PROJECT MANAGEMENT FOR STATE CONTRACT MANAGERS

Size: px
Start display at page:

Download "PROJECT MANAGEMENT FOR STATE CONTRACT MANAGERS"

Transcription

1 PROJECT MANAGEMENT FOR STATE CONTRACT MANAGERS by William D. Agee, Jr. WDA and Associates, Inc.

2 Project Management While we all acknowledge that we understand the concepts of project management. However, when asked for a definition we are all at a loss for words. It is not that the task is that big and broad, rather that the task, is so large we are often a loss for exactly where and how to begin. Simply stated project management is the portion of the project or the contract that is acquired or contracted from anotherfirm or that which must be scheduled and managed from either our firm or that must be scheduled and acquired from anotherfirm or from a sister facility. As such, our purpose is to describe the project management process in a meaningful way so as to help the project manager and their team do a better job of coordinating and managing the contract to a successful fruition. Over the last few years, as projects have become more complex and the reach of the projects extend further outside the company to even international vendors, the need for more professionalism in the field is paramount. Today, depending on the size and scope of the project, the amount of the scope contracted out could range from 25% to as high as 90%. As the projects become more complex and integrated the utilization of prime contractors, subcontractors, and teaming arrangements will progressively take a larger share of business. Thus, we must perform the management process well, if we are going to going to deliver value in our projects for the state and agency. Best value in the acquisition process can easily be lost if we do not bring the project in according the contract or project plan. The Teaming Agreement is a commonly used marketing tool whereby a prime contractor and subcontractor agree to combine resources to bid on a major government system procurement. The prime then may submit that bid as an exhibit to its own bid for the government work. In most cases, the prime is bound to use the subcontractorfor the work once the bid is accepted, and the parties will follow the teaming agreement closely when finalizing the subcontract between the parties. Benefits Why enter into a teaming arrangement? A competent, smaller business may obtain access to government business that would otherwise be denied to it by teaming with the larger prime in bidding for government work. The prime contractor, on the other hand, can achieve greater control over its costs and more certainty through a pre-bid teaming agreement a potential subcontractor. 1

3 As such we must manage both work effort and materials both MADE in the agency as well as procured from the outside under a BUY arrangement. Therefore, the equation below can have a simple but resounding foundation: Portion of the contract MADE within the agency + Portions of the contract BOUGHT outside = Project Scope Now think for a moment about the risk and impact we can have should either of the two, MADE or BOUGHT be found wanting per the contract deliverables. What are the risks if the MADE items are not available? What are the risks if the BOUGHT items are in short or unavailable supply? Good effective management and control is the ultimate key to success in either case. So what the current importance in both the state and private circles? 1

4 Take a look at the items identified as essential for the contract or project manager to know about this subject. While the list above is truncated it still highlights the importance to the overall functionality of the professional position. Each of these will be further enhanced and explained in the session but the true value will come as we show how the success of a process can come from the combining of these elements into the deliverables of the contract at the agency or state level. Define Plan the Project Implement the Project Complete the Project Evaluate the Project Schedule Cost Technical 2

5 Defining and Managing 3

6 4

7 Project A temporary undertaking to create a unique product or service. A project has a defined start and end point and specific objectives or deliverables which when completed reach the goal or conclusion of the plan. Program Management Coordinated management of a related series of projects over a period of time, delivered to accomplish the goals of the agency to which the individual projects contribute through their scope. Project Scope All of the work effort required to deliver a projects products or services within the parameters of the contract. ~ Scope Creep Refers to uncontrolled changes or continuous growth in a project's scope. ~ Hope Creep The team members hope they can catch up by the next report period or project team meeting to be back on schedule. ~ Effort Creep Effort creep is doing more work without added scope. ~ Feature Creep Is a tendency for product or project requirements to increase during development. Project Life Cycle A collection of generally sequential project phases who s specific identifying characteristics are determined by the organizations involved in the project. These could include such steps as; conceptual design, initiating, designing, developing, executing, and closeout of the projects deliverables. Remiss from this grouping of steps is the applications associated with operations of the particular product and through life maintenance. 5

8 PMI PMP CAPM Certified Associate in Project Management (CAPM) entry level position PMBOK 6

9 Consider the following as well: A Statement of Work (SOW) An Request for Proposal (RFP) A Risk Model 7

10 Project Manager Critical Skills to Possess? Contract Manager Critical Skills to Possess? 8

11 Draw a Project Life Cycle Trend p7 9

12 1) Initiating A process of formally recognizing that a new project exist or that a previous project should continue to another phase. This is also where the agency grants approval for the organization s resources to be dedicated to the attainment of the task. 2) Planning A phase in the project life cycle where the project plan or the program plan is prepared. In this phase documents are created for use throughout the remainder of the project. 3) Executing This is the deployment stage where the project plans are put in action. Costs are generally higher during the execution phase. 4) Controlling Performance measures are taken and analyzed to determine if a project is on track. Should variations or variances be found corrective action may be taken to get the project activities aligned and brought into sync to the project plan. 5) Closing Activities associated with formal acceptance of a phase, project or program and bringing it to an orderly end. Project success is evaluated and documented. 10

13 a) To initiate a contract b) When planning for a contract c) When executing a contract d) To control contract success e) When closing a contract 11

