Errors and Omissions Finance Administration Operations Committee. January 15, 2014



Similar documents
Texas Department of Transportation

BEST PRACTICES IN THE MANAGEMENT OF DESIGN ERRORS AND OMISSIONS

North Dakota Department of Transportation Consultant Administration Section August 2007

Errors and Omissions Insurance. 1.0 Introduction and Definition

CHAPTER 11 APPEALS AND DISPUTES

MINNESOTA DEPARTMENT OF TRANSPORTATION POLICY MANUAL SUBMITTAL APPROVAL AND ROUTING FORM \ ~[ l ~ ~...,. ~~ """'..

Project Management Procedures

STATE OF DELAWARE DEPARTMENT OF TRANSPORTATION DESIGN-BUILD PROJECT. for INDIAN RIVER INLET BRIDGE SCOPE OF SERVICES PACKAGE CONTRACT DOCUMENTS PART 1

BROKER/SHIPPER AGREEMENT

BUSINESS ASSOCIATE AGREEMENT

Relocation Services Request for Proposal

Title 1, Chapter 57 of the Texas Administrative Code

SPECIAL TOPICS IN GUARDIANSHIP COMPROMISING CLAIMS FOR MINORS AND INCAPACITATED ADULTS. November 8, 2013

Payment of Interest on Overdue Invoices, Some Useful Tips

SUPERIOR COURT OF THE STATE OF WASHINGTON, KING COUNTY NOTICE OF PROPOSED CLASS ACTION SETTLEMENT

REQUEST FOR PROPOSALS TO PROVIDE FINANCIAL ADVISOR SERVICES TO THE CAMINO REAL REGIONAL MOBILITY AUTHORITY. October 29, 2014

Cecilia J. Ross, 9DPH Director, Los Angeles Office of Public and Indian Housing. Joan S. Hobbs Regional Inspector General for Audit, 9DGA

How To Manage A Service In Texas

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner

Summary of SB 107 (Budget and Fiscal Review) Chapter 325, Statutes of 2015

Liberty County School District Purchasing Card Procedures

TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 I. INTRODUCTION... 2 II. OBSERVATIONS AND CONCLUSIONS... 4

SELF-INSURED FIDELITY BOND PROGRAM

Sample Business Associate Agreement (4. Other Bus. Assoc., Version )

BUSINESS ASSOCIATE AGREEMENT

THIRD PARTY ADMINISTRATOR AGREEMENT. (Hereinafter, Agreement ) Between

MEMORANDUM OF AGREEMENT BETWEEN THE DEPARTMENT OF HOMELAND SECURITY AND THE DEPARTMENT OF THE ARMY

BUSINESS ASSOCIATE AND DATA USE AGREEMENT NAME OF COVERED ENTITY: COVERED ENTITY FEIN/TAX ID: COVERED ENTITY ADDRESS:

Wake County. Accounts Receivable Policy and Board Ordinance.

ARKANSAS FIDELITY BOND TRUST FUND STATE, COUNTY, MUNICIPAL AND SCHOOL DISTRICT BLANKET DISHONESTY BOND Policy No. FBTF12

OAKLAND USD RFP /09) ATTOR RNEY ENSATION WORKERS' COMP

Procurement practices of school districts and charter schools; definitions

Appendix 18 NEC3 Options

EXHIBIT A. NPS Dispute & Claim Consultant Scope of Work

HAWAII ADMINISTRATIVE RULES TITLE 16 DEPARTMENT OF COMMERCE AND CONSUMER AFFAIRS CHAPTER 17 CAPTIVE INSURANCE COMPANIES

September 2008 Report No An Audit Report on Energy Savings Performance Contracts at Selected Agencies and Institutions of Higher Education

myra Online Terms and Conditions

the court determines at a non-jury hearing that the award is not in the best interest of the child. The burden of proof at a hearing under this

AGREEMENT BETWEEN THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO and PROJECT ARCHITECT for A PROJECT OF LIMITED SIZE OR SCOPE

Online Account Management Service The Reliant Online Account Management Service consists of the following features:

Office of Compliance and Ethics Introductory Report. Lynette Fons, Chief Compliance Officer

August 2012 Report No

SCHEDULE PART 24 THIRD PARTY SOFTWARE AND THIRD PARTY SUPPORT CONTRACTS

Audit Guide for Consulting Services Cost Rates. March 11, 2015

MUNICIPAL DEBT FINANCIAL ADVISORY SERVICES

New Jersey Administrative Code. Encumbrance Accounting and Certifications of Availability of Funds

Cumbria County Council Environment Directorate BUDGET MANAGERS

FIXED COSTS PART 45. Contents of this Part

Appendix A. Call-off Terms and Conditions for the Provision of Services

FY2016 AGREEMENT TO FUND ECONOMIC DEVELOPMENT PROGRAMS AND SERVICES OPERATED BY DOWNTOWN DURHAM, INC. USING CITY OF DURHAM GRANT FUNDS

PURCHASING CARD POLICY AND PROCEDURES

PERMIAN BASIN REGIONAL PLANNING COMMISSION GRANT APPLICATION SUBMISSION POLICIES

December 2014 Report No An Audit Report on The Telecommunications Managed Services Contract at the Health and Human Services Commission

Report of independent certified public accountants in accordance with Government Auditing Standards and Circular A-133 State of Hawaii, Department of

AGREEMENT BETWEEN COUNTY AND CONTRACTOR FOR GOODS AND SERVICES. THIS AGREEMENT, effective this 20th day of April in the year, 2015, between:

OPERATIONS MEMO For Public Release

Review: 4424 Statewide Single Audit Year Ended June 30, 2013 Illinois Department of Transportation. FINDINGS/RECOMMENDATIONS 15 Repeated 12

SOUTH SHORE CHAMBER, INC (SPECIAL SERVICE AREA #42) Financial Statements Years Ended December 31, 2010 and Independent Auditor s Report

Antonio Gastelum, Inc. INVESTMENT MANAGEMENT AND ADVISORY AGREEMENT ( Agreement )

PARTICIPATION AGREEMENT For ELECTRONIC HEALTH RECORD TECHNICAL ASSISTANCE

Hillsborough County Aviation Authority Standard Procedure S Contractual Insurance Terms and Conditions

Bylaws of the Lawyer-Client Fee Dispute Resolution Committee of the Cleveland Metropolitan Bar Association. Enacted November 18, 2015

RESTATED CERTIFICATE OF INCORPORATION CTC MEDIA, INC. (Pursuant to Section 242 and 245 of the General Corporation Law of the State of Delaware)

PROFESSIONAL/CONSULTING SERVICES AGREEMENT

JOHN DEERE DIFFERENTIAL CORRECTION SOFTWARE LICENSE AGREEMENT

TOLL VIOLATION PAYMENT AND SETTLEMENT GUIDELINE

NOTICE TO BIDDERS Request for Proposals Legal Notice Advertisement: publish two(2) times:

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

TRANSPORTATION SERVICES AGREEMENT

Archdiocese of Anchorage

CLAIMS ADMINISTRATION SERVICES AGREEMENT

Guide to Electronic Disbursement Controls for Payroll Purposes D C A. Community AFFAIRS. State of New Jersey Jon S.

INDEPENDENT CITIES RISK MANAGEMENT AUTHORITY WORKERS COMPENSATION LITIGATION MANAGEMENT POLICIES AND PROCEDURES

TEXAS DEPARTMENT OF TRANSPORTATION. Fourth Quarter 2007

Don t Wait Until It s Too Late: Top 10 Recommendations for Negotiating Your Cyber Insurance Policy

NEGOTIATING WITH MEDICARE AND MEDICAID

Are you a Table Funding Partner? Are you a Correspondent?

