COST DATA FOR LOW VOLTAGE SWITCHGEAR COMPENSATION

Size: px
Start display at page:

Download "COST DATA FOR LOW VOLTAGE SWITCHGEAR COMPENSATION"

Transcription

1 Filed: September, 00 Exhibit G Page of COST DATA FOR LOW VOLTAGE SWITCHGEAR COMPENSATION.0 INTRODUCTION Under Proceeding RP--00 the Ontario Energy Board approved that two distribution companies (Toronto Hydro Electric System Ltd. and Hydro Ottawa Ltd.) should continue to receive compensation for the low voltage switchgear equipment they own, operate and maintain in Hydro One s transformation stations. 0 The estimate of average cost of providing low voltage switchgear service in Proceeding RP--00 was reviewed so that the compensation amount can be determined for use in calculating the 00 and 00 Transformation Connection Service revenue requirement and rates. The purpose of this Schedule is to document the derivation of the average cost..0 BACKGROUND 0 In the 0s, Toronto Hydro and Ottawa Hydro decided to install and pay for their own low voltage switchgear at some of the Ontario Hydro Owned transformation stations supplying their loads. There was no credit paid to these utilities at the time. In the utilities involved negotiated with Ontario Hydro for a credit in recognition of their ownership of these assets. This credit has been paid by Ontario Hydro since that time, and the value of the credit was escalated from time to time in the same proportion as the transformer station asset base ( kv) has escalated. Upon open access, the credit mechanism ceased.

2 Filed: September, 00 Exhibit G Page of Hydro One, Toronto Hydro Electric System Ltd. and Hydro Ottawa Ltd. submitted a joint low voltage switchgear compensation proposal to Ontario Energy Board for resolution as part of the RP--00 on October 0, 000. The Board approved the proposal which specifies that Toronto Hydro Electric System Ltd. and Hydro Ottawa Ltd. should continue to receive compensation for the low voltage switchgear equipment they own, operate, and maintain in Hydro One s transformation stations after Open Access. 0.0 ESTIMATING AVERAGE COST OF LOW VOLTAGE SWITCHGEAR SERVICE The average cost of providing the low voltage switchgear service is estimated based on the Capital and OM &A costs associated with the low voltage switchgear facilities that are typical of Hydro One s Dual Element Spot Network ( DESN ) stations. The average low voltage switchgear service costs are expressed as a percentage of total station costs. Although the actual amount of the cost figures may have varied over time, the percentage has remained relatively constant. The cost estimation completed for this submission uses the same methodology as described in Proceeding RP Average Capital Costs The facilities to be covered by the low voltage switchgear service are summarized in Table below. Station facilities that are not directly related to the low voltage feeder switching (e.g. step-down transformers) or facilities that are provided at the station irrespective of the low voltage feeder switching (e.g. station fence) are excluded.

3 Filed: September, 00 Exhibit G Page of Table Station Facilities Associated with Low Voltage Feeder Switching Included Feeder switching facilities (including circuit breakers and disconnect switches) Protection & control equipment on feeders Share of low voltage bus protection Share of steel structures or metalclad and footings Share of buildings Share of station battery Methodology of Estimating Average Capital Costs Excluded High voltage equipment Step down transformers Transformer breakers and associated disconnect switches Bus-Tie Breaker and associated disconnect switches Neutral reactors or grounding transformers Capacitors and associated equipment Share of Protection & control equipment not associated with feeders Station service Station total metering and billing metering Supervisory control equipment Site Fence Outdoor lighting Oil, water, sanitation and drainage systems Fire protection 0. Identify the capital costs of station elements for typical Hydro One transformer station configurations.. Determine the percentage of each station element cost attributable to the low voltage switchgear service. The percentage is verified against the actual low voltage switchgear costs of a typical station.. Apply the percentage in () to each station element cost to calculate the share of costs attributable to the low voltage switchgear service.

4 Filed: September, 00 Exhibit G Page of. Determine the percentage of low voltage switchgear service costs for each station configuration.. Weight the percentage in () by the percentage of DESN stations in each configuration to determine the percentage contribution to low voltage switchgear service for each asset configuration.. Sum the percentages in () to arrive at the total weighted average of transformer station capital costs associated with low voltage switchgear service. 0 Results The results of the average capital cost calculation are shown in Table.

