STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES

Size: px
Start display at page:

Download "STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES"

Transcription

1 STANDARD SPECIFICATIONS SECTION SUBMITTAL PROCEDURES PART 1 GENERAL 1.1 DESCRIPTION A. Section includes general requirements and procedures related to preparation and transmittal of Submittals to include Schedules, Contractor's Drawings, Samples, Manuals, Methods of Construction, and Record Drawings to Contract Manager demonstrating performance of Work. 1. Other requirements for submittals are specified under applicable sections of Standard Specifications and Special Provisions. 1.2 SUBMITTAL REQUIREMENTS A. General. 1. Submit each under separate cover or transmittal. 2. Furnish neat, legible, and sufficiently explicit detail to enable proper review for compliance with the Contract Documents. 3. Show complete and detailed fabrication; assembly and installation details; wiring and control diagrams; catalog data; pamphlets; descriptive literature; and performance and test data. 4. Include calculations or other information sufficient to show comprehensive description of structure, machine, or system provided and its intended manner of use. a. With each submission, furnish Contract Manager specific written notation and justification of each variation in Contractor's Submittals from requirements of Contract Documents. b. Fabrication, purchase or delivery of materials to the site, and installation of materials or Work performed before approval, or not conforming to approved submittals, shall be at Contractor's risk. 5. Contract Manager s review and approval of submittals shall not relieve Contractor from responsibility for meeting the requirements of the Contract Documents, unless Contract Manager has received specific written notice of each variation and has given specific written approval. 6. Contractor assumes all risks of error and omission. 7. Contract Work, Materials, Fabrication, and Installation: Following approved submittals. B. Process and Requirements. 1. Not later than 3 days after preconstruction conference, submit written list of materials and equipment to be purchased, giving name, address, and telephone number of Supplier, Manufacturer, or processor. System Extension Permit July 2013

2 a. Submit updated material and equipment list when changes are made. 2. Coordinate and schedule submittals with Contract Manager. 3. With the first submittal, but not later than 30 days after issuance of System Extension Permit, submit a complete submittal schedule, listing as near as practicable and by Specification Section number, submittals required and approximate date submittal will be forwarded. a. Arrange submittals schedule so that related equipment items are submitted concurrently. 4. To each submittal affix the following signed Certification Statement: a. "Certification Statement: By this submittal, we hereby represent that we have determined and verified all field measurements, field construction criteria, materials, dimensions, catalog numbers and pertinent data and we have checked and coordinated each item with other applicable approved drawings and all Contract requirements." 5. Identification. a. Submit identification data, as applicable, contained thereon or permanently adhered thereto: 1) The Commission Project Number. 2) Project name and location. 3) Submittal Numbers: a) Number sequentially as submitted. b) Resubmittals shall bear original submittal number and be sequentially lettered. 4) Product identification. 5) Drawing title, drawing number, revision number, and date of drawing and revision. 6) Applicable Drawing Numbers and Specification Section and Paragraph Numbers. 7) Subcontractor's, Vendor's and/or Manufacturer's name, address and phone number. 8) Contractor's Certification Statement. b. Identify on exterior, catalog product data or brochures submitted in packages of multiple items. Include page and catalog item numbers for items submitted. 1) Highlight catalog, product data, or brochures containing various products, sizes, and materials to show particular item submitted. 2) Mark items not applicable to Project "not applicable" or cross out. 3) If one or more items in catalog submittal are not approved, resubmit only unapproved items. 6. Stamp Space: Blank space of approximately 2-1/2 inches high by 4 inches wide adjacent to the identification data to receive Contract Manager's status stamp. 7. Number of Copies: See requirements in Submittals specified herein. 8. Approval Process: a. Follow submittal schedule provided to Contract Manager. Contract Manager will return submittal within 30 days. b. Submittals will be returned, marked with one of following classifications: System Extension Permit July 2013

