A risk-management approach to a successful infrastructure project
|
|
|
- Mabel Wheeler
- 10 years ago
- Views:
Transcription
1 McKinsey Working Papers on Risk, Number 52 A risk-management approach to a successful infrastructure project Initiation, financing, and execution Frank Beckers Nicola Chiara Adam Flesch Jiri Maly Eber Silva Uwe Stegemann November 2013 Copyright 2013 McKinsey & Company
2 Contents A risk-management approach to a successful infrastructure project: Initiation, financing, and execution Project risk across the infrastructure life cycle 4 Effective risk management in infrastructure projects 6 Phase 1: Selecting, planning, and designing projects 6 Phase 2: Procurement and contractual design choices 8 Phase 3: Construction delivery 8 Phase 4: Asset operation 9 The benefits of life-cycle infrastructure-risk management: A case study 10 This working paper has been produced by collaboration between the Global Risk Practice and the Infrastructure Practice of McKinsey, with support from the McKinsey Innovation Campus. About the McKinsey Innovation Campus The McKinsey Innovation Campus (MIC) in Singapore, in partnership with the Singapore Government through the Economic Development Board (EDB), was officially launched in The first of its kind for McKinsey globally, and the first of its kind in Asia, the MIC is designed to deliver ground-breaking knowledge which helps companies in Singapore and across Asia address their toughest challenges. It will drive intellectual property creation efforts in Singapore by bringing together the best of global and local expertise for innovation at scale, piloting new cutting edge capabilities in areas such as energy efficiency, government, consumer insights, and public-sector management. McKinsey Working Papers on Risk presents McKinsey s best current thinking on risk and risk management. The papers represent a broad range of views, both sector-specific and cross-cutting, and are intended to encourage discussion internally and externally. Working papers may be republished through other internal or external channels. Please address correspondence to the managing editor, Rob McNish ([email protected]).
3 1 A risk-management approach to a successful infrastructure project: Initiation, financing, and execution The World Bank estimates that a 10 percent rise in infrastructure assets directly increases GDP by up to 1 percentage point. 1 Insufficient or underdeveloped infrastructure presents one of the biggest obstacles for economic growth and social development worldwide. In Brazil, for example, development is constrained by narrow roads, a lack of railways in the new agricultural frontiers, and bottlenecked ports, all of which are unable to meet the transport needs of a newly wealthy consumer mass. Infrastructure projects are high on governments agendas, and the infrastructure-development and investment pipeline is huge. The current global project pipeline is estimated at $9 trillion, one-third of it in Asia. India is expected to spend some $550 billion on large-scale projects over the next five years, half of which will be in the energy and utility sectors (Exhibit 1). Developed economies also have significant infrastructure plans. The United Kingdom, for example, has identified an infrastructure pipeline of over 500 projects that is worth more than 250 billion. Exhibit 1 The current global pipeline for infrastructure projects is estimated at $9 trillion. Megaproject 1 pipeline 2 $ million 3,095 Construction Energy and utilities Social and defense Transport 722 1,006 1, ,317 Asia Europe 1, Middle East 1, North America Africa Latin America Oceania % Cost >$1 billion. 2 Columns may not sum, because of rounding. However, major infrastructure projects have a history of problems. Cost overruns, delays, failed procurement, or unavailability of private financing are common (Exhibit 2). The final cost of the much-anticipated Eurotunnel between the United Kingdom and France, for example, was significantly higher than originally planned, while the Betuwe cargo railway linking the Netherlands and Germany came in at twice the original 2.3 billion budget and more than four times the original estimate. Nor are these problems confined to the past. Today, the construction of Kuala Lumpur s new airport terminal, for example, is facing huge cost overruns and significant delays following frequent design changes. 1 César Calderón, Enrique Moral-Benito, and Luis Servén, Is infrastructure capital productive? A dynamic heterogeneous approach, World Bank policy research working paper number 5682, 2009 (worldbank.org).
4 2 Exhibit 2 Large-scale projects face many challenges. Planned Actual Example Budget vs actual billion Delays and start-up problems Incorrect capacity and revenue plans Total value lost vs plan billion Eurotunnel month delay 18 months of unreliable service after opening Overestimated marketshare gain in freight and passengers by 200% ~7.5 High-speed rail Frankfurt-Cologne year delay of construction Legal and technical issues Unforeseen capped government funding ~1.5 Betuwe Line NL (cargo rail) 2.3 > year 1 delay of construction Technology choices still not finalized Annual revenue shortfall of 20 million ~3.0 Kuala Lumpur Airport Initial issues with connectivity to downtown area Complaints about facility hygiene levels Handles only ~60% of current capacity Losing market share to Singapore ~1.5 1 Project still not finalized and costs could go even higher. Source: Annual reports; Reuters; Jane's Airport Review; McKinsey analysis In our view, most overruns are foreseeable and avoidable. Many of the problems we observe are due to a lack of professional, forward-looking risk management. Direct value losses due to undermanagement of risks for today s pipeline of large-scale projects may exceed $1.5 trillion in the next five years, not to mention the loss in GDP growth, as well as reputational and societal effects. Large infrastructure projects suffer from significant undermanagement of risk in practically all stages of the value chain and throughout the life cycle of a project. In particular, poor risk assessment and risk allocation, for example, through contracts with the builders and financiers, early on in the concept and design phase lead to higher materialized risks and private-financing shortages later on. Risk is also undermanaged in the later stages of infrastructure projects, destroying a significant share of their value. Crucially, project owners often fail to see that risks generated in one stage of the project can have a significant knock-on impact throughout its later stages. The structuring and delivery of modern infrastructure projects is extremely complex. The long-term character of such projects requires a strategy that appropriately reflects the uncertainty and huge variety of risks they are exposed to over their life cycles. Infrastructure projects also involve a large number of different stakeholders entering the project life cycle at different stages with different roles, responsibilities, risk-management capabilities and risk-bearing capacities, and often conflicting interests. While the complexity of these projects requires division of roles and responsibilities among highly specialized players (such as contractors and operators), this leads to significant interface risks among the various stakeholders that materialize throughout the life cycle of the project, and these must be anticipated and managed from the outset. And because infrastructure projects have become and will continue to become significantly larger and more complex, losses due to the cost of undermanaged risks will continue to increase. This will be exacerbated by an ongoing shortage of talent and experience not only are projects more complex, but there are also more of them, which will create demand for more effective and more systematic approaches and solutions.
