Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia
|
|
- Junior Stephens
- 7 years ago
- Views:
Transcription
1 The Southern African Institute of Mining and Metallurgy Slope Stability 2015 B.J. Hutchison, S. Naude, and J. Howarth Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia B.J. Hutchison*, S. Naude, and J. Howarth *Hillgrove Resources IDS Maptek Hillgrove Resources operates the Kanmantoo Copper Mine on the eastern side of the Adelaide Hills in South Australia. Three open pits were in operation when it was recognized that the south-eastern wall of the Nugent Pit was susceptible to a flexural toppling failure. Mining personnel were able to mine for five months without disruption as flexural toppling reverse scarps slowly developed. Slope monitoring during that time comprised surface extensometers and prism readings. On 5 October 2014 a ramp blast located at the base of the 45 m high slope caused a sudden jolt of movement, resulting in an immediate requirement to alter the pit design and the monitoring programme. These alterations allowed for the continued mining of the deposit as the flexural toppling failure developed and finally collapsed. This paper describes the failure mode and the management/monitoring regime adopted to continue mining with minimal disruption and ore loss. Initial monitoring was with crack extensometers and prisms; supplemented by an I-Site 8820 laser scanner trial being undertaken at the time. Following the blast, the main thrust of the management strategy to contend with the potential failure was the deployment of an IBIS slope stability radar for providing alerts in the event of progressive movements leading to slope failure. The use of an inverse velocity plot based on radar data allowed for the prediction of the final collapse from two days out to within two hours. Early detection of slope movements and precise identification of the onset of the failure as a result of the radar allowed mining personnel to plan and implement appropriate actions with sufficient notice to minimize the effect of the failure on personnel safety and mine productivity. Introduction The Kanmantoo copper deposits have been intermittently mined since the mid-1800s, when Cornish miners first exploited the oxidized copper lenses in shallow workings. In the 1970s the Kanmantoo open pit was developed to a depth of 115 m before a fall in the copper price shut operations. Hillgrove Resources reopened the mine in 2011; initially developing the Spitfire Pit and then expanding the original Kanmantoo pit to what was called the Kavanagh Pit (Figure 1). These two pits were mined in a similar massive rock mass domain (geotechnical domain GDM1) that allowed for three relatively steep walls (north, east, and south) and a moderately dipping west wall; the latter being susceptible to planar and wedge crest failures on a bench scale. 81
2 Slope Stability 2015 Figure 1 Kanmantoo mine site plan As the Kavanagh Pit was to reach the planned depth of 230 m towards the third quarter of 2014, two smaller satellite pits were started in early These two pits, called the Emily Star and Nugent pits, were to provide ore until a new life-of-mine cutback of the main Kavanagh deposit (referred to as the Giant Pit) was sufficiently developed to supply all the ore for processing. These two satellite pits are both located partially or fully outside the massive rock mass regime (GDM1) of the original pits (Figure 2 and Table I). It was on the eastern side of the Nugent Pit in GDM2 that a 40 m high toppling failure occurred in more ductile rocks. 82
3 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia Figure 2 Kanmantoo mine site cross-sections 83
4 Slope Stability 2015 Table I. Geotechnical domains The potential for a toppling failure was recognized several months before it occurred. Conventional surface extensometers and prisms were initially used to monitor the slope. A Maptek I-Site 8820 laser scanner (and accompanying Sentry software) had been deployed in the pit as a research project and also provided intermittent coverage of the slope. Following a toe blast that caused up to 58 mm of movement at the prisms on the crest, an IBIS slope stability radar was deployed to provide critical monitoring capabilities to allow the management of continued mining directly under the potential failure. This paper describes the toppling failure characteristics, the associated monitoring results, and the management strategies adopted. Nugent Pit design stages and rock conditions The Nugent Pit design was planned with an initial mini-pit phase while awaiting regulatory approval to expand to the east to allow for a cutback to deepen the pit to its final depth (Figure 3). The eastern side of the Nugent Pit is located in a highly foliated, relatively weak biotite schist rock mass overlain by a stiff red clay unit up to 15 m in depth, which peters out to the south. As most of the exploration for this pit was carried out with reverse circulation drilling, very little geotechnical information was available. It was not until the first phase of mining when the pit was excavated m below the eastern crest that the true nature of the biotite schist was exposed. Although the rock mass did not feature the numerous foliation plane shears described in the Savage River flexural toppling failures (Hutchison et al., 2000) it was recognized that flexural toppling was the most likely failure mode that could develop, due to the easterly dip of the foliation into the wall. The Savage River experiences showed that flexural toppling was generally a very slowdeveloping phenomenon taking many months before ultimate collapse of a slope. Such developments were easily 84
5 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia managed by crest extensometers and prism monitoring. At Savage River the final delays to mining were restricted to a week or so when the final collapse and re-establishment of ramps occurred. The Savage River slopes were managed, using horizontal drain holes, up to heights of 90 m without a final collapse of the walls, although these occurred on intermediate slope angles in the order of 37. Figure 3 Nugent Pit east and southeast wall sections Based on the new Nugent rock exposures, the relatively short pit life, a regulatory need to backfill the final pit, and senior staff experiences with flexural toppling failures, the decision was made to continue with an aggressive design in the new cutback once regulatory approvals were obtained. The intent was to get in and out as quickly as possible. Still somewhat restricted by regulatory boundaries and weak rock conditions, the eastern wall slope design was altered to comprise a 50 continuous slope broken up by the main ramp (Figure 3) such that the maximum intermittent 85
