Structural Inspection Foundations

Size: px
Start display at page:

Download "Structural Inspection Foundations"

Transcription

1 Structural Inspection Foundations 0211 Footings Concrete pad and continuous footings The concrete footings consist of continuous strip footings at the building perimeter of the following sizes: 16 wide x 8 deep at the original school building; 18 wide x 8 deep footing at the gymnasium addition; 22 wide x 8 deep at the southwest wall of the gymnasium; and 14 wide x 8 deep at gymnasium shear walls and at the connection between the gymnasium and the main school building. Spread footings varying in size from 3 x 3 x 16 deep to 7 x 7 x 20 deep at the building interior. The concrete footings were not visible for inspection, however based on the lack of settlement exhibited by the structure they appear to be in good condition. Remaining life expectancy: 10+ years. No deficiencies noted for this building system Foundation Walls Foundation walls, basement walls, and pilasters Reinforced concrete foundation walls below grade. At the original building the walls are typically 8 thick at perimeter walls extending to footings immediately beneath the basement slab. At the gymnasium addition the foundation walls vary in thickness being 6 thick at the connector between the gymnasium and the main school building and 8 thick at the perimeter of the gymnasium. At the gymnasium the foundation walls extend to footings that have bottom of footing 4 feet below exterior grade. Foundation walls in general cannot be inspected as they are below ground level. Their condition can be assumed to be good as there is little or no evidence of settlement or distress. Remaining life expectancy: 10+ years May 2005 Harborview Elementary School Condition Survey Report Page 42 of 210

2 Structural Inspection Foundations Deficiency Spalled West Gym Foundation Wall The corner of the foundation wall has spalled. Deficiency category: RR Remedy Repair spalled area with repair grout. Estimated Construction Cost: $500 May 2005 Harborview Elementary School Condition Survey Report Page 43 of 210

3 Structural Inspection Foundations 0220 Slab on Grade Standard or structural slabs, trenches, pits, and pads The building has a 4 inch thick slab on grade in the basement and in the gymnasium. Plans show that at the gymnasium reinforcement is #3 bars at 12 on center each way and at the original school building the basement slab reinforcement is 1/2 diameter bars at 18 on center each way. No expansion joints are noted on the plans except that the basement slab is not tied to foundation walls. Although the slab on grade slabs are typically covered and not capable of being inspected, slab condition is believed to be acceptable as there is little sign of distress. The gymnasium floor appears to be uneven but this could be the floor covering or some minor settlement. Remaining life expectancy: 10+ years No deficiencies noted for this building system. May 2005 Harborview Elementary School Condition Survey Report Page 44 of 210

4 Structural Inspection Floor Structure 0312 Elevated Floors Structural floor diaphragm, supporting columns, and bracing The floor construction at classrooms at the main level floor and upper level floors consists primarily of open web steel joists supporting a concrete covered, metal pan deck. The east and west exterior concrete walls and lines of reinforced concrete beams above central corridor walls support the joists. Beams are supported by reinforced concrete columns. The main floor toilet room floor above the boiler room is a structural concrete slab. The corridor floors consist of a reinforced concrete slab supported by the reinforced concrete beams on each side of the corridors. The second floor in the gymnasium addition is similar to the floor construction in the main building, except supporting beams and columns are steel. There is a concretecovered, steel deck supported by open web steel joists, which, in turn, are supported by steel beams. Either steel columns or pre cast exterior wall panels support the steel beams. Floors structure appears to be in good condition. Remaining life expectancy: 10+ years. May 2005 Harborview Elementary School Condition Survey Report Page 45 of 210

5 Structural Inspection Floor Structure Deficiency Spalled Floor above Boiler Room There is a large spalled area around pipe penetrations at the underside of the elevated floor slab above the boiler room. Deficiency category: RR Remedy Patch spalled area with grout. Estimated Construction Cost: $600 May 2005 Harborview Elementary School Condition Survey Report Page 46 of 210

