1 Metro Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA 23 File #: , Version: 1 Planning and Programming May 20,2015 SUBJECT: METROLINK VINCENT GRADE/ACTON STATION SECOND PLATFORM AND SIDING EXTENSION PROJECT ACTION: PROGRAM ADDITIONAL FUNDS RECOMMENDATION A. Program $116,000 in new MeasureR 3% funds to the Vincent Grade/Acton Station Second Platform and Siding Extension Project (Vincent Project); B. Reprogram $275,000 in cost savings from the Antelope Valley Line Infrastructure Improvement Strategic Plan (AVL Study) to the Vincent Grade/Acton Station Second Platform and Siding Extension Project (Vincent Project); C. Authorize the Chief Executive Officer, or his designee, to negotiate and execute all agreements necessary for this action. ISSUE $16,400,000 in Metro and State funds have been allocated to the Vincent Project. The recent construction Invitation For Bids (IFB) low bid is higher than the engineer's construction cost estimate. Additional funding is needed to keep the Vincent Project fully funded and not jeopardize previously allocated State funds. Staff is requesting to program $116,000 in new MeasureR 3% funds to the Vincent Project and reprogram $275,000 in cost savings from the AVL Study to fully fund the Vincent Project so that Southern California Regional Rail Authority (SCRRA) can execute a construction contract in June DISCUSSION The Vincent Project will lengthen the existing siding on the Metrolink Antelope Valley Line by 4,000 feet to create a two mile long passing siding. A second side platform will be added at the Vincent Metro Page 1 of 6 Printed on 5/6/2015 powered ljv Leg!starTM

2 Station. This project adds significant capacity to the northern portion of the Antelope Valley Line, which is mostly single tracked. Longer freight trains will be able to layover on the siding and not interfere with Metrolink trains. This will result in improved overall on time performance and schedule reliability. Project Funding for $16.4M Project In October 2013, the Board approved funding for design plus $6.5M (million) as 50% match for construction, based upon an initial $13M project cost estimate. In spring 2014, a full crossover was added to the project scope, bringing the total project cost to $16.4M. The construction cost was estimated to be $1 0.6M based upon the SCRRA Design Procedures Manual. In June 2014, $1.7M was moved from the Metrolink rehabilitation and renovation program to the Vincent Project to increase the Metro funding commitment to $8.2M as 50% match for construction. The project was also submitted to the California Transportation Commission (CTC) for programing of $8.2M. In December 2014, the CTC allocated $8.2M in matching State Proposition 1 B Trade Corridor Improvement Funds (TCIF), to create $16.4M in total project funding. Cost Increase to $18.1M In March 2015, SCRRA received Invitation For Bids (IFB) construction costs. The engineer's final construction cost estimate prior to the bid opening increased to $12.6M as a result of additional scope and refining the quantities and unit costs. Additional scope included: Relocation of Sprint fiber optic lines Adjustments to drainage components to meet Army Corp of Engineers and the Regional Water Quality Board permitting requirements Signal and track revisions to accommodate a speed increase through the siding and extensions of the setout tracks Revisions to track construction phasing, i.e. adding new track vs shifting existing track, to accommodate and have little impact on rail operations Revisions to quantities based on bidders questions and comments Of the eleven bids received, the low bid was $13.6M, $1M above the engineer's construction cost estimate. A detailed review of the cost estimate revealed that unit prices and lump sum prices were generally higher than the engineer's estimate, which was based on previous construction bids of similar nature and magnitude. The cost difference is largely due to the retaining wall, sub-ballast, track and turnout construction, and railroad signals, which were between $1 OOK to $300K more than the engineer's estimate. With the favorable turn in the economy, bidders increased their unit costs for labor and materials. Eleven bids were received which were uniformly distributed between $13.6M to $17.6M. Based upon the low bid of $13.6M, the total project cost was $18.1 M, which is $1.8M more than the available project funding of $16.4M. Metro Page 2 of 6 Printed on 5/6/2015 powered b~ Leg1 star~m

3 Attachment A shows the construction budget in more detail. Items #1 thru #6 can be reduced, deferred or funded through a future maintenance of way (MOW) or rehabilitation and renovation budget. These actions will bring the total project budget down from $18.1 M to $17.2M. The table below summarizes current funding plus the additional funds requested from Metro and needed from SCRRA to proceed with executing this contract: Metro State SCRRA Total Original Estimate (1 0/13) $6,500,000 $6,500,000 $ 13,000,000 Revised Estimate with full $8,200,000 $8,200,000 $ 16,400,000 crossover added (6/14) Requested Additional Funds $ 116,000 $ 116,000 (5/15) Requested Reprogramming $ 275,000 $ 275,000 ~5/15) SCRRA PTMISEA Funds $436,000 $ 436,000 (6/15) Revised Total $8,591,000 $8,200,000 $436,000 $ 17,227,000 Reprogramming of Funds From AVL Study Savings ($ ) In September 2011, the board programmed $1 million to initiate a study of the AVL to identify projects to increase capacity and improve operating speeds. Various track and signal and line speed improvements were recommended such as the Vincent Project. The study was completed in The total study costs were $725,000. There are savings of $275,000 which staff is recommending for reprogramming, to reduce the amount of new MeasureR funds to $116,000 instead of $391,000. SCRRA Reallocation of PTMISEA Funds ($436,000) Proposition 1 B Public Transportation Modernization, Improvement and Service Enhancement Account (PTMISEA) funds accrue directly to SCRRA from the State and are eligible to be used for sealed corridor and crossing improvements. SCRRA will reallocate $436,000 to the Vincent Project to install a required pedestrian crossing warning system. The State TCIF grant requires SCRRA to execute the construction contract by June These actions will fully fund the $17.2M Vincent Project and enable SCRRA to execute the contract in June without jeopardizing the State TCI F funding. DETERMINATION OF SAFETY IMPACT The Vincent Station will have an inter-track fence between the two platforms. The fence will restrict pedestrians from crossing between the two tracks. There will be an at-grade pedestrian crossing. The Vincent Project will be constructed in accordance with the latest Metrolink design standards. Metro Page 3 of 6 Printed on 5/ pov Iered bv LegJstar'M

