QUESTION: 1 In PRINCE2 what product is used to define the information that justifies the setting up, continuation or termination of the project?

Size: px
Start display at page:

Download "QUESTION: 1 In PRINCE2 what product is used to define the information that justifies the setting up, continuation or termination of the project?"

Transcription

1 QUESTION: 1 In PRINCE2 what product is used to define the information that justifies the setting up, continuation or termination of the project? A. Project Initiation Document B. Business Case C. End Stage Approval D. Project Brief QUESTION: 2 Which product keeps track of Requests For Change? A. Request Log B. Daily Log C. Quality Log D. Issue Log QUESTION: 3 What provision in Planning can be made for implementing Requests for Change? A. Project and stage tolerances B. Contingency plans C. A Change Budget D. Adding a contingency margin to estimates QUESTION: 4 FilL in the missing phrase from a project is a management environment that is created for the purpose of delivering one or more business products according to A. TheCustomer sneds B. An Agreed Contract C. The Project Plan D. A specified Business Case

2 QUESTION: 5 In what sequence would the (a) Project Initiation Document, (b) the Project Mandate and (c) the Project Brief appear in a PRINCE2 project? A. a, b, c B. b, c, a C. c, a, b D. c, b, a QUESTION: 6 Which would require the production of an Exception Report? A. When a Project Issue is received B. When a Project Board member raises a complaint C. When a Request For Change or Off-Specification has been received D. When the current forecasts for the end of the stage deviate beyond the delegated tolerance bounds QUESTION: 7 Which statement is NOT a fundamental principle of Closing a Project? A clear end to a project A. provides a useful opportunity to take stock of achievements B. provides an opportunity to ensure that all unachieved goals and objectives are identified C. provides the opportunity to evaluate achievement of all the expected benefits D. is always more successful than the natural tendency to drift into operational Management QUESTION: 8

3 What is the more common term used in PRINCE2 for deliverable? A. Item B. Package C. Product D. Component QUESTION: 9 Which of these items does NOT involve the Project Board? A. Exception Assessment B. Highlight Reports C. Project Closure D. Work Package Authorisation QUESTION: 10 What name is given to the permissible deviation from a plan allowed without immediate reporting to the Project Board? A. Allowance B. Contingency C. Concession D. Tolerance QUESTION: 11 What other control is closely linked with configuration management? A. Risk Management B. Project Closure C. Change Control D. Project Initiation

4 QUESTION: 12 Which of these processes does NOT trigger the Planning (PL) process? A. Starting Up a Project (SU) B. Initiating a Project (IP) C. Managing Stage Boundaries (SB) D. Controlling a Stage (CS) QUESTION: 13 In a Product Breakdown Structure what category of product is a Highlight Report? A. Quality B. Specialist C. Technical D. Management QUESTION: 14 If, after a Quality Review Follow-up Action, an error is still not resolved, what action should be taken? A. An Exception Report is made B. A Project Issue is raised C. An Exception Memo is raised D. The review is reconvened QUESTION: 15 Which of the following is NOT a PRINCE2 definition of a project? A. Has an organisation structure B. Produces defined and measurable business products

5 C. Uses a defined amount of resources D. Uses a defined set of techniques QUESTION: 16 What environment does PRINCE2 assume? A. A fixed-price contract B. A Customer/Supplier environment C. A specialist environment D. A third-party environment QUESTION: 17 Which feature of PRINCE2 tells the Project Manager where a product is, what its status is and who is working on it? A. Work Package B. Product Description C. Checkpoint Report D. Configuration Management QUESTION: 18 In Closing a Project (CP)the project files are archived. What is the explanation given for this? A. To provide useful lessons to future projects B. Never throw anything away. C. This material may be needed by Programme Management D. To permit any future audit of the project s actions QUESTION: 19

6 Which of the following statements is FALSE? Project Managers using PRINCE2 are encouraged to A. Establish terms of reference as a prerequisite to the start of the project B. Use a defined structure for delegation, authority and communication C. Divide the project into manageable stages for more accurate planning D. Provide brief reports to management at regular meetings QUESTION: 20 Which of these is NOT a valid Risk Management action? A. Prevention B. Denial C. Reduction D. Transference QUESTION: 21 Which one of these is NOT a PRINCE2 Component? A. Plans B. Controls C. Work Package D. Configuration Management QUESTION: 22 Which document lists the major products of a plan with their key delivery dates? A. Product Outline B. Product Breakdown Structure C. Checkpoint Report D. Product Checklist

7 QUESTION: 23 The configuration of the final deliverable of the project is - A. The sum total of its products B. The interim products C. Its product description D. The single end-product QUESTION: 24 Which part of a product lifespan is not part of a project life cycle in the eyes of PRINCE2? A. The change-over to operational use of the product B. Assessment of the value of the product after a period of use C. The specification of the product D. Finalisation of the business case QUESTION: 25 What is the first job carried out on receipt of a new Project Issue? A. Allocation of priority B. Logging C. Decision on what type of issue D. Impact Analysis QUESTION: 26 Which of these statements is FALSE? A. The Project Plan is an overview of the total project. B. For each stage identified in the Project Plan, a Stage Plan is required.

8 C. An Exception Plan needs the approval of the next higher level of authority. D. A Team Plan needs approval by the Project Board. QUESTION: 27 Which of the following statements is FALSE? A. Customer quality expectations should be discovered in the process Starting Up a Project B. Acompany sqmsbecomespartofprince2 C. PRINCE2 may form part of a company s QMS D. The Stage Plan describes in detail how part of the Project Plan will be carried out QUESTION: 28 Which one of these statements describes the true purpose of Acceptance Criteria? A. A justification for undertaking the project based on estimated costs and anticipated benefits. B. A measurable definition of what must be done for the final product to be acceptable to the Customer. C. To provide a full and firm foundation for the initiation of a project. D. To triger Starting up a Project. QUESTION: 29 How often does PRINCE2 recommend that open Project Issues should be reviewed? A. Weekly B. At Exception Assessments C. At Checkpoint Meetings D. On a regular basis

9 QUESTION: 30 What other product is reviewed at the end of each stage apart from the Business Case and Project Plan? A. The Project Mandate B. The Team Plan C. The Risk Log D. The Project Brief QUESTION: 31 Why is a copy of the Project Issue always returned to the author? A. The author owns it. B. To acknowledge its receipt and entry into the system. C. To elicit further information. D. To notify rejection of the Issue. QUESTION: 32 Which of the options below reviews the benefits achieved by the project? A. Post-Project Review B. Post-Project Review Plan C. End Project Report D. Follow-on Action Recommendations QUESTION: 33 Which of these statements is FALSE? A. A PRINCE2 project has a finite life span B. A PRINCE2 project has a defined amount of resources C. A PRINCE2 project may have only activities, i.e. no products D. A PRINCE2 project has an organisation structure with defined responsibilities, to manage the project

10 QUESTION: 34 The person best situated to keep an eye on a risk is called its? A. Supporter B. Monitor C. Owner D. Librarian QUESTION: 35 Which document reviews actual achievements against the Project Initiation Document? A. End Project Report B. Post-Project Review C. Lessons Learned Report D. Follow-On Action Recommendations QUESTION: 36 InPRINCE2alpotentialchangesaredealtwithas? A. Configuration items B. Requests For Change C. Project Issues D. Exception Reports E. Action items QUESTION: 37 Which one of these is NOT a key criterion for producing a Product Flow Diagram?

