IMO Systems Change Management Procedures. IMO Systems Change Management Procedures for Market Participants



Similar documents
OPERATING PROCEDURE IT CHANGE MANAGEMENT PROCEDURES MANUAL. PREPARED BY: AEMO DOCUMENT NO: Enter Document ID VERSION NO: 6.

IT Service Management

University of Waikato Change Management Process

North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project CHANGE MANAGEMENT MANUAL

Customer Responsiveness Strategy

Gladstone Ports Corporation Limited

The Newcastle upon Tyne Hospitals NHS Foundation Trust. IT Change Management Policy and Process

This Service Level Agreement applies to the Services as defined in the Service Supply Agreement.

Disability ACT. Policy Management Framework

The purpose of this document is to define the Change Management policies for use across UIT.

NYSED DATA DASHBOARD SOLUTIONS RFP ATTACHMENT 6.4 MAINTENANCE AND SUPPORT SERVICES

REGISTER OF DELEGATIONS COUNCIL TO CEO Environmental Protection Act 1994

Change Management. Service Excellence Suite. Users Guide. Service Management and Service-now

Change Submitter: The person or business requesting or filing the Request For Change (RFC) notice.

Change Management Process. June 1, 2011 Version 2.7

Change Control Process

Welcome to the Centers for Medicare & Medicaid Services presentation, Accessing and Interpreting the Hospice Final Validation Report & Reviewing Top

ITIL Example change management procedure

Auditing data protection a guide to ICO data protection audits

OF THE REPUBLIC OF ARMENIA ON LIMITED LIABILITY COMPANIES

TICSA. Telecommunications (Interception Capability and Security) Act Guidance for Network Operators.

IT CHANGE MANAGEMENT POLICY

Standard operating procedure

Introduction Purpose... 4 Scope... 4 Manitoba ehealth Change Management... 4 Icons RFC Procedures... 5

CHAPTER Committee Substitute for Committee Substitute for Committee Substitute for House Bill No. 1033

Enablement Material Workflow Overview Available Workflow types and Samples

LIBERTY INDEPENDENT SCHOOL DISTRICT, LIBERTY,TEXAS REQUEST FOR PROPOSAL DELINQUENT TAX ATTORNEY RFP #13-01

Data Governance Policy. Staff Only Students Only Staff and Students. Vice-Chancellor

December 21, The services being procured through the proposed amendment are Hosting Services, and Application Development and Support for CITSS.

Information Management Policy

Regional Council of Goyder

BMDW House Rules Date: April 5, Bone Marrow Donors Worldwide House Rules approval by the BMDW Editorial Board, April 5, 2013

Capital Works Construction Project. [Insert Project Title] [Insert Sponsoring Agency]

PRISM Compliance Management Vendor Rollout Series PRISM Vendor User Training

WHITEPAPER Complying with HIPAA LogRhythm and HIPAA Compliance

RFP Automated Agenda Workflow System Questions and Answers

REVIEWED ICT CHANGE MANAGEMENT POLICY

ITIL Version 3.0 (V.3) Service Transition Guidelines By Braun Tacon

[name of project] Service Level Agreement

CITY OF BONITA SPRINGS, FLORIDA RFP #

Draft Copy. Change Management. Release Date: March 18, Prepared by: Thomas Bronack

Incident Management Policy

TAHOE REGIONAL PLANNING AGENCY REQUEST FOR PROPOSAL FOR SOFTWARE CONSULTANT

Part 2.13: Change and Baseline Management

HIPAA Privacy Rule Policies

West Dunbartonshire Council. Follow-up data protection audit report

CODE GOVERNANCE COMMITTEE CHARTER. 1 Functions and responsibilities of the Code Governance Committee

Request for Proposals RFP # Geodatabase Design and Implementation

ONLINE PROGRAM MANAGEMENT SYSTEM. Program Management System. Overview PRINTED ON 16/06/2009 PAGE 1 OF 10