4 FINANCIAL IMPACT $116,000 in Measure R 3% funds will be programmed to the Vincent Project in cost center 2415, Regional Rail, project number task $275,000 in MeasureR 3% funds will be reprogrammed from AVL Study MOU.MRSCRRA02.02 and contract PS project savings. Since this is a multi-year contract/project, the Executive Officer, Regional Rail will be accountable for budgeting the cost in future years. Expenses will start to be incurred in FY , and will be budgeted as part of the FY budget process. ALTERNATIVES CONSIDERED An alternative is to not program the funds to the Vincent Project. This is not recommended since SCRRA has already received an allocation of $8.2M in TCIF funds for the project from the State. If this project does not go forward, Los Angeles County would lose 50% matching construction funds for an important goods movement and capacity enhancing project which benefits the Metrolink commuter rail system. Another alternative is to reprogram prior year rehabilitation and renovation funds to this project. This is advised against since the state of good repair for the existing Metrolink system should not be reduced for a new capital project. Measure R 3% funds are available for new capital projects such as the Vincent Project. With Board approval, the MeasureR funds for this project will be 51% of the total project cost, which is an excellent leveraging of local funds with State funds to construct an important project to increase Metrolink capacity and improve on-time performance and schedule reliability. NEXT STEPS Metro will amend the Vincent Project MOU to add $116,000 in new MeasureR 3% funds plus $275,000 in reprogrammed savings form the AVL Study, to fully fund the Vincent Project. SCRRA will also allocate $436,000 in PTMISEA funds from sealed corridor to the Vincent Project. SCRRA will execute a construction contract in June Notice To Proceed (NTP) for construction will occur in summer SCRRA will manage the project and construction will be from summer 2015 thru Fall Metro Page 4 of 6 Printed on 5/6/2015 powered {)y Leq1starTM

5 Prepared by: Jay Fuhrman, Transportation Planning Manager, (213) Don A. Sepulveda, Executive Officer, Regional Rail (213) Metro Page 5 of 6 Printed on 5/6/2015 powered by LeglstarTM

6 twp~ ~ Bryan Pennilon Executive Director, Engineering and Construction ' Nalini Ahuja Executive Director, Finance and Budget Chief Executive Officer Metro Page 6 of 6 Printed on 5/7/2015 powered by Leg1star'M

7 ATTACHMENT A INVITATION FOR BID COST DETAIL ~ METRDLINI< Vincent Grade/Acton Station Second Platform and Vincent Siding Extension S&C DESIGN AND DESIGN SUPPORT CONSTRUCTION MANAGEMENT FLAGGING METROLINK AGENCY COSTS MAINTENANCE OF WAY TRACKISTRUCT. MAINTENANCE SUPPORT.. SIGNAL AND COMMUNICATION MAINTENANCE SUPPORT Items From Scope of Work #1) Defer Riprap Placement #2) Defer Rehabilitation of Existing Platform CIS #3) Reduce Track stabilization from $250,000 to $150,000 #4) Defer Removal of Existing Track #5) PROJECT OPTION 1 - Main Track Set Out Extension -:~~a;s.!i:.!:.!ifuture MOW or rehab funds PROJECT OPTION 2 - Future MOW or rehab funds METRO ORIGINAL FUNDING (10/13) METRO ADDITIONAL REPROGRAMMING FROM REHAB/PTMISEA (6/14) STATE TCIF FUNDING (12/14) METRO ADDITIONAL MEASURER (5/15) METRO REPROGRAMMING FROM AVL STUDY (5/15) SCRRA PTMISEA REALLOCATION $6,500,000 $1,700,000 $8,200,000 $116,000 $275, ~... Notes: 1. Estimated Project Overhead Costs based on percentage rates applied to the construction costs per SCRRA Design Procedures Manual 2. Project Overhead Costs based on actuais or refinement of estimate

8

Experts in Rail Maintenance and Infrastructure

Experts in Rail Maintenance and Infrastructure Experts in Rail Maintenance and Infrastructure It is with great people and pride, rooted in a culture of safety, D that Transdev delivers systems, technologies, and business processes to strengthen rail

More information

APPROVE PROGRAMMING RECOMMENDATION

APPROVE PROGRAMMING RECOMMENDATION 19 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net PLANNING AND PROGRAMMING COMMITTEE SEPTEMBER 17, 2014 SUBJECT: ACTION: FY 2014 FEDERAL HOMELAND SECURITY PROGRAM APPROVE PROGRAMMING

More information

Los Angeles County Metropolitan Transportation Authority

Los Angeles County Metropolitan Transportation Authority Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA gooi2-2952 zt3.922.200o Tel metro.net O REVISED EXECUTIVE MANAGEMENT COMMITTEE November 06, 2014 SUBJECT:

More information

How To Upgrade Tap To A Ctc Customer Relationship Management System

How To Upgrade Tap To A Ctc Customer Relationship Management System 14 O ne Gateway Plaza Los Angeles, CA 90012-2952 213-922.2000 Te l m etro. net FINANCE, BUDGET AND AUDIT COMMITTEE JANUARY 14, 2014 SUBJECT: ACTION: TAP CUSTOMER RELATIONSHIP MANAGEMENT (CRM) SYSTEM EXECUTE

More information

SUBJECT: ACQUISITION OF COMPUTER HARDWARE, SOFTWARE AND SERVICES APPROVE THE WESTERN STATES CONTRACTING ALLIANCE MASTER PRICE AGREEMENT

SUBJECT: ACQUISITION OF COMPUTER HARDWARE, SOFTWARE AND SERVICES APPROVE THE WESTERN STATES CONTRACTING ALLIANCE MASTER PRICE AGREEMENT 11 - - ~ Los Anples County ~ Metro One Gateway Plaza Los Angeles, CA 90012 2952 213.922.2000 Tel metro.net FINANCE, BUDGET AND AUDIT COMMITTEE JULY 16, 2014 SUBJECT: ACQUISITION OF COMPUTER HARDWARE, SOFTWARE

More information

9 One Gateway Plaza Los Angeles, CA 90012-2952

9 One Gateway Plaza Los Angeles, CA 90012-2952 9 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net FINANCE, BUDGET AND AUDIT COMMITTEE SEPTEMBER 17, 2014 SUBJECT: ACTION: HEALTH BENEFITS CONSULTING SERVICES AWARD A CONTRACT FOR

More information

EXECUTIVE MANAGEMENT COMMITTEE JUNE 20, 2013 OFF-SITE STORAGE & MAINTENANCE OF INACTIVE RECORDS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION ISSUE

EXECUTIVE MANAGEMENT COMMITTEE JUNE 20, 2013 OFF-SITE STORAGE & MAINTENANCE OF INACTIVE RECORDS APPROVE CONTRACT AWARD ACTION: RECOMMENDATION ISSUE 66 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net EXECUTIVE MANAGEMENT COMMITTEE JUNE 20, 2013 SUBJECT: ACTION: OFF-SITE STORAGE & MAINTENANCE OF INACTIVE RECORDS APPROVE CONTRACT

More information

AWARD CONTRACT TO ADP NATIONAL ACCOUNT SERVICES

AWARD CONTRACT TO ADP NATIONAL ACCOUNT SERVICES One Gateway Plaza Los Angeles, CA 90012-2952 213-922.2000 metro. net 15 FINANCE, BUDGET AND AUDIT COMMITTEE July 16, 2014 SUBJECT: ACTION: OUTSOURCED PAYROLL SERVICES AWARD CONTRACT TO ADP NATIONAL ACCOUNT