5 A risk-management approach to a successful infrastructure project: Initiation, financing, and execution 3 Some typical causes of failure Overestimating revenue and growth potential due to skewed incentives among project originators Sponsors and developers fail to plan delivery and stakeholder and project management in a sufficiently professional way Engineering and construction companies pay insufficient attention to mitigating and controlling risk during the design phase Financiers lack confidence in the ability of sponsors and other stakeholders to manage risks professionally and are not able to monitor developments and emerging risks themselves Surprisingly, the risks of large infrastructure projects often do not get properly allocated to the parties that are the best risk owners those that have a superior capability to absorb these risks. This can result from a misunderstanding or disregard on the part of governments of the risk appetite, for instance, of private investors who are sensitive to the kinds of risks they accept and under what terms. Providers of finance will often be the immediate losers from poorly allocated or undermanaged risks. Even in public-private-partnership (PPP) structures, private-risk takers and their management techniques are introduced too late to the process to influence risk management and allocation, and therefore they cannot undo the mistakes already embedded in the projects. One crucial consequence is an increase in the cost of financing PPP projects and a greater need for sovereign guarantees or multilateral-agency support. In the end, however, society at large bears the costs of failures or overruns, not least in the form of missed or slowed growth. Private sources of investment are becoming increasingly scarce. Banks have weak balance sheets and are under severe regulatory pressure to avoid or limit long-term structured finance. Many are either reducing or exiting their infrastructure-financing businesses. Other potential natural owners, such as pension funds and insurance companies, either have regulatory constraints or are still in the early stages of considering direct investments and building up the necessary expertise. This helps to explain why the dominant financing solution to deliver infrastructure projects is through budget-financed public-procurement processes. It is striking to see that in the absence of private-sector management techniques and private-sector risk takers public-infrastructure sponsors seldom apply stateof-the-art risk- and project-management tools and techniques, despite the knock-on consequences of being seen to lose public money during a time of increasingly constrained public budgets. In effect, a larger volume of riskier infrastructure projects, managed by public servants who lack of risk- and project-management skills and resources, seeks funding from a market with lower financial supply and a significantly lower risk appetite among providers of both public and private financing. This is not to argue that the public sector lacks any risk-management capabilities. In fact, many public-sector processes are very sophisticated, but they are geared toward ensuring transparency itself and avoiding the reality or appearance of misconduct and do so at the expense of effectiveness, efficiency of the process itself, and operational and execution risk-management objectives. As a result, the seeds of many project failures are sown in the early stages of development, when a poorly designed project-delivery approach or ill-considered procurement decision can lead to delays, higher costs, and ultimately diminished returns.
6 4 A more comprehensive approach to risk management would address the key issues facing all parties and stakeholders involved in a project throughout its life cycle, including project originators and sponsors, that is, governments and public entities, tackling both perceived risk, and financing gaps. In the remainder of this paper, we set out how good practices in project structuring and risk management can radically improve outcomes in big infrastructure projects. We explain what a comprehensive through the life cycle risk-management approach requires. 2 We also outline the benefits of, and processes involved in, effectively implementing a risk-management capability. Good risk-informed project management requires the following: a comprehensive conceptual framework that introduces risk management across the value chain and highlights the most critical issues and design choices to be made a strong set of practical approaches and tools that help governments and companies make these design choices and manage risks more proactively and thus more effectively an implementation framework that effectively introduces and ensures the application and execution of discipline in day-to-day business, starting in the beginning of the design phase all the way through the life cycle of a project Project risk across the infrastructure life cycle Proper front-end project planning is all about shaping the project s risk profile so it can be managed during execution, and execution is all about aggressively mitigating the risks that emerge. The key is to know what risks are inherent to a project and what degree of freedom you have to shape the risk profile before you commit the bulk of your funds; you must also have skills in place to prevent the remaining risks from getting out of control. Then you can discuss what skills and processes are needed during front-end planning versus execution. In practice, they are quite different. There is an inherent conflict between the aspiration to limit the number and volatility of potential future (interface) risks and the need to maintain flexibility to respond to unforeseen changes over the life cycle of a project. The fact that risks can materialize in later stages, but have actually been caused in earlier stages under different responsibilities, requires an end-to-end risk-management view, as opposed to a siloed, individualized process-step responsibility. There is a clear need for strong risk-management processes from the outset and for these to be applied and continuously developed throughout the life of the project. A state-of-the-art risk-management approach for infrastructure projects needs to reflect the peculiarities of the business. A good starting point is to undertake a forward-looking, life-cycle-oriented risk assessment and to generate insights into the root causes of identified and potential risks at the beginning of the project in the project-origination and design phase. A true understanding of stakeholders capabilities and willingness to take on and actively manage certain risks the risk-ownership structure and the respective allocation and pricing of these risks would be a logical next step. In addition, strategy and risk-related processes need to be strengthened, and the governance and organization as well as the risk cultures of all stakeholders need to be enhanced. The involvement of risk-taking private-financing perspectives early on, for example, as applied in a PPP, can ensure a more professional and disciplined approach to strategy, risk and project management, and deal structuring. To improve the successful provision of infrastructure projects, whether through PPPs or public procurement, all stakeholders across the value chain of an infrastructure project need to be subjected to rigorous private-sector 2 In a separate working paper, we will address the portfolio effects that need to be taken into account specifically by project sponsors and builders.
7 A risk-management approach to a successful infrastructure project: Initiation, financing, and execution 5 risk-management, risk-allocation, and financing due diligence. They should also be required to contribute to the effective implementation of risk-management and mitigation capabilities across the life cycle of the project. Assessing risks across a project s life cycle can be a powerful way of making it more resilient and ultimately more profitable for all of the participants across the value chain. This approach shares many elements with enterprise-risk-management (ERM) processes that are common in other sectors. Exhibit 3 provides an example of a generalized ERM framework. Several concepts derived from ERM are applicable for infrastructure: Forward-looking, through-the-life-cycle risk assessment: management focus on a proactive, forwardlooking business-oriented performance dialogue on risk and return Risk ownership and strategy: a conscious optimization effort to protect and create value by allocating risks to the best risk owners across the life cycle, including an explicit reflection of the respective risk appetite of these risk owners, for example, private financiers Risk-adjusted processes: risk management as an institutionalized capability, integrated into important processes such as business-case planning, as well as through explicit risk processes like monitoring, control, and mitigation, with all stakeholder parties involved across the life cycle of the project Risk governance: risk management as a priority on top management s agenda, reflected in responsibilities and organizational design, for example, through an independent view on risk An explicit and effective risk-return culture within the control functions, but especially with project managers and in the project-execution force Exhibit 3 There are concrete steps to establishing an integrated enterprise-risk-management approach. Risk culture: ensure soundness of risk culture across entire organization (perform culture diagnostic) Risk norms: new risk norms need to be embedded through various corporate processes and governance Risk skill building: implement a skill-enhancement program for key roles Risk culture and performance transformation Risk taxonomy: establish common vocabulary for different risks Risk register/risk heat map: characterize and prioritize risk based on probability, impact, and preparedness Risk insight and foresight: use business-specific scenarios, stress tests, and early indicators to understand risks and opportunities (potentially also for key customers and peers) Risk models: build simple model as support tool for business decisions Risk reporting: focus on key risks and provide 5 Insight and risk transparency clarity on these to allow actionable measures Risk archetypes: define ERM mandate of the risk function Risk organization: design risk organization across entire organization and ensure appropriation of top management Risk-function profile: establish clear allocation of responsibilities between risk taking and controlling units 4 Risk organization and governance 3 Integrated enterprise-risk management (ERM) Risk-related decisions and processes 2 1 Natural ownership, risk appetite, and strategy Risk ownership: decide which risks you own and which you don t Risk capacity: understand how much risk you can take Risk appetite: decide with how much risk taking you feel comfortable with Risk strategy: decide on actions to transform your risk profile, including trade-offs with corresponding cost Risk-related decisions: embed risk in business decision making rather than pure compliance-oriented paper pushing Risk optimization: embed in each major strategic decision before launch/positive decision Risk processes: design and execute core business processes and operations on a risk-informed basis
