A SYSTEMATIC APPROACH FOR MONITORING AND EVALUATING THE CONSTRUCTION PROJECT PROGRESS
|
|
|
- Logan Conley
- 10 years ago
- Views:
Transcription
1 A SYSTEMATIC APPROACH FOR MONITORING AND EVALUATING THE CONSTRUCTION PROJECT PROGRESS Zubair Ahmed Memon, Muhd. Zaimi Abd. Majid and Mushairry Mustaffar Construction Technology and Management Center (CTMC), Faculty of Civil Engineering, Universiti Teknologi Malaysia, UTM Skudai, Johor and ABSTRACT A persistent problem in construction is to document changes which occur in the field and to prepare the as-built schedule. In current practice, deviations from planned performance can only be reported after significant time has elapsed and manual monitoring of the construction activities are costly and error prone. Availability of advanced portable computing, multimedia and wireless communication allows, even encourages fundamental changes in many jobsite processes. However a recent investigation indicated that there is a lack of systematic and automated evaluation and monitoring in construction projects. The aim of this study is to identify techniques that can be used in the construction industry for monitoring and evaluating the physical progress, and also to establish how current computer technology can be utilised for monitoring the actual physical progress at the construction site. This study discusses the results of questionnaire survey conducted within Malaysian Construction Industry and suggests a prototype system, namely Digitalising Construction Monitoring (DCM). DCM prototype system integrates the information from construction drawings, digital images of construction site progress and planned schedule of work. Using emerging technologies and information system the DCM re-engineer the traditional practice for monitoring the project progress. This system can automatically interpret CAD drawings of buildings and extract data on its structural components and store in database. It can also extract the engineering information from digital images and when these two databases are simulated the percentage of progress can be calculated and viewed in Microsoft Project automatically. The application of DCM system for monitoring the project progress enables project management teams to better track and controls the productivity and quality of construction projects. The use of the DCM can help resident engineer, construction manager and site engineer in monitoring and evaluating project performance. This model will improve decision-making process and provides better mechanism for advanced project management. Keywords: AutoCAD, Construction Management, Database, Digital Monitoring Photogrammetry 1. INTRODUCTION Project progress monitoring and control is one of the most important tasks of construction project management. Every teammember needs to know, in a timely and accurate manner, how is the project progressing, where they are currently in comparison to the initially set plans, whether deadlines are met, budgets are safely measured and followed. It is mainly the responsibility of the general contractor to update the A r c h i t e c t / E n g i n e e, rwho, in turn, updates the owner. Figure 1 shows the traditional project progress monitoring process and the progress reports are updated on a periodic printed form; issued in most of the cases on a monthly basis. These reports discuss the current project progress with planned schedule of work in terms of time and budget to forecast the project finish date. These reports also mentioned the constructability problems, quality issues including test results, contract changes including modification in design and increase/decrease in quantities, pending issues from progress meetings. The photos are attached to these reports to show the achievement of milestones. This traditional construction management system provides a project manager with the various reports such as progress control, earned value management and resource management. Project manager spend most of his time for developing and updating of these reports instead of execution and to take in-time decision to finish the work within prescribed time scale. The successful project completion requires the concerted e ffort of the project team to carry out the various project activities, and it is the project manager who at the centre of the project network is responsible for orchestrating the whole construction process. The project manager has to maintain the project network and monitor against slippages in cost, time and quality for the duration of project. In achieving this, the project manager relies heavily on a reliable monitoring system that can provide timely signalling of project problems, whether they are real or potential. In practice little has been done to address the problem of project progress monitoring and control. The most of the research efforts in the field of project control still focus on the development of cost control models [1]. This paper describes the current status of an ongoing research project which aims to develop an easy to use tool or expert system to monitor and control the construction progress at the construction stage. A different class of computer application system are discussed in this paper, which will be used for monitoring and updating the project progress by incorporating engineering information from digital images and AutoCAD drawings. To achieve this object a prototype system was proposed namely called Digitalising Construction Monitoring (DCM) system. This is authors believe that this system can assist project manager to develop the project progress reports with speed, within time 26
2 A SYSTEMATIC APPROACH FOR MONITORING AND EVALUATING THE CONSTRUCTION PROJECT PROGRESS Figure 1: Flowchart for traditional project progress monitoring practice 27
