Guide to IT Project Management
|
|
- Madeleine Montgomery
- 7 years ago
- Views:
Transcription
1 Guide to IT Project Management Guidelines to be used in conjunction with the ECU Project Management Policy Guideline Owner: Chief Information Officer Keywords: Project Management, Project Delivery, Project Governance, Program Management, Project Portfolio Management Intent Organisational Scope Definitions Guidelines Content Accountabilities and Responsibilities Related Documents Contact Information Approval History 1 INTENT The intent of the ECU IT Project Management Guidelines is to provide supporting information on the application of Project Management for technology related projects across the University. The guidelines outline how the project management, its framework, related processes and controls should be applied to deliver a project through its stages to achieve a successful outcome and contribute to the University s strategic objectives. 2 ORGANISATIONAL SCOPE All ECU staff, contractors and all other members of the University Community involved in the initiation and/or delivery of projects that may impact on ITSC services and resources. Business change projects should engage early with ITSC to clarify implications. Project governance and resources can then be determined with stakeholder areas. Page 1 of 10
2 3 DEFINITIONS TERM DEFINITION PMO Program Management Office ITSC Information Technology Services Centre IT Information Technology PRINCE2 Projects in Controlled Environments, a common project management methodology endorsed for technology related projects at ECU Tailoring Tailoring ensures the amount of process is appropriate for the project s size and complexity and is essential to make it work properly without overly burdensome overheads and related costs Project Board The project board is responsible for providing the overall direction and accountable for the success of the project, chaired by the project sponsor who has overall accountability for the project and its business case Project Manager The Project Manager is responsible for the day-to-day management of the project within the constraints and tolerances agreed with the Project Board and documented in the PID ITGC The IT Governance Committee is the governance body that ensures University-wide compliance to technology governance in a structure manner. It makes prioritised investment recommendations to the Strategic Asset Management Forum (SAMF) based on sound governance practices Concept Brief Business Initiative Groups (BIGs) document their ideas and high level information for strategic and architecture assessment and prioritisation for consideration by ITGC Business Case A Business Case is based on an operational or strategic need within the University. This should detail and justify the baseline information about the project such as background, purpose, benefits, objectives, success factors, risks, timescale and funding sources of the proposed project. Project Brief Outlines the business case with sufficient information to justify initiation, including quality expectations and acceptance criteria for the key deliverables. For business as usual upgrade projects, it also documents the approved business case PID The Project Initiation Document is the contract for the project between the project manager and the project board. It sets out, as a minimum: What the project is aiming to achieve; why it is important to achieve it, who will be involved in managing the process what are their responsibilities, and how and when will the project be undertaken; and answer these to a sufficient level of detail to help maintain control of the project. 4 GUIDELINES CONTENT 4.1 Project Management Principles Page 2 of 10
3 Projects will be managed consistent with recognised best practices based on the PRINCE2 project management framework, including PRINCE2 Principles, Themes and Processes. There are seven management principles that help to manage projects at ECU. These principles form the foundation of ECU s PMO Project Management Framework Continued Business Justification There is a justifiable reason to start the project, the justification remains valid throughout the life of the project and the justification is documented and approved. Justification is documented through a Concept Brief or Business Case endorsed in line with the ECU Technology Governance framework. The Business Case is confirmed, updated and reviewed continuously at all stages of the project lifecycle. Internal business as usual upgrade projects require a Project Brief to document the justification of projects, approved with ITSC in used in lieu of a Concept Brief and Business Case Learn from Experience Project teams are expected to learn from the experience of previous projects and incorporate their learning and improvements into current and future projects. Lessons are sought, recorded and acted upon throughout the life of a project, reviewed at appropriate times such as stage boundaries, and collated and included in the End Project Report with appropriate actions and owners assigned Roles and Responsibilities Projects will have defined and agreed roles and responsibilities within an organisation structure that engages the business, end users and delivery teams. Key governance roles supporting projects and decision making are defined in the ECU Technology Governance guidelines Manage by Stages Projects are planned, monitored and controlled on a stage by stage basis. These stages provide project sponsors and executives with decision points at major intervals throughout the project. Decision points are usually key milestones where the status can be assessed, and business case and plans reviewed to ensure that the project remains viable and an informed decision made whether to proceed Manage by Exception Projects will have defined tolerances to establish limits of delegated authority and any escalations beyond these. When the project or a stage is planned, these tolerances are established. These tolerances help identify when a Project Manager should escalate issues or risks to their Project Board. These tolerances allow the Project Board to manage by exception when tolerances are forecast to be exceeded. Page 3 of 10
