The ERP Project Risk Assessment A case study
|
|
|
- Cordelia Walsh
- 10 years ago
- Views:
Transcription
1 The ERP Project Risk Assessment A case study Päivi Iskanius Abstract Information and communication (ICT) technology related projects, such as enterprise resource planning (ERP) projects have a high failure rate. Planned and systematically adopted risk management procedure is crucial to keep projects on time and within budget with all requirements fulfilled. In this paper, we have analysed the critical risks of ERP projects through the case study of three manufacturing small and medium size enterprises (SMEs). First, by using company-specific risk analysis method, the critical risks of the ERP projects have been identified and assessed. Second, by using characteristics analysis method, the recommendations of how to divide the ERP projects into manageable sub projects have been given. Index Terms Enterprise resource planning, risk analysis method, characteristics analysis method, small and medium sized enterprise. I. INTRODUCTION Enterprise resource planning (ERP) systems, when successfully implemented, links all functions of an organisation including order management, manufacturing, human resources, financial systems, and distribution with external suppliers and customers into a tight integrated system with shared data and visibility [1]. The primary motive for ERP implementation is the potential for enhancing the firm s competitiveness. ERP systems provide significant benefits, and companies adopted them with the goal of replacing inefficient stand-alone legacy systems, increasing communications between business functions, increasing information processing efficiencies, improving customer relations, and improving overall decision making [2]. Despite the significant benefits that ERP systems provide, the Statistics show that under 30 % of ERP implementations are successful [3], which means that projects are completed on time and on budget, with all features and functions originally specified. ERP projects are major and risky exercises for any size of company. The average implementation time of ERP system is between 6 months and 2 years [4] and the average cost is between US$1,3M and US$70M [5], and they require disruptive organisational change [4]. ERP implementation requires the allocation of special competences, and a number of financial and human resources. Also, the implementation is usually carried out concurrently with the daily business, which already ties up the available resources [5]. Especially in small and medium size enterprises (SMEs), which employ less than 250 persons and an annual turnover is not exceeding 50 M, and/or an annual balance sheet total is not exceeding 43 M, scarce Manuscript received March 2, P. Iskanius is with the Raahe Unit, University of Oulu, Oulu, Finland. (phone: ; fax: + 358; paivi,[email protected]). resources are badly needed in the daily business operations. Risks are part and parcel of ERP projects, but a planned and systematically adopted risk management procedure throughout the implementation project reduces the possibility of risks occurring. The risks are higher for SMEs as the cost overruns during implementation may put financial strain on the firm and thus substantially impact firm performance [2]. In addition, SMEs have less of a chance of recovering from a failed ERP implementation attempt than large enterprises [6]. Several standardised tools and methods have been developed to help companies to better manage their ERP projects. In this study, we present experiences of company-specific risk analysis method (RAM) and characteristics analysis method (CAM) through the case study of three manufacturing SMEs. First, by using RAM, the critical risks of the ERP projects are identified and assessed. Second, by using CAM, the recommendations of how to divide the ERP projects into manageable sub projects are given. II. RISK ASSESSMENT A. ERP project risks Several research studies have investigated the ERP risks and have attempted to classify them in various ways. Six main dimensions of risk in ERP implementation have been identified by [7], namely, 1) organizational, 2) business-related, 3) technological, 4) entrepreneurial, 5) contractual and 6) financial risks. Organizational risk derives from the environment in which the system is adopted. Business-related risk derives from the enterprise s post-implementation models, artifacts, and processes with respect to their internal and external consistency. Technological risk is related to the information processing technologies required to operate the ERP system for example the operating system, database management system, client/server technology and network. Entrepreneurial or managerial risk is related to the attitude of the owner-manager or management team, while contractual risk derives from relations with partners and financial risk from cash-flow difficulties, resulting in an inability to pay license fees or upgrading costs, for example. [7] In the research of [8], following six risk categories have been presented: 1) organizational fit, i.e. failure to redesign business processes, 2) skill mix, i.e. insufficient training and reskilling, 3) management structure and strategy, i.e. lack of top management support, 4) software systems design, i.e. lack of integration, 5) user involvement and training, i.e. ineffective communication, and 6) technology planning/integration, i.e. inability to avoid technological bottlenecks. Later, [9] develop the risk identification list based on the category of [8].
