Project Plan. Details. Project Overview (What is going to be accomplished) TeamDynamix Project Number: 241095



Similar documents
DATA CENTERS AND SERVERS

Jamie Mathews Tracy Scott. Mike Frangi

END USER SUPPORT: DEVICE MANAGEMENT SUBPROJECT PLAN. Rick Bennett Tim Wolf. Mike Frangi

OneIT Identity and Access Management Sub 2: External Forest Migrations Project Team Leads: Mike Noel, Brandon Mills, Jordan O Konek Project Manager:

Communication and Collaboration. Ryan Lenger, Scott Fuller. Isaac Podolefsky

U.S. Nuclear Regulatory Commission

COMMUNICATIONS & COLLABORATION. Ryan Lenger Scott Fuller. Isaac Podolefsky

Mark Ahrens Andy Jenkins. Jessica Richardson

76a-WCM Brief March 07.pg 2 76b- WCM Brief June 08...pg 8

Citrus College. Technology Master Plan Adopted 2011

Project Charter IDENTITY AND ACCESS MANAGEMENT. Project Information. Project Overview. Project Purpose and Benefits to Campus. Project Scope Statement

AE Initiative Summary Business Case Data Center Aggregation

FRMS Transfers. Project Charter Document

Information Technology Strategic Plan /23/2013

Project Management Plan for

Planning and Administering Windows Server 2008 Servers

CENG Information Technology Services University of North Texas

Windows Server 2012 Licensing & Pricing FAQ

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.

ELECTRONIC FILE STORAGE. Laurie Hafner Dahms Mark Wilson. David Bronder

46 years of success Anne Arundel Community College. State of Technology at AACC

Licensing & Pricing FAQ

Managing and Maintaining Windows Server 2008 Servers

About this Course This 5 day ILT course teaches IT Professionals to design and deploy Microsoft SharePoint 2010.

Expert Reference Series of White Papers. Microsoft Assessment and Planning (MAP) Toolkit Version 9.x

Windows Server 2003 Migration Guide: Nutanix Webscale Converged Infrastructure Eases Migration

Managing and Maintaining Windows Server 2008 Servers (6430) Course length: 5 days

Information Technology (IT) Strategic Plan Update Fiscal Year 2016

Iowa State University Proposal for HR-01 ISU HR Operating Model

PUB (MPI) 1-62 Reference: Gartner Scorecard

Information Technology (IT) Report April and May 2015

Server Consolidation. Report to the Joint Legislative Oversight Committee on Information Technology

University Data Communication Plan

Configuring and Deploying a Private Cloud

Phase III Work Team Project Charter and Calendar Consolidation Implementation

2. Please describe the project s alignment with the Common System Principles (Appendix 1).

Planning and Administering Windows Server 2008 Servers

Communication and Collaboration: Migration Project Team Leads:

One IT Governance. Maggie Jesse, Tim Shie. Romy Bolton

This course is intended for IT professionals who are responsible for the Exchange Server messaging environment in an enterprise.

Audience: FAA Administration and partners with Service Level Agreements FAA Strategic Goal(s) Alignment:

Audit of the Data Center Consolidation Initiative at NARA. OIG Draft Audit Report No May 10, 2012

Vodafone Cloud & Hosting Services. Gary Goodenough 13 th November 2015

Windows Server 2012 授 權 說 明

Module: Sharepoint Administrator

1. Project Charter. Sheri Kellogg. Phyllis Short. Project Title: PeopleSoft CSS / HCM Split Description:

Federal Data Center Consolidation Initiative

UT Market. Project Charter Document. Doc. Ref.: Charter UT Market Version: Draft 6 Status: REVISED on 4/27/2010 Initial Date: 2/4/2010

Implementing Hybrid Cloud at Microsoft

UNT Institutional Effectiveness Database

Stephen Hess. Jim Livingston. Program Name. IAM Executive Sponsors. Identity & Access Management Program Charter Dated 3 Jun 15

SharePoint Administrator

Service Level Agreement Between: Computing and Informational Technology And The Finance and Business Operations Division

Configuring and Deploying a Private Cloud 20247C; 5 days

Federal Data Center Consolidation Initiative (FDCCI)

W H I T E P A P E R. Reducing Server Total Cost of Ownership with VMware Virtualization Software

Server Consolidation with SQL Server 2008

Federal Data Center Consolidation Initiative

Table of contents. Matching server virtualization with advanced storage virtualization

Data Centers and Cloud Computing

Cloud Storage in a PaaS World

Using Microsoft Operations Manager To Monitor And Maintain Your Farm. Michael Noel.