4 4.1.6 Focus on Deliverables A successful project is output-oriented not activity-oriented. At ECU, the project deliverables should be agreed and defined prior to undertaking the activities required to produce them. The set of agreed deliverables defines the scope of the project and provides the basis for planning and control Tailor to suit the Environment Tailoring reflects the extent to which the key elements of the project management methodology should be applied, specifically against the project management approach, governance, processes and deliverables. Projects are tailored to their sizing and context as it evolves during the project. 4.2 Project Management Framework The Project Management Framework comprises a tailored project lifecycle and processes for project management practitioners to manage projects at ECU Sizing A project management approach should be tailored by considering a range of relevant factors in order to apply appropriate controls that are suitable for the project without executive burden of overheads. Project Sizing Guidelines have been developed for this purpose. Page 4 of 10
5 4.2.2 Phases and Stages Project phases are consistent with the ECU Technology Governance framework and supporting guidelines and comprise a number of stages and key deliverables as follows. Phase Stage Purpose Owner Key Deliverable Assess the business value, Concept strategic alignment Technology Brief Assess and architecture Governance Concept Brief impacts Services Plan Deliver Close Benefits Business Case Start-up Design Procure Build Test Deploy Transition Close Benefits Realisation 4.3 Governance Scope and justify the investment Plan and initiate the project Clarify requirements High level design Source best value for money solution and update business case where necessary Design and configure solution Test and accept quality of solution Deploy solution supported with training and handovers to operational teams Smooth and supported transition of solution into production service Formally close project Post implementation review and benefits realisation Project Manager PMO Business Case Project Brief and Project Initiation Document (PID) Requirements Architecture Procurement Plan and Evaluation if needed Low level designs and configuration UAT signoff, Business readiness and transition plan PAC approved Service Acceptance End Project Report Post Implementation Review (PIR) and Benefits reports Governance of technology-related projects sits within the ECU Technology Governance framework and supporting guidelines. This explains sponsorship, oversight, responsibilities, delegated authorities, performance, business value, and investment optimisation. Additionally, project sizing guidelines inform the recommended level of project sponsor and project board members, and should be confirmed in the business case endorsed by ITGC. Page 5 of 10
6 4.4 Assurance Includes PMO quality reviews, end stage reviews, stage gate reviews, project audits, monitoring, measurement and reporting. Assurance requirements are informed by the project s sizing, and project sponsors may request additional assurance activities. Project end stage reviews and health checks are conducted with the project either as an internal or peer review process reporting to the project sponsor. End Stage Reports are made available to the PMO. Stage gate reviews can be requested (typically by the Project Sponsor/Executive) for larger projects being conducted by the PMO and/or via a third party independent assurance. Project audits are conducted by RASC as part of regularly planned audits. 4.5 Reporting Project reporting is required at specified trigger events and to inform a regular monthly reporting cycle collated by the PMO for project and program senior stakeholders. These reporting processes are described in the ITSC PMO Project Highlight Report Guidelines. 4.6 Project Management Practice Areas Project management practices should draw upon recognised best practices and global standards. A summary of these are included in the appendix, see section 9. 5 ACCOUNTABILITIES AND RESPONSIBILITIES In relation to these guidelines, the following positions are responsible for the following: Guidelines Owner The Guidelines Owner has overall responsibility for the content of these guidelines and its operation in ECU. PMO Manager The PMO Manager maintains and promotes the effective use of these guidelines through training and support. Staff/ Contractors Staff/ /Contractors are required to apply these guidelines and to seek clarification from the PMO in the event of uncertainty as to its application. Page 6 of 10
7 6 RELATED DOCUMENTS: 6.1 The policy and guidelines are supported by the following: IT Project Management Framework IT Project Sizing Guidelines ECU Technology Governance Framework, Policy & Guidelines Information Technology Architecture Guiding Principles and Recommendations Strategic Procurement Policies, Guidelines and Procedures Integrated Risk Management Framework Financial Management Policies, Guidelines and Procedures ITSC PMO Project Highlight Reporting Guidelines IT Product Acceptance Criteria 6.2 Other documents which are relevant to the operation of the policy and guidelines are as follows: Terms of References for Advisory Boards AAB, CAB and SAB. Terms of Reference for Project Boards. 7 CONTACT INFORMATION For queries relating to this document please contact: Guidelines Owner Chief Information Officer All Enquiries Contact: IT PMO Manager Telephone: address: pmo_it@ecu.edu.au The Chief Information Officer is custodian of the University s governance over technology and on behalf of the ITGC, has overall responsibility for the content of this guideline and its operation in ECU. 8 APPROVAL HISTORY Guidelines Approved by: Date Guidelines First Approved: Date last modified: Revision History: Next Revision Due: TRIM File Reference Page 7 of 10
