOGY SERVICES DIVISION

C. La Plata County is exempt from all state taxation including state sales and use tax.

IV. Orders, Quotations, Bids and Request for Proposal (RFP) Requirements

Office of Inspector General

MASSWORKS INFRASTRUCTURE PROGRAM 2011 GRANT RECIPIENT HANDBOOK

SOLICITATION AMENDMENT

CITY OF ELK GROVE CITY COUNCIL STAFF REPORT

REQUEST FOR PROPOSAL STORAGE AREA NETWORK SOLUTIONS FOR THE PARK CITY SCHOOL DISTRICT RFP #

PUBLIC BID LAW CURRENT DEVELOPMENTS. Louisiana Department of Justice James D. Buddy Caldwell, Attorney General

New Jersey Administrative Code. Encumbrance Accounting and Certifications of Availability of Funds

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION PAGE 1

STATE OF MINNESOTA OFFICE OF THE STATE AUDITOR

Request For Information. Telecom System Management and Billing Software

Citywide Contract Compliance Audit Report

IT IS RECOMMENDED THAT YOUR BOARD: 1. Find that this project is statutorily exempt from the provisions of the California Environmental Quality Act.

Bonding and Insurance Requirements. Economic Development Committee 04/7/08

Virginia Commonwealth University School of Medicine Information Security Standard

ATTACHMENT B BID SUBMITTAL FORMS. For LIME SLUDGE REMOVAL WATER RECLAIM BASIN RFB #

REVISED 05/07/15: SEE PAGE 1, SECTION B.5. SEMCA S REQUEST FOR PROPOSALS (RFP) FOR BANKING SERVICES

REQUEST FOR PROPOSAL windows,sliding glass door repair and replacement contractors

Request for Proposal and Qualifications for Audit and Tax Preparation Services October 2015

Project Scope Statement Example

Controlling Our Critical Path: A CDOT Guide to Better Project Management Practices

TABLE OF CONTENTS. Purchasing and Contracts Division Purchasing Policies and Procedures The Competitive Process... 2

DEPARTMENT OF PUBLIC WORKS. m e m o r a n d u m

PROPOSALS REQUESTED THE TOWN OF OLD ORCHARD BEACH POLICE DEPARTMENT FOR IP-BASED VOICE COMMUNICATION SYSTEM

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

TOWN OF LINCOLN INVITATION TO BID EMERGENCY PLANNING, DISASTER RECOVERY AND HAZARD MITIGATION GRANT PROGRAM SERVICES RFP #

City of Union, Missouri Request for Proposal Audit Services

AGENDA STAFF REPORT. Budgeted: Yes Current Year Cost: $695,000 Annual Cost: N/A

GREATER SYRACUSE PROPERTY DEVELOPMENT CORPORATION DISPOSITION OF REAL AND PERSONAL PROPERTY POLICY

FY Licensed Timber Operators & Tree Service Contractors

UNO CHARTER SCHOOL NETWORK ( UNO-CSN ) Invitation for Bids ( IFB ) for ELECTRICAL UPGRADES

Amendment 3: HRIS/Payroll only

VILLAGE OF ARLINGTON HEIGHTS

Invitation to Bid FIRE ALARM & DETECTION SYSTEM

Data Center Cleaning Services Rev. 0 Bid # Scope of Work

Hospital Emergency Management Plan

CITY OF DEWITT Page 1 Regular City Council Meeting Tuesday, May 13, 2014

How to Do Business With Us ST. LOUIS COUNTY GOVERNMENT DIVISION OF PROCUREMENT AND ADMINISTRATIVE SERVICES

CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE

Texas Universities Recover from Hurricane Ike University of Texas Medical Branch Galveston and Texas A&M University Galveston

DGS (VCCS Rev. 04/15) Page 1 of 7 REQUEST FOR PROPOSALS

MOUNTAIN EMPIRE UNIFIED SCHOOL DISTRICT REQUEST FOR PROPOSAL

Public Works Contract Completion

BREVARD COUNTY MERIT SYSTEM PROCEDURES PROCEDURE II

City of Hesperia. Request for Quotes Answering Services. Release Date: 02/04/10

CHAPTER 91: LANGUAGE ACCESS

CENTRAL TEXAS COLLEGE DISTRICT REQUEST FOR PROPOSAL NO. RFP APPLICANT TRACKING/POSITION MANAGEMENT SYSTEM CLOSING DATE: JULY 7, 2014, 3:00 PM

Agenda Report. April 8, Honorable Mayor and City Council TO: THROUGH: Finance Committee (April 8, 2013) FROM: Water and Power Department