State of Wisconsin. Active Directory (AD) Service Offering Definition (SOD)

Performance Audit Concurrent Review: ERP Pre-Solicitation

Technology Services Strategic Direction

VMware vsphere: [V5.5] Admin Training

Case Study: Provade. Optimizing Application Infrastructure with High Performance Oracle RAC clusters, InfiniBand & Scalable Cloud Computing

! Internet Technology Advisory Committee! Web Accessibility Committee

Campus Mobile Framework Service Level Agreement (SLA)

Program Summary. Criterion 1: Importance to University Mission / Operations. Importance to Mission

The Cañada Technology Plan (Drafted 08/09)

Project Charter EMI Outreach July 25, OE Project Charter. 1.0 July 25, 2011 Draft w/ VC Denton comments included /02/2011 Proofed/edited

User Reports. Time on System. Session Count. Detailed Reports. Summary Reports. Individual Gantt Charts

Administrative Services Annual Program Review Report 2008

STUDENT INFORMATION SYSTEM PLANNING PROJECT

HR IN THE CLOUD. Basil Sommerfeld Partner Operations Excellence & Human Capital Deloitte

State of Minnesota IT Governance Framework

Integrated Technology Plan (FY10 FY12)

Data Centers and Cloud Computing. Data Centers. MGHPCC Data Center. Inside a Data Center

RO-Why: The business value of a modern intranet

VMware vsphere 5.1 Advanced Administration

Version: 5 Date: October 6, 2011

Windows Server 2008 R2 Hyper-V Live Migration

Designing a Microsoft SharePoint 2010 Infrastructure

Amazon.com, Inc. and its affiliates. All rights reserved.

The University of Alabama at Birmingham. Information Technology. Strategic Plan

CLASS SPECIFICATION Systems Support Analyst II

DRAFT. FY15 UW-Stout Institutional IT Plan

Request for Proposal for Application Development and Maintenance Services for XML Store platforms

Program Lifecycle Methodology Version 1.7

Microsoft Private Cloud

Information Technology Master Plan Presentation November 2013

Datacenter Migration Think, Plan, Execute

UCPath Project Status Report

Cloud Computing Trends

A Journey through Meaningful Use at a Large Academic Medical Center: Lessons of Leadership, Administration, and Technical Implementation

R3: Windows Server 2008 Administration. Course Overview. Course Outline. Course Length: 4 Day

Texas Transportation Institute Information Resources Strategic Plan

Information Technology Transformation Plan Phase I Status Report for October 2013 Issued November 2013

Program Summary. Criterion 1: Importance to University Mission / Operations. Importance to Mission

Transcription:

Details Project Name: Data Center Consolidation Project Leads: Guy Falsetti, JJ Urich, Jerry Protheroe Project Manager: Kris Halter Dynamix Project Number: 241095 Project Overview (What is going to be accomplished) To consolidate 48+ data centers on campus into the correct number of centrally supported, multi-tenant data centers based on current and future needs and requirements of the University. 1. Complete a thorough inventory, evaluation and classification of existing data center and server room spaces across campus, computing equipment housed in them and services provided. a. Retire If server/service is no longer is needed, retire the server or service. b. Consolidate If the service can be migrated to an existing service, consolidate. c. Virtualize Evaluate the current workload, CPU, memory, and disk requirements. If software will support virtualization, move to a virtual guest on central server farm. d. Cloud Evaluate the current workload, CPU, memory, and disk requirements. If the software will support a cloud provider move the service to the cloud. e. Replace Evaluate the current hardware age and configuration. If out of warranty and/or not in a configuration suitable for the data center then replace the hardware with new equipment. f. Migrate If all other options are exhausted. Move the equipment. 2. Develop process for moving Non-High Performance Computing (HPC) clusters. A team would look at evaluating each server/service. 3. Gather current energy usage or calculate estimates in the current location. 4. Develop data center services and operational models that facilitate consolidating data centers spaces. Work to ensure that services provide remote management capability and levels of support comparable to a local facility. 5. Identify schedule/sequence of server moves and server room retirements. 6. For each server room, assess the services provided by each server, identify target (move to central service, virtualize or move server) and move services/servers as needed. 7. Identify contingencies as required for services that can t move and/or perform cost benefit analysis for possible exemptions. 8. Decommission server rooms that have completed data center and server consolidation. 9. For remaining Data Centers bring them up to university standard and multi-tenancy; a. Evaluated network connections to the location. b. Install monitoring systems for the facility. c. Install video surveillance for the facility. d. Set up governance structure for the facility. Data Center Consolidation Project Plan Page 1 of 6