8 6 Importantly, ERM is not a purely administrative checking the box exercise that aims only to create regulatory or board compliance. ERM is meant to connect the boardroom, where important risk-relevant decisions are made, to the engine room of risk managers, where a lot of relevant information and insight needs to get produced. Effective risk management in infrastructure projects Typically, as noted earlier, many projects fail because of choices made in the early stages of development. A poorly designed project-delivery approach or the wrong decisions about procurement can also lead to delays, higher costs, and diminished returns. Project risk management has to be a core element of project selection, planning, and design, and it has to be continuous across the entire life cycle of the project. For each stage of a project, there are some common questions: Forward-looking risk assessment: which risks is the project facing? What is the potential cost of each of these risks? What are the potential consequences for the project s later stages as a result of design choices made now? Risk ownership: which stakeholders are involved and which risks should the different stakeholders own? What risk-management issues do each of the stakeholders face, and what contribution to risk mitigation can each of them make? Risk-adjusted processes: what are the root causes of potential consequences, and through which risk adjustments or new risk processes might they be mitigated by applying life-cycle risk-management principles? Risk governance: how can individual accountability and responsibility for risk assessment and management be established and strengthened across all lines of defense? Risk culture: what are the specific desired mind-sets and behaviors of all stakeholders across the life cycle and how can these be ensured? Phase 1: Selecting, planning, and designing projects Governments initiate the vast majority of infrastructure projects. This creates natural tension because delivery times for projects typically run beyond the election cycle, meaning that any future payoff might accrue to political opponents. In addition, governments are often reluctant to spend money at the outset, preferring to appear thrifty even if there will be far higher costs later on. Often efforts are hampered by the lack of an overarching infrastructure strategy, but many other factors can lead to individual projects being plagued with problems. These include incorrect forecasts and assumptions (for example, on demographics, demand, prices, revenues, capital expenditure, or operating expenditure), a limited understanding of market dynamics, and lack of willingness to plan for volatility and adverse scenarios. Overestimating revenue and growth potential while underestimating risk results in badly designed projects that deliver lower-than-expected returns or, in the worst case, a project that must be canceled or abandoned after significant up-front investment. The Oedo subway line in Tokyo, for example, earned revenues much more slowly than anticipated due to massive delays in delivery and overly optimistic forecasts. Other challenges include poor planning and management of future interface risks, caused by early-stage decisions regarding project structures and design. For example, the highly praised HSL-Zuid high-speed rail-line PPP in Netherlands ( which was named PPP Deal of the Year in 2001) later incurred a 43 percent cost overrun as the original particularly appetizing risk profile of the deal included the breakup of the project into three separate subprojects, causing significant interface risks that were only identified,
9 A risk-management approach to a successful infrastructure project: Initiation, financing, and execution 7 and were then poorly managed, after the deal was closed. 3 Crucially, the risk appetite of developers, contractors, and private investors, who are essential in later stages of the project life cycle, is often not taken into account. A life-cycle risk-management approach involves making decisions using a risk-based perspective. Specifically in the earliest design and planning phases of a project, this may require a conscious effort to identify, assess, and, ideally, quantify the risks the project will be exposed to across its life cycle. This includes reflection on potential adverse circumstances and scenarios (for example, stress testing). In large subway constructions, for instance, the risks of geological obstacles, environmental challenges, and future customer numbers and behaviors can and should be explicitly taken into account as drivers of volatility of project construction and future cash flows. A life-cycle approach demands the alignment of people and management toward a more risk-conscious set of processes. Each individual project should use a stage-gate approach to ensure that projects do not progress without key deliverables being completed. Using predefined risk-register templates enables this to progress smoothly. Private financial discipline should be used in planning, designing, and structuring projects even before private investors are involved, helping to adjust incentives and penalties so that they are matched appropriately and applied to each relevant party. The primary objective is to create a transparent and flawless decision-making process to select the investment that best achieves assigned targets under the global mandate of the sponsor. This is a major challenge. Too often projects are gold plated or overdesigned for the commercial opportunity, resulting in too much complexity and a lack of economic viability. Sponsors need to adopt a realistic commercial approach from the outset, making sure the project can meet its defined needs and is designed so that it also meets its target costs. Potential future interface risks would be identified early on in the process, and the required resources and skill set to manage those risks would be factored into any decision taken with respect to alternative project structures. It should be clear from the outset how any new project fits in to a wider strategy. For example, a project for a new airport should form part of an overall national strategy for transport. State-of-the-art forecasting techniques should be applied, helping to avoid common problems such as overdesign, mismatched capacity and demand, or misjudgment of interdependencies with other projects. The project can be evaluated using adverse scenarios, stress tested, and set up with the appropriate monitoring and reporting processes. An economic model that integrates time risk, cost risk, and uncertainties can be deployed to produce a clear business case and range of expected financial returns. In this regard, it is crucial to consider potential private-sector requirements early on (both technical and financial). During front-end planning, there are several key risk levers to pull: 1. conceptual design (what you ll ask the contractors to design and build) 2. the procurement model (how you select contractors) 3. contracting model (under what terms the contractors work) 4. the project-management model (how you will manage the contractors to deliver the project) 3 See also Ernst & Young, High Speed 2: International Case Studies on Delivery and Financing A Report for HS2, December 18, 2009.
10 8 All of the business-case evaluation falls under conceptual design, but success in the end is all about the interface between the owner and the contractor. Projects can go wrong for lots of other reasons (for example, a road is being built over contested ground or a natural disaster occurs), but most are addressed through force majeure. Escalation in the cost of labor or materials is something that good planning should account for and falls under the procurement and contracting models. Phase 2: Procurement and contractual design choices Public procurers, such as governments and their respective ministries, as well as public-private collaborations such as PPP units, developers, and contractors are the main stakeholders for this stage of an infrastructure project. They often fail to select the optimal risk-return ownership structure ahead of the procurement stage, making it difficult to adjust or reassign risk or responsibility once the project has commenced. The risk appetite of private players is frequently neglected or poorly understood and there is limited transparency of risk cost, risk ownership, and risk-return trade-offs. Procurers frequently select the wrong strategy, disregarding or misjudging the ability of private-sector players to control certain risks. It is extremely complex and costly to reverse a tender process once launched, as the United Kingdom found to its cost over the tender of a contract to run one of its main train routes in A failure to allocate risk to the right parties and to anticipate potential problems such as sourcing bottlenecks causes cost overrun and significant time delays. For example, the London Jubilee line extension incurred a 42 percent cost overrun in part through a failure to anticipate future risks. Again, a life-cycle risk-management approach can help to mitigate these significant risks. There should be an early focus on optimal risk-ownership allocation, including a clear knowledge of alternatives, and early application of risk management before any procurement decision is taken. Funding and financing sources should be aligned early on so that future means of funding support, such as tolls, taxes, or fares, are matched with the proposed financing, such as bank loans, bond proceeds, or equity investments. The risk profile of the funding source needs to be appropriate for the proposed finance. Stakeholders are advised to identify risks and value drivers, such as delays or increases in material prices, from the outset and decide who will be responsible for each of these. This provides a mechanism to drive contractor behavior and ensure ongoing accountability. It is vital to ensure that required expertise in planning, structuring, and so on is brought in early on, and that due diligence is conducted on contractors before selection. The project owner s ability to manage the contract must be assessed and strengthened if necessary. The life-cycle risk-management approach and early focus on optimal risk-ownership allocation are as important for budget-financed public-procurement projects as they are for PPPs involving private investors. Because governments take financial risks in public-procurement structures, they should structure their investment and manage their risks as private investors do. This could clarify their knowledge and application of available alternative risk-allocation models (for example, outsourcing of operations and maintenance activities), but could also result in a changed approach to how public funds are allocated within the government. For example, the ministry of finance or another relevant ministry could consider acting as a lender and charging a risk premium for public funds to discipline those using the funds, such as other ministries or public authorities. Phase 3: Construction delivery Asset owners and financiers are the stakeholders in the construction delivery phase insofar as this relates to engineering and construction (E&C) contractor monitoring. E&C contractors are responsible for on-time, on-budget, and on-quality delivery and financing.