6 Slope Stability 2015 slope height was restricted to 42 m. The new design was to be transitioned from 50 to 54 into the southern wall, over heights of 42 m to 70 m. The batter configuration on the south wall comprised 24 m high 60 batters with 8 m wide berms. The overall angle of the transition slope where the toppling event occurred was 52. The transitional SE wall was mainly located in the GD3 regime of ductile biotite schist. Further to the south was the contact to the massive rock with the GDM1 regime. The topple event was restricted to GDM2. It was also known that the groundwater table was at least 70 m in depth at the southern end of the pit. Cutback mining and subsequent wall movements In July 2014 regulatory approvals were obtained allowing the commencement of the new eastern wall cutback, following the continuous 50 slope design. As the cutback progressed, cracking behind the east wall crest was noted but this was not considered to be anything out of the ordinary in a stiff clay scenario. At the top of the SE transition wall some crest and upper batter dilation and cracking had previously been observed. This was being monitored with crack extensometers, prisms, and the I-Site laser scanner (a more detailed description can be found in Hutchison and Howarth, 2015). The laser scan data indicated that the main area of dilation was restricted to an area within m of the pit crest; where up to 60 mm of movement had occurred between zones 1 and 2 in the three months between June and August 2014 (Figure 4). (Green: Data not available) Figure 4 I-Site laser scanner movements (6 June to 7 September 2014) Eventually, minor reverse scarp cracking began to develop in the stiff clays on the east wall batter slopes below the crest. These cracks were the first indication of flexural toppling, with the prism and extensometer data indicating between 10 and 60 mm of total movement. On 5 October the final lower ramp blast was fired to get the new ramp back down onto the floor of the first phase of mining. This blast severely jolted the SE wall; with up to 58 mm of additional movement occurring at the crest, based on prism monitoring (Figure 5). 86
7 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia Figure 5 SE wall movements post ramp blast The laser scanner data also confirmed a similar amount of movement, with zone 1 movement increasing up to a total average of just over 105 mm (Figure 6). The scanner heat map actually showed the beginnings of the toppling event, with both the upper and lower areas moving outwards much more than the central area. Figure 6 Laser scanner data to 8 October 2015 Consideration was given to either cutting back the slope or continuing to carefully mine out the blasted material while monitoring movements. Due to the proximity of the cracking behind the crest to a public road, a third option of establishing a stabilization berm and adopting a three-stage mining strategy was chosen. The three-stage design is shown in Figure 7. After establishing the stabilization berm, the east wall ramp was to be switch backed to the northern end of the pit from where the complete floor would be stripped out by a ramp to the south (Figure 7A). Once completed, the southern end of the pit was to be backfilled, creating a down ramp system to the new floor (Figure 7B). This was to be followed by mining of the northern end of the pit (Figure 7C), taking out the northern ramp. The establishment of the stabilization berm and switchbacked ramp can be seen in Figure 8. 87
8 Slope Stability 2015 Figure 7 Three-stage mining sequence Figure 8 Stabilization berm 88
9 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia Slope monitoring and flexural toppling To enable safe mining under the SE wall, an IBIS M (Mk 2) radar was mobilized to site in late October. It was deployed in a position directly opposite the SE wall (Figure 9) to carry out critical alarm monitoring. In this position, approximately 165 m across the pit, the radar began scanning a 250 m length of wall every 5 minutes. (A subsequent upgrade to the hardware and software has decreased the scanning frequency to 3 minutes.) The radar data was sent to the IBIS Guardian software via a Telstra 3G link, allowing analyses and alarm settings to be undertaken. The pixel size of the radar scans was 0.75 m 1.5 m. Figure 9 IBIS M slope stability radar The I-Site laser scanner had been intermittently monitoring the pit from a position at the far north of pit. Following the blasting event of 5 October the laser scanner was moved to the NW wall about 30 m from the radar location. The original resolution (R8) of the scan had a pixel size of 0.5 m 0.5 m and a run time of 44 minutes. After being moved, the scanner was set at a lower (R2) resolution but at a faster scan time of 4 minutes. The pixel size reverted to approximately 1.7 m 1.7 m. Due to the lack of direct communication from the geotechnical office to the scanner, the laser scanner could not be used as a front-line critical monitoring device. It did, however, provide insight into the velocity alarm levels applied to the radar and was used to verify radar detected movements. Throughout the first three weeks of November both the radar and laser scanner detected movements of less than 0.1 mm/d diffused over the SE wall. The movements began concentrating into two main areas (Figure 10). The upper and fastest moving area (0.7 mm/d) was at and just below the crest; where the 58 mm of blast-related prism movement occurred. The second area of concentrated movement (0.4 mm/d) was located near mid-slope but with an elongated shape trending uphill to the south. 89
10 Slope Stability 2015 Figure 10 Radar displacement The elongated shape was recognized to be parallel to the trace of the steeply dipping foliation (70 east). A few days later a reverse scarp crack was identified on the slope, and when surveyed it plotted just above the mid-level movement area, as can be seen in Figure 10. The crack proved to be difficult to distinguish unless the sunlight was oriented such that the shadows delineated it. The prism surveys showed the overall crest movement of the SE wall up to 22 November 2014 to be in the order of 335 mm (Figure 11). The mid-level movement was approximately 100 mm. 90
11 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia 22 nd November Rain Event 5 th October Ramp Blast Figure 11 Prism movements On 22 November there was a 7 mm rainfall event over a 9-hour period, which triggered accelerating slope movements see Figure 10 (radar data) and Figure 11 (prism data), leading up to final collapse of the wall one week later on 29 November (Figure 12 and Figure 13). The flexural toppling mode is very evident in the photograph in Figure 13. The total crest movement just prior to the failure, as measured by the prisms, was 450 mm. The radar and laser scanner movements were significantly less, but they had base reading dates from late October and early November in comparison to early July for the prisms. Figure 12 SE wall collapse 91
