Subsea Drilling and Wellhead Systems

Size: px
Start display at page:

Download "Subsea Drilling and Wellhead Systems"

Transcription

1 MEK Drilling and Wellhead Systems Subsea Drilling and Wellhead Systems This module will cover: Applicable codes and standards Reservoir Engineering Subsea Wells Subsea Well Program Wellhead Equipment Deepwater drilling Slide 2 1

2 Goals Understand the premises and interfaces to the drilling activity To understand the main building blocks in a well To be able to participate in debates regarding drilling activity and well architecture Slide 3 Standards Overview General ISO NORSOK D-001 NORSOK D-010 NORSOK U-001 OLF Guideline 070 PSA Norway DNV-OS-C101 Riser/Umbilicals ISO ISO ISO ISO API RP 16Q API Spec 16R DNV-OSS-302 DNV-OS-F201 DNV-RP-F206 Wellhead/XT: API 6a API 17d ISO ISO BOP ISO NORSOK D-001 NORSOK D-010 API Spec 6A API Spec 16A API RP 16E API RP 53 API 16d API Spec 16C Drilling Equip. API 7K API RP 64 API 4F API 8C DNV-OS-E101 Control Systems ISO API Spec 16D Well Foundation API RP 2A Casing Tubing, Downhole ISO API 5ct(2)(3) API 14a(b)(h)(j) ISO (cement) Slide 5 2

3 Applicable codes and standards Main codes for wellhead and drilling: API 6A/ISO Specification for Wellhead and Christmas Tree Equipment API 17D/ISO Subsea wellhead and tree equipment API 16A / ISO Specification for Drill-through Equipment + ASME, ISO, BS +++ NORSOK D-010 NORSOK U-001 Slide 6 Reservoir Engineering Ormen Lange Reservoir, 350 km meter below seabed: Slide 7 3

4 Subsea Wells The main development well types: Exploration wells Production wells (oil, gas) Injection wells (water, gas) Well design through the reservoir: Vertical Deviated Horizontal Multi branch (side-track) Enhanced Recovery: Water injection Gas injection WAG; water alternating gas injection Artificial lift Slide 9 Subsea Well Program Typical Subsea Well Program: Drill 36 hole to ~80m Run and cement 30 Conductor Drill 26 hole to ~800m BOP Run and cement 20 casing with 18 3/4 (link) WH Run Blow-out-preventer (BOP) Drill 17 ½ hole to ~1300m Run and cement 13 3/8 Casing Drill 12 1/4 hole to ~1700m Run and cement 9 5/8 Casing Drill 8 ½ hole to ~2000m Clean up well Abandon well (run plug or close valve) Proceed to completion operations This program can be a 100 days plan Slide 11 4

5 Xmas Tree Systems Typical Tree Installation Sequence: Install Xmas Tree on Wellhead using drill string and Tree Running Tool (TRT) Recover TRT Run BOP and marine riser Remove down hole plugs Run completion / production tubing Perforate tubing at reservoir depth Inhibit well and prepare to abandon Install internal tree cap Retrieve marine riser and BOP Drill rig moves to next well Flowlines and flying leads installed by Rig or installation vessel BOP XT Slide 14 Well Completion - sample 18 3/4" X 7" X 2" tubing hanger 18-3/4" wellhead 18 3/4" X 13 3/8" casing hanger 36" conductor housing 36"/30" conductor at 940 mtvd 2 x 7" TRSSSV s 20" surface casing at 1600mTVD UNSTABLE ROGALAND SHALES RESERVOIR 9-5/8" production tubing, with production packer set below 9 5/8" liner lap. 7" tail pipe available for deep set plugs and downhole gauge positioning. 9-5/8 x 13-3/8" liner hanger. 9-5/8 x 7" production packer. 9-5/8 x 7" full bore isolation valve 13-3/8 x 13-5/8" intermediate casing set in 17 1/2" hole at m TVD. 9-5/8" x 7" lower completion packer 9 5/8" liner in 12 1/4" hole to top reservoir at 2705m TVD over sail section, to prevent shale 7" formation isolation valve 7 " lower completion. Slide 15 5

6 TVD vs. MD TVD True Measured Depth MD Measured Depth Slide 17 Wellhead Equipment The wellhead system suspends the casing and serve as a barrier for well fluids against the environment. There are 5 main suppliers of subsea Wellhead systems: - GE Oil & Gas (ex. Vetco Gray) - FMC - Aker Solutions - Drill-Quip - Cameron The wellheads are usually designed according to API 17D (ISO ) and API 6A (ISO10423). The 18 3/4 Wellhead Housing often has a H4 Vetco external profile for subsea wells. The internal seal and locking profiles are supplier specific. Main Components: 18 ¾ Wellhead Housing 30 Conductor Housing 9 5/8 Casing Hanger 18 ¾ Packoff (Annulus seal assembly) 13 3/8 Casing Hanger Drilling Guide Base Casing Diagram Slide 20 6

7 Wellhead Equipment Slide 21 Deepwater Drilling An increasing number of the subsea wells worldwide are located in deepwater. Deepwater is usually defined as water depths from m, with greater than 1500 m water depth classified as ultra deepwater. These depths impose significant challenges with respect to subsea drilling. Existing drilling rigs allow for drilling in water depths in the order of 2400 m. New generation drill rigs and drill ships are being designed for water depths beyond 3000 m. In deep water, drilling requires very heavy equipment, drilling operations and well control procedures are more difficult and well costs can rise dramatically. The following new techniques are considered to have a significant impact on the subsea well construction costs: Under balanced drilling (The first contract in north sea awarded by Statoil) Riser less drilling or dual gradient drilling system Expandable casing strings Casing while drilling Slide 22 7

