COMPLIANCE AUDIT REPORT TransnetBW GmbH

Size: px
Start display at page:

Download "COMPLIANCE AUDIT REPORT TransnetBW GmbH"

Transcription

1 COMPLIANCE AUDIT REPORT TransnetBW GmbH OCTOBER 2013 COMPLIANCE AUDIT CONDUCTED IN TransnetBW CONTROL CENTER IN WENDLINGEN BY THE ENTSO-E RG CE SG CME

2 DISCLAIMER The present Compliance Audit Report is based on the information as provided by the audited company. This report is in no way a guarantee that security and reliability on the system of the audited company and/or on the whole synchronously interconnected system of the Regional Group Continental Europe (RGCE) is ensured. This report cannot be considered as a certification of whatever form. Finally, this report does not as such have any impact on the compliance, by the audited company and/or by any other member of ENTSO-E, with the RGCE Operation Handbook and/or any other relevant applicable standard. Page 2 of 65

3 Contents 1 EXECUTIVE SUMMARY COMPLIANCE MONITORING IN ENTSO-E RGCE AUDITED TSO AUDITED OH STANDARDS RESULTS AUDIT REPRESENTATIVES AUDIT PLAN GENERAL PROCEDURES SCOPE METHODOLOGY EVALUATION PRINCIPLES CONFIDENTIALITY AUDIT WORKSHEET FOR 2013 ONSITE AUDIT OH STANDARD P4-A-S2. RELEVANT ELEMENTS OH STANDARD P4-A-S2.1. CRITICAL ELEMENTS OH STANDARD P4-A-S3. EXCHANGE OF INFORMATION OH STANDARD P4-A-S4.1. LONG-TERM PLANNING OH STANDARD P4-A-S5. CONFIRMATION OF PLANNED OUTAGES OH STANDARD P4-B-S2. CAPACITY ASSESSMENT OH STANDARD P4-B-S3. HARMONISATION OF CAPACITY VALUES OH STANDARD P4-B-S4. PROCEDURE FOR THE CAPACITY ASSESSMENT OH STANDARD P4-B-S6. WEEKLY OPERATIONAL TELECONFERENCE OH STANDARD P4-B-S7. CALCULATION OF ATC VALUES OH STANDARD P4-C-S2.1. NETWORK MODEL OH STANDARD P4-C-S3. DATA COLLECTION OH STANDARD P4-C-S9. SECURITY CHECK OH STANDARD P4-C-S11. ADDITIONAL DATA CONCLUSIONS SIGNATURE PAGE...65 Page 3 of 65

4 1 EXECUTIVE SUMMARY 1.1 COMPLIANCE MONITORING IN ENTSO-E RGCE The mission of the ENTSO-E System Operation Committee Regional Group Continental Europe (RGCE) is to improve the reliability and security of the interconnected power system in the Continental Europe through developing and enforcing RGCE Operation Handbook (OH) standards, monitoring the interconnected power system and assessing its future adequacy. The RGCE member TSOs are subject to compliance with all approved OH standards. The Compliance Monitoring Program (CMP) is the RGCE program that monitors and assesses compliance with these standards via: the annual process of self-assessment, which is applied to all TSOs, as well as the annual process of mandatory on-site compliance audits, which is applied to a certain number of TSOs chosen on a rotating base either directly (in case of doubts that a certain TSO complies with OH Standards) or by random. SG Compliance Monitoring & Enforcement (CME) is in charge of performing above mentioned two processes. The 2013 is the fourth year of conducting mandatory compliance audits. SG CME performed 4 voluntary compliance audits in and 18 mandatory audits in AUDITED TSO The RGCE member TSO TransnetBW was chosen for a Compliance Audit in CME conducted the audit on 16 & 17 October 2013 at TransnetBW Control Center in Wendlingen (Germany). 1.3 AUDITED OH STANDARDS The Compliance Audit encompassed 14 standards of Operation Handbook Policy 4 (Coordinated Operational Planning). In 2012, TransnetBW made compliance declarations in the self-assessment process for all standards of OH Policy 4, a subset of which has been checked against their evidence during the audit. 1.4 RESULTS The Audit Team audited 14 standards. The Audit Team found that TransnetBW is with all of the audited standards. On the borders TransnetBW-Amprion, TransnetBW-Tennet D, TransnetBW-APG there is no capacity management installed. TransnetBW, Tennet DE, Amprion and APG are in the same bidding zone. Therefore, the N/A declaration for the relevant standards is considered appropriate for these borders. Visiting of national control centre helped the audit team to better understand organisation and processes in the TransnetBW system. Necessary documentation was prepared and made available at the audit location and the representatives of TransnetBW demonstrated that they are familiar with the content of every single document. All explanations were focused to the matter and well presented. The audit team expresses its satisfaction with the TransnetBW approach both in the preparation phase and during the on-site audit. Table 1 describes TransnetBW compliance declaration in self-assessment questionnaire 2012 and compliance audit questionnaire 2013 with compliance level suggestion by the CME audit team after reviewing the evidence for the audited standards. Upgrades are highlighted with green. Standards which kept their declaration level are not highlighted. Page 4 of 65

5 TABLE 1: COMPLIANCE LEVEL CHANGES FOR THE AUDITED OH STANDARDS OH Standard Self- assessment questionnaire 2012 Compliance audit questionnaire 2013 On site compliance audit 2013 P4-A-S2. RELEVANT ELEMENTS P4-A-S2.1. CRITICAL ELEMENTS P4-A-S3. EXCHANGE OF INFORMATION P4-A-S4.1. LONG-TERM PLANNING P4-A-S5. CONFIRMATION OF PLANNED OUTAGES P4-B-S2. CAPACITY ASSESSMENT P4-B-S3. HARMONISATION OF CAPACITY VALUES P4-B-S4. PROCEDURE FOR THE CAPACITY ASSESSMENT P4-B-S6. WEEKLY OPERATIONAL TELECONFERENCE P4-B-S7. CALCULATION OF ATC VALUES P4-C-S2.1. NETWORK MODEL P4-C-S3. DATA COLLECTION P4-C-S9. SECURITY CHECK P4-C-S11. ADDITIONAL DATA Page 5 of 65

6 2 AUDIT REPRESENTATIVES The Audit Team has the task to prepare and perform the Compliance Audit as well as to develop the corresponding audit report. The audit team composition is given on Table 2. The TSO subject to a compliance audit may object any member of the Audit Team on the basis of a conflict of interests or the existence of other circumstances that could interfere with the impartial performance of his or her duties. The audited TSO is obligated to express its concerns with the proposed team member four weeks prior to the team s arrival on-site. TransnetBW did not have any objection. TransnetBW staff present during the compliance audit is given on Table 3. TABLE 2. CME AUDIT TEAM FOR TransnetBW Audit Team role Audit team leader Audit team member Audit team member Compliance Monitoring Advisor Company or association Name address PSE SA Rafal Kuczynski rafal.kuczynski@pse.pl SEPS Martin Jedinak martin.jedinak@sepsas.sk Transelectrica Octavia Unguroiu octavia.unguroiu@transelectrica.ro ENTSO-E Secretariat Emmanouil Styvaktakis emmanouil.styvaktakis@entsoe.eu TABLE 3. TransnetBW AUDIT STAFF Function in the company Manager Operational Planning & Grid Control Expert Capacity Calculation Expert Congestion Management Expert Grid Operation Expert Operational Planning Name Klaus-Wolfgang Tapp David Dudoignon Philipp Kurz Hubert Langen Norman Tietz Page 6 of 65

7 3 AUDIT PLAN 3.1 GENERAL PROCEDURES The audit covered a chosen set of Operation Handbook (OH) standards which had already been monitored within the Compliance Monitoring Program 2012 self-assessment process. The completed Audit Worksheet was sent by to the ENTSO-E Secretariat and carbon copies to all Audit Team members three weeks before the first audit day. The complete schedule of the audit process for TransnetBW is given on Table 4. All documentation (evidence) required for the onsite audit of each standard was available as a hard copy or in electronic format at the audit location. The Control Area Manager and/or other responsible expert personnel were available during the audit to provide guidance to the Audit Team on where to look in the documentation for compliance to the OH standard and, if requested, to give further explanation on criteria and procedures implemented. In preparation for the audit, TransnetBW organised its supporting compliance documentation which is the evidence of the compliance with audited standards. If needed, TransnetBW provided English versions of the documents. In some cases, TransnetBW translated the main title, index and last update of the document for the Audit Team. Previously mentioned preparations was completed prior to the start of the audit. The ENTSO-E RGCE SG CME acknowledges a satisfactory preparation for the audit. All documentation will be considered as confidential audit records and treated as such. The Audit Team will prepare a public report of its audit findings. Page 7 of 65