2 The following ERP risk factors are summarised by [4]: 1) inadequate ERP selection, 2) poor project team skills, 3) low top management involvement, 4) ineffective communication system, 5) low key user involvement, 6) inadequate training and instruction, 7) complex architecture and high numbers of modules, 8) inadequate business processes, 9) bad managerial conduction, 10) ineffective project management techniques, 11) inadequate change management, 12) inadequate legacy system management, 13) ineffective consulting services experiences, 14) poor leadership, 15) inadequate ICT system issues, 16) inadequate ICT system manutenibility, 17) inadequate ICT supplier stability and performances, 18) ineffective strategic thinking and planning, 19) inadequate financial management. Instead of using abovementioned ready-made risk lists, a company might consider identifying their own, company-specific ERP implementation risk list. These risks could be complemented by common risk lists. To minimize the risk of the ERP project, [10] have recommended the application of a risk management plan at different ERP implementation project stages; selection, implementation, and usage. A planned and systematically adopted risk management procedure throughout the ERP project reduces the possibility to risks occurring. Consequently, [11] suggest that major mistakes are made in the early stages of the ERP project, even prior to the implementation process. [12], however, emphasizes the efficiency of risk management when it is introduced at the earliest possible opportunity in the life cycle of the system in question, when planning issues are most important and the criteria for system selection are determined. This research has been carried out as a case study of three manufacturing SMEs. The case SMEs are in different phases of the ERP project. Company A is still contemplating the ERP implementation, Company B is in the selection phase, and Company C is already in the usage phase. In practice, this study has been carried out during B. Risk analysis method Risk analysis method (RAM) identifies the most essential risks and their probability in the company context. The risk list for the case study has been formed based on the risk list of [5]. In this paper, the risk list is formed out of 63 questions or statements dealing with the ERP selection, implementation, and usage. The basic aim is to identify the ERP risks arising from the company s reality and therefore the employees from various levels of organisation have been interviewed and observed. The company-specific risk list has been filled in close interaction with company personnel. Risk assessment for the risk list is done by evaluating each risk s probability and effect in a scale from one to five. The number one means very small probability and effect, and number five means high probability and catastrophic effect. Then, the risk multiplication as an indicator of risk significance has been used. It is calculated as multiplying the value of the probability by the value of the effect. Range of this value is from one to twenty-one. [5] C. Characteristics analysis method Characteristics analysis method (CAM) is a tool to ensure that the information and technology (ICT) project is manageable and consistent by its different goals content and development approaches. The result of the CAM is a recommendation of how to split the large and complex ICT project into manageable sub projects. Further, the inputs of the CAM are the project proposition document, the knowledge and experience from prior development projects, and the requirements of the of the project portfolio. [13] In this paper, the CAM analysis is formed out of 90 questions dealing with the ICT project. The basic aim is to find out the manageable size of the ERP project of the case company. Also, CAM provides recommendations what management aspects should be put more attention to successfully manage ERP project (management of a project as a whole, management of integration, project scope management, time management, cost management, quality management, human resource management, management of communication, risk management, management of purchase). The questions are either positive or negative statements for which their applicability to the project will be evaluated (0 = fault, not true, 5 = exactly right; N/A = don t know). The tool has been implemented as an MS Excel worksheet with automatic tabulation based on decision rule sets. The result can also be illustrated graphically (see figures 1 and 2). [13] III. CASE STUDY A. Case 1: Company A Company A develops blast cleaning technology and manufactures automated blast cleaning machines and robots (turnover about 1,2 M and number of personnel approximately 20). Company A has not an ERP system, but is contemplating the ERP implementation in near future. The need for the new ERP system has grown internally because of the problems in the current ICT system. Today, the company is using an excel-based ICT system, which includes e.g. the following ERP functions: customer relationship management (CRM), product data management (PDM), purchase and order management, and product lifespan management. The problem of the current system is how to manage over 100 different versions and variations of Excel, Word, and AutoCAD documents. Main problems occur in the tendering and purchase processes, and in the production capacity planning. The purpose of company A is to adopt an ERP system, which helps production capacity planning and control so that the scheduling and resource allocation for different projects can be planned in detail before the project is started. Furthermore, the new system should include warehouse and stock management functions, and it have to support purchase process. The risk list has been filled with company personnel and the effect and probability of risks have been assessed. In the ERP selection phase, the most critical risks which may be realised in company A are: misunderstanding between buyer and customer (12), system not flexible enough under processes exceptional circumstances (12), and special needs of a company not defined (10). In the ERP installation phase, the most critical risks are: company s project manager is not a full time PM (20), data transfers from old to new system is difficult (16), connecting system to other systems creates
3 problems (16), and supplier is not committed enough to system implementation (15). In the ERP usage phase, the most critical risks are: system not felt as helping the business (12) and the system supplier does not develop the system in the future (10). Company A is just contemplating to acquire an ERP system. In the RAM results, in every phase (selection, implementation, usage), the crucial factors are depended on the decision of the ERP system itself and the ERP supplier. The technical and functional factors related to the system, and the factors related the chosen system supplier, are considered the most critical. Even a company A has very few employees (under 20), the lack of resource, skills and expertise, and other factors related personnel have - surprisingly not aroused as a potential risk in this analysis. The results analysed by CAM is presented in Figure 1. Purchase Risk Communication Human Resource of the ERP project as a whole Figure 1. CAM diagram of the company A 5,0 4,0 3,0 2,0 1,0 0,0 Quality Integration Project Scope Time Cost MA AVERAG CRITICAL LEVEL According to CAM, Human Resource is the management/leadership field that clearly exceeds the critical level. Company A should direct special attention to this factor in ERP project management. In addition, several other management/leadership fields, such as Communications, Purchase, The project as a whole, Integration, Project Scope and Quality are right at the critical level. Only Cost and Time and Risk are clearly under critical level. According to CAM, factors connected with personnel training and increasing personnel skills and knowledge require more from managing the ERP project, although they are not considered to be amongst the