3 ZUBAIR AHMED MEMON, et al. and accurate to pursue for successful completion of construction work according to clients demands. 2. BACKGROUND OF STUDY This section provides a brief overview of studies reported in the literature relating to digitalising the construction monitoring for construction project. A number of commercial software packages that relate to this topic are also listed. The sources outlined here provide the basis of the analysis of project monitoring and the system development presented in the following sections. The existing computer-based construction tools seem to provide a wide of functions to manage design and construction information. The researchers attempted and developed the systems such as; ESSCAD by Wang [2], PPMS by Cheung [3], VIRCON by Dawood [4], PHOTO - N E T II by Abeid [5], CADCIMS by Stumpf [6], OSCONCAD by Maria [7], DIPA D by Streilein [8] and ADC by Sacks [9]. From the intensive review, researchers developed the integration model for project progress and the ideas for developing automated real-time monitoring systems are rapidly growing with the advancement in the information technology. However, the information integration has not been ideal in current practice. From the literature it has been cited that very few have given concern to develop the actual physical progress bar chart by capturing the information from digital images. This study uses the close range photogrammetry to develop the 3D Model from digital images with the help of PhotoModeler pro version software, which is requirement for accurate photogrammetry. This system enables the project manager to simulate the traditional practices and A r t i f i c i a l Intelligence to evaluate the physical progress of construction activities and develop the progress bar chart in Microsoft project. Most construction project employ scheduling methods to monitor and control the progress of work and develop progress reports, which involves the recording of construction achievements for detection of deviations from actual plan and for forecasting project performance. The primary control system used by project managers to obviate or mitigate time-based claims in construction industry is construction schedule [10]. T h e current practice of project control is entirely dependent on cost, schedule, and quality reports and personnel performance reviews [ 11]. Monitoring project time is one of the many challenges for the project manager. Time monitoring seeks to assess how well the project adheres to the planned schedule over a period of time. There are a variety of ways in which a construction schedule can be presented. The more common types of construction schedule include: Gantt chart, activity on the arrow, precedence network and line of balance. Bar charts or Gantt charts are a powerful communication tool and an extremely useful, visual and graphical medium in construction scheduling. A persistent problem in construction industry is to develop the as-built physical progress schedule of construction scene. The asbuilt project information presents how construction is actually performed. The research reported in this paper focuses on the issue related to developing the digitalised actual physical progress report during the construction stage. As-built schedules are costly to prepare because of the amount of research necessary to determine the actual dates and considerable judgment is also required. Since detailed records are not always available and even if they are, work on the site does not necessary confirm the planned schedule. This state of affairs leads authors to propose the prototype system for developing as-built schedule a u t o m a t i c a l l y. In addition the scenario discussed in above paragraph, a questionnaire survey was conducted within Malaysian Construction Industry. Zhang [12] stated that questionnaire survey is an effective, convenient, economical investigation tool for obtaining data and sampling the opinions of individuals in spatially diverse locations. Al-harthy [13] listed that the questionnaire survey usually provides large amount of data in a short time with relatively ease of preparation, distribution and tabulation of answers and responses can be given easily and q u i c k l y. Therefore, a close-end questionnaire was designed for this study; to identify the current practice. The result of survey supports the authors to propose the system, as MCI utilising the traditional practice for monitoring and progress reporting. T h e following sections discuss the result of questionnaire survey and propose a framework model to overcome the limitation of current practice in the MCI. 3. QUESTIONNAIRE SURVEY WITHIN MALAYSIAN CONSTRUCTION INDUSTRY The questionnaire survey form was designed to verify the existing methods and processes which are related with the project progress monitoring. It is important at early stage to decide for analysing method before developing any system of data collection. So, Statistical Analysis method has been considered to analysis the collected survey form. The data was collected by using measurement or likert scale method. Five scale rating was used to determine the severity of influence on project progress monitoring techniques by client, consultant and contractor. Al-Hammad [14], Abd.Majid [15] and Alharthy [13] used and explained the Average Index Method to analysis data in the ordinal or ranking scale. This study also uses Average Index Method to analysis data of survey and explained as follows: Where, a i = Constant expressing the weight given to i, X i = variable expressing the frequency of the response for; i = 1, 2, 3, 4, 5 and illustrated as follows: X 1 = frequency of the very rare response and corresponding to a 1 = 1; X 2 = frequency of the rare response and corresponding to a 2 = 2; X 3 = frequency of the slightly frequently response and corresponding to a 3 = 3; X 4 = frequency of the frequently response and corresponding to a 3 = 4; and X 5 = frequency of the very frequently response and corresponding to a 5 = 5. Table 1 shows the result of questionnaire survey which were conducted within Malaysian Construction Industry (MCI). The table 1 highlighted a need to propose a digitalise system for construction monitoring and progress reporting. The (3) 28
4 A SYSTEMATIC APPROACH FOR MONITORING AND EVALUATING THE CONSTRUCTION PROJECT PROGRESS Table 1: Result of questionnaire survey within MCI result of survey shows that traditional or paper- b a s e d information flow on construction projects still dominate; as computers are increasingly becoming a central component of project information systems and used for developing the planned schedule. The several areas in construction management, such as scheduling, estimating, cost control, and accounting, employ wellestablished computer applications. To carry-out the laborious calculations and data tracking for these tasks, they represent a small portion of the day-to-day construction management activities. T h e result of survey also highlighted that the updating the project progress still carried out manually, no computerised system is used for developing the project progress automatically. Figure 2: Developed frame work of digitalising construction monitoring 4. THE PROPOSED PROTOTYPE SYSTEM The basic theory behind developing the model is to extend the traditional approach to represent the dynamic and simultaneous construction operations by incorporating inter- r e l a t i o n s h i p s between