8 TABLE 4. SCHEDULE FOR THE COMPLIANCE AUDIT Submittal of the audit material on behalf of the Audit Team Objection or concern about audit team personnel Submittal of the completed Audit Worksheet to the Audit Team by TransnetBW Initial draft of the audit report based on the Audit Worksheet sent to TransnetBW by the Audit Team Opening meeting of the Audit Team and CAM of TransnetBW (1) Introduction of the Audit Team members, (2) Description of how the on-site audit will be conducted, (3) Discussion on how confidential information will be handled, (4) Discussion on data access required by the Audit Team, (5) Announcement that TransnetBW will be asked to provide feedback on the audit process and results, (6) Presentation of the TSO and TSO s organization. Start of the OH standards review* Continuation of the OH standards review Internal Audit Team meeting Closing meeting with CAM of TransnetBW (1) Presentation of preliminary audit findings and recommendations to be included on the draft audit report, with a strong emphasis on the evidences for each compliance level or non-compliance identified by the Audit Team, (2) Discussion and feedback by TransnetBW with a possibility to object the findings, (3) In case of any non-compliance or lack of evidence of compliance, first draft proposal of the TSO on an adequate mitigation plan, including deadline. Should such an immediate proposal not be possible, the TSO must submit it afterwards in written copy within seven days. 7 weeks prior to audit weeks prior to audit weeks prior to audit working days prior to audit First audit day, :00 09:30 First audit day, :30 17:30 Second audit day, :00 12:30 Second audit day, :30 14:00 Second audit day, :00 15:30 Delivery of the draft audit report to TransnetBW for review 2 weeks after the audit Remarks by TransnetBW 4 weeks after the audit Delivery of the final audit report to TransnetBW 6 weeks after the audit Acknowledgement of the final Audit Report by ENTSO-E RGCE Plenary and decision on its possible internal or external publishing. RGCE Plenary in 2014 (*) A visit to the control room will be requested by the Audit Team during the standards review. Page 8 of 65

9 3.2 SCOPE The objective of Compliance Audits in 2013 is to check chosen set of standards from OH Policy 4. These standards were also monitored in the 2012 regular compliance process via the self-assessment questionnaire. The scope of a compliance audit encompasses issues which are directly related to the compliance of the audited TSO with the investigated RGCE OH standards and issues which make a general background for the implementation of the OH at the audited TSO. Directly related issues Issues directly related to the audited RGCE OH standards: Existence of TSO s addenda and/or non-compliance declarations/non-compliance self-reports Follow-up of the TSO s mitigation plans to remove the declared non-compliances Self-assessment questionnaires of 2012 stored at the ENTSO-E Secretariat related to audited TSO concerning the audited OH standards Audit Worksheet (AW) 2013 Information and explanations which the Audit Team receives on site General background The compliance audit also encompasses issues of general nature listed below: General policies of the audited TSO rules and procedures for the control centre(s) related to the audited standards Procedures to control the application of the audited OH standards and their follow-up Procedures to improve the compliance with the audited OH standards TSO s internal report related to the implementation of the audited OH standards TSO s internal audits and/or documentation concerning implementation of OH standards TSO s internal bodies (forums, panels) for the implementation of the OH standards 3.3 METHODOLOGY The CME group prepared an audit schedule defining the chronological order of the compliance audit, which the audited TSO accepted without comment. The audit team reviewed the existing material on the audited TSO and its neighbouring TSOs already collected through the self-assessment process in the 2012 self-assessment questionnaires. It also processed (assessed) the answers in the 2013 Audit Worksheet filled in by the audited TSO. The applied methodology includes audit criteria and expectations based on best practices. The adopted criteria are objective, measurable (if possible), complete and relevant to the objectives. At defining the audit methodology, the auditors identified the potential sources of audit evidence and estimated the amount and type of evidence needed. The audit team used an Audit Worksheet (see chapter 4) for reviewing the audited OH standards. The purpose of the AW is to ensure consistency and fairness. By using the AW the Audit Team documented the material reviewed and the observations made. One of the main reasons for an on-site visit is to review the existing documentation and to interview the staff. Thus, the auditors obtain objective evidence which support the self-assessed declarations of the audited TSO. The audit team determined whether the evidence presented by the TSO is sufficient. They did this by assessing the relevance, validity and reliability of the information and documentation presented. Page 9 of 65

10 It was the responsibility of the audited TSO to provide evidence of compliance with all audited OH standards. In most cases the evidence was in written form like documents, plans, programs or records. In some cases the evidence consisted of a review of computerized records or additional supporting material provided at interviews by the staff of the audited TSO. 3.4 EVALUATION PRINCIPLES Preparatory phase activities in charge of Audited TSO Inspection of the exact wording of each audited OH standard and of additional questions formulated by the CME Fill in the audit questionnaire and submit to the audit team before the audit Identification of documents and other material to present to the auditors in order to demonstrate its compliance level with each OH standard Preparatory phase activities in charge of CME Audit team Identification of compliance level declaration inconsistency with neighbouring TSOs (Selfassessment questionnaire 2012 cross-border check regarding compliance level declarations) Analysis of the explanations and comments which the audited TSO made in the selfassessment 2012 and audit questionnaires 2013 in written form in order to evaluate the quality of explanations and comments Identification of the missing explanations in the self-assessment 2012 and audit questionnaire 2013 Analysis of the improvements achieved during the implementation of mitigation and improvement plans declared in the MLA Addendum/Addenda, in the self-assessment questionnaire 2012 and in the Audit Worksheet 2013 in case of non-compliance and sufficient compliance Audit phase Request to the audited TSO to give additional explanations, especially related to standards which were not or not fully addressed by documents and other material mentioned in the selfassessment questionnaire 2012 and audit questionnaire o The goal was to improve the quality of the explanations. Request to the audited TSO to present that evidence and, if necessary, additional evidence, in printed or electronic form o o The goal was to improve the quality of the presented evidence. The goal was to present material relevant to the audited OH standard at all. Request to the audited TSO to remark the titles of all presented documents, their relevant chapters and even relevant passages. Request to the audited TSO to provide further written explanations related to the presented material. 3.5 CONFIDENTIALITY By signing this report the audit team members assure that they will maintain the confidentiality of information obtained during the compliance audit and drafting of the audit report. Moreover, they express their readiness to sign a supplementary confidentiality agreement, if the audited TSO assert such a claim. Page 10 of 65

11 4 AUDIT WORKSHEET FOR 2013 ONSITE AUDIT 4.1 OH STANDARD P4-A-S2. RELEVANT ELEMENTS SELF-ASSESSMENT QUESTIONNAIRE 2012 P4-A-S2 Relevant elements. The set of network elements (e.g. TIE-LINES, internal lines, bus-bars, phase shifters, transformers, major generating units), automatic and protection devices which influence two or more TSOs while being out of operation has to be agreed among involved TSOs on a regional basis. Compliance Level: APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid Explanation for the full compliance declaration: A list of network elements which influence two or more TSOs while being out of operation has been agreed with respective TSOs. This list is included in bilateral contracts (appendix 5). Respective TSOs therefore have knowledge of respective network elements. Additional Questions Do you exchange a list with relevant elements, which could influence two or more TSOs while being out of operation, with the involved partners? APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid Page 11 of 65

12 AUDIT QUESTIONNAIRE 2013 P4-A-S2 Relevant elements. The set of network elements (e.g. TIE-LINES, internal lines, bus-bars, phase shifters, transformers, major generating units), automatic and protection devices which influence two or more TSOs while being out of operation has to be agreed among involved TSOs on a regional basis. Compliance Level: APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid Concise explanation and list of evidences for declared compliance level: TransnetBW and all adjacent TSOs have commonly determined in their respective transmission grids grid elements whose switching state may affect the operation of the adjacent TSOs grids. The relevant grid elements concerned are listed in the respective Agreements on Grid and System Operation Management (AGSOM), within Annexes 5a and 5b. If a risk to grid security is detected during the phase of planning, the TSOs will immediately agree upon appropriate measures to prevent insecure grid operation. The following contracts with respective annexes have been concluded: The structure of the German and English versions of the bilateral contracts is the same. Between TransnetBW and Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an RWE TSO Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von RWE TSO an EnBW TNG Between TransnetBW and APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND- Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an APG Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von APG an EnBW TNG Between TransnetBW and RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages Annex 5a: Grid elements with inter-regional relevance relevant elements (TNG to RTE) and Page 12 of 65

13 Exceptional contingency list Annex 5b: Grid elements with inter-regional relevance relevant elements (RTE to TNG) and Exceptional contingency list Between TransnetBW and swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen Annex 5a: Netzelemente mit überregionaler Bedeutung relevant elements TNG an swissgrid und Exceptional contingency list TNG an swissgrid Annex 5b: Netzelemente mit überregionaler Bedeutung relevant elements swissgrid an TNG und Exceptional contingency list swissgrid an TNG Between TransnetBW and Tennet TSO: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an E.ON Netz Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von E.ON Netz an EnBW TNG Do you have a mitigation plan to the standard? No In case of an existing Addendum or a Non Compliance Declaration; list of evidences for a mitigation plan, comments: Additional Questions Do you exchange a list with relevant elements, which could influence two or more TSOs while being out of operation, with the involved partners? APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid List of evidences, comments: TransnetBW and all adjacent TSOs have commonly determined in their respective transmission grids grid elements whose switching state may affect the operation of the adjacent TSOs grids. The relevant grid elements concerned are listed in the respective Agreements on Grid and System Operation Management (AGSOM), within Annexes 5a and 5b. TransnetBW will review and adjust the lists of relevant elements (Annexes 5a and 5b of the aforementioned bilateral contracts) according to bilateral agreements chapter 7.1 Adjustment of the Agreement on grid and system operation management when necessary yet at least once a year. Page 13 of 65

