WELCOME Best Practices for Managing Construction Delay and Interference Claims



Similar documents
Who pays the Money for the Time?

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

Construction Bonds. Vanessa S. Werden

12/14/2015 HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT INTRODUCTION AND OVERVIEW

HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

LONG INTERNATIONAL. Long International, Inc Whistling Elk Drive Littleton, CO (303) Fax: (303)

How To Perform An As-Built But For Schedule Delay Analysis

CHANGE ORDER PROTOCOL

Builder s Risk Structuring the Right Coverage, Avoiding and Resolving Disputes

Method for Calculating Schedule Delay Considering Lost Productivity

1. Emergency Services

Scheduling Best Practices

Owner s Damages for Construction Defects:

International Accounting Standard 11 Construction Contracts

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

Construction Conference

WOODLAND HOMES BUILDING PROCESS A STEP BY STEP CONSTRUCTION GUIDE TO YOUR NEW HOME

Construction Contracts

How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No December 2014

Construction Defect Claims In Colorado

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

The Principles of Schedule Impact Analysis

CONTRACTOR DEFAULT & SURETY PERFORMANCE:

Discharge 3/14/2012. Chapter 16 Performance and Discharge Byron Lilly De Anza College Byron Lilly De Anza College

APPLICATION FOR NON-SUBSTANTIAL DAMAGE / IMPROVEMENT REVIEW

CHARLOTTE COUNTY Community Development Department

North London Plumbing & Heating Terms and Conditions

Emory University Psychology Building

Dispute Resolution Services

Borges Construction Company A limited liability Corporation Page1 of 1

Almost everyone in the planning and scheduling profession

PROPERTY INSPECTION OR ASSESSMENT OF DAMAGES

Checklist 26: How Owners Can Avoid Litigation on Construction Projects

Repair and Remodeling Estimating Methods. 4th Edition. RSMeans

Notice to Property Owners

WARRANTIES AND PERFORMANCE STANDARDS T A B L E O F C O N T E N T S General Provisions Introduction Warranties Effective Date of Warranties Exclusive

Contract Administration

Important Information for Owners of Buildings in Flood Zones

SUBSTANTIAL IMPROVEMENT/DAMAGE NOTICE TO PROPERTY OWNERS

Defendant has a duty to act as a reasonable person would in like or similar circumstances to avoid causing unreasonable risk of harm to others.

The New Standard Construction Contracts: NZS3910, 3916 and 3917

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE APPLICATION REVIEW

Frequently Asked Questions (Including Definitions)

Professional Practice 544

How To Install An Overhead Sewer

Spec. Standard: 11/27/ Revision: 11/27/06

NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS

CLAIMS AGAINST TRANSLATORS: THE TRILOGY OF PREVENTION, HANDLING AND RESOLUTION PART ONE: PREVENTION AND MITIGATION

Special Use Commercial Properties

APPLICATION & RULES FOR OWNERS, CONTRACTORS, MOVERS

Case Studies. Disaster Recovery Restoration Remediation Decontamination

Contract Language and Documentation

Sri Lanka Accounting Standard -LKAS 11. Construction Contracts

PLUMBING ON TAP (REG CO NO: ) TERMS AND CONDITIONS OF BUSINESS

How to Negotiate Adequate Casualty Provisions

PROPERTY INSPECTION OR ASSESSMENT OF DAMAGES

AIA Document A312 - Electronic Format. Performance Bond

bout your HOUSE Hiring a contractor

Project Control. 1. Schedule Updating

Region IV 1371 Peachtree Street. N.E. Suite 700 Atlanta, GA 30309

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

NORTH CAROLINA WEATHERIZATION ASSISTANCE PROGRAM SUBCONTRACTOR AGREEMENT - PLUMBING

Renovation instructions

Construction Schedules

ROOFING AGREEMENT. Claims Managers Name: Property Address: Telephone (h) (w) (c) Insurance Company Policy No.

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

The Insurance Coverage Law Information Center

How To Get A Job Done

The following Accounting Standards Interpretation (ASI) relates to AS 7. ASI 29 Turnover in case of Contractors

SURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.)

EXHIBIT 2-2-C PROGRESS SCHEDULES

GENERAL SPECIFICATIONS REHABILITATION RESIDENTIAL CONTRACTORS HANDBOOK

Name of course: Residential Construction Site Management (RCSM) Level 1

INDEPENDENT CONTRACTOR AGREEMENT (ICA)

BACK TO BASICS: As The Pendulum Shifts To More Fixed Price Contracts, Be Prepared For More Contract Changes and Know How To Price Them

HOWARD UNIVERSITY. I. Policy Statement. II. Rationale. III. Entities Affected by the Policy. IV. Definitions. Policy Number:

Insurance and Post Project Dispute Resolution

Construction Contracts

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

CALCULATION AND RECOVERY OF HOME/HEAD OFFICE OVERHEAD

PN /16/ CRITICAL PATH METHOD PROGRESS SCHEDULE

9770 CULVER BOULEVARD CULVER CITY, CA Incidental improvements: improvements that do not qualify as minor or

In order for a contract to be valid, certain elements must exist:

Standard Terms & Conditions for Supply of Software Development Services

NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE)

Terms & Conditions For Electricity Supply

Standard business terms

PROJECT COST ESTIMATES & FEASIBILITIES

An Oracle White Paper April Change Management Best Practices for the Engineering and Construction Industry

Construction Claims in

Dream It. FInance It. BuIlD It.