hierarchical processes of evaluating. The objective of developing a Digitalised Construction Monitoring (DCM) model is to systematise the construction monitoring and evaluation of a project. DCM is implemented using object oriented concepts and event driven programming. The object-oriented concepts were utilised in the graphical user interface of constructing the DCM processes. Graphical interfaces were created in the Photogrammetry and photomodeler environment and then exported into Visual Basic TM (event driven programming). Relational Data base was implemented using Micro Soft Access TM engine to store project related information. T h e simulation concept of DCM model is currently being used to test and check the validity. The main goal of DCM model is to propose an interface process model between the 2D digital photo and detail design drawings and update the physical progress chart by integrating the information. Figure 2 shows the framework model for the proposed system. The proposed system is divided into four different phases. In phase-i, the input information will be browsed by the user in the 29
5 ZUBAIR AHMED MEMON, et al. format. As seen in Figure 2, the graphical information is shown in Microsoft Project Gantt chart. The next and last logical step of prototype system is to take Action as a remedial measure. This step activated when project manager realises the delays are happening and required to boot the progress and to take decisions for successful completion within prescribed time. 5. ARCHITECT OF THE DIGITALISING CONSTRUCTION MONITORING The major task of developing this model is to develop the link between existing methods of evaluating and monitoring the physical progress of construction scene with modern technology. The main aim of DCM is to develop the project progress monitoring system that improves construction management methods in project progress reporting and control. Figure 3 shows the process flow diagram for the DCM, in which digital images will be captured from site and 3D model will be developed by using Photomodeler software and AutoCAD used to display 3D information of the intended design. All the design parameters are stored in the primary and secondary data base and code are designed to calculate the percentage of actual progress. This percentage will be integrated with the Micro Architecture of the DCM Model, which shows a dynamic connection between the database and graphical information. The DCM model will be integrated with existing commercial or research prototype systems. The graphical information is created from 3D Model by using professional prototype system namely Photomodeler and AutoCAD 3D drawing. The primary data base from AutoCAD drawing has been developed at the start of the project by developing an Expert system and will be reluctant as any change order will be corrected in the data base. Secondary data base will be developed as construction work constructed and the source of information will be using photos. Vi s u a l basic will be used to build interfaces between the database developed from AutoCAD and Photos by using Photomodeler. By simulating both data base, it will calculate the percentage of progress considering the updating date and will transfer this information to Microsoft Project to show the actual physical progress in bar chart. Figure 3: Process flow diagram format of planned schedule of work, txt file and 3DAutoCAD file. Once user browsed all the information, phase-ii start, which is to process the information. The process is done by automatically, as DCM user interface was designed, developed and computer programme are written in Visual Basic. During this phase, the percentage of progress will be calculated by integrating the database. These databases were developed during the Phase-II as user browsed the required information and content the 3D coordinate values from digital images and 3DAutoCAD drawings. The phase-iii will show the result interface of the system. This phase also shows the result in graphical 6. ALGORITHM FOR USER INTERFACE OF DCM SYSTEM As discussed under the heading of Architectural of DCM, this system integrate the information from Microsoft Project, AutoCAD drawings and digital images and produce the end result in the format of Gantt chart in Microsoft Project. The figure 4 shows the detailed Algorithm for the proposed system. A s figure shows, to start working on DCM, user needs to install the setup initially on his system and for successful running, user must be equip with AutoCAD to develop 3DAutoCAD model, planned work schedule in Microsoft Project and PhotoModeler software to develop the 3D Model. These three were considered the basic tools for DCM system. 30
6 A SYSTEMATIC APPROACH FOR MONITORING AND EVALUATING THE CONSTRUCTION PROJECT PROGRESS Figure 4: Algorithm of DCM user interface The first logical step after installing and running the DCM system is to browse the planned schedule of work in Microsoft project. The figure shows the detail algorithm for browsing the work schedule. Once successfully complete this step, next step is to browse the {*.txt} file. This file is created from digital images by running with PhotoModeler Pro version. The detail of developing the 3D model from digital images is shown in figure. This algorithm is carried out before running the DCM for measuring the progress. Once {*.txt} file exported from P h o t o M o d e l e r, then it is suggested to run the DCM system. A s soon as {*.txt} file browsed the information will be grouped in Microsoft Access database to store the information. The next logical step is to browse the 3DAutoCAD drawings as can be observed from the figure. As 3DAutoCAD file is browsed, the information is stored into database and user can start the process. By clicking on process command, it starts integrating the information in the database and calculates the percentage of progress. This percentage of progress can be viewed into the Microsoft Project. The algorithm is designed for this to show the view of comparison of progress between planned and actual progress. Algorithm of user interface of DCM model is successfully designed. By implementing this algorithm model, it is a u t h o r s believe the efficiency of construction industry will be improved. The successful implementations of DCM will speedup the process of developing the progress reports and will help the project manager in decision making process. From the view of professionals in Malaysian Construction I n d u s t r y, they suggested additional remarks for the usability of DCM especially when the contract dismantled during the contract period, DCM will be more effective and efficient as this stage also. They also suggested for the improvement of the model, which will be incorporated at the time of developing prototype system. 