Essential Views of the Integrated Program Management Reports. Thomas J. Coonce Glen B. Alleman

Similar documents
+ The Killer Question For Every Manager

L10: Budgeting and Cost Control. Olivier de Weck

DATA ITEM DESCRIPTION Title: Integrated Program Management Report (IPMR) Number: DI-MGMT Approval Date:

Appendix D Glossary Of Terms

700 Analysis and Reporting

An introduction to Earned Value Analysis

Earned Value Formulae

PROJECT TRACKING and CONTROL

Basic Concepts of Earned Value Management (EVM)

This EVMS Training Snippet sponsored by the Office of Acquisition and Project Management (OAPM) covers Firm Fixed Price (or FFP type) subcontracts.

Estimating Cost at Completion - Judgment & EV Information

INSE 6230 Total Quality Project Management

Brainstorm. What is Cost and Project Cost Management?

Project Management Using Earned Value

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

PERCEPTION. Tracking Progress & EAC

Over Target Baseline and Over Target Schedule Guide

Earned Value Management Systems Application Guide

COINS EVA Earned Value Analysis

Project Control System Manual. Jefferson Science Associates, LLC. 600 Progress Status. Project Control System Manual Revision

FERMI RESEARCH ALLIANCE PROCEDURES PROJECT MANAGEMENT. Head, Office of Project Management Oversight

DCMA DCMA-EA PAM October 2012

Earned Value and Agile Reporting

Contract Cash Flow & Performance Analysis. PERCEPTION Helping The Shipyard Stay On Budget

Introduction to earn value management in Civil Engineering

SUCCESSFULLY INTEGRATING AGILE WITH EARNED VALUE MANAGEMENT

Risk Workshop Overview. MOX Safety Fuels the Future

Glen B. Alleman Niwotridge Consulting

Training Seminars. Description. Core Courses: The core courses consist of the following:

Scheduling Process Maturity Level Self Assessment Questionnaire

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Sample Examination Questions

Chapter 7. (PMBOK Guide)

PM in construction industry

A Cure for Unanticipated Cost and Schedule Growth

300 Scheduling and Budgeting

NUMBER: 12.PM-004 RESPONSIBILITY: Office of Project Support Services REVISION: 4 APPROVED BY: TITLE SUBJECT: Head, Office of Project Support Services

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Systems Application Guide

Chapter 7: Project Cost Management. Munawar

THE APPLICATION OF PERFORMANCE MEASUREMENT TECHNIQUE IN PROJECT MANAGEMENT : THE EARNED VALUE MANAGEMENT (EVM) APPROACH

Earned Value Management System (EVMS) and. Project Analysis Standard Operating Procedure (EPASOP)

AACE International Recommended Practice No. 86R 14

Earned Value Management System Description

A Guide to Managing Programs Using Predictive Measures

Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu

A Gentle Introduction to Earned Value Management Systems

Cost & Schedule Risk Assessment 6.0. Timothy J. Havranek, MBA, PMP Leigh Hostetter, PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Unit 5: Cost Management (PMBOK Guide, Chapter 7)

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?

Head, Office of Project Management Oversight

INTEGRATED COST AND SCHEDULE CONTROL IN PROJECT MANAGEMENT

EARNED VALUE MANAGEMENT. CASE STUDY USING MICROSOFT PROJECT

FOREWORD. Page 2 of 88

Simple Earned Value (Using MS Project 2010)

Lecture Slides for Managing and Leading Software Projects. Chapter 8: Measuring and Controlling Work Processes

Applied Project Management ( APM )

DRAFT RESEARCH SUPPORT BUILDING AND INFRASTRUCTURE MODERNIZATION RISK MANAGEMENT PLAN. April 2009 SLAC I

How To Manage A Project

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

CPM -100: Principles of Project Management

Amajor benefit of Monte-Carlo schedule analysis is to

Earned Value Management Best Practices

10.1 Communications Planning 10.2 Information Distribution Figure Performance Reporting 10.1 Communications Planning 10.

Project Execution - PM Elements

Develop Project Charter. Develop Project Management Plan

A Framework for Project Metrics

CPM -100: Principles of Project Management

THE CONDENSED GUIDE. Software Program Managers Network (703) Fax (703)

