1 101 BASICS SERIES LEARNING MODULE 10: LOADCENTERS Cutler-Hammer

2 WELCOME Welcome to Module 10, which is about loadcenters. A loadcenter is a device that delivers electricity from a supply source to loads in residential and light commercial/industrial applications. FIGURE 1. TYPICAL LOADCENTER Like the other modules in this series, this one presents small, manageable sections of new material followed by a series of questions about that material. Study the material carefully, then answer the questions without referring back to what you ve just read. You are the best judge of how well you grasp the material. Review the material as often as you think necessary. The most important thing is establishing a solid foundation to build on as you move from topic to topic and module to module. A Note On Font Styles Viewing the Glossary Key points are in bold. Glossary terms are underlined and italicized the first time they appear. You may view definitions of glossary items by clicking on terms and words that are underlined and italicized in the text. You may also browse the Glossary by clicking on the Glossary bookmark in the left-hand margin. 1

3 WHAT YOU WILL LEARN We ll step through each of these topics in detail: Section TitlePage Number What Does a Loadcenter Do? 3 Applications 4 Basic Circuitry And Wiring 5 Residential Service Entrance Panel 5 Residential Distribution Panel 6 Commercial/ Industrial Service Entrance Panel 7 Commercial/ Industrial Distribution Panel 7 Grounding Issues 8 Grounding the Service Entrance Panel 8 Equipment Grounding Bus 9 Grounding Downstream Loadcenters 10 Ground Fault 12 Review 1 13 Loadcenter Components and Installation 14 Anatomy of a Loadcenter 14 Enclosure 15 Installation and Mounting 16 Circuit Breakers 18 Installing Circuit Breakers 18 How Many Circuit Breakers Fit in a Loadcenter? 20 Interchangeable vs. Non-Interchangeable Breakers Ratings 21 Loadcenter Types 23 Main Breaker Loadcenter 23 Main Lug Only Loadcenter 24 Convertible Loadcenter 24 Selecting a Loadcenter 25 Required Application Information 25 Sample Application 26 Review 2 27 Glossary 28 Review Answers

4 WHAT DOES A LOADCENTER DO? Every residential and light commercial/industrial building utilizes electricity for lighting, receptacles, and/or appliance loads. Conductors are used to bring power from the power lines to the building. Then a device is needed to divide this power for branch circuits and to protect these branch circuits from overloads and short circuits. This device is called a loadcenter. Electricity moves from the supply source into the building to the loadcenter, and is then distributed through the building s branch circuits to the loads. Each branch circuit is connected, or terminated, at the loadcenter. Each branch circuit is protected by a circuit breaker housed in the loadcenter. In the event of a short circuit or an overload on a branch circuit, the circuit breaker cuts the power before any property damage or personal injury can occur. NOTE: New electrical installations use circuit breakers in the loadcenter, so we will not discuss fuses in this training module. SERVICE ENTRANCE LIGHTING SWITCHES APPLIANCES RECEPTACLES LOADCENTER GROUNDING FIGURE 2. ELECTRICAL DISTRIBUTION TO LOADS 3

5 Applications There are two main applications for a loadcenter: As a service entrance panel. This is the term for a loadcenter used at the point at where the power enters a building. There can only be one service entrance panel per building. As a distribution panel. A distribution panel is simply a loadcenter used at a point beyond the building s service entrance. This can be useful when adding additional electrical service to an existing building. The power to the distribution panel usually comes from a branch circuit of the service entrance panel. POWER FROM UTILITY SERVICE ENTRANCE PANEL DISTRIBUTION PANEL FIGURE 3. A SERVICE ENTRANCE PANEL AND A DISTRIBUTION PANEL 4

6 BASIC CIRCUITRY AND WIRING Residential Service Entrance Panel Figure 4 shows a typical residential application. Loadcenters are typically rated 225 amps or less, and a maximum of 240 volts. Most homes have 200 amp service and a 120/240-volt, single-phase, three-wire system. Three conductors run from the distribution transformer to the service entrance panel. This transformer converts the utility voltage into a voltage and current supply suitable for use in most residential applications. Two of the main service conductors (or mains) are ungrounded ( hot ), and the third is the neutral. The hots are connected to the main circuit breaker in the loadcenter. The neutral is attached to the neutral bar. If a voltmeter reading is taken between the two hot conductors ( A and B ), it will measure 240 volts. If a reading is taken between a hot conductor and the neutral ( N ), it will measure 120 volts. DISTRIBUTION VOLTAGE DISTRIBUTION TRANSFORMER A N B GROUND NEUTRAL LOADCENTER LIGHTING LOAD L M MOTOR LOAD BUS BARS FIGURE 4. TYPICAL SINGLE-PHASE, THREE-WIRE LOADCENTER This is convenient because 240 volts are needed to power central air conditioners, electric clothes dryers, and electric range tops. At the same time, 120 volts are required to service lighting, small appliances, and receptacle loads. 5

7 Residential Distribution Panel Now, let s consider the case of a residential distribution panel. Remember that a distribution panel is a panel used at a point beyond the service entrance. This means that the distribution panel is typically fed by a service entrance panel. You can add on to a loadcenter in two ways. The first way is to use a branch circuit breaker. The second way is to use feed-through lugs. MAIN BREAKER TRANSFORMER N A B SERVICE ENTRANCE PANEL N A B MAIN LUGS FEED-THROUGH LUGS N A B DISTRIBUTION PANEL FIGURE 5. A SERVICE ENTRANCE PANEL FEEDING A DISTRIBUTION PANEL In the example shown here, the service conductors (the two hots and the neutral) run from the feed-through lugs of the service entrance panel to the main lugs of the distribution panel. In this way, the distribution panel itself is protected by the main circuit breaker in the service entrance panel. The neutral conductor is isolated. The importance of this will be discussed later. Usually, a residential distribution panel is used to supply a washer, dryer, airconditioner and/or hot tub. 6

8 Commercial/ Industrial Service Entrance Panel The commercial/industrial service entrance panel is supplied with a different power system than the residential one. A distribution transformer provides a 120/208 volt, three-phase, four-wire system to the panel. Four conductors go to the service entrance. The three mains are ungrounded ( hot ), and the fourth is the neutral. The hots are connected to the main breaker in the loadcenter. The neutral is attached to the neutral bar and is connected the same way as in the residential application. If a voltmeter reading is taken between any two hot conductors ( A, B and C ), it will measure 208 volts. If a reading between any hot conductor and the neutral ( N ) is taken, it will measure 120 volts. DISTRIBUTION VOLTAGE DISTRIBUTION TRANSFORMER A N B C GROUND LOADCENTER NEUT LIGHTING LOAD L M MOTOR LOAD BUS BARS FIGURE 6. TYPICAL THREE-PHASE, FOUR-WIRE LOADCENTER This system can handle single-phase or three-phase applications. The 120/208 volt single-phase power is used the same way as in the residential application. The three-phase, 208-volt power is rarely used. For this reason, we will not discuss three-phase any further in this module. Commercial/ Industrial Distribution Panel The distribution panel is treated the same as the residential distribution panel. It is typically fed by the service entrance panel and it can be single phase or three phase. Again, it is important to remember that the neutral is isolated. 7

9 GROUNDING ISSUES Grounding is an important aspect of any electrical equipment and must be considered carefully. The National Electrical Code (NEC) defines ground as a conducting connection, whether intentional or accidental, between an electrical circuit or equipment and the earth, or to some conducting body that serves in place of the earth. There are two objectives to the intentional grounding of electrical equipment: Keep voltage differentials between different parts of a system at a minimum which reduces shock hazard. Keep impedance of the ground path to a minimum. The lower the impedance the greater the current is in the event of a fault. The greater the current the faster an overcurrent device will open. Grounding the Service Entrance Panel In the service entrance panel shown in Figure 7, the neutral from the transformer is connected to the neutral bar in the loadcenter. The neutral bar is then grounded to the earth. TRANSFORMER N A B GROUNDING ROD NEUTRAL BONDED TO BOX NEUTRAL BUS FIGURE 7. GROUNDING A SERVICE ENTRANCE PANEL 8