6 Structural Inspection Floor Structure Deficiency Lateral Load Resisting System For the main building the lateral load resisting system consists of a concrete moment frame. Building code provisions for the design of concrete moment resisting frames has changed significantly since this structure was originally designed. The structure should be analyzed to determine if a seismic retrofit is appropriate. The gymnasium lateral load resisting system is a shear wall system, It was analyzed in 2003 and found to be relatively acceptable. Some minor framing improvements were made after that study. Deficiency category: C Remedy Perform analysis of lateral load resisting system and retrofit main building if needed. Estimated Construction Cost: $15,000 for lateral load analysis $ 300,000 for retrofit (based on new shear wall costs May 2005 Harborview Elementary School Condition Survey Report Page 47 of 210

7 Structural Inspection Floor Structure 0314 Ramps Ramp structure and railings There is an elevated ramp structure (material) at the main entry. This ramp was placed above the original stairs and floor in the 1983 renovations. The ramp condition is good. Remaining life expectancy: 10+ years. No deficiencies noted for this building system. May 2005 Harborview Elementary School Condition Survey Report Page 48 of 210

8 Structural Inspection Floor Structure 0315 Special Floors Stages, platforms, computer floors, utility distribution floors, etc. The gymnasium has a stage at the northeast corner of the gym. The stage floor consists of 1x decking supported by 2x tongue and groove decking that spans across the stud walls between the storage cabinets below. The floor framing spans approximately 45 inches. The floor surface is worn and there are locations where the floor deflects significantly. Remaining life expectancy: 5 years. Deficiency No Photo Floor is worn and deflects significantly. Deficiency category: RR Remedy Remove existing 1x surface and replace. Verify that underlying support is not damaged. If necessary add plywood over the 2x decking. Estimated Construction Cost: $5,900 May 2005 Harborview Elementary School Condition Survey Report Page 49 of 210

9 Structural Inspection Roof Structure 0322 Low Slope Roof Structural roof diaphragm, supporting columns, and bracing The roof of the school building consists of open web steel joists supporting a nominal 2 inch thick, tongue and groove timber deck at the north half of the building (original construction). At the south half (1956 addition) of the main building open web steel joists support a plywood deck. Steel beams bearing on concrete columns on each side of the central corridor and the exterior walls support the joists. The condition of the roof structure appears to be adequate. Remaining life expectancy: likely more than 15 years. The gymnasium roof is comprised of open web steel joists, with a single gable of low slope, supporting a steel deck, which supports insulation and an adhered membrane. The roof joists are supported by exterior pre cast wall panels which rest on the perimeter foundation walls. A lateral load path evaluation was performed on the gymnasium addition in 2002 and found the lateral resisting system to be acceptable with minor improvements. The condition of the roof structure appears to be adequate. Remaining life expectancy: likely more than 15 years. No deficiencies noted for this building system. May 2005 Harborview Elementary School Condition Survey Report Page 50 of 210

10 Structural Inspection Stairs 0331 Stairs Stair structure The north end, south end and central stairs are reinforced concrete. The condition of the stair structure is good except for a spall at the underside of the stairs between the gymnasium level and the main floor, at the south end. There are concrete stairs at the second level of the connector between the gymnasium and the main building (on the gymnasium addition plans this room is noted as the music art room). This same room has a timber framed egress stairway between the stage area and the storage room. Remaining life expectancy: 10+ years. May 2005 Harborview Elementary School Condition Survey Report Page 51 of 210

11 Structural Inspection Stairs Deficiency Spalled Concrete Under South Stairs Deficiency category: RR Remedy Grout spalled area. Estimated construction cost: $600 May 2005 Harborview Elementary School Condition Survey Report Page 52 of 210

