Limiting Shimco Liability

Size: px
Start display at page:

Download "Limiting Shimco Liability"

Transcription

1 Limiting Shimco Liability By Dirk Laudan September 2003 The following is an opinion based on the state of the law as it exists today. This article is not intended to be relied on and you should consult a lawyer for an opinion regarding your specific circumstances. GENERAL BACKGROUND In the case Shimco Metal Erectors Ltd. v. North Vancouver (District) (2003), 11 B.C.L.R. (4 th ) 119 (B.C.C.A.) ( Shimco ), the British Columbia Court of Appeal confirmed that the Builders Lien Act creates a statutory lien against the holdback (the Holdback Lien ) that is separate from and independent of the builders lien filed against title to land (the Builders Lien ). The Holdback Lien can arise even where no lien against title is filed, and it can persist even after the Builders Lien is extinguished. It is these characteristics of the Holdback Lien that have led to serious concerns by some owners and contractors. It is important to regard the risk of a Holdback Lien in perspective. Most unpaid subcontractors who intend to pursue their remedies, file and litigate Builders Liens, contract claims, or bond claims. Holdback Liens are generally more difficult for unpaid trades to pursue. Generally speaking, it is only where the Holdback Lien is the trade s only secured remedy that the trade will invoke the Holdback Lien as its remedy. That being said, the possibility of Holdback Liens complicates the assessment of risk in releasing the statutory builders lien holdback, and careful owners and contractors will want to assess the risks involved. This paper provides a general overview of that risk, and provides some ideas that could be used as strategies for owners and contractors in managing that risk. CALGARY MONTRÉAL OTTAWA TORONTO VANCOUVER

2 This paper is not meant as legal advice. You should obtain legal advice specific to your situation from qualified legal counsel who are experienced in construction and lien matters. THE HOLDBACK LIEN Under the 1998 BC Builders Lien Act, British Columbia has a multiple-holdback system. As a result, the owner, and all contractors and subcontractors down the contractual chain who hire other subcontractors, have to retain a 10% holdback from amounts paid under their contracts. No holdback is required, however, from amounts paid to material suppliers and consultants. Any person engaged in connection with an improvement by or under the person from whom the holdback is retained is entitled to a Holdback Lien. This means an unpaid subcontractor has a Holdback Lien against every holdback above that subcontractor in the contractual chain, all the way up to the owner s holdback from the general contractor. Technically, Builders Liens arise when a claimant is unpaid, but they are only perfected when a Claim of Lien is filed against title to land. The equivalent action by which a Holdback Lien is perfected is commencing an action in the BC Supreme Court to enforce it there s no other place to register a Holdback Lien. Unlike a Builders Lien, the Holdback Lien does not expire if it is unperfected for 45 days after substantial completion. The Holdback Lien only expires after the holdback is paid. The holdback may only be validly paid to discharge unperfected holdback liens after the 55 day holdback period, and only if no Builders Lien claim has been filed against title to the land, and no action has been commenced to enforce a Holdback Lien. This means that as long as even one Builders Lien is filed against title, or one action to enforce a Holdback Lien has been commenced, the holdback cannot be paid in such as way as to extinguish those Holdback Liens. In that case, Holdback Liens appear to last forever, perhaps subject only to the six-year limitation in the BC Limitation Act. There is a limitation on the location where a Holdback Lien action must be commenced. The action must be commenced in the registry of the British Columbia Supreme Court in the same municipality as the land on which the construction project was located, or if there is no such registry, at any registry in the same judicial district as that land. For land in the lower mainland of British Columbia, this generally means actions may be commenced in Vancouver or New Westminster. Persons concerned about Holdback Liens should remember that there is a third registry in the lower mainland (in the 2