7. CONCLUSIONS The research described in this paper attempts to overcome the limitations of the previous research development in the area of evaluating the construction phase. The main focus of this paper is to design a methodology for the monitoring and evaluation of construction project and developing a systematic model considering Malaysian construction industry s view point. A questionnaire survey was carried out within MCI and analysed and the result identify the need of digitalise system for MCI. In this regard this study proposes a system and discusses the methodology for designing the prototype model to systematising monitoring and evaluation of a project. The model allows users to document and retrieve project information in the form of digital images and close-range photogrammetry techniques are used to create 3D Model. An integrated simulation model, named DCM (Digitalising the Construction Monitoring) is developed to integrate digital images of construction scene with AutoCAD drawings and it resolves the existing project progress reporting problems. Based on traditional approach, actual physical progress reports is developed manually by comparing the planned with actual 31
7 ZUBAIR AHMED MEMON, et al. performance measured on site. The Digitalising the Construction Monitoring (DCM) model is developed by using the Relational Database Management System (RDBMS). The integration of digital images and drawings will enable construction mangers to develop progress reports in a more consistent and accurate manner and more accurate as-built project schedules can be transferred to facility managers for operation, maintenance, renovation and demolition. The DCM model will improve the decision-making and productivity of the construction activity. 8. ACKNOWLEDGEMENT The authors acknowledge the contributions and support for this work by the Ministry of Science, Technology and Innovation (MOSTI), Malaysia, for the grant, under the grant number Vo t e No The author would like to give especial thanks to Dato Abdul Rashid, Former JKR Chief to visit Construction Technology and Management Centre (CTMC), Faculty of Civil Engineering, Universiti Teknologi Malaysia (UTM) and put full concentrate on the presentation of DCM model, and suggests remarkable ideas for successful launching of the system. REFERENCES [1] Hastak, M., Halpin, D. W., and Vanegas, J., COMPASS- New Paradigm for project cost control strategy and planning Journal of Construction Engineering and Management, ASCE (1996) 122(3): [2] Wang, S.Q., ESSCAD: Expert System Integrating Construction Scheduling with CAD Drawing. Construction Information Digital library paper w78-(2001)-46.content [3] Cheung, S.O., Suen, H.C.H. and Cheung, K.K.W PPMS: a web based construction Project Performance Monitoring S y s t e m, Automation in construction 13 (2004): [8] Streilein, A., Utilisation of CAD Models for the object oriented Measurement of Industrial and Architectural Objects. International Archives of Photogrammetry and Remote Sensing, Vol. XXI, Part B5, Vienna pp (1996). [9] Sacks R., Navon R. and Goldschmidt E. Building Project model support for Automated Labour Monitoring. Journal of Computing in Civil Engineering, ASCE (2003). 17(1): [10] Conlin, J. and Retik, A. The applicability of project management software and advanced IT techniques in construction delays mitigation. International Journal of Project Management (1997). 15(2): [ 11] Sanvido, V.E. and Paulson B. Site level Constru c t i o n Information System. Journal of Construction Engineering and Management ASCE (1992). 118: [12] Zhang, X. Concessionaire Selection: Methods and Criteria. Journal of Construction Engineering and Management, ASCE, (2004). 130(2): [13] Al-harthy, A.S.H. The Consultancy Fee for Structural Design Changes of Reinforced Concrete Building in Oman. Faculty of Civil Engineering, Universiti Teknologi Malaysia, Skudai, Johor, Malaysia (2006): Ph.D. Thesis. [ 1 4 ] Al-Hammad, A., Assaf, S. and Al-Shihah, M. The effect of faulty design on building maintenance. Journal of Quality in Maintenance Engineering. (1997) 3(1): [15] Abd.Majid, M.Z. Non-Excusable Delays in Construction. Department of Civil and Building Engineering, Loughborough University Loughborough, Leicestershire, UK (1997): Ph.D. Thesis. [4] Dawood, N. Sriprasert, E., Mallasi, Z. and Hobbs, B., Development of an Integrated Information Resource base for 4D/VR construction processes simulation, Automation in Construction, 12 (2002): [5] Abeid, J.N., Allouche, E., Arditi, D. and Hayman, M., PHOTO-NET II: a computer-based monitoring system applied to project management. Automation in construction, ASCE (2003). 12(5): [6] Stumpf A. L., Chin, S., Liu, L.Y. and Ganeshan, R. Use of a Relational Data-base System to Integrate Product and Process Information during Construction. Construction Information Digital Library http;//itc.scix.net/paper W78-(1995) [7] Maria F. Dr., Aouad, G. Dr. and Cooper G. Dr. OSCONCAD: A model-based CAD system Integrated with Computer Applications. Information Technology in Construction (ITcon), 3(1998):
EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT
EFFECT OF PROJECT COST AND TIME MONITORING ON PROGRESS OF CONSTRUCTION PROJCT Shreyash Raut 1, S S Pimplikar 2, Karan Sawant 3 1 Research Graduate ME Civil Construction & Management, Civil Engineering,
Virtual Reality Applications in Project Management Scheduling
71 Virtual Reality Applications in Project Management Scheduling Wael A. Abdelhameed University of Bahrain, [email protected] ABSTRACT This study concentrates on management of construction projects
Application of Time Management Tools and Techniques by Construction Industry Players: A Comparative Study between Kedah and Kelantan
Application of Time Management Tools and Techniques by Construction Industry Players: A Comparative Study between Kedah and Kelantan Ismaaini Ismail 1, Ismail Abdul Rahman 2, Aftab Hameed Memon 3, Ahmad
BIM Extension into Later Stages of Project Life Cycle
BIM Extension into Later Stages of Project Life Cycle Pavan Meadati, Ph.D. Southern Polytechnic State University Marietta, Georgia This paper discusses the process for extending the implementation of the
Pearson Education Limited 2003
156 Activities Activity 9.1 (PP. 357 358) [Project planning exercise] You are required to construct a project plan for the following information system development project. Your objective is to schedule
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.