12 Slope Stability 2015 Figure 13 Toppling structures at toe of failure Of considerable interest was the monitoring of surface movements with the progressive development of the flexural toppling. Both the radar (Figure 14) and the laser scan (Figure 15) data showed distinct bands of movement that correlated with the reverse scarp locations. The reverse scarp locations in the lower image of Figure 15 were surveyed from the laser scanner image using Maptek I-Site Studio software. 92
13 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia Figure 14 Spatial distribution of radar displacements 93
14 Slope Stability 2015 Figure 15 Spatial distribution of laser scanner displacements 94
15 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia Radar critical monitoring The critical monitoring of the slope by the IBIS slope stability radar was based on two levels of velocity alarms for preselected areas; a geotechnical alarm and a critical alarm. The geotechnical alarm was set at 1 mm/h and the critical alarm at 2 mm/h. When these levels were reached, s and SMS messages were automatically sent to the geotechnical staff, senior mining personnel, pit supervisors, and leading hands. For a geotechnical alarm, the trigger action response plan (TARP) required crews to stand off the SE wall and await an assessment by the geotechnical staff. For a critical alarm, the pit was to be immediately evacuated in accordance with the emergency egress plan developed for that pit. As can been seen in Figure 16, the geotechnical alarms began on the night of 27 November. The mine supervisor on duty and the geotechnician on call assessed that the blast-hole drilling being carried out in the centre and north of the pit could proceed through the night. Figure 16 Velocity plot This assessment was also based on the use of the inverse velocity tool in the Guardian software package. Late in the afternoon of 27 November, the geotechnical staff started seeing the first indications of a predicted failure late on 29 November. By the early hours of 28 November the inverse velocity plot (Figure 17) was consistently indicating that the failure would occur between 21:00 22:00 hours on 29 November. Figure 17 Inverse velocity plot 95
16 Slope Stability 2015 Late in the morning of 28 November the decision was made to stop all activity in the Nugent Pit and to fully inform the mining workforce of the situation. Although the workforce had been regularly informed of the minor amounts of movement, they had not previously been exposed to large wall failures. With very little evidence of large-scale movements on the slope itself, there was considerable scepticism from the workforce about the failure prediction. The wall failed at 20:00 hours on Saturday 29 November, just at sunset. Unfortunately, a member of the geotechnical staff was just returning to site to film the wall when the failure occurred and no-one actually observed the failure. The size and runout of the failure was as had been predicted in the workforce presentation. The successful alarming and failure time prediction greatly enhanced appreciation of the geotechnical staff s efforts at providing a safe workplace. The I-Site laser scanner also picked up the failure and subsequent analysis indicated that it would have been capable of providing similar critical alarming capabilities in this instance. For more information on the laser capabilities, refer to Hutchison and Howarth (2015). The laser scan data was used to estimate the volume of the slip as t, using the I- Site Studio software. Post-failure mining and assessment The failure continued to be monitored by the radar, which allowed drilling to recommence within 48 hours. Other than fine scree rilling, no medium- or large-scale movement occurred on the failed slope, even when three subsequent blasts occurred on the pit floor within three weeks of the failure. Mining directly under the failure was completed in March 2015 (Figure 18). The change back into the geotechnical domain GDM1 allowed the 50 m high-near vertical wall to be mined directly in front of the topple. The final 22 m was carried out in two goodbye cuts, carefully monitored by the IBIS radar. Figure 18 Post-failure mining A review of the failure and the monitoring concluded that: The potential for a toppling failure in the GDM2 geotechnical domain of the east wall of Nugent Pit was recognized several months prior to the failure The continuous 50 batter slope design, with a maximum height of 40 m, was successful at preventing toppling failures on the east wall The toppling failure occurred on the transitional SE wall, where the slope varied between 50 and 55, over heights of m. 96
17 Management of a toppling failure wall collapse at the Kanmantoo Copper Mine in South Australia The initial movements were instigated by a blast of a ramp shot on 5 October, which toed out at 50 m below the crest in the centre of the topple area Following the blast, a stabilization berm was placed on blasted ground such that only a 40 m high wall was left exposed Movements continued at a rate of up to 4 mm/d until the stability berm was completed, and then gradually slowed to approximately 1 mm/d until 21 November A 7 mm, nine-hour duration rain event on 22 November instigated accelerating movements, before the final collapse on 29 November The final topple occurred above the stabilization berm, with some material rilling down on the southern end to the working floor 19 m below the top of the stabilization berm. Material reached a distance of 28 m from the toe of the slope on that working floor The groundwater table was well below the failure extent, so groundwater was not a factor In the early stages of the wall movement, prisms and surface extensometers were quite adequate for monitoring movements An IBIS slope stability radar was used to monitor the wall during the four weeks prior to the final collapse, and it successfully provided critical alarms and predicted the time of failure within two hours using an inverse velocity prediction tool A Maptek I-Site 8820 laser scanner had been deployed as a research development project and the data collected provided complementary information that was also used in managing the slope failure Average velocity alarm levels of 1 and 2 mm/s were set for establishing geotechnical (assessment) and critical (evacuation) alarms in the ductile rock conditions. Subsequent analysis indicated that 1.5 and 3 mm/s levels would have been adequate and would have reduced the number of alarms prior to the actual collapse The inverse velocity tool in the IBIS software successfully and continually predicted the failure to within two hours from 38 hours prior to the actual event. The pit was closed to all personnel 32 hours prior to the event. Although the slope did not exhibit classical extensive reverse scarp development (such as the 1 m high scarps at Savage River), the radar and laser