5 Table : LVS Credit Average Capital Costs Calculation Filed: September, 00 Exhibit G Page of Actual Cost Estimate Cost (E&CS July 00) LV Credit Costs Belle River TS Bermondsey Jones Jones Bermondsey Small TS** New HN Station Bermondsey Jones Jones Bermondsey Small TS** New HN Station -.kv, AIS 0-kV -kv -.kv 0-.kV -./. kv Jones 0-kV -kv -.kv 0-.kV -./. kv Jones x / MVA x/ MVA, x0/ MVA x0/ MVA x0/00 MVA x0/ MVA 0-. x/ MVA, x0/ MVA x0/ MVA x0/00 MVA x0/ MVA 0-. Fdrs Fdrs Fdrs Fdrs 0 Fdrs Fdrs 0/ MVA Fdrs Fdrs Fdrs 0 Fdrs Fdrs 0/ MVA In-service May 00 Trafalgar TS I/S Dec escalated to 00 **** Cost Factor (%) Applicable to LV Credit Trafalgar TS I/S Dec Major Equipment Transformers,000,00,0,0,0,0,0 Circuit Breakers - Trf Brkrs + Bus Tie Brkr (Including Bus Duct) Feeder Brkrs % HV Switchyard & LV Structures or GIS, % 0 0 LV Disconnect Switches, PT's & SA % HV Switches & Other equipment Capacitor Banks - kv x. Mx none Elect Hardware & Spare Components % Subtotal,,,0,,,0,,,,0, Ancillary / Auxilliary Equipment Relaying - HV Line related Relaying - Feeders % Local Control / annunciation 0 0% Battery/Charger 0 0% Grounding / Instrumentation Wiring % 0 Neutral Reactors 0 0 Station Service Trfs x kva Netralizing Trfs or Tone Equip none HVAC Lighting 0 0 Subtotal 0 Civil Construction Site Prep & Grading Access Road & Services* Control Bldg % Switchyard Foundations & Oil Containment % Finish Grading & Fencing Site Restoration & Landscape Subtotal,00,,,,,0 Electrical Construction Transformers - ship of load, dress Erection & Installation % Grounding & Aux Services % Control & Instrumentation 0 0 0% Subtotal, Commissioning % 00 0 Approvals, Permits Engineering & Design Geotech, Noise, Ground Studies % Preliminary Eng & Related Studies % 0 0 Detailed Engineering,00,00,00,0,0,000, % Site Supervision 0% Subtotal,0,0,,,,00, Project Management Project Manager & Support Services Total 0,,,0,00,,0,,,,0,0,, Contingency (0% of Major Equipment) Contingency (% of Labour Related) Interest During % PeopleSoft (NS) surcharges, sundries, etc.(.%),00,,,0,,, % Total Station Costs,,,,0, 0,,0,,,0,,, Land Cost*** & Regulatory Approvals Total Costs - STATION WITH LAND,,,0,0, 0,, LV Credit % 0% 0% 0% 0% % % Approximate Number of HONI DESN Stations in Each Category ***** : % Contribution OF LV Credit for Each Asset Class :.%.%.%.%.%.% TOTAL Weighted Averge of LV Credit :.% Notes: * Not included in Elecsar Eng Estimates. Estimate of $k for access roads added seperately. ** Small TS based on similar estimate for Jones type station with only feeder positions *** Land Cost based on $00k/acre **** Escalation factor for to 00 =.% ***** Not all stations have the same number of feeders as the cost examples 0

6 Filed: September, 00 Exhibit G Page of. Average Operating & Maintenance Costs The costs are based on an average operating and maintenance costs of a typical DESN station. All annual costs for routine preventive maintenance activities were derived from the Preventive Maintenance Optimization ( PMO ) process described in Exhibit C, Tab, Schedule. 0 Methodology of Estimating Average Operating and Maintenance Costs. Identify the OM&A costs of station elements and related maintenance activities for a typical Hydro One DESN station.. Determine the percentage of the costs from () attributable to the low voltage switchgear service.. Calculate the share of costs attributable to the low voltage switchgear service based on the percentage from ().. Determine the percentage of the total average OM&A costs of a typical DESN station attributable to the low voltage switchgear service. 0 Results The results of the average OM&A cost calculation are shown in Table below.