10 Grounding the Service Entrance Panel (continued) This is accomplished by running a conductor from the loadcenter s neutral bar to a cold water pipe or copper rod buried in the ground (or other suitable grounding electrode.) Then, a bonding screw or strap is used to physically bond the neutral bar to the metal enclosure. In this way, the neutral bar, the neutral of the transformer, and the enclosure are grounded. When the neutral is grounded in this manner, the equipment ground from the branch circuits is sometimes allowed to connect to the neutral. Equipment Grounding Bus The equipment grounding bus. is connected directly to the loadcenter enclosure. For safety, all equipment (on both the feeder and branch circuits) is connected to the equipment grounding bus. This requirement keeps the connected equipment at the same potential as the enclosure itself. EQUIPMENT GROUNDING BUS FIGURE 8. EQUIPMENT GROUNDING BUS One additional point for service entrance applications: this bonded and grounded neutral can also be used as the point of connection for equipment grounding. 9

11 Grounding Downstream Loadcenters It is important to remember that the service entrance panel is the only ground connection point for the neutral. The neutral is both insulated and isolated at any downstream panels. As shown in Figure 9, the downstream panel s enclosure is grounded with a grounding conductor running back to the service entrance panel. TRANSFORMER INSULATED NEUTRAL N A B SERVICE ENTRANCE PANEL EQUIPMENT GROUND N A B N A B DISTRIBUTION PANEL FIGURE 9. GROUNDING THE DOWNSTREAM LOADCENTER 10

12 Grounding Downstream Loadcenters (continued) In Figure 10, the table lamp has a short circuit. If you trace the thick line back, you will see how fault current is returned to the source. This is why the downstream loadcenter contains a branch circuit breaker. It trips, disconnecting power from the load. TRANSFORMER INSULATED NEUTRAL N A B SERVICE ENTRANCE PANEL EQUIPMENT GROUND N A B N A B DISTRIBUTION PANEL FIGURE 10. A SHORT IN A DOWNSTREAM LOAD 11

13 Ground Fault In most cases, NEC also requires equipment to have an additional grounding conductor. This conductor connects the metal housing of an appliance to the system ground to reduce the possibility of a shock due to a ground fault. A ground fault is simply current leakage from an ungrounded conductor to the grounding path in an electrical system. Consider Figure 11. A piece of insulation covering a conductor at an electrical outlet has flaked off. This could allow current to pass from the conductor to the metal outlet box. The box is part of the system ground. If properly grounded, the current should follow the grounding path to ground, instead of an unfortunate person s finger that touched the box. BARE CONDUCTOR IN CONTACT WITH METAL OUTLET BOX FIGURE 11. GROUND FAULT Since a distribution panel takes its power from the service entrance panel (Figure 9), the neutral needs to be isolated from the ground. It is considered a branch circuit of the main service panel, and needs to have its own ground to prevent a ground fault. If all the loads in a panel are connected evenly between A-N and B-N, no current will flow in the neutral. However, loads are rarely balanced. As a result, some current usually flows through the neutral. The amount current flowing in the neutral conductor at any one time is the difference between the current flowing through leg A and leg B. This is why a path to ground is needed. 12

14 REVIEW 1 Answer the following questions without referring to the material just presented. Begin the next section when you are confident that you understand what you ve already read. 1. Loadcenters have two main applications. These are: 2. In which two market segments are loadcenters typically used? / 3. For safety reasons, the National Electrical Code (NEC) requires the service entrance panel s to be grounded. Beyond the service entrance equipment, it is always and. 4. In your own words, explain under what conditions no current will flow through the neutral. Then explain how to figure the amount of current flowing through the neutral. 5. In your own words, explain the main purpose of a loadcenter. 13

15 LOADCENTER COMPO- NENTS AND INSTALL- ATION Before we go any further in our exploration of the loadcenter, let s take a moment to consider the main components and features of a typical loadcenter. Anatomy of a Loadcenter FIGURE 12. ANATOMY OF A TYPICAL LOADCENTER 1.Front CoverProvides a neat, protective face for the product. Usually includes a hinged door to allow access to the circuit breaker handles. 2.Inner Cover or Dead Front 3/4.Inner Cover Adjustment Screws Serves as a protective barrier to prevent contact with energized ( hot ) parts within the unit. Used to secure the inner cover tightly against the tops of the circuit breakers. This eliminates any space that might allow access to hot parts inside. 5.TwistoutsRemovable perforated metal spaces that can be twisted out, to allow the protrusion of the circuit breaker handles. 6.Wiring DiagramLists the specifics of the loadcenter, including: circuit breaker application, UL information, short circuit ratings, series ratings, wire connection torque values, and unit accessories. 7.Sliding LatchProvided on indoor loadcenters to allow easy opening of the loadcenter door. 8.DoorThe hinged part of the front cover which allows access to the circuit breaker handles. 9/19.Backpan Top and Bottom Mounting Screws Allows for easy removal of the loadcenter interior assembly. 14

16 10/18. Enclosure Mounting Keyholes Located at top center and bottom center. Whether surface-mounted right-side up or inverted, the unit can be easily centered on the wall by hanging the enclosure with the uppermost keyhole. 11.Drywall Scribe Markings 12.Surface Mounting Holes (4) 13.Main Lugs or Main Breaker Serve as a guide for mounting the loadcenter flush with the drywall and between the wall studs. Once centered for surface mounting, the loadcenter is affixed with screws through these four holes. Provide the means for the termination of the power cables coming from the electric meter. Main lugs simply provide a safe mechanical connection to the bus bars. A main breaker provides thermal magnetic protection for the loadcenter. 14.BackpanThe solid steel piece that supports the loadcenter bus bar assembly. It also provides the means to affix branch circuit breakers. 15.Bonding StrapUsed to bond the neutral to the enclosure (when required by code). 16.Bus Bars (2)An extension of the incoming power cables. Provide a mechanical means of affixing branch circuit breakers. Notches are added to (or omitted from) the bus bars to limit the number of branch circuits allowed. 17.KnockoutsCircular indentations in the top, bottom, sides, and back of the enclosure. When removed, the electrician can bring wire into and out of the loadcenter without compromising safety. 20.Neutral BarProvides the termination point for the neutral wires from both the incoming service and the load circuits. Most loadcenters have a twin neutral design, positioning terminations on both sides of the unit. This is a wiring convenience for the electrician. Enclosure The loadcenter enclosure is typically constructed of cold rolled or galvanized steel. It serves to house the other loadcenter components. It is designed to provide component and personnel protection. The National Electrical Manufacturers Association (NEMA) and UL have established guidelines for electrical enclosures. They are as follows: NEMA Type 1 General Purpose NEMA Type 3R Raintight This enclosure type is for general purpose, indoor use. It is suitable for most applications where unusual service conditions do not exist. It provides protection from accidental contact with enclosed equipment This enclosure type is intended for outdoor use. It provides protection against falling rain and sleet, and damage from external ice formation. It has a gasket cover. 15

17 Installation and Mounting A loadcenter can be flush-mounted or surface-mounted against a wall. A flushmounting is recessed into a hole in the wall. A surface-mounting is attached to (and projects out from) the wall. Practically all loadcenters are flush mounted, which offers some important benefits such as: Space savings Since the box is behind the wall, the room is not robbed of space Appearance This option is more attractive, as the wiring and box are concealed Safety Except for the trim, the panel does not jut out to possibly catch clothing or other objects FIGURE 13. FLUSH-MOUNT VS. SURFACE-MOUNT Surface-mounted loadcenters are generally used in industrial buildings, and in basements of office and commercial buildings. Since most of these areas have walls made of poured concrete, flush-mounting is impractical. Steel columns are often used for surface mounting. 16