most potential risk factors according to RAM. On the basis of the CAM, it can be deduct that Company A has a clear view of the costs caused by the ERP project, the time spent for it, as well as the technical and operational risks involved. B. Case 2: Company B Company B provides demanding sheet metal work, welding, and heavy metal works, specialising in steel, paper, chemistry, and ship manufacturing related machinery and equipment. In addition, the company manufactures offshore equipment and ship propellers. The company, founded in 1974, currently employs ca. 150 people. Company B is in the selection phase of the ERP project. The company has interviewed several ERP suppliers. The company has already gone through more detailed discussions with two potential suppliers. The company has made a preliminary requirement specification, a type of demand list, through which they are able to limit their ERP suppliers to two options. Also, some consultants have worked for the company. Company B is very aware that the existing ICT systems are already in the end of their life cycle, and they had to invest in a new ERP system. The risk list has been filled with company personnel and the effect and probability of risks have been assessed. In the ERP selection phase, the most critical risks which may be realised in company B are: system is poor compromise for all parties (12), choosing poor project manager or project group, and misunderstandings between buyer and customer (10), choosing improper ERP system (10). In the ERP installation phase, the most critical risks are: normal business disturbs ERP project activities (20), ERP project disturbs normal business (16), timetable falls behind schedule (16), Software configuration and testing don t function swiftly (16), disciplined use of the system (data entry is not achieved) (16). In the ERP usage phase, the most critical risks are: ERP system not used in a disciplined manner (12), and only part of the system used and benefits realized (12). Company B is in the selection phase of the ERP project. In the RAM results, the crucial factors are mostly depended on the personnel (including project manager/team and top management level) behavior, skills, and experience. Company B is also worried of the changes what the new ERP system will affect to the company s normal business, and in opposite, how the normal business hinders the ERP project progress. The results analysed by CAM; is presented in the figure 2. Risk Communication of the ERP project as a whole Purchase Human Resource 5,0 4,0 3,0 2,0 1,0 0,0 Quality Figue 2. CAM diagram of the company B Integration Project Scope Time Cost MA AVERAG CRITICAL LEVEL According to RAM, Communications is the management/leadership field that clearly exceeds the critical level. Company B should direct special attention to the factor considered people skills, knowledge and expertise. In
4 addition, Human Resource and Quality are right at the critical level. To manage ERP project successfully, the company should pay attention to these three management/leadership factors. C. Case 3: Company C Company C has implemented an ERP system a few years ago but only part of the system was functioned complete. Company C is going to continue the ERP project and adopt several new functions of the ERP system in use. The risk list has been filled with company personnel and the effect and probability of risks have been assessed. The risk analysis has been done focusing on the main risks considered the new modules adoption. Also, because the company C already has the ERP system in use, the selection phase was skipped. In the ERP installation phase, the most critical risks which may be realised in company C are: normal business disturbs ERP project activities (25), cost rise compared to initial estimations (25), supplier is not committed enough to system implementation (25), software configuration and testing don t function swiftly (25), company is not important customer for supplier and don t get the best effort (25), and supplier don t understood the customer needs (25). In the ERP usage phase, the most critical risks are: all needed information is not entered into the system (15), only part of the system used and benefits realized (12), and system not felt as helping the business (12). Company B estimates several risks and their probability with maximum rates. This estimate is possibly coloured by the partial failure of their old ERP project, and the communication difficulties they experienced with their ERP supplier. Company B also has few employees (under 20), and when the contact person of the system supplier disappeared in the middle of the project, the risks came true. The CAM was not carried out in the company B, since they were already at the usage phase of their ERP project. Main usage phase problems occur because of the poor requirements specification phase, and lack of documentations in the implementation phase related to configuration and parameterisation. Also, the key person of the ERP vendor shifted to another company middle of the project. IV. DISCUSSION The ERP project should not be viewed merely as a project of acquiring and implementing a new ICT system but as a framework project for the company s all business processes. According to [14], twofold approaches should be taken for ERP projects: 1) Change the business processes to fit the software with minimal customisation. On one hand, fewer modifications to the software application should reduce errors and help to take advantage of newer versions and releases On the other hand, this choice could mean changes in long-established ways of doing business (that often provide competitive advantage), and could shake up important people roles and responsibilities; and 2) modify the software to fit the processes. This choice would slow down the project, could affect the stability and correctness of the software application and could increase the difficulty of managing future releases, because the customizations could need to be torn apart and rewritten to work with the newer version. Conversely, it implies less organizational changes, because it does not require dramatically changing the company best practices, and therefore the way people work. SME companies usually have great difficulties in their ERP through. The most common risk that may entail project failure is the ubiquitous lack of resources and IT skills or the company personnel [2]. ERP systems are typically designed for large companies, and the ERP suppliers do not necessarily understand the special characteristics and operational processes of small companies [11]. The success of an ERP project also largely depends on how well SMEs can manage changes in their business and how well personnel can adopt new way of operations. This change process is best to start already in the early phase of the ERP project, because many risks can be eliminated before the ERP project system starts. The SMEs can e.g. hire temporary staff to perform the routine operations so the key persons get more time to concentrate on the ERP system characteristics and new work practices. The most potential risks can be divided in the following categories: the ERP supplier, the ERP system, and the customer company. The most potential risk related to the ERP supplier, is simple to choose the wrong supplier, which doesn t understand the company s special demands, or are not interested enough to committed to the ERP project of small customer. Also, the high potential risk is that the ERP supplier chosen ends the development and/or support of the system. Most potential risks related to the ERP system are depended on its technical and functional performance and features; how well the system can be implemented, configured, parameterised, and integrated. Most potential risks related to the company are connected with the factors of company personnel and company top management; their skills, knowledge, and experience. Also, resistance to change is a typical potential risk factor. Personnel may not see the benefits of the system in their own work