11 A. Are the products clearly and unambiguously defined? B. On what other products is each product dependent? C. Is any product dependant on a product outside the scope of this plan? D. Which products can be developed in parallel? QUESTION: 38 For a Quality Review, when are suitable reviewers identified? A. When the product is passed to configuration management B. In the Project Quality Plan C. During the QR preparation step D. In planning the relevant stage QUESTION: 39 The existence of what product is checked in Starting up a Project and its initial version finalized in Initiating a Project? A. The Project Mandate B. The Project Plan C. The Project Brief D. The Business Case QUESTION: 40 Which does PRINCE2 regard as the third project interest, given user and supplier as the other two? A. Technical B. Management C. Business D. Quality

12 QUESTION: 41 PRINCE2 lists a number of reasons why it is seldom desirable or possible to plan an entire project in detail at the start. Which of these is NOT one of these reasons? A. A changing or uncertain environment B. A PRINCE2 requirement C. Difficulty in predicting business conditions in the future D. Difficulty in predicting resource availability well into the future QUESTION: 42 In which process is the Project Brief produced? A. Starting Up a Project B. Initiating a Project C. Authorising Initiation D. Authorising a Project QUESTION: 43 When should a Product Description be baselined? A. As soon as it is available in draft form B. When the associated product has passed its quality check C. When the plan containing its creation is baselined D. As soon as it is written QUESTION: 44 An Exception Plan covers what period? A. From the problem to the end of the project B. From the problem to the end of a plan that will no longer finish within agreed tolerances C. The work needed to put the project back within its tolerances

13 D. The time needed to produce an Exception Report QUESTION: 45 There are several benefits that the end stage assessment brings to a project. Which one of the following is NOT a benefit? A. To enable the approval of an Exception Report B. To provide a review of a risky project at key moments when new information about those risks appears C. To ensure that key decisions are made prior to the detailed work needed to implement them D. To provide a fire break for the project by encouraging the Project Board to assess the project viability at regular intervals QUESTION: 46 The initial Project Plan is based on the Project Brief, the Project Quality Plan and which other product? A. The Project Approach B. The Project Initiation Document C. The project start-up notification D. The Project Mandate QUESTION: 47 Which document is a record of some current or forecast failure to meet a requirement? A. Exception Report B. Off-Specification C. Follow-On Action Recommendations D. Highlight Report

14 QUESTION: 48 If there is a request to change a baselined product, and the change can be done within the stage or Work Package tolerances, how can the decision to implement the change be made? A. Project Manager s decision B. Team Manager s decision C. Team member s decision to whom the work has been allocated D. formal change control QUESTION: 49 ControlingaStage driveswhichotherprocesonafrequent,iterativebasis? A. Managing Stage Boundaries B. Approving a Stage or Exception Plan C. Managing Product Delivery D. Planning QUESTION: 50 The Project Quality Plan is written in which process? A. Initiating a Project B. Starting up a Project C. Managing Stage Boundaries D. Directing a Project QUESTION: 51 What are defined as partitions of the project with decision points? A. Work Packages B. Product Descriptions C. Quality Reviews

15 D. Stages QUESTION: 52 In which lower level process of Controling a Stage is the Risk Log up dated? A. Reporting Highlights B. Assessing Progress C. Capturing Project Issues D. Examining Project Issues QUESTION: 53 If a question arises on why a particular product was changed, which element of PRINCE2 would be of most help in finding the information? A. Issue Log B. Quality Log C. Configuration Management D. Change Control QUESTION: 54 In which sub-process is a Stage Plan updated with actuals? A. Assessing Progress B. Reviewing Stage Status C. Planning a Stage D. Reporting Highlights QUESTION: 55 In which sub-process are Checkpoint Reports created?

16 A. Executing a Work Package B. Assessing Progress C. Reporting Highlights D. Reviewing Stage Status QUESTION: 56 Are the following statements true or false? 1 Delegated Project Assurance roles report directly to corporate or programme management 2 In PRINCE2 the Project Manager role must be full time 3 A project management structure is a temporary structure A. All three are false B. Only the third is true C. Only the first is false D. The second and third are true QUESTION: 57 The proces, Directing a Project begins when? A. From Starting up a Project B. After the start-up of the project C. At the end of the Initiation Stage D. Before start-up of the project QUESTION: 58 Apart from Initiating a Project in which proces is the Busines Caseupdated? A. Managing Product Delivery B. Controlling a Stage C. Managing Stage Boundaries D. Authorising a Stage

17 QUESTION: 59 The existence of what in formation is expected by the proces Starting Up a Project? A. A Project Plan B. A Project Mandate C. An appointed organisation D. Project Initiation Document QUESTION: 60 In the PRINCE2 document management structure, how many types of file are recommended? A. One for each Stage B. Two, Management and Specialist C. Just the Quality File D. Three; project, stages and quality QUESTION: 61 In a Quality Review which role does PRINCE2 suggest must ensure that all reviewers are provided with the relevant review products? A. Producer B. Scribe C. Review Chairperson D. Configuration Librarian QUESTION: 62 Which of these is mandatory in a PRINCE2 project?

18 A. The use of Team Managers B. The use of Exception Plans C. The use of Stages D. The use of Product Checklists QUESTION: 63 The Project Board has three responsibilities towards the management of risk. Which of the following options is the FALSE one? A. Notifying the Project Manager of any external risk exposure to the project B. Making decisions on recommended reactions to risk C. Identifying, recording and regularly reviewing risks D. Striking a balance between levels of risk and potential benefits QUESTION: 64 What function creates, maintains and monitors the use of a quality system? A. Project Support B. Quality Planning C. Quality Control D. Quality assurance QUESTION: 65 Which is NOT a purpose of configuration management? A. To identify products B. To create products C. To track products D. To protect products

19 QUESTION: 66 Which step is NOT part of Acepting a Work Package? A. Understand the reporting requirements B. Agree tolerance margins for the Work Package C. Monitor and control the risks associated with the Work Package D. Produce a Team Plan which shows that the Work Package can be completed within the constraints QUESTION: 67 Which process provides the information needed for the Project Board to assess the continuing viability of the project? A. Starting up a Project B. Closing a Project C. Planning D. Managing Stage Boundaries QUESTION: 68 Which of the following are described in the Communication Plan? 1) Who needs information 2) What information they need 3) Why they need it 4) The format in which it should be presented. A. The fourth is wrong B. All four are correct C. Only the first two are correct D. The third is wrong. QUESTION: 69 In which process are decisions made on Exception Reports?

20 A. Managing Stage Boundaries B. Closing a Project C. Directing a Project D. Managing Product Delivery QUESTION: 70 Which process checks for changes to the project management team? A. Starting up a Project B. Managing Stage Boundaries C. Closing a Project D. Directing a Project QUESTION: 71 Fromtheproductslisted,which one i s produced during Starting Up a Project? A. The Project Initiation Document B. The Project Plan C. The Project Quality Plan D. The Project Approach QUESTION: 72 Quality responsibilities, both within and external to the project, are defined in which process? A. Initiating a Project B. Starting up a Project C. Managing Stage Boundaries D. Directing a Project

21 QUESTION: 73 Acceptance for the completed products is obtained as part of which process? A. Closing a Project B. Managing Product Delivery C. Managing Stage Boundaries D. Controlling a Stage QUESTION: 74 An Exception Report is produced in which sub-process? A. Taking Corrective Action B. Reviewing Stage Status C. Escalating Project Issues D. Reporting Highlights QUESTION: 75 Which of the following are functions of the start-up process, SU? 1) Setting up the project management team 2) Developing the Project Mandate into the Project Brief 3) Confirming the Project Approach 4) Creating the Issue Log A. All four B. the first three C. the first two D. the third is wrong QUESTION: 76 Which role from the following list does PRINCE2 say cannot be delegated? A. Team Manager B. Project Assurance

22 C. Project Board Member D. Project Support QUESTION: 77 New versions of the Project Plan are produced at the end of each stage to reflect updated information. Identify which option is FALSE. A. Progress already made B. Benefits already achieved C. Any agreed changes in circumstances D. Any revised forecast of cost QUESTION: 78 The decision on whether a project s solution will be contracted to third parties is made in which product? A. The Project Plan B. The Project Approach C. The Project Brief D. The Project Quality Plan QUESTION: 79 Apart from Initiating a Project in which process is the Business Case updated? A. Managing Product Delivery B. Controlling a Stage C. Managing Stage Boundaries D. Authorising a Stage QUESTION: 80

23 What does PRINCE2 suggest may assist in the ultimate acceptance of the project? A. Identifying Risks associated with a plan B. Agreeing the Quality Criteria for a product with the Customer C. Establishing tolerance levels D. Follow-on Action Recommendations QUESTION: 81 Which individual role is ultimately accountable for the project? A. Project Manager B. Senior Supplier C. Executive D. Senior User QUESTION: 82 Who is responsible for the project producing a result that is capable of achieving the benefits defined in the Business Case? A. The Executive B. The Project Manager C. The Senior User D. The entire Project Board QUESTION: 83 In which document does PRINCE2 look for the identification of the Chairman of a Quality Review? A. Project Plan B. Stage Quality Plan C. Project Quality Plan D. Project Initiation Document

24 QUESTION: 84 Which of the following quality measures is covered in the process Initiating a Project (IP)? A. How quality will be achieved B. When each product will be tested C. By whom each product will be tested D. Options A, B and C QUESTION: 85 In terms of configuration management what are described as the assets of a project? A. The resources B. The plans C. The products D. The business benefits QUESTION: 86 Which of the following products is NOT created during the PRINCE2 process model? A. Project Brief B. Project Mandate C. Project Initiation Document D. Project Plan QUESTION: 87 Which statement is NOT a fundamental principle of Closing a Project?