7 Filed: August, 00 Draft Exhibit G Tab Page of Table Average Operating & Maintenance Costs DESN OM&A Costs Annual Equip. Cost / unit Qty Mntc. Costs (annualized) Cost Factor(%) Applicable to LV Credit LV Credit Costs Note Major Equipment Transformers 0 $,0 Tapchangers 0 $, Feeder Brks 0 $,0 00% $,0.00 Transformer Bank, Bus Tie and Cap Brks 0 $,0 Bus $ HV Switches - Motorized $ LV Switches - Manual 0 $,0 Note % $,.00 Subtotal $, Ancillary/ Auxillary Equipment Relaying - HV Bus Backup $ Relaying - Transformer Diff. $ Relaying - Transformer Gas Protection $ Relaying - Transformer Backup $ Relaying - Line Backup ( non self checking) $ Relaying - Bus Protection $ Relaying - Breaker Failure $ Relaying - Load Shedding $ Relaying - Cap Protection $ Relaying - Feeder Protection $ Zone Test Trip 0 $ All Protection - Inspection $ Note % $. Battery - Inspection & Maintenance 0 $,0 Note % $. Battery Charger $, Note % $. Station Service Trfs Maintenance 0 $0 Station Service AC/DC $, Neutralizing Trfs 000 $,000 Note Telecom Communication 00 $,00 Telecom Metallic Cable $ Note HVAC and Fans $, Inspect All NT, IT & Optical isolators $ Subtotal $, Station & Site Station Inspection - Power Equipment $, Note % $. Station Thermovision $ Note % $0. Buildings, enclosures, yard, fence, water & sewage 0 $,0 Station Fire Protection 0 $0 Station Fire Detection System $ Station Containment System - minor maintenance $ Roads, Bridges, Railroads & Cranes 0 $0 Station herbicide application & reporting $, PCB & waste mgmt 0 $,0 Land Assessment and Remediation $, Subtotal $,0 Other Operational Routines $0 Note $0.00 Field Switching 0 $,0 Note % $0. Trouble Calls $, Note % $,0. Corrective Maintenance - Station Equipment $, Note % $,. Corrective Maintenance - P&C $, Note % $,0. Corrective Maintenance - Revenue metering $, Corrective Maintenance - Telecom $ Note Corrective Maintenance - Infra-structure $, Note Corrective Maintenance - Ancilliary Equip. $, Subtotal $, Total Station OM&A Costs $, LV Credit $ $, Note: LV Credit %.% ) % credit was based on LV feeder switches out of a total of 0 LV switches including LV switches for bank/bus-tie/cap breakers and ) % credit was based on feeder protections versus a total of protections at the station. There is no routine feeder protection ) % credit was based on the proportion of LV feeder breakers versus the total number of major equipment at the station (I.e. transformers, tapchangers, HV motorized switches, bank breakers, bus-tie breaker, cap breaker and feeder breakers). ) All Telecom work is associated with HV bus backup, line backup and transformer protections. ) Operation Routines are no longer tracked as a separate entity since H does not have travelling operator, instead it is incorporated in the Field Switching Expense. ) % credit for field switching was based on the proportion of LV feeder breakers to the total number of switching equipment at the station (I.e. tapchangers, HV switches, bank breakers, bus-tie breaker, cap breaker, 0 LV switches and feeder breakers) ) Corrective Maintenance - Infra-structure includes all corrective work associated with Station buildings, structures, yard, fence, drains and all other installed electrical and mechanical systems at site, but exclude all power and ancillary equipment.

8 Filed: September, 00 Exhibit G Page of.0 CONCLUSION The average low voltage switchgear service costs comprise.0% of Hydro One s total DESN station cost. This remains the same as the previous estimate in Proceeding RP- -00 filed with Ontario Energy Board on October 0, 000.

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

INVESTMENT SUMMARY FOR PROGRAMS/PROJECTS IN EXCESS OF $3 MILLION

INVESTMENT SUMMARY FOR PROGRAMS/PROJECTS IN EXCESS OF $3 MILLION Filed: September 30, 2008 EB-2008-0272 Exhibit D2 Tab 2 Schedule 3 Page 1 of 80 1 2 INVESTMENT SUMMARY FOR PROGRAMS/PROJECTS IN EXCESS OF $3 MILLION 3 4 5 6 7 8 Sustaining Capital S1 to S36 Development

More information

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

Distribution Substation Manual (DSM) Section I - Introduction

Distribution Substation Manual (DSM) Section I - Introduction (DSM) Section I - Introduction March 2007 Document release information Client Project name Western Power Distribution Substation Manual Document number 3463019 Document title Revision status Introduction

More information

Emirates Aluminium starts up World s first fully integrated power distribution system from ABB

Emirates Aluminium starts up World s first fully integrated power distribution system from ABB Reprint from Aluminium World 2009, Volume 2 Emirates Aluminium starts up World s first fully integrated power distribution system from ABB Emirates Aluminium (EMAL), a joint venture between Abu Dhabi s

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: PHONE: PHONE: ARCHITECT/ENGINEER

More information

Addendum #2 Contract UK-11-13

Addendum #2 Contract UK-11-13 Addendum #2 Contract UK-11-13 Utilities Kingston Purchase and Replacement of Switchgear at Kingston Hydro Substation MS11 March 25, 2011 Delivered to: All RFP recipients Total number of pages: Nine (9)

More information

QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room

QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room QUESTIONS and ANSWERS RFB 745-15-9894, Metal Clad Switchgear and Power Control Room 1) When you click on the UTHSCSA Drawing the site takes you to the E-1 drawing no other. Will there be other drawings

