INTERACTIVE VISUAL LEAN SYSTEM FOR RESOURCE PLANNING OF EARTHWORK OPERATIONS



Similar documents
How To Implement Lean And Bim On An Infrastructure Project

THE LEADING MINE SCHEDULING SOLUTION

Applying the Chronographical Approach to the Modelling of Multistorey Building Projects

REAL-TIME SUPPLY CHAIN MANAGEMENT USING VIRTUAL DESIGN AND CONSTRUCTION AND LEAN

APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION

A PRODUCTION PLANNING SUPPORT SYSTEM FOR CONSTRUCTION PROJECTS

Planning and Scheduling. Railway Maintenance Work. with TILOS

Deswik.Sched. Gantt Chart Scheduling

(Refer Slide Time: 01:52)

ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY

Sage 200 Manufacturing Datasheet

Construction Equipment Fleet Management

Trapeze Rail System Simulation and Planning

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

ANALYSIS OF PLANNING AND MANAGEMENT PRACTICES IN THE CONSTRUCTION INDUSTRY

Keywords: Programming, planning, linear work, civil engineering, time chainage, 4D, virtual reality.

Linear Schedules for Tunnel Projects

CRITICAL PATH METHOD (CPM) SCHEDULES

joint Resource Optimization and Scheduler

Full-time MSc in Logistics and Supply Chain Management

Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose

Linear Planning in Pipeline Construction

Is Truck Queuing Productive? Study of truck & shovel operations productivity using simulation platform MineDES

EXPLORATIVE APPLICATION OF THE MULTI- DOMAIN MATRIX METHODOLOGY IN LEAN DESIGN

Project Time Management

3D Modelling & Mine Planning Software. Comprehensive tools provide a competitive advantage from exploration to rehabilitation.

MDM AS A PROCESS MAPPING TOOL IN LEAN CONSTRUCTION

CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS

Software engineering used in simulation of Flexible Manufacturing Systems

TRACKING HAULING TRUCKS FOR CUT-FILL EARTHMOVING OPERATIONS

SITE & PROJECT MANAGEMENT

CRASHING-RISK-MODELING SOFTWARE (CRMS)

The Plan s Journey From Scope to WBS to Schedule

GPS BASED TRUCK DISPATCH SYSTEM (TDS) IN HIGHLY MECHANIZED BAUXITE MINES A CASE STUDY.

Ming Sun 1, Ghassan Aouad, Nick Bakis, Stuart Birchall, William Swan

Spec. Standard: 11/27/ Revision: 11/27/06

Transvision Waste Planner

Project Time Management

Technique (LOBST) for a Real estate sector

Backward Scheduling An effective way of scheduling Warehouse activities

TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *

PREDICTIVE AND OPERATIONAL ANALYTICS, WHAT IS IT REALLY ALL ABOUT?

White Paper Operations Research Applications to Support Performance Improvement in Healthcare

LAST PLANNER, LOOK AHEAD, PPC: A DRIVER TO THE SITE OPERATIONS

CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL

Course Syllabus For Operations Management. Management Information Systems

Teaching Lean Construction: Pontifical Catholic University of Peru Training Course in Lean Project & Construction Management

A new approach to rail asset management.

TechnicalNotes. Terramodel Software for Construction

PROFESSIONAL PROJECT MANAGEMENT SOFTWARE FOR THE CONSTRUCTION INDUSTRY. Version 8

Empirical Application of GPS Fleet Tracking Technology to a Soil Excavation Process

Project Scheduling: PERT/CPM

High-Mix Low-Volume Flow Shop Manufacturing System Scheduling

Construction Equipment Fleet Management: Case Study of Highway Construction Project

STOCHASTIC SIMULATION MODEL FOR A LONG DISTANCE SAND TRANSPORTATION PROCESS

Application Survey Paper

Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time

A new short- and medium-term production scheduling tool MineSight Schedule Optimizer (MSSO)

Project management: a simulation-based optimization method for dynamic time-cost tradeoff decisions

Project Management Tools

Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects

Practical Aspects of Construction Scheduling

Bachelor of Games and Virtual Worlds (Programming) Subject and Course Summaries

SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING. Mikhail Hanna Janaka Y. Ruwanpura

Scheduling Glossary Activity. A component of work performed during the course of a project.