12 Structural Inspection Stairs 0333 Ladders Ship s ladders and other fixed ladders There are the following fixed ladders: 1) There is an interior fixed ladder to access the roof in a second floor communication room, 2) There is an exterior ladder from the main building high roof to the lower roof at the connection to the gymnasium. The condition of the interior ladder is good. The exterior ladder is rusted, but sound. Remaining life expectancy: greater than 15 years No deficiencies noted for this building system.. May 2005 Harborview Elementary School Condition Survey Report Page 53 of 210

SECTION 3 ONM & J STRUCTURAL ANALYSIS

SECTION 3 ONM & J STRUCTURAL ANALYSIS Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION

More information

EAST LYME HIGH SCHOOL

EAST LYME HIGH SCHOOL Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed

More information

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA

STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA STRUCTURAL ASSESSMENT REPORT BOLINAS MARINE STATION - BOLINAS, CALIFORNIA College of Marin c/o Swinerton Management & Consulting P.O. Box 144003 835 College Avenue, Building MS-3 Kentfield, California

More information

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland

Building Condition Assessment: 109-111 North Howard Street Baltimore, Maryland KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,

More information

Technical Assignment 2 TABLE OF CONTENTS

Technical Assignment 2 TABLE OF CONTENTS 2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17

More information

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and

More information

14 September 2015. Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102

14 September 2015. Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102 Sarah Zorn Planning and Economic Development 25 West Fourth Street, Ste. 1100 St. Paul, MN 55102 Project No.: 15538.00 Re: Structural Condition Review of the building at 700 4 th St. E. Dear Sarah: We

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

Building Foundation and Structure

Building Foundation and Structure Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original

More information

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael

More information

PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007

PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007 PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT November 2007 PURPOSE OF INVESTIGATION Determine possible locations of moisture intrusion into and through facade. Determine cause of horizontal and vertical

More information

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components

Facility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development

More information

Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland

Building Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,

More information

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE

201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,

More information

Engineers, Civil Structural Survey

Engineers, Civil Structural Survey Engineers, Civil Structural Survey 317 STREET 0 6 3 6 0 886-1966 886-9165 FAX. September 1 1 Mr. Alan Bergren City Manager City of Norwich Broadway, Floor Norwich, 06360 Re: Limited Structural Condition

More information

The minimum reinforcement for the stem wall is the placement of:

The minimum reinforcement for the stem wall is the placement of: PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20

More information

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona

Project Report. Structural Investigations Hotel del Sol Yuma, Arizona Project Report Structural Investigations Yuma, Arizona Prepared by: 2619 Spruce Street Boulder, CO 80302 303-444-3620 Prepared for: Principle Engineering Group, Inc. 833 East Plaza Circle, Suite 100 Yuma,

More information

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

Structural Assessment Report

Structural Assessment Report Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive

More information

What is Seismic Retrofitting?

What is Seismic Retrofitting? What is Seismic Retrofitting? SEISMIC RETROFITTING A Seismic Retrofit provides existing structures with more resistance to seismic activity due to earthquakes. In buildings, this process typically includes

More information

4. ANCHOR BOLTS AND STRAPS a. ½" anchor bolts shall be embedded 7" into concrete a maximum of 6' on center and 12" from corners and ends of plates.

4. ANCHOR BOLTS AND STRAPS a. ½ anchor bolts shall be embedded 7 into concrete a maximum of 6' on center and 12 from corners and ends of plates. GENERAL CODE REQUIREMENTS (BASEMENTS) 1. FOOTINGS a. Footings shall be below frost line depth (42"). b. For an 8" foundation wall, footings shall be no less than 8" deep and 16" wide. c. Steel reinforcement

More information

6 RETROFITTING POST & PIER HOUSES

6 RETROFITTING POST & PIER HOUSES Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This

More information

Certification: Building Plans Examiner. Exam ID: B3

Certification: Building Plans Examiner. Exam ID: B3 Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building