11 A risk-management approach to a successful infrastructure project: Initiation, financing, and execution 9 Problems often arise because E&C contractors either fail to meet their contracts, resulting in cost overruns, delays, and defects, or are only able to perform their contractual obligations at the cost of significantly reduced profitability of their business. Poor original planning and performance management of resources and cost is one of the key drivers of this failure, and this is compounded in many cases by a failure to identify potential issues early in the process. Moreover, there is often a focus on the management of individual contracts, which means that the portfolio effects of multiple contracts at the enterprise level are overlooked. Further, there is often a disconnect between contractual obligations and transparency about a contractor s ability to deliver. Management of the relationships between clients, suppliers, and subcontractors can be haphazard, and often this comes back to poor contractor selection and management in the early phases. A consequence can be cost and budget overruns, and these can have a significant impact on a broader economy. Delays to the opening of Hong Kong airport, for example, resulted in a loss of more than $600 million to the economy. A life-cycle approach can alleviate many of these issues. Owners need to design appropriate metrics and processes to measure contractor performance. This should be translated into a proper documentation and log system for tracking progress that allows the owner to get the information they need to manage the contractor effectively. This could include a detailed monthly schedule, with measureable key performance indicators (KPIs) linked to the contract. Financial risk should be managed and an incentive system established through milestone payments and daily contractor-compliance monitoring. Professional standards of information storage and flow should be ensured through clear rules on how information should be handled and the interaction required and expected between owner and supplier. Any slippage from contractual obligations can be planned for within an overall portfolio of obligations and contracts. Often it is helpful to designate a dedicated project risk manager and team with overarching risk responsibility. For each package or area of a project, clear risk owners need to be identified, and daily site meetings should be held to assess progress against targets, slippage, and potential problems. In summary, during project execution, the key risks for the sponsor or developer are related to contractual default, claims, keeping public political stakeholders aligned, and monitoring for any mismanagement by the contractor. The interface with the contractor is therefore the critical element. However, this phase is all about mitigating risks, and the ability to influence the magnitude of these risks is smaller than during planning. Phase 4: Asset operation Finally, operation is the least complicated phase because you have a steady-state system where good operational practices can address many of the issues. In this phase of a project, asset owners and financiers are the stakeholders insofar as this relates to operation and maintenance (O&M) contractor monitoring, while O&M contractors are responsible for ensuring on-time, on-budget, and on-quality service delivery and financing. In reality, they often fail to meet contractually agreed-upon KPIs for service quality or availability, resulting in delays and increased costs. This can be because incorrect design specifications do not meet contractors requirements or because of poor forecasting around service load, maintenance cycles, or operating expenses. An inability to adjust to a changed commercial environment through changes in contract terms can also be a factor. As a first step, project owners can reduce and better manage these risks by outsourcing O&M monitoring to avoid in-house restructuring and to allow for the replacement of poorly performing contractors. A design or construction interface with the O&M contractor should be planned and managed early on and the long-term implications of today s design choices evaluated. State-of-the-art forecasting techniques should be applied and KPIs planned under adverse scenarios, including stress testing. Ongoing monitoring and reporting should be established, and the project should allow for operational flexibility by focusing on KPIs rather than operational structure.
12 10 The benefits of life-cycle infrastructure-risk management: A case study In 2011, a major transportation-asset operator and developer embraced a life-cycle approach to managing its large project pipeline (Exhibit 4). Top management committed to reduce its risk-related provisions by one-third; better risk management was identified as a core driver of profit and loss, value creation, and competitiveness. At the outset, there was a lack of a single risk definition or risk taxonomy across projects, project stages, and departments. In addition, there was no systematic formulation of how risk management added value to the company, for example, in deriving risk-management objectives from a corporate value framework, or demonstrating how risk management could lead to better decisions. The organization s focus was on the mitigation of project-schedule and cost overruns, but not on risk optimization. This meant there were disconnects throughout the project stages; design requirements were often not understood in the construction phase, for instance, leading to expensive changes in specifications and orders. There was no streamlined risk-governance model headed by an overarching risk committee or divisional risk committees, and some ambiguity surrounded risk ownership with regard to who was responsible for risk at the project or portfolio level and in migrating risk ownership across project stages. Further, the organization s existing risk-management tools were not implemented effectively. There were strongly siloed views of risks and risk-management activities across departments and a lack of riskmanagement standards across projects, meaning project managers could shape project risk management to their own preferences. This was compounded by a lack of effective compliance or management of consequences when things went wrong. Reactions to changed circumstances tended to be slow, as if risk was only really considered at the beginning of a specific project. There was little discussion of root causes and risk events and no clarity on how continuous risk management could add value and enhance motivation. Exhibit 4 A number of uncertainties and complexities exist along the project life cycle. 1 Asset-class integration Railways are built but the residential buildings are delayed, leading to lower patronage Risk assessment Issues around identifying or anticipating new risks and building on past bad experience (skills, capacity, process) Risk register hasn t been validated with contractors Economic and risk modeling Overconfident projections around demand/revenue side Stakeholder management Limited attention for assessing risks around stakeholders No institutionalized processes to manage stakeholders Planning and portfolio strategy Determine single-project economics Determine finance structure, debt ratio, ownership Manage construction, budget, timeline, quality Optimize net present value and performance for asset Manage assets in portfolio Contractor selection Underresourced contractors being selected (underbidding) Previously underperforming contractors being selected Commercial terms with contractors Lack of contractor incentives to drive efficiency gains Lack of contractor accountability for delay recovery Low contractor mind-set of "pain/gain sharing" Supplier management Flaws in communication/interaction with designers, suppliers 8 9 Risk-monitoring and mitigation processes Flaws in risk monitoring (eg, risk register not updated during delivery) and quality inspections Unclear escalation and decision-making model No proper risk-mitigation process, tools, or decision making in place Inadequate transparency on incurred costs Change/delay management Improper contractor incentives to assume ownership for delay recovery Slow solution-finding processes in case of delay Lack of flexibility/willingness to adjust contract terms/incentives if external conditions change to increase productivity