3 1) APPROVED: Requires no corrections, no marks. 2) APPROVED AS NOTED: Requires a few minor corrections. Items may be fabricated as marked without further resubmission. Resubmit 2 corrected copies to the Contract Manager. 3) APPROVED AS NOTED - RESUBMIT: Requires corrections. Items not marked may be fabricated. Resubmit entire submittal following original submission with corrections noted. Allow 30 days for checking and Contract Manager s appropriate action. 4) REJECTED: Requires major corrections or is otherwise not following Contract Documents. No items shall be fabricated. Resubmit entire submittal following original submission with corrections noted. Allow 30 days for checking and Contract Manager s appropriate action. 5) INFORMATION ONLY: Items specified by Contract Documents. C. Electronic Submittals: PDF Format, as approved by Contract Manager. 1.3 SUBMITTALS A. Shop Drawings. 1. For original submittal and each subsequent resubmittal required, submit 1 each reproducible transparency and 6 legible prints. Contract Manager will return 3 copies of shop drawing prints. 2. Show types, sizes, accessories, and layouts, including plans, elevations, and sectional views; component, assembly, and installation details; and all other information required to illustrate how applicable portions of Project requirements will be fabricated and/or installed. 3. In case of fixed mechanical and electrical equipment, submit layout drawings drawn to scale, to show required clearances for operation, maintenance, and replacement of parts. Include manufacturer's certified performance curves, catalog cuts, pamphlets, descriptive literature, installation, and application recommendations, as required. Submit together shop drawings for closely related items such as a pump and its motor. Additional shop drawings and information required for electrical and mechanical equipment are listed in appropriate Specification Sections. 4. Shop drawings for continually furnished items such as pipe, fittings, valves, precast structures and metal work will be waived provided Contractor submits letter naming manufacturer who will furnish these items. Manufacturer shall have on file certified drawing(s) containing above information approved by the Commission, and items furnished shall be as described on certified drawing(s). If Standard Details or Specifications change after certified drawings are approved, new submittals are required. B. Catalog Data. 1. For original submittal and each subsequent resubmittal required, submit 12 copies of catalog data. Contract Manager will return 3 copies. System Extension Permit July 2013

4 2. Manufacturer's Catalog, Product, and Equipment Data: Certified and include material type, performance characteristics, voltage, phase, capacity, and similar data. a. Furnish wiring diagrams when applicable. b. Indicate catalog, model, and serial numbers representing specified equipment. c. Submit complete component information to verify specified required items. C. Working Drawings. 1. For original submittal and each subsequent resubmittal required, submit 1 each reproducible transparency and 6 legible prints. Contract Manager will return 3 copies. 2. Submit working drawings as required for changes, substitutions, Contractor design items, and Contractor designed methods of construction. Requirements for working drawings are listed in appropriate Specification Sections or in Special Provisions. 3. Include with drawings calculations or other information to completely explain structure, machine, or system described and its intended use. Review or approval of drawings by Contract Manager shall not relieve Contractor from responsibility for fulfillment of requirements of the Contract Documents. Contractor assumes risks of error, and Contract Manager shall have no responsibility. 4. Submit working drawings and calculations sealed, dated, and signed by Professional Engineer registered in State of Maryland and experienced in the work or discipline involved. D. Method of Construction. 1. For original submittal and each subsequent resubmittal required, submit 12 copies of data detailing method of construction. Contract Manager will return 3 copies. 2. When Contract Manager specifies or directs, submit proposed method of construction for specific portions of Work. a. Include detailed written description of phases of construction operation to fully explain to Contract Manager proposed method of construction. b. If required by Specifications, submit working drawings to supplement description. 3. Review will follow the process herein and shall not relieve Contractor from responsibility for fulfillment of the requirements of the Contract Documents. Contractor assumes risks associated with proposed method. 4. After review, submit requests for modifications in detail, including justification for them. Do not implement modifications prior to Contract Manager s review. E. Manufacturer's Installation Recommendations. 1. For original submittal and each subsequent resubmittal required, submit 12 copies of manufacturer s installation recommendations. Contract Manager will return 3 copies. 2. Furnish written detail for step by step preparation and installation of the materials and products, including recommended tolerances and space for maintenance and operation. System Extension Permit July 2013

5 F. Samples. 1. General: As soon as practicable after issuance of the System Extension Permit, submit samples required by Specifications or at Contract Manager s request. Unless otherwise specified, submit 3 samples of each item as original submittal. 2. Obtain approval before delivery of material to Project site. 3. Samples: Representative of actual material proposed for use in project and of sufficient size to demonstrate design, color, texture, and finish when these attributes will be exposed to view. a. If samples deviate from Contract Documents, advise Contract Manager in writing with submittal and state reason. 4. Identification. a. Permanently attach to each sample: 1) The Commission Project Number. 2) Project Name and Location. 3) Product Identification. 4) Applicable Drawing and Specification Section Number. 5) Subcontractor's, Vendor's and/or Manufacturer's Name, Address and Phone Number. b. Mail under separate cover a letter submitting each shipment of samples containing identification information listed herein. Enclose copy of this letter with shipment. 5. Approval Process. a. Allow 30 days for Contract Manager s checking and appropriate action. Certain samples may be required to be tested at an approved independent lab for specified requirements by the Commission before approval. Failure of sample to pass tests will be sufficient cause for refusal to approve. b. Samples of various material or equipment delivered to site or during placement may be required to be tested by Contract Manager. Samples failing to meet Contract Document requirements will automatically void previous approvals, and resubmittal of samples will be required. G. Record Drawings (As-builts). 1. Applicant will prepare and furnish sewer and water main as-builts and service connection finals to the Contract Manager. As-builts and service connection finals are to be submitted by the Applicant or their designated representative. The asbuilt information package is to be submitted to the Contract Manager allowing 2 weeks for review. Their approval is part of the WSSC requirements for obtaining a Certificate of Substantial Completion and water meter release(s). 2. The package will include: a. Three (3) Green Line copies of Water As-built Drawings, showing the most current revisions to the Drawings and Profile, including connection permit numbers with the water survey final as-built data, as specified below. b. Three (3) Red Line copies of Sewer As-built Drawings, showing the most current revisions to the Drawings and Profile, including connection permit numbers with the sewer survey final as-built data, as specified below. System Extension Permit July 2013