More information

OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007

OTTAWA CIVIC CENTRE & NORTH SIDE STANDS LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007 OTTAWA CIVIC CENTRE & NORTH SIDE STANDS at LANSDOWNE PARK FRANK CLAIR STADIUM STRUCTURAL ADEQUACY REPORT 2007 for CITY OF OTTAWA REAL PROPERTY ASSET MANAGEMENT prepared by ADJELEIAN ALLEN RUBELI LIMITED

More information

Facility Assessment for. 11801 East Main Street, Huntley, IL

Facility Assessment for. 11801 East Main Street, Huntley, IL Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested

More information

School Construction Authority Architecture & Engineering

School Construction Authority Architecture & Engineering SCOPING GUIDELINES 1.0 GENERAL GUIDELINES 2.0 BUILDING ENVELOPE SCOPING GUIDELINES 3.0 CATEGORIES AND COMPONENTS: The Flood Elimination/Below Grade Capital Category may include some or all of the following

More information

Braselton Bros. Store Redevelopment 5134 HWY 53 BRASELTON, GA 30548 LEVEL 0 - DEMO & NEW PLAN. Room. Room. Room. Room. Room. Room. Room. Room.

Braselton Bros. Store Redevelopment 5134 HWY 53 BRASELTON, GA 30548 LEVEL 0 - DEMO & NEW PLAN. Room. Room. Room. Room. Room. Room. Room. Room. 1.d 2.d 3.d 4.d 1.d 2.d 3.d 4.d REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE, REPAIR, & REPLACE EXISTING STOREFRONT SYSTEMS D.1 D.2 REMOVE STAIR & INFILL WALL C.1 REMOVE DOOR &

More information

CHAPTER 6 CONSTRUCTION TYPES

CHAPTER 6 CONSTRUCTION TYPES CHAPTER 6 CONSTRUCTION TYPES SECTION 601 GENERAL 601.1 Scope. Provisions of this chapter shall govern the classification of construction type by materials and fire resistance of its elements and the use

More information

COMMONLY USED RESIDENTIAL BUILDING CODES

COMMONLY USED RESIDENTIAL BUILDING CODES COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section

More information

Re: Damages to Alaska Building from Legislative Information Office Construction

Re: Damages to Alaska Building from Legislative Information Office Construction 510 L Street Suite 200 Anchorage, AK 99501-1949 (907) 274-22362236 Phone (907) 274-25202520 Fax www.bbfm.com July 22, 2015 Jim Gottstein Alaska Building 406 G Street, Suite 206 Anchorage, AK 99501 Re:

More information

Report on Sanctuary/Chancel Crawl Space Inspection. St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove. Project No.

Report on Sanctuary/Chancel Crawl Space Inspection. St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove. Project No. Report on Sanctuary/Chancel Crawl Space Inspection St. John in The Wilderness, 2896 Old Lakeshore Road Bright s Grove Project No. E112056 1. Background St. John in the Wilderness (SJITW) is considering

More information

Mark Cramer Inspection Services, Inc.

Mark Cramer Inspection Services, Inc. Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction

More information

Chapter 3 Pre-Installation, Foundations and Piers

Chapter 3 Pre-Installation, Foundations and Piers Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory

More information

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs

The better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................

More information

Executive Summary. June 2005 Auke Bay Elementary School Condition Survey Report Page 4 of 228

Executive Summary. June 2005 Auke Bay Elementary School Condition Survey Report Page 4 of 228 Building History 1. The original building was built in 1968. It is essentially a 2 story building built into a hillside. A portion of the second floor steps up the hill a half level above the second floor

More information

Seattle Public Schools Building Excellence IV Projects Under Construction

Seattle Public Schools Building Excellence IV Projects Under Construction Seattle Public Schools Building Excellence IV Projects Under Construction Project Slide Number Arbor Heights Elementary School 2 Cascadia Elementary School & Robert Eagle Staff Middle School 13 Genesee

More information

Formwork for Concrete

Formwork for Concrete UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Formwork for Concrete Horizontal Formwork Design and Formwork Design