13 A risk-management approach to a successful infrastructure project: Initiation, financing, and execution 11 Improvements to the existing approach were viewed as something that would require extra effort and time and bring the risk of failure. Senior management decided to embrace a systematic step change to enhance institutional risk-management capabilities, from daily employee practices and behaviors to mind-sets and corporate culture. An integrated life-cycle approach was put in place to address many of the problems outlined above. Management needed to formulate a clear business case for the value of risk-management activities and to devise a risk strategy that was tightly linked to the business. The appropriate transparency on risk cost and the key drivers and sources of risk then had to be established, along with a much clearer understanding of what risk-management levers and instruments were available. Having established this at the top of the organization, it was then vital that effective risk-management governance, organization, and processes were put in place and that a strong risk culture and awareness was driven throughout the organization (Exhibit 5). Reliable and transparent communication is vital to the success of any project, so it was crucial that an improved system of communication was put in place between top departmental teams involved in any infrastructure project. This enabled cross-divisional cooperation and ensured alignment of goals and processes. Proper interaction with, and performance tracking of, contractors was established to help monitor and evaluate risk on a timely basis, and there were clear directions from the top of the organization to operating levels that cascaded risk-management awareness downward. This approach also required on-site shop floor risk transparency to be further advanced, as well as a move from ad hoc reactive risk mitigation to proactive risk anticipation. Exhibit 6 shows how far reaching this effort was across the organization; it involved people processes, management practices, governance, approval processes, and day-to-day behavioral norms at every level. Exhibit 5 Day-to-day risk management can be improved in several areas. Issues Lack of communication between top teams of civil and engineering/maintenance Essence of best-practice approach Major risks and solutions regularly discussed in a structured way, involving relevant areas Key decisions always incorporate risk insights along the project life cycle Continuous and focused risk transparency Possible tools Risk-input template for key decisions Top-management risk dashboard Regular senior-management discussions on risk Insufficient interaction between client s and contractor s top teams Failure to cascade riskmanagement awareness from top levels to lower levels Lack of on-site transparency Ad hoc risk management instead of proactive risk anticipation Early transparency about risk ownership and consequence management Regular interaction on operational and top level to align on status and anticipation of risks Risk-mitigation actions are clearly articulated and compliance mechanism in place Organization has a risk-conscious culture enforced by consequence management Clear change-order management in place to allow fast resolution time Risk-anticipation and mitigation actions are emphasized on the ground via simple, practical tools that are used daily Bottom-up escalation routes are clear, trigger points are predefined Risk discussion/reporting less focused on status checking, rather used as navigation tool for upcoming risk-event anticipation Raising the alarm is preferred to blaming the bad news courier Report on allocation of risks Contract with risk-transfer chapter Regular risk dialogue with contractor Risk dashboard for site manager Internal process enforcing mitigation Change-order routes defined Dedicated project risk team and local risk champions Daily check-in/out meetings On-site visual management Daily contractor-compliance monitoring On-site change-request handling War room/control tower with regular look ahead sessions Checklists for on-site risk anticipation Trigger-event checklist for escalation
14 12 Exhibit 6 Specific initiatives can improve risk culture. People processes Management practices Governance Approval processes Norms Findings following risk-culture diagnosis Several gaps in risk training Risk criteria insufficiently taken into account in promotion and compensation Lack of systematic consideration of how business strategy affects risk position (eg, no clear view on consolidated country exposure given business-expansion plans) Each division has different practices on risk management; some are more formal, others less so Multiple systems for management approvals with partial overlaps and with lack of consistent audit trail Hero in the organization seen as the person that can sail close to the wind and get projects through Initiatives Introduction of risk orientation for lateral hires Introduction of risk training for upper tenure as prerequisite for promotion Letter to newly appointed managing directors, making clear that leadership review committee considered individual risk behavior New function on corporate level set up to monitor high-level risk topics across the corporation Design of a more harmonized set of divisionally led risk committees to strengthen direct risk mitigation and informal risk dialogue Multiple adjustments of management approval for more consistency Symbolic actions put in place to increase the impact of risk-culture initiatives and emphasize new approach to risk across the organization Make risk norms highly visible to reinforce desired risk behaviors via posters, screen savers, intranet pages, brochures The infrastructure sector significantly undermanages risks and lacks professional risk management. While undermanagement of risk happens across the whole value chain, poor risk management during early conceptual planning and design phases, mostly under the responsibility of public project sponsors, has a particularly negative impact on governments and private developers ability to achieve the hoped-for improvement of infrastructure services. Even if the involvement of private-sector risk takers, for example, investors and lenders in PPP projects, means that certain risk-management capabilities are applied later on in the process, they are not able to undo earlystage mistakes. Poorly designed and planned projects lead to significantly higher financing costs and too often even to the inability to mobilize private-sector financing and risk allocation completely. In the absence of private financing and risk sharing, budget-financed public-procurement structures continue to undermanage risk throughout the entire life cycle of the project, leading to even higher rates of project failure and poor results. Professional risk management can not only significantly improve results in public procurement processes; it can also attract and mobilize additional private financing. Given the scale and scope of emerging infrastructure projects, there is a strong case for embracing risk management throughout the life cycle of individual projects and also at the portfolio level.
15 Frank Beckers is a senior adviser in McKinsey s Dubai office, Nicola Chiara is a consultant in the Abu Dhabi office, Adam Flesch is an associate principal in the Budapest office, Jiri Maly is a principal in the Toronto office, Eber Silva is an associate principal in the São Paulo office, and Uwe Stegemann is a director in the Cologne office. Contact for distribution: Francine Martin Phone: +1 (514) [email protected]
16 McKinsey Working Papers on Risk 1. The risk revolution Kevin Buehler, Andrew Freeman, and Ron Hulme 2. Making risk management a value-added function in the boardroom André Brodeur and Gunnar Pritsch 3. Incorporating risk and flexibility in manufacturing footprint decisions Eric Lamarre, Martin Pergler, and Gregory Vainberg 4. Liquidity: Managing an undervalued resource in banking after the crisis of Alberto Alvarez, Claudio Fabiani, Andrew Freeman, Matthias Hauser, Thomas Poppensieker, and Anthony Santomero 5. Turning risk management into a true competitive advantage: Lessons from the recent crisis Andrew Freeman, Gunnar Pritsch, and Uwe Stegemann 6. Probabilistic modeling as an exploratory decision-making tool Andrew Freeman and Martin Pergler 7. Option games: Filling the hole in the valuation toolkit for strategic investment Nelson Ferreira, Jayanti Kar, and Lenos Trigeorgis 8. Shaping strategy in a highly uncertain macroeconomic environment Natalie Davis, Stephan Görner, and Ezra Greenberg 9. Upgrading your risk assessment for uncertain times Eric Lamarre and Martin Pergler 10. Responding to the variable annuity crisis Dinesh Chopra, Onur Erzan, Guillaume de Gantes, Leo Grepin, and Chad Slawner 11. Best practices for estimating credit economic capital Tobias Baer, Venkata Krishna Kishore, and Akbar N. Sheriff EDITORIAL BOARD Rob McNish Managing Editor Director Washington, DC [email protected] Martin Pergler Senior Expert Montréal Anthony Santomero External Adviser New York Hans-Helmut Kotz External