Transcription:

WELCOME Best Practices for Managing Construction Delay and Interference Claims Kenneth A. Slavens 314.345.6419 Husch Blackwell LLP

Topics to be covered Delay Acceleration Disruption

Delay Impact on Project Participants For the contractor Adjustments in time Adjustment in costs For the owner Loss of use Liquidated damages

Escalation Impact on Project Participants More resources need to complete the project on schedule Completion date need not be delayed Increased cost attributable to performing work at a date later than planned Impact of changes in sequence can cause escalation in costs

Disruption Effect on Project Potential impact of extra work: Disruption in the planned sequence of the work Extend the work into inclement weather Impact productivity of the trades

Delay Why talk about it? For the contractor May need additional time May consume additional resources For the owner Project not delivered when promised (loss of use) Not generating revenue Entitlement to Actual or Liquidated Damages

Delay Entitlement to Additional Time Contractor's entitlement to additional time to complete: If the delay is excusable Potentially can recover increased costs as well

Delays If an excusable delay For the contractor, an excusable delay will: Justify time extensions Preclude termination of the contract for the delay Preclude recovery of actual or liquidated damage

Delay Is the delay excusable? Read the Contract: frequently defines excusable delays Examples common in contracts or if the contract is silent Owner or architect delays Acts of God / Unforeseeable Events Strikes Owner Supplied materials

Delays What if the delay was foreseeability? Some circumstances, even if the cause of the delay is an otherwise excusable event, it may not be excused If the event is "known or knowable," i.e.: contractor knows that there is an impending strike when the contract is signed

Delay Impact of foreseeability on an otherwise excusable delay Dicon, Inc. v. Marben Corp. Contractor knew the owner would be late delivering plans and specs Cannot rely on this owner delay for extra time

Delay Foundation Underlying an Excusable Delay Implied term of every contract: Neither party will do anything to prevent performance by the other party or permit an act that will hinder or delay performance Owner prevents or hinders the contractor's performance: excusable Changes in the work at the direction of the Owner, for example, may cause an excusable delay

Delay Liquidated Damages Generally enforceable May need to show that the calculation of damages from late completion is impossible or very difficult to estimate at time of execution of the contract Amount is a reasonable forecast of the harm of late completion

Delay Liquidated Damages and the Public Project For public works contracts a reasonable approximate is not necessary Public body needs to only show unexcused late completion

Delay Liquidated Damages Liquidated Damage are the owner s sole recovery for late completion Even if the actual damages exceed the liquidated damage amount - as long a not unreasonably disproportionate to actual damages

Delay Notice of Delay Read the contract Frequently required by the contract When in doubt give the notice even if the contract is unclear Failure to give the notice can bar an extension for an otherwise excusable delay. See: Southwest Engineering Co. v. Reorganized School District R-9

Delay It's Excusable, but is it compensable? May be excusable, but does not equate to compensable (more money) Excusable delay will entitle a contractor to more time Must be compensable to be entitled to more money

Delay What is compensable? Compensable: damages are recoverable from the party that "caused" the delay Neither party caused the delay: neither is entitled to recover from the other

Delay Compensable Delay Examples of events for which the owner may have liability: Work suspensions Interferences Hindrances Design Defects Differing site conditions

Protection from Delay Damages: No Damage for Delay Clauses No Damage for Delay clauses theoretically Protect the owner from all delays Downside: contractor may build additional funds into the bid to account for the risk and drive up the cost (you may end up paying for an event that never happens) Generally enforceable on private projects

Protection from Delay Damages: No Damage for Delay Clauses For public projects: Many states have statutes invalidating these clauses on public works projects Void in Missouri: Section 34.058, RSMo 2000

Delay What Damages can be Recovered Reasonably foreseeable damages caused by a compensable delay are recoverable Increased labor Equipment Office overhead General conditions Interest

Delay What Damages can be Recovered Owner Damages: Loss of use of the project Loss of revenue which would have been generated Liquidated Damages

Delay Damages Overriding Principal to Damage Recovery Increased costs are recoverable if the costs would not have been incurred, but for the delay

Delay Proving Damages Methods of proving damages Total Cost Method Modified Total Cost Method Jury Verdict Method

Delay Damages Total Cost Total Cost Method is highly disfavored Viewed with caution Considered a last resort Underlying premise of Total Cost Method Contractor s compensable damages are the difference between the costs expected at the outset (the contractor s estimate) and the actual costs Assumes the only reason for the delay is the ownercaused delay

Delay Damages Total Cost Assumes the project would have occurred exactly as expected, but for the excusable delay Assumes: Original estimate of the contractor was accurate All increased costs were caused by the other party

