Statewide Longitudinal Data System Quarterly Project Oversight Report: Comprehensive Review For January March 2015
|
|
- Jennifer Greene
- 8 years ago
- Views:
Transcription
1 Florida Department of Education Statewide Longitudinal Data System For Period January - March 2015
2 Report Period End: 3/31/2015 Agency Name: Florida Department of Education Project Name: Statewide Longitudinal Data System Project Description: The Statewide Longitudinal Data System (SLDS) incorporates data from numerous sources. The four largest contributors are the staff and student databases for prekindergarten and K-12 reporting, career and adult education (or workforce education), the Florida colleges, and state universities. Other resources include student assessment, facilities, special education, English language learners, early childhood programs, human resources, and employment information. The SLDS program is supported by a combination of federal grants and state appropriation. This project is designed to upgrade key education data systems to improve data management, assist in decision-making, allow for more efficient data collection, broader data accessibility, and tighter data security. To reach the programmatic goals of the grants there are underlying infrastructure and technology components to be achieved as well. Overcoming the incompatibility between outdated platforms with newer, more efficient technologies drives the need to design and implement an enterprise-level data processing environment which will strategically consolidate assets and minimize toolsets. Improved data management and data quality processes will enable the Florida Department of Education (FLDOE) to be more responsive to key executive and legislative interests as well as to the general public while reducing administrative processing costs. Section I: Executive Summary Executive Summary Scope: The project scope is within the acceptable variance range for the reporting period. Cost: The project is under budget (exceeding the acceptable variance range) for the reporting period. Delays in obtaining, and problems with retaining, project resources have resulted in the project spending less than was anticipated. Schedule: The project schedule is within the acceptable variance range for the reporting period. There have been slight delays in some tasks, but the team expects to implement the system by the scheduled completion date. The minor delays are related to retaining the appropriate number of personnel (either due to hiring and retention, or due to competing priorities for resources) and other issues. Risks and Issues: Risks and Issues remained stable for the reporting period. 12/10/2014 Page 2 Revision.01
3 Section II: Scope Scope Summary The project scope is within the acceptable variance range for the reporting period. There have been no scope changes as compared with the Schedule IV-B scope. Although the project has no formal scope document, the Work Breakdown Structure (WBS) and project schedule (extrapolated from the original Schedule IV-B scope) has not changed and is divided into the following sub-projects: Florida Education Identifier (FLEID) Sub-Project This project will improve data security and accuracy for FLDOE student-unique, personal identifier data. Key characteristics of the FLEID system include K-20 use; improved data matching processes; establishment of a secure vault containing all personally identifiable data; and inclusion of tools necessary to assign and manage identification (ID) assignments between the departments, districts and institutions in a more secure and consistent manner. FLEID will minimize the necessity of transmitting personally identifiable information (e.g., social security numbers) and feature a heightened level of secure transmission and storage of personally identifiable information. Business Intelligence (BI) Plan Sub-Project - An Education Information Portal that connects people with reports and statistical information related to PK-12, college, career and adult education and employment outcomes for Florida students, staff and schools. Data Quality (DQ2) Sub-Project - Phase I will allow districts to run data through various edits without using expensive mainframe CPU time and will improve data quality. This will facilitate timely and higher quality data submissions as well as reduce redundant data submissions. High Stakes Class Size Sub-Project Conversion from mainframe processing to client server processing of class size calculations. Metadata Sub-Project Improved business rules, improved transformation processes, established reporting functionality with statistical and interdependency information on data and streamlined identification of useful data elements for FLDOE s data systems. Educational Data Warehouse (EDW) Database Migration Sub-Project Migration of data from the Oracle environment into the SQL Server (enterprise solution) database environment. Data Governance Sub-Project Establish an actionable data governance program to ensure the privacy and confidentiality of education records. The project is an organizational approach to data and information management that is formalized as a set of policies and procedures that encompass the full life cycle of data - from acquisition to disposal. Although organized as part of the SLDS effort, the Data Governance Sub-Project will provide an overarching data governance process that will be used by the entire department (enterprise solution). 12/10/2014 Page 3 Revision.01