Adviser Frankfurt Andrew Freeman External Adviser London 12. Bad banks: Finding the right exit from the financial crisis Gabriel Brennan, Martin Fest, Matthias Heuser, Luca Martini, Thomas Poppensieker, Sebastian Schneider, Uwe Stegemann, and Eckart Windhagen 13. Developing a postcrisis funding strategy for banks Arno Gerken, Matthias Heuser, and Thomas Kuhnt 14. The National Credit Bureau: A key enabler of financial infrastructure and lending in developing economies Tobias Baer, Massimo Carassinu, Andrea Del Miglio, Claudio Fabiani, and Edoardo Ginevra 15. Capital ratios and financial distress: Lessons from the crisis Kevin Buehler, Christopher Mazingo, and Hamid Samandari 16. Taking control of organizational risk culture Eric Lamarre, Cindy Levy, and James Twining 17. After black swans and red ink: How institutional investors can rethink risk management Leo Grepin, Jonathan Tétrault, and Greg Vainberg 18. A board perspective on enterprise risk management André Brodeur, Kevin Buehler, Michael Patsalos-Fox, and Martin Pergler 19. Variable annuities in Europe after the crisis: Blockbuster or niche product? Lukas Junker and Sirus Ramezani 20. Getting to grips with counterparty risk Nils Beier, Holger Harreis, Thomas Poppensieker, Dirk Sojka, and Mario Thaten 21. Credit underwriting after the crisis Daniel Becker, Holger Harreis, Stefano E. Manzonetto, Marco Piccitto, and Michal Skalsky
17 McKinsey Working Papers on Risk 22. Top-down ERM: A pragmatic approach to manage risk from the C-suite André Brodeur and Martin Pergler 23. Getting risk ownership right Arno Gerken, Nils Hoffmann, Andreas Kremer, Uwe Stegemann, and Gabriele Vigo 24. The use of economic capital in performance management for banks: A perspective Tobias Baer, Amit Mehta, and Hamid Samandari 25. Assessing and addressing the implications of new financial regulations for the US banking industry Del Anderson, Kevin Buehler, Rob Ceske, Benjamin Ellis, Hamid Samandari, and Greg Wilson 26. Basel III and European banking: Its impact, how banks might respond, and the challenges of implementation Philipp Härle, Erik Lüders, Theo Pepanides, Sonja Pfetsch, Thomas Poppensieker, and Uwe Stegemann 27. Mastering ICAAP: Achieving excellence in the new world of scarce capital Sonja Pfetsch, Thomas Poppensieker, Sebastian Schneider, and Diana Serova 28. Strengthening risk management in the US public sector Stephan Braig, Biniam Gebre, and Andrew Sellgren 29. Day of reckoning? New regulation and its impact on capital markets businesses Markus Böhme, Daniele Chiarella, Philipp Härle, Max Neukirchen, Thomas Poppensieker, and Anke Raufuss 30. New credit-risk models for the unbanked Tobias Baer, Tony Goland, and Robert Schiff 31. Good riddance: Excellence in managing wind-down portfolios Sameer Aggarwal, Keiichi Aritomo, Gabriel Brenna, Joyce Clark, Frank Guse, and Philipp Härle 32. Managing market risk: Today and tomorrow Amit Mehta, Max Neukirchen, Sonja Pfetsch, and Thomas Poppensieker 33. Compliance and Control 2.0: Unlocking potential through compliance and quality-control activities Stephane Alberth, Bernhard Babel, Daniel Becker, Georg Kaltenbrunner, Thomas Poppensieker, Sebastian Schneider, and Uwe Stegemann 34. Driving value from postcrisis operational risk management : A new model for financial institutions Benjamin Ellis, Ida Kristensen, Alexis Krivkovich, and Himanshu P. Singh 35. So many stress tests, so little insight: How to connect the engine room to the boardroom Miklos Dietz, Cindy Levy, Ernestos Panayiotou, Theodore Pepanides, Aleksander Petrov, Konrad Richter, and Uwe Stegemann 36. Day of reckoning for European retail banking Dina Chumakova, Miklos Dietz, Tamas Giorgadse, Daniela Gius, Philipp Härle, and Erik Lüders 37. First-mover matters: Building credit monitoring for competitive advantage Bernhard Babel, Georg Kaltenbrunner, Silja Kinnebrock, Luca Pancaldi, Konrad Richter, and Sebastian Schneider 38. Capital management: Banking s new imperative Bernhard Babel, Daniela Gius, Alexander Gräwert, Erik Lüders, Alfonso Natale, Björn Nilsson, and Sebastian Schneider 39. Commodity trading at a strategic crossroad Jan Ascher, Paul Laszlo, and Guillaume Quiviger 40. Enterprise risk management: What s different in the corporate world and why Martin Pergler 41. Between deluge and drought: The divided future of European bank-funding markets Arno Gerken, Frank Guse, Matthias Heuser, Davide Monguzzi, Olivier Plantefeve, and Thomas Poppensieker 42. Risk-based resource allocation: Focusing regulatory and enforcement efforts where they are needed the most Diana Farrell, Biniam Gebre, Claudia Hudspeth, and Andrew Sellgren 43. Getting to ERM: A road map for banks and other financial institutions Rob McNish, Andreas Schlosser, Francesco Selandari, Uwe Stegemann, and Joyce Vorholt 44. Concrete steps for CFOs to improve strategic risk management Wilson Liu and Martin Pergler 45. Between deluge and drought: Liquidity and funding for Asian banks Alberto Alvarez, Nidhi Bhardwaj, Frank Guse, Andreas Kremer, Alok Kshirsagar, Erik Lüders, Uwe Stegemann, and Naveen Tahilyani 46. Managing third-party risk in a changing regulatory environment Dmitry Krivin, Hamid Samandari, John Walsh, and Emily Yueh 47. Next-generation energy trading: An opportunity to optimize Sven Heiligtag, Thomas Poppensieker, and Jens Wimschulte 48. Between deluge and drought: The future of US bank liquidity and funding Kevin Buehler, Peter Noteboom, and Dan Williams 49. The hypotenuse and corporate risk modeling Martin Pergler 50. Strategic choices for midstream gas companies: Embracing Gas Risk Cosimo Corsini, Sven Heiligtag, and Dieuwert Inia 51. Strategic commodity and cash-flow-at-risk modeling for corporates Martin Pergler and Anders Rasmussen 52. A risk-management approach to a successful infrastructure project: Initiation, financing, and execution Frank Beckers, Nicola Chiara, Adam Flesch, Jiri Maly, Eber Silva, and Uwe Stegemann
18 McKinsey Working Papers on Risk November 2013 Designed by Global Editorial Services Copyright McKinsey & Company
Concrete steps for CFOs to improve strategic risk management
McKinsey Working Papers on Risk, Number 44 Concrete steps for CFOs to improve strategic risk management Wilson Liu Martin Pergler April 2013 Copyright 2013 McKinsey & Company Contents Concrete steps for
Introducing a holistic approach to stress testing
McKinsey Working Papers on Risk, Number 55 Introducing a holistic approach to stress testing Christopher Mazingo Theodore Pepanides Aleksander Petrov Gerhard Schröck June 2014 Copyright 2014 McKinsey &
First-mover matters. McKinsey Working Papers on Risk, Number 37. Building credit monitoring for competitive advantage
McKinsey Working Papers on Risk, Number 37 First-mover matters Building credit monitoring for competitive advantage Bernhard Babel Georg Kaltenbrunner Silja Kinnebrock Luca Pancaldi Konrad Richter Sebastian
Top-down ERM: A Pragmatic Approach to Managing Risk from the C-Suite
McKinsey Working Papers on Risk, Number 22 Top-down ERM: A Pragmatic Approach to Managing Risk from the C-Suite André Brodeur and Martin Pergler August 2010 Copyright 2010 McKinsey & Company This report
Commodity trading at a strategic crossroad
McKinsey Working Papers on Risk, Number 39 Commodity trading at a strategic crossroad Jan Ascher Paul Laszlo Guillaume Quiviger December 2012 Copyright 2012 McKinsey & Company 2 Contents Commodity trading
Getting to ERM. McKinsey Working Papers on Risk, Number 43. A road map for banks and other financial institutions
McKinsey Working Papers on Risk, Number 43 Getting to ERM A road map for banks and other financial institutions Rob McNish Andreas Schlosser Francesco Selandari Uwe Stegemann Joyce Vorholt March 2013 Copyright
Compliance 2.0: Emerging Best Practice Model
Compliance 2.0: Emerging Best Practice Model Global Risk Practice October 2015 Authored by: Piotr Kaminski Kate Robu 1 Introduction Compliance risk has become one of the most significant ongoing concerns
Strategic commodity and cash-flowat-risk modeling for corporates
McKinsey Working Papers on Risk, Number 51 Strategic commodity and cash-flowat-risk modeling for corporates Martin Pergler Anders Rasmussen October 2013 Copyright 2013 McKinsey & Company Contents Strategic
How To Create A Credit Risk Model For The Unbanked
McKinsey Working Papers on Risk, Number 30 New credit-risk models for the unbanked Tobias Baer Tony Goland Robert Schiff March 2012 Copyright 2012 McKinsey & Company Contents New credit-risk models for
Risk in emerging markets
McKinsey Working Papers on Risk, Number 56 Risk in emerging markets The way forward for leading banks Omar Costa Jawad Khan Cindy Levy Alfonso Natale Ozgur Tanrikulu June 2014 Copyright 2014 McKinsey &
Variable Annuities in Europe after the Crisis: Blockbuster or Niche Product?