Delay Damages Total Cost To have the Total Cost Method accepted, must show: Impossible to estimate actual damages with a reasonable degree of certainty The estimate was accurate Actual cost of performing the work was reasonable No other causes for increased costs aside from the compensable delay Contractor used a reasonable accounting system to accumulate job costs

Delay Damages Total Cost Fundamental Concept of Total Cost Recovery: the contractor cannot share any of the liability for the delays Concept is virtually impossible to prove

Delay Damages Modified Total Cost Avoids inflexibility of Total Cost Method Allows flexibility particularly two main elements Accuracy of the estimate Can address inaccuracies Can address mistakes Actual Costs incurred: remove those costs not the responsibility of the Owner

Delay Damages Jury Verdict Method Different spin on the Total Cost Method Need to establish: Contractor is damaged Defendant is responsible Must prove damages "beyond speculation" Allows the jury to make a fair and reasonable approximation of the contractor s damages No Missouri case has accepted this method

Delay Damages Schedule Analysis Generally accepted more reliable than the Total Cost Method, Modified Total Cost, or Jury Verdict Use General Conditions Approach Specifically identify the effect of the delay on each element of increased cost Quantify The delay The increased costs

Common Components of Delay Damages Most commonly associated with a delay claim General conditions (direct overhead) Office overhead (indirect overhead) Equipment Costs Productivity Losses Additional Interest

Delay Damages General Conditions / Direct Overhead Common elements Project managers and project administrators Utilities Project Trailer or Office Security Equipment Generally can show a direct connection between increased project time and increased costs

Delay Damages - Extended Home Office Overhead / Indirect Overhead Often called indirect overhead or general and administrative costs Damages claimed in this area are often attacked They are often thought of as soft damages They vary greatly depending on the accounting methods No generally accepted protocol for what is included in home office overhead

Delay Damages Extended Home Office Overhead / Indirect Overhead Most of the home office overhead is time driven If a project is extended beyond the reasonable projection, home office costs are also extended Not absorbed by the project Costs incurred benefit all of the contractor s projects

Delay Damages Extended Home Office Overhead / Indirect Overhead Virtually impossible to directly allocate overhead costs to a specific delay period Fraught with accounting difficulties Multiple jobs with varying start dates and completion dates makes it almost impossible

Delay Damages Extended Home Office Overhead / Indirect Overhead Recovery is based on the argument that there should be recovery because the delay precluded other projects from being able to absorb the overhead Need to prove: Other work is available and the contractor would have been able to obtain that work; or The contractor tried to obtain that work to absorb the overhead

Delay Damages Extended Home Office Overhead / Indirect Overhead Eichleay allocates home office overhead on a ratio Delayed project s billings to the firm s total contract billings During the period of the performance of the delayed project Total overhead amount for the period of the delayed project is divided by the number of actual contract days to determine daily rate Multiply the number of days of delay by the daily overhead rate

Delay Damages Home Office Overhead / Indirect Overhead Use of Eichleay: still estimates the overhead Fails to consider: Inefficient management Timing of the delay on the overhead levels Impact of other work during the project s delay

Delay Damages Recovery of Equipment Costs Idle or under-utilized equipment Consider Ownership costs Maintenance Repair Storage Depreciation Rental Rates

Delay Damages Interest Review the contract May have circumstances when you can recover May have the rate for interest Refer to the statute if no contract provision Section 408.020 RSMo 2000 Interest at 9% If liquidated Liquidated: amount can be determined by mathematical computation

Delay Damages Interest Interest generally does not begin to accrue until there is a demand for payment Make your liquidated claim as soon as possible to trigger the interest

Delays Problems caused by Concurrent or Joint Cause General proposition: no liability for the other party s delays unless Caused by the party Caused by circumstances under the party s control Contractual clauses can change this allocation of risk

Delay Early Completion Even if the contractor finishes earlier than the contractual completion date Can still claim a delay if the party can show the project would have finished earlier than it did but for the compensable delay

Impact, Escalation, and Acceleration Conduct of others may hinder productivity - even if finished on time May cause: Out of sequence work Stacking of trades Congestion Shift work Access issues

Impact, Escalation, and Acceleration Escalation: increased cost attributable to performing the work at a later date than planned Acceleration: process of adding resources to the project to complete on schedule

Disruption Generally associated with change orders Ripple effect impacts the project aside from the direct costs associated with the change Contractors will often try to preserve the indirect impact from the changes Absent the preservation, the Owner may well have a valid defense to subsequent claims The Change Order is accord and satisfaction Relieves the Owner from responsibility for the ripple effect

Delays and Interference Claims Ken Slavens ken.slavens@huschblackwell.com 314-345-6419

Best Practices for Managing Construction Delay and Interference Claims Prepared and Presented by: Quackenbush & Associates April 23, 2014

A step by step presentation of a contemporaneous schedule analysis performed during the project. (Resolving delays as they occur)

1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 5 5 4 3 4 8 12 16 Sawcut Concrete Slab - Install Gas & Plumbing Patch Concrete Wall Framing Rough- In Electrical Drywall 9 3 7 4 20 24 28 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 8 30 Final Trimout - Project Complete 4 A RESTAURANT RENOVATION