and, thus, are not committed to the new business model, and don t use the system in a disciplined manner. Normal business also disturbs the ERP implementation, and personnel may be unwilling to put time or effort to the development work. Top management support to the project is the most important success factor for the ERP project [15]. The second success factor is the proper project manager [4]. According to the CAM, the biggest investments in terms of bringing the ERP project to the finish line should be directed at Human Resource and Communications. In such a large change project the challenge is to make the employees stand behind the change. The acquisition of an ERP system includes within it changes for the company modes of operation and processes. For this reason the commitment of staff should be strong, so that new operational models are taken into use and the system can therefore be exploited to its full potential. The risk of sticking to old ways of doing things after system implementation is often high. People are experts at finding reasons why there is no need to change things or why it is better to stick to the old way of doing things, when they do not fully understand the purpose for the change. The change process is as a ground rule condemned to failure if people do not understand the need for change. For this reason it is important to create a
5 clear vision of the desired change and to communicate this really actively to the people involved in the change. In a long ERP project it is also important to obtain short-term successes so that people do not lose interest in the change process and the final aims are reached. Hence, it is good to divide the project into smaller part projects. It is typical for change processes that a process is declared a success too soon, at a stage when the first goals of the process are reached. For example, in the case of ERP projects it is erroneous to proclaim the project a success at the stage when the system they have has managed to run the system successfully and they have just started using it. Only when the system can be fully exploited and the original goals have been achieved can you consider the project to have succeeded. It is possible to enhance staff commitment to the process and the new operational model by communicating the change and by training staff. It is very typical that the need for communication and training is underestimated. The importance of communication can also be seen in the fact that communications enhance the commitment of the management level in the process. It also pays off to communicate issues during the project that are not being done. In this way you can diminish the potential of misunderstandings and to be in control of expectations. At the beginning of the ERP process it is recommended that a communications plan be drawn up, in which target groups, means and timing are outlined. In the case that everything possible in the project is outsourced the company staff will not consider the operational model to be their own. V. CONCLUSION This study presents experiences that are obtained in case studies in which three SME companies were drawn an ERP project risk analysis and characteristics analysis. The case companies considered both of the methods as good tools; they forced the company to think of the potential risks that might go off at the different stages of the ERP project, whether these risks had to do with the technical and functional characteristics of the system itself, or with the expertise and commitment of the staff, top management or ERP system vendor. The RAM presents risks in a form and language that is understandable, because the analysis have been done in the company context. As negative aspect of this RAM is that it requires a significant amount of work, and also help from external experts. The CAM helped the case companies in dividing their ERP project into manageable entities and provided them with recommendations on what leadership/management aspects they should devote special attention to. The CAM also showed inadequacies in the fields of management and leadership that the implementation of an ERP system causes in companies. Cooperation with the research group provided the companies with new skills and the drive to continue in their own ERP project. Company A will take the next step in their ERP project and is faced with an extensive requirement specification process with the objective of mapping out the suitable ERP solutions for their company and to choose their ERP in Company B aims at enhancing the system they already have in use and to adopt new modules in Company B has initiated new contacts with their system integrator/provider and commenced the change requirement specification phase of adjusting their system. Company C made their decision on which ERP system they will choose at the end stage of this research. Implementation will commence in REFERENCES [1] I.J. Chen, Planning for ERP systems: analysis and future trend, Business Process Journal, vol. 7, no. 5, pp , [2] S.J. Cereola, The performance effects of latent factors on assimilation of commercial open-source ERP software on small-medium enterprises, Virginia Commonwealth University, Richmond, Virginia, September [3] Standish Group International, Inc., 2004, The Quarter Research Report [4] D. Aloini, R. Dulmin, V. Mininno, Risk management in ERP project introduction: Review of a literature, Information &, vol. 44, pp , [5] I. Vilpola, Applying use-centered design in ERP implementation requirements analysis, Tampere University of Technology, Publication 739, Tampere, [6] J Muscatello, M. Small, I Chen, Implementing enterprise resource planning (ERP) systems in small and midsize manufacturing firms, Internationa Journal of Operations and Production, vol. 23, no. 7/8, pp , [7] P. Poba-Nzaou, L Raymond, B. Fabi, Adoption and risk of ERP systems in manufacturing SMEs. a positivist case study, Business Process Journal, vol. 14, no. 4, pp , [8] M. Sumner, Risk Factors in enterprise-wide/erp Projects, Journal of Information Technology, vol. 15, pp , [9] S.M. Huang, I.C. Chang, S.H. Li, M.T. Lin, Assessing risk in ERP projects: identify and prioritize the factors, Industrial and Data Systems, vol. 108, no. 8, pp , [10] M.L. Markus, C. Tanis, The enterprise systems experience From adoption to success, in: R.W. Zmud, (Ed.), Framing the domains of IT management: Glimpsing the future through the past, Pinnaflex, Cincinnati, OH, 2000, pp [11] E.W.N. Bernroider, M.J. Leseure, Enterprise resource planning (ERP) diffusion and characteristics according to the system's lifecycle: A comparative view of small-to-medium sized and large enterprises, Working Papers on Information Processing and Information, no. 01, Wirtschaftsuniversität Wien, Vienna. [12] R.L. Kliem, Risk management for business process reengineering project, Information Systems, vol. 17, no. 4, pp.71-73, 2000 [13] P. Forselius, Software development program characteristics, 2008, read in 2/2009 [14] R. McAdam, A. Galloway, Enterprise resource planning and organisational innovation: a management perspective, Industrial and Data Systems, vol. 105, no. 3, pp , [15] S.F. King, T.F. Burgess, Beyond critical success factors: A dynamic model of enterprise system innovation, International Journal of Information, vol. 26, pp , 2006 [16] G. Buonanno, P. Faverio, F. Pigni, A. Ravarini, D. Sciuto, M. Tagliavini,, Factors affecting ERP system adoption. A comparative analysis between SMEs and large companies, Journal of Enterprise Information, vol. 18, no. 4, pp , 2005 Päivi Iskanius, (Doctor of Technology) works as a Postdoctoral Research Fellow at the University of Oulu. She has received her Master in Mechanical Engineering in 1988, emba in 2002, Licentiate s degree in Mechanical Engineering in 2004 and Doctoral degree in Industrial Engineering and in All of these degrees are from the University of Oulu. Her research interests are logistics, supply chain management and e-business applications in the SME business networks. At present, she has over 70 research publications in these areas.