8 9 Appendix 9.1 Project Management Practice Areas Project management practices should draw upon recognised best practices and global standards such as PRINCE2 and the Project Management Body of Knowledge that are complementary in this area Stakeholder Engagement Stakeholders are those with an interest or influence on the project s delivery and outcomes. Stakeholders should be identified and analysed early and included in communication and change management plans. Key stakeholders are initially identified in the Concept Brief and Business Case, and engagement and change management plans developed during Start-up stage and evolved during the project Planning Effective project management relies on effective planning as without a plan there is no control. At a minimum, this should result in a list of key milestones and deliverables as a baseline to measure progress against. A separate stage plan should be used to for start-up and deliver the PID, after which the project plan supporting the PID may lead to further stage plans if needed Scheduling Project scheduling is the modelling of project plans in a project scheduling tool, typically MS Project. Schedules should include identification of critical path activities and enable time management, with baseline schedules used to monitor progress, control and raise changes against. When schedule forecasts exceed the baseline schedule, agreed tolerance and interdependencies, a change is raised for the project board to consider and endorse the updated schedule and milestones. PMO also reviews schedule changes to overall program delivery and interdependencies taking the appropriate steps to manage or where necessary escalate Organisational Change Management Change management to support operational adoption and business benefits realisation should be approached consistent with Prosci Change Management practices (best practice methodology) including planned activities to influence and build Awareness, Design, Knowledge and Reinforcement of changes. This includes change leadership at relevant levels and visible change sponsorship by the project executive sponsor Quality Management Project quality management is the process of identifying and managing quality requirements and/or standards for the project and deliverables, and documenting how the project will demonstrate compliance and verify and validate deliverables. The PRINCE2 quality theme defines and implements the means by which the project will create and verify deliverables that are fit for purpose. This includes a quality plan in the PID and activities such as quality reviews and testing during delivery Cost Estimation and Budget Management Page 8 of 10
9 Project cost estimation determines how much the project will cost and how accurate is the estimate. An accurate estimate relies on clear assumptions, defined scope, realistic risk assessment, and accurate resource availability and productivity rates. Actual costs must be tracked and compared to planned costs from the approved plan and budget. Variances between planned and actual must be controlled for an escalated when exceeding agreed tolerances. Costs are estimated at several key stages including Concept Brief and Business Case, and when endorsed become the baseline to control against. Project Managers will report and control project costs against Oracle Financials GL month-end reports, including any accruals, and review and reconcile any discrepancies. Forecasts are updated at least quarterly and when exceeding the approved budget and tolerance, a change is raised for the project board and then ITGC to consider and endorse the updated budget Human Resource Management Project Human Resource Management ensures that the project has sufficient human resources, with the correct skills sets and experience, to enable the project to be successful completed. This may include sourcing or allocating additional resources, their performance management and exiting. It is important to estimate resource and raise resource requirements with their relevant team leaders as early as possible and clarify and reconfirm closer to the time. As ITSC is resourced for business as usual, projects need to estimate additional resource requirements and gaps in capabilities based on external contractor rates and backfilling where appropriate. This is estimated at a high level during Concept Brief and with increasing detail for Business Case and subsequent stages. The PMO reviews all projects for aggregate demand and collates aggregate supply from teams to inform a high-level program/portfolio capacity plan Procurement Project procurement includes the processes required to purchase or acquire deliverables, services or results needed from outside the project. Projects must comply with ECU Strategic Procurement Policy and guidelines. Projects should consider the procurement strategy during the initial Concept Brief stage, and then as part of the planning phase review and finalise the procurement strategy Risk Management Every project involves risks and every project needs a management strategy for dealing with the threats and opportunities represented by each risk. Project risk management includes processes to manage, plan, identify, analyse, respond to, and monitor and control project risks. Risks are managed as part of the integrated risk management framework. Risks should be registered and maintained in a project risk register made available to the PMO, e.g. in the Project Workbook Issues and Change Management A project issue is any relevant event that has happened, wasn t planned, and requires management action. Issues are registered in the project issues register included in the project workbook, their impacts assessed and changes proposed as part of the change process, decided by the project board or change authority. Resulting changes are recorded in the change register and effected consistent with configuration management. For example, updated documents are republished with a new version Page 9 of 10