4 Scope Variance Discussion The project scope is within the acceptable variance range for the reporting period. 12/10/2014 Page 4 Revision.01
5 Section III: Cost Management Cost Management Summary The project is outside of the acceptable variance range for the reporting period. The project has a spending plan; however, FY Quarter 3 actual costs were 27.25% under budget. Cost Variance Discussion There were a number of factors influencing the cost variance. There were extended procurement activities, the hiring and retention of staff has resulted in less incurred costs than originally planned for FY and there was a delay in contracting with the data governance vendor. These occurrences have affected the actual cost in the reporting period significantly, resulting in approximately $500,000 less being expended than anticipated. Although the under budget variance range is expected to decrease, the project is projected to finish FY under budget. 12/10/2014 Page 5 Revision.01
6 Section IV: Schedule Management Schedule Management Summary The project schedule is within the acceptable variance range for the reporting period. The schedule is not baselined. As of this reporting period, there were 57 late tasks. Current Project Progress: FLEID Sub-Project: BI Plan Sub-Project: Data Quality (DQ2) Sub-Project: High Stakes Class Size Sub-Project: Metadata Sub-Project: 42% complete 88% complete 75% complete 57% complete 98% complete EDW Database Migration Sub-Project: 100% complete The Data Governance Sub-Project is in the procurement process and work has not started as of this reporting date. The Data Quality and High Stakes Sub-Projects will continue to operate into the pilot phase to ensure the quality of system data and assist customer agencies in their adoption and usage of the system. It would benefit the project team to work towards an integrated, baselined master project schedule to support performance management reporting (earned value analysis). The WBS in the schedule should define all deliverables, milestones, tasks, and resources required to complete the project based on the approved project scope. All tasks should be baselined. Once this is in place, FLDOE and the Agency for State Technology (AST) can objectively assess project performance including task and milestone completion dates. Schedule Variance Discussion The project is slightly behind schedule (but within the acceptable variance range) for the reporting period. Although the project schedule reports overdue tasks for the reporting period, the project team has also completed 149 FY Quarter 4 tasks and are ahead of schedule on an additional 19 tasks for FY Quarter 4. Three areas of minor project delays and their resolutions are discussed below: 12/10/2014 Page 6 Revision.01
7 Schedule Variance Discussion Pre FY Quarter 3 delays related to issues discovered with the load testing of the Graduation Rate Report delayed implementation of this report and also subsequent report tasks for the Fine Arts Report and the Enrollment Report. Following the successful deployment of the Graduation Rate Report, work resumed on the Fine Arts Report and the Enrollment Report and both have been completed. The completion of the Florida College Graduation Report was delayed to revise the design based on Legislative staff feedback. This report is back on schedule and will be completed by the June 15, 2015 due date. The High-Stakes Class Size conversion from the legacy mainframe (Oracle) to the SAS application (SQL Server) has resulted in a schedule revision. During execution, it was determined that there was a greater interrelationship among the tasks than originally thought which caused for an adjustment in the completion order of the existing tasks. There was no change in scope or requirements involved in this change. As a result of these changes to the High-Stakes Class Size Sub-Project, there were 57 tasks due to be completed by March 31, 2015 that have been delayed until FY Quarter 4. However, there were 75 High-Stakes tasks due FY Quarter 4 that were completed in FY Quarter 3. The Data Governance Sub-Project was delayed because of procurement / contracting issues. This Data Governance Sub-Project completion date will be slightly delayed (estimated 3 weeks to a month), but this effort is independent of the system and will not affect the implementation of the SLDS. Section V: Risk Assessment Evaluation of Project Risks and Issues Risks and issues remained stable for the reporting period. AST recommends the following risks be addressed by the project team and mitigation strategies be identified: Stakeholder and project team turnover could cause delays in the project s completion. In addition, the current project staff has significant demands (outside the project) for their time. Local funding and management priorities could delay implementation of the SLDS project within customer agencies. 12/10/2014 Page 7 Revision.01