scanner data and observations of the slope did confirm that the failure mode was flexural toppling, with reverse scarp heights in the order of mm The final 40 m high failure involved 64 kt of rock, most of which was retained on a stabilization berm, with some material rilling out 28 m onto the lower working floor Although the stabilization berm did not prevent the wall failure, it did restrict the extent of the failure and allowed mining to continue well below the toe of the failure. It also prevented the head scarp from potentially extending outside the mining lease. Summary The Kanmantoo Copper Mine experienced a 64 kt wall collapse in the Nugent Pit that was initially monitored by conventional extensometers and prisms. A Maptek I-Site laser scanner was also used on an intermittent basis. Following a blast at the toe of the slope, which caused up to 58 mm of movement, an IBIS slope stability radar was deployed to provide critical alarm monitoring capability to safely manage the slope until and after the eventual collapse of the wall. The inverse velocity capabilities of the radar provided consistent predictions of the failure time within two hours of the actual time from up to 38 hours before the event. References Hutchison, B.J., Dugan K., and Coulthard, M.A Analysis of flexural toppling at Australian Bulk Minerals, Savage River Mine. Proceedings of GeoEng2000, Melbourne, Australia, November Hutchison, B.J. and Howarth, J Kanmantoo Mine - Rockfall and rock wall failures - I-Site 8820 laser scanning applications. Proceedings of Slope Stability 2015, Cape Town, South Africa, October Southern African Institute of Mining and Metallurgy, Johannesburg. 97
18 Slope Stability 2015 The Author Bruce Hutchison, Principal Engineer, Hillgrove Resources Bruce has 40 years of experience in the civil and mining engineering industries. His civil experience has been gained worldwide in Canada, China, the Philippines and Australia where he specialized in hydro-electrical and tunnelling investigations and construction. In the mining industry Bruce has been involved in open pit production specializing in the geotechnical fields of slope stability, slope monitoring and in mine planning; and in civil engineering related projects such as tailings dams, river crossings and haul roads. He has been involved with acid mine drainage rehabilitation and dump designs. Bruce was the Senior Geotechnical/Principal Engineer at Grange Resources Savage River Mine for 15 years before joining Hillgrove Resources in April His mining career has also involved in operations and consulting on mining projects in Western Australia, Queensland and Mongolia. 98
THE TRANSITION FROM OPEN PIT TO UNDERGROUND MINING: AN UNUSUAL SLOPE FAILURE MECHANISM AT PALABORA
THE TRANSITION FROM OPEN PIT TO UNDERGROUND MINING: AN UNUSUAL SLOPE FAILURE MECHANISM AT PALABORA Richard K. Brummer*, Hao Li* & Allan Moss *Itasca Consulting Canada Inc., Rio Tinto Limited ABSTRACT At
More informationALCYONE REPORTS JORC SILVER RESOURCES
ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR
More informationNuevas tendencias de la Minería Subterránea profunda Planeación, operación y estabilización del macizo rocoso
Nuevas tendencias de la Minería Subterránea profunda Planeación, operación y estabilización del macizo rocoso By Ernesto Villaescusa, PhD Chair in Rock Mechanics WA School of Mines, CRC Mining & Curtin
More information3D Laser Scanning Technology. Rugged hardware and powerful software combined with streamlined survey workflow
3D Laser Scanning Technology Rugged hardware and powerful software combined with streamlined survey workflow Maptek specialises in the research, development and application of 3D laser scanning technology.
More informationSettlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains
Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced
More informationPekka Bergström Senior Geotechnical Consultant
Pekka Bergström Senior Geotechnical Consultant Education GradCert.Eng in Mine Design & Planning, West Australian School of Mines, Australia MSc in Geology and Mineralogy, Oulu University, Finland Diploma
More informationBackfill for Bench Stoping Operations
Backfill for Bench Stoping Operations E. Villaescusa Professor of Mining Geomechanics, Western Australian School of Mines K. Kuganathan Senior Backfill Research Engineer, Mount Isa Mines ABSTRACT This
More informationSLOPE MONITORING STRATEGY AT PPRUST OPEN PIT OPERATION. M.J. Little Rock Engineering Department, PPRust, Limpopo, South Africa
SLOPE MONITORING STRATEGY AT PPRUST OPEN PIT OPERATION M.J. Little Rock Engineering Department, PPRust, Limpopo, South Africa ABSTRACT Potgietersrust Platinums Ltd (PPRust) is Anglo Platinum s only open
More informationANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY
ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY ANNEX D1: BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN DRA FOR SAFETY D1-1 ANNEX D1 BASIC CONSIDERATIONS
More information3D Modelling & Mine Planning Software. Comprehensive tools provide a competitive advantage from exploration to rehabilitation.
3D Modelling & Mine Planning Software Comprehensive tools provide a competitive advantage from exploration to rehabilitation. Maptek Vulcan, the world s premier 3D mining software solution, allows users
More informationI-SiTE - Laser Scanning Revolutionises Site Survey
I-SiTE - Laser Scanning Revolutionises Site Survey I.K. Kapageridis Maptek/KRJA Systems Ltd, United Kingdom ABSTRACT: MAPTEK's revolutionary I-SiTE 3D Laser Imaging System, presented in this paper, is
More informationExploration. Exploration methods
Exploration Activities related to establishing a mineral deposit through geological, geophysical and geochemical methods. It is preceded by Prospecting and followed by Planning & Development. Geological
More informationSafety Applications for GPS Systems in the Mining Industry
Safety Applications for GPS Systems in the Mining Industry Introduction The Global Positioning System (GPS) has been available for civilian use for more than 20 years now. It has found many navigation,
More informationCHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION
CHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION 9.1 Conclusions Based on the stability cross-sections down the SE flank of Snodgrass Mountain, most landslides on low- to moderate-gradient slopes have
More informationWorked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites
Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites Worked example to accompany MBIE Guidance on the seismic design of retaining
More informationFor personal use only
Investigator Resources Limited Date: 7 th February 2012 up to 2.25% Ag at the new Paris prospect in South Australia First assays received for new drilling on Paris Line 7 with all three holes assayed returning
More informationWhich month has larger and smaller day time?