6 c. Three (3) copies of the Fire Hydrant Summary Sheet. d. Three (3) copies of the Sewer As-built Data Work Sheet. e. One (1) copy of the water and sewer grade notes sheets, including field notes. 3. The As-Built Record Drawings (plan and profile) shall be completed in accordance with the following: a. All field changes will be shown on as-built drawings. Manhole to manhole distances and swing tie measurements shall be carried to the nearest tenth. Manhole depths shall be carried to the nearest hundredth. The as-built information will be submitted on the most current, revised Drawings. A Registered Surveyor or Engineer will certify the as-built. b. As-built coordinates for manholes, fire hydrants and water valves shall be shown in a table on the as-built drawing where space permits or on a separate sheet, in accordance with NAD 83/91 datum. Coordinates may be placed on the profile view above each manhole, fire hydrant and water valve station in lieu of a table. c. Complete the as-built data box on Sheet 1 of the Drawings: 1) Contract Manager WSSC Contract Manager on the job 2) Contractor who installed 3) Inspector site inspector for WSSC 4) L&G surveyor 5) Dated started 6) Date completed substantial date per CM 7) Type of pipe W water main type of pipe 8) Date Finaled 9) Finaled by name of the Survey company preparing the as-built 4. Sewer Main As-built information a. Provide the following information on the horizontal plan sheet in RED type: 1) Three swing ties to the center of each manhole cover (see Swing Tie Requirements). 2) When manholes are built over an existing sewer, provide a distance from the center of the upstream and downstream manhole covers to the center of the built over manhole cover. b. Provide the following information on the profile in RED type: 1) On the profile view, place a check next to those elevations and stations that were built per Drawings. Where they have changed, cross out with a single line and write the as-built elevation and station in red. 2) Depth of the manhole (in vertical feet) from top of rim to channel centerline. 3) Sewer line lengths (in linear feet) from centerline of manhole cover to centerline of manhole cover. 4) Drop connection elevation at the centerline of manhole and inside wall of manhole. 5) Manhole rim elevations. 6) Percent of sewer line grade to be calculated from centerline of manhole to centerline of manhole except for those lines of grade or less. In those cases the lines are to be calculated and indicated on the as- System Extension Permit July 2013

7 built from the incoming invert at the inside manhole wall to the next upstream manhole s outgoing invert at the inside manhole wall. 5. Water Main As-built Information a. Three swing ties shall be provided to the center of each water fitting listed below (see swing tie requirements) in a tie box on the horizontal plan using Green type: 1) Caps/plugs (include depth in vertical feet) 2) Valves 3) Test stations b. Provide fire hydrant data, listed below in a tie box on the horizontal plan using Green type: 1) Fire hydrant station 2) Street name 3) Measurements from center of fire hydrant valve to fire hydrant 4) Height (in vertical feet) of fire hydrant 5) Fire Hydrant Manufacturer 6) Operating nut (top of hydrant) elevation c. Note all changes in Green on profile. 1) If station on water main is the same, put a check next to it. 2) 0+00 never changes. 6. The Service Connection Final shall be completed in accordance with the following: a. Provide two (2) copies of the Service Connection Certification form (found in the Attachments Section) and two complete sets of Drawings showing all revisions and connection permit numbers. The Service Connection Certification form will show the following information: 1) Lot, block and connection permit number. 2) Mainline sewer tee station when both water and sewer connections are in the same location, measuring from the downstream manhole. 3) Mainline water station when there are no sewer connections. 4) Linear footage of the service connections from the centerline of the main[s] to the property line. 5) Depth (in vertical feet) of each connection at the cleanout stack and/or curb stop. 6) Ties: Three swing ties from the green board and/or cleanout stack. When water service is in different trench than sewer service, three swing ties to the water meter or curb stop. 7. Swing Tie Requirements are as follows: a. Swing ties, preferably under 100-feet, are to be taken from above ground structures provided in the following order of preference and are to be labeled. 1) Manholes (sewer, water, storm drain) (taken at the center of the cover) 2) Telecommunications and electric manholes or structures (C&P, PEPCO, BG&E) with the location plotted on as-built drawings and the measurement taken at the center of the structure. 3) Fire hydrants. 4) House or building corners. System Extension Permit July 2013