More information

FINANCE, BUDGET AND AUDIT COMMITTEE June 18, 2014 AGENCY-WIDE BUDGET SYSTEM UPGRADE APPROVE CONTRACT AWARD RECOMMENDATION

FINANCE, BUDGET AND AUDIT COMMITTEE June 18, 2014 AGENCY-WIDE BUDGET SYSTEM UPGRADE APPROVE CONTRACT AWARD RECOMMENDATION 7 One Gateway Plaza Los Angeles, CA 90012-2952 2 13.922.2000 Tel metro. net FINANCE, BUDGET AND AUDIT COMMITTEE June 18, 2014 SUBJECT: ACTION: AGENCY-WIDE BUDGET SYSTEM UPGRADE APPROVE CONTRACT AWARD RECOMMENDATION

More information

AWARD CONTRACT TO SHARED TECHNOLOGIES FOR TELEPHONE SYSTEM MAINTENANCE AND SERVICE IN AN AMOUNT NOT TO EXCEED $1,534 489

AWARD CONTRACT TO SHARED TECHNOLOGIES FOR TELEPHONE SYSTEM MAINTENANCE AND SERVICE IN AN AMOUNT NOT TO EXCEED $1,534 489 Metro Me',opo!;", r,,",po"o';o, Auth"" One Gateway Plaza Los Angeles, CA 90012-2952 213. 922.2000 Tel metro. net FINANCE & BUDGET COMMITTEE JULY 15, 2004 SUBJECT: ACTION: TELEPHONE SYSTEM SERVICE CONTRACT

More information

EXCESS LIABILITY INSURANCE PROGRAM FOR OPERATIONS

EXCESS LIABILITY INSURANCE PROGRAM FOR OPERATIONS Metro Los Angeles County Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA gooiq I FINANCE AND BUDGET COMMITTEE JUNE 15,2011 SUBJECT: ACTION: EXCESS LIABILITY INSURANCE PROGRAM FOR

More information

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES

APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan Transportation Authority (Metro) 2009 Transportation Improvement Program Call for Projects APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan

More information

COUNTY OF LOS ANGELES

COUNTY OF LOS ANGELES COUNTY OF LOS ANGELES DEPARTMENT OF PUBLIC WORKS "To Enrich Lives Through Effective and Caring Service" DEAN D. EFST A THIOU, Acting Director 900 SOUTH FREMONT AVENUE ALHAMBRA, CALIFORNIA 91803-133 I Telephone:

More information

Lankershim Depot Rehabilitation Project - Overview

Lankershim Depot Rehabilitation Project - Overview One Gateway Plaza Los Angeles, CA 90012-2952 213-922.200< metro.net 32 CONSTRUCTION COMMITTEE FEBRUARY 19, 2015 SUBJECT: ACTION: REHABILITATION OF LANKERSHIM DEPOT PHASE TWO APPROVE RECOMMENDATION TO INCREASE

More information

IDOT Chicago - St. Louis High-Speed Rail Program Management

IDOT Chicago - St. Louis High-Speed Rail Program Management 1 www.idothsr.org www.connectthemidwest.com IDOT Chicago - St. Louis High-Speed Rail Program Management Lessons Learned: Sealing the Corridor For 110 MPH Operations Thomas W. Hunter Parsons Brinckerhoff

More information

Metro REVISED PLANNING AND PROGRAMMING COMMITTEE JANUARY 14, 2015 SUBJECT: METROLINK REHABILITATION AND RENOVATION PROGRAM

Metro REVISED PLANNING AND PROGRAMMING COMMITTEE JANUARY 14, 2015 SUBJECT: METROLINK REHABILITATION AND RENOVATION PROGRAM 21 Metro Los Angeles County One Gateway Plaza zi3.gzz.z000 ',.:, Metropolitan Transportation Authority Los Angeles, CA gooiz-z952 metro.net REVISED PLANNING AND PROGRAMMING COMMITTEE JANUARY 14, 2015 SUBJECT:

More information

SYSTEM SAFETY AND OPERATIONS COMMITTEE OCTOBER 17, 2013 GLASS ANTI-GRAFFITI FILM MAINTENANCE AND REPLACEMENT SERVICES AND ETCHED GLASS REPAIR SERVICES

SYSTEM SAFETY AND OPERATIONS COMMITTEE OCTOBER 17, 2013 GLASS ANTI-GRAFFITI FILM MAINTENANCE AND REPLACEMENT SERVICES AND ETCHED GLASS REPAIR SERVICES 40 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net SYSTEM SAFETY AND OPERATIONS COMMITTEE OCTOBER 17, 2013 SUBJECT: ACTION: GLASS ANTI-GRAFFITI FILM MAINTENANCE AND REPLACEMENT

More information

Southern California Regional Rail Authority

Southern California Regional Rail Authority Southern California Regional Rail Authority Fiscal Year 2014-15 Adopted Budget SOUTHERN CALIFORNIA REGIONAL RAIL AUTHORITY FISCAL YEAR 2014-15 ADOPTED BUDGET June 15, 2014 Adopted June 27, 2014 Los Angeles

More information

SYSTEMWIDE REQUIREMENTS

SYSTEMWIDE REQUIREMENTS SYSTEMWIDE REQUIREMENTS for the Peninsula Rail Program San Francisco to San Jose on the Caltrain Corridor Description of the Systemwide Context for the High Speed Train Project This document provides a

More information

æ Met ro Met.opo'"'" T"",,,t.t'o" '"tho""

æ Met ro Met.opo'' T,,,t.t'o 'tho æ Met ro Met.opo'"'" T"",,,t.t'o" '"tho"" One Gateway Plaza 213.922.2000 Tel Los Angeles, CA 90012-2952 metro. net 33 OPERATIONS COMMITTEE MAY 18, 2006 SUBJECT: ACTION: CONTRACT NO. PS0692401822, DATA

More information

Owner s Procurement Forum

Owner s Procurement Forum Washington Metropolitan Area Transit Authority Construction Management Association of America National Capitol Chapter Owner s Committee Owner s Procurement Forum February 24, 2015 OVERVIEW of WMATA INFRASTRUCTURE:

More information

Metro REVISED EXECUTIVE MANAGEMENT COMMITTEE MAY 15, 2014 SUBJECT: DISABLED VETERAN'S BUSINESS ENTERPRISE (DVBE) BUSINESS PROGRAM

Metro REVISED EXECUTIVE MANAGEMENT COMMITTEE MAY 15, 2014 SUBJECT: DISABLED VETERAN'S BUSINESS ENTERPRISE (DVBE) BUSINESS PROGRAM Metro Los Angeles County One Gateway Plaza 2~3.9sz.zo Metropolitan Transportation Authority Los Angeles, CA gooi2-z952 metro.net REVISED EXECUTIVE MANAGEMENT COMMITTEE MAY 15, 2014 SUBJECT: DISABLED VETERAN'S