IT Services. Service Level Agreement

Maruleng Local Municipality ICT CHANGE MANAGEMENT POLICY

Qualified Entity (QE) Member Facing Services Requirements

GUIDANCE NOTES ON UNIVERSITY REGULATIONS FOR THE DEGREE OF DOCTOR OF PHILOSOPHY

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

Redlined BSCP71 text for CP1430 Clarification to the ECVA/MVRN processes

INTERNATIONAL FOUNDATION FOR ELECTORAL SYSTEMS (IFES) RFQ/15/0061

DRAFT TEMPLATE FOR DISCUSSION CORPORATE GOVERNANCE COMPLIANCE STATEMENT

<PROJECT NAME> PROJECT MANAGEMENT PLAN

Page 1 of 8. Any change, which meets the following criteria, will be managed using IM/IT Change Management Process.

How To Manage A Board In The Kandijan Germany

Accounts Payable Automation 7 Ways Automation Can Reduce Pain Points in Accounts Payable. Ebook

IN THE SUPREME COURT OF THE STATE OF NEVADA

Quality Management Plan Template

Agenda. OCR Audits of HIPAA Privacy, Security and Breach Notification, Phase 2. Linda Sanches, MPH Senior Advisor, Health Information Privacy 4/1/2014

UMHLABUYALINGANA MUNICIPALITY PATCH MANAGEMENT POLICY/PROCEDURE

EAST TEXAS COUNCIL OF GOVERNMENTS CRIMINAL JUSTICE DEPARTMENT POLICIES AND PROCEDURES

Regulated Documents. A concept solution for SharePoint that enables FDA 21CFR part 11 compliance when working with digital documents

European Code of Conduct on Data Centre Energy Efficiency

Document Control in an ISO Environment

PSU Hyland OnBase Document Imaging and Workflow Services Level Memorandum of Understanding

COMPLIANCE FRAMEWORK AND REPORTING GUIDELINES

1. INCIDENT MANAGEMENT

Article 29 Working Party Issues Opinion on Cloud Computing

Guide to Assessment and Rating for Services

CONTRACT MANAGEMENT POLICY

SIS Release Management Breakout Session

Office of the City Auditor. Audit Report. AUDIT OF THE SERVICE LEVEL AGREEMENT OF THE at&t MANAGED SERVICES AGREEMENT (Report No.

Template for Automatic Number Plate Recognition (ANPR) Infrastructure Development Privacy Impact Assessment

CODE OF PRACTICE APPOINTMENT TO POSITIONS IN THE CIVIL SERVICE AND PUBLIC SERVICE MERIT PROBITY ACCOUNTABILITY

Corporate Governance Guidelines. 1. The Board of Directors

Change Management Procedures Re: The Peoplesoft Application at Mona

Transcription:

IMO Systems Change Management Procedures for Market Participants Version 1.0 25 January 2007

1 Approvals The undersigned have approved the release of Version 1.0 of the IMO s IT Change Management Procedures for Market Participants Title Signature Date Chief Executive Officer Manager, Market Operations Manager, Market Administration Manager, System Capacity 2 Table of Contents IMO Change Management Procedures for Market Participants... 1 1 Approvals... 2 2 Table of Contents... 2 3 Change History... 3 3.1 About this Document... 3 3.2 What help is available to assist in using the Change Management Process?... 3 4 Change Management... 3 4.1 Objectives and Principles... 3 4.2 Definition of Change... 4 4.3 Market Participant Impact... 4 5 Participant Involvement... 4 5.1 System Changes... 4 5.2 Bug Fixes... 5 6 Change Management Process... 5 6.1 Change Initiation... 5 6.2 Change Assessment and Authorisation... 6 6.3 Release Implementation... 6 6.4 Operations Desk... 7 7 Change Management Working Group... 7 7.1 Role... 7 7.2 Membership... 7 7.3 Administration... 7 7.4 Agenda for Committee Meetings... 7 8 Change Management Workflow... 9