Achieve greater efficiency in asset management by managing all your asset types on a single platform.

State-Based Probabilistic Scheduling Using STROBOSCOPE s CPM Add-On

Comparison of Mine2-4D versus MineSched for Mine Scheduling

LS/ATN Living Systems Adaptive Transportation Networks

Asset Management Policy March 2014

Project Time Management an essential element to project success

Microsoft Project 2010

Mastering Microsoft Project 2013

VisPMIS: A VISUAL PROJECT MANAGEMENT INFORMATION SYSTEM

Science Stage 6 Skills Module 8.1 and 9.1 Mapping Grids

Automated Mine Scheduling: What is it and will it help me?

Agile Software Development

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS

Differences Between CPM and Linear Schedules

processes 1 This survey report is written within the PWO Project: Production scheduling of batch

Model, Analyze and Optimize the Supply Chain

Transcription:

652 INTERACTIVE VISUAL LEAN SYSTEM FOR RESOURCE PLANNING OF EARTHWORK OPERATIONS Nashwan Dawood 1, Rajiv Chavada 2, Claudio Benghi 3 and Romeu Sanches 4 ABSTRACT Poor resource planning and low productivities in road construction projects are among the major factors that contribute to cost escalation and projects overruns. Although a number of tools and methods have been developed to enhance road construction planning and in particular earthworks planning and visualisation, current practices suggest that these tools are not practical and fragmented. The aim of this paper is to develop a practical, lean and transparent knowledge driven model to reduce the complexity of earthwork operations, improve efficiency of planning processes and reduce waste at operational phase. In this context, this research presents an interactive visual lean system that integrates different earthwork modules (including resource productivity, profile visualisation, planning and scheduling activities) to achieve efficient and productive construction plans. The system integrates atomic model configuration for productivity calculation, profile visualisation for Mass-haul and Time-distance profile, Gantt viewer for activity planning and management. The paper introduces the theoretical aspects of planning and scheduling in linear projects, develops system framework for the proposed model, discusses the prototype and demonstrates the prototype through a real life case study. KEY WORDS Visualisation tool, Integrated system, Earthwork operations, Object oriented environment, Lean Construction INTRODUCTION AND LITERATURE REVIEW Construction projects are inherently unpredictable and complex due to the dynamic nature of site operations. Current practices suggest that project planners carry out earthwork operations in road construction using deterministic methods based on their past experience and knowledge. This has resulted in cost and time overruns caused by the lack of inclusion and appreciation of unique risk factors. Also, there is a lack of appropriate information technology (IT) tools and methods which can be used to comprehend the construction operations and processes. Information Technology has 1 2 3 4 Professor, School of Science and Engineering, and Director of the Centre for Construction Innovation and Research, Teesside University, Middlesbrough, TS1 3BA, UK, Phone +44 1642/342494, FAX 1642/342494, n.n.dawood@tees.ac.uk PhD Student, Centre for Construction Innovation and Research, School of Science and Engineering, Teesside University, Middlesbrough, TS1 3BA, UK, Phone +44 1642/342494, FAX 1642/342494, H8130479@tees.ac.uk Senior Lecturer, Northumbria University, Newcastle upon Tyne, NE1 8ST, Phone +44 191/2437368, claudio.benghi@northumbria.ac.uk Program Manager, Mota-Engil, Romeu.Sanches@mota-engil.pt Proceedings IGLC-18, July 2010, Technion, Haifa, Israel