8 5) Valve Box 6) Telephone poles (pole number must be included on as-built drawings). 7) Curb box or cleanout stack, which are located on a different property. 8) Retaining wall corners. 9) Point on line from the downstream manhole to upstream manhole (use only one point on line tie per water main fitting) 10) Property corners, if nothing else exists. H. Substitutions: See Section PART 2 PRODUCTS NOT USED PART 3 EXECUTION NOT USED **WSSC** System Extension Permit July 2013

SECTION 5 DRAFTING STANDARDS

SECTION 5 DRAFTING STANDARDS SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.

More information

SECTION 01 78 29 AS-BUILT DOCUMENTATION

SECTION 01 78 29 AS-BUILT DOCUMENTATION SECTION 01 78 29 AS-BUILT DOCUMENTATION PART 1: GENERAL 1.01 AS-BUILTS Where identified as a product of the Work, provide as-built drawings adhering to the criteria provided here and in the special conditions.

More information

LANSING COMMUNITY COLLEGE 14205.00 TLC BUILDING SERVER ROOM UPGRADES SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.

LANSING COMMUNITY COLLEGE 14205.00 TLC BUILDING SERVER ROOM UPGRADES SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1. SECTION 013300 - SUBMITTAL PROCEDURES PART 1 - GENERAL 1.1 SUMMARY A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings,

More information

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:

The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm: Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section

More information

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects

Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects Wastewater Collection System Supplemental Design Standards for Capital Improvement Program Projects March 2013 i Metropolitan Sewer District of Greater Cincinnati Wastewater Collection System Supplemental

More information

SEWER LINE EXTENSION DESIGN CHECKLIST

SEWER LINE EXTENSION DESIGN CHECKLIST SEWER LINE EXTENSION DESIGN CHECKLIST SWLE# Utilities Staff Date DISCLAIMER - This checklist is provided to Consulting Engineers for the express purpose of assisting them in compiling design plans for

More information

Request for Proposal # 2016-054

Request for Proposal # 2016-054 Request for Proposal # 2016-054 GIS Editing & Updating Services Due Date: July 7, 2016 Time: 2:00PM Receipt Location: Government Center, 500 N. Main Street, 7 th Floor, Room #709, Monroe, NC 28112 Procurement

More information

CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST

CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST CITY OF ANN ARBOR PUBLIC SERVICES PLAN REVIEW CHECKLIST NOTE: The following list shall only be used as a guide and shall not be used in lieu of the specifications found in the CITY OF ANN ARBOR PUBLIC

More information

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, Storm Drain Installation, of these Standard Provisions. SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and

More information

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE

PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE REGION OF PEEL PUBLIC WORKS DESIGN, SPECIFICATIONS & PROCEDURES MANUAL LINEAR INFRASTRUCTURE Storm Sewer Design Criteria REVISED July 2009 PUBLIC WORKS STORM SEWER DESIGN CRITERIA TABLE OF CONTENTS 1.0

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

SETTLEMENT INSTRUMENTATION & MONITORING

SETTLEMENT INSTRUMENTATION & MONITORING SECTION 02445 SETTLEMENT INSTRUMENTATION & MONITORING PART 1 - GENERAL 1.01 SUMMARY A. The Work specified in this Section includes furnishing, installing, and monitoring settlement instrumentation to monitor

More information

G.S. 47-30 Mapping Requirements for Recordable Maps

G.S. 47-30 Mapping Requirements for Recordable Maps G.S. 47-30 Mapping Requirements for Recordable Maps 47-30. Plats and subdivisions; mapping requirements. (a) Size Requirements. All land plats presented to the register of deeds for recording in the registry

More information

SECTION 5: SANITARY SEWER SYSTEM DESIGN

SECTION 5: SANITARY SEWER SYSTEM DESIGN SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities

More information

CITY OF FARMERSVILLE, TEXAS

CITY OF FARMERSVILLE, TEXAS CITY OF FARMERSVILLE, TEXAS MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES Subdivision Ordinance #2007-08 Exhibit B February 13, 2007 TABLE OF CONTENTS Description Page No. General... 1 Water