18 Installation and Mounting (continued) The NEC specifies clearances around loadcenters. This is to provide access and working space. There are three basic rules: Headroom in the location must be a minimum of 6-1/2 feet. For systems up to 150 volts, the minimum distance from the loadcenter to the ground shall be 3 feet. For access, there must be 30 inches minimum space in front of the loadcenter, and sufficient space to allow the hinged door to open and rotate 90 degrees. 6 ½ FEET HEADROOM 30 INCHES IN FRONT OF DOOR SPACE ALLOWANCE OF 90 DEGREES FOR DOOR TO OPEN FIGURE 14. LOADCENTER CLEARANCE REQUIREMENTS 17

19 CIRCUIT BREAKERS Installing Circuit Breakers Now, let s take some time to look at one of the main components of a loadcenter: the circuit breaker. Each branch circuit in the loadcenter is protected by a branch circuit breaker (better known as a miniature circuit breaker). Miniature circuit breakers are covered in much more detail in Module 9, Miniature Circuit Breakers. Miniature circuit breakers are also called plug-in breakers because they are connected by plugging them into the bus bar stabs. The bus bars provide a convenient means of providing electricity to the various loads in a building. The circuit breakers attach to the bus bars on vertical stabs that alternate from each hot source. Single pole and double pole circuit breakers are the most commonly used breakers in a loadcenter. If a double pole breaker is plugged onto two adjacent stabs, 240 volts are drawn. A single pole breaker is plugged onto a single bus stab and feeds a 120-volt circuit. To understand how this is possible, consider the physical shape of the bus bars. BUS BARS DOUBLE POLE BREAKER DOUBLE POLE BREAKER PLUGGED ONTO A STAB FROM EACH BUS BAR DRAWS 240 VOLTS SINGLE POLE BREAKER SINGLE POLE BREAKER PLUGGED ONTO ONLY ONE STAB DRAWS 120 VOLTS FIGURE 15. GETTING 120V AND 240V POWER FROM THE BUS BARS 18

20 Now, to reinforce the point, consider Figure 16. DISTRIBUTION VOLTAGE DISTRIBUTION TRANSFORMER A N B NEUTRAL NEUTRAL LOADCENTER LIGHTING LOAD L M MOTOR LOAD BUS BARS FIGURE 16. TYPICAL SINGLE-PHASE, THREE-WIRE LOADCENTER Trace the 240-volt M circuit. Current comes in on conductor A, flows through the left bus bar and branch circuit breaker, and enters the motor load s branch circuit. From there, current passes through another branch breaker and out on conductor B. The circuit is made across both ungrounded legs of the transformer. Trace the 120-volt L circuit. Current comes in on conductor A, flows through the left bus bar and branch circuit breaker, and enters the lighting load s branch circuit. From there, current passes out on the neutral N. The circuit is made from an ungrounded leg of the transformer to the transformer s grounded leg. A 240-volt circuit typically consists of four wires: two "hots", one neutral, and one ground. A 120-volt circuit consists of three wires: one hot, one neutral, and one ground. Usually, hot wires are both color-coded black, although the second hot could be red. Neutral wires are always white. Ground wires are either green or bare (uninsulated) copper. 19

21 How Many Circuit Breakers Fit in a Loadcenter? The number of single-pole circuit breakers that can be installed in a loadcenter is limited by the number of stabs on the bus bars. A breaker can be applied to each side (right and left) of a stab. Therefore, a loadcenter with six stabs would accommodate twelve single-pole circuit breakers. To balance the loads, the breakers should be evenly applied to each side of the stab. STAB NOTCHED TAB ALLOWS FOR ADDITONAL BREAKER INSTALLATION ON LEFT SIDE BRANCH CIRCUIT BREAKER BUS BARS FIGURE 17. BREAKER INSTALLATION (VIEWED FROM ABOVE) If the stab is notched, then half-size branch circuit breakers can be used. Half-sized branch circuit breakers allow for two single-pole circuit breakers to be installed in one space. Each unit is typically only 1/2 wide. These breakers are every bit as functional as the full-size units and allow the added convenience of a more compact installation. Some local inspectors will not allow the use of half-size branch circuit breakers. This is because there is a possibility of overloading the loadcenter and/or unbalancing the system. FIGURE 18. SOLID AND NOTCHED AND STABS The number of notched and unnotched stabs in a particular loadcenter and therefore the number of breakers that may be installed is limited by UL requirements. This is to prevent a panel from being overloaded. Regardless of ampere ratings, a lighting and appliance type of loadcenter is limited to 42 circuits in one enclosure. If the specifications require more than 42 circuits, two or more loadcenters will be required. 20

22 Interchangeable vs. Non- Interchangeable Breakers Branch circuit breakers are available from many manufacturers and have evolved over the years. Those referred to as interchangeable have 1 wide frames, which means that a single pole, interchangeable breaker is 1 wide, or takes up a 1 space in the loadcenter. While these units, in many cases, will physically fit in another interchangeable manufacturer s loadcenter, it is not approved by the NEC, UL, or the manufacturer of the panel. Non-interchangeable branch circuit breakers typically have a 3/4 frame width for a single-pole unit and are unique to a single manufacturer s loadcenter. These units cannot be installed into another manufacturer s loadcenter because they will not physically fit. Ratings Every circuit breaker has a specific ampere, voltage, and fault current interruption rating. Ampere rating The ampere rating defines the maximum current a circuit breaker can carry without tripping. The typical for miniature circuit breakers is ratings from amps. Voltage rating In residential applications, single pole breakers protect 120 volt branch circuits and two-pole breakers protect 240 volt branch circuits. The rating of a circuit breaker can be higher than the circuit voltage, but never lower. Short circuit interrupting rating This is the maximum available fault current that a breaker is designed to interrupt. Typical ratings is from 10,000 amps to 65,000 amps. 21

23 Ratings (continued) When selecting loadcenters and overcurrent protection devices, it is extremely important to know both the maximum continuous amperes and available fault current. There are two ways to meet this requirement: the full rating method and the series-rated method. The full rating method selects circuit protection devices with ratings equal to or greater than the available fault current. Consider a building service entrance with has 22,000 amps of fault current available. All downstream circuit protection devices must be rated at 22,000 amps. The requirements of the series-rated method are somewhat looser. The building s main circuit protection device must have an interrupting rating which is at least equal to the system s available fault current. However, the all downstream, series-connected panels can have lower ratings. Consider the same building, still with 22,000 amps of available fault current. While the breaker at the service entrance is rated at 22,000 amps, additional downstream breakers could be rated at only 10,000 amps. BRANCH BREAKERS 22,000 AMPS BRANCH BREAKERS 10,000 AMPS MAIN BREAKER 22,000 AMPS MAIN BREAKER 22,000 AMPS FIGURE 19. FULL RATING METHOD (AT LEFT) VS. SERIES-RATED METHOD (AT RIGHT) In the typical single family home, available fault current is normally 10,000 amps or less. 22

24 LOADCENTER TYPES There are three different types of loadcenters made today. These are: Main Breaker Main Lug Only Convertible MAIN BREAKER MAIN LUG CONVERTIBLE FIGURE 20. MAIN CONFIGURATIONS Main Breaker Loadcenter The incoming supply cables of a main breaker loadcenter are connected to the main breaker, which in turn feeds power to the loadcenter and its branch circuits. Power from the mains is fed through the main breaker to the bus bars, which are an extension of the utility power cables. With the main circuit breaker in the off position, no power will flow to the bus bars for the branch circuit breakers. This serves as a quick and simple way to disconnect power to the entire building. MAINS MAIN BREAKER BRANCH CIRCUIT BREAKERS BRANCH CIRCUITS (TO LIGHTS, ETC.) BUS BARS FIGURE 21. SIMPLIFIED MAIN BREAKER TYPE LOADCENTER With the main breaker in the on position, power is allowed to flow from the bus bars to the branch circuits. Branch circuits run throughout the building to supply power for lighting and appliances. Because of these features, the main breaker is normally used as a service entrance panel. 23