ACTIVITY-1 Which month has larger and smaller day time? Problem: Which month has larger and smaller day time? Aim: Finding out which month has larger and smaller duration of day in the Year 2006. Format
More informationHOMEOWNER S GUIDE. to LANDSLIDES. and MITIGATION RECOGNITION, PREVENTION, CONTROL, Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J.
HOMEOWNER S GUIDE to LANDSLIDES RECOGNITION, PREVENTION, CONTROL, and MITIGATION Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J. Andrew Federal Emergency Management Agency Region 10 If you are
More informationRESULTS FROM A SIMPLE INFRARED CLOUD DETECTOR
RESULTS FROM A SIMPLE INFRARED CLOUD DETECTOR A. Maghrabi 1 and R. Clay 2 1 Institute of Astronomical and Geophysical Research, King Abdulaziz City For Science and Technology, P.O. Box 6086 Riyadh 11442,
More informationWILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10
WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta
More informationDAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015
DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015 CONTENT GLOBAL OPERATIONS WHERE WE VE COME FROM REVERSING THE TREND TRANSFORMATION
More informationCOVER SYSTEMS FOR MINE CLOSURE AND REHABILITATION TWO CASE STUDIES
COVER SYSTEMS FOR MINE CLOSURE AND REHABILITATION TWO CASE STUDIES Jason Song 1 and Mike O Kane 2 1 O Kane Consultants Inc., 200 1121 Centre Street N.W., Calgary, AB T2E 7K6, Canada Email: jsong@okc-sk.com
More informationAPPLICATION OF OPENRISK AT OPEN CAST COAL MINES
APPLICATION OF OPENRISK AT OPEN CAST COAL MINES * ** B.J. Madden *** I. Canbulat * Anglo Technical Division ** G-Ro Geotechnical Services (Pty) Ltd *** Groundwork Consulting (Pty) Ltd ABSTRACT OpenRisk,
More information1 2 A very short description of the functional center network: regarding the Hydraulic and Hydrogeological risk, the national alert system is ensured by the National Civil Protection Department (DPCN),
More informationPermits to Dig / Permits to Excavate / Permits to work near underground services
Permits to Dig / Permits to Excavate / Permits to work near underground services Aim and purpose The aim of this guidance is to identify what should be included in a permit to excavate / dig and additional
More informationGeotechnical Management. An Overview on typical system elements
Geotechnical Management An Overview on typical system elements Purpose of presentation Overview of the elements of a robust geotechnical system for an Open Cut to allow you to ask questions at this seminar
More informationHow To Understand General Relativity
Chapter S3 Spacetime and Gravity What are the major ideas of special relativity? Spacetime Special relativity showed that space and time are not absolute Instead they are inextricably linked in a four-dimensional
More informationCat Detect. for Surface Mining Applications
Cat Detect for Surface Mining Applications Enhance Your Site s Safety through Increased Operator Awareness Configurable to suit your operation s needs, Cat MineStar System is the industry s broadest suite
More informationCOASTAL DAMAGE INSPECTION SOUTHWEST VITI LEVU, FIJI AFTER CYCLONE SINA
COASTAL DAMAGE INSPECTION SOUTHWEST VITI LEVU, FIJI AFTER CYCLONE SINA Brendan J. Holden SOPAC Technical Secretariat July 1992 SOPAC Technical Report 148 Prepared for: South Pacific Applied Geoscience
More informationEngineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1)
Engineering Geological Asset Management for Large Dams Yasuhito SASAKI (1) (1) Geology Research Team, Public Works Research Institute, Japan E-mail:ya-sasa@pwri.go.jp Abstract Comprehensive inspection
More informationThe successful integration of 3D seismic into the mining process: Practical examples from Bowen Basin underground coal mines
Geophysics 165 Troy Peters The successful integration of 3D seismic into the mining process: Practical examples from Bowen Basin underground coal mines This paper discusses how mine staff from a number
More information3D Laser Scanner. Extra long range laser scanner combined with a high resolution digital panoramic camera
3D Laser Scanner Fast, PORTABLE, accurate Extra long range laser scanner combined with a high resolution digital panoramic camera INTRODUCING THE MAPTEK I-SITE 8800 LASER SCANNER > From Pit to Mine Model
More informationMine Wide Risk Assessment What is the State of your Arteries. L.Human, J Doolan and L Potts Xstrata Zinc
Mine Wide Risk Assessment What is the State of your Arteries L.Human, J Doolan and L Potts Xstrata Zinc Abstract A geotechnical mine wide risk management approach is presented for the systematic inspection,
More informationEstablishing the feasibility of your proposed mining venture
RUPPRECHT, S. Establishing the feasibility of your proposed mining venture. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy, 2004. Establishing
More informationThe correct answers are given below. Some talking points have been added for the teachers use.