14 If necessary, TransnetBW will exchange the adjusted lists with the involved partners (cf. NSV TransnetBW TenneT D ). Between TransnetBW and Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an RWE TSO Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von RWE TSO an EnBW TNG Between TransnetBW and APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND- Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an APG Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von APG an EnBW TNG Between TransnetBW and RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages Annex 5a: Grid elements with inter-regional relevance relevant elements (TNG to RTE) and Exceptional contingency list Annex 5b: Grid elements with inter-regional relevance relevant elements (RTE to TNG) and Exceptional contingency list Between TransnetBW and swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen Annex 5a: Netzelemente mit überregionaler Bedeutung relevant elements TNG an swissgrid und Exceptional contingency list TNG an swissgrid Annex 5b: Netzelemente mit überregionaler Bedeutung relevant elements swissgrid an TNG und Exceptional contingency list swissgrid an TNG Between TransnetBW and Tennet TSO: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG Page 14 of 65

15 an E.ON Netz Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von E.ON Netz an EnBW TNG AUDIT PHASE COMPLIANCE AUDIT 2013 Compliance Level suggestion by the audit team: Explanation for the suggested compliance level: TransnetBW presented the following documents (that are kept in the control room): With Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an RWE TSO and Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von RWE TSO an EnBW TNG contained the relevant elements list (latest update: ). With APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND-Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an APG and Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von APG an EnBW TNG contained the relevant elements list (latest update: ). With RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages (signed ). Annex 5a: Grid elements with inter-regional relevance relevant elements (TNG to RTE) and Exceptional contingency list and Annex 5b: Grid elements with inter-regional relevance relevant elements (RTE to TNG) and Exceptional contingency list that contained the relevant elements list (latest update , last signed version: ). With swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Netzelemente mit überregionaler Bedeutung relevant elements TNG an swissgrid und Exceptional contingency list TNG an swissgrid and Annex 5b: Netzelemente mit überregionaler Bedeutung relevant elements swissgrid an TNG und Exceptional contingency list swissgrid an TNG contained the relevant elements list (latest update: ). With Tennet: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an E.ON Netz and Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von E.ON Netz an EnBW TNG contained the relevant elements list (latest update: ). Protection devices are also included in the lists (an example was shown for the list for Amprion). Page 15 of 65

16 4.2 OH STANDARD P4-A-S2.1. CRITICAL ELEMENTS SELF-ASSESSMENT QUESTIONNAIRE 2012 P4-A-S2.1 Critical elements. A subset of relevant elements which are considered to have a major influence on the operational management of the neighbouring systems has to be agreed among involved TSOs. The scheduling of the outages of these elements must be agreed among the TSOs involved on a regional basis This set must include at least the elements considered in the EXTERNAL CONTINGENCY LIST ((?P3-A) determined by each of the TSOs involved in the region. Compliance Level: APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid Explanation for the full compliance declaration: A list of network elements which have a major influence on two or more TSOs while being out of operation is included in bilateral contracts (appendix 5). Planned outages of network elements included in this list will be agreed at least by the involved TSOs on a regional basis (CWE region, Germany- Austria-Switzerland region). Additional Questions Do you have subset of critical elements whose outages must be agreed in advance with neighbouring TSOs APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid Page 16 of 65

17 AUDIT QUESTIONNAIRE 2013 P4-A-S2.1 Critical elements. A subset of relevant elements which are considered to have a major influence on the operational management of the neighbouring systems has to be agreed among involved TSOs. The scheduling of the outages of these elements must be agreed among the TSOs involved on a regional basis This set must include at least the elements considered in the EXTERNAL CONTINGENCY LIST ((>>P3-A) determined by each of the TSOs involved in the region. Compliance Level: APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH Concise explanation and list of evidences for declared compliance level: swissgrid A list of network elements which have a major influence on two or more TSOs while being out of operation is included in bilateral contracts (appendices 5a and 5b). Planned outages of network elements included in this list will be agreed at least by the involved TSOs on a regional basis (CWE region, DACH (Germany-Austria-Switzerland) region). In the CWE outage planning process, TransnetBW, 50Hz, Amprion, Tennet DE, TenneT NL, ELIA, RTE, CREOS, swissgrid participate. In the DACH region Amprion, APG, swissgrid, Tinetz, TransnetBW and VÜN are cooperating. Cf. Anweisungen für den Netzbetrieb Kapitel ( Handbook for System Operation at TransnetBW ): Planned outages in the interconnected grid will be coordinated in the scope of national and international outage planning in order to avoid overlapping planned outages [.] Meetings for coordination of outages will be carried out in November (CWE region) and in December (DACH region (Germany, Austria and Switzerland). The following contracts with respective annexes have been concluded: Between TransnetBW and Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an RWE TSO Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von RWE TSO an EnBW TNG Between TransnetBW and APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND- Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an APG Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von APG an EnBW TNG Page 17 of 65

18 Between TransnetBW and RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages Annex 5a: Grid elements with inter-regional relevance relevant elements (TNG to RTE) and Exceptional contingency list Annex 5b: Grid elements with inter-regional relevance relevant elements (RTE to TNG) and Exceptional contingency list Between TransnetBW and swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen Annex 5a: Netzelemente mit überregionaler Bedeutung relevant elements TNG an swissgrid und Exceptional contingency list TNG an swissgrid Annex 5b: Netzelemente mit überregionaler Bedeutung relevant elements swissgrid an TNG und Exceptional contingency list swissgrid an TNG Between TransnetBW and Tennet TSO: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an E.ON Netz Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von E.ON Netz an EnBW TNG Do you have a mitigation plan to the standard? No In case of an existing Addendum or a Non Compliance Declaration; list of evidences for a mitigation plan, comments: Additional Questions Do you have subset of critical elements whose outages must be agreed in advance with neighbouring TSOs? APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid List of evidences, comments: TransnetBW and all adjacent TSOs have commonly determined in their respective transmission grids those grid elements whose outages will be agreed in the course of the outage planning process with all neighbouring TSOs (according to bilateral contracts chapter Coordination and planning of outages ). Those critical elements ale listed in the respective Agreements on Grid and System Operation Management (AGSOM), within Annexes 5a and 5b. TransnetBW will review and adjusted the lists of critical elements (Annexes 5a and 5b of the Page 18 of 65

19 aforementioned bilateral contracts) according to bilateral agreements chapter 7.1 Adjustment of the Agreement on grid and system operation management when necessary yet at least once a year. If necessary, TransnetBW will exchange the adjusted lists with the involved partners (cf. NSV TransnetBW TenneT D ). The following contracts with respective annexes have been concluded: Between TransnetBW and Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an RWE TSO Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von RWE TSO an EnBW TNG Between TransnetBW and APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND-Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an APG Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von APG an EnBW TNG Between TransnetBW and RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages Annex 5a: Grid elements with inter-regional relevance relevant elements (TNG to RTE) and Exceptional contingency list Annex 5b: Grid elements with inter-regional relevance relevant elements (RTE to TNG) and Exceptional contingency list Between TransnetBW and swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen Annex 5a: Netzelemente mit überregionaler Bedeutung relevant elements TNG an swissgrid und Exceptional contingency list TNG an swissgrid Annex 5b: Netzelemente mit überregionaler Bedeutung relevant elements swissgrid an TNG und Exceptional contingency list swissgrid an TNG Between TransnetBW and Tennet TSO: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen Page 19 of 65

20 Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an E.ON Netz Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von E.ON Netz an EnBW TNG COMPLIANCE AUDIT 2013 Compliance Level suggestion by the audit team: Explanation for the suggested compliance level: TransnetBW presented the following documents (that are kept in the control room): With Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an RWE TSO and Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von RWE TSO an EnBW TNG contained the critical elements list (latest update: ). With APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND-Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an APG and Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von APG an EnBW TNG contained the criticalt elements list (latest update: ). With RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages (signed ). Annex 5a: Grid elements with inter-regional relevance relevant elements (TNG to RTE) and Exceptional contingency list and Annex 5b: Grid elements with inter-regional relevance relevant elements (RTE to TNG) and Exceptional contingency list that contained the critical elements list (latest update , last signed version: ). With swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Netzelemente mit überregionaler Bedeutung relevant elements TNG an swissgrid und Exceptional contingency list TNG an swissgrid and Annex 5b: Netzelemente mit überregionaler Bedeutung relevant elements swissgrid an TNG und Exceptional contingency list swissgrid an TNG contained the critical elements list (latest update: ). With Tennet: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen (signed ). Annex 5a: Schaltungskoordination regional wichtiger Betriebsmittel Information von EnBW TNG an E.ON Netz and Annex 5b: Schaltungskoordination regional wichtiger Betriebsmittel Information von E.ON Netz an EnBW TNG contained the critical elements list (latest update: ). The external contingency list contains all the elements that are defined by TransnetBW as critical. Page 20 of 65