25 Main Lug Only Loadcenter The main lug only (MLO) loadcenter does not contain a main circuit breaker to protect the loadcenter itself. Instead, it is protected by a breaker back in an upstream panel. The supply cables from the upstream panel are connected to the main lugs and bus bars. This type of loadcenter is used primarily used in a distribution panel. The MLO is often called an add-on, secondary, or downstream panel. It is most often used when the main breaker loadcenter s circuit slots are full, or to provide power at a remote point. Convertible Loadcenter The convertible loadcenter is supplied without lugs or breakers. Once the customer decides to use main lugs or main breakers, the appropriate kit is installed by an electrician. IN THE WORKPLACE In this home, a main breaker loadcenter supplies power to a main lug only loadcenter in the home s workshop. Main lug only loadcenters can also be fed from metering equipment when used in apartment installations. MAIN BREAKER LOADCENTER MAIN LUG ONLY LOADCENTER USING A MAIN LUG ONLY LOADCENTER 24

26 SELECTING A LOADCENTER Required Application Information When assisting a customer in selecting a loadcenter for an application, it is best to start by interviewing the customer to determine the application s requirements. 1. Ask whether this application will involve an indoor or outdoor installation. This will determine the enclosure type for the loadcenter. NEMA Type 1 General Purpose This enclosure type is for general purpose, indoor use. It is suitable for most applications where unusual service conditions do not exist. It provides protection from accidental contact with enclosed equipment. NEMA Type 3R Raintight This enclosure type is intended for outdoor use. It provides protection against falling rain and sleet, and damage from external ice formation. It has a gasketed cover. If it is an indoor installation, ask whether it will be flush-mounted or surface mounted. FIGURE 22. OUTDOOR, FLUSH AND SURFACE MOUNTING TYPES 2. Ask whether the loadcenter is to serve as a service entrance panel or a distribution panel. 3. Ask whether the application involves a single-phase, three-wire system or a three-phase, four-wire system. 4. Ask what type of main, either a Main Lugs Only or a Main Circuit Breaker. 5. Ask for the main ampere rating. 6. Ask what type and rating main breaker is required, if applicable. 7. Ask for the number of breakers required, and for their ratings. 8. Ask how many spaces are required. The customer may want to leave extra spaces in the loadcenter for future needs. Once this information is obtained, go to the product catalog. These questions should cover everything needed to recommend products that fit the customer s application needs. 25

27 Sample Application To assist you in visualizing the product selection process, let s consider a simple, commonplace customer application. Suppose a customer comes to you and wants to add two branch circuit breakers to an existing loadcenter for a newly remodeled kitchen. How would you go about sizing the breaker? First, interview the customer to find out what loads will be on the branch circuits. Let s say that one will be dedicated to a dishwasher, and the other will be dedicated to a garbage disposal. Next, obtain the amperage requirements of the loads from the customer. Suppose the dishwasher runs on 12.5 amps and the garbage disposal runs on 9.8 amps. Based on these numbers alone, you might think that it would be a good idea to recommend a 15 amp breaker for the dishwasher circuit, and a 10 amp breaker for the garbage disposal circuit. But this would result in a lot of nuisance tripping. So, we need to do a little simple math. Figure in a 25% safety margin by multiplying the amp ratings by Dishwasher12.5 ampsx 1.25 = amps Garbage Disposal9.8 ampsx 1.25 = amps This will be sufficient to eliminate nuisance tripping, but the breakers will still trip in the case of a true overload condition. Based on these calculations, you would recommend a 20 amp breaker for the dishwasher circuit, and a 15 amp breaker for the garbage disposal circuit. 26

28 REVIEW 2 Answer the following questions without referring to the material just presented. 1. List the three main loadcenter types made today. 2. In your own words, explain why a double pole breaker draws twice the voltage of a single pole breaker installed in the same panel. 3. Regardless of ampere ratings, a lighting and appliance type of loadcenter is limited to circuits in one enclosure. 4. List four application questions to ask when working with a customer. 27

29 GLOSSARY Bonding The permanent joining of metallic parts to form an electrically conductive path that will ensure electrical continuity to ground. Branch Circuit Branch Circuit Breaker Bus Bars Circuit Breaker Convertible Loadcenter Distribution Panel Distribution Transformer Double Pole Equipment Grounding Bus Feed-Through Lugs Flush-Mounted Full Rating Method A circuit that supplies power to a load in a building and is terminated at the loadcenter. Also Miniature Circuit Breaker. A reusable overcurrent protection device, used to protect a branch circuit. After tripping to break the circuit, it can be reset to protect the branch circuit again. A component of a loadcenter that serves as an extension of the main service conductors. Simplifies the connection of branch circuit breakers to the main service conductors. A reusable overcurrent protection device. After tripping to break the circuit, it can be reset to protect the circuit again. A loadcenter supplied without main lugs or a main breaker. Once in the field, it is up to the electrician to install the appropriate device. A loadcenter used at a point beyond the building s service entrance. It is not supplied with a main breaker. This type of panel can be useful when adding additional electrical service to an existing building. It has an isolated neutral. A device that converts utility voltage into a voltage and current supply suitable for use in most residential applications. Term used to describe a breaker that draws power from both poles of a loadcenter. A bus connected directly to the enclosure. Used for grounding all feeder and branch circuit equipment. A set of lugs in a service entrance panel where feeder cables for a distribution panel are terminated. A style of mounting a loadcenter in which the loadcenter is recessed into a hole in the wall. A method of selecting circuit protection devices for use in a loadcenter. All devices must have ratings equal to or greater than the available fault current. 28

30 Fuse Ground Fault Grounding Path Half-Size Branch Circuit Breakers Interchangeable Loadcenter Mains Main Circuit Breaker Main Lugs Main Lug Only (MLO) Loadcenter Main Service Conductors Miniature Circuit Breaker A non-reusable overcurrent protection device. After tripping to break the circuit, it must be replaced to restore power to the circuit. Current leakage from an ungrounded conductor to the grounding path in an electrical system A solid conducting path for electricity to follow to ground. A specialized reusable overcurrent protection device designed to take up only half as much space in a loadcenter as a normal branch circuit breaker. Can only be installed in loadcenters equipped with notched stabs. A type of branch circuit breaker that is standardized in size to fit in many different manufacturers loadcenters. A device that delivers electricity from a supply source to loads in light commercial or residential applications. Also Main Service Conductors. The conductors that bring electricity into a building from the power source. Also Main Breaker. A reusable overcurrent protection device designed to protect an entire loadcenter. Component of a loadcenter not equipped with a main breaker. Termination point for a feeder cable from another loadcenter. A loadcenter where power from the mains is fed directly to the bus bars. Also Mains. The conductors that bring electricity into a building from the power source. Also Branch Circuit Breaker. A reusable overcurrent protection device, used to protect a branch circuit. After tripping to break the circuit, it can be reset to protect the branch circuit again. 29

31 Non- Interchangeable Plug-In Series-Rated Method Service Entrance Panel Single Pole Stab Surface-Mounted Terminated Voltmeter A type of branch circuit breaker that is unique to a single manufacturer s loadcenters. This type of breaker cannot be installed into another manufacturer s loadcenter because it will not physically fit. A style of miniature circuit breaker, so named for the method of installation into the loadcenter. It is literally plugged into the bus bar stabs. A method of selecting circuit protection devices for use in a loadcenter. The main upstream circuit protection device must have an interrupting rating equal to or greater than the available fault current of the system. Downstream devices connected in series can be rated at lower values. The term used to describe a loadcenter used as a service entrance. Term used to describe a breaker that draws power from only one pole of a loadcenter. A protrusion on the bus bars of a loadcenter which accepts a miniature circuit breaker. A style of mounting a loadcenter in which the loadcenter is attached to and projects out from the wall. The end connection of a circuit. For example, branch circuits are terminated at the service entrance panel. A device used to find the potential voltage between two points. 30