25 A. A clear end to a project provides a useful opportunity to take stock of achievements and experience B. A clear end to a project provides an opportunity to ensure that all unachieved goals and objectives are identified C. A clear end to a project provides the opportunity to evaluate achievement of all the expected benefits D. A clear end to a project is always more successful than the natural tendency to drift into use and subsequent modification of the product QUESTION: 88 In which process are checks made for changes to the project management team? A. Starting up a Project B. Managing Stage Boundaries C. Closing a Project D. Directing a Project QUESTION: 89 What provision in Planning can be made for implementing Requests for Change? A. Project and Stage Tolerances B. A Change Budget C. Contingency Plans D. Adding a contingency margin to estimates QUESTION: 90 Which option is NOT part of the Project Initiation Document? A. Project Mandate B. Initial Business Case C. Project Quality Plan D. Communication Plan

26 QUESTION: 91 On behalf of whom do any appointed assurance jobs assure the project? A. Project Manager B. Corporate Management C. Project Executive D. One or more members of the Project Board QUESTION: 92 Which statement most accurately reflects the reason for an Exception Assessment in PRINCE2? A. For the Project Manager to present an Exception Plan to the Project Board B. The Project Manager delivers a progress report to the Project Board as a confidence boost C. The Project Board meets to consider an Exception Report D. The Project Manager reviews and revises the Risk Log with those with assurance roles QUESTION: 93 If a product is to be changed, what else must also pass through change control? A. Stage Quality Plan B. Product Breakdown Structure C. Product Description D. Quality Log QUESTION: 94 As part of Assessing Progress the Project Manager looks at Checkpoint Reports, Work Packages status and what other product?

27 A. Highlight Reports B. The Quality Log C. The Business Case D. Project Initiation Document QUESTION: 95 What document is input to the Project Board with a request to authorise the project? A. The Project Brief B. The Project Mandate C. The Project Initiation Document D. An Implementation Plan QUESTION: 96 What is the first task in product-based planning? A. Creating a Product Checklist B. Creating a Product Description for the final product C. Creating a Product Flow Diagram D. Creating a Product Breakdown Structure QUESTION: 97 Which one of these is NOT a Project Issue? A. Annotation of minor errors on a Quality Review product B. Request to change the specification of requirements C. Suggestion to improve a project product D. Record of some current or forecast failure to meet a requirement

28 QUESTION: 98 Which role is suggested might act as Scribe to a Quality Review? A. Project Assurance B. Reviewer C. Project Support D. The Review Chairman QUESTION: 99 What does PRINCE2 say must drive the project? A. The Project Mandate B. The Project Initiation Document C. The Project Brief D. The Business Case QUESTION: 100 Which phrase applies to the user representative in a PRINCE2 project management team? A. They will be impacted by the outcome B. May need to use both in-house and external teams to construct the final outcome C. Representation from the business viewpoint D. Will provide the funding QUESTION: 101 Which process covers overall direction and decision-making of the project? A. Managing Product Delivery B. Controlling a Stage C. Directing a Project D. Managing Stage Boundaries

29 QUESTION: 102 What is the fundamental principle behind the process Managing Product Delivery? A. A controlled break between Project Manager and product creation/provision by third party suppliers B. Before a Work Package is allocated to the team, there should be agreement with the Project Manager on what is to be delivered C. Whatever the type of project, the actual task of creating the required products needs to be managed D. Work only commences and continues with the consent of the Project Manager QUESTION: 103 The Product-based Planning technique is recommended for which plans? A. Stage Plans only B. Project and Stage Plans only C. All levels of plan D. All levels of plan except the Exception Plan QUESTION: 104 The use of which of these roles is OPTIONAL? A. Executive B. Project Manager C. Senior User D. Team Manager QUESTION: 105 Which of the following statements is FALSE?

30 A. The two standard elements to tolerance are time and cost B. Tolerance is the permissible deviation from plan without bringing the deviation to the attention of the next higher authority. C. Separate tolerance figures should be given for time and cost. D. The Project Board has absolute discretion to set new tolerances at Project and Stage Plan levels whenever it wishes to whatever levels it wishes. QUESTION: 106 In which lower level process of Controlling a Stage is a Stage Plan updated with actuals? A. Assessing Progress B. Reviewing Stage Status C. Planning a Stage D. Reporting Highlights QUESTION: 107 Which process produces operational and maintenance acceptance of products? A. Managing Stage Boundaries B. Managing Product Delivery C. Closing a Project D. Controlling a Stage QUESTION: 108 Who does PRINCE2 say may re-evaluate the priority of an issue after impact analysis? A. The Team Manager B. Those with assurance responsibilities C. The Author D. The Project Board

31 QUESTION: 109 Which report does the Project Manager receive on a regular basis? A. Highlight Report B. Checkpoint Report C. Issue Report D. Exception Report QUESTION: 110 In PRINCE2 all potential changes are dealt with as? A. Requests For Change B. Off-Specifications C. Configuration Items D. Project Issues QUESTION: 111 Given that producing a Product Breakdown Structure and a Product Flow Diagram are two of the steps of product-based planning, which is another? A. Identifying activities and dependencies B. Writing Product Descriptions C. Scheduling D. Defining and analysing products QUESTION: 112 In preparing for a Quality Review, who should distribute a copy of the product and Product Description to the reviewers?

32 A. The Project Manager B. the Scribe C. the Team Manager D. the Producer QUESTION: 113 What are described as the backbone of the management information system required for any project? A. Highlight Reports B. Plans C. The control points D. End Stage Assessments QUESTION: 114 Which PRINCE2 technique helps to ensure that all personnel affected by a product have the same understanding of the product s purpose? A. Quality Review B. Configuration Management C. Product-based Planning D. Change Control QUESTION: 115 If there were a need to know what the precise content of an old version of a product was, what part of PRINCE2 would most help us? A. The Stage Plan B. The Issue Log C. Configuration Management D. Work Package Authorisations

33 QUESTION: 116 The initial Project Plan is based on the Project Brief, the Project Quality Plan and which other product? A. The Project Approach B. The Project Initiation Document C. The project start-up notification D. The Project Mandate QUESTION: 117 What is a concession? A. A contract to a third party B. An error found in a Quality Review which is not corrected C. An Off-Specification accepted by the Project Board without corrective action D. An allowance above and beyond tolerance levels QUESTION: 118 Are the majority of PRINCE2 controls described as? A. Event-driven B. Time-driven C. Ad hoc D. Technique-based QUESTION: 119 Which product does PRINCE2 suggest should include the budget and schedule impact of changes? A. Checkpoint Report

34 B. Exception Report C. Highlight Report D. Lessons Learned Report QUESTION: 120 What time-driven control ascertains the status of team members work? A. Highlight Report B. Checkpoint Report C. Exception Report D. End Stage Report QUESTION: 121 What plan identifies quality responsibilities for the project? A. The Project Plan B. a Stage Quality Plan C. the Project Quality Plan D. a Team Plan QUESTION: 122 In which process does the Project Manager ask the Project Board where the authority for making change lies? A. During Starting Up A Project B. During Initiating a Project C. In Giving Ad Hoc Direction D. When Authorising a Stage QUESTION: 123

35 Apart from the Issue Log, what else is updated by the lower level process Examining Project Issues? A. Lessons Learned Log B. Business Case C. Risk Log D. Stage Plan QUESTION: 124 Closure of the project can only be authorised in which of these processes? A. Initiating a Project B. Closing a Project C. Managing Stage Boundaries D. Directing a Project QUESTION: 125 Which report assesses what management processes worked well and what went badly? A. Follow-on Action Recommendations B. End Stage Report C. Business Case review D. Lessons Learned Report QUESTION: 126 What does PRINCE2 suggest is a direct input to the Project Quality Plan? A. ISO 9001 B. Stage Quality Plan C. The supplier quality policy D. Customer Quality Expectations

36 QUESTION: 127 What name is given to the review that checks that the configuration management process is being done to a standard? A. Product Status Account B. Configuration audit C. Quality Review D. Quality Assurance QUESTION: 128 Who might receive completed products before the Team Manager reports that the Work Package has been completed? A. The Customer B. The User C. Configuration Librarian D. The Project Board QUESTION: 129 In the suggested filing system, where is the Risk Log kept? A. Quality File B. Project File C. Each Stage File D. Specialist File Answer: B QUESTION: 130 For a Quality Review, when are suitable reviewers selected? A. When the product is passed to Configuration Management