Interactive Visual Lean System for Resource Planning Of Earthwork Operations 653 the capacity to demonstrate uncertain and stochastic behaviour of different processes to predict the outcomes of construction projects. A number of literatures have been reviewed regarding earthwork operations and IT enabled lean approaches to construction projects. Jayawardane and Price (1994) developed RESOM (Roadwork Earthwork moving Simulation Optimisation Model) to optimise earthwork operations applying linear/integer programming techniques. Liapi (2003) focused on visualisation tool to validate the construction process visually by developing collaborative decision-making construction scheduling and planning for highway construction projects. Kang et. al. (2006) used morphing (visual) techniques to simulate earthwork operations such as cutting and filling where progress of site activities are simulated and changes of ground levels due to cut and fill are visualised. Chi-Ming et. al. (2007) developed an integrated system that combines a path-finding algorithm: ripple ring, plant database and genetic algorithms for optimising the feasible alternatives. Shah et. al. (2008) proposed a model that produces weekly location plans presented in the form of time-chainage. Over the years construction industries have been criticized for having wasteful processes, unsafe working practices and less technological innovation (Egan, 1998). Al-Sudairi et. al. (1999) presented value specification, value stream (waste elimination), flow, pull, and continuous pursuit of perfection as the lean principles. Ballard (2000) argued the planning of construction just involved scheduling activity and no resource allocation. By implementing a Lean system, it provides an opportunity to allocate the resources that minimize the risk factor of uncertainty of a project completion. Kemppainen et. al. (2004) used Dyanroad2 to support planner and contractor to optimise mass-haul, monitor and control production plan. It was used for minimizing the cost of resources and control construction schedule. Rischmoller and Alarcon (2005) presented a synergistic qualitative framework to explain theoretical lean principals on the construction process and the impacts of IT on the construction industries in order to increase communication, visualisation and mitigate complexities of construction operations. Dave et. al. (2008) suggested that there is a need of redesign the construction processes in order to integrate process, people and information to deliver efficient and safe practices. In this research context, the system demonstrates the lean principles by specifying the value, mapping the value stream, smooth process flow, pull approach and transparent model for continuous improvement. It plays an important role for earthwork operations planning in order to achieve more transparency to reduce the complexity of site operations, waste of the resources and improve resource planning that impact on project time. Some of the commercial tools have been used for earthwork planning such as: TILOS 5 is a time-location planning tool for managing linear construction projects such as roads, rail lines, pipelines and tunnels. DynaRoad 6 is a tool that can be used for schedule, mass haulage optimisation and progress control for earthwork operations in construction projects such as roads and railways. However it lacks the functionalities to simulate the productivity and cost considering variable factors such as sets of equipment, site constraints and soil characteristics using what if scenarios. Furthermore, users need to calculate existing and design ground level of road section separately before importing into the tool for optimisation of haulage distance and time 5 TILOS (2010), Available at: [http://www.tilos.org] 6 DynaRoad (2010), Available at: [http://www.dynaroad.com] Enabling Lean with IT