14 There are nine (9) core competencies that are used to classify each of the five (5) project management process groups. Proper planning is essential to project success and consideration must be made concerning all nine (9) of the project management knowledge areas. The nine competencies known as Project Management Knowledge Areas (Heldman 43) include: Integration Management The process of achieving unity of effort amongst the various parties involved in the accomplishment of a project s goals and objectives. Integration management includes developing a project plan, executing the plan, and managing change. Scope Management The process of managing the boundaries of a project. Specifically, defining what constitutes the deliverables of a project and which deliverables are outside the scope of a project. Scope management involves all of the processes involved with the work on a project, and only the work that is required to complete the project. Time Management Involves estimating the duration of project activities, devising a project schedule, and monitoring and controlling deviations from the schedule. Generally, some form of project management software will be used to assist with time management. 12

15 Despite the obvious there are a number of reasons projects fail. However, the root cause of most failures hubs around the following common and consistent areas: 1) Lack of managers support 2) Lack of organizational commitment 3) Poor communications 13

16 A successful project delivers a result that does what is expected, when it is supposed to be done, for or below the predicted costs, and at or above the expected quality. Success is determined by the project stakeholders or owner. Many times stakeholders have conflicting interests. It is the contract manager s responsibility to understand these conflicts and try to help resolve them. There are five (5) essential activities for ensuring project success. 1) Organizational commitment 2) Communications 3) Team work 4) Project life cycle 5) Project Management 14

17 15

18 It has been stated not only in project management but all areas of business and interpersonal relationships that the primary tool to enhance your chances of success is good, effective communication. 16

19 17

20 Initiating Approval is granted to commit the organization s resources to working on the project phase. Planning Documents are formulated and revised to be used throughout the remainder of the project. Planning is the most critical and intensive part of any project. Executing Project plans are put into action. Costs are generally highest during the execution phase. This also involves the operational phase of the project or program. Controlling Performance measures are taken and analyzed to determine if a project is on track. If variances exist, corrective action may be taken to get project activities aligned with the project plan. Closing Project success is evaluated and documented. Project closing is often the most neglected part of a project. It is important to remember that project closeout is also an essential process group. 18

21 19

22 Page 16 1) List the five project management process groups. 2) Poor communications is a common reason many projects fail? True or False 3) All of the following are phases of a project life cycle except; 20

23 This is the phase where the team recognizes that a new project should exist or that and existing project should be continued. They say that this is one of the hardest part of the project management and contract management cycle. The reason is that if the scope was not well defined by the customer or the project owner the first step is the last step before a project fails. The end well you must begin correctly so this is a very critical juncture for the entire project and agency. 21

24 One of the primary aspect which could be conveyed to the project manager is that we work hard to ensure the success of the project. If you look at the listing above we are trying to start correctly in accordance to the contract and what the defined deliverables are as set forth in the contract. Before we can ensure the success of the project we must also know when and how we are going to complete and what constitutes a satisfactory closure to the project. Exactly how will our customer communicate their complete satisfaction for a project well completed. The deliverables are like applying bricks to the outside of the building. Yes, there is a correct alignment, order and sequence to how we need to apply the bricks to create a completed wall. The same applies to a project and the steps could possible be sequential and paramount to the success of the project. Constraints are throughout a project and must be actively sought and minimized if not eliminated so that the project can go to a successful fruition. Assumption are some of the unknown of a project which over the course of the entire acquisition, contracting and project deliverable will come to sight and later known. These initially might be how the project scope is assembled but should come to a solid form shortly. These can affect the original scope, budget and schedule. 22

25 Needs are one of the most basic requirements of all people and at the same time one of the more critical aspects everyone must satisfy to some regard. Project are generally initiated as a result of various needs which may include some of the listed below. These are; ~ marketing demands ~ business needs and requirements ~ customer requests ~ technology enhancements/changes ~ legal issues and requirements ~ social or human needs 23

26 1. Product description A document that describes the product and clearly indicates the business need(s) that is driving the reason for the product. In contract management the product description is known as a specification or statement of work (SOW). 2. Strategic plan New projects should take into consideration the agency s strategic plan. For example, if one of the agency s goals is to develop five (5) technical support centers then it would make sense that a project initiated in order to furnish the centers would take all five (5) centers into consideration. 3. Project selection criteria Similar to the make or buy analysis in procurement. Project selection involves making decisions regarding which projects to accept or reject based on criteria such as financial data, risk, efficiency, etc. 4. Historical information When evaluating new projects, historical information regarding similar projects can be useful in determining if the new project should be accepted and initiated. Each of these project initiation inputs is processed and applied using tools and techniques to produce the project initiation outputs including the project charter. 24

27 If you carefully look at the goal listed in the right column in the slide above you will see they are both very broad and may be intangible. They are the ultimate end result of an ultimate accomplishment toward which and effort is so directed. // Think for a moment about the last project you were a part of or possibly managed. What was the goal? Was it well defined? Was it too broad to be specifically accomplished leaving alternative ways around? Did the project satisfy the customers needs and meet the objectives of the agency? Would you do it differently if you had been brought in sooner to the process? 25