37 B. In the Project Quality Plan C. During the QR Preparation step D. In planning the relevant stage QUESTION: 131 Which of these is NOT a specific objective of an end stage assessment? A. Perform a risk analysis and management review of the project B. Revise the Project Mandate C. Review the tolerances set for the next Stage D. Review the next Stage Plan against the Project Plan QUESTION: 132 Defining the stages of a project is fundamentally a process of balancing a number of parameters. Which one of the following is NOT one of the parameters A. The availability of the project board for progress meetings B. How far ahead in the project it is sensible to plan C. Where the key decision points need to be on the project D. Too many small stages versus too few big ones QUESTION: 133 In which sub-process of Controlling a Stage is the Risk Log updated? A. Capturing Project Issues B. Assessing Progress C. Examining Project Issues D. Reporting Highlights QUESTION: 134

38 Which step is NOT part of Accepting a Work Package? A. Understand the reporting requirements B. Agree tolerance margins for the Work Package C. Monitor and control the risks associated with the Work Package D. Produce a Team Plan which shows that the Work Package can be completed within the constraints QUESTION: 135 The configuration of the final deliverable of the project is - A. The single end product B. The interim products C. Its product description D. The sum total of its products QUESTION: 136 In the PRINCE2 document management structure, how many major types of file are recommended? A. Three-plans, risk and quality B. Three-project, stage and quality C. Just the Quality File D. One per Project Issue QUESTION: 137 When is a Project Quality Plan created? A. In 'Starting up a Project' B. During Initiation C. As part of 'Managing Stage Boundaries' D. As part of the Project Mandate

39 QUESTION: 138 The following appears on the cover sheet of a PID: 'Version 1. 3 Draft'. Which Component of PRINCE2 would be responsible for this entry? A. Controls B. Configuration Management C. Quality in a Project Environment D. Change Control QUESTION: 139 When should an initial examination of a Project Issue be performed? A. As soon as it is logged B. On a weekly basis C. At the next execution of the sub-process, Reviewing Stage Status D. At end stage assessment QUESTION: 140 In addition to the normal steps of a Quality Review an extra one, Quality Review Planning is recommended. In which process does PRINCE2 suggest that this step should be done? A. Planning B. Starting up a Project C. Initiating a Project D. Controlling a Stage QUESTION: 141 Quality management is

40 A. The means of ensuring that products meet the quality criteria B. The establishment of the objectives and requirements for quality C. The creation and maintenance of a quality system D. The process of ensuring that the quality expected by the customer is achieved QUESTION: 142 What should be reviewed as part of preparing a Work Package? A. The Issue Log B. The appropriate Product Descriptions C. Project Board Authorisation to Proceed D. Timesheets QUESTION: 143 The person operating the configuration management method is called A. Configuration Librarian B. Configuration Auditor C. Product Assurance D. Version Controller QUESTION: 144 Which of the following statements is FALSE? Project Managers using PRINCE2 are encouraged to A. Establish terms of reference as a prerequisite to the start of the project B. Use a defined structure for delegation, authority and communication C. Ensure resource commitment from management is part of any approval to proceed D. Provide brief reports to management at regular meetings

41 QUESTION: 145 The Quality File has seven divisions. Five of these are for customer s quality expectations, Project Quality Plan, Configuration Management Plan, Configuration Item Records and Quality inspection records. Which of the following is another one? A. Off-Specifications B. Specialist Products C. Acceptance Criteria D. Stage Quality Plans QUESTION: 146 Which process covers the work required of people who may not be using PRINCE2? A. Managing Stage Boundaries B. Starting up a Project C. Directing a Project D. Managing Product Delivery QUESTION: 147 It would be chaotic to have the people who are working on the project starting activities whenever they think fit. What product does PRINCE2 use to control this? A. Project Issue B. Work Package C. Checkpoint Report D. Risk Log QUESTION: 148 What element of PRINCE2 provides an objective measurement for progress control? management A. Quality Review

42 B. Checkpoint Report C. Highlight Report D. End Stage Report QUESTION: 149 What environment does PRINCE2 assume? A. A fixed-price contract B. A Customer/Supplier environment C. A specialist environment D. A third-party environment QUESTION: 150 The Project Board has three responsibilities towards the Management of Risk. Which of the following options is the FALSE one? A. Notifying the Project Manager of any external risk exposure to the project B. Ensuring that risks are identified, recorded and regularly reviewed C. Making decisions on recommended reactions to risk D. Striking a balance between level of risk and potential benefits QUESTION: 151 There are 6 variables involved in all projects. The first 5 are costs, timescales, quality, scope and risk. What is the 6th? A. Products B. Management C. Outcomes D. Benefits QUESTION: 152

43 In the Plan the Next Stage activity, which project role is responsible for reviewing the next Stage Plan? A. Project Manager B. Project Assurance C. Senior User D. Corporate/Programme Management QUESTION: 153 What is the first step in Product-based Planning? A. Create a Product Breakdown Structure B. Write a Project Product Description C. Create a Product Flow Diagram D. Write Product Descriptions QUESTION: 154 Controlling a Stage describes the day-to-day work of the Project Manager. Which of the following statements is false? A. In Controlling a Stage, the Stage Plan is updated with actuals and progress is checked against the plan B. Controlling a Stage drives Managing Product Delivery C. The Project Manager uses the process Controlling a Stage to manage any deviations from Stage or Project Plans D. All of Controlling a Stage is used in a time-driven manner QUESTION: 155 At which point should a project be terminated? A. A project should be terminated once it is predicted to exceed the project tolerance B. A project should be terminated if the Project Manager or a member of the Project Board resigns

44 C. Once a project commences, it should continue to completion D. A project should be terminated when the Project Board decides that the project is no longer viable QUESTION: 156 The Project Mandate is usually derived from: A. A sketch on the back of an envelope? B. The very first PRINCE2 process? C. A PRINCE2 project think-tank of the Project Manager, other team members and the Project Board? D. Programme or corporate management? QUESTION: 157 Which process is the Quality Register created? A. Initiating a Project B. Managing Product Delivery C. Controlling a Stage D. Starting Up a project QUESTION: 158 At which point does the PRINCE2 Project Board carry out its first major activity? A. After Starting up a Project B. Once corporate / programme management has given a Project Mandate C. At the beginning of Starting up a Project D. Once the Project Mandate has been created QUESTION: 159

45 Which of the following does not aid the Project Manager in exerting control? A. Project Initiation Documentation B. Work Package C. Exception Plan D. Project Plan QUESTION: 160 Which of the following is an in put to the Plan the Next Stage activity in the Managing a Stage Boundary process? A. Issue Register B. Checkpoint Report C. Project Product Descriptions D. Exception Plan QUESTION: 161 Which of the following are produced during the Starting Up a Project stage? A. Project Plan B. Project Initiation Document C. Project Quality Plan D. Project Brief QUESTION: 162 Which of the following is a trigger for the Project Manager to update the Stage Plan with actuals? A. Once agreed, the Stage Plan never gets updated B. Receipt of a Checkpoint Report from a team manager C. Receipt of a Project Issue D. An entry made into the daily log

46 QUESTION: 163 A Project Mandate is turned into a Project Brief by which of the following processes? A. Managing Product Delivery B. Starting Up a Project C. Initiating a Project D. Authorising Initiation QUESTION: 164 Which product documents issues and should be monitored on a regular basis? A. Daily Log B. Issue Register C. Lessons Log D. Issue Report QUESTION: 165 Which of the following is NOT a step in PRINCE2 Risk Management? A. Assess B. Risk budget C. Identify D. Implement QUESTION: 166 Which Process is used to design the Project Management Team? A. Initiating a Project B. Authorising a Project

47 C. Starting Up a Project D. Directing a Project QUESTION: 167 Which of the following is not an objective of the process Initiating a Project? A. It encourages the Project Board to take ownership of the project B. It provides the benchmark for decision-making processes throughout the projects life C. It confirms the existence of an acceptable Business Case justifying the project D. It ensures that all project management authorities are appointed QUESTION: 168 Which of the following is NOT an objective of the process Controlling a Stage? A. Ensure that quality is achieved as planned B. Manage any deviations from Stage or Project Plans C. Identifying the key products that the project will deliver D. Manage on-time delivery of products within agreed tolerances QUESTION: 169 Whose responsibility is it to supply the Customer s quality expectations? A. Project Manager B. Senior User C. Executive D. Senior Supplier QUESTION: 170 The Project Board keeps a control of the project through: 1. Highlight Reports

48 2. Checkpoint Reports 3. Exception assessment 4. Quality Log A. 1, 3 and 4 only B. All of the above C. land 3 only D. 1, 2 and 3 only QUESTION: 171 Which of the following is a stable element within the Project Initiation Document? A. Business Case B. Project Plan C. Project tolerance D. Risk Log QUESTION: 172 Which of the following are NOT covered in the management product Project Approach? 1. Whether the solution is to be bespoke 2. What quality levels the product must meet 3. Whether an off the shelf product will be used A. 2 B. 2&3 C. None of the above D. 1&2 QUESTION: 173 Which of the following is an in put to the Prepare the Communication Management Strategy?