CONTEMPORANEOUS TECHNIQUE FLOAT 0 +3 +3 +4 +9 +9 +9 +9 0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 5 5 4 3 0 0 0 0 0 0 0 0 CRITICAL PATH 5 14 14 17 17 24 24 28 28 35 35 38 38 46 46 50 4 8 12 16 20 24 28 30 Sawcut Concrete Set, Hook- Laminate Final Floor & Wall Slab - Install Wall Up & Test Drywall Panels In Trimout - Rough-In Tile In Gas Framing Project Electrical All & Plumbing Complete Equipment Patch Conc. 9 3 7 4 7 3 8 4 A RESTAURANT RENOVATION

CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. IMPACT STEP DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 DAYS OF DELAY CONCURRENCY

CONTEMPORANEOUS TECHNIQUE Original Completion Date = 50 Net Delay -3 0 +5 +5 +6 +12 +12 +12 +12 0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 5 5 4 3 0 0 0 0 0 0 0 0 5 14 16 19 19 26 26 30 30 37 37 40 40 48 49 53 4 8 12 16 20 24 28 30 Sawcut Set, Hook- Concrete Laminate Floor & Wall Up Final Slab - Install Wall Drywall Panels In Rough-In Tile In & Test Trimout - Gas Framing All Project Electrical & Plumbing Equipment Complete Patch Conc. 9 3 7 4 7 3 8 4 0 0 14 16 48 49 I10 I11 Saw Cutting & Piping Install 2nd For 2nd Deep Fryer Deep Fryer 2 1 A RESTAURANT RENOVATION IMPACT #1 - ADD 2ND DEEP FRYER

CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. IMPACT STEP DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 DAYS OF DELAY CONCURRENCY

Update A End of Day 10 CONTEMPORANEOUS TECHNIQUE 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 0 5 75% 1 4 5 6 5 5 4 3 4 8 12 16 Sawcut Concrete Slab - Install Gas & Plumbing Patch Conc. 55% 4 9 Wall Framing Rough-In Electrical Drywall 3 7 4 20 24 28 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 8 30 Final Trimout - Project Complete 4 I10 Saw Cutting & Piping For 2nd Deep Fryer 2 I11 Install 2nd Deep Fryer 1 UPDATE A - END OF DAY 10

Update A End of Day 10 CONTEMPORANEOUS TECHNIQUE +3 +3 +4 +10 +10 +10 +10 11 11 16 16 22 22 27 27 32 32 36 36 39 1 2 6 10 14 18 22 26 Project Completion Unchanged - Net Delay = 0 Some Float Used On Non-Critical Activities NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 0 5 75% 1 4 5 6 5 5 4 3 0 0 0 0 0 0 0 0 14 16 19 19 26 26 30 30 37 37 40 40 48 49 53 4 8 12 16 20 24 28 30 Sawcut Concrete Slab - Install Gas & Plumbing Patch Conc. 55% 4 9 Wall Framing Rough-In Electrical Drywall 3 7 4 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 8 Final Trimout - Project Complete 4 0 0 14 16 48 49 I10 I11 Saw Cutting & Piping For 2nd Deep Fryer Install 2nd Deep Fryer 2 1 UPDATE A - END OF DAY 10

CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. IMPACT STEP DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 2 N/A DAY 10 2 STATUS UPDATE END OF DAY 10 53 0 DAYS OF DELAY CONCURRENCY

CONTEMPORANEOUS TECHNIQUE I20 New Electrical Sub 5 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 0 75% 1 5 6 5 5 4 3 4 8 12 16 Sawcut Concrete Slab - Install Wall Drywall Rough-In Gas Framing Electrical & Plumbing Patch Conc. 55% 4 3 7 4 20 24 28 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 8 30 Final Trimout - Project Complete 4 I10 Saw Cutting & Piping For 2nd Deep Fryer 2 I11 Install 2nd Deep Fryer 1 IMPACT #2 - FIND AND MOBILIZE NEW ELECTRICAL SUBCONTRACTOR

CONTEMPORANEOUS TECHNIQUE I20 15 New Electrical Sub 5 Project Completion Extended by 1 Day = Total Delays to Date -4 11 15 20 20 26 26 31 31 36 36 40 40 43 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 0 75% 1 5 6 5 5 4 3 14 16 19 20 27 27 31 31 38 38 41 41 49 50 54 4 8 12 16 20 24 28 30 Sawcut Concrete Slab - Install Gas & Plumbing Patch Conc. 55% 4 Wall Framing Rough-In Electrical Drywall 3 7 4 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 8 Final Trimout - Project Complete 4 14 16 49 50 I10 I11 Saw Cutting & Piping For 2nd Deep Fryer Install 2nd Deep Fryer 2 1 IMPACT #2 - FIND AND MOBILIZE NEW ELECTRICAL SUBCONTRACTOR

Was Impact #2 Electrical Subcontractor Replacement paced? What other options did contractor have? 1. Pay premium to start ASAP. 2. Hire on time and materials basis. What if contractor mis-judges the amount of pacing time available? Is it still pacing?