More information

LAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application

LAKEHAVEN UTILITY DISTRICT. Developer Extension Agreement Application Applicant shall indicate that the required information has been provided or is not applicable to the project by placing the appropriate mark in the first column of this checklist. Missing or incomplete

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African

TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African TOPOGRAPHICAL SURVEY REPORT - PART OF L.R No. 7413/11 Done on February 2015 at International Union for Conservation of Nature (IUCN) Eastern African Regional Office 01 CHAPTER ONE Checklist Page 2 of 8

More information

FIBER-OPTIC CABLE PLAN CHECK

FIBER-OPTIC CABLE PLAN CHECK Engineering Division 201 North Broadway, Escondido, CA 92025 (760) 839-4651, FAX (760) 839-4597 FIBER-OPTIC CABLE PLAN CHECK To: Date: Project: Project No. Address: Check No. Attn: Via: The attached plans

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

SECTION 15410 GROUND WATER STORAGE TANKS

SECTION 15410 GROUND WATER STORAGE TANKS SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design

More information

APPENDIX D. (Standard Notes and Signature Blocks)

APPENDIX D. (Standard Notes and Signature Blocks) APPENDIX D (Standard Notes and Signature Blocks) Use this note on all construction plans in Raleigh: ATTENTION CONTRACTORS The Construction Contractor responsible for the extension of water, sewer, and/or

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS 854.1 DESCRIPTION: This item shall govern sanitary sewer laterals installed in accordance with these

More information

Close-Out Documents... 9

Close-Out Documents... 9 Water and Sanitary Sewer Service Connection Requirements Service Connection Requirements... 1 Application for Services... 2 Water Meter Application... 2 Wet Tap/Tie-in Connection Requirements... 3 Meter

More information

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way)

Right-of-Way Permit Application Process (Plans that affect District owned or maintained right-of-way) Flood Control District of Maricopa County (District) 2801 W. Durango Street Phoenix, AZ 85009 Telephone: 602-506-4583 or 602-506-5476 Fax: 602-506-1663 Right-of-Way Permit Application Process (Plans that

More information

Section 100 Contractor Quality Control Program

Section 100 Contractor Quality Control Program 7/21/2014 AC 150/5370-10G Section 100 Contractor Quality Control Program 100-01 General. When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and

More information

ORDINANCE NO. 2013 -

ORDINANCE NO. 2013 - ORDINANCE NO. 2013 - AN ORDINANCE OF BREVARD COUNTY, FLORIDA AMENDING CHAPTER 62, LAND DEVELOPMENT REGULATIONS SECTION 62-2891, LOT DRAINAGE, AND CHAPTER 22 BUILDINGS AND BUILDING REGULATIONS, SECTION

More information

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant

More information

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS STANDARD SPECIFICATIONS SECTION 02956 CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements to execute internal closed

More information

Lot Number. City. Architect Name SUBCONTRACTORS - COMPLETE AND ATTACH LIST ON PAGE 4

Lot Number. City. Architect Name SUBCONTRACTORS - COMPLETE AND ATTACH LIST ON PAGE 4 New Construction Permit Application Village of Shorewood Building Division One Towne Center Blvd Shorewood, IL 60404 (815)553-2310 Fax (815)744-6766 SUBMISSION CHECKLIST - Complete this application and

More information

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT

CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT Page 1 CITY OF VAUGHAN SCHEDULE O LOT GRADING DESIGN FOR RESIDENTIAL DEVELOPMENT CIVIC CENTRE 2141 MAJOR MACKENZIE DRIVE MAPLE ONTARIO L6A 1T1 905-832-2281 Page 2 SECTION 1 - GENERAL OBJECTIVES To provide

More information

Florida s Turnpike Enterprise (FTE) Shop Drawing Review Process for Design Bid Build (Conventional) Projects

Florida s Turnpike Enterprise (FTE) Shop Drawing Review Process for Design Bid Build (Conventional) Projects General: Florida s Turnpike Enterprise (FTE) Shop Drawing Review Process for Design Bid Build (Conventional) Projects The information outlined within this document, depicts a portion of Florida s Turnpike

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Residential Building Permits Information

Residential Building Permits Information City of Bonham Building Department 514 Chestnut St. Bonham, Texas 75418 OFFICE: (903) 583-7555 FAX: (903)583-5761 Residential Building Permits Information Application for Permits: To apply for a permit,

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

Let Us Give Utilities the Respect that they Deserve.