10 and communicated to stakeholders, or production change are registered as part of the change request process in ServiceNow Architecture To ensure projects continue on the agreed architecture and solution path determined architecture reviews are performed throughout all phases of the project, Architecture reviews are aligned to key touch points at specific project stages defined in the project management framework Service Design and Production Acceptance Service design and implications are initially considered in the Concept Brief stage and reviewed and refined throughout the project as the service is designed. Production acceptance of the new or changed service is considered initially within the planning phase of the project, with required deliverables and stakeholders identified and incorporated within the project plan and schedule, enabling a smooth transition to the production service. The Production Acceptance Criteria (PAC) is a useful prompt list for the Project Manager identifying the stakeholder areas and required deliverables Post Implementation Review Post-Implementation Review assesses both how well the project has been managed and the realisation of benefits projected in the business case and developed in the benefits realisation plan. As these are achieved through other activities, postimplementation review is effectively split into two: End Project Report and Benefits Review End Project Report The End Project Report (EPR) is the Project Manager s report to the Project board documenting how well the project was managed against the Project Initiation Document (PID). It should comment on approved changes to the PID and cover any exceptions, comment on how well the customer s quality expectations have been met, highlight lessons learned, and includes any benefits that are already being realised. The EPR is produced as part of the formal project closure process in the Closure stage Benefits Review Benefits review assesses the realisation of benefits projected in the business case and as described in the benefits realisation strategy. Any deviations from expected benefits should be documented and explained in the benefits report. This is an important input for the Realise Benefits stage gate review. Page 10 of 10
WHAT IS PRINCE2? Benefits There are many benefits of using PRINCE2 but primarily it:
WHAT IS PRINCE2? Introduction PRINCE2 (Projects in a Controlled Environment) is a structured project management method that can be applied regardless of project scale, type, organisation, geography or
More informationSound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
More informationR U N D O. The ECU Technology Governance Framework A brief guide
PLAN R U N D O DO The ECU Technology Governance Framework A brief guide The ECU Technology Governance Framework A brief guide The ECU Technology Governance Framework is made up of a set of processes, effected
More informationPRINCE2:2009 Glossary of Terms (English)
accept (risk response) acceptance acceptance criteria activity agile methods approval approver assumption assurance A risk response to a threat where a conscious and deliberate decision is taken to retain
More informationMaturity Model. March 2006. Version 1.0. P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce
Maturity Model March 2006 Version 1.0 P2MM Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value Added product which is outside the scope of the HMSO
More informationGateway review guidebook. for project owners and review teams
Gateway review guidebook for project owners and review teams The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and
More informationPROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
More information1. What is PRINCE2? Projects In a Controlled Environment. Structured project management method. Generic based on proven principles
1. What is PRINCE2? Projects In a Controlled Environment Structured project management method Generic based on proven principles Isolates the management from the specialist 2 1.1. What is a Project? Change
More informationThe Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
More informationPurpose: Content: Definition: Benefits: outputs outcomes benefits Business Case dis-benefit Key Responsibilities: Approach: Executive Developed
Key Learning Points The Swirl Logo is a trade mark of the AXELOS Limited. Is used by the Project Board throughout the project to verify its continued viability:- Is the investment in this project still
More informationPORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value
More informationNSW Government ICT Benefits Realisation and Project Management Guidance
NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control
More informationThe Foundation Examination
The Foundation Examination Sample Paper 2 January 2013 Release Multiple Choice 1-hour paper Instructions 1. All 75 questions should be attempted. 2. 5 of the 75 questions are under trial and will not contribute
More informationPLANNING FOR YOUR PROJECT
PLANNING FOR YOUR PROJECT This tool kit has been designed to provide an introduction to planning. It will help you to think about the reasons behind why you should plan, what to plan and the variations
More informationProject Management Fact Sheet:
Project Management Fact Sheet: Project Documentation Version: 2.2, November 2008 DISCLAIMER This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It follows that
More informationPRINCE2 and governance
PRINCE2 and governance Andy Murray, lead author of PRINCE2 (2009) and Director of Outperform UK Ltd White Paper November 2011 2 PRINCE2 and governance Contents 1 Purpose of this white paper 3 2 What is
More informationThe Department for Business, Innovation and Skills IMA Action Plan PRIORITY RECOMMENDATIONS
PRIORITY RECOMMENDATIONS R1 BIS to elevate the profile of information risk in support of KIM strategy aims for the protection, management and exploitation of information. This would be supported by: Establishing
More informationProgramme Governance and Management Plan Version 2
PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from
More informationGeneral Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use the proforma answer sheet provided.