A Framework of Information Management System for Construction Projects
A Framework of Information Management System for Construction Projects Ma Zhiliang and Qin Liang Department of Civil Engineering, Tsinghua University, Beijing 100084 ([email protected]; [email protected])
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects
MS Project Tutorial for Senior Design Using Microsoft Project to manage projects Overview: Project management is an important part of the senior design process. For the most part, teams manage projects
AUTOMATED PROJECT SCHEDULE AND INVENTORY MONITORING USING RFID
24th International Symposium on on Automation & Robotics in in Construction (ISARC 2007) Construction Automation Group, I.I.T. Madras AUTOMATED PROJECT SCHEDULE AND INVENTORY MONITORING USING RFID Geetha
A Systematic Change Management Capability Maturity Assessment Framework for Contracting Organizations
American Scientific Research Journal for Engineering, Technology, and Sciences (ASRJETS) ISSN (Print) 2313-4410, ISSN (Online) 2313-4402 Global Society of Scientific Research and Researchers http://asrjetsjournal.org/
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
Urban planning and management information systems analysis and design based on GIS
Available online at www.sciencedirect.com Physics Procedia 33 (2012 ) 1440 1445 2012 International Conference on Medical Physics and Biomedical Engineering Urban planning and management information systems
Information Technology Engineers Examination. Network Specialist Examination. (Level 4) Syllabus. Details of Knowledge and Skills Required for
Information Technology Engineers Examination Network Specialist Examination (Level 4) Syllabus Details of Knowledge and Skills Required for the Information Technology Engineers Examination Version 2.0
EVALUATION OF DIGITAL PHOTOGRAMMETRY AND 3D CAD MODELLING APPLICATIONS IN CONSTRUCTION MANAGEMENT
EVALUATION OF DIGITAL PHOTOGRAMMETRY AND 3D CAD MODELLING APPLICATIONS IN CONSTRUCTION MANAGEMENT Turker Bayrak and Ammar Kaka School of the Built Environment, Heriot Watt University, Riccarton, Edinburgh,
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Seon-Gyoo Kim Abstract The construction environment has been changing rapidly over
Solving Fundamental Problems in Model Based, Semi-Automated Building Project Scheduling
Solving Fundamental Problems in Model Based, Semi-Automated Building Project Scheduling Can Ersen FIRAT Construction Management and Economics, TKK Helsinki University of Technology Juhani KIIRAS Construction
A Project Based Approach for Teaching System Analysis, Design, and Implementation Courses
A Project Based Approach for Teaching System Analysis, Design, and Implementation Courses Nabil A. Yousif 1 and Masoud Naghedolfeizi 2 Abstract-In curricula of Computer Information Systems at Fort Valley
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
An Automated Workflow System Geared Towards Consumer Goods and Services Companies
Proceedings of the 2014 International Conference on Industrial Engineering and Operations Management Bali, Indonesia, January 7 9, 2014 An Automated Workflow System Geared Towards Consumer Goods and Services
THE USE OF VISUALISATION TO COMMUNICATE DESIGN INFORMATION TO CONSTRUCTION SITES
THE USE OF VISUALISATION TO COMMUNICATE DESIGN INFORMATION TO CONSTRUCTION SITES A. Ganah 1, C. Anumba and N. Bouchlaghem Civil & Building Engineering Dept. Loughborough University, LE11 3TU, UK Architectural
POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections
POLICY STATEMENT Commonwealth of Pennsylvania Department of Corrections Policy Subject: Policy Number: Project Management 1.1.5 Date of Issue: Authority: Effective Date: May 29, 2009 Signature on File
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Strategies to Speed Collaboration and Data Management Using Autodesk Vault and Riverbed WAN Optimization Technology
Autodesk Vault Professional Manufacturing Industry Marketing 2011 Strategies to Speed Collaboration and Data Management Using Autodesk Vault and Riverbed WAN Optimization Technology Geographically dispersed
Terms of Reference. Egypt Post - Several position: Architects, Interior Design, Structure Design, Site Engineer and Electromechanical Design.
Terms of Reference Duty Station: Type of contract: Title: Duration of the contract: Egypt Service Contract (Only Egyptians) Egypt Post - Several position: Architects, Interior Design, Structure Design,
Ming Sun 1, Ghassan Aouad, Nick Bakis, Stuart Birchall, William Swan
The ASCE 8th International Conference on Computing in Civil and Building EngineeringStandford University California, USA, August 14-17, 2000, pp130-137 Integrated Information Management and Exchange for
Linear Planning in Pipeline Construction
Linear Planning in Pipeline Construction A case study how to use TILOS in pipeline industry for scheduling and controlling construction works. Pipeline construction, as with other linear projects; presents
The Construction of Seismic and Geological Studies' Cloud Platform Using Desktop Cloud Visualization Technology
Send Orders for Reprints to [email protected] 1582 The Open Cybernetics & Systemics Journal, 2015, 9, 1582-1586 Open Access The Construction of Seismic and Geological Studies' Cloud Platform Using
Open Access Review of Delay Analysis Methods: A Process-Based Comparison
The Open Construction and Building Technology Journal, 2009, 3, 81-89 81 Open Access Review of Delay Analysis Methods: A Process-Based Comparison Jyh-Bin Yang*,1 and Chih-Kuei Kao 2 1 Department of Construction
Information Technology Career Field Pathways and Course Structure
Information Technology Career Field Pathways and Course Structure Courses in Information Support and Services (N0) Computer Hardware 2 145025 Computer Software 145030 Networking 2 145035 Network Operating
Engineering and Construction
Engineering and Construction I Manage risk. Protect profit. Today s engineering and construction market is highly competitive, driving profit margins down as risks increase. It only takes one failed project
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
Keywords: Programming, planning, linear work, civil engineering, time chainage, 4D, virtual reality.