49 A. Stage Plan B. Quality Management Strategy C. Configuration Item Record D. Benefits Review Plan QUESTION: 174 Which of the following is the definition for an off-specification? A. An issue the Project Manager needs to resolve or escalate B. Something forecast or currently not meeting society C. A proposal for a change to a basket D. A statement of concern QUESTION: 175 In which strategy would the change control process be recorded? A. Quay Management Strategy B. Configuration Management Strategy C. Risk Management Strategy D. Communication Management Strategy QUESTION: 176 It me Project Board are too busy to authorize all change requests themsekes they can appoint...? A. A Change Authorty B. A Change Board C. A Change Commtee D. A Change Budget QUESTION: 177

50 What is the purpose of a Product Status Account? A. A set of records that descrbe rformaton about the project B. A bg used to record problems or concerns about products C. An aud( or review to compare actual status of products D. A report covemg the status about the state of the projects products withn QUESTION: 178 When examining a project issue, which three aspects should be considered? 1. Performance targets 2. Business Case 3. Resources 4. Risk A. 1,3,4 B. 2,3,4 C. 1,2,4 D. 1,2,3 QUESTION: 179 Who would be responsible for maintaining the Configuration Item Records? A. Project Manager B. Project Support C. Project Assurance D. Team Manager QUESTION: 180 When does Directing a Project begin? A. From the beginning of Starting up a Project B. From the begnniig of Inliatrig a Project C. From the completion of Startng up a Project D. From the completion of Tniatiig a Project

51 QUESTION: 181 Which management product do the Project Board use to decide whether to authonse initiation? A. Project Bnef B. Busness Case C. Project Intiation Documentation D. Project Product Descrption QUESTION: 182 Which of the following is NOT a tngger fo the project marager to authorise a work package? A. Stage Authonsation B. Correctie Action C. Exception plan approved D. Reporting hjhkjhts QUESTION: 183 Which activity is responsible for updating the stage plan with actual during Controlling a Stage? A. Review the stage status B. Review work package status C. Repot Hhbghts D. Take corrective action QUESTION: 184 During Execubng a Work package, specialist products are createi and quality reviews are carried out which management product captures the details of these reviews?

52 A. Team Plan B. Checkpoint Report C. Quay Register D. Configuration Item Record QUESTION: 185 During a work package the Team manager needs to keep the project manager informed, which management product is used for this? A. Highhght report B. Checkpont Report C. Issue Report D. End Stage Report QUESTION: 186 When updating the project plan as part of Managing a stage boundary, what else might be updated? A. Exception P an B. Project Management team C. Busriess Case D. Project Inaiabon Documentation QUESTION: 187 Whicti of the following management products is NOT updated as part of Managing a stage boundary? 1. Business Case 2 Benefits Review Plan 3. Configuration Item Records 4. Project Brief A. 1,2,3 B. 1,3,4

53 C. 1,2,4 D. 23,4 QUESTION: 188 Which of the following activities could tngger the production of an exception plan? A.Review Stage status B. Givng ad hoc drection C. Escalatng a project issue D. Report stage end QUESTION: 189 Which of the following statements is FALSE regarding the Continued Business Justifcation A. The justifcaton for the project must reman the same throughout the project. B. The justaficabon for the project shouki remali vahd. C. The justification for the project may change. D. If the project is no longer justified t should be stopped. QUESTION: 190 Which of the following activties is NOT an action of preparing for planned closure? A. Update the project plan wth actua B. Update the Project Management Team C. Request a product status account D. Confirm project has dehvered what defned ii Project PrOduCt Descrtion QUESTION: 191 Whicts princpie Is supported by the activity Evaluate the Project9

54 A. Continued Business Justificaton B. Defried roles and responsbies C. Learn from experence D. Manage by stages QUESTION: 192 Which of the following is False? A Successful project management team should, A. Have business, user and suppler stakeholders representation B. Never be reviewed as members should stay with the team for the duration C. Ensure appropriate governance by defiling responsive for directing, managing and delving the project and clearly defining accountable at all levels D. Have an effective strategy to manage communication flows to and from stakeholders QUESTION: 193 Which of the following statements is true of the business interest on the project? A. Ensures the project provides value for money B. Ensures the requirements for the project are defined C. Ensures the products produced meet the desired quality D. Represents the users of the product QUESTION: 194 Which of the following represents the four key characteristics a good Project board should di splay? A. Authority, Credulity, Ointment, Availably B. Authority, Credibity, Delegation, Avadabity C. Authority, Availably, Connections, Delegation D. Authority, Crudity, Connections, Delegation

55 QUESTION: 195 In which Management product would the Project Board specify where the authority for change requests lies? A. Risk Management Strategy B. Quaky Management Strategy C. Communication Strategy D. Configuration Management Strategy QUESTION: 196 Who is responsible for ensuring That Communication Management Strategy is appropriate and that planned communication activities actually take place? A. Project Assurance B. Project Manager C. Corporate or Programme Management D. Project Support QUESTION: 197 Which of the following roles cannot be combined? A. Executive and Senior User B. Project Manager and Project Support C. Project Assurance and Team Manager D. Senior Supplier and Supplier Assurance QUESTION: 198 PRINCE2 proposes 3 levels of Plan, which are they? A. Initiation, Project and Stage Plans

56 B. Project, Stage and Exception Plans C. I Initiation, Project and Benefit Review Plans D. Project, Stage and Team Plans QUESTION: 199 Having completed designing the plan, in which order should the next steps take place to produce a plan? 1 Prepare Estimates 2 Define and analyze Products 3. Prepare the schedule 4. Identify activities and dependencies A. 2,4,3,1 B. 4,2,1,3 C. 4,3,2,1 D. 2,4,1,3 QUESTION: 200 Product based planning focuses on which of the following 1. Creating product descriptions 2. Identifying activities 3 Creating a Product hierarchy 4. Creating a Product sequence A. 1,2,3 B. 2,3,4 C. 1,3,4 D. 1,2,4 QUESTION: 201 Who sets the tolerances for a work package? A. The project board B. The project manager

57 C. The team manager D. Corporate or programme management QUESTION: 202 Which of the following is not part of the composition of a Plan? A. Pre-requests B. Assumptions C. Quality responsibilities D. Product descriptions QUESTION: 203 Who is responsible for committing user resources to the project? A. Senior User B. Senior Suppler C. Executive D. Project Board QUESTION: 204 Which ol the following statements describes an outcome? A. Any of the projects specialist products B. A result of the change derived from using the project s products C. A measurable improvement resulting from a change D. Something perceived as advantages by a stakeho¼ier QUESTION: 205 Which of the following should NOT be included in the business case? A. Reasons

58 B. Major Risks C. Business options D. Business approach QUESTION: 206 When considering the business options in the business case, which of these is NOT an option? A. Do nothing B. Do the maximum C. Do the minimum D. Do something QUESTION: 207 Which of the following statements s TRUE with regard to expected benefits? A. They cannot be assented B. They don t need to follow corporate objectives C. They should be measured D. Tolerances cannot be set against expected benefits QUESTION: 208 Who is responsible for ensuring that the value-for- money solution is constantly reassessed? A. Business Assurance B. Senior User C. Corporate or Programme Management D. Project Support QUESTION: 209