More information

AGREEMENT FOR MOVING OVERSIZED LOADS OVER HIGHWAY-RAIL GRADE CROSSINGS SCRRA FORM NO. 4

AGREEMENT FOR MOVING OVERSIZED LOADS OVER HIGHWAY-RAIL GRADE CROSSINGS SCRRA FORM NO. 4 AGREEMENT FOR MOVING OVERSIZED LOADS OVER HIGHWAY-RAIL GRADE CROSSINGS SCRRA FORM NO. 4 SCRRA File No. SCRRA Project/Task No. CPUC No. Subdivision Thomas Guide Page The Contractor, hereby requests permission

More information

TELEPHONE SYSTEM SERVICE CONTRACT

TELEPHONE SYSTEM SERVICE CONTRACT Metro Met,opoUt'" T"",portal;on '"",o,;ty One Gateway Plaza Los Angeles, CA 90012-2952 213. 922.2000 Tel metro. net FINANCE & BUDGET COMMITTEE FEBRUARY 19, 2004 SUBJECT: ACTION: TELEPHONE SYSTEM SERVICE

More information

to imagine a transportation vision

to imagine a transportation vision to imagine a transportation vision Before 2007 many wondered Was collaboration and coalition building even possible in Los Angeles County? Creating the Measure R coalition sent a new message This is how

More information

5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES

5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.0 FINANCIAL ANALYSIS AND COMPARISON OF ALTERNATIVES 5.1 FINANCIAL ANALYSIS The cost of a transportation investment falls into two categories: capital costs, and operating and maintenance (O&M) costs.

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015)

Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Mid-Coast Corridor Transit Project San Diego, California New Starts Engineering (Rating Assigned November 2015) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total Capital

More information

CONSTRUCTION COMMITTEE NOVEMBER 06,2014 PMIS HOSTING SUPPORT SERVICES CONTRACT INCREASE CONTRACT VALUE RECOMMENDATIONS ISSUE DISCUSSION

CONSTRUCTION COMMITTEE NOVEMBER 06,2014 PMIS HOSTING SUPPORT SERVICES CONTRACT INCREASE CONTRACT VALUE RECOMMENDATIONS ISSUE DISCUSSION One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net CONSTRUCTION COMMITTEE NOVEMBER 06,2014 SUBJECT: ACTION: PMIS HOSTING SUPPORT SERVICES CONTRACT INCREASE CONTRACT VALUE RECOMMENDATIONS

More information

Wilmington to Newark Commuter Rail Improvement Project

Wilmington to Newark Commuter Rail Improvement Project Wilmington to Newark Commuter Rail Improvement Project The Delaware Transit Corporation (DTC), a subsidiary of the Delaware Department of Transportation (DelDOT), is undertaking a rail capacity expansion

More information

RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4

RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 RED RIVER DIVERSION FARGO MOORHEAD METRO FLOOD RISK MANAGEMENT PROJECT, FEASIBILITY STUDY, PHASE 4 APPENDIX G COST ESTIMATES EXHIBIT J RAILROAD BRIDGE QUANTITIES Report for the US Army Corps of Engineers,

More information

Metrolink Positive Train Control Program May 2012

Metrolink Positive Train Control Program May 2012 Metrolink Positive Train Control Program May 2012 Metrolink s aggressive Positive Train Control (PTC) program calls for installing a back-office system, replacing the current computeraided dispatch system,

More information

Chapter 5 Financial Plan

Chapter 5 Financial Plan The Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA_LU) requires that the MTP incorporate a financial plan for the planning period. The MTP is required to

More information

RIGHT -OF-WAY ACQUISITION AND RELOCATION SERVICES BENCH AUTHORIZE INCREASE TO CONTRACT MODIFICATION AUTHORITY

RIGHT -OF-WAY ACQUISITION AND RELOCATION SERVICES BENCH AUTHORIZE INCREASE TO CONTRACT MODIFICATION AUTHORITY ~...,eo.., Metro...-,..._ One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 metro. net 39 CONSTRUCTION COMMITTEE SEPTEMBER 19, 2013 SUBJECT: ACTION: RIGHT -OF-WAY ACQUISITION AND RELOCATION SERVICES

More information

FloridaNOTAllAboard RESOLUTION NO. 28-15

FloridaNOTAllAboard RESOLUTION NO. 28-15 RESOLUTION NO. 28-15 A RESOLUTION OF THE CITY COMMISSION OF THE CITY OF DELRAY BEACH, FLORIDA, EXPRESSING CONCERN WHETHER ALL ABOARD FLORIDA WILL HAVE AN ADVERSE IMPACT ON THE CITY; STATING THAT THE CITY

More information

One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA 90012-2952 CALL CENTER TELEPHONE SYSTEM REPLACEMENT PROJECT

One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA 90012-2952 CALL CENTER TELEPHONE SYSTEM REPLACEMENT PROJECT 37 Metro Los Angeles County One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net SYSTEM SAFETY & OPERATIONS COMMITTEE JUNE 19, 2014 SUBJECT: ACTION:

More information

UNDERGROUND CELL PHONE AND DATA SERVICES PROVIDER

UNDERGROUND CELL PHONE AND DATA SERVICES PROVIDER 55 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net EXECUTIVE MANAGEMENT COMMITTEE FEBRUARY 21, 2013 SUBJECT: ACTION: UNDERGROUND CELL PHONE AND DATA SERVICES PROVIDER APPROVE CONTRACT

More information

Metro. Board Report. Metro. File #: 2015-0667, Version: SYSTEM, SAFETY, SECURITY AND OPERATIONS COMMITTEE MAY 21, 2015

Metro. Board Report. Metro. File #: 2015-0667, Version: SYSTEM, SAFETY, SECURITY AND OPERATIONS COMMITTEE MAY 21, 2015 Metro Metro Board Report Los Angeles County Metropolitan Transportation Authority One Gateway Plaza 3rd Floor Board Room Los Angeles, CA File #: 2015-0667, Version: SYSTEM, SAFETY, SECURITY AND OPERATIONS

More information

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014)

Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Mid-Coast Corridor Transit Project San Diego, California New Starts Project Development (Rating Assigned November 2014) Summary Description Proposed Project: Light Rail Transit 10.9 Miles, 9 Stations Total

More information

Metro REVISED REGULAR BOARD MEETING OCTOBER 2, 2014 SUBJECT: MAJOR CONSTRUCTION UMBRELLA INSURANCE PROGRAM PURCHASE UMBRELLA INSURANCE ACTION:

Metro REVISED REGULAR BOARD MEETING OCTOBER 2, 2014 SUBJECT: MAJOR CONSTRUCTION UMBRELLA INSURANCE PROGRAM PURCHASE UMBRELLA INSURANCE ACTION: Metro Los Angeles County One Gateway Plaza Zi3.92z.z000 Tel Metropolitan Transportation Authority Los Angeles, CA goo~z-2952 metro.net REVISED REGULAR BOARD MEETING OCTOBER 2, 2014 SUBJECT: MAJOR CONSTRUCTION

More information

APPROVE CONTRACT MODIFICATION IN THE AMOUNT OF $255 000 FOR A TWO-YEAR PERIOD COVERING SYSTEM DEVELOPMENT SERVICES IN SUPPORT OF TRANSITSAFETM

APPROVE CONTRACT MODIFICATION IN THE AMOUNT OF $255 000 FOR A TWO-YEAR PERIOD COVERING SYSTEM DEVELOPMENT SERVICES IN SUPPORT OF TRANSITSAFETM Metro Metropolitan Transportation Authority One Gateway Plaza Los Angeles, CA 90012-2952 213. 922.2000 Tel metro. net OPERATIONS COMMITTEE MAY 20 2004 SUBJECT: ACTION: MODIFICATION NO. 3 TO CONTRACT NO.