8 AST Risk Assessment Evaluation of the project with the Execution Phase Diagnostic Risk Assessment indicates that the project is low risk at this point in project execution. Although specific project documentation from the Planning Phase is minimal, the project processes currently underway meet project management best practices and the needs of the project. Where possible, functions of the new system are being turned on as they are completed. The Execution Phase of the project is planned to be completed June 30, 2015 with the implementation of the final system functions. There is no indication, at this time, that there will be any delay. Post-implementation of maintenance and support will be provided by the Northwest Regional Data Center (NWRDC) (for equipment and database maintenance) and the software vendor (under a maintenance and support agreement contract). As specific issues with the project are being monitored and most have been resolved, a corrective action plan is not needed. Outstanding problems are being aggressively handled by the project team. Not applicable for this reporting period. Section VI: Corrective Action Plan for Out of Variance Projects AST s Recommended Corrective Action Plan (CAP) # Description Action Completion Date (Planned) Scope Completion Date (Actual) Schedule Cost Risk & Issues 12/10/2014 Page 8 Revision.01
Report on Act 38 of 2009
Report on Act 38 of 2009 An Act Relating to PreK-12 and Higher Education Partnerships Section 3: Electronic Longitudinal Data System REPORT January 15, 2016 Submitted to House and Senate Education Committees
More informationFlorida PALM Quarterly Project Oversight Report: Comprehensive Review For January March 2015
Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Financial Services Project
More informationREQUEST FOR QUOTES FOR BUILDING A PROTOTYPE P20 FLORIDA EDUCATION IDENTIFIER FOR STUDENTS AND STAFF - THE FLEID
REQUEST FOR QUOTES FOR BUILDING A PROTOTYPE P20 FLORIDA EDUCATION IDENTIFIER FOR STUDENTS AND STAFF - THE FLEID Florida Department of Education 325 West Gaines Street Tallahassee, Florida 32399-0400 Please
More informationProject Number: P344. Business Intelligence Tool Data Warehouse Implementation. Project Charter Version 1.2 1/12/2011
Project Number: P344 Business Intelligence Tool Data Warehouse Implementation Project Charter Version 1.2 1/12/2011 Table of Contents I) P344 Business Intelligence Tool Data Warehouse Implementation...
More informationDepartment of Highway Safety & Motor Vehicles Motorist Modernization Project Phase One
Motorist Modernization Project Phase One For Period: April - June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Highway Safety & Motor Vehicles (HSMV) Project Name: Motorist
More informationSECTION I PROJECT SUMMARY (TRW)
SECTION I PROJECT SUMMARY (TRW) Table I Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Managers: Ron McCranie/Andy Loveland Status Meeting Date:
More informationDepartment of Highway Safety & Motor Vehicles Motorist Modernization Project Phase One
Motorist Modernization Project Phase One For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Highway Safety & Motor Vehicles (HSMV) Project Name: Motorist Modernization
More informationQuarterly Performance Review of the Arizona Education Learning and Assessment System: AELAS
Quarterly Performance Review of the Arizona Education Learning and Assessment System: AELAS Submitted to the Arizona Department of Education and the Arizona Department of Administration by WestEd and CELT
More informationCounty of Orange ~ Information Technology Quarterly IT Project Status Detail Report Fiscal Year 2014-15, 1st Quarter
County of Orange ~ Information Technology Quarterly IT Project Detail Report Fiscal Year 2014-15, 1st Quarter Executive Summary The Quarterly IT Project Detail report provides an inventory of all County
More informationOFFICE OF THE CIO. PROCEDURE Informational VERSION: 1.0
OFFICE OF THE CIO PROCEDURE Informational VERSION: 1.0 Purpose Project Management of Major or Large NDUS Information Technology Projects Project Managers Guide/Checklist This procedural process will ensure
More informationState of Montana. Office Of Public Instruction IT Strategic Plan 2014. 1. Executive Summary
State of Montana Office Of Public Instruction IT Strategic Plan 2014 1. Executive Summary 1 The IT Division has experienced dramatic growth of its supported environment in the past three to four years.
More informationReal World Strategies for Migrating and Decommissioning Legacy Applications
Real World Strategies for Migrating and Decommissioning Legacy Applications Final Draft 2014 Sponsored by: Copyright 2014 Contoural, Inc. Introduction Historically, companies have invested millions of
More informationSCOPE... p. 2. DATA STAKEHOLDERS... p. 2. APPLICATION... p. 3. OPERATIONAL CAPACITY.. p. 4. Figure 1: SLDS Data Lifecycle... p. 4
DATA GOVERNANCE PARTNERS 2 TABLE OF CONTENTS SCOPE.... p. 2 DATA STAKEHOLDERS... p. 2 APPLICATION.... p. 3 OPERATIONAL CAPACITY.. p. 4 Figure 1: SLDS Data Lifecycle... p. 4 LEADERSHIP AND ACCOUNTABILITY....
More informationPROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010
More informationResponse to Written Inquiries April 24, 2009 Redesign and Implementation of Improved Cost Allocation Plan
Response to Written Inquiries April 24, 2009 Redesign and Implementation of Improved Cost Allocation Plan 1. Should the vendor proposals include proposals for and the price of cost allocation software
More informationMaine Statewide Longitudinal Data System. August 2009
Maine Statewide Longitudinal Data System August 2009 SLDS Project Goal Design, develop and implement a longitudinal data system that stakeholders can draw upon to make well-informed decisions about improving
More informationQuarterly Performance Review of the Arizona Education Learning and Accountability System: AELAS
Quarterly Performance Review of the Arizona Education Learning and Accountability System: AELAS Submitted to the Arizona Department of Education by WestEd and CELT Date: December 29, 2014 Table of Contents
More informationNorth Carolina Government Business Intelligence Competency Center Program. February 2013. North Carolina Office of the State Controller
North Carolina Government Business Intelligence Competency Center Program February 2013 North Carolina Office of the State Controller David McCoy, State Controller Table of Contents Executive Summary...2
More informationDepartment of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
More informationFinance & Administration Committee Information Item IV-B May 9, 2013 Human Capital Plan
Finance & Administration Committee Information Item IV-B May 9, 2013 Human Capital Plan Page 56 of 71 Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information
More informationSECTION I PROJECT SUMMARY (TRW)
AS OF OCTOBER 11, 2010 SECTION I PROJECT SUMMARY (TRW) Table I Project Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Project Director: Tom McCullion
More informationQuarterly Performance Review of the Arizona Education Learning and Assessment System: AELAS
Quarterly Performance Review of the Arizona Education Learning and Assessment System: AELAS Submitted to the Arizona Department of Education and the Arizona Department of Administration by WestEd and CELT
More informationProject Management Plan for
Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...
More informationNorth Carolina Government Data Analytics Center
North Carolina Government Data Analytics Center Report to the Chairs of the House of Representatives Appropriations Committee Chairs of the Senate Based Budget/Appropriations Committee Joint Legislative
More informationPHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
More informationSENTINEL AUDIT V: STATUS OF
SENTINEL AUDIT V: STATUS OF THE FEDERAL BUREAU OF INVESTIGATION S CASE MANAGEMENT SYSTEM U.S. Department of Justice Office of the Inspector General Audit Division Audit Report 10-03 November 2009 Redacted
More informationPHASE 8: IMPLEMENTATION PHASE
PHASE 8: IMPLEMENTATION PHASE The Implementation Phase has one key activity: deploying the new system in its target environment. Supporting actions include training end-users and preparing to turn the
More informationPerformance Management for Enterprise Applications
performance MANAGEMENT a white paper Performance Management for Enterprise Applications Improving Performance, Compliance and Cost Savings Teleran Technologies, Inc. 333A Route 46 West Fairfield, NJ 07004
More informationGTA Board of Directors September 4, 2014
GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership
More informationVirginia Longitudinal Data System
Virginia Longitudinal Data System Book of Data Governance Version 1.0 Page 1 Signature Page The following parties agree upon the policies and procedures outlined in this version of the VLDS Book of Data
More informationProject Management Guidelines
Project Management Guidelines Overview Section 86-1506 (5) directs the NITC to adopt guidelines regarding project planning and management. The goal of project management is to achieve the objectives of
More informationAudit of Veterans Health Administration Blood Bank Modernization Project
Department of Veterans Affairs Office of Inspector General Audit of Veterans Health Administration Blood Bank Modernization Project Report No. 06-03424-70 February 8, 2008 VA Office of Inspector General
More informationOpportunities with Predictive Analytics. Greg Leflar, Vice President greg.leflar@parivedasolutions.com
Opportunities with Predictive Analytics Greg Leflar, Vice President greg.leflar@parivedasolutions.com Opportunities for Predictive Analytics We help you separate the Value from the Hype The field of predictive
More informationINFORMATION CONNECTED
INFORMATION CONNECTED Business Solutions for the Utilities Industry Primavera Project Portfolio Management Solutions Achieve Operational Excellence with Robust Project Portfolio Management Solutions The
More informationPROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
More informationA. What are the Data Strategy or Master Data Management (MDM) tools currently being utilized? (ex: Hyperion, Cognos, etc) UMUC Response
DATE: July 2, 2013 TO: FROM: RE: All Prospective Proposers Alicia Hopkins Senior Buyer, Information Technology 301-985-7223 Solicitation 91127 Data Strategy Assessment Q&A Addendum dated 07/02/13 The following
More informationTERMS OF REFERENCE (ToR)