8 Mono Bore Drilling Slide 23 Buzz group What are the main principles in order to get the oil and gas? Please give details - How do you get to the reservoir? - How do you get the oil/gas out? - Where does the oil/gas go from there? - Think of some safety features in Drilling operations Slide 25 8

9 Safeguarding life, property and the environment Slide Conductor Housing Wellhead Locking Profile Guidebase Landing Shoulder Running Profile Conductor Extension Flow by Port Slide 27 9

10 18 3/4 Wellhead Housing Vetco H4 Profile Lockdown ring Slide /8 Casing Hanger 13 3/8 Casing Pup Joint Slide 29 10

11 9 5/8 Casing Hanger Landing Shoulder 9 5/8 Casing Pup Joint Fluted Centraliser Slide /4 Pack-off Locking Mandrel Wellhead Lock Ring Metal Seal Slide 31 11

12 Drilling Guide Base Slide 32 Casing Diagram Slide 33 12

13 Subsea BOP Blowout.wmv Slide 34 13

Introduction to Subsea Production System

Introduction to Subsea Production System Introduction to Subsea Production System 04 Xmas Tree Systems Bjørn Søgård Xmas Tree Systems This module will cover: Main codes for XT equipment XT Principles and functions Typical schematic Main types

More information

MEK4450. Templates & Manifolds. 29 August 2012. 05 Templates and Manifolds. This module will cover:

MEK4450. Templates & Manifolds. 29 August 2012. 05 Templates and Manifolds. This module will cover: 29 MEK4450 05 Templates and Manifolds Templates & Manifolds This module will cover: Applicable Codes and Standards Templates - Purpose of a template Manifolds - Purpose of a manifold Foundations 2 1 29

More information

NORSOK Standard D-010 Rev. 4, August 2012

NORSOK Standard D-010 Rev. 4, August 2012 Below is a listing of the main changes 1. Definitions of suspension, temporary and permanent abandonment 2. Included more examples of well barrier schematics 3. Included illustrations for permanent abandonment

More information

Subsea Drilling Systems

Subsea Drilling Systems Subsea Drilling Systems 2 Reliable, cost-effective solutions for offshore drilling... FMC Technologies Subsea Drilling Systems lead the industry with reliable and cost-effective drilling solutions which

More information

Rigorous Qualification and Development Program

Rigorous Qualification and Development Program FMC Subsea High Capacity 20K Wellhead System Overview 03/20/2013 UWD HC-20 Subsea Wellhead System Rigorous Qualification and Development Program 2 1 Qualification program Qualification testing is performed

More information

Subsea Standard & Rules What is Subsea?

Subsea Standard & Rules What is Subsea? Subsea Standard & Rules What is Subsea? MEK4450 Standards and Rules Bjørn Søgård, Anders Husby Goals General knowledge of subsea development and production systems Understand the building blocks forming

More information

LINKING SEABED TO SURFACE

LINKING SEABED TO SURFACE LINKING SEABED TO SURFACE The use of HIGH PRESSURE JACKUP DRILLING RISERS for SUBSEA DEVELOPMENTS 2 High Pressure Jackup Drilling Riser Contents Typical Jackup Well Configuration Typical Subsea Well Configuration

More information

An Introduction to Oil and Gas Well Servicing

An Introduction to Oil and Gas Well Servicing An Introduction to Oil and Gas Well Servicing Educational Material from the IOM 3 Oil and Gas Division The global network for the materials cycle Introduction The Institute of Materials, Minerals & Mining

More information

Competitive Edge through System Engineering

Competitive Edge through System Engineering Competitive Edge through System Engineering KBD Forum 6-7 March 2013 Tore Halvorsen FMC Technologies 0 Floating Production Partial Subsea Processing Subsea Systems today: the enabler for deepwater developments

More information

Subsea wellhead systems. Advanced solutions for extreme conditions

Subsea wellhead systems. Advanced solutions for extreme conditions Subsea wellhead systems Advanced solutions for extreme conditions Subsea wellhead systems As offshore drilling pushes past 10,000-foot water depths and 30,000- foot wells, pressure increases exponentially

More information

HPHT CAPPING STACKS AND NEW TECHNOLOGY FOR SUBSEA WELL CONTROL. December 3, 2014 Presenter: Mike Cargol

HPHT CAPPING STACKS AND NEW TECHNOLOGY FOR SUBSEA WELL CONTROL. December 3, 2014 Presenter: Mike Cargol HPHT CAPPING STACKS AND NEW TECHNOLOGY FOR SUBSEA WELL CONTROL December 3, 2014 Presenter: Mike Cargol Agenda Development Update HPHT Capping Stack Mudline Closure Device Divert and Flow System Well Kill

More information

Plug and Abandonment Forum

Plug and Abandonment Forum Plug and Abandonment Forum Developments in Non-Traditional Plug and Abandonment Methods Thomas Ferg ConocoPhillips Norway June 13, 2013 Efficient P&A Thoughts - Do as Much as Possible Without a Rig Remove

More information

Total Subsea Solutions

Total Subsea Solutions Total Subsea Solutions Total Subsea Solutions Developing new energy reserves, managing, and improving producing fields means an unprecedented number of technical challenges. In partnership with our customers,

More information

Subsea School The training program

Subsea School The training program Subsea School The training program Table of Contents Welcome to the FMC Subsea School... 3 Training Schedules and Participation... 4 SS Subsea Technology Introduction... 5 MPS - Subsea Structures... 6

More information

10 Wireline operations

10 Wireline operations 10 WIRELINE OPERATIONS... 1 10.1 GENERAL... 1 10.2 WELL BARRIER SCHEMATICS... 1 10.3 WELL BARRIER ACCEPTANCE CRITERIA... 1 10.3.1 Well control equipment configuration... 1 10.3.2 Deployment of toolstrings...