Introductory Certificate The APM Project Fundamentals Qualification. Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60
More informationDo not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Introductory Certificate in Project Management Exam paper Candidate Reference Number Date of Exam Location of the Exam General Notes Time allowed 1 hour Answer all 60 multiple choice questions Use
More informationRetained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
More informationNetwork Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
More informationOperations. Group Standard. Business Operations process forms the core of all our business activities
Standard Operations Business Operations process forms the core of all our business activities SMS-GS-O1 Operations December 2014 v1.1 Serco Public Document Details Document Details erence SMS GS-O1: Operations
More informationIntroductory Certificate. The APM Project Fundamentals Qualification
The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment
More information5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]
231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for
More informationAIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
More informationPRINCE2 Introduction PRINCE2 Introduction
Managing Successful Projects with PRINCE2 PRINCE2 Introduction PRINCE2 Introduction A Summary of PRINCE2 Managing Successful Projects with PRINCE2 OGC/APM Group Accredited Event UKAS/APMG Certificate 001
More informationHHS OCIO Policy for Information Technology (IT) Enterprise Performance Life Cycle (EPLC)
Office of the Chief Information Officer Office of the Assistant Secretary for Resources and Technology Department of Health and Human Services HHS OCIO Policy for Information Technology (IT) Enterprise
More informationProject, Programme and Portfolio Management Delivery Plan 6
Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy
More informationCyber Security Consultancy Standard. Version 0.2 Crown Copyright 2015 All Rights Reserved. Page 1 of 13
Cyber Security Consultancy Standard Version 0.2 Crown Copyright 2015 All Rights Reserved Page 1 of 13 Contents 1. Overview... 3 2. Assessment approach... 4 3. Requirements... 5 3.1 Service description...
More informationProject Management Manual
Project Management Manual PM01 Introduction to the Project Management Manual Ref: PM01 (V7.01) - Uncontrolled once Printed Issued on 20 th December 2006 Manual Owner: James Couper Head of Project Management
More informationGovernance, Risk and Best Value Committee
Governance, Risk and Best Value Committee 2.00pm, Wednesday 23 September 2015 Internal Audit Report: Integrated Health & Social Care Item number Report number Executive/routine Wards Executive summary
More informationAuditing the Software Development Lifecycle ISACA Geek Week. Mike Van Stone Sekou Kamara August 2014
Auditing the Software Development Lifecycle ISACA Geek Week Mike Van Stone Sekou Kamara August 2014 Agenda Introduction Audit Scope Project Initiation SDLC Processes Stakeholders Common Development Methodologies
More informationESKITP7145.01 Manage IT service delivery performance metrics
Overview This sub-discipline covers the competencies required to manage the monitoring, analysis and communication of IT service delivery performance metrics. Monitoring service level performance is a
More informationWhite Paper. Making the case for PPM
Introduction There are many reasons why organizations decide to implement project portfolio management solutions, but typically it is to help senior management confidently and consistently answer questions
More informationChange Management Office Benefits and Structure
Change Management Office Benefits and Structure Author Melanie Franklin Director Agile Change Management Limited Contents Introduction 3 The Purpose of a Change Management Office 3 The Authority of a Change
More informationTransport for London. Projects and Planning Panel
Agenda Item 4 Transport for London Projects and Planning Panel Subject: TfL Pathway Date: 8 May 2013 1 Purpose 1.1 At its meeting of 8 January 2013 the Panel asked for further information about Pathway,
More informationWhite Paper. PPP Governance
PPP Governance The Governance of Projects, Programs and Portfolios (PPP) (sometimes called project governance for convenience) is the sub-set of corporate and organisational governance 1 focused on assisting
More informationIntroductory Certificate The APM Project Fundamentals Qualification
Introductory Certificate The APM Project Fundamentals Qualification Syllabus, learning outcomes and assessment criteria aligned to the APM Body of Knowledge 6th edition The syllabus provides a summary
More informationProject organisation and establishing a programme management office
PROJECT ADVISORY Project organisation and establishing a programme office Leadership Series 1 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital
More informationModule 2: The Project Initiation Stage
Overview Initiation stage is highly instrumental in the life cycle of a project as it defines the boundaries of the project gives clarity to all participants about the objectives, scope, cost timescale
More informationMNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
More informationStakeholder management and. communication PROJECT ADVISORY. Leadership Series 3
/01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,
More informationWhy are PMO s are Needed on Large Projects?