More information

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION

INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION INDUSTRIAL AND COMMERCIAL SERVICE TRANSFORMER & METERING INSTALLATION SPECIFICATION February 2013 NOTE: If conflict exists between St. Thomas Energy s Conditions of Service and this document, the Conditions

More information

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories: Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission

More information

Power Plant Electrical Distribution Systems

Power Plant Electrical Distribution Systems PDH Course E184 Power Plant Electrical Distribution Systems Gary W Castleberry, PE 2008 PDH Center 2410 Dakota Lakes Drive Herndon, VA 20171-2995 Phone: 703-478-6833 Fax: 703-481-9535 www.pdhcenter.com

More information

Substation Automation and Smart Grid

Substation Automation and Smart Grid GE Energy Substation Automation and Smart Grid John D. McDonald, P.E. GM, T&D Marketing IEEE PES Past President IEEE Division VII Director IEEE Fellow The Smart Grid POWERING POTENTIA L Current Situation

More information

Remote Monitoring and REC 501 Control Unit Product Guide

Remote Monitoring and REC 501 Control Unit Product Guide Remote Monitoring and Control Unit REC 501 Product Guide Issued: May 1999 Status: Updated Version: B/06.11.2001 Data subject to change without notice Features Remote control and monitoring unit for the

More information

MOBILE DC POWER SYSTEMS FOR SUBSTATION APPLICATIONS

MOBILE DC POWER SYSTEMS FOR SUBSTATION APPLICATIONS MOBILE DC POWER SYSTEMS FOR SUBSTATION APPLICATIONS Gary P. Guagliardi Director Sales & Marketing HindlePower, Inc. Easton, PA Introduction This paper explores the use of mobile DC power systems for three

More information

ICM Project Station Infrastructure and Equipment

ICM Project Station Infrastructure and Equipment EB 0 00 Schedule B. ( pages) ICM Project Station Infrastructure and Equipment (THESL) EB 0 00 Schedule B. I EXECUTIVE SUMMARY 0. Project Description Many Municipal Substations (MS) located outside of downtown

More information

Asset Management Plans

Asset Management Plans November 213 Introduction Table of Contents Page # ACS Buildings & Grounds 2 Purpose and Scope ACS Buildings & Seismic 3 The purpose of these ( Plans ) is to demonstrate how we intend to deliver on the

More information

Primary and Secondary Electrical Distribution Systems

Primary and Secondary Electrical Distribution Systems Primary and Secondary Electrical Distribution Systems Critical Facilities Round Table 12th Quarterly Membership Meeting June 2, 2006 David D. Roybal. P.E. Eaton Electrical Cutler-Hammer Products Utility

More information

6. The estimated costs here do not include any applicable ITCC tax

6. The estimated costs here do not include any applicable ITCC tax General Notes and Clarifications: 1. The following estimated costs are based on past experiences and are intended to provide an order of magnitude of the total project cost given the major system components.

More information

SCOPE OF WORK - SUBSTATION

SCOPE OF WORK - SUBSTATION SCOPE OF WORK - SUBSTATION VI - i TABLE OF CONTENTS 4.2 SCOPE OF WORK - SUBSTATIONS... 1 4.2.1 General... 1 4.2.2 Standard Substation... 2 4.2.3 33 kv Switchgear GIS Type... 2 4.2.3.1 Transformer Bay...

More information

DELAWARE STATE FIRE MARSHAL FIRE ALARM SYSTEM CERTIFICATE OF INSTALLATION

DELAWARE STATE FIRE MARSHAL FIRE ALARM SYSTEM CERTIFICATE OF INSTALLATION Phone System Owner Phone System Engineered by: of Record Drawings: of System Manuals: of Test Reports: System Installer 1. GENERAL INFORMATION Phone Delaware License No: Certificate Holder No. System Supplier

More information

Switchgear Capabilities. NexGear is a Division of PowerSecure NASDAQ: POWR

Switchgear Capabilities. NexGear is a Division of PowerSecure NASDAQ: POWR Switchgear Capabilities NexGear is a Division of PowerSecure NASDAQ: POWR Discussion Points Introducing PowerSecure Introducing NexGear Solutions Offered Scope of Services Examples of Work Q & A NexGear,

More information

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS

MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS MEDIUM AND HIGH VOLTAGE CAPACITORS, CAPACITOR BANKS AND SYSTEMS Meher Capacitors offers reliable and innovative products and solutions in the fields of Reactive Power Compensation, Power Quality and Energy

More information

RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER. tgood.com. Energy. Fast.

RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER. tgood.com. Energy. Fast. RENEWABLE ENERGY SUBSTATIONS SOLAR PHOTOVOLTAIC AND WIND POWER tgood.com Energy. Fast. TGOOD is a world leading manufacturer of prefabricated renewable energy substations PRODUCT CONCEPT ENVIRONMENTAL

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

ABB PSPS Erich Steinmann; Generator control-2013

ABB PSPS Erich Steinmann; Generator control-2013 ABB PSPS Erich Steinmann; Generator control-2013 GENERATOR CONTROL THE MODULAR SOLUTION FOR GENERATORS To make sure that power is efficiently converted into electric energy, it is necessary to supervise

More information

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL FORM CM-36 CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL February 7,2012 AGENDA ITEM Request for Approval to Issue a Request for Qualification (RFQ) of Firms, and Request for Proposal (RFP) to Engineer,

More information

EXPRESSION OF INTEREST

EXPRESSION OF INTEREST EXPRESSION OF INTEREST Contractor: WorleyParsons Canada Services Ltd. Project: Hebron Topsides Project Package: 2001 Switchgear and MV MCC s Category: XXXXX-XXXXX Closing Date: 31 October 2011 General

More information

ABB Power Systems. Substations References

ABB Power Systems. Substations References ABB Power Systems Substations References Jingzhou, China BA PTPS - 2 - Connection of power from the 3-Gorges-Project to Guandong province (940km away) HVDC Transmission station, Filter banks and GIS Extremely

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design Basis of Design This section applies to the design, installation and integration of metering and monitoring equipment, including: hardware installed in the electrical service and distribution equipment,

More information

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT 1.1 General 1.1.1 These Special Conditions of Contract supplement the General Instructions.

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std.

2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1. 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. 2a. IEM Indoor Metal Clad Medium Voltage Switchgear 15KV 16346-1 2a. Section 16346 INDOOR METAL CLAD MEDIUM VOLTAGE SWTICHGEAR (Std. Relays) Part 1 General 1.1 CONDITIONS AND REQUIREMENTS: A. Refer to

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

Project-related Expenditures:

Project-related Expenditures: Page 1 of 9 Capital Expenditures The table on the last two pages of this provides the details of PowerStream s capital expenditures during 2004. PowerStream has segregated its capital expenditures into

More information

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR)

WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS. No of Staff Provided by BCE. Overall Project Value (SR) WATER / WASTEWATER & POWER PROJECTS LAST 5 YEARS A. Completed December 2001 Shedgum Debottlenecking # 45943/00 47.34 Million Total 600.8 Million 154 n American Oil Co. (ARAMCO) ARAMCO Feb. 1998 to Dec.

More information

PowerPlus. Integrated Power Distribution Cabinets. Most effective space-saving. integrated system on the market. Engineered to be shipped as a

PowerPlus. Integrated Power Distribution Cabinets. Most effective space-saving. integrated system on the market. Engineered to be shipped as a PowerPlus Integrated Power Distribution Cabinets Most effective space-saving integrated system on the market. Engineered to be shipped as a completely assembled, wired system. Compatible with every electrical

More information

Ralf Christian, CEO Low and Medium Voltage. Making Things Right with Totally Integrated Power (TIP)

Ralf Christian, CEO Low and Medium Voltage. Making Things Right with Totally Integrated Power (TIP) Ralf Christian, CEO Low and Medium Voltage Making Things Right with Totally Integrated Power (TIP) siemens.com/hannovermesse Making Things Right with Totally Integrated Power (TIP) Trade LV 100 kw Industrial

More information

SUMMARY OF CAPITAL EXPENDITURES

SUMMARY OF CAPITAL EXPENDITURES Filed: 0--9 EB-0-0 Exhibit D Tab Schedule Page of SUMMARY OF CAPITAL EXPENDITURES.0 SUMMARY OF CAPITAL EXPENDITURES 8 The requested capital expenditures result from the rigorous business planning and work

More information

Fukushima Daini Nuclear Power Station: Progress Status Based on the Recovery Plan (As of the End of April 2013)

Fukushima Daini Nuclear Power Station: Progress Status Based on the Recovery Plan (As of the End of April 2013) Attachment 1 Progress milestone dates are defined as follows: : The date when an equipment is removed power station: The date when an equipment is carried into the relevant building within the premises

More information

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage

More information

Transmission Related Station Power Use at Substations

Transmission Related Station Power Use at Substations Transmission Related Station Power Use at Substations BUSINESS PRACTICE This Business Practice identifies the cost responsibility for energy consumption at substations by American Transmission Company

More information

ELECTRICIAN TRADE REGULATION

ELECTRICIAN TRADE REGULATION Province of Alberta APPRENTICESHIP AND INDUSTRY TRAINING ACT ELECTRICIAN TRADE REGULATION Alberta Regulation 274/2000 With amendments up to and including Alberta Regulation 122/2014 Office Consolidation

More information

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H.