More information

Setting a Global Standard. www.dril-quip.com. SingleBore Subsea Completion System

Setting a Global Standard. www.dril-quip.com. SingleBore Subsea Completion System Setting a Global Standard www.dril-quip.com SingleBore Subsea Completion System Dril-quip s Vertical Tree Surface Tree Tubing or Drill Pipe Running String Offshore, Time is Money. Dril-quip s SingleBore

More information

Introduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2

Introduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2 Introduction Canadian Oilwell Systems Company and it s subsidiaries are suppliers of oil well Electric Submersible Pumping systems (ESPs). Such pumps are used to lift oil from oil wells so that the oil

More information

Certification of Materials and Components

Certification of Materials and Components OIL & GAS Certification of Materials and Components Standardisation of the industry s approach to quality control and assurance processes Martin Fowlie 12th February 2015 1 DNV GL 2013 12th February 2015

More information

How To Build A Kingkong Production System

How To Build A Kingkong Production System MOSAIC Certified Mariner Energy, Inc./Agip Petroleum King Kong Development Cameron MOSAIC Systems for the King Kong Field Development King Kong Development The King Kong Deepwater Gulf of Mexico Development

More information

Argentina Tataru*, Marcel Adrian Piteiu*, Dan-Paul Stefanescu*, Ioana Vlasin*

Argentina Tataru*, Marcel Adrian Piteiu*, Dan-Paul Stefanescu*, Ioana Vlasin* WIERTNICTWO NAFTA GAZ TOM 24 ZESZYT 1 2007 Argentina Tataru*, Marcel Adrian Piteiu*, Dan-Paul Stefanescu*, Ioana Vlasin* NEW TECHNICAL CONSIDERATIONS OF ROMGAZ COMPANY REGARDING DRILLING, COMPLETION AND

More information

Evaluering av risiko forbundet med løftegass i ringrom og forskellige gassløft barrierer

Evaluering av risiko forbundet med løftegass i ringrom og forskellige gassløft barrierer Evaluering av risiko forbundet med løftegass i ringrom og forskellige gassløft barrierer ESRA seminar, September 3, 2014, Stavanger Per Holand, ExproSoft Ivar Aasen Operator; Det Norske Production start;

More information

The Python Subsea Wellhead

The Python Subsea Wellhead The Python Subsea Wellhead Craig Hendrie, Technical Director, Plexus Holdings plc. COPYRIGHT. All rights reserved. Plexus Holdings plc. Subsea Wellhead challenges - 2010 Following the Macondo disaster

More information

Havbunnsproduksjon. NTNU, 15 april 2013 Eldar Lundanes System Responsible for Controls and Data Management, Eastern Region.

Havbunnsproduksjon. NTNU, 15 april 2013 Eldar Lundanes System Responsible for Controls and Data Management, Eastern Region. Havbunnsproduksjon NTNU, Eldar Lundanes System Responsible for Controls and Data Management, Eastern Region Objectives The student shall be able to describe, with respect to a subsea production system;

More information

Guidelines the DNV way

Guidelines the DNV way Guidelines the DNV way for safe service elastomers in oil & gas Jon Huse Guidelines the DNV way for safe service elastomers Content: What is a DNV-guideline? Examples of DNV-guidelines - Qualification

More information

SUBSEA CHRISTMAS TREE SYSTEMS

SUBSEA CHRISTMAS TREE SYSTEMS NORSOK STANDARD COMMON REQUIREMENTS SUBSEA CHRISTMAS TREE SYSTEMS U-CR-003 Rev. 1, December 1994 Please note that whilst every effort has been made to ensure the accuracy of the NORSOK standards neither

More information

Fiber Optics in a Bakken Multi-Stage Fractured Well. Montana Tech 2011 SPE Drilling Symposium Presented by: Chelsea Kadler

Fiber Optics in a Bakken Multi-Stage Fractured Well. Montana Tech 2011 SPE Drilling Symposium Presented by: Chelsea Kadler Fiber Optics in a Bakken Multi-Stage Fractured Well Montana Tech 2011 SPE Drilling Symposium Presented by: Chelsea Kadler Agenda FracPoint Design FracPoint Real-time Monitoring System Downhole Equipment

More information

Tax Executives Institute

Tax Executives Institute Tax Executives Institute Texas Oil and Gas Transactions May 6, 2013 Circular 230 disclaimer Any US tax advice contained herein was not intended or written to be used, and cannot be used, for the purpose

More information

Handbook. Purchasing Guidelines. API Monogram Equipment. Purchase API Specs online at www.global.ihs.com