654 Naswan Dawood, Rajiv Chavada, Claudio Benghi, and Romeu Sanches location chart. One of the main shortfalls of the tools and methods produced by the above research projects is the lack of industrial applicability and practicality of using such tools on site. The research project presented in this paper is a continuation of previous research efforts by Dawood and Castro (2009). They have developed a knowledge-based simulator dubbed RoadSIM to assist planners to select resources and determine construction cost and time. This research project aims to present a methodology that develops an interactive visual lean system to assist project managers in achieving accurate and effective resource planning and management of earthwork activities. It is hypothesized that by integrating different earthwork modules, including resource module (RoadSIM), profile visualisation, activity planning and scheduling efficient, productive and efficient and lean construction sites can be materialized. In order to develop an interactive visual lean system, a number of objectives have been set: Design a framework to identify and integrate different earthwork components including resource module, activity planning module, distance optimisation and earthwork profile visualisation. Implement earthwork modules into an integrated environment using object oriented methodology to develop the interactive visual lean system. Run a real life case study to demonstrate the system. The next section proposes a conceptual framework and describes the different modules for earthwork projects and their functionalities. DEVELOPMENT OF AN INTERACTIVE VISUAL LEAN SYSTEM The system integrates the different earthwork modules which include: resource module, profile visualisation, optimal distance calculation, activity planning and scheduling in an object oriented environment. Figure 1 presents a conceptual framework for the developed system. It describes the input data structure, system processes and outcomes of the system. The input information describes empirical data that was collected from many different sites in order to calculate the possible accurate productivity of resources. The system process presents an integration of above mentioned earthwork modules to exchange the information between different component for earthwork operations, productivity rate calculation, activity planning and scheduling processes. It aids the project planners to manage the site operations efficiently and accurately by avoiding an unnecessary execution of resources in order to reduce waste at operational phase. Earthwork operations have predefined resources and their duration is calculated through productivity rates. The system demonstrates an interactive profile viewer for Mass-haul and Time-distance profiles, resource model for productivities calculation, Gantt viewer for activity planning and management. The system demonstrates adoption of the lean principles such as: Specifying the value (empirical data from site experiences) It collects the equipment data from number of site experiences. It specifies the empirical data of resources such as equipment type, site constraints, and external factors among others. It inputs the real-time data of earthwork profiles. Map the value stream (Develop Atomic model) It develops a number of atomic models. It reduces the complexity of the resources by creating an Proceedings IGLC-18, July 2010, Technion, Haifa, Israel

Interactive Visual Lean System for Resource Planning Of Earthwork Operations 655 atomic model mechanism that assists to avoid unnecessary allocation of resources in order to eliminate the waste of resources at operational phase. Smooth flow of Information (Integrating earthwork modules) - The model integrates different earthwork modules such as Earthwork views, resource configuration and project planning management in order to exchange information smoothly between different earthwork components. Pull approach (customise productivity rates and project planning)- The system can focus and customise productivity rates by managing atomic models and activities planning. It improves the resource planning by allocating resource as per project requirements at specific time. Pursue perfection (applying above all + transparent interactive knowledge driven model) Combine all of the previous improvements that develop transparent knowledge driven model for continuous improvement in order to reduce wastes at operational phase. This simplifies the working procedure substantially, especially in performing what-if analyses. Section 2.1 to 2.4 describes the various earthwork modules in details. Earthwork profile information Chainage distance Actual earthwork profile and Design earthwork profile. Cut/Fill volume quantity information Rock (%) percentage cutting Database Resource knowledge Equipment type Soil type Working condition I N P U T P Resource productivity calculation Integrated knowledgebase system Earthwork profile visualisation component R O C E Project planning and scheduling component Optimal distance calculation S S Final outcomes Profile visualisation. Mass-haul view. Time-distance view. Project planning module (Gantt Viewer). Resource productivity model. O U T P U T Figure 1 : System framework Enabling Lean with IT

656 Naswan Dawood, Rajiv Chavada, Claudio Benghi, and Romeu Sanches INPUT OF THE SYSTEM There are two types of system inputs: I) Resource knowledgebase database II) Earthwork profile data. Resource module stores site experience knowledge of equipment data to carry out different earthwork operations such as cutting/filling on construction sites. It specifies the empirical values of resources such as soil type, equipment type, resource efficiency and haul distance. The user should input earthwork profiles into the system prototype that store input data such as chainage distance, volume quantities, actual and design ground level. Sections below elaborate on the atomic models for different set of resource model calculation. Atomic Models An atomic model refers to the involvement of the number of equipment units which can be used to perform an activity, such as cutting or filling, in earthwork operations. In order to reduce the complexity of earthwork operations, atomic models are divided into the set of equipments. Each model has a different set of equipment to carry out different earthwork activities. Atomic models use empirical information augmented by interviews and knowledge elicitation from construction managers (Castro and Dawood, 2005). It maps the value stream to avoid unnecessary execution of resources and reduce resource waste during the execution phase. It assists project planner to carry out different What if-scenarios to facilitate the choice of resource selections as per project demands. Examples of atomic models presented in figure 2 are given below: Excavation operation- Excavate the soil mass using Excavation equipment. Tipper truck Hauling- Haul the excavated soil to a specific distance using tipper truck. Soil Excavator Ready to Operate Manoeuvre and positioning Start excavating soil mass Excavator Travel backward Deposit soil in stock pile Excavator Travel forward Tipper truck hauling Travel loaded Dumping queue Manoeuvre and positioning Dump the soil mass Ready to go Truck load Loading queue Return Figure 2 : Atomic model for Cutting operation SYSTEM PROCESS The system process presents an integration of various earthwork modules: Profile visualisation, Resource productivity calculation, Optimal distance calculation and Project resource planning for earthwork operations on construction sites. Profile Visualisation This is an interactive earthwork visualisation component. This component visually manages the resource information for planning the earthwork operations. It visualises Proceedings IGLC-18, July 2010, Technion, Haifa, Israel