More information

Proposed Capital Improvement Program (CIP) for FY 2015-2019

Proposed Capital Improvement Program (CIP) for FY 2015-2019 RELATED TO AGENDA ITEM 17 Proposed Capital Improvement Program (CIP) for FY 2015-2019 February 20, 2014 Presentation Overview Planning Agency roles District s capital needs Bridge funding plan Capital

More information

Agenda. Planning and Programming Committee Meeting. Wednesday, January 16, 2008 1:00 P.M. One Gateway Plaza 3rd Floor Boardroom.

Agenda. Planning and Programming Committee Meeting. Wednesday, January 16, 2008 1:00 P.M. One Gateway Plaza 3rd Floor Boardroom. Wednesday, January 16, 2008 1:00 P.M. Agenda Planning and Programming Committee Meeting One Gateway Plaza 3rd Floor Boardroom Call to Order Directors Yvonne B. Burke, Chair Zev Yaroslavsky, Vice Chair

More information

-25 A-se =, zai,*,:.-.a -322-295;

-25 A-se =, zai,*,:.-.a -322-295; Los Angeles County Service Authority for Freeway Emergencies %'a- 6' B d,-a 2. *&a, -j 1-a -25 A-se =, zai,*,:.-.a -322-295; I SAFE BOARD MEETING JUNE 28,2012 SUBJECT: ACTION: ADOPT THE FISCAL YEAR 201

More information

TRANSITION OF TAP CALL CENTER AND REDUCED FARE APPLICATION SERVICES FROM XEROX TO METRO IN-HOUSE

TRANSITION OF TAP CALL CENTER AND REDUCED FARE APPLICATION SERVICES FROM XEROX TO METRO IN-HOUSE 54 One Gateway Plaza 213 9 Los Angeles, CA 90012-2952 metro. net EXECUTIVE MANAGEMENT COMMITTEE JULY18,2013 SUBJECT: ACTION: TRANSITION OF TAP CALL CENTER AND REDUCED FARE APPLICATION SERVICES FROM XEROX

More information

When is BRT the Best Option? 1:30 2:40 p.m.

When is BRT the Best Option? 1:30 2:40 p.m. TRB/APTA 2004 Bus Rapid Transit Conference When is BRT the Best Option? 1:30 2:40 p.m. Paul Larrousse Director, National Transit Institute (NTI) (Moderator) TRB/APTA 2004 Bus Rapid Transit Conference Session

More information

CHAPTER 8 CIVIL DESIGN

CHAPTER 8 CIVIL DESIGN CHAPTER 8 CIVIL DESIGN A. GENERAL This Chapter includes standards and design considerations for other civil engineering design in structural, drainage and utilities. Design considerations for electrical

More information

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT

CRENSHAW/LAX TRANSIT CORRIDOR PROJECT CRENSHAW/LAX TRANSIT CORRIDOR PROJECT A New Beginning for the Crenshaw Corridor Through Use of Innovative Procurement Strategies Robert Ball, P.E. and Kimberly Ong, P.E. Los Angeles Metropolitan Transportation

More information

PROGRAM SUPPORT- EMPLOYER ANNUAL PASS PROGRAMS AWARD CONTRACT TO INLAND TRANSPORTATION SERVICES

PROGRAM SUPPORT- EMPLOYER ANNUAL PASS PROGRAMS AWARD CONTRACT TO INLAND TRANSPORTATION SERVICES 5 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net FINANCE, BUDGET & AUDIT COMMITTEE FEBRUARY 18, 2015 SUBJECT: ACTION: PROGRAM SUPPORT- EMPLOYER ANNUAL PASS PROGRAMS AWARD CONTRACT

More information

HASTUS SYSTEM v2014 SOFTWARE UPGRADE APPROVE CONTRACT PS92403192 AWARD TO GIRO, INC.

HASTUS SYSTEM v2014 SOFTWARE UPGRADE APPROVE CONTRACT PS92403192 AWARD TO GIRO, INC. One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2ooo Tel metro. net SYSTEM SAFETY SECURITY AND OPERATIONS COMMITTEE SEPTEMBER 18,2014 SUBJECT: ACTION: HASTUS SYSTEM v2014 SOFTWARE UPGRADE APPROVE

More information

Project Management Manual. Volume 1: PM Desk Book

Project Management Manual. Volume 1: PM Desk Book Project Management Manual Volume 1: PM Desk Book Revision 0: July 15, 2011 THE PROJECT MANAGER S TEN COMMANDMENTS PROJECT MANAGERS SHALL: 1. Draft the Project Charter to define the scope, schedule, budget,

More information

..."... Cou"" Metro M"'"'""""'"r"...,..."..., SYSTEMS SAFETY AND OPERATIONS COMMITTEE APRIL 18, 2013 DIVISION 11 WATER MITIGATION

...... Cou Metro M'''r...,......, SYSTEMS SAFETY AND OPERATIONS COMMITTEE APRIL 18, 2013 DIVISION 11 WATER MITIGATION ..."... Cou"" Metro M"'"'""""'"r"...,....."..., One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro.net 34 SYSTEMS SAFETY AND OPERATIONS COMMITTEE APRIL 18, 2013 SUBJECT: ACTION: DIVISION

More information

Planned Safety and Security Systems. Jon Tapping, Director of Risk Management Board Meeting: Agenda Item 4 August 4, 2015 Sacramento, CA

Planned Safety and Security Systems. Jon Tapping, Director of Risk Management Board Meeting: Agenda Item 4 August 4, 2015 Sacramento, CA Planned Safety and Security Systems Jon Tapping, Director of Risk Management Board Meeting: Agenda Item 4 August 4, 2015 Sacramento, CA HIGH-SPEED RAIL: Around the World 12 Countries with High-Speed Rail