More information

APPLICANT: ORANGE COUNTY, NEW YORK

APPLICANT: ORANGE COUNTY, NEW YORK Figure 1 Div 1 3 rd Flr Leakage in County Executives Office Figure 2 Div 1 3 rd Flr Location 067 approximately 2 SF of visible mold growth above entrance to Room 341 Figure 3 Div 1 3 rd Flr Location 067

More information

Guernsey s Structural Engineering Experience

Guernsey s Structural Engineering Experience Guernsey s Structural Engineering Experience Foundation Settlement Issues: Trinity Valley Electric Cooperative, Kaufman, TX: Analyzed their headquarters facility for issues with soil movement that was

More information

Slavic Village Building Condition Review

Slavic Village Building Condition Review Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities

More information

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway:

~iffiui ~ Bridge Condition Survey. Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Texas Depadment of Transpo,tation Bridge Condition Survey Inspection Date: 21 May 2003 District: San Angelo County: Tom Green Highway: Irving Street Facility Name: Lone Wolf Bridge Structure Number: B00315-031

More information

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)

NCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003) NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:

More information

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit

Envelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed

More information

Hunter College school of Social Work Thesis Proposal

Hunter College school of Social Work Thesis Proposal Fall 2009 Hunter College school of Social Work Thesis Proposal To analyze how energy efficiency can be implemented using facade and green roof redesign. It ties structural engineering concepts with existing

More information

Renovating Your Basement

Renovating Your Basement building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Renovating Your Building America Report - 0309 2003 (revised 2007) Building Science Corporation Abstract:

More information

www.citiesinspection.com October 5, 2015 Dear Client,

www.citiesinspection.com October 5, 2015 Dear Client, www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.

More information

Building Construction. Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two

Building Construction. Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two Factors governing type selection Economics not necessarily the one that requires the least structural

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

STANDARD OPEN PATIO COVER

STANDARD OPEN PATIO COVER STANDARD OPEN PATIO COVER BUILDING & SAFETY DIVISION 201 E. LA HABRA BLVD. LA HABRA, CA 90631 62-90-9710 Call Before You Dig 1-800-227-2600 PLEASE NOTE: This information Bulletin is made available to assist

More information

Architectural Inspection Site Structures

Architectural Inspection Site Structures 0141 Freestanding Shelters Open air shelters not attached to the building. Bike rack shelter with bike racks: This 8'x30' structure is located on the north east side of the building on the wooded landscape

More information

4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections. Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls

More information

Chapter 6 ROOF-CEILING SYSTEMS

Chapter 6 ROOF-CEILING SYSTEMS Chapter 6 ROOF-CEILING SYSTEMS Woodframe roof-ceiling systems are the focus of this chapter. Cold-formed steel framing for a roof-ceiling system also is permitted by the IRC but will not be discussed;

More information

CLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.

CLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C. CLIENT Inspection Report 271 Front St. Alert Bay, B.C. Island Building Inspections 2013 V ANCOUVER I SLAND B. C. Elevation Photos For the Property at 271 Front Street Alert Bay, BC ELEVATION PICTURES Front

More information

DRAPER ELEMENTARY SCHOOL

DRAPER ELEMENTARY SCHOOL INITIAL YEAR BUILT 1953 BUILDING AREA 54,000 SF CURRENT PROGRAM CAPACITY 250 ENROLLMENT 2008 84 WARD 8 PROPOSED PROGRAM CAPACITY 325 Site Plan DRAPER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

Building Construction. Lightweight construction. Conventional Construction

Building Construction. Lightweight construction. Conventional Construction Ventilation 53 Building Construction The firefighter s ability to safely and efficiently ventilate a building through its roof will depend to some degree on the firefighter s understanding of roof construction.

More information

Whitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman.

Whitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman. Building Type Building Code Whitley Classroom Buildings BOCA, UBC, SBCCI, NEC, ADA Structural Support Outrigger construction standard, Whitley model classrooms. Main support beams to be 12 11.8# per lineal

More information

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings

More information

Energy Company Obligation (ECO): Technical Monitoring Questions

Energy Company Obligation (ECO): Technical Monitoring Questions Energy Company Obligation (ECO) Technical Monitoring Questions v1 30/05/2013 Energy Company Obligation (ECO): Technical Monitoring Questions Under ECO suppliers are required to instruct suitably qualified

More information

PROFESSIONAL ENGINEERING INSPECTIONS, INC.

PROFESSIONAL ENGINEERING INSPECTIONS, INC. PROFESSIONAL ENGINEERING INSPECTIONS, INC. P. O. BOX 271492 HOUSTON, TEXAS 77277 Registered Engineering Firm #1503 http://www.profengineering.com (713) 664-1264 July 8, 2004 Mr. Simple Samson 2831 Octoberfest

More information

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.

This handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances. Residential Decks Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org

More information

Simpson Engineering A state licensed engineering firm F-1607

Simpson Engineering A state licensed engineering firm F-1607 Simpson Engineering A state licensed engineering firm F-1607 4126 Allencrest 13901 Midway Lane, Dallas, Road, Texas Ste.102-136 75244 Telephone: 214-351-1637 Dallas, - Fax: TX 214-351-1639 75244-4388 Telephone:

More information

Residential Decks. Planning and Development Services Department

Residential Decks. Planning and Development Services Department Building Safety Division 8500 Santa Fe Drive Overland Park, KS 66212 (913) 895-6225 Fax (913) 895-5016 Email: permitservices@opkansas.org Planning and Development Services Department Residential Decks

More information

WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204

WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204 WEBSTER ELEMENTARY SCHOOL New Rochelle, New York Evaluation of Collapsed Ceiling Room 204 Structural Inspection Report Client: CSArch Architecture Engineering Construction Management 19 Front Street, Newburgh,

More information

Excerpts from the Canadian National Building Code (NBC)

Excerpts from the Canadian National Building Code (NBC) Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more

More information

POST AND FRAME STRUCTURES (Pole Barns)

POST AND FRAME STRUCTURES (Pole Barns) POST AND FRAME STRUCTURES (Pole Barns) Post and frame structures. The following requirements serve as minimum standards for post and frame structures within all of the following structural limitations:

More information

Seismic Retrofitting for School Buildings in Japan Nonstructual Seismic Retrofitting

Seismic Retrofitting for School Buildings in Japan Nonstructual Seismic Retrofitting Seismic Retrofitting for School Buildings in Japan Nonstructual Seismic Retrofitting for School Buildings in Japan 8 January 2009 Koichi Shinpo Director, Educational Facilities Research Center National

More information

SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST

SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000

More information

Building Condition Assessment Report

Building Condition Assessment Report Building Condition Assessment Report Asset C3c - Oak Terrace Cottage 121 Address Riverview Lands, 2601 Lougheed Highway, Coquitlam, BC. V5C 4J2 Construction Year Size (Gross Floor Area) 1920. 2,553 Sq.Ft.

More information

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14 Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318

More information

The Collapse of Building 7 by Arthur Scheuerman December 8, 06

The Collapse of Building 7 by Arthur Scheuerman December 8, 06 The Collapse of Building 7 by Arthur Scheuerman December 8, 06 WTC s Building 7 was a 47-story office building completed in 1987 by Silverstein Properties on land owned by the Port Authority. It was built

More information

Uncovered Decks & Porches

Uncovered Decks & Porches Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed

More information

COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS

COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS Permit applicants shall submit three (3) COMPLETE SETS of plans and specifications with each application for a permit. Plans and specifications

More information

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed.