Handbook. Purchasing Guidelines. API Monogram Equipment. Purchase API Specs online at www.global.ihs.com Handbook Revision 10.01.09 Purchasing Guidelines Handbook API Monogram Copyright 2009 -. All rights reserved. Handbook Revision 10.01.09 Practical Guidelines for Making Practical Choices Dear Colleagues,

More information

Recommended Practices Associated with Hydraulic Fracturing Operations

Recommended Practices Associated with Hydraulic Fracturing Operations Recommended Practices Associated with Hydraulic Fracturing Operations API standards program includes best-practices for hydraulic fracturing which include: Proper well construction and integrity Zonal

More information

Riser less Light Well Intervention (RLWI) - "A success for reducing OPEX - cost and increasing oil recovery for subsea completed fields"

Riser less Light Well Intervention (RLWI) - A success for reducing OPEX - cost and increasing oil recovery for subsea completed fields Classification: Internal Status: Draft Riser less Light Well Intervention (RLWI) - "A success for reducing OPEX - cost and increasing oil recovery for subsea completed fields" Underwater Technology Conference

More information

New Generation of Deepwater BOP Stacks. Dominique Allegre CAMERON Paris, October 23rd 2013

New Generation of Deepwater BOP Stacks. Dominique Allegre CAMERON Paris, October 23rd 2013 New Generation of Deepwater BOP Stacks Dominique Allegre CAMERON Paris, October 23rd 2013 Agenda: Evolution of Standards API Standard 53 RP 17W New Equipment & Technology Developments: Shearing Technology

More information

Deepwater Horizon Accident Investigation Report

Deepwater Horizon Accident Investigation Report Deepwater Horizon Accident Investigation Report September 8, 2010 This is the report of an internal BP incident investigation team. The report does not represent the views of any individual or entity other

More information

Irresponsible of Statoil

Irresponsible of Statoil Irresponsible of Statoil Having reviewed all the available information, Bellona feels it is irresponsible of Statoil to resume production at Gullfaks C. All production from the Gullfaks C platform was

More information

STANDARD. Subsea equipment and components DNVGL-ST-0035:2014-08 DNV GL AS

STANDARD. Subsea equipment and components DNVGL-ST-0035:2014-08 DNV GL AS STANDARD DNVGL-ST-0035:2014-08 Subsea equipment and components The electronic pdf version of this document found through http://www.dnvgl.com is the officially binding version. The documents are available

More information

BOP Basic Safety Functions. Katrine Harsem Lund Principal Engineer, Department Manager Scandpower AS 2011.10.11

BOP Basic Safety Functions. Katrine Harsem Lund Principal Engineer, Department Manager Scandpower AS 2011.10.11 BOP Basic Safety Functions Katrine Harsem Lund Principal Engineer, Department Manager Scandpower AS 2011.10.11 Deepwater Horizon Deepwater Horizon Agenda What is a BOP/BOP Stack Safety Functions for a

More information

Deepwater Horizon Disaster

Deepwater Horizon Disaster Deepwater Horizon Disaster Professor Satish Nagarajaiah Dept. of Civil & Env. Eng., Dept. of Mechanical Eng. & Material Sc. Rice University, Houston, TX, USA Satish.Nagarajaiah@rice.edu Member, Deepwater

More information

Description. ACTIVITY GROUP Advertising A-6-002. Air- Conditioning related services A-6-001. Architecture A-4-001. Aviation

Description. ACTIVITY GROUP Advertising A-6-002. Air- Conditioning related services A-6-001. Architecture A-4-001. Aviation CODE A-1-001 A-2-001 A-3-001 A-4-001 A-5-001 A-5-002 A-6-001 A-6-002 A-7-001 A-7-002 A-7-003 A-7-004 A-7-005 A-7-006 A-7-007 A-7-008 A-7-009 A-7-010 A-7-011 A-8-001 A-8-002 A-9-001 ACTIVITY GROUP Advertising

More information

Send your email directly to oseghaleokohue@chesssubseaengineering.com

Send your email directly to oseghaleokohue@chesssubseaengineering.com Welcome to Chess Engineering Virtual Office - EVO Our engineering virtual office assistants are highly trained and provide a number of engineering support services depending on your EPIC business needs.

More information

An Approach To Oil Spill Containment For Floating Drilling Operations In Canadian Beaufort Sea Pack Ice Conditions

An Approach To Oil Spill Containment For Floating Drilling Operations In Canadian Beaufort Sea Pack Ice Conditions For Floating Drilling Operations In Canadian Beaufort Sea Pack Ice Conditions Canada - US Northern Oil and Gas Research Forum Calgary, Alberta December 2 nd, 2010 An Overview An Overview Of Same Season

More information

Assessment of dynamic barriers in oil/gas well operations

Assessment of dynamic barriers in oil/gas well operations Assessment of dynamic barriers in oil/gas well operations Vurdering av dynamiske barrierer i olje/gass brønner Jan Runar Tangstad Subsea Technology Submission date: September 2014 Supervisor: Marvin Rausand,

More information

Ceiba Field Early Production System. Cameron MOSAIC Systems

Ceiba Field Early Production System. Cameron MOSAIC Systems MOSAIC Certified Ceiba Field Early Production System Cameron MOSAIC Systems for the Ceiba Field Early Production System The Ceiba Field Early Production System Nigeria 0 100 KM Niger Delta C B D E Malabo