Interactive Visual Lean System for Resource Planning Of Earthwork Operations 657 customized earthwork profile information into mass-haul and time-distance visualisation profile. The user should input earthwork profile data to be able to visualise this information into graphical as well as tabular format. There are two types of representation for earthwork profiles: I) Mass-haul profile: It visualises cutting and filling volume quantities along with Bruckner curve (Mass-curve). Planners can interactively select earthwork volume to calculate cutting/filling quantities and assign resources (team and equipment) on a specific chainage distance. II) Time-distance view profile: This presents an earthwork profile along a chainage distance versus activity progress direction and time. It demonstrates a specific activity (duration is presented in number of weeks) that will be carried out on a chainage distance. The system has a feature to demonstrate activity progress into forward and backward direction (Refer figure 3). Resource model Earthwork Profile Visualisation Resource Productivity Calculation Figure 3 : Earthwork Components The productivity formulas have considered all factors affecting the productivity including site working conditions, resources availability, site constraints and external factors. An equipment productivity calculation has been developed by RoadSIM (Dawood and Castro, 2009). The resource model specifies the atomic model level and resource level which adds the value during productivity calculation by eliminating the repetition of dependent value such as earthwork type, equipment efficiency among others in the resource model hierarchy (Refer figure 3). Optimal Distance Computation Activity planning module Mass-haul distance optimisation is achieved by linear optimisation technique. It minimises the waste and maximizes the utilization of resources by optimising the mass-haul movements that impacts on time and budget. It optimise the mass-haul movement along with consideration of borrow pit and land-fill section (form of waste). The simplex algorithm has been implemented to solve linear optimisation Enabling Lean with IT