Let Us Give Utilities the Respect that they Deserve. Water & Sewer Utilities Miscellaneous Design and Plan Preparation Guidelines Issued by: Ray Mowla, P.E. Jefferson Parish Department of Engineering, Utilities Section The purpose of issuing these miscellaneous

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

Chapter 9 Sanitary Sewers

Chapter 9 Sanitary Sewers Chapter 9 Sanitary Sewers S:/Engineering/Design Standards/Chapter 9 12/29/2014 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

How To Build A Basement House

How To Build A Basement House Single Family Basement Finish Purpose of Guide The purpose of this guide is to assist you in the permit process for your project. This handout is intended as a basic plan submittal under the 2009 International

More information

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

CAD Standards Guideline For Facility Documentation and Construction Projects

CAD Standards Guideline For Facility Documentation and Construction Projects CAD Standards Guideline For Facility Documentation and Construction Projects Page 1 of 12 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4. External References 5.

More information

University of Northern Iowa Design Documents Standards. October 2014

University of Northern Iowa Design Documents Standards. October 2014 University of Northern Iowa Design Documents Standards October 2014 2014 UNI BUILDING AND DESIGN STANDARDS 1.1 CONTRACT DOCUMENT FORMAT 1.1.1 The Electronic Word Programs used for the Project manual shall

More information

COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES

COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES These guidelines are to be used for ALL commercial cooking hoods, ventilation systems and related fire suppression

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE 1.0 GENERAL 1.1 DESCRIPTION This section addresses the procedures to be employed for pipe bursting existing water/sewer pipelines, as identified on the drawings, and replacing with new Restrained Joint

More information

Requirements for Building Application Submission

Requirements for Building Application Submission THE DEVELOPMENT CONTROL AND PLANNING BOARD P O Box 597 Phone: 869 465-2277 Bladen Commercial Development Fax: 869 465-5842 Basseterre, St. Kitts Email: phyplskb@caribsurf.com To: Architects, Designers

More information

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included

More information

CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS

CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS TABLE OF CONTENTS CHAPTER 6 SEWER SYSTEM DESIGN STANDARDS 6.00 Objective Page 1 6.01 Additional Referenced Standards Page 2 6.02 Special Design Problems Page 2 6.03

More information

FY08 SEWER POINT REPAIRS BID TABULATION

FY08 SEWER POINT REPAIRS BID TABULATION 6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "

More information

CITY OF TUCSON, WATER DEPARTMENT DESIGN STANDARD NO. 8-07 WATER PLAN DRAFTING STANDARDS TABLE OF CONTENTS

CITY OF TUCSON, WATER DEPARTMENT DESIGN STANDARD NO. 8-07 WATER PLAN DRAFTING STANDARDS TABLE OF CONTENTS TABLE OF CONTENTS 8-07.0.0... 3 8-07.1.0 GENERAL... 3 1.1 Purpose... 3 1.2 Definitions... 3 1.3 Applicability... 3 8-07.2.0 CONTENT REQUIREMENTS, WATER PLAN SHEETS... 3 2.1 Content Requirements, All Plan

More information

GUIDELINES FOR AUGUST 1995

GUIDELINES FOR AUGUST 1995 GUIDELINES FOR ELECTRICAL ENGINEERING SERVICES AUGUST 1995 PUBLISHED BY: PROFESSIONAL ENGINEERS AND GEOSCIENTISTS OF NEWFOUNDLAND & LABRADOR (PEGNL) P.O. Box 21207, St. John's, NL A1A 5B2 Telephone: (709)

More information

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3

MULTI-FAMILY, COMMERCIAL, INDUSTRIAL, AS GOVERNED BY THE BC BUILDING CODE PART 3 TOWN OF SIDNEY Multi-Family, Commercial, Industrial and Institutional Building Permit Guide The information provided is intended as a guide only and does not replace current bylaws and regulations. Complete

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Civil. Topographical Survey. Design Evaluation. Construction Submittals

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Civil. Topographical Survey. Design Evaluation. Construction Submittals This section applies to design standards and procedures involved in the field location and plotting of all natural objects and surface improvements. This section also includes the requirements for submittal

More information

Residential Building Permit Process

Residential Building Permit Process Residential Building Permit Process Planning and Economic Development Department Development Services Division INTRODUCTION The City of Tulsa is committed to economic development and to being a helpful

More information

CAD Standards Guideline For Facility Documentation and Construction Projects

CAD Standards Guideline For Facility Documentation and Construction Projects CAD Standards Guideline For Facility Documentation and Construction Projects Implemented March 2010 Page 1 of 9 Table of Contents A. Software B. CAD Methods 1. Layer Standards 2. Font 3. Lineweights 4.