28 Think about the SMART approach above and what could be do to increase our efficiency using this application on an agency project? ~ specific, ~ measurable, ~ achievable, ~ realistic, ~ time bound. Projects must also be performed within specific time frames and produce realistic and tangible results. The following table highlights the difference between goals and objectives. Goals Broad in scope Highlights general intentions Intangible results Abstract concept. Not measurable Objectives Narrow in scope States precise intention. Tangible result. Concrete concepts Measurable 26

29 One way to begin determining project deliverables is to identify the project initiator. Whose idea was it that led to the creation of your project? Chances are it is not the same person that assigned the project to you. Once you have identified the project initiator, you should interview them to see what they expect as project deliverables. Once you have interviewed and received feedback from the project initiator, it is important to seek feedback from others who will play a role in your project. What are their expectations, opinions, and assumptions about the project and the project s deliverables? Be exhaustive in your search for information Get information from all possible sources/stakeholders. Get information from primary sources/stakeholders whenever possible. Collect written sources. Speak to two (2) or more people from the same area to confirm information. Arrange to have at least one (1) person in addition to yourself present when speaking with people. Write down all information obtained from personal meetings. Plan to meet at least two (2) times with key audiences. Confirm the information you learn in personal meetings with information from written sources whenever possible. * Sidney Portny. Project Management for Dummies 27

30 What could be some good questions you might ask in order to determine project deliverables on your next project. What could be some checklist questions which are mainstays in nearly all project in which you manage the output for a similar customer? 1) 2) 3) 4) 5) 6) 7) 8) 9) 28

31 There are four primary statements of work often employed in attaining project and contract deliverables. These can have a significant impact on the time and output responsibilities of the owner as well as the contractor. Every buyer, contract administrator and project manager should know these well. These are: 1) Functional 2) Performance 3) Design/Technical 4) Level of Effort (LOE) 29

32 30

33 A constraint can be almost anything! Now that s a huge problem. To effectively manage constraints, you must first identify the primary constraint of the project. One way to do this is to communicate with the project sponsor, or in the case of procurement, the end user to determine their priority. For example, if an end user prefers quality over rapid delivery then you know that quality is the primary constraint to which you will manage. Take a look at the primary constraints associated with a project and see if these can occur independently of each other or are they dependent on each other in their occurrence? a) time/schedule b) budget/cost c) quality/technical 31

34 Assumptions actually lend and breathe of credibility to a proposal or a contract despite the fact they are not always valid in fact. If that is the case how then do then lend this credibility to the project and its deliverables from a contractor placing a certain degree of reliance on their basis?

35 Today, the package of information in your contact and project file is validation and documentation. However, in the future that same documentation you control today could be called evidence. What to keep or not?? It s not an easy question to answer but lets defined some critical parameters. 33

36 When you compare the timely, comprehensive measurement of progress against the progress charter you have generated a project status report or update. These status reports provide a description of where the project currently stands; part of the performance reporting process, and those formal reports on input, output, issues, constraints, and actions resulting from a project status meeting. 34

37 As we walk through the simple charter exercise think about the sections you feel would have beneficial had you had a charter to work with on your last major project. Also, think about ways we could enhance this to be a better document we can style as a checklist going forward. 35

38 36

39 A project planning phase involved developing the best tactical approach for accomplishing the project or programs objectives. Some of the activities will include developing and maintaining the project plan, identifying the project objectives, activities required to complete the project and ensuring the resources and quantities required to carry out the specified activities. 37

40 38

41 39

42 Knowledge Areas Integration Management Scope Management Time Management Cost Management Quality Management Human Resource Management Communication Management Risk Management Procurement Management 40 Processes

43 Scope Statement Scope Management Plan Work Breakdown Structure Communications Management Plan Resource Requirements Document Staffing Requirements List Organizational Chart Project Team Directory Activity List Project Network Diagram Cost Estimates Cost Management Plan Quality Management Plan List of Prioritized Risks Risk Management Plan Procurement Documents Statement of Work Evaluation Criteria Procurement Management Plan Schedule Management Plan Cost Baseline Project Plan 41

44 Project scope management is the application of all processes that ensures the project includes all the work required, and only the work required to successfully complete the project. Other segments of the project scope will include the initiation, scope planning, scope definition, scope verification and (scope) configuration management and control. 42

45 Project Initiation Project Planning Project Execution Project Controlling Project Closing 43

46 A well defined communications conduit is said to be a 360 degree design divided into three parts. What would you feel a very effective communication conduit would look like? The three sections of the conduit are top, middle and bottom. The first area employed is the middle with the contract manager and the project manager interfacing with their counterparts. This is then followed by the lower section which is the direct and adjunct team members of the project. The top or upper management tier is for status, communication on results and counsel. 44

47 Resource Requirements Document A detailed description of the kinds of resources and the quantity needed for the project. Staffing Requirements Document Identifies the kinds of skills required, the individuals or groups who might posses the named skills and contribute to the project, and the estimated length of time each person will be needed for the project. Roles and Responsibility Assignment Determines the project roles and responsibilities for the project manager and the project team members and is usually represented by a Responsibility Assignment Matrix (RAM). Staffing Management Plan Documents how and when people are introduced to and released from the project and is usually represented by a resource histogram. Organizational Chart A chart, similar to a WBS, which shows the reporting relationships of project members. Supporting Detail A document that further describes the impact to organizational units due to work requests. Project Team Directory A document listing the names of all project team members. Statement of Work A document that contains the details of the procurement item in clear, concise terms. 45