658 Naswan Dawood, Rajiv Chavada, Claudio Benghi, and Romeu Sanches problems in order to balance mass quantities and optimal distance. This algorithm has been developed in C#.Net by using LPSolve library (Open source). Project Planning and Scheduling The Gantt chart is a useful graphical representation technique to plan and schedule activities for complex earthwork projects. The Gantt-viewer assists planner to organize a list of weekly earthwork activities. It visualises the activities into Gantt chart format in order to analyse the sequence of operations. This module has a project management capability so that planners can change dates, predecessor and successor as required. It focuses on pull approach by allowing user planning customisation and necessary resource allocation. Activity duration depends upon the selection of the resources for mass-haulage. If the atomic model changes, productivity will change which affects the total activity duration. This is a very powerful project management engine that identifies the critical path of the earthwork projects (Refer figure 3). OUTCOME OF THE SYSTEM The system is a sophisticated, user-friendly and valuable tool for resource planning of earthwork operations. The system can be useful for planners to analyse various information such as earthwork operation volume quantities, time location planning etc by producing Mass-haul, Time distance, and Bruckner view (Mass-curve) diagrams. The interactive nature of the system aids the planner to select balanced volume quantities in order to plan different earthwork activities. The system also visualises road obstruction elements such as Bridges, Hydraulic passage, Entry access point, Upper and under passage etc. The resource model simulates resource productivity calculation for project planner to carry out different What if-scenarios in order to facilitate the choice of resource selections as per project demands. The system has a graphic Gantt viewer to analyse the different plan activities and visualises the sequences of planned activity operations. In overall this system verifies the integration of different earthwork modules and use of lean principles in order to improve quality, productivity and efficiency on road construction sites. DEMONSTRATION OF PROCESS THROUGH REAL LIFE CASE STUDY The real life site case study data is used to test the system prototype in order to verify the expected outcomes. The collected data of a 5.6 km length of road section in Portugal was used to demonstrate the developed prototype functionalities. As an input data, earthwork profile (Chainage distance, 25m intervals), Actual and Design ground level) and sectional volume profiles were considered to calculate the earthwork operations quantities. Below section presents a brief overview of system processes. BRIEF OVERVIEW OF INTERACTIVE VISUAL LEAN SYSTEM PROCESSES This section presents process of the developed prototype (Refer to figure 4). First, the system is started by the user, and then a new project file is created to store the project configuration for later use. The user must create and load earthwork profiles. Based on the loaded earthwork profiles, the system visualise volume quantities and generates Bruckner-curve (Mass-curve). The user creates a team that instantiate atomic model to Proceedings IGLC-18, July 2010, Technion, Haifa, Israel

Interactive Visual Lean System for Resource Planning Of Earthwork Operations 659 configure resource parameters such as site working conditions, equipment efficiency and external factors for earthwork operations and allocate resources. Start Create a new project file Earthwork profile information: Chainage distance, Actual and design profile NO Create profile? YES Load profiles information Earthwork volume profile: Sectional quantity of cutting/filling, % of Rock NO DB Create team? YES Resource information: Load equipment data Load resource atomic model for Productivity calculation Interactively select profile to calculate and view operation volume information Visualise volume quantities profiles. View time-distance profile (see the forward or backward progress of activity planning). Add road modeling elements as per project requirements. Plan and schedule a list of activity User can choose different atomic model to update the productivity that will change the activity duration. Plan and schedule a list of activity. End Figure 4 : Functional model of system prototype The user can select the alternative atomic model to calculate volume quantities for the selected chainage distance area (Interactively users can select earthwork volume profiles on 2D graphic viewer modules). The atomic models selection and planning management modules enables continuous improvement during planning activities. The system visualises time-distance view to demonstrate working location against time duration. The gantt viewer calculates the activity duration based on the selected productivity rates. It demonstrates planned activities in a sequential order to analyse the resource planning information. The system can also add and visualise the obstruction information such as Bridges, Hydraulic passage. The functional model aids users to understand the flow of the system in order to plan resources efficiently. Enabling Lean with IT

660 Naswan Dawood, Rajiv Chavada, Claudio Benghi, and Romeu Sanches The system assists project planners at the planning and execution stage of road projects in order to manage resources for earthwork operations. CONCLUSION This research paper presents an interactive visual lean system to mitigate the complexity of earthwork operations, improve resource planning processes and reduce waste at operational phase. A review of current practices indicated that poor resource planning, low productivity and complicated nature of the construction sites are the major problems in construction industries. Such problems could be tackled by the use of IT enabled lean approaches. Considering practical limitations of existing practices, this research paper test the hypothesis by proposed interactive visual lean methodology to plan on site resources for earthwork operations. It integrates different earthwork modules including the Resource information module (atomic model, resource productivity calculation, team allocation), the project planning and earthwork visualisation components (Actual and design graph, chainage distance, mass-haul and time-distance view, bruckner curve, road obstruction). It demonstrates the exchange of information between different earthwork modules using lean principles such as specify value, map the value, smooth flow of information, pull approach and pursue perfections which enables user friendly system functionalities and transparent knowledge driven model. The lean principles enabled conceptual framework is proposed for an interactive lean system to identify important research components. The system enables more interactivity and flexibility in terms of user interaction due to the customisable sophisticated user interface. The system provides more transparency to the planner by customising different views of earthwork profile such as mass-haul, time distance and planning various activities. The system is a valuable tool for construction planner to improve project efficiency and resource planning process in construction sites. FUTURE WORK The future work will include control modules in order to measure the project performance and track the progress of the projects. The proposed system can plan and schedule the construction projects using critical path method and will apply lean enabled principles to schedule the projects for 4-6 weeks ahead in order to do shortterm planning. The developed system will verify and validate a proposed hypothesis through a real life case study in order to confirm the practicality of the system in the real time road construction projects. In a further development knowledge base H&S rule and workspace conflicts can be integrated into project planning to do further development. ACKNOWLEDGMENTS The presented research was supported by the Centre for Construction Innovation and Research (CCIR), Teesside University, UK and Portugal based International Construction Company (Mota-Engil). Sincere appreciation is given to the sponsor from the authors. Proceedings IGLC-18, July 2010, Technion, Haifa, Israel