ANCILLARY EQUIPMENT AND ELECTRICAL EQUIPMENT Power Supply Systems and Electrical Equipment for Desalination Plants - Y.M. Hamud and A.H. POWER SUPPLY SYSTEMS AND ELECTRICAL EQUIPMENT FOR DESALINATION PLANTS Y.M. Hamud and A.H. Anwar Abu Dhabi Water and Electricity Authority, Abu Dhabi, UAE Keywords : Electrical System, Network for Desalination,

More information

INSPECTION AND TESTING FORM

INSPECTION AND TESTING FORM INSPECTION AND TESTING FORM SERVICE ORGANIZATION PROPERTY NAME (USER) DATE: 08-04-15 TIME: 8:00 Name: Siemens Industries Inc. Name: Kcvtcs Madisonville Tech, School Bldg. Address: 2700 Stanley Gault Pkwy

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS LIGHTING CONTROL PANELS 4 AND 8 RELAYS INSTALLATION INSTRUCTIONS INSTALLATION OVERVIEW The installation instructions contained in this document are provided as a guide for proper and reliable installation.

More information

Customer Substation Manual 08/05/02

Customer Substation Manual 08/05/02 Customer Substation Manual Table of Contents Section Page 2 of 85 Description 0 Preface 010.00 General 010.10 Information Required for the Review of New Customer Substations 010.20 New Customer Substation

More information

Protection and Substation Automation. Training Programmes

Protection and Substation Automation. Training Programmes Protection and Substation Automation Training Programmes Protection and Substation Automation Training Programme Overview The objective of the Training Program is to provide education and training to make

More information

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525

05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 CITY OF LOS ANGELES CIVIL SERVICE COMMISSION CLASS SPECIFICATION POSTED JUNE 1999 05-15-98 ELECTRICAL ENGINEERING ASSOCIATE, 7525 Summary of Duties: Performs professional electrical engineering work in

More information

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS

PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS PRE COMMISSIONING TESTS ON EQUIPMENT AT 33/11 KV SUB STATIONS TESTS ON TRANSFORMERS 1. IR Values a) For 33/11 KV Power Transformer 2500 V megger is to be need. b) Power Transformer neutral Earthing is

More information

Up-to-Date with Electrical Equipment

Up-to-Date with Electrical Equipment Figure 1. Parts of production lines 2 & 3. Viktor Stieger, ABB Switzerland Ltd, provides details on Qassim Cement Company s electrical upgrades. Up-to-Date with Electrical Equipment Introduction Qassim

More information

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT NETWORK SYSTEMS SECTION

CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT NETWORK SYSTEMS SECTION CONSOLIDATED EDISON CO. OF NEW YORK, INC. 4 IRVING PLACE NEW YORK, NY 10003 DISTRIBUTION ENGINEERING DEPARTMENT NETWORK SYSTEMS SECTION SPECIFICATION EO-2022 REVISION 15 DECEMBER 2009 EFFECTIVE DATE DECEMBER

More information

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264 BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

Study Guide for Substation Operator

Study Guide for Substation Operator Study Guide for Substation Operator Test Number: 2866 Human Resources Talent Planning and Programs Southern California Edison An Edison International Company REV091114 Introduction The Substation Operator

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

Typical Data Requirements Data Required for Power System Evaluation

Typical Data Requirements Data Required for Power System Evaluation Summary 66 Carey Road Queensbury, NY 12804 Ph: (518) 792-4776 Fax: (518) 792-5767 www.nepsi.com sales@nepsi.com Harmonic Filter & Power Capacitor Bank Application Studies This document describes NEPSI

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

PLAN REVIEW GUIDE FOR FIRE ALARM

PLAN REVIEW GUIDE FOR FIRE ALARM PLAN REVIEW GUIDE FOR FIRE ALARM PROJECT NAME: PERMIT # PROJECT ADDRESS: CONTACT PERSON: PHONE Fire alarm system installation information shall be provided on the appropriate architectural and electrical

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

TRANSMISSION Field Services (January 30, 2014)

TRANSMISSION Field Services (January 30, 2014) TRANSMISSION Field Services (January 30, 2014) Vice President Transmission Field Services The Vice President - Transmission Region Operations is responsible for the safe, reliable, cost-effective, and

More information

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark...