59 Which of the following activities is the Executive responsible for? A. Ensure the desired B. Responsible for the C. Assess and update D. Responsible for the QUESTION: 210 Which of the following principles describes this statement? xxx defines tolerances for each project objective to establish limits of delegated authority A. Manage by stages B. Focus on products C. Manage by exception D. Learn from experience QUESTION: 211 Which of the following statements is NOT correct The Learn from Experience principle suggests that lessons should be actively sought.. A. When Starting a Project B. When initiating a Project C. As the project progresses D. As the project doses Answer: c QUESTION: 212 Which of the following principles uses Product Descriptions to provide clarity by defining each products purpose, composition, derivation, format, quality criteria and quality method? A. Tailor to suit the project environment B. Focus on products C. Manage by stages

60 D. Continued business justification QUESTION: 213 Which of the following statements is FALSE regarding the Continued Business Justification? A. The justification for the project must remain the same throughout the project B. The justification for the project should remain valid C. The justications for the project may change D. If the project is no longer justified t. should be stopped QUESTION: 214 The Manage by Exception principle sets tolerances for six areas of the project, Time, Cost and Qualities are three of them, what are the other three? A. Scope, People & Resources, Benefit B. Scope, Risk, Product C. Risk, Benefit, Product D. Scope, Risk. Benefit QUESTION: 215 Which statement best explains the purpose of Tailor to suit the project environment? A. Ensure project controls are based on project s scab, complexity, repentance, capably and risk B. To use a set of pre-defined templates for the size of project C. To tailor the use of the principles to suit the project D. To pick which PRTNCE2 processes to apply and which to leave out QUESTION: 216

Purpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed

Purpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed Key Learning Points The Swirl Logo is a trade mark of the AXELOS Limited. Is used by the Project Board throughout the project to verify its continued viability:- Is the investment in this project still

More information

BUY ONLINE AT: http://www.itgovernance.co.uk/products/1748

BUY ONLINE AT: http://www.itgovernance.co.uk/products/1748 PRINCE2 FOR DUMMIES Introduction About This Book Foolish Assumptions How This Book is Organised Part I: How PRINCE Can Help You Part II: Working Through Your Project Part III: Help with PRINCE Project

More information

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management

Retained Fire Fighters Union. Introduction to PRINCE2 Project Management Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type

More information

1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles

1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles 1. What is PRINCE2? Projects In a Controlled Environment Structured project management method Generic based on proven principles Isolates the management from the specialist 2 1.1. What is a Project? Change

More information

PRINCE2:2009 Glossary of Terms (English)

PRINCE2:2009 Glossary of Terms (English) accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain

More information

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce

Maturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO

More information

The Foundation Examination

The Foundation Examination The Foundation Examination Sample Paper 2 January 2013 Release Multiple Choice 1-hour paper Instructions 1. All 75 questions should be attempted. 2. 5 of the 75 questions are under trial and will not contribute

More information

WHAT IS PRINCE2? Benefits There are many benefits of using PRINCE2 but primarily it:

WHAT IS PRINCE2? Benefits There are many benefits of using PRINCE2 but primarily it: WHAT IS PRINCE2? Introduction PRINCE2 (Projects in a Controlled Environment) is a structured project management method that can be applied regardless of project scale, type, organisation, geography or

More information

Managing Successful Projects

Managing Successful Projects 2008 AGI-Information Management Consultants May be used for personal purporses only or by libraries associated to dandelon.com network. Managing Successful Projects with PRINCE2 Office of Government Commerce

More information

Prince 2 Health Check

Prince 2 Health Check Prince 2 Health Check Start-up Was there a Project Mandate? Was the Project Board designed/appointed before initiation was authorised? Was a Project Brief produced? Is the Project Brief to PRINCE standards?

More information

An Introduction to PRINCE2

An Introduction to PRINCE2 Project Management Methodologies An Introduction to PRINCE2 Why use a Project Methodology and What Does PRINCE2 Enable? PRINCE - PRojects IN Controlled Environments - is a project management method covering

More information

A COMPARISON OF PRINCE2 AGAINST PMBOK

A COMPARISON OF PRINCE2 AGAINST PMBOK Introduction This comparison takes each part of the PMBOK and gives an opinion on what match there is with elements of the PRINCE2 method. It can be used in any discussion of the respective merits of the

More information

The principles of PRINCE2

The principles of PRINCE2 The principles of PRINCE2 The project management framework known as PRINCE2 is based upon a set of principles. These principles are the bedrock and foundations upon which everything else in the framework

More information

Project Management Standards: A Review of Certifications/Certificates

Project Management Standards: A Review of Certifications/Certificates Project Standards: A Review of Certifications/Certificates Standards for Project Supporting Certification and Certificates Certificate Certification The Project Body of Knowledge PMBOK Guide Projects in

More information

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room. APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use

More information

INTRODUCTION TO PROJECT MANAGEMENT FRAMEWORKS

INTRODUCTION TO PROJECT MANAGEMENT FRAMEWORKS Economic Cooperation Organisation and United Nations in Iran INTRODUCTION TO PROJECT MANAGEMENT FRAMEWORKS Ali Farzin - United Nations Project Management Workshop February 24-25, 2010 Tehran WORKSHOP

More information

B.2.2. Project Management Principles

B.2.2. Project Management Principles B.2.2. Project Management Principles Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations

More information

University of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further

University of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further University of Cambridge Information Services Committee Governance of ISC Projects Originated January 2009 (updated December 2011; awaiting further revision June 2014) 1. Introduction This paper defines

More information

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)

PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value

More information

PRINCE2 Introduction PRINCE2 Introduction

PRINCE2 Introduction PRINCE2 Introduction Managing Successful Projects with PRINCE2 PRINCE2 Introduction PRINCE2 Introduction A Summary of PRINCE2 Managing Successful Projects with PRINCE2 OGC/APM Group Accredited Event UKAS/APMG Certificate 001

More information

PRINCE2 Practitioner - Instructor: Patrick von Schlag

PRINCE2 Practitioner - Instructor: Patrick von Schlag PRINCE2 Practitioner - Instructor: Patrick von Schlag Time Clips Course Introduction Course Introduction 0:00:10 0:01:25 0:01:06 0:02:41 3 Chapter 01 - Course Introduction Lesson: Course Introduction 0:00:10

More information

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.

General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided. Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

ICT Service Desk Creation

ICT Service Desk Creation ICT Service Desk Creation Project Initiation Document Document: ICT Service desk Creation: PID Issue Date: 26 th November 2010 Version: 0.1 Draft Version Number: 1.0 Change Control Quality Assurance Document:

More information

How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC. Abstract. About PRINCE2

How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC. Abstract. About PRINCE2 How PRINCE2 Can Complement PMBOK and Your PMP Jay M. Siegelaub Impact Strategies LLC Abstract PMBOK is the recognized (de facto) standard of project management knowledge. In the UK and Europe, PRINCE2

More information

Operations. Group Standard. Business Operations process forms the core of all our business activities

Operations. Group Standard. Business Operations process forms the core of all our business activities Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations

More information

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan

An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan Of interest to students of Paper P5 Integrated Management. Increasingly, there seems to be a greater recognition of the

More information

Managing a Successful Project Using Syllabus

Managing a Successful Project Using Syllabus Managing a Successful Project Using 2013 Version 1.5 (Status Live) Page 0 Ow ner Chief Examiner 1. Introduction The Managing Successful Projects w ith PRINCE2 manual provides guidance on the principles,

More information

Project Sizing Guide. Property & Campus Services

Project Sizing Guide. Property & Campus Services Purpose This document is intended to assist in deciding what sort of management overheads would be justified for a proposed project. Instructions for Use 1. Evaluate the proposed work against each of the

More information

PROCESS FOR CHANGE Programme Governance Plan

PROCESS FOR CHANGE Programme Governance Plan High Level Design Stage and Beyond Arrangements for Programme and Project Management Recognising the complexity of delivering all the elements of the programme in a tight timescale the following governance

More information

Copyright protected. Use is for Single Users only via a VHP Approved License. For information and printed versions please see www.vanharen.