More information

MUNICIPAL OPERATORS / UFS REGIONAL CENTRAL DATA COMPUTER SYSTEM

MUNICIPAL OPERATORS / UFS REGIONAL CENTRAL DATA COMPUTER SYSTEM Metro Me'ropoU". T,,",po"";o. Auth~;" One Gateway Plaza Los Angeles, CA 90012-2952 213. 922.2000 Tel metro. net OPERATIONS COMMITTEE OCTOBER 21, 2004 SUBJECT: ACTION: MUNICIPAL OPERATORS / UFS REGIONAL

More information

Los Angeles County Service Authority for Freeway Emergencies Kenneth Hahn Call Box System

Los Angeles County Service Authority for Freeway Emergencies Kenneth Hahn Call Box System Los Angeles County Service Authority for Freeway Emergencies Kenneth Hahn Call Box System 3 S.A.F.E One Gateway Plaza Los Angeles, California 90012-2952 TEL (21 3) 922-5652 FAX (213) 922-2955 SAFE BOARD

More information

ALAMEDA CORRIDOR TRANSPORTATION AUTHORITY PROGRAM & OPERATING BUDGET

ALAMEDA CORRIDOR TRANSPORTATION AUTHORITY PROGRAM & OPERATING BUDGET ALAMEDA CORRIDOR TRANSPORTATION AUTHORITY PROGRAM & OPERATING BUDGET FISCAL YEAR 2007/2008 Adopted June 21, 2007 Table of Contents Transmittal Letter...i Policy Overview...1 Budget Development & Overview...9

More information

BID BOND. are held firmly bound unto the LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY, hereinafter called Metro, DOLLARS.

BID BOND. are held firmly bound unto the LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY, hereinafter called Metro, DOLLARS. KNOW ALL MEN BY THESE PRESENTS: THAT, and, as Principal are held firmly bound unto the LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY, hereinafter called Metro, as Surety in the sum of (use words)

More information

California State Transportation Agency Call for Projects for the. 2016 Transit and Intercity Rail Capital Program

California State Transportation Agency Call for Projects for the. 2016 Transit and Intercity Rail Capital Program California State Transportation Agency Call for Projects for the 2016 Transit and Intercity Rail Capital Program Summary: This call for projects details the application requirements and procedures for

More information

Los Angeles County One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA g0012-2g52 AWARD CONTRACT FOR AC/AIR COMPRESSORS

Los Angeles County One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA g0012-2g52 AWARD CONTRACT FOR AC/AIR COMPRESSORS 52 Los Angeles County One Gateway Plaza Metropolitan Transportation Authority Los Angeles, CA g0012-2g52 Metro OPERATIONS COMMI'ITEE JUNE 18,2009 SUBJECT: ACTION: AIR CONDITIONING (AC) AND AIR COMPRESSORS

More information

Project Management Oversight Services

Project Management Oversight Services Solicitation Number: Reference-Number-FTA-08-PMOC Project Management Oversight Services Federal Transit Administration Our fundamental business strategy is forging strong, long-term relationships with

More information

MAXIMIZING COMPETITION & EXPANDING OPPORTUNITIES FOR SMALL BUSINESS

MAXIMIZING COMPETITION & EXPANDING OPPORTUNITIES FOR SMALL BUSINESS Los Angeles County One Gateway Plaza 213.922.2000 Tel Metropolitan Transportation Authority Los Angeles, CA 90012-2952 metro.net Metro SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE MARCH 19, 2015 SUBJECT:

More information

TRAIN WRAPS TIMETABLE ADS TICKETS STATION POSTERS METROLINK MATTERS NEWSLETTER STATION SAMPLING WEBSITE: METROLINKTRAINS.COM

TRAIN WRAPS TIMETABLE ADS TICKETS STATION POSTERS METROLINK MATTERS NEWSLETTER STATION SAMPLING WEBSITE: METROLINKTRAINS.COM METROLINK MATTERS TIMETABLES METROLINKTRAINS.COM HOW-TO-RIDE GUIDE DESTINATION GUIDE TICKETS TRAIN WRAPS STATION POSTERS ON-BOARD BANNERS & POSTERS STATION SAMPLING ADVERTISING RATES & INFORMATION METROLINK

More information

CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP)

CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP) Local Assistance Program Guidelines Chapter 4 CHAPTER 4 SURFACE TRANSPORTATION PROGRAM (STP) CONTENTS Section Subject Page Number 4.1 INTRODUCTION... 4-1 4.2 ELIGIBILITY CRITERIA... 4-1 General... 4-1

More information

Metropolitan Transportation Authority One Gateway Plaza 213.g22.2000 Tel. Los Angeles, CA 90012-2952 metro.net

Metropolitan Transportation Authority One Gateway Plaza 213.g22.2000 Tel. Los Angeles, CA 90012-2952 metro.net Metro Metropolitan Transportation Authority One Gateway Plaza 213.g22.2000 Tel Los Angeles, CA 90012-2952 metro.net OPERATIONS COMMITTEE JANUARY 17,2008 45 SUBJECT: ACTION: PEST CONTROL SERVICES, CONTRACT

More information

Metro. METRO SERVICE AREA Downtown. DowntownISan Gabriel Valley West Los Angeles South BayILong Beach San Fernando Valley

Metro. METRO SERVICE AREA Downtown. DowntownISan Gabriel Valley West Los Angeles South BayILong Beach San Fernando Valley Metro Los Angeles County One Gateway Plaza ZI~.~ZZ.ZOO( Metropolitan Transportation Authority Los Angeles, CA 90012-2952 rnetro.net EXECUTIVE MANAGEMENT COMMITTEE JANUARY 19,2012 SUBJECT: MEDICAL CLINIC

More information

Request for Proposals July 13, 2015

Request for Proposals July 13, 2015 Maintenance and Skilled Trades Division Request for Proposals July 13, 2015 District Wide Pavement Assessment The East Bay Regional Park District ( District ) is soliciting proposals from consultants to

More information

RESOLUTION NO. 2012-1 8 BOARD OF DIRECTORS, PENINSULA CORRIDOR JOINT POWERS BOARD STATE OF CALIFORNIA ***

RESOLUTION NO. 2012-1 8 BOARD OF DIRECTORS, PENINSULA CORRIDOR JOINT POWERS BOARD STATE OF CALIFORNIA *** RESOLUTION NO. 2012-1 8 BOARD OF DIRECTORS, PENINSULA CORRIDOR JOINT POWERS BOARD STATE OF CALIFORNIA *** AUTHORIZING APPROVAL OF THE HIGH-SPEED RAIL EARLY INVESTMENT STRATEGY FOR A BLENDED SYSTEM MEMORANDUM

More information

Railway Age, Passenger Trains on Freight Railroads. Negotiating Insurance and Liability Issues: Constructive Solutions. October 21-22, 2008

Railway Age, Passenger Trains on Freight Railroads. Negotiating Insurance and Liability Issues: Constructive Solutions. October 21-22, 2008 Railway Age, Passenger Trains on Freight Railroads Negotiating Insurance and Liability Issues: Constructive Solutions October 21-22, 2008 Kevin M. Sheys 1 My topic today is Constructive Solutions for Negotiating

More information

Establish a life of project budget for the Metro Information Security Improvement Program in the amount of $7,814,000. The FY16 portion is $860,000.