21 4.3 OH STANDARD P4-A-S3. EXCHANGE OF INFORMATION SELF-ASSESSMENT QUESTIONNAIRE 2012 P4-A-S3 Exchange of information. TSOs collect and share information about planned outages of the relevant elements within regional groups. The scheduled outages of critical elements are reviewed at the Weekly Operational Teleconference (>>B- S7: WOPT). Compliance Level: APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid Explanation for the full compliance declaration: Relevant elements are defined in bilateral contracts appendix 5. The outages of these elements communicated to the CWE and CEE WOPT participants upfront the repsective teleconferences. During the CWE WOPT, the outages for the upcoming week are coordinated finally with the affected TSOs. Additional Questions Do you collect and share the planned outages of all relevant elements (in the meaning of critical elements) within the WOPT or other kinds of information exchange (i.e. only with one partner)? APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid Page 21 of 65

22 AUDIT QUESTIONNAIRE 2013 P4-A-S3 Exchange of information. TSOs collect and share information about planned outages of the relevant elements within regional groups. The scheduled outages of critical elements are reviewed at the Weekly Operational Teleconference (>>B- S7: WOPT). Compliance Level: APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH Concise explanation and list of evidences for declared compliance level: swissgrid Information about planned outages of the relevant elements is exchanged in the scope of the yearly outage planning process within CWE and DACH region. The updated outages for the rest of the year are also sent to adjacent TSOs every month in the year. On a weekly basis TransnetBW exchanges the planned outages for the upcoming week with CWE and CEE WOPT participants. Yearly Planning: Document CWE-Liste_2013_v2_offiziell.xls Document DACH_2013_V3_Liste_bearbeitet.xls Monthly Planning: Process description Monatsplanungsprozess (engl. Monthly Outage Planning ) s Monthly Outage Planning Weekly Planning: _Netzsicherheitskonzept_Anlage_1_WOPT_V2R4 - Nachbereitung und Berichtswesen (eng.: Grid security concept Annex 1 WOPT - Reviewing and Documentation) Example of exchanged WOPT document Folder structure in shared mailbox The following contracts naming all relevant elements with respective annexes have been concluded: Between TransnetBW and Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen Between TransnetBW and APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND- Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen Page 22 of 65

23 Between TransnetBW and RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages Between TransnetBW and swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen Between TransnetBW and Tennet TSO: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen Do you have a mitigation plan to the standard? No In case of an existing Addendum or a Non Compliance Declaration; list of evidences for a mitigation plan, comments: Additional Questions Do you collect and share the planned outages of all relevant elements (in the meaning of critical elements) within the WOPT or other kinds of information exchange (i.e. only with one partner)? APG-Austrian Power Grid AG RTE Amprion TenneT TSO GmbH swissgrid List of evidences, comments: Planned outages of all relevant elements are shared within the WOPT (including all adjacent TSOs). Process description WOPT: _Netzsicherheitskonzept_Anlage_1_WOPT_V2R4 - Vorbereitung (eng.: Grid security concept Annex 1 WOPT - Preparation) Example of exchanged WOPT document Folder structure in shared mailbox COMPLIANCE AUDIT 2013 Compliance Level suggestion by the audit team: Explanation for the suggested compliance level: TransnetBW presented the above mentioned documents (that are kept in the control room) that describe the exchange of information process: Page 23 of 65

24 With Amprion: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen (signed ). With APG: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND-Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen (signed ). With RTE: Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages (signed ). With swissgrid: Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen (signed ). With Tennet: Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen (signed ). An for the confirmation of the 2013 outage planning was shown (an from Amprion to the relevant TSOs CWE and DACH); the 2013 planned outages included in this was also shown. An for the confirmation of the monthly outage planning was also presented. In the monthly process, updated outages for the rest of the year are exchanged. TransnetBW shares with the neighbouring TSOs the list produced by a software tool used by TransnetBW for outage planning. For the weekly process, example information exchanged within WOPT was shown. Page 24 of 65

25 4.4 OH STANDARD P4-A-S4.1. LONG-TERM PLANNING SELF-ASSESSMENT QUESTIONNAIRE 2012 P4-A-S4.1 Long-term planning. In the second half of the preceding year, TSOs start outages scheduling in regional groups for the forthcoming year. At the end of the preceding year, TSOs agree on a joint schedule of outages of all network elements impacting two or more TSOs for the next year. Compliance Level: Explanation for the full compliance declaration: At the end of each year, outage planning for the upcoming year is coordinated within CWE-region (including TransnetBW, 50HzT, Amprion, Tennet DE, TenneT NL, ELIA, RTE, CREOS, swissgrid) as well as in the D-A-CH-region (TransnetBW, Amprion, Tennet DE, APG, swissgrid, VKW and TIWAG). As a result a co-ordinated and agreed list of planned outages is shared amongst all affected TSOs. Additional Questions Do you have established a long-term respectively yearly operational outage planning? Do you have at the end of the year a jointly agreed list of planned outages of all relevant elements of all involved partners for the next year? Page 25 of 65

26 AUDIT QUESTIONNAIRE 2013 P4-A-S4.1 Long-term planning. In the second half of the preceding year, TSOs start outages scheduling in regional groups for the forthcoming year. At the end of the preceding year, TSOs agree on a joint schedule of outages of all network elements impacting two or more TSOs for the next year. Compliance Level: Concise explanation and list of evidences for declared compliance level: Each year the responsible colleagues of the CWE-region (RTE, Elia, Creos, TenneT NL, Amprion, swissgrid, TenneT D and TransnetBW) and the DACH-region (APG, swissgrid, TenneT D, Amprion, VÜN, Tinetz and TransnetBW) have meetings where outages for the upcoming year are coordinated and agreed. The main focus is to coordinate all outages of grid elements which have an influence to another TSO s grid and its own outage planning. As a result, the outage of all critical elements will be agreed amongst the respective TSOs. Adjacent TSOs will be informed about the outage of relevant elements. The possibly problematic outages are discussed one by one and adapted if necessary. Evidences: Anweisungen für den Netzbetrieb Chapter Hierzu finden die Koordinationsbesprechungen im November (CWE-Region) und im Dezember (DACH-Region) statt. (eng. Handbook for System Operation at TransnetBW chapter Therefore coordination meetings take place for CWE-Region in November and DACH-Region in December. Bilateral contracts, Chapter Coordination and planning of outages, Chapter Long-term planning Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und RWE Transportnetz Strom GmbH, Dortmund über den Systembetrieb zwischen der EnBW TNG und RWE TSO, Chapter Koordination und Planung von Schaltungen, Chapter Langfristplanung Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und VERBUND-Austrian Power Grid AG, Wien über den Systembetrieb zwischen der EnBW TNG und APG, Chapter Koordination und Planung von Schaltungen, Chapter Langfristplanung Agreement on Grid and System Operation Management between Contracting party TransnetBW GmbH, Germany and Réseau de Transport d Electricité, France, Chapter Coordination and planning of outages Chapter Long-term planning Netz- und Systemführungsvertrag zwischen TransnetBW GmbH, Stuttgart und swissgrid ag, Laufenburg über den Systembetrieb zwischen der TNG und swissgrid, Chapter Koordination und Planung von Schaltungen, Chapter Langfristplanung Netz- und Systemführungsvertrag zwischen EnBW Transportnetze AG, Stuttgart und E.ON Netz GmbH, Bernecker Straße 70, Bayreuth über den Systembetrieb zwischen der EnBW TNG und E.ON Netz, Chapter Koordination und Planung von Schaltungen, Page 26 of 65

COMPLIANCE AUDIT REPORT MACEDONIAN TRANSMISSION SYSTEM OPERATOR AD (MEPSO)

COMPLIANCE AUDIT REPORT MACEDONIAN TRANSMISSION SYSTEM OPERATOR AD (MEPSO) COMPLIANCE AUDIT REPORT MACEDONIAN TRANSMISSION SYSTEM OPERATOR AD (MEPSO) COMPLIANCE AUDIT CONDUCTED IN THE NATIONAL CONTROL CENTRE OF MEPSO IN SKOPJE BY THE ENTSO-E RG CE SG CME DISCLAIMER The present

More information

The pivotal role of TSOs in European energy market integration

The pivotal role of TSOs in European energy market integration The pivotal role of TSOs in European energy market integration To meet the needs of modern society, the energy market is having to change. Concerns about environmental sustainability and dwindling supplies

More information

POLITICAL DECLARATION OF THE PENTALATERAL ENERGY FORUM

POLITICAL DECLARATION OF THE PENTALATERAL ENERGY FORUM POLITICAL DECLARATION OF THE PENTALATERAL ENERGY FORUM The Ministers of the Pentalateral Energy Forum, consisting of Austria, Belgium, France, Germany, Luxembourg, the Netherlands and Switzerland, WELCOMING

More information

[ REPORT ON EU ELECTRICITY MARKET TRANSPARENCY: COUNTRY COMPARISON ]

[ REPORT ON EU ELECTRICITY MARKET TRANSPARENCY: COUNTRY COMPARISON ] 2014 Issued: 21 Aug 2014 Jan Smolen [ REPORT ON EU ELECTRICITY MARKET TRANSPARENCY: COUNTRY COMPARISON ] REVIEW 2 Disclaimer This report is issued by the energy analytics, s.r.o. as its internal document

More information

TABLE OF CONTENTS. Page

TABLE OF CONTENTS. Page 3 TABLE OF CONTENTS Page 1 INTRODUCTION...5 1.1 BACKGROUND AND SCOPE...5 1.2 EXCHANGE OF RESERVES BETWEEN SEPARATE SYNCHRONOUS SYSTEMS...6 2 DEFINITIONS...10 2.1 IMBALANCE...10 2.2 BALANCING CONTROL...11

More information

Cooperation between 50Hertz and ČEPS A stable basis for European Infrastructure

Cooperation between 50Hertz and ČEPS A stable basis for European Infrastructure Cooperation between 50Hertz and ČEPS A stable basis for European Infrastructure Michael Kranhold Head of Corporate Strategy/Cooperation 50Hertz Transmission Agenda 1. 50Hertz the Company 2. Cooperation

More information

Data management - without measuring data nothing works!