TERMS OF REFERENCE (ToR) Consultancy services for Monitoring the Implementation of Computerized Integrated Financial Management Information System (IFMIS) of BREB & PBSs for Institutional Strengthening
More informationHow To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
More informationR00A99. Early Childhood Development. Maryland State Department of Education. Response to the Analyst s Review and Recommendations
R00A99 Early Childhood Development Maryland State Department of Education Response to the Analyst s Review and Recommendations House Education and Economic Development Subcommittee February 26, 2015 Senate
More informationCentralized vs. Federated:
Centralized vs. Federated: State Approaches to P-20W Data Systems Historically, efforts to create a P-20W 1 data repository resulted in the development and use of a single, centralized data system that
More informationCODE: E.003 Financial Services BUDGET AND BUSINESS PLANNING POLICY. 1.2 The essential activities covered by this policy include:
BUDGET AND BUSINESS PLANNING POLICY CONTENTS 1.1 Budget and business planning is undertaken to support strategic planning and decision-making and to serve accountability by enabling administration to plan
More informationOutcome 1.0: Data Warehouse Expansion
1. PROJECT NARRATIVE (Outcomes) Outcome 1.0: Data Warehouse Expansion a. Outcome Summary: Initiated in 2001, the Colorado Department of Education s Enterprise Data Warehouse continues to mature and evolve.
More informationTOPS Cost Proposal Form v1.1 Response #: COST PROPOSAL Cost proposal must include all costs required to perform the work as described, including but not limited to travel costs, labor, overhead, etc. BOTH
More informationFiscal Year 2015-16 Information Technology Request
PROGRAM PLAN STATUS and OIT BEST PRACTICES 2015-046 Approved Program Plan? N/A Date Approved: DOR and OIT collaborated in developing the project RFP including the business, technical, and security specifications.
More informationRealizing the Benefits of Data Modernization
February 2015 Perspective Realizing the Benefits of How to overcome legacy data challenges with innovative technologies and a seamless data modernization roadmap. Companies born into the digital world
More informationADVANTAGES OF IMPLEMENTING A DATA WAREHOUSE DURING AN ERP UPGRADE
ADVANTAGES OF IMPLEMENTING A DATA WAREHOUSE DURING AN ERP UPGRADE Advantages of Implementing a Data Warehouse During an ERP Upgrade Upgrading an ERP system presents a number of challenges to many organizations.
More informationRequest for Resume (RFR) CATS+ Master Contract All Master Contract Provisions Apply. Section 1 General Information
Section 1 General Information RFR Number: (Reference BPO Number) Functional Area (Enter One Only) R00B4400129 FUNCTIONAL AREA 7 INFORMATION SYSTEM SECURITY LABOR CATEGORY Security, Computer Systems Specialist
More informationFixed Scope Offering for. Oracle Taleo EE Saas Implementation
Fixed Scope Offering for Oracle Taleo EE Saas Implementation Agenda Company Profile Business Challenges Business Objectives Solution Proposal Scope Modules and Functionalities Implementation Approach Project
More informationSelf-Funded Multi-Tenant Statewide eprocurement System. Request for Response to Statement of Objectives
Self-Funded Multi-Tenant Statewide eprocurement System Request for Response to Statement of Objectives Department of the Treasury Office of Information Technology & Division of Purchase and Property TABLE
More informationDOC Electronic Timekeeping System Quarterly Project Oversight Report: Comprehensive Review For Period January March 2015
Department of Corrections Electronic Timekeeping System Project For Period: January March 2015 Quarter Ending: 3/31/2015 Agency Name: Department of Corrections (DOC) Project Name: Electronic Timekeeping
More informationDesigning a Microsoft SharePoint 2010 Infrastructure
Course Code: M10231 Vendor: Microsoft Course Overview Duration: 5 RRP: 1,980 Designing a Microsoft SharePoint 2010 Infrastructure Overview This five day ILT course teaches IT professionals to design and
More informationData Integration Initiative Semi Annual Report April 2009. State of North Carolina Office of the State Controller
Data Integration Initiative Semi Annual Report April 2009 State of North Carolina Office of the State Controller David McCoy, State Controller April 1, 2009 Table of Contents I. Background... 1 II. BEACON
More informationBusiness Intelligence Project Management 101
Business Intelligence Project Management 101 Managing BI Projects within the PMI Process Groups Too many times, Business Intelligence (BI) and Data Warehousing project managers are ill-equipped to handle
More informationMNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
More informationDepartment of Human Resources
Workforce Services Workforce Policy and Planning Department Management/ Human Resource Information Systems Employee Relations Employment Compensation and Workforce Analysis Employee Benefits Organizational
More informationManag. Roles. Novemb. ber 20122
Information Technology Manag gement Framework Roles and Respo onsibilities Version 1.2 Novemb ber 20122 ITM Roles and Version History Version ed By Revision Date Approved By Approval Date Description of
More informationPESC Spring 2015 Summit: Community Best Practices Defining Outcomes. 2015 Eduventures, Inc.