BMA ADVISORS, LLC Investment Advisory Agreement

Company DBA: Company Legal Name: Company Federal EIN: Company State Unemployment ID Number:

Policy No: F&A Approved by Council: June 26, 2013 Resolution: The policy should assist in:

SANTA CRUZ COUNTY CRIMINAL DEFENSE CONFLICTS PROGRAM POLICIES AND PROCEDURES

LIFEMARK VILLAGE SCHEME RULES A SIX-PILLAR QUALITY ASSURED RETIREMENT COMMUNITY

Fiscal Year 2014 Fiscal Year 2016 DBE Goal Update

Florida is currently revising their PLI coverage requirements.

Concise clinical record documentation is critical to providing long term care residents

05 SB270/AP. Senate Bill 270 By: Senators Williams of the 19th, Whitehead, Sr. of the 24th and Kemp of the 46th A BILL TO BE ENTITLED AN ACT

Internet Services Terms and Conditions

DISMISSED WITH PREJUDICE: August 28, 2012 CBCA 2453, 2560 PRIMETECH, DEPARTMENT OF HOMELAND SECURITY,

Waterfront Auckland s Credit Card Policy

HiCAMS User Guide. Chapter 3: Contract Adjustments. Section 1: Review Claims

Contract Administration

CONTRACT ADMINISTRATION AND MANAGEMENT GUIDE

Reports of Compliance Concerns and Violations

Maryland State Department of Education

IEC Electronics Terms and Conditions

Small Public Work Contract

REQUEST FOR QUALIFICATIONS PROPERTY APPRAISAL SERVICES. Prepared by. City of Richmond Finance Department. February 18, 2016 RESPONSES DUE:

Amendment and Consent No. 2 (Morris County Renewable Energy Program, Series 2011)

STATE OF NEW JERSEY DEPARTMENT OF THE TREASURY DIVISION OF TAXATION REQUEST FOR INFORMATION ON TAX DEBT ADMINISTRATION AND RESOLUTION

CITY OF LEMOORE REQUEST FOR PROPOSALS FOR CREDIT CARD PROCESSING SERVICE. City of Lemoore Finance Department 119 Fox St Lemoore, CA 93245

Transcription:

Errors and Omissions Finance Administration Operations Committee January 15, 2014

Agenda Reasons contracts and plans change Errors and omissions defined Tollway process Successful design track record Minimal recoverable costs to date Continually seek best practices Discussion 2

Reasons Plans and Contracts Change Change is common in large capital programs Accelerated program schedules Differing site conditions Unidentified utilities Unidentified and unsuitable soil conditions Specification changes Tollway initiated Other agency initiated Balance final field measurements Errors and omissions Miscellaneous (such as weather) 3

Errors and Omissions Defined Error: An incorrect, conflicting, insufficient or ambiguous plan or specification detail or contract administration action Omission: A failure to indicate on drawings, specifications or other products of professional service the requirement for a feature, system or equipment necessary for the complete and proper function of a project 4

Tollway Process Contract Cost Change Controls Committee (C5) comprised of representatives from Engineering, Procurement, Finance and Audit reviews all construction contract changes C5 Committee identifies potential E and O items E and O items of more than $50,000 in construction change value reviewed in detail for possible cost recovery Design consultant notified and provided an opportunity to submit additional information or dispute E and O Chief Engineer makes final determination 5

Excellent Design Track Record Qualified and professional people performing the work Perform detailed plan reviews at each design submittal Manage quantities in construction process effectively One measure of design success is the cost of changes in construction (CO/EWOs) The Tollway has substantially lower costs of construction changes compared to industry average Percentage of change compared to total construction costs Industry average* Illinois Tollway 5 to 10 percent Less than 1 percent 6 *American Council of Engineering Consultants Library: Model for Qualifying the Impact of Change Orders on Project Costs for US Roadwork, December 2009

Minimal Recoverable Costs To Date Few potential E and O items identified From 2005 to 2013, nearly 15,000 Authorizations to Proceed (ATPs) approved; 243 identified as potential E and O for further evaluation Recoverable costs are not the total value of the change, but those costs that would not have been incurred had the plans been correct Of the 209 potential E and O items that have been evaluated to date, only $20,000 was identified as recoverable 7