3 Vancouver Westminster Judicial District), in Chilliwack. Holdback Lien claimants and persons concerned about Holdback Liens must take care, and seek professional advice on the correct registry to commence an action in, or to search. Absent special circumstances, the risk of a Holdback Lien is limited to the ownercontractor and to other persons who are obligated to retain holdbacks. Non-contracting owners and purchasers generally have no direct liability for a Holdback Lien. Under the former Condominium Act the BC Supreme Court held that the purchaser s holdback in the conveyance of a strata unit was subject to a lien similar to the Holdback Lien. The wording of the replacement provisions in the current Strata Property Act is different from those in the previous legislation, and the status and existence of a Condominium Holdback Lien is therefore arguable. There is no lien against contractual holdbacks kept by a purchaser of property in connection with builders lien claims. STRATEGIES FOR OWNERS There are several strategies an owner can use to reduce the potential for a Holdback Lien arising before release of the holdback. The following can be considered a checklist, beginning with the easier and less expensive strategies and moving to the more expensive and difficult. Conduct an LTO search for the property before payment of the holdback It probably goes without saying that you should conduct a Land Title search of the parcel or parcels on which construction occurred to see if any Builders Liens have been filed before releasing the lien holdback. It is worth remembering, too, that most unpaid claimants will file a Builders Lien against title, even if it is probably late, before those claimants begin an action asserting the Holdback Lien. Simply confirming that there are no Builders Liens against the relevant parcels may tell you that a Holdback Lien is unlikely, although still possible. Conduct a Court registry search before payment of the holdback Along with conducting an LTO search, you can conduct a Court registry search, in the appropriate registries where a Holdback Lien action could be validly commenced, to see if any Holdback Lien has been commenced, before releasing the builders lien holdback. 3

4 The owner can get an indemnity in its general contract Owners should consider including, in tender and general contract terms, a requirement that the contractor indemnify the owner against Holdback Liens. That indemnity would probably not protect the owner in the case of the insolvency of the general contractor, but otherwise should provide some relief against Holdback Liens from a dispute down the contractual chain. The owner should impose standard contract bond (LMP bond) requirements Owners should consider including in tender and general contract terms a requirement that the contractor post a labour and material payment ( LMP ) bond. LMP bonds permit qualified claimants generally unpaid subcontractors who have a direct contract with general contractor to claim unpaid contract claims from the surety. These bonds can provide an alternative and potentially easier method for recovery than advancing a Holdback Lien. Unpaid contractors are unlikely to advance a difficult Holdback Lien if they can be paid out by a surety. Owners might also consider including a tender or contractual requirement that the general contractor obtain LMP bonds from their principal subcontractors. Remember that sub-subcontractors are also entitled to a Holdback Lien against the owner s holdback. Obtaining LMP bond coverage for such second-tier claimants would give them an alternative to a Holdback Lien claim. Owners might consider whether broad form LMP bond requirements, providing for multiple levels of claimants. Owners may wish to consult with bonding companies or the Surety Association of Canada before putting out a tender with non-standard bond language, however. Notify subcontractors of the holdback release Before paying the holdback, owners should consider notifying the project mailing list all contractors and material suppliers known to be working on the project of the intention to release the holdback. That notice should state that if the owner is not notified of claims, the owner will rely on the silence and proceed to pay the holdback. The principal purpose of this notification is to identify any unpaid potential lien claimants to beat the bushes for potential claimants before releasing the holdback. 4

5 Require the contractor to post release of holdback bonds? On several occasions a large municipality has recently included a requirement for a holdback release bond for bidders for municipal construction projects, indemnifying the municipality from any liability arising from the holdback release. If issued, these bonds could effectively eliminate the owner s risk from potential Holdback Liens. But there are some practical problems. The surety companies are unenthusiastic about writing such bonds. Sureties standard release of holdback bonds are not available to all contractors who otherwise qualify for bonding, and are designed to permit a contractor to release the holdback into the project cash flow, not to indemnify Holdback Lien liability. Release of holdback bonds are priced as financial guarantees, higher than normal contract bonds. Assuming such bonds are available, the practical result of requiring release of holdback bonds would likely be to both increase bid prices to pay for the significant bond premiums, and to reduce the number of tenders to those qualifying for these bonds. Pay the holdback to a solicitor s trust accounts Another possible strategy for dealing with the Holdback Lien liability is to set up an arrangement where the holdback is paid into a solicitor s account on trust conditions, so it can be repaid if a lien subsequently appears. This may or may not be successful in setting up a defence to any subsequent Holdback Lien actions. Pay the money into Court If even one Builders Lien is filed against title, the owner may actually be better off! The owner is then entitled to pay the holdback into Court under Section 23 of the Builder Lien Act, thereby extinguishing the owner s liability for Builders Liens and Holdback Liens. The Owner has to pay the legal costs of obtaining the order, which in practice are generally unrecoverable. STRATEGIES FOR CONTRACTORS The strategies for contractors are similar to those for owners, above. Whether the expense or difficulties involved in pursuing such strategies are deemed to be worthwhile, will likely depend on the amount of the holdback that the contractor is required to retain from each subcontractor, and on how risk averse the contractor is. 5