More information

SECTION 22 LIGHTNING PROTECTION SYSTEM

SECTION 22 LIGHTNING PROTECTION SYSTEM SECTION 22 LIGHTNING PROTECTION SYSTEM 22.01 SCOPE: A. These Specifications shall form a part of the Contract Documents and shall govern construction work for all buildings to be built or modified for

More information

OIL CONTAINMENT TANK. For SPRING CREEK SUBSTATION TUB PROJECT E-007633

OIL CONTAINMENT TANK. For SPRING CREEK SUBSTATION TUB PROJECT E-007633 SECTION 00 01 01 TITLE PAGE OIL CONTAINMENT TANK For SPRING CREEK SUBSTATION TUB PROJECT E-007633 Prepared and issued by: Tullahoma Utilities Board Tullahoma, TN (Buyer & Engineer) In coordination with:

More information

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714

CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 CITY OF YORBA LINDA P.O. BOX 87014 CALIFORNIA 92885-8714 BUILDING DIVISION (714) 961-7120 Single Family Residential New Construction, Additions & Alterations Submittal Requirements Required agency approvals

More information

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014 Section Subsection Name Date Modification Division 1 All subsections General Provisions

More information

PIPING DRAWINGS BASICS N.P.TODKAR

PIPING DRAWINGS BASICS N.P.TODKAR PIPING DRAWINGS BASICS N.P.TODKAR There are two types of views used in the piping drawings: a) Orthographic- Plans and Elevations b) Pictorial - Isometric Views Piping layout is developed in both plan

More information

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06

Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06 SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

Suffolk County Department of Health Services. Division of Environmental Quality

Suffolk County Department of Health Services. Division of Environmental Quality Suffolk County Department of Health Services Division of Environmental Quality Guidelines For the Construction of Storage Areas for Portable Containers ~~~~ Clare B. Bradley, M.D., M.P.H. Suffolk County

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

Utility Marking Trace Wire Guide

Utility Marking Trace Wire Guide Manufacture product options: Utility Marking Trace Wire Guide The information provided by Copperhead Industries gives you product options to help you choose the correct wire termination points connectors

More information

SECTION 7 UNDERDRAIN SERVICE

SECTION 7 UNDERDRAIN SERVICE SECTION 7 UNDERDRAIN SERVICE ARTICLE I USE OF THE PUBLIC UNDERDRAIN SYSTEM 7.100 The purpose of the District s underdrain system is to provide a method for conveying ground water from around building foundations

More information

Designer Quality Control Plan Guidelines

Designer Quality Control Plan Guidelines Designer Quality Control Plan Guidelines Guidelines, as defined for this manual, are detailed minimum requirement to implement a Designer Quality Control Plan 7/9/2014 Quality Control Plan Acknowledgement

More information

Section 2651 Television Inspection

Section 2651 Television Inspection Section 2651 Television Inspection PART 1: General 1.1 Description Provide all labor, materials, tools, equipment and incidentals as shown, specified, and required to perform television (TV) inspection

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

Reference Guide for Obtaining Permits and Utility Services For New Construction

Reference Guide for Obtaining Permits and Utility Services For New Construction Reference Guide for Obtaining Permits and Utility Services For New Construction (Revised 04-2012) Table of Contents City Offices Telephone Numbers...1 Application for Utilities...2 Building Permits New

More information

WINDOW AND DOOR REPLACEMENT REQUIREMENTS

WINDOW AND DOOR REPLACEMENT REQUIREMENTS WINDOW AND DOOR REPLACEMENT REQUIREMENTS Should you have any questions after reading the following information, please call the Building Inspection Department at 651-439-4439 to discuss the topics of concern.

More information

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION

ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION ATTACHMENT 2: SPECIFICATION FOR SEWER CCTV VIDEO INSPECTION 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, insurance, accessories, tools, transportation, supplies,

More information

Workflow Information Packet Land Development Projects

Workflow Information Packet Land Development Projects Workflow Information Packet Land Development Projects Typical Construction Flow Diagram for Land Development Projects Construction Plans Approved and Construction Permit Issued by Loudoun Water Pre-Construction

More information

Code of Standard Practice for Timber Frame Structures

Code of Standard Practice for Timber Frame Structures TFEC 2-2013 Code of Standard Practice for Timber Frame Structures August 2013 Preface This Code is intended to represent a reasonable consensus of what constitutes ordinary and acceptable practice within

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

Bold items are particular to the City of Euless

Bold items are particular to the City of Euless EULESS FIRE DEPARTMENT FIRE MARSHAL S OFFICE INFORMATION LINE: Revised 2/12 Fire Chief Wes Rhodes Fire Marshal Paul Smith EFD-FMO 3-2 2009 International Fire & Building Code as Amended NFPA Standards Adopted