Interactive Visual Lean System for Resource Planning Of Earthwork Operations 661 REFERENCES Al-Sudairi, A., Diekmann, J., Songer, A. and Hyman, B. (1999) - "Simulation of construction processes: traditional practices versus lean principles", in Tommelein, I. (Ed.), Proceedings 7th Ann. Conf. Intl. Group for Lean Construction IGLC-7, Berkeley, CA. Ballard, H.G. (2000) - The Last Planner System of Production Control, Ph.D. Dissertation, School of Civil Engg, Univ. of Birmingham, U.K., Page 192. Castro, S. and Dawood, N. (2005) - Roadsim: Simulation modeling applied to road construction, International conference on Computing in Civil Engineering, Cancun, Mexico. Chi Ming, T., Thomas, K. L. and Bill, W. L. (2007) - An integrated system for earthmoving planning, construction management and economics, volume 25, issue 11, pg 1127 1137. Dave, B., Koskela, L., Kagioglou, M. and Bertelsen, S. (2008) - A critical look at integrating people, process and information systems within the construction sector Available at : [http://www.iglc.net/conferences/2008_manchester/conferencepapers/]. Dawood N, Castro S (2009) Automating road construction planning with a specific- domain simulation system, ITcon Vol. 14, pg. 556-573, http://www.itcon.org/2009/36 Egan Sir J (1998) - Rethinking construction: report of the construction task force on the scope for improving the quality and efficiency of UK construction. London: Department of the Environment, Transport and the Regions. Jayawardane, A. and Price A. (1994) - A new approach for optimising earthmoving operations, Proceedings of Institute of Civil Engineering. Kang, L.S., Jee, S.B., Kim, C.H., Pak, S.Y., and Moon, H.S. (2006) - 4D System for visualisation Scheduling Progress of Horizontal Construction Project Including Earth Work, Proceedings of the CONVR Conference 2006, 4-6 August, Florida, USA. Kemppainen, J., Mäkinen, J., Seppänen, O. and Kankainen, J. (2004) Lean Construction Principles in Infrastructure Construction - Available at: [http://www.iglc2004.dk/_root/media/13058_039-kemppainen-makinenseppanen-kankainen-final.pdf]. Liapi, A. K. (2003) - 4D Visualisation of Highway Construction Projects, Proceedings of the 7th International Conference on Information Visualisation (IV 03), 1093-9547/03 2003 IEEE. Rischmoller, L. and Alarcón, L.F. (2005) Using Lean Principles as a Framework to Study Information Technology in Construction, [Available at]: [http://www.iglc.net/conferences/2005/papers/session04/20_079_rischmoller_ala rcon.pdf]. Shah, R. K., Dawood, N. and Castro, S. (2008) - Automatic generation of progress profiles for earthwork operations using 4D visualisation model, ITcon Vol. 13, pg. 491-506. Enabling Lean with IT