IMPACT STEP CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 2 N/A DAY 10 2 STATUS UPDATE END OF DAY 10 53 0 3 DAY 10 DAY 10 3 IMPACT #2 REPLACE ELECTRICAL SUBCONTRACTOR DAYS OF DELAY CONCURRENCY 54-1 SEE BELOW Summary of Delays (If Impact #2 Was Paced) Owner Responsible (Impact #1 & #3) Contractor Responsible (Impact #2) Summary of Delays (If Impact #2 Was Not Paced) Owner Responsible (Impact #3) Contractor Responsible (Last Day Impact #2) Concurrent (Impact #1 & First 3 Days of Impact #2)

CONTEMPORANEOUS TECHNIQUE I20 Update B End of Day 18 New Electrical Sub 100% 0 5 Project Completion Date Unchanged Delays to Date -4 20 20 26 26 31 31 36 36 40 40 43 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 0 75% 100% 0 1 60% 2 5 6 5 5 4 3 20 20 27 27 31 31 38 38 41 41 49 50 54 4 8 12 16 20 24 28 30 Set, Hook- Up Drywall & Test Sawcut Concrete Slab - Install Wall Gas Framing & Plumbing Patch Conc. 55% 100% 0 4 30% 2 3 Rough-In Electrical 7 4 Floor & Wall Tile In Laminate Panels In All Equipment 7 3 8 Final Trimout - Project Complete 4 I10 Saw Cutting & Piping For 2nd Deep Fryer 100% 02 49 50 I11 Install 2nd Deep Fryer 1 UPDATE B - END OF DAY 18

IMPACT STEP CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 2 N/A DAY 10 2 STATUS UPDATE END OF DAY 10 53 0 3 DAY 10 DAY 10 3 IMPACT #2 REPLACE ELECTRICAL SUBCONTRACTOR 4 N/A DAY 18 4 STATUS UPDATE END OF DAY 18 54 0 DAYS OF DELAY CONCURRENCY 54-1 SEE BELOW Summary of Delays (If Impact #2 Was Paced) Owner Responsible (Impact #1 & #3) Contractor Responsible (Impact #2) Summary of Delays (If Impact #2 Was Not Paced) Owner Responsible (Impact #3) Contractor Responsible (Last Day Impact #2) Concurrent (Impact #1 & First 3 Days of Impact #2)

CONTEMPORANEOUS TECHNIQUE I20 New Electrical Sub Project Completion Extended by -3 Days Project Delay to Date = -7 100% 0 20 20 26 26 31 31 36 36 40 40 43 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 0 100% 0 60% 2 6 5 5 4 3 20 20 27 30 34 34 41 41 44 44 52 53 57 4 8 12 16 20 24 28 30 Set, Hook- Up Drywall & Test Sawcut Concrete Slab - Install Gas & Plumbing Patch Conc. Wall Framing 100% 0 30% 2 Rough-In Electrical 7 4 Floor & Wall Tile In Laminate Panels In All Equipment 7 3 8 Final Trimout - Project Complete 4 I10 Saw Cutting & Piping For 2nd Deep Fryer 100% 0 27 30 52 53 I30 I11 City Requires Electrical Improvements 3 Install 2nd Deep Fryer 1 IMPACT #3 CITY REQUIRES ELECTRICAL IMPROVEMENTS

IMPACT STEP CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 2 N/A DAY 10 2 STATUS UPDATE END OF DAY 10 53 0 3 DAY 10 DAY 10 3 IMPACT #2 REPLACE ELECTRICAL SUBCONTRACTOR 4 N/A DAY 18 4 STATUS UPDATE END OF DAY 18 54 0 5 DAY 22 DAY 18 5 IMPACT #3 CITY REQUIRES ELECTRICAL UPGRADE DAYS OF DELAY CONCURRENCY 54-1 SEE BELOW 57-3 Summary of Delays (If Impact #2 Was Paced) Owner Responsible (Impact #1 & #3) Contractor Responsible (Impact #2) Summary of Delays (If Impact #2 Was Not Paced) Owner Responsible (Impact #3) Contractor Responsible (Last Day Impact #2) Concurrent (Impact #1 & First 3 Days of Impact #2)

CONTEMPORANEOUS TECHNIQUE I20 New Electrical Sub 100% 0 Update C End of Day 31 Project Completion Date - Unchanged Delays to Date -7 1 2 6 10 14 35 35 40 40 44 44 47 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 100% 0 100% 0 60% 0 2 100% 0 6 20% 4 5 5 4 3 34 34 41 41 44 44 52 53 57 4 8 12 16 20 24 28 30 Sawcut Concrete Slab - Install Wall Drywall Rough-In Gas Framing & Plumbing Electrical Patch Conc. 100% 100% 0 30% 0 2 100% 0 7 25% 3 4 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 8 Final Trimout - Project Complete 4 I10 Saw Cutting & Piping For 2nd Deep Fryer 100% 0 I30 City Requires Electrical Improvements 100% 0 3 52 53 I11 Install 2nd Deep Fryer 1 UPDATE C END OF DAY 31