Copyright protected. Use is for Single Users only via a VHP Approved License. For information and printed versions please see www.vanharen. Colofon Title: Author: Editor: Reviewers: (for the Best Practice User Group Nederland) Publisher: PRINCE2 2009 Edition Quick Reference Card Henny Portman Steve Newton Hans Schneider Ron Seegers (Projectmeester)

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

South Norfolk Council Project Management Handbook

South Norfolk Council Project Management Handbook South Norfolk Council Project Management Handbook Version 1.0 With special thanks and acknowledgement to the Manchester City Council in particular Kevin Fletcher, Bob Rutt, Julie Sprigg, Alan Holding &

More information

International. How PRINCE2 Can Complement the PMBOK Guide and Your PMP. Jay M. Siegelaub Impact Strategies LLC

International. How PRINCE2 Can Complement the PMBOK Guide and Your PMP. Jay M. Siegelaub Impact Strategies LLC International How PRINCE2 Can Complement the PMBOK Guide and Your PMP Jay M. Siegelaub Impact Strategies LLC A Guide to the Project Management Body of Knowledge (PMBOK Guide) is the recognized (de facto)

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee

Project Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Management Toolkit Version: 1.0 Last Updated: 23rd November- Formally agreed by the Transformation Programme Sub- Committee Page 1 2 Contents 1. Introduction... 3 1.1 Definition of a... 3 1.2 Why have

More information

Resource Management. Determining and managing the people resources on projects can be complex as:

Resource Management. Determining and managing the people resources on projects can be complex as: Baseline Resource Management RESOURCE MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project people resources. Overview This Phase is used to establish

More information

Programme Governance and Management Plan Version 2

Programme Governance and Management Plan Version 2 PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from

More information

BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service

BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS. RDTL MINISTRY OF FINANCE Procurement Service RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 6: ESTABLISHING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which

More information

PRINCE2 and governance

PRINCE2 and governance PRINCE2 and governance Andy Murray, lead author of PRINCE2 (2009) and Director of Outperform UK Ltd White Paper November 2011 2 PRINCE2 and governance Contents 1 Purpose of this white paper 3 2 What is

More information

Project Management. What is Project Management?

Project Management. What is Project Management? Project Management Project Management enables your business to proceed with new initiatives in a way that allows: Costs to be controlled Agreed outcomes to be measured and confirmed Timescales to be met

More information

Project Risk Analysis toolkit

Project Risk Analysis toolkit Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,

More information

Single Stage Light Business Case Template

Single Stage Light Business Case Template Better Business Cases Single Stage Light Business Case Template Prepared by: Prepared for: Date: Version: Status: Better Business Cases Single Stage Light Business Case Template Document Control Document

More information

1. Background and business case

1. Background and business case 1. Background and business case This section explains the context and why the project is being undertaken. It provides the justification for investing the time and resources in the project. 1.1 Reasons

More information

The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements.

The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision of resources to support service requirements. CAPACITY AND AVAILABILITY MANAGEMENT A Project Management Process Area at Maturity Level 3 Purpose The purpose of Capacity and Availability Management (CAM) is to plan and monitor the effective provision

More information

Project Management Competency Standards

Project Management Competency Standards BSB01 Business Services Training Package Project Management Competency Standards CONTENTS BSBPM401A Apply scope management techniques...3 BSBPM402A Apply time management techniques...8 BSBPM403A Apply

More information

CP14 ISSUE 5 DATED 1 st OCTOBER 2015 BINDT Audit Procedure Conformity Assessment and Certification/Verification of Management Systems

CP14 ISSUE 5 DATED 1 st OCTOBER 2015 BINDT Audit Procedure Conformity Assessment and Certification/Verification of Management Systems Certification Services Division Newton Building, St George s Avenue Northampton, NN2 6JB United Kingdom Tel: +44(0)1604-893-811. Fax: +44(0)1604-893-868. E-mail: pcn@bindt.org CP14 ISSUE 5 DATED 1 st OCTOBER

More information

Enterprise Architecture Governance Procedure

Enterprise Architecture Governance Procedure Governance Procedure Adrian Hollister Head of Strategy and Craig Douglas Architect 26 February 2014 Version Control Version Date Detail Contributor 0.1 26/2/2014 Initial Document CJD 0.2 14/3/2014 Amended

More information

Certification Procedure of RSPO Supply Chain Audit

Certification Procedure of RSPO Supply Chain Audit : 1 of 19 Table of Contents 1. Purpose 2. Scope 3. Unit of Certification 3.1 Identity Preserved, Segregation, Mass Balance, 3.2. Book and Claim 4. Definitions 5. Responsibilities 5.1 Head of the Certification

More information

IT Project Management

IT Project Management IT Project Management IT Project Management provides a structured approach to making things happen and in doing so, enables initiatives (projects) to be delivered to time, quality and budget. www.business.wales.gov.uk/superfastbusinesswales

More information

LGS Project Management Methodology

LGS Project Management Methodology Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant

More information

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors

Procurement Transformation Division. Procurement guidance. Engaging and managing consultants. Includes definitions for consultants and contractors Procurement guidance Engaging and managing consultants Includes definitions for consultants and contractors Procurement guidance: Engaging and managing consultants Page 2 of 17 Table of contents Table

More information

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman)

The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) The Project Management Life Cycle By Jason Westland (A book review by R. Max Wideman) 11/17/07 Introduction Editor's Note: We liked so much of this book that we asked for the author's permission to quote

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Project Management Process

Project Management Process Project Management Process Description... 1 STAGE/STEP/TASK SUMMARY LIST... 2 Project Initiation 2 Project Control 4 Project Closure 5 Project Initiation... 7 Step 01: Project Kick Off 10 Step 02: Project

More information

PROJECT RISK MANAGEMENT

PROJECT RISK MANAGEMENT PROJECT RISK MANAGEMENT DEFINITION OF A RISK OR RISK EVENT: A discrete occurrence that may affect the project for good or bad. DEFINITION OF A PROBLEM OR UNCERTAINTY: An uncommon state of nature, characterized

More information

Welcome to the Eastwood Harris Pty Ltd Introduction to PRINCE2 TM Revised 2009 and Microsoft Office Project. Page 1

Welcome to the Eastwood Harris Pty Ltd Introduction to PRINCE2 TM Revised 2009 and Microsoft Office Project. Page 1 Welcome to the Eastwood Harris Pty Ltd Introduction to PRINCE2 TM Revised 2009 and Microsoft Office Project Page 1 Purpose of the Presentation Present an overview of the changes to the PRINCE2 methodology

More information

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7?

HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? HOW TO START WORKING WITH P2WARE PROJECT MANAGER 7? This document contains introduction to P2ware Project Manager 7 views (P2ware Project Manager 7 walkthrough) and shows how to create high quality plans

More information

1.1 Terms of Reference Y P N Comments/Areas for Improvement

1.1 Terms of Reference Y P N Comments/Areas for Improvement 1 Scope of Internal Audit 1.1 Terms of Reference Y P N Comments/Areas for Improvement 1.1.1 Do Terms of Reference: a) Establish the responsibilities and objectives of IA? b) Establish the organisational

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

5.1 Project Control Overview

5.1 Project Control Overview 5.1 Project Control Overview Project Control is a formal process in project management. In most respects, there is not a lot of room for creativity in the Control Phase of project management. The PMBOK

More information

PROJECT MANAGEMENT FRAMEWORK

PROJECT MANAGEMENT FRAMEWORK PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to

More information

Integrating PRINCE2 and Scrum for successful new product development

Integrating PRINCE2 and Scrum for successful new product development 1 Goal Professional Services Pty Ltd 2 Renewtek Pty Ltd Integrating PRINCE2 and Scrum for successful new product development Rankins G J 1 and Kearns M 2 This paper was presented at the Australian Institute

More information

Step by Step Project Planning

Step by Step Project Planning Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2

More information

To provide a procedure and associated guidelines to facilitate the management of project dependencies.

To provide a procedure and associated guidelines to facilitate the management of project dependencies. Management DEPENDENCY MANAGEMENT Purpose To provide a procedure and associated guidelines to facilitate the management of project dependencies. Overview Dependencies in this Phase are defined as actions,

More information

BCS THE CHARTERED INSTITUTE FOR IT BCS HIGHER EDUCATION QUALIFICATIONS. BCS Level 5 Diploma in IT APRIL 2013 IT PROJECT MANAGEMENT EXAMINERS REPORT

BCS THE CHARTERED INSTITUTE FOR IT BCS HIGHER EDUCATION QUALIFICATIONS. BCS Level 5 Diploma in IT APRIL 2013 IT PROJECT MANAGEMENT EXAMINERS REPORT BCS THE CHARTERED INSTITUTE FOR IT BCS HIGHER EDUCATION QUALIFICATIONS BCS Level 5 Diploma in IT APRIL 2013 IT PROJECT MANAGEMENT EAMINERS REPORT Section A A1 a) Name FOUR criteria by which a project can

More information

Blank Project Management Templates. Saving Time! Saving Money! Saving Stress!