Appendix A of Project Management. Appendix Table of Contents REFERENCES...761

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

earned value management

Earned Value Management Tutorial Module 6: Metrics, Performance Measurements and Forecasting. Prepared by:

Basics of Cost and Schedule Control

Step by Step Project Planning

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

PMO Metrics Recommendations

IST 302 : Project Cost Management

The To Complete Performance Index

How to successfully manage your mega-project

Procurement Management S# What? Formula Additional Notes CPPC CPFF CPAF CPIF T&M FPEPA FPAF FPIF FFP

Project Management Glossary

Baseline Change Control Procedure

Project Management: Tracking Progress and Earned Value with MS Project 2003

Earned Value Management for Enterprise Resource Planning Implementations

Project Control with ProTrack

Predicting progress on your project

The Program Managers Guide to the Integrated Baseline Review Process

Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria

Chapter 3: Project Cost Management

Project Cost Management

plans based on actual cost, schedule and technical progress of work [1, 9].

The 10 Knowledge Areas & ITTOs

EVM.01. Earned Value Analysis Why it Doesn't Work

PBL: Project Management. Competency: Project Definition

Chapter 5: Project Cost Management

Transcription:

Essential Views of the Integrated Program Management Reports Thomas J. Coonce Glen B. Alleman

Agenda Background Twenty-five metrics are proposed Twelve are demonstrated with tasserted value to the government PM Audience feedback 2

Background When contractually required, DoD acquisition contractors are obligated to submit IPMRs electronically per Data Item Description DI-MGMT-81861. Government stakeholders must acquire reader/viewers of the data to understand status and help control. Several vendors provide multiple metrics/views of these data: Some data more useful than others. Different users have different interests. Easy for the government PM to be overwhelmed" Key question is which metric/views are considered Essential to accomplish the stated goal of helping the material developer to keep the program green? 3

Background (Concluded) We synthesized research and possible metrics and distilled them to three fundamental categories 1. Evidence of a credible plan at the outset; one that is based on technical objectives and deliverables, available staffing and adjusted for risks 2. Periodic data to ensure that cost and schedule performance are in line with technical and contract deliverables progress 3. Periodic data (in addition to the technical performance data) that helps the PM identify current and likely future problem areas so they can be controlled We demonstrate the value of the metrics using a notional UAV program called the Tactical Situational Awareness System or TSAS Twenty-five metrics/views are proposed; twelve are shown and discussed in this presentation 4

The Proposed Metrics/Views 1. Key Technical Performance Measures plan(s) 2. Deliverables plan 3. Summary level of the Integrated Master Schedule (IMS) and proposed spend plan 4. Labor FTE utilization plan 5. Schedule health and performance checks 6. Risk register and mitigation actions 7. Computation of initial management reserves (MR) 8. Risk burn down plan 9. Computation of schedule reserves aka margin (SM) 10. TPM plan vs estimated actuals vs cost and schedule performance metrics (CPI, SPI) 11. Deliverables plan vs actuals vs CPI, SPI 5

The Proposed Metrics/Views 12. FTE plan vs actuals 13. Cumulative BCWS, BCWP, ACWP against IBR spend plan, earned schedule with percent spent, percent complete, and percent scheduled (Enhanced Gold Card) 14. Risk burn down plan vs actual 16. C/S Performance Informed by Risk Burn Down Actuals 17. Schedule heath and schedule performance related data on the goforward IMS (similar to view # 5) 18. Cumulative BCWS, BCWP, ACWP against IBR spend plan with Earned Schedule and status dates, percent spent, percent complete, and percent scheduled (same as # 13) 19. Tornado (or Galaxy) chart that shows the relative percentage of Budget at Complete to total for any level of WBS 6

The Proposed Metrics/Views Periodic Data That Indicates Current and Likely Future Problem Areas (Concluded) 20. Management Reserve usage and balance 21. Sources and uses of MR and Undistributed Budget 22. Updated Risk Register (same as metric/view # 5) 23. Forecast of EAC and ECD 24. Confidence level of meeting contractor best case, worst case and most like EACs and ECDs 25. Schedule and cost crucially indices 7