Risk Management in ERP Project in the Context of SMEs
Risk in ERP Project in the Context of SMEs Päivi Iskanius Abstract This paper contributes to the discussion on Enterprise Resource Planning (ERP) implementations in the context of small and medium size
Experiences of ERP use in small enterprises
Provided by the author(s) and NUI Galway in accordance with publisher policies. Please cite the published version when available. Title Experiences of ERP use in small enterprises Author(s) Halonen, Raija
Risks in ERP Project Case Study of IS/ICT Management Capability Maturity Level and Risk Assessment
Risks in ERP Project Case Study of IS/ICT Management Capability Maturity Level and Risk Assessment Mika Ojala 1 ; Inka Vilpola 2 Ilkka Kouri 1 1 Institute of Industrial Management, Tampere University of
Do You Need ERP? The Magnum Group Technical Publications Division
Do You Need ERP? A Cost-Benefit Analysis of ERP with Respect to Small and Medium Business Enterprises Compiled by the Database Services Division of The Magnum Group What is ERP? Today s business scenario
ERP SYSTEMS IMPLEMENTATION: FACTORS
ERP SYSTEMS IMPLEMENTATION: FACTORS INFLUENCING SELECTION OF A SPECIFIC APPROACH? Björn Johansson [email protected] Frantisek Sudzina [email protected] Center for Applied ICT, Copenhagen Business School Abstract
Executive Summary. At the end of the twentieth century and. Enterprise Systems for Higher Education Vol. 4, 2002
01 Executive Summary At the end of the twentieth century and into the twenty-first, higher education has invested, by a conservative estimate, $5 billion in administrative and enterprise resource planning
Enterprise System Assimilation: phases, activities, and outcomes
Przemysław Lech * Enterprise System Assimilation: phases, activities, and outcomes Introduction Enterprise systems (ES) are the backbone of most global manufacturing and service enterprises [Muscatello,
A Work Breakdown Structure for Implementing and Costing an ERP Project
94 Aisha Momoh, Decision Engineering Centre, Cranfield University, Bedford, UK,[email protected] Rajkumar Roy, Decision Engineering Centre, Cranfield University, Bedford, UK, [email protected]
Avoiding ERP Implementation Pitfalls. Pre-Purchase Considerations
Avoiding ERP Implementation Pitfalls Pre-Purchase Considerations It has often been said that one needs to have nerves of steel when setting out to implement a major business change initiative. That said,
Study of Effectiveness of Using ERP Systems in Cost Optimization of Just-In-Time Manufacturing Cases
World of Computer Science and Information Technology Journal (WCSIT) ISSN: 1-0741 Vol. 2,. 7, 225-229, 2012 Study of Effectiveness of Using ERP Systems in Cost Optimization of Just-In-Time Manufacturing
Empirical Study of ERP Implementation Strategies-Filling Gaps between the Success and Failure of ERP Implementation Process
International Journal of Information & Computation Technology. ISSN 0974-2239 Volume 4, Number 6 (2014), pp. 633-642 International Research Publications House http://www. irphouse.com Empirical Study of
Research Report IT barometer 2009. A survey on the importance of IT in Finnish companies from the perspective of IT and business management
Research Report IT barometer 2009 A survey on the importance of IT in Finnish companies from the perspective of IT and business management 1. Introduction... 3 1.1. Research Data... 3 1.2. Summary... 4
Preparing for ERP Implementation
Jaakko Kotiranta Preparing for ERP Implementation Case: Enersize Oy Helsinki Metropolia University of Applied Sciences Bachelor of Business Administratoin International Business and Logistics Bachelor
Global Shared Support Service:
Global Shared Support Service: Leveraging expertise, sharing costs andderiving value Chandra Shekar Kakal Shared service in any field comes with an implicit assumption of reduced cost and improved efficiency.
Course: Enterprise Applications and Open Source Systems for e-governance implementation. Day 3. Session 3: Introduction to ERP Applications
Course: Enterprise Applications and Open Source Systems for e-governance implementation Day 3 Session 3: Introduction to ERP Applications Agenda Introduction to ERP Applications Benefits of ERP Applications
PROJECT MANAGEMENT IN ENTERPRISE RESOURCE PLANNING (ERP) IMPLEMENTATION
PROJECT MANAGEMENT IN ENTERPRISE RESOURCE PLANNING (ERP) IMPLEMENTATION Ms.Madhavi A.Mainkar Lecturer Dr. BNCPE, Dept. Of Computer Science and Technology. Yavatmal Abstract: ERP is one the latest technologies
E TE T R E PR P IS I E S E R ES E O S URCE E P L P A L NNIN I G
االله الرحمن الرحيم بسم ENTERPRISE RESOURCE PLANNING SYSTEMS OVERVIEW Omer Omarabi January 2010 Agenda IT Planning & Challenges In Sudan What is an ERP System? Why You Need an ERP System? How to get your
ERP Implementation - The Traps
The PROJECT PERFECT White Paper Collection ERP Implementation - The Traps Neville Turbit Overview ERP implementations are littered with tales of lost millions and withdrawals after implementation. Many
Enterprise Resource Planning Systems in Higher Education
EDUCAUSE Center for Applied Research Research Bulletin Volume 2002, Issue 22 November 12, 2002 Enterprise Resource Planning Systems in Higher Education Paula King, EDUCAUSE Center for Applied Research
Enterprise resource planning Product life-cycle management Information systems in industry ELEC-E8113
Enterprise resource planning Product life-cycle management Information systems in industry ELEC-E8113 Contents Enterprise resource planning (ERP) Product data management (PDM) Product lifecycle management
A benefits realisation road-map
The current issue and full text archive of this journal is available at wwwemeraldinsightcom/1741-0398htm framework for ERP usage in small and medium-sized enterprises José Esteves Instituto de Empresa
Is Cloud ERP Really Cheaper?