Project Staffing (Who will perform the work) Who Skill Set Estimated Time Commitment Guy Falsetti Project Lead 200 JJ Urich Project Lead 200 Jerry Protheroe Project Lead 200 Kris Halter Project Manager 200 Gary Arner Project Member 150 Kevin Zhu Project Member 100 Mark Sadewasser Project Member 100 Stephen Hoffman Project Member 100 Sys Admins System Migration 400 Total Hours 1650 Project Schedule (When will the work be started/completed) Phase 1 - Initiation (Spring Summer 2015) April 2015 June 2015 COMPLETE Develop project charter Develop stakeholder registry Form advisory committee Form project team Phase 2 - Planning (Summer/Fall 2015) June 2015 October 2015 COMPLETE Macro level audits of all server rooms. Determine engagement and communication strategy. Engage IT campus community as needed for feedback. Outline high level Data Center service offerings for migrations and consolidations. Determine what rooms will get consolidated, and what rooms may get upgraded. Determine additional requirements. Finalize project plan and post for public comment. Phase 3 - Implementation - October 2015 August 2018 Stage 1 Low Hanging Fruit - July 2015 June 2016 Consolidate management of the future state centrally run Data Centers into one work group. Use the service migration process to close 20 server rooms. For each server room closed, develop, scope and complete a decommission plan. Continue campus engagement as defined in Stage 1 (provide updates on Project and gather feedback). Flesh out baseline service offerings. Data Center Consolidation Project Plan Page 2 of 6

OneIT Steering Committee review and feedback of baseline service offerings. Vet service offerings to campus IT community. Start implementing baseline services. Tweak service based on feedback. Flesh out next round of service offerings. Develop network redesign requirements for support of multitenancy DCs. Stage 2 Enhance DCS Service offerings and consolidate mid-level rooms - July 2016 June 2017 Consolidate server management into one group. Use the service migration process to close 8 data centers. For each server room closed, develop, scope and complete a decommission plan. Continue campus engagement as defined in Stage 1 (provide updates on Project and gather feedback). Flesh out expanded service offerings. Update campus IT community and OneIT Steering Committee. Tweak service based on feedback. Stage 3 Consolidate remaining rooms - July 2017 June 2018 Use the service migration process to close 4 data centers. For each server room closed, develop, scope and complete a decommission plan. Stage 4 Finalize Consolidation - July 2018 Complete all service migrations. Phase 4 (Fall 2018) August 2018 Project Close Out. Ongoing service enhancements. Project Budget 1. Funding a. Data Center Server Consolidation FY16 - $250K i. - $20K initial funding for the project. b. Data Center Network Aggregation FY16 - $350K c. DC Facilities FY16 - $280K d. Data Center Server Consolidation FY17 - $250K e. Data Center Network Aggregation FY17 - $350K f. DC Facilities FY17 - $280K Data Center Consolidation Project Plan Page 3 of 6