More information

The Competitive Edge. The Foundation For Competing

The Competitive Edge. The Foundation For Competing Passion - Creativity - Innovation - Initiative - Intellect - Dedication - Compliance - The Competitive Edge The Foundation For Competing Statoil s Subsea Technology Strategy, with selected technology challenges

More information

BOP PRESSURE TESTING PROCEDURE

BOP PRESSURE TESTING PROCEDURE 0 Discuss Operator BOP requirements WITH RIG MANAGER. Insure that all Romfor's BOP equipment is tested consistent with Romfor's policy. This may require Nabors to incur the cost for the testing subcontractor

More information

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM

WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM WellCAP IADC WELL CONTROL ACCREDITATION PROGRAM WORKOVER & COMPLETION OPERATIONS CORE CURRICULUM AND RELATED FORM WCT-2WF FUNDAMENTAL LEVEL The purpose of the core curriculum is to identify a body of knowledge

More information

SPE/IADC WELL CONTROL ASIA PACIFIC 2009 Velocity string installation in deep live gas wells.

SPE/IADC WELL CONTROL ASIA PACIFIC 2009 Velocity string installation in deep live gas wells. SPE/IADC WELL CONTROL ASIA PACIFIC 2009 Velocity string installation in deep live gas wells. Koper Mark & Mahmmed Kindi, Petroleum Development Oman LLC; John Brumfield, Halliburton; Bruce Mecleod, RedSpider.

More information

FIBER-OPTIC SENSING TECHNOLOGIES

FIBER-OPTIC SENSING TECHNOLOGIES PRODUCTION ENHANCEMENT FIBER-OPTIC SENSING TECHNOLOGIES FOR WELL MONITORING TO RESERVOIR MANAGEMENT Solving challenges. A H A L L I B U R T O N S E R V I C E Fiber-Optic Sensing Technologies CUTTING-EDGE

More information

An Introduction to Well Integrity

An Introduction to Well Integrity An Introduction to Well Integrity Rev 0, 04 December 2012 0 Preface This document has been prepared as a joint project between members of the Norwegian Oil and Gas Association's Well Integrity Forum (WIF)

More information

Department of the Interior

Department of the Interior Thursday, October 14, 2010 Part III Department of the Interior Bureau of Ocean Energy Management, Regulation and Enforcement 30 CFR Part 250 Oil and Gas and Sulphur Operations in the Outer Continental

More information

number 2) proposed well's type, location, elevation, total depth, etc. 3) site inspection, 2) assess the adequacy of the proposed engineering

number 2) proposed well's type, location, elevation, total depth, etc. 3) site inspection, 2) assess the adequacy of the proposed engineering APPENDIX 8 - FORMS USED IN THE OIL, GAS AND SOLUTION MINING PROGRAM Application for Permit to Drill, Deepen, Plug Back or Convert a Well Subject to the Oil, Gas and Solution Mining Law (185-12-5). - Applicant

More information

HIPPS Application in the Gulf of Mexico. Christopher Lindsey-Curran BP Senior Subsea Engineer

HIPPS Application in the Gulf of Mexico. Christopher Lindsey-Curran BP Senior Subsea Engineer HIPPS Application in the Gulf of Mexico Christopher Lindsey-Curran BP Senior Subsea Engineer Agenda Introduction and background HIPPS overview Codes and standards System design Regulatory issues Conclusions

More information

WELL COMMANDER Versatile multi-cycle ball-activated drilling valve for mitigating downhole hazards

WELL COMMANDER Versatile multi-cycle ball-activated drilling valve for mitigating downhole hazards WELL COMMANDER Versatile multi-cycle ball-activated drilling valve for mitigating downhole hazards Note: Operating instructions updated July 2014 WELL COMMANDER: Versatile multicycle ball-activated drilling

More information

PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA

PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA PRESS KIT IVAR AASEN DET NORSKE OLJESELSKAP ASA Table of content 1. INTRODUCTION... 2 1.1. Purpose of document... 2 1.2. Det norske oljeselskap... 2 1.3. HSE... 2 2. ABOUT THE IVAR AASEN FIELD... 2 2.1.

More information

The Technology Challenge. Agenda - The Technology Challenge

The Technology Challenge. Agenda - The Technology Challenge The Technology Challenge British and Norwegian Oil and Gas Industry Collaboration Conference R. Rasmus Sunde Executive Vice President London, October 26, 2005 Agenda - The Technology Challenge Overall

More information

Drill Cutting, Mud and Slurry Handling Oil & Gas Industry

Drill Cutting, Mud and Slurry Handling Oil & Gas Industry Drill Cutting, Mud and Slurry Handling Oil & Gas Industry Natural gas production platform Åsgard B (Photo Øyvind Hagen, Statoil Petroleum ASA) Drill Cuttings Handling Storage and Pumping on Rigs Since

More information

NORSOK STANDARD D-010 Rev. 3, August 2004. Well integrity in drilling and well operations

NORSOK STANDARD D-010 Rev. 3, August 2004. Well integrity in drilling and well operations NORSOK STANDARD D-010 Rev. 3, August 2004 Well integrity in drilling and well operations This NORSOK standard is developed with broad petroleum industry participation by interested parties in the Norwegian

More information

Subsea Technology. Alain Marion, Senior VP Assets & Subsea Technology. Investor Day in Brazil, October 4, 2011