IMPACT STEP CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 2 N/A DAY 10 2 STATUS UPDATE END OF DAY 10 53 0 3 DAY 10 DAY 10 3 IMPACT #2 REPLACE ELECTRICAL SUBCONTRACTOR 4 N/A DAY 18 4 STATUS UPDATE END OF DAY 18 54 0 5 DAY 22 DAY 18 5 IMPACT #3 CITY REQUIRES ELECTRICAL UPGRADE DAYS OF DELAY CONCURRENCY 54-1 SEE BELOW 57-3 6 N/A DAY 31 6 STATUS UPDATE END OF DAY 31 57 0 Summary of Delays (If Impact #2 Was Paced) Owner Responsible (Impact #1 & #3) Contractor Responsible (Impact #2) Summary of Delays (If Impact #2 Was Not Paced) Owner Responsible (Impact #3) Contractor Responsible (Last Day Impact #2) Concurrent (Impact #1 & First 3 Days of Impact #2)

CONTEMPORANEOUS TECHNIQUE I20 New Electrical Sub 100% 0 Update D End of Day 40 Project Completion Date - Unchanged Delays to Date -7 41 41 46 46 50 50 53 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 100% 0 100% 0 100% 0 100% 0 80% 1 5 5 4 3 4 8 12 16 Sawcut Concrete Slab - Install Gas & Plumbing Patch Conc. Wall Framing 100% 0 100% 0 Rough-In Electrical 100% Drywall 0 100% 0 4 41 41 44 44 52 53 57 20 24 28 30 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 90% 1 7 3 8 Final Trimout - Project Complete 4 I10 I30 52 53 I11 Saw Cutting & Piping For 2nd Deep Fryer City Requires Electrical Improvements Update D End of Day 40 Install 2nd Deep Fryer 100% 0 100% 0 1 UPDATE D END OF DAY 40

IMPACT STEP CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 2 N/A DAY 10 2 STATUS UPDATE END OF DAY 10 53 0 3 DAY 10 DAY 10 3 IMPACT #2 REPLACE ELECTRICAL SUBCONTRACTOR 4 N/A DAY 18 4 STATUS UPDATE END OF DAY 18 54 0 5 DAY 22 DAY 18 5 IMPACT #3 CITY REQUIRES ELECTRICAL UPGRADE DAYS OF DELAY CONCURRENCY 54-1 SEE BELOW 57-3 6 N/A DAY 31 6 STATUS UPDATE END OF DAY 31 57 0 7 N/A DAY 40 7 STATUS UPDATE END OF DAY 40 57 0 Summary of Delays (If Impact #2 Was Paced) Owner Responsible (Impact #1 & #3) Contractor Responsible (Impact #2) Summary of Delays (If Impact #2 Was Not Paced) Owner Responsible (Impact #3) Contractor Responsible (Last Day Impact #2) Concurrent (Impact #1 & First 3 Days of Impact #2)

CONTEMPORANEOUS TECHNIQUE I20 New Electrical Sub 100% 0 Update E End of Day 51 1 2 6 10 14 18 22 26 53 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet Project Completion Date - Unchanged Delays to Date -7 100% 0 100% 0 100% 0 100% 0 100% 0 15 100% 0 5 100% 0 4 30% 2 3 4 8 12 16 20 Sawcut Concrete Slab - Install Wall Gas Framing & Plumbing Patch Conc. 100% 0 100% 0 Rough-In Electrical 100% Drywall 0 100% 0 Floor & Wall Tile In 24 28 Laminate Panels In Set, Hook- Up & Test All Equipment 100% 0 7 100% 0 3 100% 0 8 53 57 30 Final Trimout - Project Complete 4 I10 I30 51 52 I11 Saw Cutting & Piping For 2nd Deep Fryer 100% 0 City Requires Electrical Improvements 100% 0 Update E End of Day 51 Install 2nd Deep Fryer 1 UPDATE E END OF DAY 51

CONTEMPORANEOUS SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. IMPACT STEP DELAY START DATE DATA DATE SCHEDULE RUN NUMBER DESCRIPTION PROJECTED COMPLETION DATE 0 N/A DAY 0 ORIGINAL ORIGINAL BASELINE SCHEDULE 50 0 DAYS OF DELAY CONCURRENCY 1 DAY 2 DAY 0 1 IMPACT #1 ADD 2 ND DEEP FRYER 53-3 2 N/A DAY 10 2 STATUS UPDATE END OF DAY 10 53 0 3 DAY 10 DAY 10 3 IMPACT #2 REPLACE ELECTRICAL SUBCONTRACTOR 54-1 SEE BELOW 4 N/A DAY 18 4 STATUS UPDATE END OF DAY 18 54 0 5 DAY 22 DAY 18 5 IMPACT #3 CITY REQUIRES ELECTRICAL UPGRADE 57-3 6 N/A DAY 31 6 STATUS UPDATE END OF DAY 31 57 0 7 N/A DAY 40 7 STATUS UPDATE END OF DAY 40 57 0 8 N/A DAY 51 8 STATUS UPDATE END OF DAY 51 57 0 Summary of Delays (If Impact #2 Was Paced) Owner Responsible (Impact #1 & #3) Contractor Responsible (Impact #2) = -6 Compensable Days = -1 Non-Compensable Days Summary of Delays (If Impact #2 Was Not Paced) Owner Responsible (Impact #3) Contractor Responsible (Last Day Impact #2) Concurrent (Impact #1 & First 3 Days of Impact #2) = -3 Compensable Days = -1 Non-Compensable Days = -3 Excusable/Non-Compensable Days