Six Steps To Creating a Credible PMB Step` ❶ Define WBS ❷ Build IMP ❸ Identify Reducible Risk Outcome With SOW, SOO, ConOps, WBS, and other program documents, develop CWBS of system deliverables and work processes to produce the program outcomes. Develop CWBS Dictionary describing scope of work and Criteria for the successful delivery of these outcomes. Develop Integrated Master Plan (IMP), showing how each system element in the CWBS moves through the maturation process at each Program Event. Define Measures of Effectiveness (MOE) for each Accomplishment. Define Measures of Performance (MOP) for each Criteria. For each key system element in the CWBS, identify reducible risks, probability of occurrence, mitigation plan, and residual risk in the Risk Register. Risk mitigation activities placed in IMS and PMB to assure probability of occurrence and probability of impact reduced. For risks without mitigation plans, Management Reserve (MR) (calculated) will be used to handle risk when it becomes an Issue. 8

Six Steps To Creating a Credible PMB (Concluded) Step ❹ Build the IMS Outcome Arrange Work Packages and Tasks in a logical network of increasing maturity of the deliverables. Define exit criteria for each Work Package to assess planned Physical Percent Complete to inform BCWP using TPM, MOP, MOE, and Risk Reduction activities in support of Accomplishments in the IMS. ❺ Adjust for Irreducible Risks For irreducible risks in the IMS, use Reference Classes for Monte Carlo Simulation anchored with Most Likely duration to calculate needed schedule reserve (margin). Assign schedule margin tasks in the IMS, to protect the key system elements, per DI-MGMT-81861 guidance. ❻ Establish PMB Using risk adjusted IMS, calculate needed Management Reserve (MR) to account for the latent risks in the Risk Register. With deterministic IMS and its embedded Schedule Reserves and Management Reserve for latent risk, determine the resulting confidence level of the PMB. 9

Schedule Health Checks at IBR 5 Value: Provides evidence that the contractor s initial plan meets quality schedule standards. Project success is not possible without a quality schedule. 10

Schedule Health Checks at IBR (Concluded) 5 11

The PMB Must Be Adjusted for Uncertainty The probability of an event that we can do something about reducing this probability through explicit actions. Reducible Uncertainty Irreducible Statistical range of natural randomness characterized by a historical data and therefore irreducible Probabilistic Events Probabilistic Impacts Periods of Exposure Natural Variability Ambiguity Known but un-mitigateable 13

Plan at IBR Must Be Adjusted for Reducible Risks Note Pre and Post Mitigation Risk Scores Value: Showing the Risk Register at the IBR provides evidence that all major risks have been considered and that the contractor has incorporated plans into the baseline to mitigate those risks. It also provides transparency about risk that have not been mitigated which can impact the probability of success. 14

Example of One Mitigation Strategy Value: Provides evidence that the contractor has a realistic risk buy down plan and has planned way points to reassess the mitigation actions and remaining risks. 14

Management Reserve Calculation Principles Management reserve (MR) is held for growth within the currently authorized work scope, for rate changes, and for other program unknowns. MR is not used to offset accumulated overruns or underruns and it is not a contingency budget than can be used for new work or eliminated from the contract price during subsequent negotiations. The management reserve budget is not included as part of the Performance Measurement Baseline (PMB). Source: ACQuipedia Operational Definition: Management Reserves (MR) covers inscope known reducible risks that were not mitigated. It is for in-scope work that may or may not materialize. 15

TSAS Monte Carlo Simulation for Unmitigated Reducible Risks Only 7 16

TSAS Management Reserve Calculation 7 17

TSAS IMS Prior to Adjustment for Irreducible Uncertainty 9 This is the revised TSAS IMS after adjustments for reducible uncertainty that remain in the Risk Register after mitigation actions. 18

Monte Carlo Simulation Results to Adjust the PMB for Irreducible Risks and Set Schedule Margin 9 Value: Ensuring the project plan accounts for the experience of historical projects (irreducible risks) yields a higher probability of meeting the planned delivery date. 19