Subsea Technology. Alain Marion, Senior VP Assets & Subsea Technology. Investor Day in Brazil, October 4, 2011 Subsea Technology Alain Marion, Senior VP Assets & Subsea Technology Investor Day in Brazil, October 4, 2011 Subsea Technology Technip s Commitment to Subsea R&D Technip Leadership Position Emerging Technologies

More information

Solving challenges. Drill out solutions Package

Solving challenges. Drill out solutions Package Solving challenges. Drill out solutions Package Why Choose Halliburton for your Drill Out Challenges? Engineered solution package coupled with next generation surface equipment to maximize efficiency,

More information

Hydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009

Hydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009 Hydraulic Fracturing Operations Well Construction and Integrity Guidelines API GUIDANCE DOCUMENT HF1 FIRST EDITION, OCTOBER 2009 Hydraulic Fracturing Operations Well Construction and Integrity Guidelines

More information

Selection and Determination of Tubing and Production Casing Sizes

Selection and Determination of Tubing and Production Casing Sizes CHAPTER 3 Selection and Determination of Tubing and Production Casing Sizes OUTLINE 3.1 Overview 3.2 Overview of Nodal Analysis 3.3 Selection and Determination of Tubing and Production Casing Sizes for

More information

Setting a Global Standard. www.dril-quip.com. SS Series Subsea Wellhead Systems

Setting a Global Standard. www.dril-quip.com. SS Series Subsea Wellhead Systems Setting a Global Standard www.dril-quip.com SS Series Subsea Systems Table of Contents Systems SS-15 System...2 SS-15 RLD System...3 SS-15ES System...4 SS-15 BigBore II...5 SS-10C and SS-10 System...6

More information

We build products that extract oil and gas

We build products that extract oil and gas Manufacturing and Machining Services We build products that extract oil and gas Throughout the world s oil and gas producing regions, operators and service companies alike rely on Hunting s vast array

More information

News Volume 1 Edition 1

News Volume 1 Edition 1 News Volume 1 Edition 1 Providing Insight Onsite A New Dimension to Process Mapping of Subsea Separator Vessels with The TRACERCO Profiler By Magne K. Husebø, General Manager, Tracerco Norge AS Co-authors:

More information

OFFSHORE FIELD DEVELOPMENT

OFFSHORE FIELD DEVELOPMENT OFFSHORE FIELD DEVELOPMENT OPTIONS & STRATEGY By: Nguyen Ngoc Hoan M.Sc of Petroleum Engineering Hoannn@pidc.com.vn PRESENTATION CONTENT Field Development Consideration Field Development Options & Strategy

More information

NFLB høstkonferansen 2011

NFLB høstkonferansen 2011 part of Aker NFLB høstkonferansen 2011 High Pressure Manifolds & Well Control Arild Grasdal / Knut Bakke Victoria Hotel Stavanger 17. September 2011. 2011 Aker Solutions part of Aker STEP Offshore - Mud

More information

12/08/2015. Introduction to Subsea Production Systems. Module structure. 08 Production Control Systems. August 2015

12/08/2015. Introduction to Subsea Production Systems. Module structure. 08 Production Control Systems. August 2015 OIL & GAS Introduction to Subsea Production Systems 08 Production Control Systems August 2015 DNV GL 2013 2015 August 2015 SAFER, SMARTER, GREENER Module structure Section 1 Introduction to control systems

More information

Technion Israel Institute of Technology Masters of Engineering in Energy Engineering

Technion Israel Institute of Technology Masters of Engineering in Energy Engineering Technion Israel Institute of Technology Masters of Engineering in Energy Engineering Curriculum for a Specialization in Natural Gas & Petroleum Engineering (NG&PE) Introduction The Masters in Engineering

More information

Operations in the Arctic areas? New challenges: Exploration Development Production

Operations in the Arctic areas? New challenges: Exploration Development Production Operations in the Arctic areas? New challenges: Exploration Development Production The oil and gas cycle Life cycle of oil and gas (time) 1) 2) 3) 4) 5) 6) Activity In-house study and get licenses: Find

More information

Maersk Resilient. Maximised drilling efficiency and uptime. Optimised for concurrent activities

Maersk Resilient. Maximised drilling efficiency and uptime. Optimised for concurrent activities Maersk Resilient Maximised drilling efficiency and uptime Optimised for concurrent activities Maersk Resilient TYPE MSC CJ50-X100 MC, 350 ft jack-up drilling rig BUILT Keppel FELS, 2008 CLASS American

More information

Master thesis WELL INTEGRITY OF SUBSEA WELLS DURING LIGHT WELL INTERVENTIONS. Stud.techn. Sigbjørn Tornes Birkeland. June 2005

Master thesis WELL INTEGRITY OF SUBSEA WELLS DURING LIGHT WELL INTERVENTIONS. Stud.techn. Sigbjørn Tornes Birkeland. June 2005 WELL INTEGRITY OF SUBSEA WELLS DURING LIGHT WELL INTERVENTIONS By Stud.techn. Sigbjørn Tornes Birkeland June 2005 Preface This thesis constitutes the results of the 10 th semester of my master degree program

More information

RISER SYSTEMS. Our world class innovation solving your riser challenges

RISER SYSTEMS. Our world class innovation solving your riser challenges RISER SYSTEMS Our world class innovation solving your riser challenges OUR WORLD CLASS INNOVATION SOLVING YOUR RISER contents Riser Analysis 3 Subsea Riser Systems 4 Connectors (Subsea and Surface) Surface