PESC Spring 2015 Summit: Community Best Practices Defining Outcomes Agenda Defining Outcomes Data Collection and Sharing Trends Data Sources and Methods Partners and Trusted Sources 2 Defining Outcomes
More informationANSWERS ALASKA S P-20W SLDS
ANSWERS Overview - Legislative Aides February 24, 2014 ANSWERS ALASKA S P-20W SLDS Mission: Deliver outcomes information to Alaska stakeholders to assess, evaluate, and improve the state s education and
More informationProject Audit & Review Checklist. The following provides a detailed checklist to assist the PPO with reviewing the health of a project:
Project Audit & Review Checklist The following provides a detailed checklist to assist the PPO with reviewing the health of a project: Relevance (at this time) Theory & Practice (How relevant is this attribute
More informationPHASE 6: DEVELOPMENT PHASE
PHASE 6: DEVELOPMENT PHASE The Phase features a key step in the project: system construction. The previous phases lay the foundation for system development; the following phases ensure that the product
More informationMichigan Criminal Justice Information Network (MiCJIN) State of Michigan Department of Information Technology & Michigan State Police
Michigan Criminal Justice Information Network (MiCJIN) State of Michigan Department of Information Technology & Michigan State Police NASCIO 2006 Recognition Awards Enterprise Architecture Category Executive
More informationSAMPLE WORK BREAKDOWN STRUCTURES VARIOUS TYPES OF PROJECT
Applications Development Project Sample WBS Management and support Provide project management Provide quality control Conduct meetings and reviews Materials and supplies Travel and living costs Miscellaneous
More informationProgram and Budget Committee
E WO/PBC/21/12 ORIGINAL: ENGLISH DATE: JULY 1, 2013 Program and Budget Committee Twenty-First Session Geneva, September 9 to 13, 2013 PROGRESS REPORT ON THE IMPLEMENTATION OF A COMPREHENSIVE INTEGRATED
More informationAbout this Course This 5 day ILT course teaches IT Professionals to design and deploy Microsoft SharePoint 2010.
Course 10231B: Designing a Microsoft SharePoint 2010 Infrastructure OVERVIEW About this Course This 5 day ILT course teaches IT Professionals to design and deploy Microsoft SharePoint 2010. Audience Profile
More informationWashington State s Use of the IBM Data Governance Unified Process Best Practices
STATS-DC 2012 Data Conference July 12, 2012 Washington State s Use of the IBM Data Governance Unified Process Best Practices Bill Huennekens Washington State Office of Superintendent of Public Instruction,
More informationCloud Development Manager Like Tweet 0
1 of 9 Contact Info. Feedback. Sitemap Advanced Search Home Job Roles Competencies Courses Readiness Kit FAQ Partners NICF Overview Events News Sign In HOME > JOB ROLES > SEARCH JOB ROLE > JOB DETAIL Cloud
More informationSoftware Asset Management on System z
Software Asset Management on System z Mike Zelle Tivoli WW IT Asset Management Marketing SAM in SHARE Project Manager mzelle@us.ibm.com Agenda Why Software Asset Management (SAM) The Discipline of Software
More informationThe 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
More information[Year] State of Michigan MiHIN Shared Services Operational Plan
[Year] State of Michigan MiHIN Shared Services Operational Plan Table of Contents 1 Stakeholder Approvals...1 2 Executive Summary...1 2.1 Governance...2 2.2 Finance...2 2.3 Technical Infrastructure...3
More informationPositive Train Control (PTC) Program Management Plan
Positive Train Control (PTC) Program Management Plan Proposed Framework This document is considered an uncontrolled copy unless it is viewed online in the organization s Program Management Information
More informationUT Market. Project Charter Document. Doc. Ref.: Charter UT Market Version: Draft 6 Status: REVISED on 4/27/2010 Initial Date: 2/4/2010
UT Market Project Charter Document Doc. Ref.: Charter UT Market Version: Draft 6 Status: REVISED on 4/27/2010 Initial Date: 2/4/2010 To be Approved by: FRMS Operational Sponsors and Executive Sponsor Document:
More informationMarch 26, 2013 ADDENDUM NO. 1. RFP #MWJ1304 PeopleSoft Campus Solutions Implementation Project Office of Information Technology