Why are PMO s are Needed on Large Projects? Keeps Project Manager focused on: Priority risks Priority issues Stakeholder alignment Technical challenges Ensures administrative tasks are completed: Projects
More informationCHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT
CHECKLIST OF COMPLIANCE WITH THE CIPFA CODE OF PRACTICE FOR INTERNAL AUDIT 1 Scope of Internal Audit 1.1 Terms of Reference 1.1.1 Do terms of reference: (a) establish the responsibilities and objectives
More informationPosition Description
Position Description Job title Group Section Responsible to Responsibility for staff Project Coordinator Natural Resource Operations Rotorua Lakes Protection & Restoration Programme Rotorua Lakes Business
More informationITIL Introducing service transition
ITIL Introducing service transition The goals of service transition Aligning the new or changed service with the organisational requirements and organisational operations Plan and manage the capacity and
More informationSenate. SEN15-P17 11 March 2015. Paper Title: Enhancing Information Governance at Loughborough University
SEN15-P17 11 March 2015 Senate Paper Title: Enhancing Information Governance at Loughborough University Author: Information Technology & Governance Committee 1. Specific Decision Required by Committee
More informationDepartment of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
More informationObjectives. Project Management Overview. Successful Project Fundamentals. Additional Training Resources
Project Management for Small Business Moderator: Maria Mancha Frontline Systems, Inc. Objectives Project Management Overview Successful Project Fundamentals Additional Training Resources Project Management
More informationAPMP. The APM Project Management Qualification. Syllabus, learning outcomes and assessment criteria aligned to the APM Body of Knowledge 6 th edition
The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment
More informationThe STFC Project Management Framework
The STFC Project Management Framework Version 4 April 2016 For further information contact: Tony Medland, Programmes Directorate (tony.medland@stfc.ac.uk) Matt Fletcher, National Laboratories Directorate
More informationAssociation for Project Management Business Management System
Association for Project Management Business Management System December 2012 2 Association for Project Management About APM Formed in 1972, the Association for Project Management (APM) is committed to developing
More informationPart 1 Checklist. Feasibility 2. Investigation 9. Design 18. Construction 26
Part 1 Checklist Process Page 2 9 Design 18 26 Page 1 FEASIBILITY 1. Establishment 1.1 Establishment Recognise problem, need or opportunity. Formulate goal and objectives. Prepare project charter. Obtain
More informationProject Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
More informationNFSA Project Management Guidelines
NFSA Project Management Guidelines Project Management Guide Purpose of this Guide This Guide outlines the NFSA Project Management Guidelines, and includes: NFSA Project Life Cycle Governance Roles and
More informationSelecting a project management methodology
VICTORIAN GOVERNMENT CIO COUNCIL Project Management Selecting a project management methodology Guideline This guideline provides advice for selecting and tailoring a project management methodology. Keywords:
More informationPrince 2 Health Check
Prince 2 Health Check Start-up Was there a Project Mandate? Was the Project Board designed/appointed before initiation was authorised? Was a Project Brief produced? Is the Project Brief to PRINCE standards?