Schedule Margin Calculation 9 Value: Including schedule reserve or margin, ensures the project possess a realistic probability of meeting the targeted delivery date. It is derived by running a Monte Carlo Simulation with the irreducible risks and resource-loaded IMS as inputs. 20

Placement of Schedule Margin in TSAS IMS 9 Value: This shows the PM how the contractor is providing time cushions in order to meet project milestones. 21

TSAS Summary Level IMS and Spend Plan CBB PMB Management Reserves = $3.5M Value: Provides PM with a big picture of the contractor s spend plan, the reasonableness of milestones, and management reserves 22

Weights vs. C/S Performance (as of 1QTR2016) 10 Value: Showing the technical progress such as weight against the cost and schedule performance data of the associated work packages is a leading indicator. 3QTR2015 weight is above plan and both CPI and SPI reflect this. By 1QTR 2016, weigh is on plan, because contractor spent more resources. C/S indices reflect same. 23

11 Deliverables and FTEs vs. C/S Performance (as of 3/31/2015) 12 Value: Showing the deliverables and planned vs actual personnel helps tell the story of the negative cost and schedule performance since labor is usually the largest component of cost. The contractor is more likely to be meet technical, cost and schedule objectives if the right personnel are put on the effort when planned. These data provide the PM an early warning signal. 15 24

TSAS Full Motion Video (FMV) C/S Performance Informed by Risk Burn Down 15 Value: Tells PM whether contractor s mitigation plans were successful and ensures that cost and schedule performance reflect those actions. 25

Example of Traditional Method of Forecasting EAC and ECD The Plan: Twelve month effort for $36K 23 The Performance at status date (5/31/2015): BCWS cum = $15K ACWP cum = $18K BCWP cum = $12.5K SPI cum =.833 CPI cum =.694 ES = 124d SPI t =.824 EAC Forecast: EAC composite = ACWP + [(BAC-BCWP cum )/(CPI cum SPI cum )] = $58.6K ECD Forecast Duration: Status Duration +( PD-ES)/SPI t = 150d + (366-124)/.824 = 444d ECD Forecast Date: Date Format of (42005+444) = 3/19/2016 Value: Tells PM the final cost and delivery date IF the contractor continues to perform exactly as it has done in the past (rearward focus). Facilitates problem diagnosis and discussions with the contractor. 26

Quantification of EACs and ECD From MCS of Remaining Reducible and Irreducible Risks 24 Worst Case EAC/ECD (1,100d,$24.1 <96%) (1,106d,$23.1 <60%) (830d,$17 <1%) Best Case EAC/ECD Most Likely EAC/ECD Value: Tells PM the range of possible final cost and delivery dates and probabilities of the contractor-stated projected EACs and ECDs based on a forward focus of the impact of reducible and irreducible remaining risks. Fosters pro-active management with the contractor. 27

Summary Proposed an enhanced set of key, or essential, program management metrics that a government program manager ought to have as a minimum to proactively manage and help control contracted efforts Demonstrated selected metrics with a notional UAV program Received suggestions for improvements 28

Questions 29 29

Process to Calculate Management Reserves 7 Calculate Contract Budget Base (CBB) from Price and Fee: CBB = Price/(1+fee percent) BAC i (from initial resource-loaded IMS) DO WHILE P80 Cost > CBB Run Monte Carlo Simulation for reducible risks in the Risk Register Revise Cost Plan (BAC i ) END DO Final cost plan = BAC f MR = CBB - BAC f 30

Schedule Margin Calculation Steps 9 Create Bottom-up IMS Plan (P) after adjusting for reducible risks DO WHILE P80 Date > Need Date (contractually required date) Run Monte Carlo Simulation for Irreducible Uncertainty Revise IMS Plan (P) END DO P f = PMB Final Finish Date Schedule Margin = Need Date Duration (P80 duration) P f Duration WHERE Irreducible Duration Uncertainty is determined from historical data 31

TSAS Risk Burn Down Plan 8 32

TSAS Schedule Margin Burn Down Plan 9 33