Abstract The technique for the representation of the information based on the time chainage diagrams (usually denoted as T.C.D.) is the most common approach, compared to more traditional systems such as
STOCHASTIC SIMULATION MODEL FOR A LONG DISTANCE SAND TRANSPORTATION PROCESS
STOCHASTIC SIMULATION MODEL FOR A LONG DISTANCE SAND TRANSPORTATION PROCESS *J. Kang Texas A&M University 3137 TAMU College Station, TX 77845 (*Corresponding author: [email protected]) S. Ahn Samsung
DESKTOP COMPUTER SKILLS
1 Desktop Computer Skills Price List DESKTOP COMPUTER SKILLS Microsoft Office 2010 Microsoft Office 2010: New Features Please note all prices exclude VAT Approx. Learning Hours: 3 Price: 45 Office 2010
APPLICATIONS AND RESEARCH ON GIS FOR THE REAL ESTATE
APPLICATIONS AND RESEARCH ON GIS FOR THE REAL ESTATE Chengda Lin, Lingkui Meng, Heping Pan School of Remote Sensing Information Engineering Wuhan University, 129 Luoyu Road, Wuhan 430079, China Tel: (86-27)-8740-4336
Oracle s Primavera P6 Enterprise Project Portfolio Management
Oracle s Primavera P6 Enterprise Project Portfolio Management Oracle s Primavera P6 Enterprise Project Portfolio Management is the most powerful, robust and easy-to-use solution for prioritizing, planning,
BUSINESS BREAKDOWN STRUCTURE FOR CONSTRUCTION MANAGEMENT AND WEB-BASED APPLICATION SYSTEM
BUSINESS BREAKDOWN STRUCTURE FOR CONSTRUCTION MANAGEMENT AND WEB-BASED APPLICATION SYSTEM SUBMITTED: March 2005 REVISED: July 2005 PUBLISHED: August 2005 at http://www.itcon.org/2005/13/ EDITOR: B-C. Bjork
MSP How to guide session 2 (Resources & Cost)
MSP How to guide session 2 (Resources & Cost) 1. Introduction Before considering resourcing the schedule it is important to ask yourself one key question as it will require effort from the scheduler or
GCE APPLIED ICT A2 COURSEWORK TIPS
GCE APPLIED ICT A2 COURSEWORK TIPS COURSEWORK TIPS A2 GCE APPLIED ICT If you are studying for the six-unit GCE Single Award or the twelve-unit Double Award, then you may study some of the following coursework
Introduction. Project Management in New Zealand
AN ANALYSIS OF THE USE OF INFORMATION TECHNOLOGY FOR PROJECT MANAGEMENT IN THE NEW ZEALAND CONSTRUCTION INDUSTRY Dr Suzanne Wilkinson, Senior Lecturer, Department of Civil and Resource Engineering The
Industrial Case Study of Electronic Design, Cost and Schedule Integration
Industrial Case Study of Electronic Design, Cost and Schedule Integration Sheryl Staub 1, Martin Fischer 2 and Melody Spradlin 3 1 Project Engineer, Hathaway/Dinwiddie Construction Group Santa Clara, CA
Microsoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
RFID based Bill Generation and Payment through Mobile
RFID based Bill Generation and Payment through Mobile 1 Swati R.Zope, 2 Prof. Maruti Limkar 1 EXTC Department, Mumbai University Terna college of Engineering,India Abstract Emerging electronic commerce
A decision support tool for subcontractor multi-project resource allocation
icccbe 2010 Nottingham University Press Proceedings of the International Conference on Computing in Civil and Building Engineering W Tizani (Editor) A decision support tool for subcontractor multi-project
An Investigation on the Impact of Laddering Technique in Project plan: a Case of Road Construction
2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore An Investigation on the Impact of Laddering Technique in Project plan: a Case
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
CPM Scheduling with Primavera Unifier
CPM Scheduling with Primavera Unifier Don McNatty, PSP March 26, 2014 2014 Technical Webinar Series Thank you for joining today s technical webinar Mute all call in phones are automatically muted in order
BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses
BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction
Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad
Applications of Building Information Modeling (BIM) to Real Estate Projects of Ahmedabad Debasis Sarkar 1 & Raj Modi 2 Associate Professor and Head, Department of Civil Engineering, School of Technology,
A PROPOSED CONSTRUCTION DESIGN CHANGE MANAGEMENT TOOL TO AID IN MAKING INFORMED DESIGN DECISIONS
A PROPOSED CONSTRUCTION DESIGN CHANGE MANAGEMENT TOOL TO AID IN MAKING INFORMED DESIGN DECISIONS H.Hindmarch 1, A.W.Gale 1 and R.E.Harrison 2 1 Department of Mechanical, Aerospace and Civil Engineering,
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
DEVELOPING A CONSTRUCTION INTEGRATED MANAGEMENT SYSTEM Yan-Chyuan Shiau, Ming-Teh Wang, Tsung-Pin Tsai, Wen-Chian Wang