COLLAPSED AS-BUILT ANALYSIS 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 5 5 4 3 4 8 12 16 Sawcut Concrete Slab - Install Wall Gas Framing & Plumbing Patch Conc. 9 3 Rough-In Electrical Drywall 7 4 20 Floor & Wall Tile In 24 28 Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 8 30 Final Trimout - Project Complete 4 RESTAURANT RENOVATION - AS-PLANNED SCHEDULE

THE BUT-FOR LEGAL CONCEPT You can only claim damages (money and/or time) for delays that would not have been experienced but-for the delay in question. Basis of concurrent delay theory If you would have finished the project at the same time even if delay in question had not occurred then you have a concurrent delay. (Maybe! Must Consider Pacing!)

BUT-FOR SCHEDULE ANALYSIS (If it makes sense in evaluating concurrent delays why doesn t it make sense in schedule analysis?)

THE PIT BULL PROJECT

PIT BULL MOVES IN NEXT DOOR Pit Bulls can jump 3 wall. Pit Bulls cannot jump 6 wall. Owner directs contractor to build wall 6 high instead of 3 high. Contractor says ok but it will cost more and take 2 weeks longer. Owner OK s added work

COLLAPSED AS-BUILT ANALYSIS 0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 5 5 4 3 5 14 14 17 17 24 24 28 28 35 35 38 38 46 46 50 4 Sawcut 8 12 16 20 24 28 30 Concrete Laminate Set, Hook- Final Floor & Wall Slab - Install Wall Drywall Panels In Up Trimout - Rough-In Tile In Gas Framing & Test Project Electrical & Plumbing All Complete Patch Conc. Equipment 9 3 7 4 7 3 8 4 RESTAURANT RENOVATION - AS-PLANNED SCHEDULE

COLLAPSED AS-BUILT ANALYSIS 0 15 I20 New Electrical Sub 15 Note: this work was paced to known project delays. 0 5 5 9 15 20 20 26 26 41 41 46 46 50 50 53 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet As-Built Critical Path 5 4 5 6 15 5 4 3 5 14 16 20 20 27 30 34 34 41 41 44 44 51 53 57 4 8 12 16 20 24 28 30 Sawcut Concrete Slab - Install Wall Gas Framing & Plumbing Patch Conc. 9 4 Rough-In Electrical Drywall 7 4 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 7 Final Trimout - Project Complete 4 14 16 27 30 51 52 I10 I30 I11 Saw Cutting & Piping For 2nd Deep Fryer 2 Note: this work took longer than planned. City Requires Electrical Improvements 3 Note: this work was performed faster than planned. Install 2nd Deep Fryer 1 AS-BUILT SCHEDULE

COLLAPSED AS-BUILT ANALYSIS I20 New Electrical Sub 15 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 15 5 4 3 4 8 12 16 20 Sawcut Concrete Slab - Install Wall Gas Framing & Plumbing Patch Conc. 9 4 Rough-In Electrical Drywall 7 4 Floor & Wall Tile In 24 28 Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 7 30 Final Trimout - Project Complete 4 I10 Saw Cutting & Piping For 2nd Deep Fryer I30 City Requires Electrical Improvements 0 2 0 3 0 1 COLLAPSE OWNER DELAYS When would project have been completed if owner delays had not occurred? I11 Install 2nd Deep Fryer

COLLAPSED AS-BUILT ANALYSIS 0 15 I20 New Electrical Sub 15 Owner Delays Collapsed From Schedule - No Change In Completion Date - No Compensable Delays 0 5 5 9 15 20 20 26 26 41 41 46 46 50 50 53 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet Critical Path With Owner's Delays Collapsed Out 5 4 5 6 15 5 4 3 5 14 14 18 20 27 27 31 31 38 38 41 41 48 53 57 4 8 12 16 20 24 28 30 Sawcut Concrete Set, Hook- Laminate Final Floor & Wall Slab - Install Wall Up Drywall Panels In Trimout - Rough-In Tile In Gas Framing & Test Project Electrical & Plumbing All Complete Patch Conc. Equipment 9 4 7 4 7 3 7 4 I10 I30 I11 Saw Cutting & Piping For 2nd Deep Fryer City Requires Electrical Improvements When would project have been completed if owner delays had not occurred? Install 2nd Deep Fryer 0 2 0 3 0 1 COLLAPSE OWNER DELAYS - RECALCULATE CRITICAL PATH