March 26, 2013 ADDENDUM NO. 1 RFP #MWJ1304 PeopleSoft Campus Solutions Implementation Project Office of Information Technology All proposals are due Monday, April 1, 2013, by 12:00 p.m. to: City Colleges
More informationA WHITE PAPER By Silwood Technology Limited
A WHITE PAPER By Silwood Technology Limited Using Safyr to facilitate metadata transparency and communication in major Enterprise Applications Executive Summary Enterprise systems packages such as SAP,
More informationHalton Regional Police Service Public Agenda Recommendation Report
Halton Regional Police Service Public Agenda Recommendation Report To: Chairman and Police Service Board Members From: Chief Stephen J. Tanner Subject: SINGLE SOURCE BUCHANAN TECHNOLOGIES Report #: P15-5-CPS-R-01
More informationEnterprise Performance Life Cycle Management. Guideline
Enterprise Performance Life Cycle Management Guideline Version 2.1 PREPARED BY THE ENTERPRISE PROGRAM MANAGEMENT OFFICE MAY 2011 Table of Contents Document Control...i 1. Introduction... 2 1.1 Purpose...
More informationINFORMATION TECHNOLOGY PROJECT REQUESTS
INFORMATION TECHNOLOGY PROJECT REQUESTS Guidelines & Instructions for Maryland State Agencies Revised Two Step PPR/PIR Approval Process Fiscal Year 2013 Table of Contents Part 1: Overview... 2 1.1 Introduction...
More informationRace to the Top Monthly Report - C3
USED Monthly Pat B Report, C3 IIS, North Carolina, May 2014 1 Race to the Top Monthly Report - C3 Application sub-criterion: (C)(3): Using data to improve instruction STATE s goals for this sub-criterion:
More informationEffective Testing & Quality Assurance in Data Migration Projects. Agile & Accountable Methodology
contents AUT H O R : S W A T I J I N D A L Effective Testing & Quality Assurance in Data Migration Projects Agile & Accountable Methodology Executive Summary... 2 Risks Involved in Data Migration Process...
More informationTemplate K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
More informationCapability Statement. Enterprise Data Management with the Datalynx Data Management Suite
Capability Statement Enterprise Data Management with the Datalynx Data Management Suite Why Datalynx? Like you, Datalynx truly understands the challenges of managing critical business data across a complex
More informationScope of Work Microsoft Infrastructure Upgrade
Introduction Scope of Work Microsoft Infrastructure Upgrade The University of Texas M. D. Anderson Cancer Center (M. D. Anderson) in Houston, Texas, celebrating six decades of Making Cancer History, is
More informationBefore getting started, we need to make sure we. Business Intelligence Project Management 101: Managing BI Projects Within the PMI Process Group
PMI Virtual Library 2010 Carole Wittemann Business Intelligence Project Management 101: Managing BI Projects Within the PMI Process Group By Carole Wittemann, PMP Abstract Too many times, business intelligence
More informationFRMS Transfers. Project Charter Document
FRMS Transfers Project Charter Document FRMS Transfers Charter.docx 1 Last Update Date: 8/2/2011 Executive Summary The FRMS Transfers project will simplify and streamline the process of creating requests
More informationICT Strategy for the Secretariat
ICT Strategy for the Secretariat Stronger ICT for a Better United Nations Briefing for the UN Reform Series organized jointly by UNITAR and the Permanent Mission of Switzerland to the United Nations 4
More informationDivision of Human Resources. Strategic Plan For a Culture of Excellence
Division of Human Resources Strategic Plan For a Culture of Excellence TABLE OF CONTENTS INTRODUCTION... 2 DEPARTMENTAL MISSION STATEMENT ALIGNMENT... 4 HUMAN RESOURCES STRATEGIC DIRECTIONS... 5 HR STRATEGIC
More informationInformation Technology Services. Roadmap 2014-2016
Information Technology Services Roadmap 2014-2016 Introduction This document charts the direction for Humboldt State University s Information Technology Services department over the next three years. It
More informationUpgrade Business Intelligence Software
A REPORT TO THE BOARD OF COMMISSIONERS OF PUBLIC UTILITIES Upgrade Business Intelligence Software Hydro Place April 2012 SUMMARY Hydro uses several tools to provide a Business Intelligence software solution.