..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... ..OR How To Protect your 3-Phase Equipment Investment with 3-Phase Monitors from Time Mark... TIME MARK CORPORATION 11440 EAST PINE STREET TULSA, OK 74116 USA tel 918 438-1220 fax 918 437-7584 www.time-mark.com

More information

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas ENERGY NETWORKS ASSOCIATION Electricity Industry EMF Measurement Protocol for High Field Areas Contents 1 Introduction 1.1 Background 1.2 High Field Areas 2 High Field Area - Generation Businesses 2.1

More information

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval. Polk School District Specifications for the New Fire Alarm in the Existing Building Eastside Elementary School FIRE ALARM SYSTEM 1.01 SUBMITTALS A. Shop drawings shall be submitted as follows: 1. Manufacturer's

More information

Current Transformers Ratio / Polarity / Types

Current Transformers Ratio / Polarity / Types CT1 Current Ratio / Polarity / Types Application Current (CT s) are instrument transformers that are used to supply a reduced value of current to meters, protective relays, and other instruments. CT s

More information

Exceptional... Everytime!

Exceptional... Everytime! Oil & Gas Exceptional... Everytime! Oil & Gas Industry With each Team Leader possessing 10 20 Years experience, BAR Engineering not only contributes high level engineering expertise, but also the practical

More information

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions

SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS. Presented by SAI Advanced Power Solutions SWITCHGEAR SOLUTIONS FOR MISSION CRITICAL APPLICATIONS POWER DISTRIBUTION RACKS IN A MISSION CRITICAL SYSTEM MODULES IN A MISSION CRITICAL SYSTEM UPS Convertor Main Inverter Load Battery BPC UPS & BATTERY

More information

Modular Systems wind portfolio overview Power Collection and Grid Connection products

Modular Systems wind portfolio overview Power Collection and Grid Connection products Modular Systems wind portfolio overview Power Collection and Grid Connection products Slide 1 Modular Systems wind portfolio Wind power - definition A wind turbine is a device that converts kinetic energy

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012

INTRODUCTION TO SYSTEM PROTECTION. Hands-On Relay School 2012 INTRODUCTION TO SYSTEM PROTECTION Hands-On Relay School 2012 CONGRATULATIONS On choosing the field of system protection. It is an exciting, challenging profession. System protection has changed considerably

More information

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS Terence Hazel Senior Member IEEE Schneider Electric 38050 Grenoble France Abstract The power requirements for large industrial sites is increasing.

More information

Secondary Unit Substations

Secondary Unit Substations 14 SWITCHGEAR Secondary Unit Substations Overview Siemens offers a wide variety of unit substation designs to meet customer requirements. A unit substation consists of one or more transformers mechanically

More information

Approved Meter Sockets and Cabinets

Approved Meter Sockets and Cabinets Single Unit Residential Guide 1 PHASE, 120/240 VOLT S METERING (Metering sockets and cabinets are supplied by Customer). Outdoor meter mounting height is 1730 mm ( 5 8 ) to center of meter ± 100 mm ( 4

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS

4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS 4160: THE GREEN 480 MEDIUM VOLTAGE ELECTRICAL SYSTEMS for DATA CENTERS Michael Mosman, PE Chief Technical Officer CCG Facilities Integration Incorporated FACILITIES INTEGRATION INCORPORATED MEDIUM VOLTAGE

More information

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Project name: Customer: Address, location of the system: Serial number

More information

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

APS Substation Maintenance. October 8, 2009

APS Substation Maintenance. October 8, 2009 APS Substation Maintenance October 8, 2009 Substation Criticality Ranking Criticality Ranking Tiers Equipment ranked by access, consequence, replacement cost, replacement time, redundancy, safety, and

More information

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES SECTION 26 29 23 VARIABLE FREQUENCY DRIVES PART 1 GENERAL 1.01 SCOPE A. Furnish and install individual freestanding variable frequency AC drives (VFD) as shown on the Drawings and specified herein. 1.02

More information

CLASSIFICATION SYSTEM BY FIELD AND SUB-FIELD OF EXPERTISE SUPPLIERS REGISTRY OF GOODS AND SERVICES ENAP GROUP OF COMPANIES I. Suppliers are classified in three groups: Classification Equipments, materials

More information

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective

Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective Technical Specification Of Substation Protection & Control System with IEC 61850 BHEL s Perspective India Core Events 2008 September 24 th 2008 1 Background Stability & Reliability Data Storage Communication

More information

ATS - Automatic Changeover

ATS - Automatic Changeover ATS - Automatic Changeover Manufacturers of Electrical Switchgear Choosing an Automatic Transfer System Switchgear Systems offer a variety of solutions for multiple supply switching needs. As well as our

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides

More information

FA-300 Series. LCD Fire Alarm Control Panel. User Guide. LT-954 Rev. 0.1 February 2013. FA-300 SERIES Fire Alarm Control Panel