32 REVIEW 1 ANSWERS distribution panel service entrance panel residential commercial / light industrial 3. neutral, insulated, isolated 4. Answer should basically say If all the loads in a panel are connected exactly evenly between A-N and B-N, no current will flow in the neutral. The amount current flowing in the neutral conductor at any one time is the difference between the current flowing through leg A and leg B. 5. Answer should basically say To supply power to lights, receptacles and loads like dryers, washers, and air conditioners. REVIEW 2 ANSWERS 1. Main Breaker Main Lug Only Convertible 2. Answer should basically say A double pole breaker is plugged onto two adjacent bus stabs. The circuit is made across both ungrounded legs of the transformer. A single pole breaker is plugged onto a single bus stab. The circuit is made from an ungrounded leg of the transformer to the transformer s grounded leg Any four of the following: Indoor or outdoor installation? If indoor, flush-mount or surface-mount? Service entrance panel or a distribution panel? Single-phase, three-wire system or a three-phase, four-wire system? What type of main, Main Lugs Only or Main Circuit Breaker? Main ampere rating? What type and rating main breaker is required? (if applicable) How many branch breakers required, and the rating of each? How many spaces are required? 31

33 Cutler-Hammer Milwaukee, Wisconsin U.S.A. Publication No. TR T.E February 1999 Printed in U.S.A. (GSP) 101 Basics Series and 201 Advanced Series are trademarks of Cutler-Hammer University, Cutler-Hammer and Eaton Corp. 1999, Eaton Corp.

Learning Module 13: Panelboards and Switchboards. 101 Basic Series

Learning Module 13: Panelboards and Switchboards. 101 Basic Series Learning Module 13: Panelboards and Switchboards 101 Basic Series What You Will Learn We ll step through each of these topics in detail: Introduction 4 Definitions 4 Similarities Between Panelboards and

More information

101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION. Cutler-Hammer

101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION. Cutler-Hammer 101 BASICS SERIES LEARNING MODULE 3: FUNDAMENTALS OF ELECTRICAL DISTRIBUTION Cutler-Hammer WELCOME Welcome to Module 3, Fundamentals of Electrical Distribution. If you have successfully completed Module

More information

Grounding & Bonding Why it is done And How to Install Properly

Grounding & Bonding Why it is done And How to Install Properly Grounding & Bonding Why it is done And How to Install Properly The technical information provided herein is to assist qualifi ed persons in planning and installing electric service to farms and residences.

More information

CHAPTER 4 UTILITY SYSTEMS ELECTRICAL. Utility Systems Electrical. Main Panel

CHAPTER 4 UTILITY SYSTEMS ELECTRICAL. Utility Systems Electrical. Main Panel CHAPTER 4 UTILITY SYSTEMS ELECTRICAL Utility Systems Electrical The electrical supply to your home begins outside, where you will see either an overhead feed and piping down the side of your home or (if

More information

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to

More information

GUIDELINES FOR WIRING SINGLE FAMILY DWELLING UNITS

GUIDELINES FOR WIRING SINGLE FAMILY DWELLING UNITS GUIDELINES FOR WIRING SINGLE FAMILY DWELLING UNITS This guideline has been prepared to assist the owner/occupant of a single family dwelling with compliance to the requirements of the National Electrical

More information

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS:

RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: RESIDENTIAL ELECTRICAL REQUIREMENTS (REVISED 3/28/2008) PERMIT REQUIREMENTS: Signed completed Electrical Permit application form. Minnesota law requires all electrical work is to be performed by licensed,

More information

ELECTRICAL INSPECTION BULLETIN (Effective 2000-03-01)

ELECTRICAL INSPECTION BULLETIN (Effective 2000-03-01) ELECTRICAL INSPECTION BULLETIN (Effective 2000-03-01) Rule 28-900 Standby Generator Installations Due to the increasing number of standby generator installations being established to maintain continuity

More information

Electrical Grounding. Appendix C

Electrical Grounding. Appendix C Appendix C Electrical Grounding Low-Voltage Equipment Grounding The most frequently cited Office of Safety and Health Administration (OSHA) electrical violation is improper occupational grounding of equipment

More information

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2014 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits Trade of Electrician Standards Based Apprenticeship Three-phase Distribution Boards And Socket Circuits Phase 2 Module No. 2.3 Unit No. 2.3.2 COURSE NOTES Created by Charlie Walsh - Athlone TC Revision

More information

Arc Fault Circuit Interrupters Frequently Asked Questions

Arc Fault Circuit Interrupters Frequently Asked Questions Contents My AFCI is tripping! What do I do? What is the difference between branch feeder and combination type Arc Fault Circuit Interrupters? What is new with the 2008 NEC versus the 2005 NEC with respect

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

ELECTRIC METERING COMMERCIAL & INDUSTRIAL

ELECTRIC METERING COMMERCIAL & INDUSTRIAL ELECTRIC METERING COMMERCIAL & 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 METER LOCATIONS 5.0 UNDERGROUND TERMINATIONS 6.0 METERING TRANSFORMER ENCLOSURES 7.0 SINGLE CUSTOMER METER INSTALLATIONS

More information

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D

METER REQUIREMENTS GENERAL REQUIREMENTS SECTION D 12 - ELECTRIC SERVICE HANDBOOK SECTION D METER REQUIREMENTS This chapter gives you information on Central Lincoln s metering requirements. It's divided into three sections: General requirements This section

More information

INSTALLATION & SERVICE MANUAL. Display Panel

INSTALLATION & SERVICE MANUAL. Display Panel INSTALLATION & SERVICE MANUAL Display Panel The PowerLine EMS TM is a specialized power distribution and energy management system intended to be used in recreational vehicles. The Control Module is housed

More information

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264 BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

Residential Electrical Inspection. Checklist

Residential Electrical Inspection. Checklist 443 Lafayette Road N. St. Paul, Minnesota 55155 www.doli.state.mn.us Residential Electrical Inspection (651) 284-5064 1-800-DIAL-DLI Fax: (651) 284-5743 TTY: (651) 297-4198 Checklist Generally, Minnesota

More information

Introduction. Upon completion of Basics of Load Centers you should be able to: Explain the role of a load center in residential power distribution

Introduction. Upon completion of Basics of Load Centers you should be able to: Explain the role of a load center in residential power distribution Table of Contents Introduction...2 Residential Power Distribution...4 Load Centers...6 Load Center Construction...8 Residential Circuit Breakers... 16 Ground Fault Protection...23 Arc Fault Protection...25

More information

Electrical Code Regulation

Electrical Code Regulation Electrical Code Regulation St. Clair County has adopted the 2005 National Electrical Code in its entirety for the unincorporated areas of the county and all communities that have contracted with the county

More information

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS

ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS Prepared by: ABB1 ELECTRICAL SERVICE REQUIREMENTS FOR MOBILE HOME DEVELOPMENTS 052521 Asset Type: Electric Metering Function: Construction Issued by: Quoc Hoang (QxH1) Date: 07-01-16 Rev. #06: This document

More information

ELECTRICAL - WIRING DESIGN AND PROTECTION SELF INSPECTION CHECKLIST

ELECTRICAL - WIRING DESIGN AND PROTECTION SELF INSPECTION CHECKLIST Name of School: OPTIONAL INFORMATION Date of Inspection: Vocational Program/Course/Room: Signature of Inspector: ELECTRICAL - WIRING DESIGN AND PROTECTION SELF INSPECTION CHECKLIST Guidelines: This checklist

More information

Protect your home and family with Advanced Technology from Cutler-Hammer

Protect your home and family with Advanced Technology from Cutler-Hammer Protect your home and family with Advanced Technology from Cutler-Hammer Residential Home Fire Statistics Annually - over 415,000 Residential Fires Annually - over 40,000 electrical fires over 350 deaths

More information

Top Commercial / Residential Electrical Requirements *

Top Commercial / Residential Electrical Requirements * Department of Community Development Building Division 4800 West 92 nd Avenue Westminster, Colorado 80031 For Information call (303) 658-2075 Fax (303) 706-3922 www.westminsterpermits.com Top Commercial