48 Procurement Management Plan Details how the procurement process will be managed. 45

49 The scariest commodity in the world and the only commodity which can only be procured with a common unit of value. Time management is the process of using tools and techniques to manage time. Estimating the duration of project activities involves identifying the activities and sequencing them in the correct order. If you use project management software to help manage your projects then project activity times will most likely be estimated using the precedence diagramming method (PDM), also known as activity on node (AON). Precedence diagrams connect activities with arrows that show dependencies between the activities. A project management chart is a tool that is often used to manage either a complete project or WBS segments individually as separate sub projects. The purpose of a project management chart is to estimate the duration of project processes and activities. 46

50 A Gantt chart is a common project management tool used to manage projects in relation to units of time. Some of the common names include MS Project, Fast Track, and Primavera. It consists of a vertical individual task list and a horizontal timeline or calendar expressed in a unit of time such as hours, days, weeks, etc.. It can also keep track of work assignments by individuals, resources other than personnel and costs. The PERT charts display tasks, duration, and dependency information. Each chart starts with a preliminary point from which the first task(s) begins. Each task is represented by a line upon which is generally written a task identifier (i.e. name), task duration, number of people assigned to the task, and in some cases the initials of each assigned person. (see example on board) CPM charts are similar to PERT charts. They are used for complex, one time projects that generally include high costs. CPM charts track interrelated and interdependent activities allowing the project or contract manager to pinpoint areas (critical paths) that will have the most impact on the completion of a project. Tasks that fall on the critical path should be indicated by a special designation or symbol. Some of the ways to do this is to create a double line or colored line for critical paths. What these all have in common as a project management tracking tool is the ability to estimate the duration of the project processes and activities. 47

51 How can resource leveling be of benefit in effectively managing a project in regards to the primary constraints associated effective project management?

52 Project management often employs three types of estimating techniques to affect control over project costing. These include: 1. Analogous Estimating A top down estimating technique that involves using historical information from similar projects to determine project costs. Analogous estimating is a form of expert judgment and is not the most accurate way to determine project costs. 2. Parametric Modeling A mathematical model that uses parameters, or project characteristics, to forecast project costs. If multiple parameters exist in a project, then it is important to account for each parameter separately and incorporate those into the total project cost. Parametric modeling is most successful when used in conjunction with analogous estimating. 3. Bottom up Estimating A cost estimating technique used to determine the costs of every input and output associated with a project and adding the estimates together to determine the ultimate project cost. Pricing is a vendor function and is a strategic decision made by management that includes the costs associated with producing a product or providing a service plus a profit margin. It is important for you to understand general components that make up their price. 49

53 A standard is a basis of comparison employing a criterion bases application. For example; UL approved on wiring. Assessing and employing quality is not difficult as there are over fifty different standards organizations. Some of the resources include: International Organization for Standardization (ISO) ( American National Standards Institute (ANSI) ( ASTM International ( NSF International ( National Council for Prescription Drug Program (NCPDP) ( and the American Society for Quality (ASQ) ( You can also find a listing of federal r4egulations on the Internet at There are three costs associated with quality; 1) prevention costs, 2) appraisal costs, and 3) failure costs. 50

54 There are several ways to identify risks associated with a project. These include:. Brainstorming. Interviewing. SWOT. Delphi Technique. Nominal Group Technique 51

55 In the space below create a risk matrix for a project and with your group mitigate the risk for your project/ High Medium Low

56 It has been stated that how you manage risk is up to you, but it will be determined in part by its potential for damage! What are some of the ways we utilize these risk mitigation techniques almost everyday at work and home? 53

57 Answer the following questions with your group or table. What are some inherent risks you can identify with this portion of the project? What control risks will you need to consider? What are some assumptions that you have already made from reading about the project? What major constraint has been identified? What risk management method(s) would you use if you were in charge of the project? 54

58 Procurement planning is the process of determining what goods or services you will purchase externally. This determination is often made by conducting a make or buy or make vs. do analysis where direct and indirect costs are analyzed to determine whether it is more cost effective to make or buy the products and/or services needed for a project. If the buyer, or team, elects to procure the goods or services then the procurement process as shown abo0ve will need to be implemented. The two other state agencies which serve in an advisory role to the Contract Advisory Team (CAT) in the state are the Legislative Budget Board (LBB) and the State Auditor s Office (SAO). Why is it stated that the end of the SoT Procurement Cycle is actually the beginning? 55

59 The project plan combines all outputs from the project planning processes to create a complete project document that is used to track project performance. It is an assortment of documents that constitutes what the project is, what it will deliver, and how all the processes will be managed. When information documented in the project plan changes, the project plan should be updated accordingly. Caution should be exercised when people try to utilize an open order or unfinished contract to morph or change the scope of the approved and acquired original acquisition. 56

60 57

61 This is a phase in a general project life cycle where the product or service to be delivered by the project or program is either produced or made. It has been referred to a the execution phase or the implementation phase of a project. 58