Is Cloud ERP Really Cheaper? A Simple Guide to Understanding the Differences Between Cloud and On- Premise Distribution Software This guide attempts to outline all of the principal considerations that
Increasing operational efficiency through improved customer service a case from the process maintenance business
Increasing operational efficiency through improved customer service a case from the process maintenance business Jaana Auramo, Kari Tanskanen and Johanna Småros Department of Industrial Engineering and
ERP Implementation for Small and Medium Sized Companies Leads to Rocketing Revenues
Microsoft Business Solutions Food and Beverage Customer Solution Case Study ERP Implementation for Small and Medium Sized Companies Leads to Rocketing Revenues Overview Country or Region: USA Industry:
A Survey Instrument for Identification of the Critical Failure Factors in the Failure of ERP Implementation at Indian SMEs
A Survey Instrument for Identification of the Critical Failure Factors in the Failure of ERP Implementation at Indian SMEs ABSTRACT Dr. Ganesh L 1, Arpita Mehta 2 Many quantitative and qualitative studies
The importance of selecting the right ERP solution
The importance of selecting the right ERP solution The benefits of selecting and successfully implementing the right ERP solution for your business are widespread. The right ERP solution, tailored to suit
Current and Competitive ERP
Current and Competitive ERP Evaluate current ERP system capabilities and determine how to meet future growth plans. oday s enterprise resource planning (ERP) solutions differ greatly from versions T introduced
Business Interruption Factsheet
Business Interruption Factsheet Business Interruption (BI) should be an essential part of your business insurance protection to provide cover against both loss of income and additional expenses you incur
META DATA QUALITY CONTROL ARCHITECTURE IN DATA WAREHOUSING
META DATA QUALITY CONTROL ARCHITECTURE IN DATA WAREHOUSING Ramesh Babu Palepu 1, Dr K V Sambasiva Rao 2 Dept of IT, Amrita Sai Institute of Science & Technology 1 MVR College of Engineering 2 [email protected]
ENTERPRISE RESOURCE PLANNING SYSTEMS
CHAPTER ENTERPRISE RESOURCE PLANNING SYSTEMS This chapter introduces an approach to information system development that represents the next step on a continuum that began with stand-alone applications,
Commonwealth Caribbean Regional Conference. Investing in Youth Exploring Strategies for Sustainable Employment. Financing and Financial Mechanisms
Commonwealth Caribbean Regional Conference Investing in Youth Exploring Strategies for Sustainable Employment Financing and Financial Mechanisms Presented by Ian Chinapoo May 25 th, 2011 Outline: Background
A Foundation for Understanding Enterprise Resource Planning Systems
A Foundation for Understanding Enterprise Resource Planning Systems Develop an understanding of how ERP systems can improve the effectiveness of information systems in organizations Understand the business
Enterprise Resource Planning Business Case Considerations: A Review for Small and Medium-Sized Enterprises
IBIMA Publishing Journal of Innovation Management in Small & Medium Enterprises http://www.ibimapublishing.com/journals/jimsme/jimsme.html Vol. 2012 (2012), Article ID 752328, 15 pages DOI: 10.5171/2012.752328
Nazli Sadat Safavi, Nor Hidayati Zakaria and Mahyar Amini. Department of Information System, Faculty of Computing, Universiti Teknologi Malaysia
World Applied Sciences Journal 31 (9): 1669-1676, 2014 ISSN 1818-4952 IDOSI Publications, 2014 DOI: 10.5829/idosi.wasj.2014.31.09.140 The Risk Analysis of System Selection and Business Process Re-Engineering
"Selling" restructuring to SMEs through ERP implementation
"Selling" restructuring to SMEs through ERP implementation Igor Nazor Centar za stručne studije Sveučilišta u Splitu [email protected] Abstract. Small and medium enterprises (SMEs) have been receiving
Executive Brief. Best Practices for Software Selection. Best Practices for Software Selection. July 2013. #1 Structured Selection Methodology
Executive Brief Best Practices for Software Selection July 2013 In today s rapidly evolving organization climate a paradigm shift is beginning to unfold. The lowering of deployment obstacles for organizations
SAP Business One The Right Solution for Small & Medium Enterprises
SAP Business One The Right Solution for Small & Medium Enterprises www.praxisinfosolutions.com About the Author: Dattatreya R Kulkarni (http://tinyurl.com/o3j7fga), is one of the Founding Directors of
Factors for the Acceptance of Enterprise Resource Planning (ERP) Systems and Financial Performance
Factors for the Acceptance of Enterprise Resource Planning (ERP) Systems and Financial Performance Ayman Bazhair and Kamaljeet Sandhu Abstract The purpose of this research paper to present the synthesized
SUPPLY CHAIN MODELING USING SIMULATION
SUPPLY CHAIN MODELING USING SIMULATION 1 YOON CHANG AND 2 HARRIS MAKATSORIS 1 Institute for Manufacturing, University of Cambridge, Cambridge, CB2 1RX, UK 1 To whom correspondence should be addressed.
AN OVERVIEW OF SYSTEMS ANALYSIS: SYSTEMS ANALYSIS AND THE ROLE OF THE SYSTEMS ANALYST. Lecture 1. 21.10.2014, Tuesday
AN OVERVIEW OF SYSTEMS ANALYSIS: SYSTEMS ANALYSIS AND THE ROLE OF THE SYSTEMS ANALYST Lecture 1 21.10.2014, Tuesday 2 A Series of Lectures 1.The Role of the Systems 2.Project Planning and Project Management
US ONSHORING OFFERS SUPERIOR EFFECTIVENESS OVER OFFSHORE FOR CRM IMPLEMENTATIONS
US ONSHORING OFFERS SUPERIOR EFFECTIVENESS OVER OFFSHORE FOR CRM IMPLEMENTATIONS Whitepaper Eagle Creek Software Services March 2015 Introduction CRM services are shifting from a focus on point solution
Agile Project Portfolio Management
C an Do GmbH Implerstr. 36 81371 Munich, Germany AGILE PROJECT PORTFOLIO MANAGEMENT Virtual business worlds with modern simulation software In view of the ever increasing, rapid changes of conditions,
Data Quality Assurance
CHAPTER 4 Data Quality Assurance The previous chapters define accurate data. They talk about the importance of data and in particular the importance of accurate data. They describe how complex the topic
UNIVERSITY EDUCATION USING CLOUD AND ERP
UNIVERSITY EDUCATION USING CLOUD AND ERP Arun Korath 1, Negeso Edasa Wako 2 1 Associate Professor, College of Business and Economics, Dilla University, Ethiopia 2 Lecturer, College of Business and Economics,
USE OF ICT IN SMES MANAGEMENT WITHIN THE SECTOR OF SERVICES
USE OF ICT IN SMES MANAGEMENT WITHIN THE SECTOR OF SERVICES Plumb Ion Academy of Economic Studies Bucharest, Faculty of Management, 6 th Piata Romana RO 030173 Bucharest Romania, [email protected], +4021.319.19.00/287
Do more with less: The 5 strategies used by successful SMB manufacturers
Infor ERP Do more with less: The 5 strategies used by successful SMB manufacturers Table of contents Executive summary... 3 Building a framework for growth... 5 Vision... 5 Process... 6 Metrics... 7 Automation...