More information

E-Line and Braided Line. E-Line Open Hole wireline

E-Line and Braided Line. E-Line Open Hole wireline E-Line and Braided Line E-Line Open Hole wireline Braided Line More strength Less feel Harder to seal Much harder to fish Braided line stronger (2800 to 3500 lb working strength, but less feel when fishing

More information

Ageing and life extension

Ageing and life extension Ageing and life extension April 7th workshop Background NPD recommended NORSOK AGn to start developing guidelines for life extension (2000). NPD initiated a PhD study on ageing and life extension of offshore

More information

NORSOK STANDARD DRILLING & WELL OPERATIONS

NORSOK STANDARD DRILLING & WELL OPERATIONS NORSOK STANDARD DRILLING & WELL OPERATIONS D-010 Please note that whilst every effort has been made to ensure the accuracy of the NORSOK standards neither OLF nor TBL or any of their members will assume

More information

SIEM WIS AS. Siem WIS. UTC June 2008 By Jan Atle Andresen

SIEM WIS AS. Siem WIS. UTC June 2008 By Jan Atle Andresen Siem WIS UTC June 2008 By Jan Atle Andresen Agenda Background Challenges- Technology- Solutions Siem WIS background Well Intervention Solutions AS (Siem WIS), was established in February 2005 and is located

More information

Subsea Systems. in Norway. Fueling the future with comprehensive technologies and support services for the most extreme conditions.

Subsea Systems. in Norway. Fueling the future with comprehensive technologies and support services for the most extreme conditions. GE Oil & Gas Subsea Systems Subsea Systems in Norway Fueling the future with comprehensive technologies and support services for the most extreme conditions Snøhvit Fueling the future with subsea systems

More information

Texas Oil Tools Subsea Well Intervention Equipment

Texas Oil Tools Subsea Well Intervention Equipment Texas Oil Tools Subsea Well Intervention Equipment Leading specialty manufacturers and suppliers of pressure control equipment At NOV, we ve come a long way in establishing ourselves as one of the leading

More information

117 NORWEGIAN OIL AND GAS RECOMMENDED GUIDELINES FOR WELL INTEGRITY

117 NORWEGIAN OIL AND GAS RECOMMENDED GUIDELINES FOR WELL INTEGRITY 117 NORWEGIAN OIL AND GAS RECOMMENDED GUIDELINES FOR WELL INTEGRITY No.: 117 Established: 01.10.08 Revision no: 4 Date revised: 06.06.2011 Page: 2 Preface This guideline is supported by Norwegian Oil and

More information

Oil and gas fields in norway Industrial Heritage plan

Oil and gas fields in norway Industrial Heritage plan survey of all the areas, fields and installations on the Norwegian continental shelf. It also describes developments in these waters since the 1960s, including why Norway was able to become an oil nation,

More information

API Std 53 - Blowout Prevention Equipment Systems for Drilling Wells Last update: August 12, 2015

API Std 53 - Blowout Prevention Equipment Systems for Drilling Wells Last update: August 12, 2015 6.1.2.12 53-03-15 Referring to Section 6.1.2.12, can a surface BOP stack arrangement with one annular, one blind shear ram, and two pipe rams, with the fifth device being optional, be considered a Class

More information

Advancing Reservoir Performance. Wellbore Cleanup Tools and Displacement Chemicals

Advancing Reservoir Performance. Wellbore Cleanup Tools and Displacement Chemicals Advancing Reservoir Performance Wellbore Cleanup Tools and Displacement Chemicals Wellbore Cleanup Tools and Displacement Chemicals Introduction Since the first oil well was drilled in the late 19th century,

More information

PETROLEUM PRODUCTION MASTERCLASSES

PETROLEUM PRODUCTION MASTERCLASSES PETROLEUM PRODUCTION MASTERCLASSES New For 2010! One Date Only Limited Places Available Book Now! Offshore Safety & Risk Management for the Oil Industry & Gas Industry 21st and 22nd of February 2011, New

More information

FLOWBACK & PRODUCTION TESTING SERVICES

FLOWBACK & PRODUCTION TESTING SERVICES FLOWBACK & PRODUCTION TESTING SERVICES PREPARED DEPENDABLE EFFICIENT CATHEDRAL ENERGY SERVICES PROVIDES FLOWBACK AND PRODUCTION TESTING SOLUTIONS TO NORTH AMERICAN ENERGY COMPANIES. FLOWBACK SERVICES SERVICES

More information

Directive 059: Well Drilling and Completion Data Filing Requirements

Directive 059: Well Drilling and Completion Data Filing Requirements Directive 059 Directive 059: Well Drilling and Completion Data Filing Requirements December 19, 2012 Effective June 17, 2013, the Energy Resources Conservation Board (ERCB) has been succeeded by the Alberta

More information

Understanding Well Construction and Surface Footprint

Understanding Well Construction and Surface Footprint Understanding Well Construction and Surface Footprint Well Construction Timeline Well Site Planning & Preparation Drilling Stage 1: Planning and Preparation Acquire Surface Lease Agreement Determination

More information

Translated Publications

Translated Publications CHINESE * Spec Q1 Manufacturing Organizations for the Petroleum and Natural Gas Industry translation of Spec Q1. 9th Edition June 2013 Product Number: G0Q109C Price: $84.00 Spec Q2 Service Supply Organizations