62 59

63 It is important to understand the organizational policies for information systems, human resources, purchasing, fiscal, and other departments that may play a role during your project in order to keep the project on track and avoid schedule delays. Considering the listing of all the other areas which could contribute to possible delays in a project what are some of the specific areas each could be cited for? 1) 2) 3) 4) 5) 60

64 61

65 Define a Team. Team members should be selected based on their knowledge, skills, abilities, attitudes, and leadership potential. You want to choose team members with experience and expertise regarding the scope of your project. Team members should be able to cooperate and adapt in a changing environment. 62

66 Forming Storming Norming Performing 63

67 Motivation is the reason(s) behind a person's actions which causes them to act in a particular way. In business, motivation occurs when people perceive a clear business reason for pursuing knowledge. Motivation can be extrinsic where people are motivated by material things like bonuses, the use of a company car, training opportunities, and administrative leave, or intrinsic where people are motivated from within. Several motivational theoriesa) Maslow s Hierarchy of Needs b) Expectancy Theory c) Achievement Motivation Theory d) McGregor s XY Theory Recognition and reward should be directly linked to project performance. Team members should be recognized and offered a reward for going above and beyond the call of duty during a project. However, it is important to consider individual preferences and cultural differences when recognizing a team member 64

68 65

69 66

70 67

71 One of the primary reports a project manager can generate through this process is either a GAPs analysis or a variance report. Both of these reports shows the objective compared to the actual performance and the open space or the gap is the variance to the plan. However, it is important to remember than all variances are not necessarily bad. For example, actual cost versus planned or budgeted could show a lower cost saving the agency money on the project. It is through this process that we can ensure that the planned event do occur as slated and that the unplanned events do not occur at all. What are the tools you currently employ for this at your agency today? 68

72 69

73 70

74 71

75 Earned Value Graph I l 72

76 Performance Criteria Metrics Schedule Scope of Work Cost Quality End User Satisfaction Procurement lead time Percent on time delivery Percent milestones completed on time Schedule Variance Number of contract changes Number of configuration changes Budgeted Cost of Work Scheduled Budgeted Cost of Work Performed Actual Cost of Work Performed Cost Variance Mean Time Between Failures Mean Time to Repair Number of Product Returns Number of Product Failures Number of Customer Service Complaints Repeat Business Letters of Appreciation 73

77 Corrective action alone does not signify a major problem for the project manager. Actually, to have a contractor or vendor who can adjust and improve their situation is a major improvement. 74

78 75

79 There are a variety of quality control techniques a project manager could employ. These include; Inspection involves physically looking at, measuring, or testing results to determine if they conform to requirements and quality standards. The purpose of inspection is to prevent errors in a product or process from reaching the customer. Control charts measure the results of processes over time and display the results in graph form. Control charts are generally used to measure products that must meet specific specifications and fall within certain variances to be considered in control. Pareto Diagrams are a tool for identifying the most significant problems in order to help prioritize improvements. They are displayed as bar charts that plot failure modes from left to right largest cause of failure to least cause of failure. Statistical sampling involves taking a sample number of parts from the whole population and examining them to determine if they fall within the variances outlined by the quality control plan. Flowcharting and trend analysis were discussed earlier in this workbook. The results of quality audits are quality improvements. 76

80 All change requests should be submitted in writing so that there is a paper trail to help you manage project changes. It should also well define the point person for the tendering of a change, the process we have established and who has the final authority to approve. NO CIRCUMVENTING THE CHAIN!! One important aspect of change is that it does not always have to be accepted. If you allowed changes every time they were requested, the project may never be completed. It is important that you review the reasons for the change and determine if change is justifiable. It is wise to employ a change control log as part of the project managers documentation package. This can be a quick validation of in or out of scope. When changes are submitted to the CM/PM they should initially be reviewed to see if they are already apart of the original scope. If out of scope or a owner generated change, for which the contractor should be compensated, this should be reviewed against the documented WBS from the original proposal. A valid change control system should establish the procedures for any and all changes, create a change control log for tracking throughout the project all contractor or owner generated changes and establish the levels of authority for any such changes. 77

81 78

82 Project closeout is usually the processes which provide for project acceptance by the projects owner or PM, completion of the various project records, final revision and issue of he document to reflect the actual deliverable or as built condition, and retention of essential project documentation. This is all inclusive to validate that the work effort or the services provided meet the standards of the project and a final payment to the contractor should be issued. 79

83 80

84 Projects generally come to a close as a result of the following four (4) events: Project Addition Projects that evolve into ongoing operations and surpass the criteria of being unique and temporary with a definite beginning and ending date. Project Starvation Projects whose funding resources are eliminated. Project Integration Projects whose personnel resources are reassigned or eliminated. Project Extinction Projects that are successfully completed and accepted by all stakeholders. There are two (2) processes that occur during project closeout: a) contract closure, and b) administrative closure. 81

85 82

86 83

87 84

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Input, Output and Tools of all Processes

Input, Output and Tools of all Processes 1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /

More information

Making project management indispensable for business results. Project Management 101

Making project management indispensable for business results. Project Management 101 Making project management indispensable for business results. Project Management 101 Donald E. Moore, MBA, PMP, President of PMI NB Kelly Barter, Chapter Manager of PMI NB AGM April 28, 2011 Topics of