Actual vs. Planned ERP Systems Implementation Costs in European SMEs
Actual vs. Planned ERP Systems Implementation Costs in European SMEs Björn Johansson and Frantisek Sudzina Copenhagen Business School, Frederiksberg, Denmark [email protected] [email protected] Abstract: Enterprise
What is Business Process Design and Why Should I Care?
What is Business Process Design and Why Should I Care? by Jay Cousins and Tony Stewart, RivCom Ltd Introduction No matter how hard individuals work, they cannot overcome a flawed process design, much less
Critical factors for successful implementation of enterprise. systems
The research register for this journal is available at http://www.mcbup.com/research_registers The current issue and full text archive of this journal is available at http://www.emerald-library.com/ft
HUMAN DIMENSION OF CRM. 1. Introduction VILIAM LENDEL MILAN KUBINA. Classification JEL: M12 Personnel Management, M15 IT Management
HUMAN DIMENSION OF CRM VILIAM LENDEL MILAN KUBINA Abstract Customer relationship management is a comprehensive business and marketing strategy that integrates technology, process, and people. The human
An Integrated Methodology for Implementing ERP Systems
APDSI 2000 Full Paper (July, 2000) An Integrated Methodology for Implementing ERP Systems Su-Yeon Kim 1), Eui-Ho Suh 2), Hyun-Seok Hwang 3) 1) Department of Industrial Engineering, POSTECH, Korea ([email protected])
Investigation of Enterprise Resource Planning System (ERP) implementation in Libyan oil Service Company Redha M. Elhuni
Investigation of Enterprise Resource Planning System (ERP) implementation in Libyan oil Service Company Redha M. Elhuni Abstract This paper presents the findings of the investigation of ERP implementation.
Christina Soh, Sia Siew Kien, and Joanne Tay-Yap
Christina Soh, Sia Siew Kien, and Joanne Tay-Yap CULTURAL FITS AND MISFITS: IS ERP The universality of embedded business models of industry best practices is considered from an Asian perspective. A UNIVERSAL
Lowering business costs: Mitigating risk in the software delivery lifecycle
August 2009 Lowering business costs: Mitigating risk in the software delivery Roberto Argento IBM Rational Business Development Executive Valerie Hamilton IBM Rational Solution Marketing Manager and Certified
0845 345 3300 [email protected] www.theaccessgroup.com THE FINANCIAL FRONTIER
0845 345 3300 [email protected] www.theaccessgroup.com THE FINANCIAL FRONTIER Executive summary Many firms use ERP-derived stock modules to manage inventory levels and positioning. Unfortunately
About ERP Software Whitepaper
About ERP Software Whitepaper Many people have heard the term ERP used in a conversation but don t fully understand what it means. This whitepaper will provide information about the processes and advantages
INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN ICED 01 GLASGOW, AUGUST 21-23, 2001
INTERNATIONAL CONFERENCE ON ENGINEERING ICED 01 GLASGOW, AUGUST 21-23, 2001 REDUCING DEVELOPMENT CYCLE BY DATA MANAGEMENT WITHIN THE OFFICE Mario Storga, Davor Pavlic and Dorian Marjanovic Keywords: Product
WHITE PAPER. The Real Cost of Outsourcing
WHITE PAPER The Real Cost of Outsourcing INTRODUCTION When it comes to the figures of investing in outsourcing, statistics can give you an overall cost of official bills. Actually, you would be surprised
Four Clues Your Organization Suffers from Inefficient Integration, ERP Integration Part 1
Four Clues Your Organization Suffers from Inefficient Integration, ERP Integration Part 1 WHY ADOPT NEW ENTERPRISE APPLICATIONS? Depending on your legacy, industry, and strategy, you have different reasons
Global Headquarters: 5 Speen Street Framingham, MA 01701 USA P.508.872.8200 F.508.935.4015 www.idc.com
Global Headquarters: 5 Speen Street Framingham, MA 01701 USA P.508.872.8200 F.508.935.4015 www.idc.com EXECUTIVE INSIGHTS Knowledge Transfer Enables Enterprise Performance Michael Brennan INTRODUCTION
How to Select and Implement an ERP System
How to Select and Implement an ERP System Prepared by 180 Systems Written by Michael Burns 180 Systems WHAT IS ERP?... 3 ANALYSIS... 4 VENDOR SELECTION... 6 VENDOR DEMONSTRATIONS... 8 REFERENCE CALLS...