Data management - without measuring data nothing works! Data management - without measuring data nothing works! Strict meter data management requirements for distribution grid operators 2009 will see a pioneering innovation in the Swiss electricity market,

More information

System Adequacy for Germany and its Neighbouring Countries: Transnational Monitoring and Assessment

System Adequacy for Germany and its Neighbouring Countries: Transnational Monitoring and Assessment System Adequacy for Germany and its Neighbouring Countries: Transnational Monitoring and Assessment Study commissioned by Federal Ministry for Economic Affairs and Energy Scharnhorststraße 34-37, 10115

More information

Potential cross-border balancing cooperation between the Belgian, Dutch and German electricity Transmission System Operators

Potential cross-border balancing cooperation between the Belgian, Dutch and German electricity Transmission System Operators Potential cross-border balancing cooperation between the Belgian, Dutch and German electricity Transmission System Operators 50Hertz Transmission GmbH, Amprion GmbH, Elia System Operator NV, TenneT TSO

More information

29 October 2015. Disclaimer

29 October 2015. Disclaimer Explanatory document to all TSOs proposal for Capacity Calculation Regions (CCRs) in accordance with Article 15(1) of the Commission Regulation (EU) 2015/1222 of 24 July 2015 establishing a Guideline on

More information

Implementation progress of the EASEE-gas Common Business Practices (CBP's)

Implementation progress of the EASEE-gas Common Business Practices (CBP's) 1 Implementation progress of the EASEE-gas Common Business Practices (CBP's) 1. Introduction The European Association for the Streamlining of Energy Exchange-gas, or EASEE-gas, was established on March

More information

National Technology Platform Smart Grids Austria

National Technology Platform Smart Grids Austria Andreas Lugmaier, MSc Coordinator NTP Smart Grids Austria Siemens AG email: koordinator@smartgrids.at Paper 032 www.smartgrids.at National Technology Platform Smart Grids Austria 1. Background 2. NTP Smart

More information

UCTE Security Package. Jakub Fijalkowski Vienna 20 February 2009

UCTE Security Package. Jakub Fijalkowski Vienna 20 February 2009 Jakub Fijalkowski Vienna 20 February 2009 Presentation outline UCTE mission and structure UCTE Security Package page 2 of 32 European synchronous areas Capacity: 85 GW Peak load: 66 GW Consumption: 400

More information

Internal Audit Strategic and Annual Plans 2015/16

Internal Audit Strategic and Annual Plans 2015/16 Internal Audit Strategic and Annual Plans 2015/16 Financial Scrutiny and Audit Committee 10 February 2015 Agenda Item No 8 Summary: This report provides an overview of the stages followed prior to the

More information

Impediments to Electricity Trading in Central and Eastern Europe (CEE)

Impediments to Electricity Trading in Central and Eastern Europe (CEE) www.pwc.at Impediments to Electricity Trading in Central and Eastern Europe (CEE) Austria, Czech Republic, Germany, Hungary, Poland, Slovakia, Slovenia Traders Survey 2011 2 PwC 2011 Table of Contents

More information

Second Political Declaration of the Pentalateral Energy Forum of 8 June 2015

Second Political Declaration of the Pentalateral Energy Forum of 8 June 2015 PENTALATERAL ENERGY FORUM Second Political Declaration of the Pentalateral Energy Forum of 8 June 2015 The Ministers of the Pentalateral Energy Forum, consisting of Austria, Belgium, France, Germany, Luxembourg,

More information

ACER call for comments on the Network Code on Emergency and Restoration

ACER call for comments on the Network Code on Emergency and Restoration ACER call for comments on the Network Code on Emergency and Restoration Evaluation of responses 23 June 2015 Agency for the Cooperation of Energy Regulators Trg Republike 3 Ljubljana - Slovenia Table of

More information

GUIDANCE NOTE ON THE CONCEPT OF RELIANCE

GUIDANCE NOTE ON THE CONCEPT OF RELIANCE Final version of 23/02/2009 COCOF 09/0002/01-EN EUROPEAN COMMISSION DIRECTORATE-GENERAL REGIONAL POLICY GUIDANCE NOTE ON THE CONCEPT OF RELIANCE ON THE WORK OF OTHER AUDITORS DISCLAIMER This is a Working

More information

Challenges to integrate Renewables In the French and European Power System. Michel Béna, SmartGrids Director

Challenges to integrate Renewables In the French and European Power System. Michel Béna, SmartGrids Director Challenges to integrate Renewables In the French and European Power System Michel Béna, SmartGrids Director EDF R&D, 7th november 2012 RTE, in a few words Owner and Operator of EHV and HV network from

More information

Code of Practice on Electronic Invoicing in Europe

Code of Practice on Electronic Invoicing in Europe Code of Practice on Electronic Invoicing in Europe 24 th March 2009 Version 0.17 Approved by Expert Group Plenary on 24 th March 2009 This Code of Practice on Electronic Invoicing in Europe is recommended

More information

Code of Practice on Electronic Invoicing in Europe

Code of Practice on Electronic Invoicing in Europe Code of Practice on Electronic Invoicing in Europe 24 th March 2009 Version 0.17 Approved by Expert Group Plenary on 24 th March 2009 This Code of Practice on Electronic Invoicing in Europe is recommended

More information

Statistical Factsheet 2013

Statistical Factsheet 2013 Statistical Factsheet 0 (formerly Memo) provisional values as of April 0 European Network of Transmission System Operators for Electricity ENTSO-E in figures Electricity system data of member TSOs countries

More information

How To Create A Power Market In European Power Markets

How To Create A Power Market In European Power Markets THEMA Report 2011-15 ISBN no. 978-82-93150-07-7 Market design and the use of FTRs and CfDs A report prepared for Energy Norway September 2011 CONTENT 1 SUMMARY AND CONCLUSIONS...3 2 INTRODUCTION...4 3

More information

EA IAF/ILAC Guidance. on the Application of ISO/IEC 17020:1998

EA IAF/ILAC Guidance. on the Application of ISO/IEC 17020:1998 Publication Reference EA IAF/ILAC-A4: 2004 EA IAF/ILAC Guidance on the Application of ISO/IEC 17020:1998 PURPOSE This guidance document is for ISO/IEC 17020: General Criteria for the operation of various

More information

ENTSOG Draft Network Code on Interoperability and Data Exchange Rules Public Consultation Questionnaire; GEODE advises on further action

ENTSOG Draft Network Code on Interoperability and Data Exchange Rules Public Consultation Questionnaire; GEODE advises on further action ENTSOG Draft Network Code on Interoperability and Data Exchange Rules Public Consultation Questionnaire; GEODE advises on further action GEODE, the Association of the Independent European Distribution

More information

North American Electric Reliability Corporation. Compliance Monitoring and Enforcement Program. December 19, 2008

North American Electric Reliability Corporation. Compliance Monitoring and Enforcement Program. December 19, 2008 116-390 Village Boulevard Princeton, New Jersey 08540-5721 North American Electric Reliability Corporation Compliance Monitoring and Enforcement Program December 19, 2008 APPENDIX 4C TO THE RULES OF PROCEDURE

More information

1 SCOPE OF APPLICATION

1 SCOPE OF APPLICATION Rules for the Participation in Trading in Electric Power and in the Clearing and Settlement of Exchange Transactions Concluded in Trading in Electric Power on the Vienna Stock Exchangein its Function as

More information

P1 Policy 1: Load-Frequency Control and Performance [C]

P1 Policy 1: Load-Frequency Control and Performance [C] P1 Policy 1: Load-Frequency Control and Performance [C] Chapters A. Primary Control B. Secondary Control C. Tertiary Control D. Time Control Introduction The GENERATION of power units and CONSUMPTION of

More information

In the electricity sector, market coupling with Southern and Eastern neighbouring countries would be beneficial.