More information

Quick Reference Guide Interactive PDF Project Management Processes for a Project

Quick Reference Guide Interactive PDF Project Management Processes for a Project Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process

More information

The 10 Knowledge Areas & ITTOs

The 10 Knowledge Areas & ITTOs This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading

More information

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)

Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: Support@Nutek-us.com

More information

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs

Knowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing

More information

TEXAS BUILDING AND PROCUREMENT COMMISSION MISSION AND PHILOSOPHY

TEXAS BUILDING AND PROCUREMENT COMMISSION MISSION AND PHILOSOPHY TEXAS BUILDING AND PROCUREMENT COMMISSION MISSION AND PHILOSOPHY Mission Employ cost-effective, efficient and innovative methods to provide quality goods, services and facilities to meet the demands of

More information

Certification Exam Objectives: PK0-003

Certification Exam Objectives: PK0-003 Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

Project Integration Management

Project Integration Management Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform

More information

Certificate In Project Management (CIPM)

Certificate In Project Management (CIPM) Conceptualize Plan Plan & Deliver Organize Implement Control Change if Required Integrate Deliver & Closeout Knowledge Leverage Certificate In Project Management (CIPM) Course Overview The Certificate

More information

www.aryanengineering.com Email: info@aryanengineering.com

www.aryanengineering.com Email: info@aryanengineering.com What is PMP Certification exam? www.aryanengineering.com PMP stands for Project Management Professional certification exam. PMP, is one of the most respected and globally recognized certification is offered

More information

Managing IT Projects. Chapter 2 The PMI Framework

Managing IT Projects. Chapter 2 The PMI Framework Managing IT Projects Chapter 2 The PMI Framework The PMI Framework The Project Management Institute,USA is an internationally acclaimed organization Devoted to Creation & sharing of knowledge in the area

More information

PMP Examination Tasks Puzzle game

PMP Examination Tasks Puzzle game PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in

More information

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP

PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP TSE015 PROJECT MANAGEMENT PROFESSIONAL CERTIFIED ASSOCIATE IN PROJECT MANAGEMENT (PMP & CAPM) EXAM PREPARATION WORKSHOP Course Outline I. Introduction and Course Objectives A. About PMI B. PMP and CAPM

More information

Time Management. Herb Pollard III

Time Management. Herb Pollard III Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas

More information

Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK

Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK Interpreting the Management Process in IEEE/EIA 12207 with the Help of PMBOK Lewis Gray, Ph.D., PMP Abelia Fairfax, Virginia USA www.abelia.com Copyright 2002 by Abelia Corporation. All rights reserved

More information

PMP Project Management Professional Study Guide, Third Edition

PMP Project Management Professional Study Guide, Third Edition PMP Project Management Professional Study Guide, Third Edition Joseph Phillips McGraw-Hill is an independent entity from the Project Management Institute, Inc. and is not affiliated with the Project Management

More information

Project Management Certificate (IT Professionals)

Project Management Certificate (IT Professionals) Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.

More information

Certification Preparation Course LATVIKON (R.E.P.)Centre

Certification Preparation Course LATVIKON (R.E.P.)Centre PMP Certification Preparation Course LATVIKON (R.E.P.)Centre ABOUT THIS COURSE Your ability as a project manager to demonstrate best practices in Project Management both on the job and through professional

More information

PBL: Project Management. Competency: Project Definition

PBL: Project Management. Competency: Project Definition Competency: Project Definition 1. Define project management and the context of modern project management. 2. Describe how to manage projects throughout the five major process groups. 3. Define the characteristics

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet

Project Management Institute (PMBOK 2000) PMP Preparation Worksheet Project Integration Management Processes required to ensure that the various elements of the project are properly coordinated to meet / exceed stakeholder expectations. Project Plan Development Other ning

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

The contact workshop is a mix of instructor lead and self paced learning, designed as per the PMBOK Fifth edition of Project Management Institute.

The contact workshop is a mix of instructor lead and self paced learning, designed as per the PMBOK Fifth edition of Project Management Institute. PMP Bootcamp workshop Duration: 4 Days - 35 PDUs GRT Consulting LLP brings you their eminent PMP Boot camp workshop to address the requirements of delegates preparing for the Project Professional (PMP

More information

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Introduction to the ITS Project Management Methodology

Introduction to the ITS Project Management Methodology Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer

More information

Project Time Management

Project Time Management Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

More information

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500

Comparing PMBOK Guide 4 th Edition, PMBOK Guide 5 th Edition and ISO 21500 Project Training Company Comparing PMBOK Guide 4 th Edition, Edition and STS Sauter Training & Simulation S.A. Avenue de la Gare 10 1003 Lausanne Switzerland Web: www.sts.ch E-mail: office@sts.ch Phone:

More information

Project Management Professional (PMP) Boot Camp

Project Management Professional (PMP) Boot Camp Project Management Professional (PMP) Boot Camp According to the Project Management Institute, the world's leading association for the project management profession: "PMP Certification is the profession's