COLLAPSED AS-BUILT ANALYSIS I20 New Electrical Sub 0 15 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 5 15 5 4 3 4 8 12 16 20 Sawcut Concrete Slab - Install Gas & Plumbing Patch Conc. Wall Framing 9 3 4 Rough-In Electrical Drywall 7 4 Floor & Wall Tile In 24 28 Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 7 30 Final Trimout - Project Complete 4 I10 I30 I11 Saw Cutting & Piping For 2nd Deep Fryer 2 City Requires Electrical Improvements 3 If contractor delays had not occurred when would the project have finished? Install 2nd Deep Fryer 1 COLLAPSE CONTRACTOR DELAYS

COLLAPSED AS-BUILT ANALYSIS 0 0 I20 New Electrical Sub 0 15 Contractor Delays Collapsed From Schedule Completion Date 2 Days Earlier, Contractor Responsible for 2 Days of Delay 0 5 5 9 9 14 14 20 20 25 25 30 30 34 34 37 1 2 6 10 14 18 22 26 NTP & Complete Interior Demolition Wall & Soffit Framing Electrical Rough-In Drywall In Painting Light Fixtures & Electrical Terminations Décor & Woodwork Carpet 5 4 5 6 5 15 5 4 3 5 14 16 19 19 26 29 33 33 40 40 43 43 50 51 55 4 8 12 16 20 24 28 30 Sawcut Concrete Slab - Install Wall Gas Framing & Plumbing Patch Conc. 9 3 4 Rough-In Electrical Drywall 7 4 Floor & Wall Tile In Laminate Panels In Set, Hook- Up & Test All Equipment 7 3 7 Final Trimout - Project Complete 4 14 16 26 29 50 51 I10 I30 I11 Saw Cutting & Piping For 2nd Deep Fryer 2 City Requires Electrical Improvements 3 If contractor delays had not occurred when would the project have finished? Install 2nd Deep Fryer 1 Critical Path With Contractor's Delays Collapsed Out COLLAPSE CONTRACTOR DELAYS - RECALCULATE CRITICAL PATH

COLLAPSED AS-BUILT SCHEDULE ANALYSIS RESTAURANT RENOVATION QUACKENBUSH & ASSOCIATES, INC. PROJECTED DAYS COMPLETION OF STEP DESCRIPTION DATE DELAY CONCURRENCY 1 As-Planned Schedule 50 0 2 As-Built Schedule 57-7 3 Collapse Owner Delays 57 0 4 Collapse Contractor Delays 55-2 5 Remainder of Delays Concurrent Between Owner & Contractor 55-50 -5 Summary of Delays: Owner Responsible 0 Contractor Responsible 2 Concurrent Responsible 5

Concurrency Criteria Two or More Delays in Same Time Frame Both Delays Must be on Critical Path Both Must Control the Project Completion Date But For The Other Delay Both Delays Must be Completely Independent Physically Managerially (No Pacing)

CONCURRENT DELAYS MEETING AT DENNY S SCENARIO #1 Bill and Dan agree to have a business meeting at Denny s the next morning at 7:00AM. Both Bill and Dan leave their home with enough time to arrive at Denny s by 7:00 AM. Bill decides to stop at the dry cleaners on the way, which consumes 10 minutes. Dan has a flat tire and it takes him 15 minutes to change the tire. Bill arrives at Denny s at 7:10 AM and is relieved to see that Dan has not yet arrived. Dan arrives at 7:15AM. Bill says Boy, Dan you are 15 minutes late. I have been waiting here a long time. You really need to be more responsible. WHO DELAYED THIS BREAKFAST MEETING AND BY HOW MANY MINUTES? Answer: Dan and Bill jointly delayed the meeting by 10 minutes, Dan delayed the meeting an additional 5 minutes. Reason: Both Bill and Dan were required at the meeting or it could not occur, thus they were both on the critical path, and both individuals acted independently. (Neither party knew the other was running late.) Thus a 10 minute Concurrent Delay.

CONCURRENT DELAYS MEETING AT DENNY S SCENARIO #2 Bill and Dan agree to have a business meeting at Denny s the next morning at 7:00AM. Both Bill and Dan leave home with enough time to arrive at Denny s by 7:00 AM. Bill has dry-cleaning to drop off but decides he better do that later so he can be on time to the meeting. Dan gets a flat tire and he immediately calls Bill on his cell phone to tell him he will be 15 minutes late. Bill decides he now has the time to drop the dry cleaning off and arrives at Denny s at 7:10 AM. Dan arrives at 7:15 AM. WHO DELAYED THIS BREAKFAST MEETING AND BY HOW MANY MINUTES? Answer: Dan delayed the meeting by 15 minutes. Bill did not delay the meeting at all. No Concurrent Delay Reason: Both Bill and Dan were required at the meeting, thus they were both on the critical path, but both individuals did not act independently. (Bill modified his planned approach based on information provided by Dan.) THIS IS COMMONLY CALLED PACING. Bill adjusted his activities based on Dan s delay.

QUESTIONS? THANK YOU huschblackwell.com