McKinsey Working Papers on Risk, Number 19 Variable Annuities in Europe after the Crisis: Blockbuster or Niche Product? Lukas Junker Sirus Ramezani February 2010 Copyright 2010 McKinsey & Company This
Getting to grips with counterparty risk
McKinsey Working Papers on Risk, Number 20 Getting to grips with counterparty risk Nils Beier, Holger Harreis, Thomas Poppensieker, Dirk Sojka, and Mario Thaten June 2010 Copyright 2010 McKinsey & Company
Europe s wholesale gas market
McKinsey Working Papers on Risk, Number 54 Europe s wholesale gas market Innovate to survive Cosimo Corsini Sven Heiligtag Marco Moretti Johann Raunig May 2014 Copyright 2014 McKinsey & Company 1 Europe
A Board Perspective on Enterprise Risk Management
McKinsey Working Papers on Risk, Number 18 A Board Perspective on Enterprise Risk Management André Brodeur Kevin Buehler Michael Patsalos-Fox Martin Pergler February 2010 Copyright 2010 McKinsey & Company
It s not just about getting your ratios right
Risk and Regulation It s not just about getting your ratios right Basel s far-reaching new risk IT requirements January 2013 Keiichi Aritomo Tommaso Cohen Philipp Härle Holger Harreis Kayvaun Rowshankish
Getting things done How governments can deliver public infrastructure projects on time and within budget
Getting things done How governments can deliver public infrastructure projects on time and within budget Alexander Franke Alex Wittenberg One of the greatest potential threats to global prosperity is a
Enterprise risk management
McKinsey Working Papers on Risk, Number 40 Enterprise risk management What s different in the corporate world and why Martin Pergler December 2012 Copyright 2012 McKinsey & Company Contents Enterprise
Impact of Basel III Liquidity Requirements on the Payments Industry
Cards & Payments the way we see it Impact of Basel III Liquidity Requirements on the Payments Industry Liquidity management strategy for banks providing payment services Table of Contents 1. Summary 3
PPP Basics and Principles of a PPP Framework
Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership
A Risk-Adjusted Operating Model for Insurers: Addressing Regulatory and Market Demands
A Risk-Adjusted Operating Model for Insurers: Addressing Regulatory and Market Demands While most insurers have recovered from the fiscal crisis of 2008, significant challenges remain on multiple fronts
Placing a Value on Enterprise Risk Management ADVISORY
Placing a Value on Enterprise Risk Management ADVISORY Placing a Value on Enterprise Risk Management 1 In turbulent economic times, the case for investing in an enterprise risk management (ERM) program
Credit Risk Management: Trends and Opportunities
Risk & Compliance the way we see it Credit Risk Management: Trends and Opportunities The Current State of Credit Risk Management 1 Overview The crisis exposed the shortcomings of existing risk management
THE MISSING LINKS IN INVESTMENT ANALYSIS A PORTFOLIO MANAGEMENT STRATEGY TO MAKE INVESTMENTS WORK
THE MISSING LINKS IN INVESTMENT ANALYSIS A PORTFOLIO MANAGEMENT STRATEGY TO MAKE INVESTMENTS WORK MICHAEL HEPINSTALL DANIEL LYONS MARK PELLERIN Confronted with tighter profit margins and greater risks,
Integrated Risk Management:
Integrated Risk Management: A Framework for Fraser Health For further information contact: Integrated Risk Management Fraser Health Corporate Office 300, 10334 152A Street Surrey, BC V3R 8T4 Phone: (604)
Accenture Federal Services. Federal Solutions for Asset Lifecycle Management
Accenture Federal Services Federal Solutions for Asset Lifecycle Management Assessing Internal Controls 32 Material Weaknesses: identified in FY12 with deficiencies noted in the management of nearly 75%
OPTIMUS SBR. Optimizing Results with Business Intelligence Governance CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE.
OPTIMUS SBR CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE. Optimizing Results with Business Intelligence Governance This paper investigates the importance of establishing a robust Business Intelligence (BI)
Operational Risk Management - The Next Frontier The Risk Management Association (RMA)
Operational Risk Management - The Next Frontier The Risk Management Association (RMA) Operational risk is not new. In fact, it is the first risk that banks must manage, even before they make their first
Utilities Webinar Asset Lifecycle Management and Capital Projects & Infrastructure
Utilities Webinar Asset Lifecycle Management and Capital Projects & Infrastructure October 31, 2013 Agenda 1. Context - the Utility CEO s Agenda 2. Asset Lifecycle Management and Utilities 3. What s at
The Role of the Board in Enterprise Risk Management
Enterprise Risk The Role of the Board in Enterprise Risk Management The board of directors plays an essential role in ensuring that an effective ERM program is in place. Governance, policy, and assurance
The Four Planes of Capital Projects
The Four Planes of Capital Projects An Integrated Approach to Capital Project Due Diligence August 2009 Westney Consulting Group, Inc. www.westney.com Management by objectives work - if you know the objectives.
Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified.
Asset management Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified. Data is about more than numbers. It tells
THE FUTURE OF ASSET MANAGEMENT ON THE ROAD TO AN ASSET MANAGEMENT REVOLUTION
THE FUTURE OF ASSET MANAGEMENT ON THE ROAD TO AN ASSET MANAGEMENT REVOLUTION T his is the first in a series of Arcadis reports analyzing the role and evolution of asset management in organizations. Asset
How to Develop Successful Enterprise Risk and Vendor Management Programs
Project Management Institute New York City Chapter January 2014 Chapter Meeting How to Develop Successful Enterprise Risk and Vendor Management Programs Christina S. Kite Senior Vice President Corporate
Integrated Stress Testing
Risk & Compliance the way we see it Integrated Stress Testing A Practical Approach Contents 1 Introduction 3 2 Stress Testing Framework 4 3 Data Management 6 3.1 Data Quality 6 4 Governance 7 4.1 Scenarios,
Best Practices in adopting a Shared Services Model August 2013 22011YYYY
Best Practices in adopting a Shared Services Model August 2013 22011YYYY In their endeavors to become high performing organizations, businesses are pushing all innovation frontiers to do more with less
In control: how project portfolio management can improve strategy deployment. Case study
Case study In control: how project portfolio can improve strategy deployment Launching projects and initiatives to drive revenue and achieve business goals is common practice, but less so is implementing
Accenture Risk Management. Industry Report. Life Sciences
Accenture Risk Management Industry Report Life Sciences Risk management as a source of competitive advantage and high performance in the life sciences industry Risk management that enables long-term competitive
Part B1: Business case developing the business case
Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project
Deriving Value from ORSA. Board Perspective
Deriving Value from ORSA Board Perspective April 2015 1 This paper has been produced by the Joint Own Risk Solvency Assessment (ORSA) Subcommittee of the Insurance Regulation Committee and the Enterprise
Understanding and articulating risk appetite
Understanding and articulating risk appetite advisory Understanding and articulating risk appetite Understanding and articulating risk appetite When risk appetite is properly understood and clearly defined,
Principles for An. Effective Risk Appetite Framework
Principles for An Effective Risk Appetite Framework 18 November 2013 Table of Contents Page I. Introduction... 1 II. Key definitions... 2 III. Principles... 3 1. Risk appetite framework... 3 1.1 An effective
Cost of capital in the financial turmoil: how should utilities deal with it?