Establish a life of project budget for the Metro Information Security Improvement Program in the amount of $7,814,000. The FY16 portion is $860,000. 25 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net SYSTEM SAFETY, SECURITY & OPERATIONS COMMITTEE MARCH 19, 2015 SUBJECT: ACTION: INFORMATION SECURITY IMPROVEMENT PROGRAM APPROVE

More information

CITY OF BAYTOWN Building Inspections

CITY OF BAYTOWN Building Inspections CITY OF BAYTOWN Building Inspections PERMIT SCHEDULE Residential Building Permit Fees Sec. 18-127. (a) Any person applying to the city for a building permit shall pay to the city, prior to the issuance

More information

EXECUTIVE MANAGEMENT COMMITTEE FEBRUARY 21, 2013 BOARDROOM AUDIO-VIDEO SYSTEM UPGRADE AWARD CONTRACT ACTION: RECOMMENDATION

EXECUTIVE MANAGEMENT COMMITTEE FEBRUARY 21, 2013 BOARDROOM AUDIO-VIDEO SYSTEM UPGRADE AWARD CONTRACT ACTION: RECOMMENDATION 53 One Gateway Plaza Los Angeles, CA 90012-2952 213-922.2000 metro. net EXECUTIVE MANAGEMENT COMMITTEE FEBRUARY 21, 2013 SUBJECT: ACTION: BOARDROOM AUDIO-VIDEO SYSTEM UPGRADE AWARD CONTRACT RECOMMENDATION

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 11 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. The selected firm is referred to herein as either the Consultant or the

More information

Introduction to Station Area Planning The Charlotte Story

Introduction to Station Area Planning The Charlotte Story Introduction to Station Area Planning The Charlotte Story Boston 2009 Steve Hamwey - Sasaki Associates, Inc. Troy Russ - Glatting Jackson, Inc. October 31 st, 2009 Station Area Planning October 15th History

More information

MODIFICATION NO. 3 TO CONTRACT NO. PS-6810-1282 WITH TRANSPORTATION RESOURCE ASSOCIATES

MODIFICATION NO. 3 TO CONTRACT NO. PS-6810-1282 WITH TRANSPORTATION RESOURCE ASSOCIATES Metro Met"'poll',. T,,",po.',"o. Authority One Gateway Plaza Los Angeles, CA 90012-2952 213. 922. 2000 Tel metro. net OPERATIONS COMMITTEE MAY 20, 2004 SUBJECT: ACTION: MODIFICATION NO. 3 TO CONTRACT NO.

More information

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Informational Workshop Public Meeting Kanawha Falls Bridge Project Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal

More information

DATE ISSUED: February 19 2015 REPORT NO. 201 (REVISED) San Diego Regional Park Improvement Fund Oversight Committee Agenda of February 19 2015

DATE ISSUED: February 19 2015 REPORT NO. 201 (REVISED) San Diego Regional Park Improvement Fund Oversight Committee Agenda of February 19 2015 DATE ISSUED: February 19 2015 REPORT NO. 201 (REVISED) ATTENTION: SUBJECT: San Diego Regional Park Improvement Fund Oversight Committee Agenda of February 19 2015 Quarterly Projects Update - Allocation

More information

ACQUISITION OF COMPUTER HARDWARE, SOFTWARE AND SERVICES

ACQUISITION OF COMPUTER HARDWARE, SOFTWARE AND SERVICES Metro Met..po'"'" T""'porta"O" Autho." One Gateway Plaza Los Angeles, CA 90012-2952 213. 922. 2000 - metro. net FINANCE & BUDGET COMMITTEE AUGUST 19, 2004 SUBJECT: ACTION: ACQUISITION OF COMPUTER HARDWARE,

More information

AWARD AND APPROVAL OF CONSTRUCTION CONTRACT CONTRACTOR: JOHNSON-PELTIER ELECTRICAL CONTRACTOR

AWARD AND APPROVAL OF CONSTRUCTION CONTRACT CONTRACTOR: JOHNSON-PELTIER ELECTRICAL CONTRACTOR THE PORT OF LOS ANGELES Executive Director's Report to the Board of Harbor Commissioners DATE: MAY 24, 2016 FROM: CONSTRUCTION RESOLUTION NO. AWARD AND APPROVAL OF CONSTRUCTION CONTRACT CONTRACTOR: JOHNSON-PELTIER

More information

Integrating State of Good Repair with PPP s

Integrating State of Good Repair with PPP s Los Angeles County Metropolitan Transportation Authority Integrating State of Good Repair with PPP s NCPPP Conference San Diego, California, July 7-8, 2009 Denise L. Longley Deputy Executive Officer, Facilities-Operations,

More information

Los Angeles San Diego. Coastal Rail Corridor. San Diego Segment. Building Today. Boarding Tomorrow.

Los Angeles San Diego. Coastal Rail Corridor. San Diego Segment. Building Today. Boarding Tomorrow. LOSSANSan Luis Los Angeles San Diego Obispo Coastal Rail Corridor San Diego Segment Building Today. Boarding Tomorrow. Building Today Boarding Tomorrow LOSSAN Los Angeles, San Diego, San Luis Obispo Coastal

More information

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015

Expo Light Rail Line. Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Board Presentation Monthly Project Status Update May 7, 2015 Expo Phase 1 Phase 1 Project Status Closeout Status Completing Closeout of Remaining Elements of Work Final As-Builts nearing completion

More information

EXHIBIT "A" INSURANCE REQUIREMENTS FOR RIGHT OF ENTRY AGREEMENTS

EXHIBIT A INSURANCE REQUIREMENTS FOR RIGHT OF ENTRY AGREEMENTS EXHIBIT "A" INSURANCE REQUIREMENTS FOR RIGHT OF ENTRY AGREEMENTS Contractor shall procure and maintain for the duration of the contract insurance against claims for injuries to persons or damages to Property,

More information

DESIGN-BUILD IN CALIFORNIA

DESIGN-BUILD IN CALIFORNIA DESIGN-BUILD IN CALIFORNIA 1. Why Design-Build Design Build Drivers, Goals and Challenges (see Reed Construction Data and DGS handouts) 2. Who Can Do Design-Build Design-Build Authorizing Statutes for

More information

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing.