More informationApplication Management Services (AMS)
Contents 1. AMS : An Overview 2. AMS : Models 3. Delivery Organization 4. Processes & Tools 5. Transition Methodology 6. Pricing Application Management Services (AMS) Enterprise Application Services Capability
More informationProject Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
More informationBusiness Intelligence at the University of Minnesota
Business Intelligence at the University of Minnesota Defining the need and the solution for a comprehensive decision support system for the University of Minnesota Internal Communications Network December
More informationState ofnorth Dakota Longitudinal Data System Strategic Roadmap Executive Summary
APPENDIXM State ofnorth Dakota Longitudinal Data System Strategic Roadmap Executive Summary Longitudinal Data System Committee Information Technology Department 600 E Boulevard Ave - Dept 112 Bismarck,
More informationMichigan Criminal Justice Information Network (MiCJIN) State of Michigan Department of Information Technology & Michigan State Police
Michigan Criminal Justice Information Network (MiCJIN) State of Michigan Department of Information Technology & Michigan State Police NASCIO 2005 Recognition Awards Enterprise Architecture Category Executive
More informationFor more information about this proposal, contact: [David Greenbaum, Director IST Data Services, 2195 Hearst Avenue #250B, 510-642-7429]
FY 07-08 IT Budget Proposal Chief Information Officer: Data Management Governance ABBA Category One: Institutional Effectiveness ABBA Category Two: Information Technology For more information about this
More informationCase Study. ElegantJ BI Business Intelligence. ElegantJ BI Business Intelligence Implementation for a leading Pipes Manufacturer. www.elegantjbi.
ISO 9001:2008 www.elegantjbi.com Get competitive with ElegantJ BI,today.. To learn more about leveraging ElegantJ BI Solutions for your business, please visit our website. Client The client is one of the
More informationBlueprint for Selecting Improvement Approach
Kenan-Flagler Business School State of North Carolina Business Systems Infrastructure Study Phase II Blueprint for Selecting Improvement Approach Executive Summary January 5, 2004 Business Case www.osc.state.nc.us
More information2015 2015 2 1, 2014 30, 2015. 2014 2015 FY
FY 2015 Budget The Connect for Health Colorado FY 2015 budget is the final budget that will incorporate federal grant funding under the Exchange Implementation Level 2 grant. The following narrative explains
More informationEARLY LEARNING INSIGHT
EARLY LEARNING INSIGHT Delaware s Early Childhood Integrated Data System (ECIDS) Presentation to the Delaware Early Childhood Council February 10, 2015 ECIDS Vision An Early Childhood Integrated Data System
More informationTexas Transportation Institute Information Resources Strategic Plan 2012 2016
Texas Transportation Institute Information Resources Strategic Plan 2012 2016 June 2012 Information Resources Strategic Plan 2012 2016 Texas Transportation Institute The Texas A&M University System The
More informationSTATE OF NORTH CAROLINA
STATE OF NORTH CAROLINA INFORMATION SYSTEMS AUDIT OFFICE OF INFORMATION TECHNOLOGY SERVICES INFORMATION TECHNOLOGY GENERAL CONTROLS OCTOBER 2014 OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA STATE AUDITOR
More information2015 ANNUAL REPORT CHIEF INFORMATION OFFICER UNIVERSITY OF VIRGINIA
Summary In FY2014-15, goals for the CIO areas were aligned around two areas: the Cornerstone Plan (particularly Pillar V, Organizational Excellence, and Pillar II, Research Infrastructure and Services)
More information