Photo 2. View showing flour mill, machine shed, veranda and saw mill + storage shed. May 7,2015 KSANDER & ASSOCIATES CONSULTING PROFESSIONAL ENGINEERS 130 HUINTER STREET, UNIT 103, PETERBOROUGH, ONTARIO K9H2K8 TELEPHONE (705) 743-9221 FAX 743-0904 Ontario Region Conservation Authority

More information

STRUCTURAL ASSESSMENT

STRUCTURAL ASSESSMENT STRUCTURAL ASSESSMENT Project: 1432-1434 East Commerce St. Job. No: 122200 Location: San Antonio, TX Date: Dec. 10, 2012 Weather: Sunny, Windy,60 deg Performed by: Jeff Haughton and Frank Lamas, Alpha

More information

Basement Moisture Problems

Basement Moisture Problems Foundations Foundation Purpose The purpose of a foundation is to distribute the weight of a structure securely into the ground. Engineering data regarding soil, rock and water conditions are used to design

More information

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS

RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS RESIDENTIAL FOUNDATION GUIDELINE Johnson County, KS Johnson County Building Officials Association January 2008 Residential Foundation Guideline Foundation designs for one-and two-family dwellings may use

More information

Property Condition Assessment

Property Condition Assessment Property Condition Assessment Business, Wisconsin Inspection Date: 8/2009 Prepared For: Business Owner Report Number: TD999909 Prepared By: Shamrock Building Inspection Consultants LLC N29 W29951 Shel-Mar

More information

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT

SAMPLE SCHEDULE OF VALUES APPLICATION & CERTIFICATE FOR PAYMENT SAMPLE SCHEDULE OF S 1.00 General Conditions 1.01 Project Management 1.02 General Superintendent 1.03 Superintendents 1.04 Safety Engineer 1.05 Scheduling 1.06 Field Engineering 1.07 Bonds 1.08 Trailer

More information

Photos showing the change in condition from 2006 to 2012 are located in Appendix A.

Photos showing the change in condition from 2006 to 2012 are located in Appendix A. January 27, 2012 Ms. Theresa Gallavan Economic Development Director City of Lompoc 100 Civic Center Plaza Lompoc, California 93436 RE: Lompoc Theater Limited Visual Condition Assessment Dear Theresa: Representatives

More information

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT

Property Inspection. 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT Property Inspection 83A Ascot Avenue North New Brighton Christchurch STRUCTURAL REPORT March 2013 This document has been prepared for the benefit of Clint Marston. No liability is accepted by this company

More information

How To Design A Post Tensioned Deck For A Building

How To Design A Post Tensioned Deck For A Building SAMUEL ÁVILA STRUCTURAL OPTION FACULTY CONSULTANT: THOMAS BOOTHBY UNIVERSITY OF CENTRAL FLORIDA S ACADEMIC VILLAGES ORLANDO, FL THESIS PROPOSAL EXECUTIVE SUMMARY DECEMBER 12, 2005 Introduction: The University

More information

REQUEST FOR QUALIFICATIONS FROM FOUNDATION REPAIR CONTRACTORS BROOMFIELD DEPOT FOUNDATION REHABILITATION PROJECT

REQUEST FOR QUALIFICATIONS FROM FOUNDATION REPAIR CONTRACTORS BROOMFIELD DEPOT FOUNDATION REHABILITATION PROJECT Project Description and Scope The City and County of Broomfield, Colorado (Broomfield) hereby solicits this Request for Qualifications (RFQ) to prequalify and shortlist up to five (5) foundation repair

More information

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com

HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com HEDDERMAN ENGINEERING, INC. www.heddermanengineering.com Office 281-355-9911, Fax 281-355-9903 office@heddermanengineering.com, 2011 TO: Mr. REF: CONDITION OF PROPERTY SURVEY Dear Mr. : At your request,

More information

Professional Engineers Providing Structural Engineering Services In Buildings

Professional Engineers Providing Structural Engineering Services In Buildings GUIDELINE Professional Engineers Providing Structural Engineering Services In Buildings 1995 Published by Association of Professional Engineers of Ontario Revised 12/11/98 CONTENTS INTRODUCTION...3 PART