Management Accounting: Genesis Cost Accounting. Oracle Projects module extension: Cost accounting in Oracle ERP
Management Accounting: Genesis Cost Accounting Oracle Projects module extension: Cost accounting in Oracle ERP Whitepaper Informative Document, January 2013 Table of contents SYSTEM ARCHITECTURE WITH ORACLE
Development, Acquisition, Implementation, and Maintenance of Application Systems
Development, Acquisition, Implementation, and Maintenance of Application Systems Part of a series of notes to help Centers review their own Center internal management processes from the point of view of
ERP Implementation. Different phases and related issues
Volume 1, No. 11, January 2013 ISSN 2278-1080 The International Journal of Computer Science & Applications (TIJCSA) RESEARCH PAPER Available Online at http://www.journalofcomputerscience.com/ ERP Implementation
Integrating EDI for users of small business accounting and ERP software
Small Business EDI Integration Integrating EDI for users of small business accounting and ERP software The promise of EDI integration has always been alluring, but financially out of reach for the small
THE PROCESS OF PREPARATION AND IMPLEMENTATION OF CRM IN THE COMPANY
Journal of Information, Control and Management Systems, Vol. 6, (2008), No.1 95 THE PROCESS OF PREPARATION AND IMPLEMENTATION OF CRM IN THE COMPANY Viliam LENDEL, Milan KUBINA University of Žilina, Faculty
THE ORGANISATION. Senior Management Major end users (divisions) Information Systems Department
THE ORGANISATION Senior Management Major end users (divisions) Information Systems Department Technology Hardware Software Information Systems Specialists CIO Managers Systems analysts Systems designers
Lecture-2-The Strategic Role of Information Systems
Lecture-2-The Strategic Role of Information Systems Thepul Ginige 1 LEARNING OBJECTIVES Analyze roles of 6 types of information systems Describe types of information systems Analyze relationships between
REVIEW OF CURRENT STATE OF EUROPEAN 3PL MARKET AND ITS MAIN CHALLENGES
Computer Modelling and New Technologies, 2008, Vol.12, No.2, 17 21 Transport and Telecommunication Institute, Lomonosova 1, LV-1019, Riga, Latvia REVIEW OF CURRENT STATE OF EUROPEAN 3PL MARKET AND ITS
Strategic Planning for Successful ERP Implementation
Strategic Planning for Successful ERP Implementation Abdelmageed Elsadek Abdelrazek Since early 1990s, many firms around the world have shifted their information technology (IT) strategy from developing
The Real ROI from SAP
RESEARCH NOTE ROI ANALYSIS YOU CAN TRUST TM The Real ROI from SAP THE BOTTOM LINE Fifty-seven percent of SAP customers interviewed did not believe that they had achieved a positive ROI, after having used
ERP SYSTEM IMPLEMENTATION: A CASE STUDY OF THE CONSTRUCTION ENTERPRISE
ERP SYSTEM IMPLEMENTATION: A CASE STUDY OF THE CONSTRUCTION ENTERPRISE Andrejs Tambovcevs Riga Technical University, Latvia, [email protected] Abstract The enterprise resource planning software market has
The Beginners Guide to ERP for Food Processors
The Beginners Guide to ERP for Food Processors Technically, ERP stands for Enterprise Resource Planning software, but really it could stand for Everything Right & Profitable or Easier Realized Profits.
Why improving your line managers people skills will improve your profits
As part of our Tomorrow s Executive series of articles we bring you: an executive s guide to implementing strategy By Paul Hughes, Mercuri Urval Global Client Services Why improving your line managers
The Importance of Integrative Components in the Field of e-business and Information Systems
Jelica Trninić Jovica Đurković The Importance of Integrative Components in the Field of e-business and Information Systems Article Info:, Vol. 3 (2008), No. 1, pp. 023-028 Received 12 Januar 2008 Accepted
Pain Points Challenges for future Enterprise Resource Planning (ERP) systems
Pain Points Challenges for future Enterprise Resource Planning (ERP) systems Björn Johansson 1 1 Copenhagen Business School, Center for Applied ICT, [email protected] Abstract. The questions asked in this
14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003
14TH INTERNATIONAL CONFERENCE ON ENGINEERING DESIGN 19-21 AUGUST 2003 A CASE STUDY OF THE IMPACTS OF PRELIMINARY DESIGN DATA EXCHANGE ON NETWORKED PRODUCT DEVELOPMENT PROJECT CONTROLLABILITY Jukka Borgman,
THE PLANNING OF A CUSTOMER RELATIONSHIP MANAGEMENT PROJECT: REQUIREMENTS AND OPPORTUNITIES
THE PLANNING OF A CUSTOMER RELATIONSHIP MANAGEMENT PROJECT: REQUIREMENTS AND OPPORTUNITIES Professor PhD Adriana OLARU Lecturer Alexandru CAPATINA Dunărea de Jos University of Galati, Romania Abstract:
How to Choose a CRM System.
How to Choose a CRM System. Contents How to Choose a CRM System... 3 Understanding CRM... 4 Getting Started... 5 Understanding the Core Components of CRM... 6 Involve the Right People... 7 Select a System
Blue Saffron Managed Services : The Customer Experience
Blue Saffron Managed Services : The Customer Experience 1 Contents Background... 3 Section 1: SME Business and ICT Challenges... 3 Section 2: Key Drivers and Considerations for Managed Services... 5 Section
The ERP Systems in Czech Republic A strategical innovation
The ERP Systems in Czech Republic A strategical innovation José Arnaldo Cardoso Monteiro de Melo I. Introduction Nowadays it is possible to verify that the global tendencies of the market pointed out to
Process Streamlining. Whitepapers. Written by A Hall Operations Director. Origins
Whitepapers Process Streamlining Written by A Hall Operations Director So, your processes are established and stable, but are clearly inefficient and you are not meeting your performance expectations.
Current Status of Technology Adoption: Micro, Small and Medium Manufacturing Firms in Boston
Current Status of Technology Adoption: Micro, Small and Medium Manufacturing Firms in Boston Authors: Pratyush Bharati Management Science and Information Systems College of Management University of Massachusetts,
Chamber SME E-Business Survey 2002
Chamber SME E-Business Survey 2002 Prepared for Chambers of Commerce of Ireland September 2002 Chambers of Commerce of Ireland 17 Merrion Square Dublin 2 Ireland W: www.chambersireland.ie E: [email protected]