More information

MCC Ratings. Voltage Rating

MCC Ratings. Voltage Rating MCC Ratings In addition to the various ratings of individual components used in motor control centers, the overall ratings of the motor control center must also be considered. Voltage Rating Motor control

More information

Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760

Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760 Data Bulletin Determining the Cause of AFCI Tripping Branch/Feeder and Combination Arc Fault Circuit Interrupters Class 760 Retain for future use. 0760DB0204 Replaces 0760DB0204 R09/07 Precautions DANGER

More information

For Models #6-5001, #6-7501, #10-7501 & #10-12K1

For Models #6-5001, #6-7501, #10-7501 & #10-12K1 EmerGen Switch Manual Transfer Switch Manufactured by CONNECTICUT ELECTRIC SWITCH MFG. CO. 1-800-730-2557 OWNER S MANUAL & INSTALLATION INSTRUCTIONS For Models #6-5001, #6-7501, #10-7501 & #10-12K1 PLEASE

More information

Sentron Series Circuit Breakers

Sentron Series Circuit Breakers Sentron Series Circuit Breakers Siemens Sentron Series circuit breakers are available in nine frame sizes: ED, FD, JD, LD, LMD, MD, ND, PD, and RD. Sentron Series circuit breakers have a wide range of

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

Parallel Circuits. Objectives After studying this chapter, you will be able to answer these questions: 1. How are electrical components connected

Parallel Circuits. Objectives After studying this chapter, you will be able to answer these questions: 1. How are electrical components connected This sample chapter is for review purposes only. Copyright The Goodheart-Willcox Co., Inc. All rights reserved. Electricity Objectives After studying this chapter, you will be able to answer these questions:.

More information

Cable/Conduit Conversion

Cable/Conduit Conversion Cable/Conduit Conversion Busway can be used in many applications where cable and conduit are more commonly used. The question arises, Why use busway instead of conventional cable and conduit? Benefits

More information

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage:

Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016. Underground branch circuit feeding a detached garage: Electrical for Detached Garages: Updated Feb 19, 2016 for 2015 CE Code in force Jan. 1, 2016 * Garage construction requires permits (electrical, building) * Permits must be applied for at the time. * Dial

More information

Generator Transfer Switch Model # HTS15-AUTO

Generator Transfer Switch Model # HTS15-AUTO Generator Transfer Switch Model # HTS15-AUTO Congratulations on your purchase of our Single Circuit Generator Transfer Switch, We hope this meets and exceeds your expectations. If at anytime you have any

More information

Residential Electrical Inspection Checklist

Residential Electrical Inspection Checklist Residential Electrical Inspection Checklist Based on the 2008 National Electrical Code Generally, Minnesota law requires all electrical work to be performed by licensed, bonded and insured electrical contractors

More information

BERTHOLD ELECTRIC GENERATOR CONNECTION CABINET

BERTHOLD ELECTRIC GENERATOR CONNECTION CABINET BERTHOLD ELECTRIC GENERATOR CONNECTION CABINET Berthold Electric Company s Generator Connection Cabinet provides a quick and convenient station to connect a portable generator to a facility s main service

More information

Reverse-feed applications for circuit breakers

Reverse-feed applications for circuit breakers Technical Publication PU01200001E Contents Description Page Intoduction.......................................................................... 2 breaker classifications..........................................................

More information

Metallic and Non-Metallic Air Conditioning Disconnects. A Complete Family of. Disconnects with Exclusive Time Saving Features

Metallic and Non-Metallic Air Conditioning Disconnects. A Complete Family of. Disconnects with Exclusive Time Saving Features Metallic and Non-Metallic Air Conditioning Disconnects A Complete Family of Disconnects with Exclusive Time Saving Features Enclosed Molded Case Disconnect Switch Not-Fusible The preferred molded case

More information

Fundamentals of Power

Fundamentals of Power Fundamentals of Power Fundamentals of Power 2008 American Power Conversion Corporation. All rights reserved. All trademarks provided are the property of their respective owners. Learning Objectives At

More information

Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide

Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Instruction Bulletin EAV85226 08/2014 Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Retain for future use. Product Description Kit Contents The Wiser Panel Meter is for use in energy management

More information

Commercial/Industrial Electricity

Commercial/Industrial Electricity 1 ELC 210 Commercial/Industrial Electricity Course Package Presented and Approved July 31, 2008 2 Contact person(s) DAVE WHITE Date of proposal to JULY 31, 2008 Curriculum Committee NEW COURSE PACKAGE

More information

The Different Types of AC Power Connectors in North America

The Different Types of AC Power Connectors in North America The Different Types of AC Power Connectors in North America White Paper #20 Executive Summary A confusing array of AC power plugs and receptacles exist to deliver power to various electronic loads. This

More information

Installation Instructions

Installation Instructions READ BEFORE INSTALLING UNIT For Slider Casement Air Conditioners To avoid risk of personal injury, property damage, or product damage due to the weight of this device and sharp edges that may be exposed:

More information

Siemens STEP 2000 Course Basics of Electrical Products

Siemens STEP 2000 Course Basics of Electrical Products Siemens STEP 2000 Course Basics of Electrical Products It's easy to get in STEP! Download any course. Hint: Make sure you download all parts for each course and the test answer form. Complete each chapter

More information

Video Camera Installation Guide

Video Camera Installation Guide Video Camera Installation Guide The intent of this guide is to provide the information needed to complete or modify a video camera installation to avoid lightning and induced power surge damage. This guide

More information

The Service Entrance. Technical Terms Drip loop Insulator Meter Meter enclosure

The Service Entrance. Technical Terms Drip loop Insulator Meter Meter enclosure This sample chapter is for review purposes only. Copyright The Goodheart-Willcox Co., Inc. All rights reserved. 10 The Entrance Objectives Information in this chapter will enable you to: List the components

More information

Secondary Unit Substations

Secondary Unit Substations 14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically

More information

MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS

MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS 01. SAFETY INSPECTION of service equipment at FPL Power Source 02. Construction GFI power outlets (Temp Pole for Construction) 03. 90 day temporary power

More information

Engineers Edge, LLC PDH & Professional Training

Engineers Edge, LLC PDH & Professional Training 510 N. Crosslane Rd. Monroe, Georgia 30656 (770) 266-6915 fax (678) 643-1758 Engineers Edge, LLC PDH & Professional Training Copyright, All Rights Reserved Engineers Edge, LLC An Introduction to Interior

More information

Application Bulletin 103 - NEC Reference Guide for SolarBridge-Enabled AC Module Installers

Application Bulletin 103 - NEC Reference Guide for SolarBridge-Enabled AC Module Installers 9229 Waterford Centre Dr. Bldg C, Suite 110 Austin, Tx 78758 Application Bulletin 103 - NEC Reference Guide for SolarBridge-Enabled AC Module Installers Current Version: 13 AC Modules are a new product

More information

Residential Electrical Inspection. Checklist

Residential Electrical Inspection. Checklist Electrical Licensing and Inspection 443 Lafayette Road North St. Paul, Minnesota 55155-4342 www.doli.state.mn.us 651-284-5064 Fax: 651-284-5743 TTY: 651-297-4198 1-800-DIAL-DLI Residential Electrical Inspection

More information

Installation Instructions For Slider Casement Air Conditioners

Installation Instructions For Slider Casement Air Conditioners Installation Instructions For Slider Casement Air Conditioners NOTE: These instructions describe installation in a typical wood framed window with a wood SLIDE-BY sash, or installation in a metal CASEMENT

More information

City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov

City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov PHOTOVOLTAIC PERMITTING GUIDELINES The information provided in this document is general and is intended only as a

More information

Instruction / Installation Sheet DataComm Electronics 50-6623-WH-KIT Flat Panel TV Cable Organizer Kit with Duplex Power Solution

Instruction / Installation Sheet DataComm Electronics 50-6623-WH-KIT Flat Panel TV Cable Organizer Kit with Duplex Power Solution Instruction / Installation Sheet DataComm Electronics 50-6623-WH-KIT Flat Panel TV Cable Organizer Kit with Duplex Power Solution DataComm Electronics, Inc. 6349 Peachtree Street Norcross, GA 30071-1725

More information

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services

Circuit Breakers and Switchgear. Thomas Greer Director of Engineering TLG Services Circuit Breakers and Switchgear Thomas Greer Director of Engineering TLG Services Presentation Outline Switchgear Definition Overcurrent Protection Devices Circuit Breaker Trip Curves and Coordination

More information

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings *** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not

More information

County of Riverside Building and Safety Department

County of Riverside Building and Safety Department County of Riverside Building and Safety Department Mike Lara Director Photovoltaic Permitting Guidelines The information provided in this document is general and is intended only as a guide. Each project

More information

Table of Contents. www.hunterfan.com. What to Expect with. Preparation. Tools Needed. Wiring. Hanging the Fan. Blades. Motor Housing.