6 Conduct an LTO search for the property before payment of the holdback Contractors should consider conducting Land Title searches of the relevant properties, and reviewing them to determine that no Builders Liens have been filed against title, before releasing their holdbacks. Note that where the project involves a large number of parcels (as where a large number of strata titles have been raised), obtaining and reviewing those searches may have significant cost implications. The value of taking this step will have to be weighed against the amount of the holdback. Conduct a Court registry search before payment of the holdback The general contractor should also consider conducting a registry search of actions naming it as a defendant, before releasing the holdback to a subcontractor, particularly in the case of major subcontractors. Again, there is a question of the cost-effectiveness of this precaution. Get an indemnity in your subcontract or include in your purchase order In their subcontracts or purchase orders, the general contractors should consider a requirement that the subcontractors indemnify it against any claims against the contractors or the owner s holdback. The indemnity against claims against the owner s holdback will be important if the contractors have themselves indemnified the owner for such claims. The subcontractors should consider analogous provisions in their subsubcontracts or purchase orders; and on down the line. Contract bond (LMP bond) requirements General contractors should consider requiring subcontractors to post LMP bonds, to provide a remedy for unpaid trades engaged by their subcontractors, instead of advancing a Holdback Lien claim. Some general contractors already require bonds from their subcontractors above a certain size, regardless of whether the owner requires it. Notify subcontractors of the holdback release Such notification would also assist contractors in determining whether the potential Holdback lien claimants are likely to advance claims. See above, for owners. 6

7 Release of lien bonds It appears unlikely that sureties would issue release of holdback bonds for subcontractors. Pay the holdback to a solicitor s trust accounts Contractors could also release the holdback to solicitors on undertakings. See above, for owners. Pay the money into Court If there is a Builders Lien by a subcontractor of the contractor retaining a holdback, the contractor is also entitled under Section 23 to make an application to pay its holdback into Court. STRATEGIES FOR VENDORS Vendors would only be liable for the Holdback Lien if they were also parties to a construction contract. In that case, their strategies to limit risk are as noted above under owners. Since the holdback under the Strata Corporation Act is released to the vendor, no steps to protect the vendor in connection with that release need be considered. STRATEGIES FOR PURCHASERS Purchasers are not liable for a Holdback Lien. With regard to the potential lien against the purchaser s holdback under the Strata Property Act, the purchaser may consider certain steps to limit its risk. LTO search It perhaps goes without saying that the purchaser should obtain a search of the land title office after the holdback period to confirm that no Builders Liens are filed. Court registry search Cautious purchasers should also consider obtaining a Court registry search, particularly if the holdback is sizeable. The language of the Strata Property Act may lend itself to the argument that the vendor should provide the purchaser with that search, since the 7

8 absence of proceedings against the holdback is a precondition to holdback release to the vendor. 8

How BC s Builders Lien Act Applies to Contractors

How BC s Builders Lien Act Applies to Contractors How BC s Builders Lien Act Applies to Contractors The purpose of this summary is to give a general idea of the rights and liabilities which flow from the most important provisions in the Act. This summary

More information

PERFORMANCE BONDS AND LABOUR AND MATERIAL PAYMENT BONDS: WHAT THE CONSTRUCTION INDUSTRY SHOULD KNOW

PERFORMANCE BONDS AND LABOUR AND MATERIAL PAYMENT BONDS: WHAT THE CONSTRUCTION INDUSTRY SHOULD KNOW PERFORMANCE BONDS AND LABOUR AND MATERIAL PAYMENT BONDS: WHAT THE CONSTRUCTION INDUSTRY SHOULD KNOW Deborah E. Palter, B.A., LL.B., J.D. What is a Bond? A bond is a three party written agreement. The three

More information

Performance Bond. Business):

Performance Bond. Business): Performance Bond CONTRACTOR (Name and Address): (Name and Address of Principal Place of Business): OWNER (Name and Address): City of Cedar Rapids City Clerk, 101 First Street SE Cedar Rapids, IA 52401

More information

SURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.)

SURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.) Performance Bond Document A312 2010 CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal status and address) CONSTRUCTION CONTRACT

More information

Construction Bonds. Vanessa S. Werden 604.408.2033 vsw@shk.ca

Construction Bonds. Vanessa S. Werden 604.408.2033 vsw@shk.ca Construction Bonds Vanessa S. Werden 604.408.2033 vsw@shk.ca What is a bond? A bond is a special form of contract whereby one party guarantees the performance by another party of certain obligations. A

More information

388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com ADDENDUM NO. 1

388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com ADDENDUM NO. 1 388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com May 6, 2015 To: All Plan Holders From: Vicki Morris General Manager Subject: Water Serviceline Installation

More information

Forms Guide. Builders Lien Act. A guide to filing and. cancelling a claim. of builders lien. in British Columbia

Forms Guide. Builders Lien Act. A guide to filing and. cancelling a claim. of builders lien. in British Columbia Forms Guide Builders Lien Act A guide to filing and cancelling a claim of builders lien in British Columbia Prepared by the Construction Secretariat BC Ministry of Employment and Investment Fall 1999 The

More information

Kentucky Department of Education Version of Document A312 2010

Kentucky Department of Education Version of Document A312 2010 Kentucky Department of Education Version of Document A312 2010 Performance Bond CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal

More information

2013 Stewart McKelvey. All rights reserved. Not to be copied or used in whole or in part without the express written consent of Stewart McKelvey

2013 Stewart McKelvey. All rights reserved. Not to be copied or used in whole or in part without the express written consent of Stewart McKelvey Construction Bonds Presented by: Sheree Conlon April 17, 2013 2013 Stewart McKelvey. All rights reserved. Not to be copied or used in whole or in part without the express written consent of Stewart McKelvey

More information

AIA Document A312 - Electronic Format. Performance Bond

AIA Document A312 - Electronic Format. Performance Bond AIA Document A312 - Electronic Format Performance Bond THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION. AUTHENTICATION

More information

a guide to construction surety bonds

a guide to construction surety bonds Standard construction document CCDC 22 2002 a guide to construction surety bonds Canadian Construction Documents Committee TABLE OF CONTENTS INTRODUCTION 1. WHAT IS SURETYSHIP? 1.1 HISTORY 1.2 WHAT IS

More information

COMMERCIAL CONSTRUCTION AGREEMENT. This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between <> ( Owner ) and <> ( Contractor ).

COMMERCIAL CONSTRUCTION AGREEMENT. This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between <> ( Owner ) and <> ( Contractor ). COMMERCIAL CONSTRUCTION AGREEMENT This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between ( Owner ) and ( Contractor ). A. Contractor wishes to enter into the following Contract with

More information

AIA Document A310 TM 2010

AIA Document A310 TM 2010 AIA Document A310 TM 2010 Bid Bond CONTRACTOR: OWNER: «Lane County» «125 East Eighth Avenue BOND AMOUNT: $ PROJECT: (Name, location or address, and Project number, if any) «Lane County Adult Corrections

More information

Mortgage Enforcement in British Columbia

Mortgage Enforcement in British Columbia A Limited Liability Partnership under the laws of Ontario Andrew Bury Vancouver May 2002 Montréal Ottawa Toronto Hamilton Waterloo Region Calgary Vancouver Moscow Andrew Bury is a partner in the Vancouver

More information

Bidding / Contracts General Information

Bidding / Contracts General Information Bidding / Contracts General Information We have provided this information sheet on various requirements and terminology when bidding on or completing various service and/or construction contracts for the

More information

Strata Corporations and the new Limitation Act By Shawn M. Smith Cleveland Doan LLP

Strata Corporations and the new Limitation Act By Shawn M. Smith Cleveland Doan LLP Strata Corporations and the new Limitation Act By Shawn M. Smith Cleveland Doan LLP The application of limitation periods has generally not been given much consideration in the strata community. That is

More information

MANAGING A BUSINESS California Mechanics Liens and Stop Notices Mechanics Liens. Stop Notices. Other Remedies. Procedure.