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

A Comparison of PMI s PMBOK Guide Versions 4 & 3

A Comparison of PMI s PMBOK Guide Versions 4 & 3 PM WORLD TODAY FEATURED PAPER MAY 2009 A Comparison of PMI s PMBOK Guide Versions 4 & 3 By Germán Bernate The Project Management Institute PMI announced on December 31, 2008 the availability of PMBOK Version

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and their

More information

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION

PMP SAMPLE QUESTIONS BASED ON PMBOK 5TH EDITION PMP SAMPLE QUESTIONS http://www.tutorialspoint.com/pmp-exams/pmp_sample_questions_set2.htm Copyright tutorialspoint.com BASED ON PMBOK 5TH EDITION Here are 200 more objective type sample questions and

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

PROJECT MANAGEMENT PLAN CHECKLIST

PROJECT MANAGEMENT PLAN CHECKLIST PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,

More information

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited

PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,

More information

IMCPM04 Project Scheduling and Cost Control. Course Outline

IMCPM04 Project Scheduling and Cost Control. Course Outline IMCPM04 Project Scheduling and Cost Control Course Outline January 2012 Project Scheduling and Cost Control Course Aim Project Scheduling and Cost Control is a five-day (5 day) course which provides participants

More information

Project Management Professional (PMP) Examination Content Outline

Project Management Professional (PMP) Examination Content Outline Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP ) Examination Content Outline Revised August 2011 Published by: Project

More information

Project Management Professional (PMP) Examination Content Outline

Project Management Professional (PMP) Examination Content Outline Project Management Professional (PMP) Examination Content Outline Project Management Institute Project Management Professional (PMP) Examination Content Outline June 2015 Published by: Project Management

More information

Project Management Process. Prepared by Jay Knape

Project Management Process. Prepared by Jay Knape Project Management Process Prepared by Jay Knape PMI Project Project is... temporary endeavor undertaken to produce a unique products, service or result. UITS Project Definition For Columbus State University

More information

Chapter 2: Project Time Management

Chapter 2: Project Time Management Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.

More information

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB51407 Diploma of Project Management First published 2010 ISBN 978-1-74205-511-4 Department of Training and

More information

Project Time Management

Project Time Management Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

Project Management Standards: A Review of Certifications/Certificates

Project Management Standards: A Review of Certifications/Certificates Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in

More information

The Plan s Journey From Scope to WBS to Schedule

The Plan s Journey From Scope to WBS to Schedule The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)

More information

Project success depends on

Project success depends on Project success depends on many factors both within and outside the control of the project team. One of the aspects that is within the control of the project team is the planning. Almost everything we

More information

PROJECT PROCUREMENT MANAGEMENT

PROJECT PROCUREMENT MANAGEMENT 12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,

More information

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects

Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The ning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.

Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52. Program Title: Advanced Project Management Knowledge, Skills & Software Program ID: #1039168 Program Cost: $4,690 Duration: 52.5 hours Program Description The Advance Project Management Knowledge, Skills

More information

The purpose of this course is to provide practical assistance for defining and managing project scope.

The purpose of this course is to provide practical assistance for defining and managing project scope. Scope Definition and Scope Management Purpose - To provide practical assistance for defining and managing project scope. This course will focus on tips for creating a scope statement rather than a step-by-step

More information

Chapter 6. (PMBOK Guide)

Chapter 6. (PMBOK Guide) Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: marajabi@ut.ac.irac ir Homepage:

More information

PROJECT AUDIT METHODOLOGY

PROJECT AUDIT METHODOLOGY PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit

More information

PHASE 8: IMPLEMENTATION PHASE

PHASE 8: IMPLEMENTATION PHASE PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the

More information

Partnering for Project Success: Project Manager and Business Analyst Collaboration

Partnering for Project Success: Project Manager and Business Analyst Collaboration Partnering for Project Success: Project Manager and Business Analyst Collaboration By Barbara Carkenord, CBAP, Chris Cartwright, PMP, Robin Grace, CBAP, Larry Goldsmith, PMP, Elizabeth Larson, PMP, CBAP,

More information

Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved

Description of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program

More information

STARTING A PROJECT. Sergey V. Nesterov MD, PhD, PMP

STARTING A PROJECT. Sergey V. Nesterov MD, PhD, PMP STARTING A PROJECT Sergey V. Nesterov MD, PhD, PMP QUESTIONS to ask at the start 1. What is the situation? 2. What do you need to do? 3. Why do you need to do it? 4. What will you do? 5. How will you do

More information

Project Knowledge Areas

Project Knowledge Areas From Houston S: The Project Manager s Guide to Health Information Technology Implementation. Chicago: HIMSS; 2011; pp 27 39. This book is available on the HIMSS online bookstore at www. himss.org/store.