Table of Contents. www.hunterfan.com. What to Expect with. Preparation. Tools Needed. Wiring. Hanging the Fan. Blades. Motor Housing. www.hunterfan.com Table of Contents What to Expect with Your Installation 30 inches Hanging the Fan Wiring 8 Maintenance, Operation & Cleaning Light Kit 13??? 14 1 9 Troubleshooting 11 5 Blades Motor Housing

More information

Short Circuit Current Calculations

Short Circuit Current Calculations Introduction Several sections of the National Electrical Code relate to proper overcurrent protection. Safe and reliable application of overcurrent protective devices based on these sections mandate that

More information

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation

MTE SERIES RLW. World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930. 2009 MTE Corporation MTE SERIES RLW World REACTORS USER MANUAL PART NO. INSTR 030 REL. 090930 2009 MTE Corporation IMPORTANT USER INFORMATION NOTICE MTE Series RLW reactors are components designed to improve the reliability

More information

A guide to understanding and maintaining your home s electrical system. A publication presented by the Electrical Safety Foundation International

A guide to understanding and maintaining your home s electrical system. A publication presented by the Electrical Safety Foundation International A guide to understanding and maintaining your home s electrical system A publication presented by the Electrical Safety Foundation International What s Inside? Everything you need to know Should You Do-It-Yourself?

More information

Services. Three Phase Service

Services. Three Phase Service Services Primary Service vs Secondary Service Overhead vs Underground Common Service Types Three Phase Wye Closed Open Delta Corner Grounded Center Tapped Open Single Phase Three Phase Service Wye Delta

More information

VS CONTROL PACK INSTALLATION INSTRUCTIONS

VS CONTROL PACK INSTALLATION INSTRUCTIONS VS CONTROL PACK INSTALLATION INSTRUCTIONS Hot Tub Works www.hottubworks.com 1-800-770-0292 CustomerCare@HotTubWorks.com Congratulations! You have purchased and are about to install in your spa, the most

More information

Homeowner Information Guide Electrical Safety. British Columbia Safety Authority

Homeowner Information Guide Electrical Safety. British Columbia Safety Authority Homeowner Information Guide Electrical Safety British Columbia Safety Authority The following information should be carefully reviewed before performing any electrical work. The information contained in

More information

ELECTRIC CONVECTION BUILT-IN OVEN

ELECTRIC CONVECTION BUILT-IN OVEN ENGLISH ESPAÑOL FRANÇAIS INSTALLATION MANUAL ELECTRIC CONVECTION BUILT-IN OVEN Please read these instructions thoroughly before installing and operating the oven. LWS3081ST LWD3081ST LSWS305ST LSWD305ST

More information

Bypass transfer switch mechanisms

Bypass transfer switch mechanisms Power topic #6013 Technical information from Cummins Power Generation transfer switch mechanisms > White paper By Gary Olson, Director, Power Systems Development This paper describes the configuration

More information

Generator DoCKInG StatIonS

Generator DoCKInG StatIonS Generator DOCKING STATIONS TRYSTAR Portable Power Cable Cam to cam cable extensions 2000V, 100A-400A rated to NEC table 400.5 (B) All portable power cable sold is highly flexible and UL & C-UL or CSA Listed

More information

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL

SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL SECTION 26 09 13 - POWER MONITOR FOR ELECTRICAL, STEAM CONDENSATE, AND WATER PART I - GENERAL 1.1 SUMMARY A. This section describes the requirements for the installation of Power Monitors and associated

More information

101 BASICS SERIES LEARNING MODULE 2: FUNDAMENTALS OF ELECTRICITY. Cutler-Hammer

101 BASICS SERIES LEARNING MODULE 2: FUNDAMENTALS OF ELECTRICITY. Cutler-Hammer 101 BASICS SERIES LEARNING MODULE 2: FUNDAMENTALS OF ELECTRICITY Cutler-Hammer WELCOME Welcome to Module 2, Fundamentals of Electricity. This module will cover the fundamentals of electricity in a practical

More information

PREFACE. Your comments or suggestions are welcome and appreciated. They should be sent to:

PREFACE. Your comments or suggestions are welcome and appreciated. They should be sent to: PREFACE UL developed the Dead-Front Switchboard Marking Guide for code authorities, electric utilities, contractors, installers, users, designers, and other interested parties to aid in understanding deadfront

More information

Utility Distribution Systems

Utility Distribution Systems Utility Distribution Systems 6/2012 A0011037 1 WARRANTY This equipment is warranted to be free from defects in materials and workmanship, under normal use and service, for a period of 12 months from date

More information

IRRIGATION PUMPING Table of Contents - Section 900

IRRIGATION PUMPING Table of Contents - Section 900 IRRIGATION PUMPING Table of Contents - Section 900 PARAGRAPH 900.1 GENERAL 1 900.2 METERING REQUIREMENTS 1 900.3 CUSTOMER S CONTROL EQUIPMENT 2 900.4 SERVICE CONDUCTOR REQUIREMENTS 2 900.5 RECOMMENDATIONS

More information

Chapter 9. Bonding and Grounding

Chapter 9. Bonding and Grounding Chapter 9 Bonding and Grounding Objectives Describe why the cable should be bonded Describe bonding and grounding procedures Define Bonding and Grounding Explain Safety Benefits and intent of bonding and

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Overhead Electric Service Installation This brochure addresses most typical residential overhead service installations. Variances for the following specifications must be

More information

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope

3. TYPES OF SERVICE AVAILABLE. 3.1 Scope 3. TYPES OF SERVICE AVAILABLE 3.1 Scope UI supplies 60 hertz, alternating current with different voltage and ampere ratings. Not all voltage and ampere ratings are available throughout the entire service

More information

IntelliBrite Controller (For IntelliBrite Pool, Spa and Landscape Lighting Fixtures) Installation and User s Guide

IntelliBrite Controller (For IntelliBrite Pool, Spa and Landscape Lighting Fixtures) Installation and User s Guide IntelliBrite Controller (For IntelliBrite Pool, Spa and Landscape Lighting Fixtures) Installation and User s Guide *619751* P/N 619751 - Rev C IMPORTANT SAFETY INSTRUCTIONS READ AND FOLLOW ALL INSTRUCTIONS

More information

AMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5

AMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5 AMFA-27 AMFA-29 Operator s Manual & Installation Instructions Rev. 2.5 Date: 17 July, 2010 Permanently-connected, utility Interactive, single-phase, inverters Model AMFA-27 WIND TURBINE INVERTER (240 VAC

More information

Guidelines on the Short Circuit Current Rating for Industrial Control Panels

Guidelines on the Short Circuit Current Rating for Industrial Control Panels usa.siemens.com/sccr Guidelines on the Short Circuit Current Rating for Industrial Control Panels Technical Paper for Practical Applications White Paper I October 2014 As per NEC Edition 2014, and UL508A

More information

BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS

BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS BUILT-IN DISHWASHER INSTALLATION INSTRUCTIONS PLEASE READ COMPLETE INSTRUCTIONS BEFORE YOU BEGIN LEAVE INSTALLATION INSTRUCTIONS AND USER'S GUIDE WITH OWNER ALL ELECTRIC WIRING AND PLUMBING MUST BE DONE

More information

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

National Craft Assessment and Certification Program S P E C I F I C A T I O N S National Craft Assessment and Certification Program S P E C I F I C A T I O N S INDUSTRIAL ELECTRICIAN V4 ELEC26_O4 Released September 2013 Focus Statement An Industrial Electrician must be able to interpret

More information

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013

ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 ARCO Electric Products Installation and Maintenance Manual Low Voltage Automatic Power Factor Correction Capacitor Systems 2013 READ CAREFULLY These instructions are intended to cover good practices in

More information

Common Electrical Hazards in the Workplace Including Arc Flash. Presented by Ken Cohen, PhD, PE & CIH (Ret.)