More informationBenefits realisation. Gate
Benefits realisation Gate 5 The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and Planning, January 2010. The Queensland
More informationSuperseded by T MU AM 04001 PL v2.0
Plan T MU AM 04001 PL TfNSW Configuration Management Plan Important Warning This document is one of a set of standards developed solely and specifically for use on the rail network owned or managed by
More informationInformation Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review
Information Sharing Lessons Learned from Gateway Reviews: Gate 5 Benefits Realisation Review October 2013 The purpose of this document is to share lessons learned to support agencies to better identify
More information<Business Case Name> <Responsible Entity> <Date>
(The entity Chief Information Officer, Chief Financial Officer and Business Area programme Lead must sign-off the completed business case) Signed: Date:
More informationUsing PRINCE2 to Manage US Federal Government IT Projects
For Portfolio, Programme, Project, Risk and Service Management Using PRINCE2 to Manage US Federal Government IT Projects Applying the PRINCE2 project management method to support Capital Planning and Investment
More informationService Integration &
This is a DRAFT document, being published for review & comment The content is therefore subject to change & revision This document is part of the XGOV Strategic SIAM reference set Service Integration &
More informationLearning Outcome 1 The learner will: Be able to initiate the preliminary stages of a project.
Unit Title: Project Management Guided Learning Hours: 210 Level: Level 6 Number of Credits: 25 Learning Outcome 1 The learner will: Be able to initiate the preliminary stages of a 1.1 Identify an appropriate
More informationProgram Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
More informationProject Management Policy and Procedure
Project Management Policy and Procedure Author(s): Laura Graham Peter Griggs Approved SMT: October 2006 Issue Date: October 2006 Policy Review Date Ref: Contents: 1. Purpose and Scope 2. Aims and Objectives
More informationPRINCE2 Practitioner - Instructor: Patrick von Schlag
PRINCE2 Practitioner - Instructor: Patrick von Schlag Time Clips Course Introduction Course Introduction 0:00:10 0:01:25 0:01:06 0:02:41 3 Chapter 01 - Course Introduction Lesson: Course Introduction 0:00:10
More informationProject Governance. New Corporations Unit (NewCo) PWC Structural Separation Program
New Corporations Unit (NewCo) Department of the Chief Minister Level 14, NT House, 22 Mitchell Street, Darwin PWC Structural Separation Program Project Governance January 2014 Table of Contents 1. Introduction...
More informationIntegrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans
Integrated Assurance & Approval Strategy and Integrated Assurance & Approval Plans A guide to implementing integrated assurance and approvals Version 1.0 - May 2011 Contents Introduction 03 Integrated
More informationHow To Prepare A Configuration Change Change Request For The Tfnsw Cmaac
Guide TfNSW Configuration Management and Asset Assurance Committee Submissions Guide Important Warning This document is one of a set of standards developed solely and specifically for use on public transport
More informationProcurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
More informationJuly 2012 Report No. 12-045. An Audit Report on The ReHabWorks System at the Department of Assistive and Rehabilitative Services
John Keel, CPA State Auditor The ReHabWorks System at the Department of Assistive and Rehabilitative Services Report No. 12-045 The ReHabWorks System at the Department of Assistive and Rehabilitative Services
More informationVoice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
More informationBUY ONLINE AT: http://www.itgovernance.co.uk/products/1748
PRINCE2 FOR DUMMIES Introduction About This Book Foolish Assumptions How This Book is Organised Part I: How PRINCE Can Help You Part II: Working Through Your Project Part III: Help with PRINCE Project
More informationBenefits. MIRACLE Benefits. I have no idea! What is going on in here? Konferencja "Bezpieczny Projekt" WARSZAWA 11 maja 2010 r.
Programme Plan MIRACLE Benefits Benefits What is going on in here? I have no idea! 1 W A R S Z A W A R Z E S Z Ó W W R O C Ł A W 1 Fitting the pieces together How the APMG Product Set helps you manage
More informationConfident in our Future, Risk Management Policy Statement and Strategy
Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents
More informationJUNE 2010. Assurance for high risk projects
JUNE 2010 Assurance for high risk projects Our vision is to help the nation spend wisely. We apply our unique perspective of public audit to help Parliament and government drive lasting improvement in
More informationINVESTING IN REFORM INVESTING IN STOCKPORT DRAFT BUSINESS CASE
INVESTING IN STOCKPORT DRAFT BUSINESS CASE INVESTING IN REFORM IIS Programme/Project Name: Project Name: Portfolio: IIS Outcome: IIS Board SRO: IIS Project Lead: Public Realm and Solutions SK Communities
More informationTHE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT
THE SOUTH AFRICAN HERITAGE RESOURCES AGENCY MANAGEMENT OF PERFORMANCE INFORMATION POLICY AND PROCEDURES DOCUMENT ACCOUNTABLE SIGNATURE AUTHORISED for implementation SIGNATURE On behalf of Chief Executive
More informationOxford City Council Managing Capital Projects
www.pwc.co.uk Internal Audit Report 2014/2015 August 2015 Oxford City Council Managing Capital Projects Table of Contents 1. Executive Summary... 3 2. Background and scope... 5 3. Detailed findings...