DEVELOPING A CONSTRUCTION INTEGRATED MANAGEMENT SYSTEM Yan-Chyuan Shiau, Ming-Teh Wang, Tsung-Pin Tsai, Wen-Chian Wang Associate Professor Department of Construction Engineering Chung Hua University Email:
The management of the projects with MS Project
The management of the projects with MS Project Author: AgimDerguti 1 What is Microsoft Project? Microsoft Project is a project management software program developed and sold by Microsoft Designed to assist
Civil Engineering Department College of Engineering and Petroleum Kuwait University
Civil Engineering Department College of Engineering and Petroleum Kuwait University GUIDELINES for CE CAPSTONE DESIGN PROJECTS (0620-490 : Capstone Design) 1. Basics of CE Capstone design projects 2. Contents
Source Code Translation
Source Code Translation Everyone who writes computer software eventually faces the requirement of converting a large code base from one programming language to another. That requirement is sometimes driven
CHAPTER 1 INTRODUCTION
CHAPTER 1 INTRODUCTION 1.1 Overview Web Content Management Systems (WCMS) consist of applications used to create, manage, store and deploy content on the Web, including text, graphics, video or audio,
Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study
Synchronous Building Information Model-Based Collaboration in the Cloud: a Proposed Low Cost IT Platform and a Case Study J. Munkley 1, M. Kassem 2 and N. Dawood 2 1 Niven Architects, Darlington, DL3 7EH,
Introduction and Overview
Introduction and Overview Definitions. The general design process. A context for design: the waterfall model; reviews and documents. Some size factors. Quality and productivity factors. Material from:
Designing and Embodiment of Software that Creates Middle Ware for Resource Management in Embedded System
, pp.97-108 http://dx.doi.org/10.14257/ijseia.2014.8.6.08 Designing and Embodiment of Software that Creates Middle Ware for Resource Management in Embedded System Suk Hwan Moon and Cheol sick Lee Department
INFORMATION SYSTEMS (INFO)
VCU 1 INFORMATION SYSTEMS (INFO) INFO 160. Digital Literacy: Computer Concepts, Internet, Digital Devices. 1 Hour. Semester course; 1 credit. Overview of basic computer concepts, the Internet, new technologies
TOOL FOR MAPPING MANUFACTURING CRTICAL-PATH TIME IN JOB SHOP ENVIRONMENT Chong Kuan Eng 1, How Whee Ching 2 1,2 Faculty of Manufacturing Engineering,
Sci.Int.(Lahore),26(4),1585-1589,2014 ISSN 1013-5316; CODEN: SINTE 8 1585 TOOL FOR MAPPING MANUFACTURING CRTICAL-PATH TIME IN JOB SHOP ENVIRONMENT Chong Kuan Eng 1, How Whee Ching 2 1,2 Faculty of Manufacturing
Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education
Evaluation of Building Information Modeling (BIM) Estimating Methods in Construction Education Keith E. Sylvester, Ph.D. and Charlotte Dietrich, Undergraduate Student East Carolina University Greenville,
Priority: Medium Channel to Actor: Graphical User Interface (GUI) Usage Frequency: Weekly Secondary Actors: Database, Brisk Application
University of Arkansas CSCE Department Capstone I Preliminary Report Spring 2015 Abstract Brisk - Intelligent Time Management Riley Turben, Daniel Pumford, Eric Hall, Ryan McAlister Managing teams of people
Please Note: Temporary Graduate 485 skills assessments applicants should only apply for ANZSCO codes listed in the Skilled Occupation List above.
ANZSCO Descriptions This ANZSCO description document has been created to assist applicants in nominating an occupation for an ICT skill assessment application. The document lists all the ANZSCO codes that
Using artificial intelligence methods and 3D graphics for implementation a computer simulator for ophthalmology
Using artificial intelligence methods and 3D graphics for implementation a computer simulator for ophthalmology V. V. Gribova, M. V. Petryaeva, L. A. Fedorischev Intelligent System Laboratory, Institute
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION
APPLYING A STOCHASTIC LINEAR SCHEDULING METHOD TO PIPELINE CONSTRUCTION Fitria H. Rachmat 1, Lingguang Song 2, and Sang-Hoon Lee 2 1 Project Control Engineer, Bechtel Corporation, Houston, Texas, USA 2
Design/Construction Integration thru Virtual Construction for Improved Constructability Walid Thabet, Virginia Tech
Design/Construction Integration thru Virtual Construction for Improved Constructability Walid Thabet, Virginia Tech Executive Summary: Changing industry needs have take big leaps in the past two decades.