FA-300 Series. LCD Fire Alarm Control Panel. User Guide. LT-954 Rev. 0.1 February 2013. FA-300 SERIES Fire Alarm Control Panel ABC DEF GHI JKL MNO PQR STU YZ WXY FA-300 Series LCD Fire Alarm Control Panel Advanced Life Safety Solutions System Normal 10:36AM WED 2003-10-01 SYSTEM RESET A.C. ON ALARM SUPV TRBL CPU FAIL SIGNAL SILENCE

More information

RELIABILITY PLANNING CRITERIA

RELIABILITY PLANNING CRITERIA RELIABILITY PLANNING CRITERIA Version 4.0 01/20/2016 Date Rev. No. Individual Making Edits REVISION HISTORY Reason / Comments 07/01/2013 1 J. Johnson Initial document 06/06/2014 2 R. Chapman Document review;

More information

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity

More information

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT

SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT SECTION 23 00 01 HEATING, VENTILATION AND AIR CONDITIONING EQUIPMENT PART 1 - GENERAL 1.1 DESCRIPTION A. The Work specified in this Section consists of designing, furnishing and installing factory-assembled

More information

SWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan)

SWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan) From the SelectedWorks of Radhey Shyam Meena Winter July 12, 2012 SWITCH YARD OPERATION IN THERMAL POWER PLANT(KaTPP Jhalawar Rajasthan) RADHEY SHYAM MEENA, Er. Available at: http://works.bepress.com/radhey_meena/5/

More information

PA PUC AERS & Metropolitan Edison Company Site Visit

PA PUC AERS & Metropolitan Edison Company Site Visit PA PUC AERS & Metropolitan Edison Company Site Visit October 26, 2010 Scott Lowry Director-Operation Services, Met-Ed Andrew Zulkosky Manager-Engineering, Met-Ed Curt Christenson Manager-York Customer

More information

Benchmarking Questionnaire on Facility Management Costs and Business Practices

Benchmarking Questionnaire on Facility Management Costs and Business Practices Benchmarking Questionnaire on Facility Management Costs and Business Practices April 21, 2004 Introduction KPMG has been contracted by Hydro Quebec s Facility Management Division to perform a benchmark

More information

Attachment 9. Trouble signals. Interfaced equipment. Primary (main) power supply

Attachment 9. Trouble signals. Interfaced equipment. Primary (main) power supply FIRE DETECTION, ALARM AND MASS NOTIFICATION SYSTEMS Inspection, testing, and maintenance of fire detection, alarm and Mass Notification systems shall be performed in accordance with the manufacturer's

More information

HYDROMATRIX Jebel Aulia - Sudan

HYDROMATRIX Jebel Aulia - Sudan HYDROMATRIX Jebel Aulia - Sudan www.andritz.com HYDROMATRIX - Concept Jebel Aulia - Sudan HYDROMATRIX is a new concept of hydraulic energy generation, which has been developed by an American engineer in

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

Comprehensive Electrical Distribution Master Planning at North Carolina State University. Alan Daeke Michael Dempsey

Comprehensive Electrical Distribution Master Planning at North Carolina State University. Alan Daeke Michael Dempsey Comprehensive Electrical Distribution Master Planning at North Carolina State University Alan Daeke Michael Dempsey CAMPUSENERGY2015 Agenda Campus Overview Overview of Existing System Project Goals Project

More information

Product overview brochure. ABB Medium Voltage Products Our one-stop approach for every medium voltage application

Product overview brochure. ABB Medium Voltage Products Our one-stop approach for every medium voltage application Product overview brochure ABB Medium Voltage Products Our one-stop approach for every medium voltage application Overview ABB meets every need for reliable, safe and energy-efficient medium voltage switchgear,

More information

APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE

APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE APPENDIX D PAGE 1 APPENDIX D DISTRIBUTION WIRES ONLY RATE BASE This appendix is composed of the following three parts: 1. Part I - Guidelines for determining the distribution or wires only assets and activities;

More information

Distribution Voltage Regulators

Distribution Voltage Regulators Distribution Voltage Regulators Type JFR Single Phase 2.5 to 19.9 kv Type SFR Three Phase 13.2 to 34.5 kv Power Transmission & Distribution Siemens JFR & SFR Voltage Regulators Improving Quality of Service

More information

OBOA 2009 Huntsville, ON Overview of ULC Standards Affecting Building Occupancy Alan Cavers Area Manager Fire & Security Systems Group

OBOA 2009 Huntsville, ON Overview of ULC Standards Affecting Building Occupancy Alan Cavers Area Manager Fire & Security Systems Group OBOA 2009 Huntsville, ON Overview of ULC Standards Affecting Building Occupancy Alan Cavers Area Manager Fire & Security Systems Group Course Title: Rev Date Agenda Introduction to Underwriters Laboratories

More information