More information

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,

More information

Sewer Service Line Installation & Inspection Process

Sewer Service Line Installation & Inspection Process Sewer Service Line Installation & Inspection Process March 2016 White House Utility District Details for Gravity Sewer Service Connections to Main-Line Stub-outs and connections to Water Service Stub-outs

More information

MINIMUM STANDARDS OF ACCURACY, CONTENT AND CERTIFICATION FOR SURVEYS AND MAPS ARTICLE I. TYPES OF SURVEYS

MINIMUM STANDARDS OF ACCURACY, CONTENT AND CERTIFICATION FOR SURVEYS AND MAPS ARTICLE I. TYPES OF SURVEYS MINIMUM STANDARDS OF ACCURACY, CONTENT AND CERTIFICATION FOR SURVEYS AND MAPS ARTICLE I. TYPES OF SURVEYS Current with material published in Conn.L.J. through 5/13/08 Sec. 20-300b-1. General There are

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

PART 1 GENERAL 1.1 SECTION INCLUDES

PART 1 GENERAL 1.1 SECTION INCLUDES J-1 Section 09110 Long Form Specification INTERIOR METAL STUD FRAMING This section includes lightweight, usually 0.036 inch (0.9 mm) thick or lighter, non-axial load bearing metal stud framing including

More information

SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT

SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT SPECIFICATIONS FOR THE INSTALLATION OF FIRE ALARM SYSTEMS, SPRINKLER SYSTEMS, AND MASTER BOXES IN THE POQUONNOCK BRIDGE FIRE DISTRICT The purpose of these specifications is to insure that there are minimum

More information

AIRPORT SECURITY FENCING. A. American Society for Testing and Materials (ASTM):

AIRPORT SECURITY FENCING. A. American Society for Testing and Materials (ASTM): SECTION 02832 AIRPORT SECURITY FENCING PART 1-GENERAL 1.1 SUMMARY A. Section includes: Construct airport security chain-link fence and gate at specified areas and conforming lines, grades, details indicated

More information

SUMMIT TOWNSHIP SIGN PERMIT PROCESS

SUMMIT TOWNSHIP SIGN PERMIT PROCESS SUMMIT TOWNSHIP SIGN PERMIT PROCESS How to Apply For a Sign Permit The Zoning Department is providing the following information to aid applicants wishing to apply for a permanent or temporary sign permit.

More information

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS SECTION 27 05 36 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS PART 1 GENERAL 1.01 DESCRIPTION A. The work covered by this section of the Specifications includes all labor necessary to perform and complete such

More information

CHAPTER 7 BUILDING ARTICLE 7-1 UNIFORM CODES 1. 7-1-1 Adoption. Board of Appeals. Annual Review

CHAPTER 7 BUILDING ARTICLE 7-1 UNIFORM CODES 1. 7-1-1 Adoption. Board of Appeals. Annual Review CHAPTER 7 BUILDING ARTICLE 7-1 UNIFORM CODES 1 7-1-1 Adoption 7-1-2 Board of Appeals 7-1-3 Annual Review Section 7-1-1 Adoption A. Those certain documents known as the 1997 Uniform Building Code, Volumes

More information

GOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline

GOUVEIA ENGINEERING. Pre-Bid Conference Meeting Minutes. City of Los Banos. Henry Miller Area Storm Drain and L Street Waterline GOUVEIA ENGINEERING Pre-Bid Conference Meeting Minutes City of Los Banos Henry Miller Area Storm Drain and L Street Waterline Conference held at Intersection of West I Street and L Street, in Los Banos

More information

MANUAL FOR THE DESIGN OF WATER AND SEWER LINES

MANUAL FOR THE DESIGN OF WATER AND SEWER LINES SECTION I: GENERAL PROVISIONS 1.01 This manual is intended to aid and assist engineers in the layout and design of sanitary sewers and water lines to definite standards and to obtain uniformity in the

More information

Building Permit Application

Building Permit Application Building Permit Application Administrative Use Only PARENT PERMIT NUMBER (Required if part of another project) PERMITTEE: PERMITTEE ADDRESS: E-MAIL ADDRESS: ARCHITECT/ENGINEER: PHONE: PHONE: ARCHITECT/ENGINEER

More information

CHAPTER 67.2 RESIDENTIAL BUILDING CODE

CHAPTER 67.2 RESIDENTIAL BUILDING CODE CHAPTER 67.2 RESIDENTIAL BUILDING CODE 1. APPLICABILITY. This Chapter shall have, along with the Code adopted hereby, the scope and applicability set out in said code except as modified by the provisions

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by

More information

EXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS

EXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS EXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS 1. SCOPE 1.1 This specification covers the type, physical properties and dimensions of Expanded Polystyrene Insulation Board intended for use

More information