Common Electrical Hazards in the Workplace Including Arc Flash. Presented by Ken Cohen, PhD, PE & CIH (Ret.) Common Electrical Hazards in the Workplace Including Arc Flash Presented by Ken Cohen, PhD, PE & CIH (Ret.) 1 What s New In February 1972, OSHA incorporated the 1971 edition of the National Fire Protection

More information

INSPECTION GUDELINES

INSPECTION GUDELINES GENERAL REQUIREMENTS Building permit and approved set of plans Building permit on the card is the same as on the route "If this is not the first inspection, read inspection records and notes on permit

More information

MONTGOMERY COUNTY EXECUTIVE REGULATION Offices of the County Executive. 101 Monroe Street. Rockville, Maryland 20850

MONTGOMERY COUNTY EXECUTIVE REGULATION Offices of the County Executive. 101 Monroe Street. Rockville, Maryland 20850 Montgomery County Regulation on: ADOPTION OF THE 2008 NATIONAL ELECTRICAL CODE DEPARTMENT OF PERMITTING SERVICES Issued by County Executive Regulation # 15-09 Authority: Code Section 17-2 and 17-3 Supersedes:

More information

GENERAL WIRING RULES FOR HOUSES

GENERAL WIRING RULES FOR HOUSES GENERAL WIRING RULES FOR HOUSES 1. Romex has to be installed in drilled holes in joists or studs even above suspended ceilings - No stapling to bottom edges of joists or studs. You may staple wire to flat

More information

Three-Phase Electric Power Distribution for Computer Data Centers

Three-Phase Electric Power Distribution for Computer Data Centers Three-hase Electric ower Distribution for Computer Data Centers WHITE AER E901 Geist January 008 Summary This paper will describe the characteristics of three-phase power and outline the advantages of

More information

Proper Application of 415V Systems in North American Data Centers. A White Paper from the Experts in Business-Critical Continuity

Proper Application of 415V Systems in North American Data Centers. A White Paper from the Experts in Business-Critical Continuity Proper Application of 415V Systems in North American Data Centers A White Paper from the Experts in Business-Critical Continuity Introduction Increasing pressure to reduce operating expenses and be more

More information

INSTALLATION MANUAL ELECTRIC RANGE. Please read these instructions thoroughly before installing and operating the range.

INSTALLATION MANUAL ELECTRIC RANGE. Please read these instructions thoroughly before installing and operating the range. ENGLISH ESPAÑOL INSTALLATION MANUAL ELECTRIC RANGE Please read these instructions thoroughly before installing and operating the range. LRE3025ST LRE3085ST LRE3083ST LRE3083SB LRE3083SW LRE3021ST LDE3037ST

More information

Remote Power Panels with Breakers

Remote Power Panels with Breakers Remote Power Panels with Breakers 8 Series Panels & Enclosures N/A N/A Remote power panels with breakers are available in two different sizes, each of which may be either surfacemounted or recess-mounted,

More information

Construction Electrical Terminology. Electricians

Construction Electrical Terminology. Electricians Construction Electrical Terminology Electricians Acknowledgments Winnipeg Technical College and the Department of Labour and Immigration of Manitoba wish to express sincere appreciation to all contributors.

More information

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS MIOSHA-STD-1313 (10/15) 6 Pages For further information Ph: 517-284-7740 www.michigan.gov/mioshastandards DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION SAFETY STANDARDS

More information

Corner-Grounded Delta (Grounded B Phase) Systems

Corner-Grounded Delta (Grounded B Phase) Systems Data Bulletin 2700DB0202R03/12 09/2012 Replaces 2700DB0202R2/09 dated 02/2009 Corner-Grounded Delta (Grounded B Phase) Systems Class 2700 Retain for future use. Introduction Corner-grounded delta systems

More information

INSTALLATION INSTRUCTION SPEC. SHEET 7/00. City of New York Calendar #40747 ETL LISTED UNDER U.L. STD. 2108 LOW VOLTAGE TRACK LIGHTING SYSTEM

INSTALLATION INSTRUCTION SPEC. SHEET 7/00. City of New York Calendar #40747 ETL LISTED UNDER U.L. STD. 2108 LOW VOLTAGE TRACK LIGHTING SYSTEM 7/00 INSTALLATION INSTRUCTION SPEC. SHEET 99052 99063 City of New York Calendar #40747 Copyright c 2000 ALFA Lighting, Inc. All rights reserved. Call:1-415-975-8080 QUICK JACK QJS R LISTED 9901483 ETL

More information

ELECTRIC UTILITY SERVICE EQUIPMENT REQUIREMENTS COMMITTEE, EUSERC

ELECTRIC UTILITY SERVICE EQUIPMENT REQUIREMENTS COMMITTEE, EUSERC ELECTRICAL SERVICE REQUIREMENTS ELECTRIC UTILITY SERVICE EQUIPMENT REQUIREMENTS COMMITTEE, EUSERC TABLE OF CONTENTS TITLE SECTION NO. List of Approved Electric Utility Service Equipment Requirements Committee

More information

DC disconnects for solar photovoltaic installations. Connecting the. power of the sun

DC disconnects for solar photovoltaic installations. Connecting the. power of the sun DC disconnects for solar photovoltaic installations Connecting the power of the sun Solar energy is heating up Interest in renewable energy sources has never been greater, and the fastest growing of these

More information

HM-W536 Install Guide

HM-W536 Install Guide HM-W536 Install Guide 9/13/2013 IMPORTANT SAFETY INSTRUCTIONS Warning - When using electrical devices, basic safety precautions should be followed to reduce the risk of fire, electrical shock or injury.

More information

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23

INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 INDUSTRY WIDE LABOR-MANAGEMENT SAFETY COMMITTEE SAFETY BULLETIN #23 GUIDELINES FOR WORKING WITH PORTABLE POWER DISTRIBUTION SYSTEMS AND OTHER ELECTRICAL EQUIPMENT "ADDENDUM C" WORKING WITH 480 VOLT SYSTEMS

More information

Applications. Remote Display Mounting Kits

Applications. Remote Display Mounting Kits June 200 Sheet 105 Surge Protection Products TVSS General Description Clipper Power System Visor Series.1-5 Clipper Power System Visor Series General Description Eaton s Cutler-Hammer leading-edge surge

More information

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less.

SWITCHGEAR Section 16. SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. PART 1 - GENERAL SECTION INCLUDES This Section includes service and distribution switchboards rated 600 V and less. RELATED SECTIONS Division 16 Section "Basic Electrical Materials and Methods" for general

More information

Questions and Answers for Heating and A/C Contractors

Questions and Answers for Heating and A/C Contractors 1. How do we accomplish grounding of furnaces and / or water heaters on two wire circuits? 250.134 Equipment Fastened in Place or Connected by Permanent Wiring Methods (Fixed) Grounding. Unless grounded

More information

Mini Power-Zone Unit Substation Product Description. Product Description. Features. Typical Applications

Mini Power-Zone Unit Substation Product Description. Product Description. Features. Typical Applications Product Description Product Description The Mini Power-Zone Unit Substation from Schneider Electric is a miniaturized version of our Power-Zone Unit Substation. Included are: Circuit Breaker Sealed Step-Down

More information