More information

How to achieve and maintain market leadership position in subsea from Norway

How to achieve and maintain market leadership position in subsea from Norway How to achieve and maintain market leadership position in subsea from Norway Subsea Valley Conference Telenor Arena, 2. April 2014 Arild Selvig 2 nd April 2014 FMC Technologies NCS A lot of Firsts in subsea

More information

Code of Practice for Coal Seam Gas

Code of Practice for Coal Seam Gas Code of Practice for Coal Seam Gas Well Integrity DEPARTMENT OF TRADE & INVESTMENT, REGIONAL INFRASTRUCTURE & SERVICES RESOURCES & ENERGY SEPTEMBER 2012, WWW.RESOURCES.NSW.GOV.AU Title: NSW Code of Practice

More information

Drilling, Completion & Well Intervention and its relation to Geology

Drilling, Completion & Well Intervention and its relation to Geology Drilling, Completion & Well Intervention and its relation to Geology Kjell Kåre Fjelde A more detailed presentation on drilling & geology can be found on the resource CD Exercise related to the Festningen

More information

ADX ENERGY. Sidi Dhaher Well test Briefing Live Webcast, 4 July 2012. Wolfgang Zimmer, Paul Fink

ADX ENERGY. Sidi Dhaher Well test Briefing Live Webcast, 4 July 2012. Wolfgang Zimmer, Paul Fink ADX ENERGY Sidi Dhaher Well test Briefing Live Webcast, 4 July 2012 Wolfgang Zimmer, Paul Fink Decision to test ASX announcement, 3 October 2011 2 Decision to test: First Evidence Wellsite geologists (highly

More information

Deepwater Horizon Summary of Critical Events, Human Factors Issues and Implications

Deepwater Horizon Summary of Critical Events, Human Factors Issues and Implications Deepwater Horizon Summary of Critical Events, Human Factors Issues and Implications 23 Sept 2010 Alison Hubbard David Embrey Deepwater Horizon Summary of Critical Events, Human Factors Issues and Healthcare

More information

havard.bo[at] gmail.com

havard.bo[at] gmail.com E U R O P E A N C U R R I C U L U M V I T A E F O R M A T PERSONAL INFORMATION Name BØ, HÅVARD Address (****) STAVANGER NORWAY Telephone **** E-mail havard.bo[at] gmail.com Nationality Norwegian Date of

More information

Main areas of services are:

Main areas of services are: Pakistan Foundation for the Advancement of Engineering & Technology provides superior solutions to Oil & Gas Companies/ industry upstream, production, transportation, refining and related industries. Upstream

More information

Long Distance Challenges -Control Systems

Long Distance Challenges -Control Systems Long Distance Challenges -Control Systems Vidar Sten-Halvorsen, FMC Holmenkollen Park Hotel Oslo February 2008 Challenges for ultra long step out distances Challenges and solutions for traditional systems

More information

Cellar Tech Containment Well Cellar Systems www.cellartech.com

Cellar Tech Containment Well Cellar Systems www.cellartech.com Sealed Well Cellars are protected by US patent 7637692, 7987904, 8127837, and 8256505. Additional US patents pending. Basic Containment Well Cellar Sealed Well Cellars are protected by US patent 7637692,

More information

RESEARCH REPORT 013. Hazard assessment of well operations from vessels HSE

RESEARCH REPORT 013. Hazard assessment of well operations from vessels HSE HSE Health & Safety Executive Hazard assessment of well operations from vessels Prepared by Team Energy Resources Limited for the Health and Safety Executive 2002 RESEARCH REPORT 013 HSE Health & Safety

More information

TULLOW OIL SUPPLY CHAIN

TULLOW OIL SUPPLY CHAIN TULLOW OIL SUPPLY CHAIN Whether you are an international supplier looking for opportunities across the countries in which we operate, or a local supplier, we are interested in hearing from you. The following

More information

Pressurised Pipeline Repair or Modification Enabled by Double Block And Bleed Isolation Tools

Pressurised Pipeline Repair or Modification Enabled by Double Block And Bleed Isolation Tools STATS GROUP Process & Pipeline Integrity Solutions Pressurised Pipeline Repair or Modification Enabled by Double Block And Bleed Isolation Tools Dale Millward Director EPRS & Subsea Services Presentation

More information

Schedule of. Onshore Petroleum Exploration. and. Production Safety Requirements. August 1992

Schedule of. Onshore Petroleum Exploration. and. Production Safety Requirements. August 1992 Schedule of Onshore Petroleum Exploration and Production Safety Requirements August 1992 SCHEDULE OF ONSHORE PETROLEUM EXPLORATION AND PRODUCTION SAFETY REQUIREMENTS (August 92) 1. Preliminary Title 101.

More information

DecisionSpace Well Engineering Software

DecisionSpace Well Engineering Software DATA SHEET DecisionSpace Well Engineering Software DecisionSpace Drilling & Completions Key features Configure the right tools to drill any type of well Dramatically simple to use, complete complex fluids

More information

Design of an Electric X-mas Tree Gate Valve Actuator

Design of an Electric X-mas Tree Gate Valve Actuator Design of an Electric X-mas Tree Gate Valve Actuator Einar H. Winther-Larssen Master of Science in Engineering Cybernetics Submission date: June 2007 Supervisor: Ole Morten Aamo, ITK Co-supervisor: Voula

More information