More information

PHASE 3: PLANNING PHASE

PHASE 3: PLANNING PHASE PHASE 3: PLANNING PHASE The Planning Phase focuses principally on required project planning work. Proper comprehensive project planning is essential to a successful IT project, and incomplete project planning

More information

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided. Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60

More information

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021

- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 - ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and

More information

Chapter 6: Project Time Management

Chapter 6: Project Time Management CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD jwoo5@calstatela.edu California State University, LA Computer and Information System Department Chapter 6: Project Time Management

More information

Project Management. Systems Analysis and Design, 8e Kendall & Kendall

Project Management. Systems Analysis and Design, 8e Kendall & Kendall Project Management Systems Analysis and Design, 8e Kendall & Kendall Learning Objectives Understand how projects are initiated and selected, define a business problem, and determine the feasibility of

More information

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072

Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define

More information

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management

Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB41507 Certificate IV in Project Management Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB41507 Certificate IV in Project Management First published 2010 ISBN 978-1-74205-510-7 Department of Training

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT 6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity

More information

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES

ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES 1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through

More information

SOFTWARE PROJECT MANAGEMENT

SOFTWARE PROJECT MANAGEMENT SOFTWARE PROJECT MANAGEMENT http://www.tutorialspoint.com/software_engineering/software_project_management.htm Copyright tutorialspoint.com The job pattern of an IT company engaged in software development

More information

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False

Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,

More information

Project Scope Management in PMBOK made easy

Project Scope Management in PMBOK made easy By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating

More information

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

PMP 2013 Exam Prep. Course Overview

PMP 2013 Exam Prep. Course Overview PMP 2013 Exam Prep Course Overview This course has been designed to prepare participants to take the Project Management Institute's Project Management Professional (PMP) Exam, 2013 edition and is based

More information

BSB41513 Certificate IV in Project Management Practice

BSB41513 Certificate IV in Project Management Practice RPL Assessment Tool Kit AUSTRALIAN SALESMASTERS TRAINING CO RPL Assessment Tool Kit BSB41513 Certificate IV in Project Management Practice Page 1 of 126 BSB415137 Certificate IV in Project Management Practice

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT 11 PROJECT RISK MANAGEMENT Project Risk Management includes the processes concerned with identifying, analyzing, and responding to project risk. It includes maximizing the results of positive events and

More information

output: communications management plan

output: communications management plan Q1. (50 MARKS) A. List the nine PMBOK knowledge areas and give a one sentence description of the purpose of each knowledge area along with at least one output (document etc.) and its purpose. 1.Project

More information

A Glossary of Project Management Terms

A Glossary of Project Management Terms OpenStax-CNX module: m31434 1 A Glossary of Project Management Terms Merrie Barron, PMP, CSM Andrew R. Barron This work is produced by OpenStax-CNX and licensed under the Creative Commons Attribution License

More information

IT Project Management Methodology. Project Scope Management Support Guide

IT Project Management Methodology. Project Scope Management Support Guide NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Scope Management Support Guide Version 0.3 Version Date Author Change Description 0.1 23 rd Mar, 2013 Gerald

More information

NFSA Project Management Guidelines

NFSA Project Management Guidelines NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART C CERTIFIED PRACTISING PROJECT MANAGER (CPPM) February 2010 Version 1.12 Copyright: Australian Institute of Project Management Document

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

State of Michigan (SOM) August 2013. Department of Technology, Management & Budget

State of Michigan (SOM) August 2013. Department of Technology, Management & Budget State of Michigan (SOM) PROJECT MANAGEMENT KEY TERMS, DEFINITIONS AND ACRONYMS August 2013 Department of Technology, Management & Budget Table of Contents Table of Contents Key Terms, Definitions, and

More information

Lesson 10: IT Project and Program Management

Lesson 10: IT Project and Program Management Lesson 10: IT Project and Program Management Lesson 10 Objectives Identify resources for technical data Identify project management fundamentals Identify project management skills Identify the five project

More information

Module 1 Diploma of Project Management

Module 1 Diploma of Project Management Module 1 Diploma of Project Management Project Management Fundamentals in association with This two day course takes participants through all aspects of Project Management and provides in depth examination

More information

Module 7 Human Resources Management PMP Exam Questions

Module 7 Human Resources Management PMP Exam Questions Module 7 Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Question 1 You and your manager are discussing

More information

Project Management for IT/IS Projects

Project Management for IT/IS Projects Project Management for IT/IS Projects The Course Design, Outline and Behavior Objectives: Project Management for IT/IS Projects is consistent with the PMI Project Management Body of Knowledge, PMBOK. To

More information

MIS 460 Project Management

MIS 460 Project Management Ursuline College Accelerated Program CRITICAL INFORMATION! DO NOT SKIP THIS LINK BELOW... BEFORE PROCEEDING TO READ THE UCAP MODULE, YOU ARE EXPECTED TO READ AND ADHERE TO ALL UCAP POLICY INFORMATION CONTAINED

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

Technical Project Management Engineers Week 2009

Technical Project Management Engineers Week 2009 Technical Project Management Engineers Week 2009 Presented by: Denise Jackson, PhD, PE Associate Professor University of Tennessee Space Institute djackson@utsi.edu 1 Technical Project Management: Outline

More information

Chapter 01. PMP work book answers V3 2012. Exercise 01: Question Answer Question Answer

Chapter 01. PMP work book answers V3 2012. Exercise 01: Question Answer Question Answer Chapter 01 Exercise 01: Question Answer Question Answer i. Procurement Management KA ii. Integration Management KA iii. Cost Management KA iv. HR Management KA v. Risk Management KA vi. Quality Management

More information

Project Management Concepts and Strategies

Project Management Concepts and Strategies Project Management Concepts and Strategies Contact Hours: 24 Course Description This series provides a detailed examination of project management concepts and strategies. It discusses the seven components

More information