3 Change History Version Date July, 2006 Draft 1.0 M Pember 24/01/2007 Draft Version 3.1 About this Document This document describes the IMO IT Change Management process as it relates to Market Participants. 3.2 What help is available to assist in using the Change Management Process? The IMO Change Manager is available to explain the process in detail and can be contacted on 9254 4307. 4 Change Management Change Management Standards are essential for the controlled and auditable implementation of changes to IMO Systems. This document outlines Market Participant involvement within the IMO s Change Management process. These procedures will be adhered to for all changes to IMO systems that have an impact on Market Participants. 4.1 Objectives and Principles The objectives of the Change Management Process for Market Participants with respect to the IMO Systems environment are to: enforce an evaluation of a proposed change (other than changes resulting from Market Rule Changes) in terms of its benefit, its cost, and risk to the systems, and the implications of the change to both IMO and Participants; to enable all parties to assess the impact and risk to market operations at any time via a clear snapshot of current and planned change activities; provide a defect-free introduction of changes; Ensure Participants are notified of changes to, and development of, IMO IT Systems with sufficient lead time to develop their own systems The principles of Change Management are: All changes to the IMO IT Systems environment must be authorised by the IMO Management The Change Manager coordinates the movement of the change from initiation through assessment and approval to implementation.

4.2 Definition of Change In terms of these IT Change Management Procedures a change is defined as the addition of any item to, the deletion of any item from, or the alteration of any component of the IMO s Market Systems that will impact Market Participants For the purposes of these procedures changes are defined in terms of four categories namely: A change that arises from approved Market Rule changes. A change which relates to the development of a new program or which alters the functional characteristics of an existing program, within the scope of the current Market Rules. A change which is to fix a fault with the operation of an existing program. This type of change is required to make the program conform to the most relevant, approved functional and design specifications. Changes which are of an operational/housekeeping status, typically implemented during normal day-to-day market operations, and these types of changes are managed differently to other changes. 4.3 Market Participant Impact The term Market Participant Impact is used to specifically indicate the impact the change request has on the Wholesale Electricity Market participants. Where relevant, a statement about market impact should be included in the change description. 5 Participant Involvement The IMO is committed to the involvement of participants in changes to, and in the future development of the WEM IT systems. Participant involvement will develop as the market matures. These initial procedures aim to keep participants informed of changes and coordinate the release of changes with the aim of having minimal disruption to the market. There are two distinct processes that will be followed, depending on how the changes are initiated. Changes that are a result of Bug Fixes and changes that are initiated by either participants or the IMO and involve a fundamental change to the way an IMO system operates. The later can be further categorised into changes that do, and changes that don t, arise from approved Market Rule changes. 5.1 System Changes The process will flow as follows: Either the IMO or Participants will raise issues and propose changes directly; or changes will be implemented as a result of Market Rule changes. Submissions other than those arising from Rule changes might be referred to the relevant User Group or the submitters might be asked to demonstrate support from a wider proportion of Participants. IMO Change Working Group will analyse the change request and if the request is approved, it will be placed in a nominated release. Release Plans will be developed and project managed by IMO and will be published. Where a change is approved, all Market Participants will be advised.

IMO will issue change notices to advise Participants of upcoming changes when scheduling allows. 5.2 Bug Fixes Bug fixes will follow the following procedure with the exception of emergency releases. Where an emergency change must be made to an IMO system, Market Participants will be provided with a WEM Change Notice Market Advisory with as much notification as possible, but will not be consulted on a release schedule. Otherwise, the process will flow as follows: The IMO identifies an error in an existing system and requests a fix from the system developer. The developer will release the change to the IMO and the IMO will analyse the release to determine Market Participant impact. Where Market Participants will be impacted, the IMO will advise Participants and propose a market release date. Participants will provide feedback on the release date 6 Change Management Process There are three major steps within the Change Management Process: Change Initiation: - involved with initiating and logging the change request. Change Assessment and Authorisation: - involved with assessing the business and technical issues from both an IMO and Participant point of view which will be done by either the IMO Working Group or the Imo itself. Authorising changes to proceed. Change Implementation: - involved with the planning, scheduling and implementing of changes to IMO s Managed Product List. 6.1 Change Initiation Change requests may be initiated by approved Market Rule Changes, Participants, IMO Service Providers or the IMO and processed according to the following: Rule Changes will be progress to development and implementation automatically. The analysis on the need for the change, release dates and market impact have already been determined as part of the Rule Change process. Participants register a change request through the IMO Operations Desk which results in a Project Issue Report (PIR) being issued. All PIRs are to be reviewed. If the PIR is rejected the person requesting the change is to be notified. IMO Service Providers (eg System Management, DTF, Software Vendors, etc). Changes recommended by the Service Providers to IMO systems must be supported by documentation from the Service Providers recommending the change. IMO initiated change requests are formally registered as a PIR via the IMO s issue management tool.