Cost of capital in the financial turmoil: how should utilities deal with it? Virat Patel Partner Marco Venneri Manager As a direct result of the current credit crisis, the Weighted Average Cost of Capital
SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND
SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND CONTENTS INTRODUCTION 3 EFFECTIVELY MANAGE THE SCOPE OF YOUR IMPLEMENTATION
Capital Requirements Directive Pillar 3 Disclosure. December 2015
Capital Requirements Directive Pillar 3 Disclosure December 2015 1. Background The purpose of this document is to outline the Pillar 3 disclosures for BlueBay Asset Management LLP ( BlueBay ). BlueBay
Remarks by. Carolyn G. DuChene Deputy Comptroller Operational Risk. at the
Remarks by Carolyn G. DuChene Deputy Comptroller Operational Risk at the Bank Safety and Soundness Advisor Community Bank Enterprise Risk Management Seminar Washington, D.C. October 22, 2012 Good afternoon,
RISK MANAGEMENT REPORT (for the Financial Year Ended 31 March 2012)
RISK MANAGEMENT REPORT (for the Financial Year Ended 31 March 2012) Integrated Risk Management Framework The Group s Integrated Risk Management Framework (IRMF) sets the fundamental elements to manage
Enterprise Risk Management & Information Technology
Enterprise Risk Management & Information Technology Presented by Scott Perry and Gary Ross Slalom Consulting, San Francisco Agenda Introductions Session Objectives Overview of Enterprise Risk Management
14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution
2015 ERP GUIDE 14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution Some ERP implementations can be described as transformational, company-changing events. Others are big disappointments
Two trillion and counting
Two trillion and counting Assessing the credit gap for micro, small, and medium-size enterprises in the developing world OCTOBER 2010 Peer Stein International Finance Corporation Tony Goland McKinsey &
UNECE PPP Healthcare Standard
INTERNATIONAL SPECIALIST CENTRE OF EXCELLENCE ON PPPs IN HEALTH MANILA, PHILIPPINES UNECE PPP Healthcare Standard Questions on lessons learned in the development of Public-Private Partnership ( PPP ) programmes
Enterprise Risk Management
Cayman Islands Society of Professional Accountants Enterprise Risk Management March 19, 2015 Dr. Sandra B. Richtermeyer, CPA, CMA What is Risk Management? Risk management is a process, effected by an entity's
Supply Chain [QUARTERLY] A better way to engage with suppliers p. 24 Q4/2012. Standardized software: Eroding your competitive edge?
Supply Chain Q4/2012 A better way to engage with suppliers p. 24 [QUARTERLY] Standardized software: Eroding your competitive edge? From many, one: IBM unifies its supply chains www.supplychainquarterly.com
Enterprise Risk Management in a Highly Uncertain World. A Presentation to the Government-University- Industry Research Roundtable June 20, 2012
Enterprise Risk Management in a Highly Uncertain World A Presentation to the Government-University- Industry Research Roundtable June 20, 2012 CRO Council Introduction Mission The North American CRO Council
THE ROLE OF FINANCE AND ACCOUNTING IN ENTERPRISE RISK MANAGEMENT
THE ROLE OF FINANCE AND ACCOUNTING IN ENTERPRISE RISK MANAGEMENT Let me begin by thanking Baruch College for giving me the opportunity to present this year s prestigious Emanuel Saxe Lecture in Accounting.
Course Brochure. New York. Doha
Course Brochure LONDON New York Dubai Hong Kong Singapore Johannesburg Doha Aberdeen abuja kuala lumpur Table of contents Background page 3 Oil & Gas Faculty pages 5-8 Mining Faculty pages 9-11 Public
Portfolio Management for Banks
Enterprise Risk Solutions Portfolio Management for Banks RiskFrontier, our industry-leading economic capital and credit portfolio risk management solution, along with our expert Portfolio Advisory Services
Risk appetite as a dynamic management tool
Risk appetite as a dynamic management tool Background The topic of risk appetite is at the centre of attention currently. There are various reasons for this: the financial crisis, which has made it clear
EXECUTIVE SUMMARY...5
Table of Contents EXECUTIVE SUMMARY...5 CONTEXT...5 AUDIT OBJECTIVE...5 AUDIT SCOPE...5 AUDIT CONCLUSION...6 KEY OBSERVATIONS AND RECOMMENDATIONS...6 1. INTRODUCTION...9 1.1 BACKGROUND...9 1.2 OBJECTIVES...9
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
WFP ENTERPRISE RISK MANAGEMENT POLICY
WFP ENTERPRISE RISK MANAGEMENT POLICY Informal Consultation 3 March 2015 World Food Programme Rome, Italy EXECUTIVE SUMMARY For many organizations, risk management is about minimizing the risk to achievement
CSR / Sustainability Governance and Management Assessment By Coro Strandberg Principal, Strandberg Consulting www.corostrandberg.
Introduction CSR / Sustainability Governance and Management Assessment By Coro Strandberg Principal, Strandberg Consulting www.corostrandberg.com June 2015 Companies which adopt CSR or sustainability 1
Next-Generation Supply Management
Cisco Internet Business Solutions Group (IBSG) Cisco IBSG 2012 Cisco and/or its affiliates. All rights reserved. Next-Generation Supply Management Authors Ram Muthukrishnan Kevin Sullivan May 2012 Cisco
Risks and uncertainties
Risks and uncertainties Our risk management approach We have a well-established risk management methodology which we use throughout the business to allow us to identify and manage the principal risks that
Essential Elements for Any Successful Project
In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable
Risk Management. Risk Identification
Management This part provides guidance on the treatment of risks on a PPP project, and; Identifies the major risks common to many PPP projects across all sectors; Allocates the identified risks between
Consumer Goods and Services
Accenture Risk Management Industry Report Consumer Goods and Services 2011 Global Risk Management Point of View Consumer Goods and Services 2011 Global Risk Management Point of View Consumer Goods and
THE UH OH MOMENT. Financial Services Enterprises Focus on Governance, Transparency and Supply Chain Risk
THE UH OH MOMENT Financial Services Enterprises Focus on Governance, Transparency and Supply Chain Risk By Lois Coatney, Chuck Walker and Joseph Yacura, ISG Directors www.isg-one.com INTRODUCTION A top
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
Guidance Note: Stress Testing Class 2 Credit Unions. November, 2013. Ce document est également disponible en français
Guidance Note: Stress Testing Class 2 Credit Unions November, 2013 Ce document est également disponible en français This Guidance Note is for use by all Class 2 credit unions with assets in excess of $1
Bringing wisdom to ITSM with the Service Knowledge Management System
Processes 415 Bringing wisdom to ITSM with the Service Knowledge Management System 7.3 Bringing wisdom to ITSM with the Service Knowledge Management System nowledge is a process of piling up facts; wisdom
P3M3 Portfolio Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction
Transforming risk management into a competitive advantage kpmg.com
INSURANCE RISK MANAGEMENT ADVISORY SOLUTIONS Transforming risk management into a competitive advantage kpmg.com 2 Transforming risk management into a competitive advantage Assessing risk. Building value.
Corporate Portfolio Management
Corporate Risk Corporate Portfolio Management Capital allocation from a risk-return perspective Premise Aligning the right information with the right people to make effective corporate decisions is one
The Change Enablement Center
Importance of Change Management The ability to execute strategic, ambitious, and sustainable change is creating winners. An organization today must navigate an increasingly complex global landscape, responding
Financial sector leadership on natural capital
Financial sector leadership on natural capital The Natural Capital Declaration A commitment by financial institutions to mainstream natural capital in financial products and in accounting, disclosure and
University of St. Gallen Law School Law and Economics Research Paper Series. Working Paper No. 2008-19 June 2007
University of St. Gallen Law School Law and Economics Research Paper Series Working Paper No. 2008-19 June 2007 Enterprise Risk Management A View from the Insurance Industry Wolfgang Errath and Andreas
Factoring Risk into Transportation and Logistics Sourcing
Surface Transportation Factoring Risk into Transportation and Logistics Sourcing In the face of continued economic uncertainty and heightened cost and margin pressures across all industries, many shippers
Managing Risk at Bank of America Corporation. Overview
Managing Risk at Bank of America Corporation Overview Risk is inherent in every material business activity that we undertake. Our business exposes us to strategic, credit, market, liquidity, compliance,
Bridging Operational & Financial Forecasting
IBM Software Group White Paper Budgeting and Forecasting Bridging Operational & Financial Forecasting 2 Bridging Operational & Financial Forecasting Introduction The global economic downturn has accelerated