In the electricity sector, market coupling with Southern and Eastern neighbouring countries would be beneficial. Austria Key issues In the electricity sector, market coupling with Southern and Eastern neighbouring countries would be beneficial. In gas, the number of system operators could be reduced in view of the

More information

A NEW AUSTRIAN GUIDELINE FOR TUNNEL SAFETY DOCUMENTATIONS

A NEW AUSTRIAN GUIDELINE FOR TUNNEL SAFETY DOCUMENTATIONS - 140 - A NEW AUSTRIAN GUIDELINE FOR TUNNEL SAFETY DOCUMENTATIONS Bopp R. 1, Brandt R. 2, Hörhan R. 3, Hubmayr. C. 3, Wiesholzer F. 3 1 BTC - Bopp Tunnel Consulting GmbH, Switzerland 2 HBI Häerter AG,

More information

Final Draft Framework Guidelines on Capacity Allocation and Congestion Management for Electricity Ref: E10-ENM-20-03 3 February 2011

Final Draft Framework Guidelines on Capacity Allocation and Congestion Management for Electricity Ref: E10-ENM-20-03 3 February 2011 Final Draft Framework Guidelines on Capacity Allocation and Congestion Management for Electricity Ref: E10-ENM-20-03 3 February 2011 European Regulators Group for Electricity and Gas Contact: Council of

More information

Market coupling: looking at the future of the Italian Power Exchange

Market coupling: looking at the future of the Italian Power Exchange Market coupling: looking at the future of the Italian Power Exchange Anna Creti, Eileen Fumagalli IEFE Università Bocconi Elena Fumagalli Politecnico di Milano Giusi Squicciarini Autorità per l energia

More information

National Technology Platform Smart Grids Austria

National Technology Platform Smart Grids Austria Andreas Lugmaier Coordinator NTP Smart Grids Austria Siemens AG, Corporate Technology CEE email: koordinator@smartgrids.at andreas.lugmaier@siemens.com www.smartgrids.at National Technology Platform Smart

More information

Market Coupling in Gas?

Market Coupling in Gas? Market Coupling in Gas? European Gas Target Model 3 rd Workshop London, 11 April 2011 Authors: Jens Büchner Robert Gersdorf Tobias Paulun Nicole Täumel Agenda 1 Scope and Objectives of the Presentation

More information

Operational Security Network Code

Operational Security Network Code Amstelveenseweg 998 1081 JS Amsterdam Phone: + 31 20 520 7970 Fax: + 31 346 283 258 Email: secretariat@efet.org Website: www.efet.org Operational Security Network Code Public consultation 3 November 2012

More information

ÖNORM EN 1504-8. The European Standard EN 1504-8 has the status of an Austrian Standard. Edition: 2005-02-01. Standards group B

ÖNORM EN 1504-8. The European Standard EN 1504-8 has the status of an Austrian Standard. Edition: 2005-02-01. Standards group B ÖNORM EN 1504-8 Edition: 2005-02-01 Standards group B Identical (IDT) with EN 1504-8:2004 ICS 91.080.40 Products and systems for the protection and repair of concrete structures Definitions, requirements,

More information

How To Make A Successful Energy Community

How To Make A Successful Energy Community Welcoming remarks CONCLUSIONS 10 th ATHENS FORUM 24-25 April 2007 1. The Secretary General of the Greek Ministry for Development opened the Forum. He underlined the progress made in developing the regional

More information

MULTILATERAL MEMORANDUM OF UNDERSTANDING CONCERNING CO-OPERATION IN THE EXCHANGE OF INFORMATION FOR AUDIT OVERSIGHT

MULTILATERAL MEMORANDUM OF UNDERSTANDING CONCERNING CO-OPERATION IN THE EXCHANGE OF INFORMATION FOR AUDIT OVERSIGHT MULTILATERAL MEMORANDUM OF UNDERSTANDING CONCERNING CO-OPERATION IN THE EXCHANGE OF INFORMATION FOR AUDIT OVERSIGHT INTERNATIONAL FORUM OF INDEPENDENT AUDIT REGULATORS Adopted on June 30, 2015 1 Table

More information

Feedback from Nordenergi on PCG target model and roadmap propositions

Feedback from Nordenergi on PCG target model and roadmap propositions Our ref. CHS PCG/ERGEG Regional Initiatives Group, pcg@ergeg.org ERI Northern region bld@ks.dk Copenhagen, 30 October 2009 Feedback from Nordenergi on PCG target model and roadmap propositions Dear Madam/Sir,

More information

Foreword 2 STO BR IBBS-1.1-2007

Foreword 2 STO BR IBBS-1.1-2007 BANK OF RUSSIA STANDARD STO BR IBBS-1.1-2007 INFORMATION SECURITY OF RUSSIAN BANKING INSTITUTIONS INFORMATION SECURITY AUDIT* Date enacted: 1 May 2007 Moscow 2007 2 STO BR IBBS-1.1-2007 Foreword 1. ADOPTED

More information

Translation Service Provider according to ISO 17100

Translation Service Provider according to ISO 17100 www.lics-certification.org Certification Scheme S06 Translation Service Provider according to ISO 17100 Date of issue: V2.0, 2015-11-15 Austrian Standards plus GmbH Dr. Peter Jonas Heinestraße 38 1020

More information

Procedures for Assessment and Accreditation of Medical Schools by the Australian Medical Council 2011

Procedures for Assessment and Accreditation of Medical Schools by the Australian Medical Council 2011 Australian Medical Council Limited Procedures for Assessment and Accreditation of Medical Schools by the Australian Medical Council 2011 Medical School Accreditation Committee These procedures were approved

More information

ENTSO-E Working Draft Network Code on Emergency and Restoration

ENTSO-E Working Draft Network Code on Emergency and Restoration ENTSO-E Working Draft Network Code on Emergency and Restoration DRAFT FOR THE FOURTH PUBLIC WORKSHOP Notice 22 January 2015 This document reflects the status of the work of Transmission System Operator

More information

CP14 ISSUE 5 DATED 1 st OCTOBER 2015 BINDT Audit Procedure Conformity Assessment and Certification/Verification of Management Systems

CP14 ISSUE 5 DATED 1 st OCTOBER 2015 BINDT Audit Procedure Conformity Assessment and Certification/Verification of Management Systems Certification Services Division Newton Building, St George s Avenue Northampton, NN2 6JB United Kingdom Tel: +44(0)1604-893-811. Fax: +44(0)1604-893-868. E-mail: pcn@bindt.org CP14 ISSUE 5 DATED 1 st OCTOBER

More information

ACER scoping document for Rules for Trading

ACER scoping document for Rules for Trading ENTSOG response to ACER questionnaire on scoping for Rules for 12 May 2014 Final ACER scoping document for Rules for ENTSOG response to the ACER questionnaire Since some of the questions are addressed

More information

Certification rules for the mark

Certification rules for the mark Identification No.: NF148 Version No.: 2 Date of approval: 13/12/2012 Edition date: 19/12/2012 Certification rules for the mark Validation of analysis methods Application to water analysis APPENDIX Validation,

More information

ERGEG Gas Focus Group/Storage TF. Guidelines for Good Practice for Gas Storage System Operators (GGPSSO) Questionnaire for SSOs

ERGEG Gas Focus Group/Storage TF. Guidelines for Good Practice for Gas Storage System Operators (GGPSSO) Questionnaire for SSOs ERGEG Gas Focus Group/Storage TF Guidelines for Good Practice for Gas Storage System Operators (GGPSSO) Questionnaire for SSOs Introduction The objective of this questionnaire is to collect information

More information

System of Governance

System of Governance CEIOPS-DOC-29/09 CEIOPS Advice for Level 2 Implementing Measures on Solvency II: System of Governance (former Consultation Paper 33) October 2009 CEIOPS e.v. Westhafenplatz 1-60327 Frankfurt Germany Tel.