Natural Resources Canada 2011: Lesson Plan Grades 11 and 12 Landslide activity 5b: Landslides in Canada quiz Description: This is an independent study activity for grades 11 and 12. Students will read
More informationDe Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value
De Grey Mining Ltd ASX RELEASE 5 July 2016 ASX Code DEG ABN 65 094 206 292 Wingina Deeps Drilling Commenced (Turner River Project) Highlights Diamond drilling programme of approximately 1,500m has COMPANY
More informationMETHODOLOGY FOR LANDSLIDE SUSCEPTIBILITY AND HAZARD MAPPING USING GIS AND SDI
The 8th International Conference on Geo-information for Disaster Management Intelligent Systems for Crisis Management METHODOLOGY FOR LANDSLIDE SUSCEPTIBILITY AND HAZARD MAPPING USING GIS AND SDI T. Fernández
More informationBruce B. Weiner, Walther W. Tscharnuter, David Fairhurst Brookhaven Instruments Corporation Holtsville, NY 11742 US
Zeta Potential: A New Approach by Bruce B. Weiner, Walther W. Tscharnuter, David Fairhurst Brookhaven Instruments Corporation Holtsville, NY 11742 US A paper presented at the Canadian Mineral Analysts
More informationINTERPRETATION ADDENDUM CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION
INTERPRETATION ADDENDUM FOR CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION ON THE SAN BERNARDO PROJECT EL GOCHICO GRID Approximate Location:
More informationInternational Year of Light 2015 Tech-Talks BREGENZ: Mehmet Arik Well-Being in Office Applications Light Measurement & Quality Parameters
www.led-professional.com ISSN 1993-890X Trends & Technologies for Future Lighting Solutions ReviewJan/Feb 2015 Issue LpR 47 International Year of Light 2015 Tech-Talks BREGENZ: Mehmet Arik Well-Being in
More informationMap Patterns and Finding the Strike and Dip from a Mapped Outcrop of a Planar Surface
Map Patterns and Finding the Strike and Dip from a Mapped Outcrop of a Planar Surface Topographic maps represent the complex curves of earth s surface with contour lines that represent the intersection
More informationAn Example of Using ReSSA in Complex Geometry of Reinforced Tiered Slope Introduction Background
An Example of Using ReSSA in Complex Geometry of Reinforced Tiered Slope By Dov Leshchinsky Copyright 2001, ADAMA Engineering, Inc. All Rights Reserved Introduction Geosynthetic reinforced soil structures
More informationBasements and Deep Building Construction Policy 2014
Basements and Deep Building Construction Policy 2014 APPROVAL Council / CEO 27 October 2014 VERSION NO: Version 1.0 TRIM REF: 14/67838 REVIEW 30/10/2019 RESPONSIBLE EXECUTIVE General Manager City Assets
More informationResearch question: How does the velocity of the balloon depend on how much air is pumped into the balloon?
Katie Chang 3A For this balloon rocket experiment, we learned how to plan a controlled experiment that also deepened our understanding of the concepts of acceleration and force on an object. My partner
More informationQueensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District
ASX Release 12 October 2012 Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District Total mineral resource at Duck Creek Project area of 960,000t @ 1.47% Cu (0.2%
More informationModule 7 (Lecture 24 to 28) RETAINING WALLS
Module 7 (Lecture 24 to 28) RETAINING WALLS Topics 24.1 INTRODUCTION 24.2 GRAVITY AND CANTILEVER WALLS 24.3 PROPORTIONING RETAINING WALLS 24.4 APPLICATION OF LATERAL EARTH PRESSURE THEORIES TO DESIGN 24.5
More informationAP Physics C. Oscillations/SHM Review Packet
AP Physics C Oscillations/SHM Review Packet 1. A 0.5 kg mass on a spring has a displacement as a function of time given by the equation x(t) = 0.8Cos(πt). Find the following: a. The time for one complete
More informationValidation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2
Validation of Cable Bolt Support Design in Weak Rock Using SMART Instruments and Phase 2 W.F. Bawden, Chair Lassonde Mineral Engineering Program, U. of Toronto, Canada J.D. Tod, Senior Engineer, Mine Design
More informationHow To Use Leica Dozernav Plus
Leica DozerNav Plus High precision GPS dozer guidance More than a guidance system Leica DozerNav Plus > helping you drive productivity with ease Leica DozerNav Plus the benefits at a glance Real-time feedback
More informationAt the completion of this guide you should be comfortable with the following:
This guide provides instructions and best practices for deployment of the Yealink W52P IP DECT phones and repeaters RT10, which is intended for qualified technicians (or administrator) who will deploy
More informationSeismic Design and Performance Criteria for Large Storage Dams
Seismic Design and Performance Criteria for Large Storage Dams Dr. Martin Wieland Chairman, ICOLD Committee on Seismic Aspects of Dam Design Poyry Switzerland Ltd., Zurich, Switzerland Integral Dam Safety
More informationAPPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND TELECOMMUNICATION CABLES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
More informationSolid shape molding is not desired in injection molding due to following reasons.
PLASTICS PART DESIGN and MOULDABILITY Injection molding is popular manufacturing method because of its high-speed production capability. Performance of plastics part is limited by its properties which
More informationCASE STUDY LANDSLIDE MONITORING
Introduction Monitoring of terrain movements (unstable slopes, landslides, glaciers, ) is an increasingly important task for today s geotechnical people asked to prevent or forecast natural disaster that
More informationOwned and operated by Ontario farmers 1-888-443-2760
Thank you for your interest in the Hay Solar free* farm building program. My name is James Mann and I am the owner and president of the Hay Solar company. My family has been involved in farming for 50
More informationLife after 30! Innovative investigation and repair of the Overvaal railway tunnel. r a i l w a y s a n d h a r b o u r s PROJECT TEAM
Text Hannes Gräbe Spoornet (Technology Management) hannesg@spoornet.co.za r a i l w a y s a n d h a r b o u r s Life after 30! Innovative investigation and repair of the Overvaal railway tunnel 1 PROJECT
More informationThere is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.
Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,
More informationQuarterly Report Highlights. Ulysses Gold Project, Western Australia. Viking Gold Project, Western Australia
ASX Announcement Quarterly Activities Report For the Quarter Ended 31 December 2015 29 January 2016 Genesis Minerals Limited ASX Code: GMD Issued Capital 446 million shares 27.2 million options Current
More informationMagnitude 7.2 GUERRERO, MEXICO
A powerful magnitude-7.2 earthquake shook central and southern Mexico on Friday. The earthquake occurred at a depth of 24 km (15 miles). Its epicenter was in the western state of Guerrero, near the seaside
More informationUpdate on Heap Leach potential of the Murchison gold project
3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and
More informationEncoded Phased Array Bridge Pin Inspection
Encoded Phased Array Bridge Pin Inspection James S. Doyle Baker Testing Services, Inc. 22 Reservoir Park Dr. Rockland, MA 02370 (781) 871-4458; fax (781) 871-0123; e-mail jdoyle@bakertesting.com Product
More information201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
More informationProfessional Resumé of Geoffrey Hokin
Professional Resumé of Geoffrey Hokin Personal Details Name: Location: Occupation: Geoffrey Hokin MSc (Hons.) Geology Toowoomba, QLD Geologist, Exploration Manager Career Summary In my Geology career I
More informationA new approach to rail asset management.
A new approach to rail asset management. Geotechnical and structural monitoring via satellite for the rail industry. With mounting pressures on the UK s ageing infrastructure networks from ever increasing
More informationTypes of Mining - Expert Table
See page 6 Minerals Downunder Teacher Guide (2002) - Activity 4a Types of Mining - Expert Table How to Jigsaw Information 1. Divide the class into Home Groups of five for the five different types of mining
More informationGEOTECHNICAL ISSUES OF LANDSLIDES CHARACTERISTICS MECHANISMS PREPARDNESS: BEFORE, DURING AND AFTER A LANDSLIDE QUESTIONS FOR DISCUSSIONS
GEOTECHNICAL ISSUES OF LANDSLIDES CHARACTERISTICS MECHANISMS PREPARDNESS: BEFORE, DURING AND AFTER A LANDSLIDE QUESTIONS FOR DISCUSSIONS Huge landslide Leyte, Phillipines, 1998 2000 casulties Small debris
More informationKeras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project, Australia
Keras Resources plc / Index: AIM / Epic: KRS / Sector: Mining 14 January 2016 Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project,
More informationDirect and Reflected: Understanding the Truth with Y-S 3
Direct and Reflected: Understanding the Truth with Y-S 3 -Speaker System Design Guide- December 2008 2008 Yamaha Corporation 1 Introduction Y-S 3 is a speaker system design software application. It is
More informationDrawing Accurate Ground Plans from Laser Scan Data
Drawing Accurate Ground Plans from Laser Scan Data Kevin Cain Institute for the Study and Integration of Graphical Heritage Techniques (INSIGHT) Abstract. In addition to the kinds of standard documentation
More informationFor personal use only
January, 202 Silver Swan Group Limited December 20 Quarterly Activities Report HIGHLIGHTS STAKEWELL Gold Project: Drilling intersected high and low grade gold mineralisation at Kohinoor, including surface
More informationbi directional loading). Prototype ten story
NEESR SG: Behavior, Analysis and Design of Complex Wall Systems The laboratory testing presented here was conducted as part of a larger effort that employed laboratory testing and numerical simulation
More informationMy presentation will be on rainfall forecast alarms for high priority rapid response catchments.
Hello everyone My presentation will be on rainfall forecast alarms for high priority rapid response catchments. My name is Oliver Pollard. I have over 20 years hydrological experience with the Environment
More informationBy Gene Kitts, Senior Vice President-Mining Services, International Coal Group, Inc.
Why Surface Mine? By Gene Kitts, Senior Vice President-Mining Services, International Coal Group, Inc. Why do we surface mine in Central Appalachia? It s certainly not because we like the public attention
More informationFor personal use only
Korab Resources Limited Gold Operations Update November 2012 Andrej K. Karpinski Executive Chairman Korab Projects BOBRIKOVO MELROSE 1 Korab Gold Projects Other Korab Projects Robust Undervalued Gold Portfolio
More informationTS-E24mm f/3.5l TS-E45mm f/2.8 TS-E90mm f/2.8 Instructions
TS-E24mm f/3.5l TS-E45mm f/2.8 TS-E90mm f/2.8 ENG Instructions Thank you for purchasing a Canon product. Canon s TS-E lenses are tilt-shift lenses designed for EOS cameras. The tilt-shift mechanism enables
More informationNorth Atlantic and Rio Tinto Joint Venture Potash Project in Saskatchewan, Canada. Resource Summary
North Atlantic and Rio Tinto Joint Venture Potash Project in Saskatchewan, Canada Resource Summary The Canadian Potash Project is located in the central Saskatchewan Potash district that represents nearly
More informationFTC 2015-2016 DIY Mountain Build Guide
FTC 2015-2016 DIY Mountain Build Guide Assembly Instructions Check out the DIY2015-2016 Prints and BoM for individual part details. Release 1.0 9/10/15 Page 1 This guide and Bill of Materials are for constructing
More informationHow To Retaining Wall Guide
How To Retaining Wall Guide Before you start: Consents and Engineering Building Consent Retaining walls over 1.5m high will require a building consent from the Local Body Council. Walls that carry extra
More informationPacifico set to commence drilling at Borroloola West Project and co-funding secured from NT Government
CORPORATE DIRECTORY Managing Director Simon Noon Directors Richard Monti (Chairman) Peter Harold (Non-exec.) Andrew Parker (Non-exec.) Company Secretary Joshua Ward Patrick Holywell Registered office Level
More informationAPPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE
APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0
More informationAn Archaeological Settlement Analysis of Goshono Site
An Archaeological Settlement Analysis of Goshono Site TAKADA Kazunori YAMADA Masahisa 1. The Planar Distribution of Remains Goshono is a late-middle Jomon settlement site in Iwate Prefecture, Ninohe County,
More informationSUMMARY REPORT ON COMPARISON OF THE QUARRY SLOPE ANGLES ADJACENT TO THREE KINGS RESERVE
SUMMARY REPORT ON COMPARISON OF THE QUARRY SLOPE ANGLES ADJACENT TO THREE KINGS RESERVE (Dated: July 2008) FOR Prepared By: Graeme W. Fulton B.Sc. (Hons), Mining and Petroleum Engineering, MAusIMM Terra
More informationebb current, the velocity alternately increasing and decreasing without coming to
Slack water (slack tide): The state of a tidal current when its velocity is near zero, especially the moment when a reversing current changes its direction and its velocity is zero. The term is also applied
More informationSURVEYING WITH GPS. GPS has become a standard surveying technique in most surveying practices
SURVEYING WITH GPS Key Words: Static, Fast-static, Kinematic, Pseudo- Kinematic, Real-time kinematic, Receiver Initialization, On The Fly (OTF), Baselines, Redundant baselines, Base Receiver, Rover GPS
More informationAdvancements in GPR for a Sustainable Tomorrow
Advancements in GPR for a Sustainable Tomorrow Shawn Lapain, BSc. E., EIT Pavement Specialist Applied Research Associates Inc. 5401 Eglinton Avenue West, Suite 105, Toronto, ON, Canada, M9C 5K6 Tel: 416-621-9555,
More informationAnirudhan I.V. Geotechnical Solutions, Chennai
Anirudhan I.V. Geotechnical Solutions, Chennai Often inadequate In some cases, excess In some cases, disoriented Bad investigation Once in a while good ones Depends on one type of investigation, often
More informationHow Curve Shape Can Influence Pump Selection
Pump ED 101 How Curve Shape Can Influence Pump Selection Joe Evans, Ph.D http://www.pumped101.com If you are new to the pump arena, you may be a bit taken back by the number of pump models offered by various
More informationCHAPTER 4 EARTHWORK. Section I. PLANNING OF EARTHWORK OPERATIONS
CHAPTER 4 EARTHWORK Section I. PLANNING OF EARTHWORK OPERATIONS IMPORTANCE In road, railroad, and airfield construction, the movement of large volumes of earth (earthwork) is one of the most important
More informationLeapfrog : new software for faster and better 3D geological modelling
Leapfrog : new software for faster and better 3D geological modelling Paul Hodkiewicz, Principal Consultant (Geology), SRK Consulting, 10 Richardson Street, West Perth WA 6005, Australia, phodkiewicz@srk.com.au
More informationName Date Class. By studying the Vocabulary and Notes listed for each section below, you can gain a better understanding of this chapter.
CHAPTER 7 VOCABULARY & NOTES WORKSHEET Earthquakes By studying the Vocabulary and Notes listed for each section below, you can gain a better understanding of this chapter. SECTION 1 Vocabulary In your
More informationAIM: KEFI 6 March 2014. KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE
KEFI Minerals Plc Doğu Akdeniz Mineralleri San. Tic. Ltd. Şti. Cemal Gürsel Cad. Yalı Apt. No:304 K:4 D:9 Karşıyaka İZMİR Tel: +90 232 381 9431 Fax: +90 232 381 9071 Email: info@kefi-minerals.com AIM:
More informationDisaster Mitigation of Debris Flows, Slope Failures and Landslides 639
Disaster Mitigation of Debris Flows, Slope Failures and Landslides 639 Anthropogenic Caused Mass Movements and their Impact on Railway Lines in Austria Christian Rachoy 1) and Manfred Scheikl 2) 1) Dept.
More informationEXCAVATOR SAFETY TRAINING
EXCAVATOR SAFETY TRAINING INSPECTION CHECKLIST INSPECTION AREA INSPECTION RESULTS Sat. Unsat. N/A Comments Carrier & Car Body Rotation system Tracks Rollers Frame, welds, bolts Drive system Upper Structure
More informationTrendline Tips And Tricks
Tantalizing! Trendline Tips And Tricks How do you capture those medium- to longer-term moves when trying to enter and exit trades quickly? D by Sylvain Vervoort aydreaming about trading? Get in a trade
More informationFunctional overview. PRECISE l RELIABLE l REAL-TIME MONITORING - 1 - Document Number: MW2511. www.mineware.com
Functional overview PRECISE l RELIABLE l REAL-TIME MONITORING Document Number: MW2511 www.mineware.com - 1 - Stay on track, on target + on plan Argus is the unrivalled system in global shovel monitoring.
More informationStructural Geology Laboratory 9 (Name)
Structural Geology Laboratory 9 (Name) Geologic maps show the distribution of different types of structures and rock stratigraphic units generally on a topographic base such as a quadrangle map. Key structures
More informationLaboratory #8: Structural Geology Thinking in 3D
Name: Lab day: Tuesday Wednesday Thursday ENVG /SC 10110-20110L Planet Earth Laboratory Laboratory #8: Structural Geology Thinking in 3D http://www.nd.edu/~cneal/physicalgeo/lab-structural/index.html Readings:
More informationRiMONITOR. Monitoring Software. for RIEGL VZ-Line Laser Scanners. Ri Software. visit our website www.riegl.com. Preliminary Data Sheet
Monitoring Software RiMONITOR for RIEGL VZ-Line Laser Scanners for stand-alone monitoring applications by autonomous operation of all RIEGL VZ-Line Laser Scanners adaptable configuration of data acquisition
More information12 Volt 30 Amp Digital Solar Charge Controller
12 Volt 30 Amp Digital Solar Charge Controller User s Manual WARNING Read carefully and understand all INSTRUCTIONS before operating. Failure to follow the safety rules and other basic safety precautions
More informationRequirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)
Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-57 Requirements for an Excavation and Lateral Support Plan Building
More information