VisPMIS: A VISUAL PROJECT MANAGEMENT INFORMATION SYSTEM
Eleventh East Asia-Pacific Conference on Structural Engineering & Construction (EASEC-11) Building a Sustainable Environment November 19-21, 2008, Taipei, TAIWAN VisPMIS: A VISUAL PROJECT MANAGEMENT INFORMATION
METHODOLOGIES FOR DETERMINING CONSTRUCTION CONTRACT TIME AND EVALUATING CONTRACT TIME EXTENSIONS FINAL REPORT
METHODOLOGIES FOR DETERMINING CONSTRUCTION CONTRACT TIME AND EVALUATING CONTRACT TIME EXTENSIONS FINAL REPORT SCDOT Research Project 652: Construction Contract Time/Construction Contract Time Extension
INTELLIGENCE BASED CADASTRAL DATABASE SELECTION AND VISUALIZATION SYSTEM: CONCEPTS AND PROTOTYPE
INTELLIGENCE BASED CADASTRAL DATABASE SELECTION AND VISUALIZATION SYSTEM: CONCEPTS AND PROTOTYPE Abdullah Hisam Omar and Amran Bachok Department of Geomatic Engineering Faculty of Geoinformation Science
A Review of an MVC Framework based Software Development
, pp. 213-220 http://dx.doi.org/10.14257/ijseia.2014.8.10.19 A Review of an MVC Framework based Software Development Ronnie D. Caytiles and Sunguk Lee * Department of Multimedia Engineering, Hannam University
Critical Path Analysis & PERT Charts (taken from www.business.com.
Critical Path Analysis & PERT Charts (taken from www.business.com. - Planning and scheduling more complex projects Critical Path Analysis and PERT are powerful tools that help you to schedule and manage
Using InstallAware 7. To Patch Software Products. August 2007
Using InstallAware 7 To Patch Software Products August 2007 The information contained in this document represents the current view of InstallAware Software Corporation on the issues discussed as of the
Risk D&D Rapid Prototype: Scenario Documentation and Analysis Tool
PNNL-18446 Risk D&D Rapid Prototype: Scenario Documentation and Analysis Tool Report to DOE EM-23 under the D&D Risk Management Evaluation and Work Sequencing Standardization Project SD Unwin TE Seiple
SCHEDULING AND TIME MANAGEMENT. Project Management and Leadership 2015D, PhD, PMP
SCHEDULING AND TIME MANAGEMENT Project Management and Leadership 2015D, PhD, PMP Our PROGRAMME: 1. INTRODUCTION TO PROJECT MANAGEMENT 2. STARTING A PROJECT 3. WORK MOTIVATION 4. COMMUNICATION 5: TEAMS
Knowledge-Based Sustainable Decision-making Framework for the Implementation of Innovative Technologies in the Malaysian Construction Industry
Knowledge-Based Sustainable Decision-making Framework for the Implementation of Innovative Technologies in the Malaysian Construction Industry ROHANA MAHBUB Faculty of Architecture Planning and Surveying
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY By Mohammad A. Ammar 1 and Emad Elbeltagi 2 ABSTRACT: Scheduling of construction projects that have multiple units, wherein activities
DEVELOPMENT OF A DISTRIBUTED CONSTRUCTION PROJECT MANAGEMENT GAME WITH COTS IN THE LOOP
Proceedings of the 2013 Winter Simulation Conference R. Pasupathy, S.-H. Kim, A. Tolk, R. Hill, and M. E. Kuhl, eds DEVELOPMENT OF A DISTRIBUTED CONSTRUCTION PROJECT MANAGEMENT GAME WITH COTS IN THE LOOP
INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2
INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2 Hyun Cho 1, Ki Hwan Lee 1, Song Hyon Lee 1, Ta Lee 1, Hyun Jun Cho 1, Sung Hoon Kim 2 and
3F6 - Software Engineering and Design. Handout 15 Software Management I With Markup. Steve Young
3F6 - Software Engineering and Design Handout 15 Software Management I With Markup Steve Young Contents 1. Software Engineering 2. Software Life Cycle 3. Team Organisation 4. Product Development 5. Specification
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
PROJECT AUDIT METHODOLOGY
PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit
DPRA Inc. 10215 Technology Drive, Suite 201 Knoxville, TN 37932-4304 Telephone: (865) 777-3772 Fax: (865) 777-4010 http://www.gsa.drpa.
General Services Administration Federal Acquisition Service Authorized Federal Acquisition Schedule Price List On-line access to contract ordering information, terms and conditions, up-to-date pricing,
Business Intelligence. A Presentation of the Current Lead Solutions and a Comparative Analysis of the Main Providers
60 Business Intelligence. A Presentation of the Current Lead Solutions and a Comparative Analysis of the Main Providers Business Intelligence. A Presentation of the Current Lead Solutions and a Comparative
APPLYING CASE BASED REASONING IN AGILE SOFTWARE DEVELOPMENT
APPLYING CASE BASED REASONING IN AGILE SOFTWARE DEVELOPMENT AIMAN TURANI Associate Prof., Faculty of computer science and Engineering, TAIBAH University, Medina, KSA E-mail: [email protected] ABSTRACT
Knowledge Acquisition and the Project Manager
A KNOWLEDGE BASED SYSTEM FOR LINKING INFORMATION TO SUPPORT DECISION MAKING IN CONSTRUCTION SUBMITTED: December 2000 REVISED: June 2002 PUBLISHED: August 2002 at http://www.itcon.org/2002/6 EDITOR: Abdul