2. Staffing Addition a. Technical Project Manager - $100K b. 2 x Sr. Systems Administrator - $140K Change Control Plan (What is the process for managing change) Changes to the order of inventories of server rooms, and staff conducting inventories will be evaluated approved by the Technical Lead. Changes to inventory timeline will be evaluated and approved by the DCS Steering Committee. Changes in the budget will be evaluated and approved by the DCS Steering Committee. Scope changes and additions will be evaluated and approved by the DCS Steering Committee. Substantial changes to project scope will be brought to the OneIT Steering Committee for evaluation and resolution for items deemed outside of timeline, budget, and scope by the DCS Steering Committee. Communications Plan (How will information be communicated) Target Audience Primary Contact Communication Mechanism OneIT Steering Committee Project Frequency Purpose/Description of Communication Chris Clark Presentation As needed Overall plan for migration. Approvals for plans and budgets. JJ Urich or Guy Discussion Bi-Weekly Project Status and Falsetti Planning CITL Community Program Office Presentation Once Understanding of Data Center Services. Buying into the process of migration of services. Where their departments can help with service consolidation. ITADmin Community Advisory Committee Deans and Department Heads Tim Wolfe Presentation As needed Overall plan for migration. Where their departments can help with service consolidation. Kris Halter Presentation Bi-Monthly Project Status and and Discussion Planning Steve Fleagle Presentation Once Consolidation of IT resources can help improve services to campus and lower the overall cost to departments. Reduce the risk of loss of university Author / Owner Guy Falsetti Guy Falsetti, Jerry Protheroe and JJ Urich Guy Falsetti and JJ Urich Guy Falsetti Data Center Consolidation Project Plan Page 4 of 6

Select Faculty Members/Research Groups Facilities Services Stakeholder for server rooms data. Improve the support for Faculty research with high speed Faculty Member Discussion Once The University supports their academic and research missions. This will allow them better network connections. Common infrastructure components are centrally funded. Steve Dellabetta and Ann Rosenthal Discussion Quarterly Consolidation of IT resources can help improve services to campus and lower the overall cost. Room Owner Discussion As many as it takes The University supports their academic and research missions. This will allow them better network connections. Common infrastructure components are centrally funded. Guy Falsetti, Jerry Protheroe and JJ Urich Risk Management Plan Risks will be identified during project team meetings, audits or discussions with project stakeholders and server room owners. Once identified the risks will be assessed and the likelihood of occurrence and impact on the project will be determined. Risk mitigation strategies will be developed for risks that have a high impact and a high likelihood of occurrence on the project. The risk tracking list will be located on the Data Center and Servers Project SharePoint Site. https://sharepoint.uiowa.edu/sites/projects/oneit/implementation/datacenter/shared%20documents/02_planning/risk %20and%20Issue%20Registry.xlsx Risk Risk Description Likelihood Impact Mitigation Strategy Number (H,M,L) (H,M,L) 1 Significant Up Front cost H H Get Central Funding to seed this project 2 Significate Labor needed H H Spread project over a number of years and consolidate server management 3 Flexibility needed by Departments H H Develop a group that will address the needs of Academic and Research units on campus 4 Resistance to Change H H Monthly Advisory meetings, preemptive emails to server room owners about project inventory plans, initial communication to faculty via Steve Fleagle, one on one s with staff and faculty as server rooms are inventoried and migrated. Data Center Consolidation Project Plan Page 5 of 6

5 Network architecture H H Redesign ITF network with multi-tenancy as goal (or is some other team doing this?) 6 Run out of space in DC s M M Develop governance and life cycle management policies 7 New DCs/Servers brought up in defunct locations M M Policy and Adherence. Removal of server room MEP (HVAC and electrical support) systems. Remodeling of locations for alternate usage. 8 Shadow IT M H Must make ITS service delivery more agile to prevent systems from returning to local offices or research labs. Issue Tracking and Resolution Plan Issues will be identified during project team meetings, audits or discussions with project stakeholders and server room owners. Once identified the issues will be evaluated, tracked and assigned in the issue tracking list located on the Data Centers and Servers Project SharePoint Site. https://sharepoint.uiowa.edu/sites/projects/oneit/implementation/datacenter/shared%20documents/02_planning/risk% 20and%20Issue%20Registry.xlsx Metrics / Key Performance Indicators Multi-tenant data center services identified and created or enhanced Number of Data Centers decommissioned Number of Physical Servers moved Number of Physical Servers converted to VMs Number of Physical Servers decommissioned Number of VMs decommissioned Energy Savings MEP Operations & Maintenance Savings Staff Savings Project Plan Approval Date MM/DD/YY Data Center Consolidation Project Plan Page 6 of 6