Blank Project Management Templates. Saving Time! Saving Money! Saving Stress! www.projectagency.co.uk Blank Project Management Templates Saving Time! Saving Money! Saving Stress! Please feel free to copy any of the attached documents. You can alter any of them to suit the needs

More information

Input, Output and Tools of all Processes

Input, Output and Tools of all Processes 1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /

More information

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)

AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document

More information

Improving Project Governance

Improving Project Governance Improving Project Governance By Phil Mann 31 October 2012 Overview This whitepaper provides a synopsis of the Victorian Government s Ombudsman s Own motion investigation into ICT-enabled, November 2011.

More information

JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management

JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

Structure and Function of the EBS NA Business Unit Project Management Office. EBS NA Project Management Office (PMO): Purpose and Function

Structure and Function of the EBS NA Business Unit Project Management Office. EBS NA Project Management Office (PMO): Purpose and Function TITLE: EBS NA Project Management Office (PMO): Purpose and Function SUMMARY: This document provides standard guidance on the purpose and function of the EBS NA Project Management Office. STATUS: Generic

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

Business Continuity Policy and Business Continuity Management System

Business Continuity Policy and Business Continuity Management System Business Continuity Policy and Business Continuity Management System Summary: This policy sets out the structure for ensuring that the PCT has effective Business Continuity Plans in place in order to maintain

More information

Appendix 14 CORPORATE GOVERNANCE CODE AND CORPORATE GOVERNANCE REPORT

Appendix 14 CORPORATE GOVERNANCE CODE AND CORPORATE GOVERNANCE REPORT Appendix 14 CORPORATE GOVERNANCE CODE AND CORPORATE GOVERNANCE REPORT The Code This Code sets out the principles of good corporate governance, and two levels of recommendations: code provisions; and recommended

More information

TIANGONG INTERNATIONAL COMPANY LIMITED (the Company ) TERMS OF REFERENCE OF AUDIT COMMITTEE

TIANGONG INTERNATIONAL COMPANY LIMITED (the Company ) TERMS OF REFERENCE OF AUDIT COMMITTEE TIANGONG INTERNATIONAL COMPANY LIMITED (the Company ) TERMS OF REFERENCE OF AUDIT COMMITTEE Membership 1. The audit committee (the Committee ) shall consist of not less than three members appointed by

More information

Comparing the Differences and Complementary features of PRINCE2 and the PMI PMBOK Guide

Comparing the Differences and Complementary features of PRINCE2 and the PMI PMBOK Guide Comparing the Differences and Complementary features of PRINCE2 and the Guide PRINCE2 is the UK Government s structured project management method. PMI stands for the Project Management Institute producing

More information

2015 SPOCE Project Management Ltd Managing Successful Projects with PRINCE2

2015 SPOCE Project Management Ltd Managing Successful Projects with PRINCE2 !!"! HO0462_1v0 Page 1 CONTENTS Contents... 1 Acknowledgements.... 2 Event Preparation Instructions Please Read And Follow Carefully... 3 Your On line PRINCE2 Event Preparation... 6 PRINCE2 Primer...

More information

The unclear relationship between change, release and project management

The unclear relationship between change, release and project management Processes 467 The unclear relationship between change, release and project management 7.7 The unclear relationship between change, release and project management Do you have a clear picture of the interfaces

More information

JC GROUP HOLDINGS LIMITED (incorporated in the Cayman Islands with limited liability) (Stock Code: 8326) (the Company ) Audit Committee

JC GROUP HOLDINGS LIMITED (incorporated in the Cayman Islands with limited liability) (Stock Code: 8326) (the Company ) Audit Committee These terms of reference are prepared in English. In case of any inconsistency between the Chinese version and the English version, the English version shall prevail. JC GROUP HOLDINGS LIMITED (incorporated

More information

White Paper On Pilot Method Of ERP Implementation

White Paper On Pilot Method Of ERP Implementation White Paper On Pilot Method Of ERP Implementation Rod Clarke Rod Clarke provides guidance, advice and support to businesses in successfully applying IS/IT in support of their business goals. He brings

More information

Appendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment

Appendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment Appendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment [S19a] Version 2.1 March 2011 COPYRIGHT NOTICE 2011 by the Government of the Hong Kong Special Administrative

More information

Human Services Quality Framework. User Guide

Human Services Quality Framework. User Guide Human Services Quality Framework User Guide Purpose The purpose of the user guide is to assist in interpreting and applying the Human Services Quality Standards and associated indicators across all service

More information

GUIDELINES FOR MANAGING PROJECTS. How to organise, plan and control projects

GUIDELINES FOR MANAGING PROJECTS. How to organise, plan and control projects GUIDELINES FOR MANAGING PROJECTS How to organise, plan and control projects NOVEMBER 2010 CONTENTS Section 0: The Purpose of the Project Management Guidelines... 3 What is a successful project?... 3 Are

More information

DNV GL Assessment Checklist ISO 9001:2015

DNV GL Assessment Checklist ISO 9001:2015 DNV GL Assessment Checklist ISO 9001:2015 Rev 0 - December 2015 4 Context of the Organization No. Question Proc. Ref. Comments 4.1 Understanding the Organization and its context 1 Has the organization

More information

Module 3: Functional Requirements

Module 3: Functional Requirements smart BA Distance Learning Programme Module 3: Functional Requirements Hello and welcome to the smart BA distance learning programme Module 3 in this module you are going to analyse the requirements of

More information

ESKITP7145.01 Manage IT service delivery performance metrics

ESKITP7145.01 Manage IT service delivery performance metrics Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a

More information

Asset Support Contract Model Service Information. Annex 25 Integrated Asset Management

Asset Support Contract Model Service Information. Annex 25 Integrated Asset Management Asset Support Contract Model Annex 25 Integrated Asset Management Page A25-1 SERVICE INFORMATION FOR ASC CONTRACT ANNEX 25 CONTENTS AMENDMENT SHEET Amend. No. Issue Date Amendments Initials Date Page A25-2

More information

NOTICE 158 OF 2014 FINANCIAL SERVICES BOARD REGISTRAR OF LONG-TERM INSURANCE AND SHORT-TERM INSURANCE

NOTICE 158 OF 2014 FINANCIAL SERVICES BOARD REGISTRAR OF LONG-TERM INSURANCE AND SHORT-TERM INSURANCE STAATSKOERANT, 19 DESEMBER 2014 No. 38357 3 BOARD NOTICE NOTICE 158 OF 2014 FINANCIAL SERVICES BOARD REGISTRAR OF LONG-TERM INSURANCE AND SHORT-TERM INSURANCE LONG-TERM INSURANCE ACT, 1998 (ACT NO. 52

More information

Involve-Project Manager

Involve-Project Manager Involve-Project Manager This article will describe: What is Project Management Why is Project Management so important to community and voluntary organisations The Key Phases of Project Management: o Initiation

More information

Complaints Policy and Procedure. Contents. Title: Number: Version: 1.0

Complaints Policy and Procedure. Contents. Title: Number: Version: 1.0 Title: Complaints Policy and Procedure Number: Version: 1.0 Contents 1 Purpose and scope... 2 2 Responsibilities... 2 3 Policy Statement: Aims and Objectives... 4 4 Definition of a complaint... 4 5 Procedure...

More information

ITIL Example change management procedure

ITIL Example change management procedure ITIL Example change management procedure An example change process diagram Change Intiators outside IT (users/customers/supplier/etc.) Change Initiators IT SERVICE DESK Filters change requests RFC REJECT

More information

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party).

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party). CONTRACT MANAGEMENT PROCEDURE Section Risk Management Contact Risk Manager Last Review February 2013 Next Review February 2016 Approval Not required Procedures Contract Initiation Request Mandatory Guidance

More information

BUSINESS CONTINUITY POLICY

BUSINESS CONTINUITY POLICY BUSINESS CONTINUITY POLICY Last Review Date Approving Body n/a Audit Committee Date of Approval 9 th January 2014 Date of Implementation 1 st February 2014 Next Review Date February 2017 Review Responsibility

More information

Business Continuity Planning and Disaster Recovery Planning

Business Continuity Planning and Disaster Recovery Planning 4 Business Continuity Planning and Disaster Recovery Planning Basic Concepts 1. Business Continuity Management: Business Continuity means maintaining the uninterrupted availability of all key business

More information

National IT Project Management Methodology

National IT Project Management Methodology NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA National IT Project Management Methodology Project Reporting Support Guide Version 0.5 Project Reporting Support Guide version 0.5 Page 1 Document Version

More information