More information

Cost Reduction Potential in the Offshore Grid

Cost Reduction Potential in the Offshore Grid Cost Reduction Potential in the Offshore Grid Dr. Markus Glatfeld, Managing Director, TenneT Offshore GmbH TenneT two TSOs, one company Europe s first transnational TSO Connections to 10 TSOs in the center

More information

Statistical Factsheet 2014 provisional values as of 27 April 2015

Statistical Factsheet 2014 provisional values as of 27 April 2015 Statistical Factsheet provisional values as of 7 April European Network of Transmission System Operators for Electricity ENTSO-E in figures Electricity system data of member TSOs countries ENTSO-E Transmission

More information

Guidance for Member States on Audit of Accounts

Guidance for Member States on Audit of Accounts EGESIF_15_0016-02 final 05/02/2016 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Audit of Accounts DISCLAIMER: This is a document prepared by the Commission

More information

Operation Handbook. June 2004. union for the co-ordination of transmission of electricity

Operation Handbook. June 2004. union for the co-ordination of transmission of electricity Operation Handbook June 2004 union for the co-ordination of transmission of electricity INTRODUCTION I Introduction to the UCTE Operation Handbook (OH) [E] Chapters A. UCTE s basic needs for the Operation

More information

PROJECT AUDIT METHODOLOGY

PROJECT AUDIT METHODOLOGY PROJECT AUDIT METHODOLOGY 1 "Your career as a project manager begins here!" Content Introduction... 3 1. Definition of the project audit... 3 2. Objectives of the project audit... 3 3. Benefit of the audit

More information

Frequently Asked Questions. (FAQs)

Frequently Asked Questions. (FAQs) Frequently Asked Questions (FAQs) on REMIT fundamental data and inside information collection 1 st Edition 31 March 2016 Version history Version Frequently Asked Questions (FAQs) on REMIT fundamental data

More information

THE UNIVERSAL SECURITY AUDIT PROGRAMME (USAP)

THE UNIVERSAL SECURITY AUDIT PROGRAMME (USAP) THE UNIVERSAL SECURITY AUDIT PROGRAMME (USAP) 1 Objectives USAP objective The objective of the USAP is to promote global aviation security through auditing Contracting States, on a regular basis, to determine

More information

VOLUNTARY CONTRACT NOTICE FOR UPCOMING PROCUREMENT PROCEDURE DEADLINE EXTENDED TO 26 OCTOBER

VOLUNTARY CONTRACT NOTICE FOR UPCOMING PROCUREMENT PROCEDURE DEADLINE EXTENDED TO 26 OCTOBER VOLUNTARY CONTRACT NOTICE FOR UPCOMING PROCUREMENT PROCEDURE PROVISION OF MEDICAL SERVICES WITH REGARD TO OCCUPATIONAL SAFETY AND HEALTH DEADLINE EXTENDED TO 26 OCTOBER (REFERENCE NUMBER: PRO-001265) Title:

More information

Information Technology Engineers Examination. Systems Auditor Examination. (Level 4) Syllabus

Information Technology Engineers Examination. Systems Auditor Examination. (Level 4) Syllabus Information Technology Engineers Examination Systems Auditor Examination (Level 4) Syllabus Details of Knowledge and Skills Required for the Information Technology Engineers Examination Version 2.0 May

More information

Deliverables and work programme 2012 Christophe Schramm DG ENER

Deliverables and work programme 2012 Christophe Schramm DG ENER Smart Grid Task Force EG4 Infrastructure Development Deliverables and work programme 2012 Christophe Schramm DG ENER 28/03/2012 Overall deliverables for 2012 Establish a process for identifying projects

More information

Review of an SMSF audit engagement questionnaire

Review of an SMSF audit engagement questionnaire Review of an SMSF audit engagement questionnaire Introduction Instructions for the Reviewer This questionnaire has been designed to help you assess whether the audit of Self Managed Superannuation Funds

More information

Introduction Anders Plejdrup Houmøller, CEO Houmoller Consulting ApS

Introduction Anders Plejdrup Houmøller, CEO Houmoller Consulting ApS Introduction Anders Plejdrup Houmøller, CEO Houmoller Consulting ApS Appendix 1 defines what intra-day trading of electricity means in a large part of Europe. Appendix 2 contains a map of 5 of the synchronous

More information

ENTSO-E Network Code on Emergency and Restoration

ENTSO-E Network Code on Emergency and Restoration ENTSO-E Network Code on Emergency and Restoration Notice 25 March 2015 This Network Code represents ENTSO-E s final proposals in line with the ACER Framework Guidelines on Electricity System Operation

More information

Audit of the Test of Design of Entity-Level Controls

Audit of the Test of Design of Entity-Level Controls Audit of the Test of Design of Entity-Level Controls Canadian Grain Commission Audit & Evaluation Services Final Report March 2012 Canadian Grain Commission 0 Entity Level Controls 2011 Table of Contents

More information

ISO 19600: The development

ISO 19600: The development 1 Baltzer Science Publishers ISO 19600: The development of a global standard on compliance management By Sylvie Bleker and Dick Hortensius* It has been a traditional complaint of the global compliance

More information

University of Southern California

University of Southern California University of Southern California Price School of Public Policy Master of Health Administration residency guidebook USC Price School of Public Policy, Graduate Programs in Health Administration 650 Childs

More information

General requirements for bodies operating assessment and certificationlregistration of quality systems (ISOIIEC Guide 6ZA996)

General requirements for bodies operating assessment and certificationlregistration of quality systems (ISOIIEC Guide 6ZA996) Edition: 1998-05-01 ldentical (IDT) with ÖVE EN 4501 2: I998 ISOIIEC 62 Guide: 1996 Supersedes ÖNORM EN 4501 2: 1990-06-08 ÖNORM EN 45012 Bbl 1:1990 08 ICS 03.1 20.20 General requirements for bodies operating

More information

Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014

Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014 Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014 adopted by the Norwegian Ministry of Foreign Affairs pursuant to Article 8.8 of the Agreement between the Kingdom of Norway

More information

Guidelines for System Accreditation Procedures. Accreditation, Certification and Quality Assurance Institute

Guidelines for System Accreditation Procedures. Accreditation, Certification and Quality Assurance Institute Guidelines for System Accreditation Procedures Accreditation, Certification and Quality Assurance Institute 1 Contents System Accreditation 4 Criteria 6 Procedure 9 Structure of the Evaluation Report

More information

HKCAS Supplementary Criteria No. 8

HKCAS Supplementary Criteria No. 8 Page 1 of 12 HKCAS Supplementary Criteria No. 8 Accreditation Programme for Information Security Management System (ISMS) Certification 1 INTRODUCTION 1.1 HKAS accreditation for information security management

More information

Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules

Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation Rules Deres referanse Vår referanse Dato PC_2012_E_13 N 26.10.2012 ACER Trg Republike 3 1000 Ljubljana, Slovenia Consultation on Forward Risk-Hedging Products and Harmonisation of Long-Term Capacity Allocation

More information

EA-7/01. EA Guidelines. on the application. Of EN 45012. Publication Reference PURPOSE

EA-7/01. EA Guidelines. on the application. Of EN 45012. Publication Reference PURPOSE Publication Reference EA-7/01 EA Guidelines on the application Of EN 45012 PURPOSE The purpose of the document is to provide explanations with a view to harmonise the application of ISO/IEC Guide 62/EN

More information

ALUMINUM CORPORATION OF CHINA LIMITED DETAILED IMPLEMENTATION RULES FOR THE AUDIT COMMITTEE UNDER THE BOARD OF DIRECTORS

ALUMINUM CORPORATION OF CHINA LIMITED DETAILED IMPLEMENTATION RULES FOR THE AUDIT COMMITTEE UNDER THE BOARD OF DIRECTORS Important Note: The following is an English translation of the Chinese version of the Detailed Implementation Rules for the Audit Committee under the Board of Directors of Aluminum Corporation of China

More information

Phase I Conduct a Security Self-Assessment

Phase I Conduct a Security Self-Assessment 61 The SEARCH IT Security Self- and Risk- Assessment Tool: Easy to Use, Visible Results To complete your self-assessment, you can use the questions we have adopted and revised from the NIST guidance under

More information

Governance and Audit Committee 23 November 2015

Governance and Audit Committee 23 November 2015 Agenda Item 7 Governance and Audit Committee 23 November 2015 Welland Internal Audit Consortium Internal Audit Plan & Performance Update 2015/16 Purpose of report: To provide Members with information on

More information

Germany. Key issues. 1. General overview

Germany. Key issues. 1. General overview Germany Key issues High volumes of renewables have changed the way the electricity market in Germany operates. In 2012 direct marketing increased, in particular in onshore wind, due to a change of the

More information

OF WESTERN BALKAN 6 ON REGIONAL ELECTRICITY MARKET DEVELOPMENT AND ESTABLISHING A FRAMEWORK FOR OTHER FUTURE COLLABORATION

OF WESTERN BALKAN 6 ON REGIONAL ELECTRICITY MARKET DEVELOPMENT AND ESTABLISHING A FRAMEWORK FOR OTHER FUTURE COLLABORATION MEMORANDUM OF UNDERSTANDING (MoU) OF WESTERN BALKAN 6 ON REGIONAL ELECTRICITY MARKET DEVELOPMENT AND ESTABLISHING A FRAMEWORK FOR OTHER FUTURE COLLABORATION The High Level representatives of the Western

More information

APES 320 Quality Control for Firms

APES 320 Quality Control for Firms APES 320 Quality Control for Firms APES 320 Quality Control for Firms is based on International Standard on Quality Control (ISQC 1) (as published in the Handbook of International Auditing, Assurance,

More information

Guide for Applicants COSME calls for proposals 2015

Guide for Applicants COSME calls for proposals 2015 Guide for Applicants COSME calls for proposals 2015 CONTENTS I. Introduction... 3 II. Preparation of the proposal... 3 II.1. Relevant documents... 3 II.2. Participants... 4 Consortium coordinator... 4

More information

Completion of the Internal Energy Market. Transport, Telecommunications and ENERGY Council meeting Brussels, 9 December 2014

Completion of the Internal Energy Market. Transport, Telecommunications and ENERGY Council meeting Brussels, 9 December 2014 Council of the European Union PRESS EN COUNCIL CONCLUSIONS Brussels, 9 December 2014 Completion of the Internal Energy Market Transport, Telecommunications and ENERGY Council meeting Brussels, 9 December

More information

German Competent Authority Experiences and Expectations from a Member State s Perspective

German Competent Authority Experiences and Expectations from a Member State s Perspective German Competent Authority Experiences and Expectations from a Member State s Perspective Warszawa, 23-24 November 2011 Dr. Ann Bambauer Federal Office for Chemicals/Authorisation of Biocides Outline 1.