6.2 Change Assessment and Authorisation All proposals for system changes will be evaluated by the IMO. Where the change has arisen due to a system error/bug fix, the IMO will manage the assessment and development process itself. Participants will be advised of the change when the IMO has received a corrected version of the software from the developer. These changes must be approved by IMO Management. Where the change has been initiated by Participants, or the IMO, and involves a fundamental change to the IMO system operation, the change will be evaluated by the IMO Change Management Working Group. These changes must all be approved by the IMO Management. Changes not arising through the Rule change process will be subject to a full cost benefit analysis. This cost benefit analysis will, in most cases, require the IMO to obtain quotes from its software vendors. At this early stage of market evolution, changes will be limited to those that, in the first instance, have majority support from participants and exhibit clear efficiency gains and improvements to system effectiveness. 6.3 Release Implementation Changes to IMO Market Systems will come in the form of a release where a single release may consist of multiple system changes. The process of implementing releases to IMO Market Systems consists of the following steps: 6.3.1 Change Notification One of the more critical elements of the Change Management Process is keeping all affected parties advised of the status of the change. The Change Manager will be responsible for these notifications. In particular, at release implementation the Change Manager will, as appropriate, arrange for: Notifications to be sent where appropriate to IMO Management and Participants through a WEM Change Notice; e-mail or facsimile copy to be sent to System Management; Copies of relevant specifications to be sent to participants. Notifications will consist of a description of the change an assessment of impact on Participant systems a proposed release date for implementation. 6.3.2 Feedback from Participants Participants will have a period of five working days from notification to provide feedback to the IMO regarding the release and proposed implementation date. Where a participant believes they will not be able to adjust their systems to comply with a change or will not be able to implement all of the changes in a release by the proposed date, they must advise the IMO in writing, citing the reasons they cannot comply with the change notice.

The IMO will review the feedback from Participants and determine if a change is required by the release date. The IMO will provide as much assistance as possible to Participants to enable them to comply with change notices and timeframes. If the IMO feels that a participant s reasons for not implementing a change are unjustified, the Change will proceed as expected so as not to disadvantage all other participants. 6.4 Operations Desk The Market Operations Desk is the initial contact point for most change requests, both from internal and external parties. Requests logged via the Operations Desk will be recorded in the IMO s issue management tool as a Project Issue Report and allocated to a change developer for assessment. 7 Change Management Working Group The Change management working Group consists of IMO and Market Participant representatives. 7.1 Role The Change Management Working Group s focus will cover three general areas: 7.2 Membership Reviewing proposed changes to the IMO s IT Systems, other than system changes resulting from approved Market Rule Changes. This includes evaluation of cost effectiveness and impact on Market Participant systems; The scheduling of system releases that cover all system changes in a manner that best meets participant and IMO requirements and, where applicable, the requirements of the Rule change; and The on-going improvement and refining of this change control procedure. Membership of the Working Group consists of the Market Manager Operations, IMO Change Manager, IMO Change Implementer and representatives from Market Participants and System Management. In order to keep the working group manageable, a place will be made available for only one representative from each market participant. 7.3 Administration The Change Manager: Convenes the Committee meeting Sets the agenda Manages the minutes of the meetings. Issues notices to Working Group members 7.4 Agenda for Committee Meetings 1. Issues arising from the previous meeting

2. Review of changes since the last meeting 3. Change reports 4. Any other issues

8 Change Management Workflow