Final Audit Report. Report No. 4A-CI-OO

City of Pittsburgh, PA - Request For Proposals and procurement Process

State of New Jersey New Jersey Public Broadcasting System New Jersey Network Standard Terms and Conditions

Request for Proposal (RFP) IP Cameras/Door Access Control

REQUEST FOR PROPOSAL: STRUCTURED CABLING, LAN SWITCHES, LONG DISTANCE SERVICE, ELECTRONIC FAXING, AND HOSTED VOIP SPECIFICATIONS

REQUEST FOR PROPOSALS. On-Call HVAC Contractor Services GFN 1661

Cook County Emergency Telephone System Board

New Jersey Department of Community Affairs. Division of Local Government Services. Extraordinary Unspecifiable Services

Fairfield, Connecticut Purchasing Department

TABLE OF CONTENTS. Prefacej... 1

MEMORANDUM TO CLIENT Attorney-Client Privileged

Transcription:

CITY OF MODESTO COUNCIL AGENDA REPORT COUNCIL MEETING: November 22, 2005 November 14, 2005 TO: FROM: SUBJECT: Mayor and City Council Finance Department / Purchasing Division Uninterruptible Power Supply (UPS) Purchase CONTACT: Gary Cook, gcook@modestogov.com 577-5229 RECOMMENDED COUNCIL ACTION: Adopt a resolution authorizing the award of bid and contract for the purchase and installation of a Liebert 65KVA Uninterruptible Power Supply (UPS) System for the Information Technology Department to Elite Power, Inc., Sacramento, CA, for an estimated purchase price of $124,650. Adopt a resolution amending the 2005/2006 budget to appropriate $24,650 from the general fund reserves 0100-800-8000-8003 to the Information Technology Department operating budget 7130-070-0744-5400 to fully fund the purchase of a Liebert 65KVA Uninterruptible Power Supply (UPS) System. I. BACKGROUND: The 5 th floor data center is provided with clean power and power outage protection through an IPM/Powerware BPII Uninterruptible Power Supply unit located on the 5 th floor. This UPS supports Citywide financial systems such as budget, accounting and payroll. The UPS has experienced several failures over the last several months to its charging system and is currently experiencing total system failure. The existing Powerware BPII is a discontinued model. Parts have limited availability and this has resulted in long delays in service and repairs. In the past three (3) months the Information Technology Department has experienced three (3) system failures resulting in total data center blackouts, as well as loss/damage to data and equipment. The system experienced total system failure on August 29, 2005, resulting in numerous service calls. Parts replacement has been unsuccessful in repairing the system. The current UPS is located in a non-environmentally controlled location. This may have been a partial cause of the system s failure.

The 5 th floor data center UPS provides continuous power to all enterprise computer equipment in the event utility provided power fails. The UPS is the failsafe that protects the City s data center, including all mission critical servers and data systems. The UPS provides critical temporary power in the event of loss of utility power to allow servers and data systems to shut down in a normal fashion. Failure of the utility provided power source, without UPS protection, would result in immediate failure and shutdown of all data center systems. Additionally, this immediate mode of shutdown often results in severe damage to the servers and/or data systems. Shutdown of data center and web-based applications will negatively impact all City staff and citizens of Modesto. Due to the critical nature of having a dependable UPS system in place that protects several operating systems Citywide, such as the financial systems budget, accounting and payroll systems, and based on the fact of recent power losses experienced by the Information Technology Department, the City Manager s Office determined this to be a critical situation, demanding a (critical need) circumstance. Due to the critical need situation the Information Technology Department obtained a rough cost estimate from an electrical contractor experienced in UPS systems. The rough cost estimate of approximately $90,000 was for the purchase of a new UPS system including installation and construction material, for a location in close proximity to the critical load or the 5th floor data center. The estimate provided by the electrical contractor was without the benefit of an onsite survey and knowledge of the circumstances surrounding the failure of the old UPS system. The Information Technology Department decided to provide City Council with an estimated cost of $100,000 for the project. This figure was determined to be a reasonably safe number above the contractor s estimate to cover unexpected cost overruns. II. REASONS FOR RECOMMENDATION: On September 13, 2005, Council approved Resolution No. 2005-464, authorizing the purchase and installation of a Liebert 65KVA Uninterruptible Power Supply System for the Information Technology Department, for a total estimated price of $100,000. Additionally, Council authorized the Purchasing Supervisor to solicit competitive quotes for the purchase and installation of a Liebert 65KVA Uninterruptible Power Supply System, evaluate bid responses for the best overall value to the City and issue a purchase order to the selected vendor, based on the critical nature of this request. On October 4, 2005, the Purchasing Division solicited Request for Bid (RFB) No. 0506-14 for the purchase and installation of a new Liebert 65KVA Uninterruptible Power Supply System to five (5) companies and posted the bid on the City s web site. At the time of the RFB submittal two (2) sites were being considered for the location of the new UPS system:

A. Fifth floor telecommunications closet located at 1010 Tenth Street, 5 th Floor, Modesto, CA. B. Basement telecommunications room located at 1010 Tenth Street, Basement, Modesto, CA. Bidders were to furnish bid pricing for both locations, and based on the bids received, the City would choose the site location that best suited its needs. On October 10, 2005, a site walk-through and bidders conference was held to allow bidders the opportunity to inspect the two (2) site locations and address bidder inquires. During the bid walk-through it was determined that the 5 th floor telecommunications closet was not a viable location to install the new UPS system due to environmental control issues (heat) in the room. On October 28, 2005, bids were opened in the Purchasing Division. Of the five (5) companies solicited, two (2) companies chose to respond. The low bid came in approximately 25% higher than the $100,000 cost estimate submitted to Council. The Information Technology Department believes the higher cost is attributed to the fact of relocating the new UPS system to the basement telecommunications room. The relocation of the UPS system to the basement requires additional materials and labor over installing the system in the 5 th floor telecommunications room. Additional electrical conduit and wiring is needed as well as additional labor to core bore each floor to provide the pathway. Each core bore is very labor intensive and costly, due to the amount of concrete that will need to be bored. Additionally, the recent hurricane disasters have affected the construction market on material prices. This was mentioned by two (2) of the contractors that attended the site walkthrough. The contractors mentioned that the hurricanes in the Louisiana and Texas regions have put a market strain on cost and availability of materials required to rebuild the devastated infrastructure in those areas. This includes copper and electrical conduit that would be used in the construction of the new UPS system. Based on being the lowest responsive and responsible bid, City staff recommends the award of bid and contract for the for the purchase and installation of a Liebert 65KVA Uninterruptible Power Supply (UPS) System for the Information Technology Department to Elite Power, Inc., Sacramento, CA, for an estimated purchase price of $124,650. Attached for review is the cost analysis abstract for Request for Proposal No. 0405-03. (See attachment B)

III. EXISTING POLICY / RELATIONSHIP TO THE STRATEGIC PLAN: The Modesto Municipal Code, MMC 8-3.203, generally requires all purchases, which meet or exceed $50,000 for material, equipment or contractual services to be formally bid. However, one exception to the code (8-3.204 (c)), allows for the Purchasing Supervisor, in his or her discretion, to determine that calling for formal bids on a competitive basis, as set forth in Section 8-3.203 is undesirable due to demanding circumstances. Based on the critical nature of the request the Purchasing Supervisor evoked that exception for this purchase and installation. The solicitation of informal competitive bids for the purchase and installation of a Liebert 65KVA Uninterruptible Power Supply System UPS conformed to MMC Section 8-3.203, and demonstrated that a competitive process was met. IV. POLICY ALTERNATIVES: The Council could determine not to authorize the purchase and installation of a new Liebert 65KVA uninterruptible power supply system and continue to maintain the current system as status quo. V. FISCAL IMPACTS: $100,000 is budgeted and available in the following account for the purchase of an uninterruptible power supply system for FY 05/06: Description: Uninterruptible Power Supply System Account Number Department/Division Available Amount 7130-070-0744-5400 IT Department $100,000 Appropriate additional $24,650 to fully fund project. From: 0100-800-8000-8003 $24,650 To: 7130-070-0744-5400 $24,650 VI. INTERDEPARTMENTAL COORDINATION: The Purchasing Division coordinated the drafting of the specifications and evaluation of the informal competitive bids for the purchase and installation of a Liebert 65KVA uninterruptible power supply system with the Information Technology Department. VII. PUBLIC PARTICIPATION: No meeting was scheduled to collect public input on this request.

VIII. COMMITTEE RECOMMENDATION: The uninterruptible power supply system does not require committee recommendation. IX. ENVIRONMENTAL REVIEW: This is not a project for the purpose of environmental review. X. STEPS FOLLOWING APPROVAL: Following Council approval, the Purchasing Supervisor will issue a purchase order for the purchase and installation of a Liebert 65KVA uninterruptible power supply system to Elite Power, Inc., Sacramento, CA, for an estimated purchase price of $124,650.

Prepared By: Reviewed By: Reviewed By: Reviewed By: Submitted By: Ken Masasso, Senior Buyer, kmasasso@modestogov.com; 577-5420 Mark L. Averell, Purchasing Supervisor, Finance Department Gary Cook, Chief Information Officer, IT Department M. Wayne Padilla, Finance Director, Finance Department George W. Britton, City Manager Attachments: A) Council Resolution B) Cost Analysis Abstract