Continual Review for Best Practices Reviewed recommended process American Association of State Highway and Transportation Officials (AASHTO) and benchmarked local agencies and other states Track changes due to E and O Identify procedure to review significant E and O Use committee of experts for significant E and O Chicago Department of Aviation Maintain appropriate threshold for E and O review Involve design consultant in discussions Wayne County Airport Authority Arizona Department of Transportation California Department of Transportation Illinois Department of Transportation Texas Department of Transportation 8

DISCUSSION What other best practices should we consider as part of our evaluation of the 2013 E and O items? Moving forward, what should be the threshold for evaluating recovery of costs? Is there value in a third-party review that warrants the cost? 9

10 Appendix

Compliance with AASHTO AASHTO recommended process: Discovery Agency conducts initial review of circumstances Initial notification Agency notifies consultant, requests their involvement Investigation/decision on liability Notification to consultant Review meeting(s) with consultant Alternative dispute resolution Recovery and collection Litigation Because litigation is expensive and time-consuming, AASHTO encourages agencies to build methods of dispute resolution into their contracts. These methods should encourage: Bringing together all parties quickly Focusing on fixing the design problem first, then addressing cost responsibility and recovery Consulting a state attorney general s office for information on appropriate alternative dispute resolution procedures Instituting a process that is fair and moves quickly to resolution 11

Local Agency Benchmarks IDOT Consultants notified of liability have 30 days to respond, process and move to dispute resolution if necessary E and O threshold: If construction less than $2 million, E and O amount limited to $20,000 If construction between $2 and $10 million, E and O amount limited to 1 percent of contract If construction greater than $10 million, E and O amount limited to $100,000 Chicago Airport System Uses reviewing committee that reviews alleged E and O, prepares written analysis and meets with consultants to resolve E and O Wayne County Airport Authority Designer pays an administrative service fee of 5 percent of actual cost of each construction change 12

Arizona DOT E and O As E and O are identified, ADOT performs a review, notifies the consultant, documents their decision on whether a claim is justified and content of the claim, and provides for consultant administrative review if the matter cannot be resolved ( MGT 00-2, Nov. 3, 2000, pp. 2-3). ADOT will estimate additional costs arising from the E and O based on the amount above that expected in the contractor s bid had the E and O not occurred. If the additional cost exceeds the lesser amount of five percent of the contractor s bid or $20,000, ADOT may file a formal claim. The amount of the initial claim will be the additional costs less the threshold value. Any future E and O claims on the project will not be subject to reduction by the threshold value. Unresolved claims over $100,000 will be forwarded to the attorney general s office. 13

CalTrans E and O As a guideline, contract change orders (CCOs) greater than $200,000 related to design changes, conflicts, ambiguities, errors and omissions and cumulative CCOs exceeding 10 percent of the construction project bid likely warrant further review and the matter is forwarded to the chairperson of the Management Review Panel (MRP). The MRP submits its recommendation to the chief engineer. If the chief engineer approves further action, he will appoint a representative or team to provide notice to the consultant and enter into informal discussions to resolve the matter. Caltrans legal division and the chief engineer will be kept apprised of the status of discussions. Alternative dispute resolution methods may be considered if agreeable to both parties. The consultant should be allowed to take part in discussions of additional costs due to design liability for which he may be held liable. If a resolution is not attained, the representative will consult with the legal division and recommend to the chief engineer if additional action should be taken. 14

Texas DOT E and O Change orders are tagged with a reason code identifying the cause of the change. If an E and O results in a change order, TxDOT must notify the consultant and give that firm an opportunity to address the matter. The amount of the recoverable cost is that which would not have been incurred had the plans been correct. The consultant must reimburse these costs in cash; in-kind services by the consultant are not acceptable as payment. A certified initial notification letter will be sent to the consultant describing the alleged E and O, related additional costs, and references to pertinent events. The consultant will be asked to respond within 30 days. If the consultant does submit payment, it is credited according to the procedural guidelines as a refund of expense on the affected construction project. If the consultant does not make payment, TxDOT may consider legal action. If litigation is the only remaining recourse, TxDOT will work with the state attorney general s office. 15

16 THANK YOU