Date. Resubmit this form during the year if there are changes in your company ownership or financial standing. COLORADO DEPARTMENT OF TRANSPORTATION CONTRACTOR PREQUALIFICATION STATEMENT (EXPERIENCE, EQUIPMENT AND FINANCIAL) Return to: Contracts & Market Analysis Prequalification Unit 4201 E. Arkansas,4th Floor

More information

TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION

TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION TOWNSHIP OF BRIGHTON REQUEST FOR PROPOSALS SANITARY SEWER REPAIRS AND/OR GRINDER PUMP INSTALLATION April 25, 2014 DUE DATE/LOCATION: Friday, May 9, 2014 Bid forms and references are due by 9:30 A.M. at:

More information

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain

Effect on structures. Uniform settlement - no concerns. Angular distortion - causes damage due to tensile strain Effect on structures Uniform settlement - no concerns Angular distortion - causes damage due to tensile strain 1/500 - safe limit for no cracking of buildings 1/150 - potential structural damage 36 37

More information

County Of Sonoma Agenda Item Summary Report

County Of Sonoma Agenda Item Summary Report County Of Sonoma Agenda Item Summary Report Department: General Services Contact: Rob Kambak Phone: (707) 565-3211 Board Date: 10/27/2009 4/5 Vote Required Deadline for Board Action: AGENDA SHORT TITLE:

More information

metro funding sources guide 12-2341tr 2012 LACMTA

metro funding sources guide 12-2341tr 2012 LACMTA 2012 metro funding sources guide 12-2341tr 2012 LACMTA TABLE OF CONTENTS INTRODUCTION... 4 EXECUTIVE SUMMARY... 5 SECTION I Listing of Local, State, and Federal Funding Sources and Major Funding Sources

More information

21101 &?I I2 P 3: 2 I. kz COZY c:oi*;: iiss:en. DOCEET COEi1 f3.x..

21101 &?I I2 P 3: 2 I. kz COZY c:oi*;: iiss:en. DOCEET COEi1 f3.x.. I l1111111 I AI Il1 l1ul I 111l Il 1111 0000072925 Sta m RR-026358-07-0222 j7 i O lo: THE COMMISSION From: Safety Division Date: June 12,2007 21101 &?I I2 P 3: 2 I kz COZY c:oi*;: iiss:en DOCEET COEi1

More information

CONVENIENCE COPYING, PRINT MANAGEMENT AND DOCUMENT MANAGEMENT SERVICES

CONVENIENCE COPYING, PRINT MANAGEMENT AND DOCUMENT MANAGEMENT SERVICES 0 Metro Los Angeies County One Gateway Plaza 213.gz2.z000 Tel Metropolitan Transportation Authority Los Angeles, CA gooi2-zg~2 metro.net OPERATIONS COMMITTEE SEPTEMBER 16,2010 SUBJECT: ACTION: CONVENIENCE

More information

FREIGHT RAILROAD PRESERVATION PROGRAM SFY 2017 PART I - APPLICATION INSTRUCTIONS

FREIGHT RAILROAD PRESERVATION PROGRAM SFY 2017 PART I - APPLICATION INSTRUCTIONS FREIGHT RAILROAD PRESERVATION PROGRAM SFY 2017 SECTION 1.0 INTRODUCTION PART I - APPLICATION INSTRUCTIONS The Freight Railroad Preservation Program (FRPP) documents are composed of four parts. Part I contains

More information

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE FEBRUARY 19, 2015 EXERCISE OPTION FOR 350 NEW FLYER BUSES RECOMMENDATION

SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE FEBRUARY 19, 2015 EXERCISE OPTION FOR 350 NEW FLYER BUSES RECOMMENDATION 23 One Gateway Plaza Los Angeles, CA 90012-2952 213.922-2ooo Tel metro. net SYSTEM SAFETY, SECURITY AND OPERATIONS COMMITTEE FEBRUARY 19, 2015 SUBJECT: ACTION: REPLACEMENTBUSES EXERCISE OPTION FOR 350

More information

Quality and Productivity Commission 22 ND Annual Productivity and Quality Awards Program The Power of Productivity

Quality and Productivity Commission 22 ND Annual Productivity and Quality Awards Program The Power of Productivity Quality and Productivity Commission 22 ND Annual Productivity and Quality Awards Program Date of Implementation/Adoption: March 2006 Project Status: Ongoing One-time only Did you submit this project before?

More information

Overview of Proposition 1 TRACIE BILLINGTON, CHIEF FINANCIAL ASSISTANCE BRANCH DIVISION OF INTEGRATED REGIONAL WATER MANAGEMENT

Overview of Proposition 1 TRACIE BILLINGTON, CHIEF FINANCIAL ASSISTANCE BRANCH DIVISION OF INTEGRATED REGIONAL WATER MANAGEMENT 1 Overview of Proposition 1 TRACIE BILLINGTON, CHIEF FINANCIAL ASSISTANCE BRANCH DIVISION OF INTEGRATED REGIONAL WATER MANAGEMENT Proposition 1 2 Sections 1-7 Reallocates Statewide Bond Costs from prior

More information

Transit, Rail, Program, Project & Construction Management Experience

Transit, Rail, Program, Project & Construction Management Experience Point of Contact Peter M. Cipolla Vice President, Rail & Transit Mobile: 925.219.5235 Email: peter.cipolla@hatchmott.com Project Management Oversight Services Introduction & Background Hatch Mott MacDonald

More information

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future

More information

REGIONAL INTERMODAL TRANSPORTATION CENTER AT THE BURBANK-BOB HOPE AIRPORT

REGIONAL INTERMODAL TRANSPORTATION CENTER AT THE BURBANK-BOB HOPE AIRPORT APRIL MAY 2015 REGIONAL INTERMODAL TRANSPORTATION CENTER AT THE BURBANK-BOB HOPE AIRPORT TICKETING UPDATE REGIONAL INTERMODAL SAFETY & SECURITY INSIDE 2 3 4 BIKE TO WORK 5 SERVICE COMING TO PERRIS VALLEY

More information

GENERAL. This manual addresses five local programs that are funded under the current Highway Act:

GENERAL. This manual addresses five local programs that are funded under the current Highway Act: OVERVIEW The Local Public Agency Manual published by the Missouri Department of Transportation (MoDOT) is intended to be used as a guide for cities and counties that sponsor projects utilizing federal

More information

SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development

SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development Draft 06162009 SCOPE OF WORK for High Speed Rail and Intercity Passenger Rail Program Federal Grant Application Development The Minnesota Department of Transportation (Mn/DOT) requires the services of

More information

RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS

RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS RPA 14/ATURA Surface Transportation Program (STP) APPLICATION FOR FUNDS Please provide the following information when applying to RPA 14/ATURA for Surface Transportation Program (STP) funding for projects

More information

February 17, 2011. ADDENDUM #2 Invitation for Bid (IFB) CN100434 Translation Services Clearinghouse for Multilingual Documents IFB

February 17, 2011. ADDENDUM #2 Invitation for Bid (IFB) CN100434 Translation Services Clearinghouse for Multilingual Documents IFB February 17, 2011 ADDENDUM #2 Invitation for Bid (IFB) CN100434 Translation Services Clearinghouse for Multilingual Documents IFB To all Prospective Bidders this addendum includes Questions and Answers

More information