More informationQuality Impact Assessment. Executive summary
Report to Public Trust Board 28 th February 2013 Title Sponsoring Executive Director Author(s) Purpose Previously considered by Quality Impact Assessment Director of Quality and Safety/ Chief Nurse Director
More informationIT Project Management
IT Project Management IT Project Management provides a structured approach to making things happen and in doing so, enables initiatives (projects) to be delivered to time, quality and budget. www.business.wales.gov.uk/superfastbusinesswales
More informationConcept of Operations for Line of Business Initiatives
Concept of Operations for Line of Business Initiatives Version 1.0 Office of E-Gov and IT, OMB March 2006 Table of Contents FOREWORD...2 1 OBJECTIVES OF THE LINES OF BUSINESS CONCEPT OF OPERATIONS...3
More informationProject Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
More informationAudit of the Management of Projects within Employment and Social Development Canada
Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can
More informationAn Introduction to PRINCE2
Project Management Methodologies An Introduction to PRINCE2 Why use a Project Methodology and What Does PRINCE2 Enable? PRINCE - PRojects IN Controlled Environments - is a project management method covering
More informationCentral Agency for Information Technology
Central Agency for Information Technology Development of a National IT Governance Framework Project Management Agenda 1 What is project management? Why it is important? 2 Leading practices 3 Project management
More informationProject Management Framework
Information Services Project Management Framework October 2003 Document ID No. Page 1 of 1 Contents 1. Introduction Page 3 2. Use of Framework Page 3 3. Project Register and Monitoring Page 4 4. Project
More informationAt the end of this chapter. Project Charter. What is a Project Charter? What is a Project Charter? Why is a Project Charter used?
At the end of this chapter Project Charter Describe what a project charter is and why it is critical to project success. Explain what a project scope statement is and why it is important. List the various
More informationCapital Projects. Providing assurance over effective delivery of projects
Capital Projects Providing assurance over effective delivery of projects Governance and oversight Project Scope and change Reporting and communication Project risk and success factors Delivery Major projects
More informationDRAFT V5. PFSC 16/05/2014 Appendix 1. Outline Plan to deliver the County Council s investment property Strategy
PFSC 16/05/2014 Appendix 1 Outline Plan to deliver the County Council s investment property Strategy 1. Strategic Drivers 1.1 The County Council s property investment strategy sets out how its property
More informationRisk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
More informationIPL Service Definition - Project Management, Programme Management and Governance
IPL Proposal IPL Service Definition - Project Management, Programme Management and Governance Project: Date: 16th Dec 2014 Issue Number: Issue 1 Customer: Crown Commercial Service Page 1 of 8 IPL Information
More informationSolvency II. PwC. *connected thinking. Solvency II GAP-analysis: practical experience (life and non-life business)
Solvency II Solvency II GAP-analysis: practical experience (life and non-life business) *connected thinking PwC Decide ambition level for Solvency II Business use Standard model, Total eller partiel Optimizing
More informationOngoing N/A TBC. Baseline
Position Title: Executive General Manager, Core Services Systems Operations Classification: SES Band 2 Position Number: 1018 Position Status (ongoing/nonongoing): Ongoing Division: Core Services Systems
More informationProject Management. What is Project Management?
Project Management Project Management enables your business to proceed with new initiatives in a way that allows: Costs to be controlled Agreed outcomes to be measured and confirmed Timescales to be met
More informationReporting The Project Board shall report to the sponsoring Department political board.
Appendix 13 La Mare de Carteret Schools Project Board Mandate Summary (Project restart version March 2014) Function The Project Board is accountable to the Education Department for all aspects contributing
More informationOPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)
OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.
More information