More information

BANK OF RUSSIA RECOMMENDATIONS ON STANDARDISATION MAINTENANCE OF INFORMATION SECURITY OF THE RUSSIAN BANKING SYSTEM ORGANISATIONS

BANK OF RUSSIA RECOMMENDATIONS ON STANDARDISATION MAINTENANCE OF INFORMATION SECURITY OF THE RUSSIAN BANKING SYSTEM ORGANISATIONS BANK OF RUSSIA RECOMMENDATIONS ON STANDARDISATION RS BR IBBS-2.1-2007 MAINTENANCE OF INFORMATION SECURITY OF THE RUSSIAN BANKING SYSTEM ORGANISATIONS GUIDELINES FOR SELF-ASSESSMENT OF CONFORMITY OF INFORMATION

More information

Appendix 14 CORPORATE GOVERNANCE CODE AND CORPORATE GOVERNANCE REPORT

Appendix 14 CORPORATE GOVERNANCE CODE AND CORPORATE GOVERNANCE REPORT Appendix 14 CORPORATE GOVERNANCE CODE AND CORPORATE GOVERNANCE REPORT The Code This Code sets out the principles of good corporate governance, and two levels of recommendations: code provisions; and recommended

More information

Capacity mechanism. General Directorate for Energy and Climate August 30, 2012

Capacity mechanism. General Directorate for Energy and Climate August 30, 2012 Capacity mechanism General Directorate for Energy and Climate August 30, 2012 Ministère de l économie, des Finances et de l Industrie Ministère de l'écologie, du Développement durable, des Transports et

More information

n130910 version of 26 november 2013 sccm Information about performing internal audits

n130910 version of 26 november 2013 sccm Information about performing internal audits Information about performing internal audits sccm Information about performing internal audits 1 We at SCCM are convinced and our experience has proven that any organization, large or small, will achieve

More information

RULES OF PROCEDURE FOR THE BOARD OF DIRECTORS, THE EXECUTIVE CHAIRMAN AND THE GENERAL MANAGER IN DOLPHIN GROUP ASA

RULES OF PROCEDURE FOR THE BOARD OF DIRECTORS, THE EXECUTIVE CHAIRMAN AND THE GENERAL MANAGER IN DOLPHIN GROUP ASA RULES OF PROCEDURE FOR THE BOARD OF DIRECTORS, THE EXECUTIVE CHAIRMAN AND THE GENERAL MANAGER IN DOLPHIN GROUP ASA ADOPTED BY THE BOARD OF DIRECTORS ON 27 APRIL 2015 1. THE BOARD OF DIRECTORS The Board

More information

How To Write An Accreditation Manual For College Governing Boards

How To Write An Accreditation Manual For College Governing Boards ACCREDITATION MANUAL FOR GOVERNING BOARDS A Publication of the Accrediting Commission for Community and Junior Colleges Western Association of Schools and Colleges May 2012 Edition ACCJC/WASC 10 Commercial

More information

Security of Supply Concept and Definition: On the Way to a Common Understanding?

Security of Supply Concept and Definition: On the Way to a Common Understanding? Security of Supply Concept and Definition: On the Way to a Common Understanding? Presentation for French-German Conference on SoS Dr. Christoph Maurer Paris 21 May 2015 0 21.05.2015 Security of Supply

More information

Procedure PS-TNI-001 Information Security Management System Certification

Procedure PS-TNI-001 Information Security Management System Certification Table of Contents 1. Purpose 2. Scope 3. Definitions 4. Responsibilities 4.1 Head of the Certification Body 4.2 QM Manager / Management Representative 4.3 Auditors 4.4 Order Service 4.5 Certification Service

More information

REGULATIONS ON PROVISION OF SERVICES BY STATUTORY AUDITOR OR STATUTORY AUDITING COMPANY

REGULATIONS ON PROVISION OF SERVICES BY STATUTORY AUDITOR OR STATUTORY AUDITING COMPANY General and Supervisory Board REGULATIONS ON PROVISION OF SERVICES BY STATUTORY AUDITOR OR STATUTORY AUDITING COMPANY Approved 3 March, 2016 This is an unofficial translation of the Regulations on Whistleblowing

More information

Specific amendments to the Capacity Allocation and Congestion Management Network Code

Specific amendments to the Capacity Allocation and Congestion Management Network Code Annex: Specific amendments to the Capacity Allocation and Congestion Management Network Code I. Amendments with respect to entry into force and application The Network Code defines deadlines for several

More information

Country profiles: Austria

Country profiles: Austria Country profiles: Austria Last updated: date (09/05/2014) 1 Implementation of Tracking Systems As electricity tracking system Austria uses electricity disclosure, which provides consumers with details

More information

Research Data Centre network for transnational access - four years of experiences by seven European RDCs

Research Data Centre network for transnational access - four years of experiences by seven European RDCs Research Data Centre network for transnational access - four years of experiences by seven European RDCs Karen Dennison (UK Data Archive) and David Schiller (IAB) Presented by Karen Dennison Luxembourg,

More information

Green and Secure. Challenges of increasing RES feed-in from a TSO perspective and from a power market point of view. René Müller 07.04.

Green and Secure. Challenges of increasing RES feed-in from a TSO perspective and from a power market point of view. René Müller 07.04. Green and Secure Challenges of increasing RES feed-in from a TSO perspective and from a power market point of view René Müller TenneT Two TSOs, one company Europe s first cross-border TSO Connections to

More information

COMBINE. Part B. Manual for Marine Monitoring in the. Programme of HELCOM. General guidelines on quality assurance for monitoring in the Baltic Sea

COMBINE. Part B. Manual for Marine Monitoring in the. Programme of HELCOM. General guidelines on quality assurance for monitoring in the Baltic Sea Manual for Marine Monitoring in the COMBINE Programme of HELCOM Part B General guidelines on quality assurance for monitoring in the Baltic Sea Annex B-3 Quality audit ANNEX B-3 QUALITY AUDIT 1. Objectives

More information

AUDITOR-GENERAL S AUDITING STANDARD 4 (REVISED) THE AUDIT OF SERVICE PERFORMANCE REPORTS. Contents

AUDITOR-GENERAL S AUDITING STANDARD 4 (REVISED) THE AUDIT OF SERVICE PERFORMANCE REPORTS. Contents AUDITOR-GENERAL S AUDITING STANDARD 4 (REVISED) THE AUDIT OF SERVICE PERFORMANCE REPORTS Contents Page Introduction 3-8301 Scope of this Statement 3-8301 Application 3-8303 Objectives 3-8304 Definitions

More information

Nordic Balance Settlement (NBS)

Nordic Balance Settlement (NBS) Nordic Balance Settlement (NBS) Common Balance & Reconciliation Settlement Design December 22 nd, 2011 Content Terminology...4 Executive Summary...6 1 Introduction... 8 1.1 Scope of the Nordic Balance

More information

Internal Audit Manual

Internal Audit Manual Internal Audit Manual Version 1.0 AUDIT AND EVALUATION SECTOR AUDIT AND ASSURANCE SERVICES BRANCH INDIAN AND NORTHERN AFFAIRS CANADA April 25, 2008 #933907 Acknowledgements The Institute of Internal Auditors

More information

How To Make A Harmonised Power Control System Work

How To Make A Harmonised Power Control System Work Supporting Document for the Network Code on Load-Frequency Control and Reserves 28.06.2013 TABLE OF CONTENTS 1 Introduction to the Supporting Document... 4 1.1 Document Structure... 4 1.2 Legal Status

More information

Guide for Applicants. Call for Proposal:

Guide for Applicants. Call for Proposal: Guide for Applicants Call for Proposal: COSME Work Programme 2014 TABLE OF CONTENTS I. Introduction... 3 II. Preparation of the proposal... 3 II.1. Relevant documents... 3 II.2. Participants... 4 II.2.1.

More information

OPERATING PROCEDURES OF THE BOARD AND COMMITTEES OF THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA. 20 November 2014 1

OPERATING PROCEDURES OF THE BOARD AND COMMITTEES OF THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA. 20 November 2014 1 OPERATING PROCEDURES OF THE BOARD AND COMMITTEES OF THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA 20 November 2014 1 1 These Operating Procedures, as approved on 21 November 2011 (GF/B25/DP7),

More information

National Occupational Standards. Compliance

National Occupational Standards. Compliance National Occupational Standards Compliance NOTES ABOUT NATIONAL OCCUPATIONAL STANDARDS What are National Occupational Standards, and why should you use them? National Occupational Standards (NOS) are statements

More information