More information

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)

More information

Structure Survey Findings:

Structure Survey Findings: Structure Survey Findings: Visible portions of the following were observed: foundations; structure to walls, columns, floors, roofs, overhang posts, and columns; attached or firmly abutting decks, balconies,

More information

Steve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022

Steve Brinkman Alain Pinel Realtors 167 S San Antonio Road Los Altos, CA 94022 RE: Foundation Inspection for 162 Del Monte Ave. Los Altos, CA 94022 M G C O N S T R U C T O R S & E N G I N E E R S, I N C. I N S P E C T O R S E N G I N E E R S B U I L D E R S C A L I F O R N I A E N G I N E E R I N G A N D B U I L D I N G L I C E N S E A / B 6 4 2 0

More information

Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building

Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building Roof Inspection Report 3840 Greenway Circle, Lawrence Kansas, 66046 Sauer-Danfoss Building Prepared For: Ms Marilyn Bittenbender Colliers International 805 New Hampshire St Lawrence Kansas, 66046 Prepared

More information

Exterior Elevated Elements Inspection Guidelines

Exterior Elevated Elements Inspection Guidelines Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code

More information

Sample Drawing Package for One and Two Family Dwelling Applications

Sample Drawing Package for One and Two Family Dwelling Applications Sample Drawing Package for One and Two Family Dwelling Applications For a full list of submission requirements, refer to the relevant checklist for your application found on our website: http://vancouver.ca/home-property-development/application-forms-and-checklists.aspx

More information

Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By

Prepared For San Francisco Community College District 33 Gough Street San Francisco, California 94103. Prepared By Project Structural Conditions Survey and Seismic Vulnerability Assessment For SFCC Civic Center Campus 750 Eddy Street San Francisco, California 94109 Prepared For San Francisco Community College District

More information

October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr.

October 30, 2014. Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR. Report of Findings, Structural Investigation, Benton, Arkansas, Dear Mr. 117 S. Market St. Benton, AR 72015 * 501-315-2626 * Fax 501-315-0024 October 30, 2014 Mr. & Mrs. Daniel Vick 101 Southwind Cove Benton, AR Re: Report of Findings,, Benton, Arkansas, Dear Mr. Vick: This

More information

PDmB, Inc. Definitions

PDmB, Inc. Definitions Page 1 of 11 Definitions S Satisfactory Meets industry standards for proper material and installation NP Not Present Condition or item was not present at time of inspection NI Not Inspected Condition or

More information

FORM DESIGN. easy to work with, and generally available.

FORM DESIGN. easy to work with, and generally available. Forms play a major role in concrete construction. They give the plastic concrete its shape and hold it until it hardens. Forms protect the concrete, assist in curing it, and support any reinforcing rods

More information

ISO Types 1-6: Construction Code Descriptions

ISO Types 1-6: Construction Code Descriptions ISO 1 Frame (combustible walls and/or roof) Class 1B Buildings where the exterior walls are wood or other combustible materials, including construction where the combustible materials are combined with

More information

Residential Foundations and Basements

Residential Foundations and Basements Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article

More information

ARROWHEAD GENERAL INSURANCE AGENCY RESIDENTIAL EARTHQUAKE INSURANCE PROGRAM UNDERWRITING GUIDELINES & RATE MANUAL

ARROWHEAD GENERAL INSURANCE AGENCY RESIDENTIAL EARTHQUAKE INSURANCE PROGRAM UNDERWRITING GUIDELINES & RATE MANUAL UNDERWRITING GUIDELINES & RATE MANUAL Arrowhead General Insurance Agency, Inc. Page 1 of 8 Producers Manual June 2001 UNDERWRITING GUIDELINES A. BINDING AUTHORITY/ELIGIBILITY Binding and risk approval

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information