MANAGING A BUSINESS California Mechanics Liens and Stop Notices Mechanics Liens. Stop Notices. Other Remedies. Procedure. MANAGING A BUSINESS California Mechanics Liens and Stop Notices Mechanics Liens. In the State of California, mechanics liens are provided in the California Constitution. Article XIV, Section 3 of the California

More information

BOND AGREEMENT: IRREVOCABLE LETTER OF CREDIT FOR COMPLETION OF IMPROVEMENTS

BOND AGREEMENT: IRREVOCABLE LETTER OF CREDIT FOR COMPLETION OF IMPROVEMENTS BOND AGREEMENT: IRREVOCABLE LETTER OF CREDIT FOR COMPLETION OF IMPROVEMENTS All property owners on record with Tooele County MUST be listed as Applicants. They must each sign and have their signatures

More information

Contract Security. Requirements. Forms of Contract Security 6.8. The purpose of contract security is to guarantee that the contractor will:

Contract Security. Requirements. Forms of Contract Security 6.8. The purpose of contract security is to guarantee that the contractor will: 6.8 Contract Security The purpose of contract security is to guarantee that the contractor will: perform and complete the work according to the contract requirements discharge lawful obligations and satisfy

More information

CONTRACTOR DEFAULT & SURETY PERFORMANCE:

CONTRACTOR DEFAULT & SURETY PERFORMANCE: CONTRACTOR DEFAULT & SURETY PERFORMANCE: A PRACTICAL GUIDE FOR UNDERSTANDING AND NAVIGATING A BOND DEFAULT SITUATION TEXAS CITY ATTORNEYS ASSOCIATION SUMMER CONFERENCE JUNE 9-11, 2010 SOUTH PADRE ISLAND,

More information

SOUTH CAROLINA & NORTH CAROLINA, MECHANIC S LIEN AND PAYMENT BOND CLAIM MANUAL *

SOUTH CAROLINA & NORTH CAROLINA, MECHANIC S LIEN AND PAYMENT BOND CLAIM MANUAL * SOUTH CAROLINA & NORTH CAROLINA, MECHANIC S LIEN AND PAYMENT BOND CLAIM MANUAL * * This manual is for general reference only and should not be used without consultation with an attorney This manual is

More information

Document A312 TM SURETY. (Name, legal status and principal place of business)

Document A312 TM SURETY. (Name, legal status and principal place of business) Payment Bond Document A312 TM 2010 CONTRACTOR: (Name, legal status and address) OWNER: (Name, legal status and address) CONSTRUCTION CONTRACT Date: Amount: $ Description: (Name and location) Uninterruptible

More information

A guide to debt recovery through a county court for small businesses. It could help you decide whether court action is right for you.

A guide to debt recovery through a county court for small businesses. It could help you decide whether court action is right for you. EX350 A guide to debt recovery through a county court for small businesses 1. Introduction This leaflet covers the sort of things to bear in mind when considering going to court. You can issue a claim

More information

MORTGAGE COLLECTIONS in British Columbia

MORTGAGE COLLECTIONS in British Columbia MORTGAGE COLLECTIONS in British Columbia MORTGAGE COLLECTIONS in British Columbia PREPARED BY ANDREW BURY October 2013 Andrew Bury is a partner in the Vancouver office of Gowling Lafleur Henderson LLP.

More information

RHODE ISLAND CONSTRUCTION LAW PRIMER

RHODE ISLAND CONSTRUCTION LAW PRIMER RHODE ISLAND CONSTRUCTION LAW PRIMER By Chad L. Hershman, Esq. chershman@haslaw.com 617-378-4192 I. Introduction: As the construction industry continues to attempt to emerge from a period of decreased

More information

Recent changes to the Home Building Act, 1989 and Home Warranty Insurance

Recent changes to the Home Building Act, 1989 and Home Warranty Insurance Recent changes to the Home Building Act, 1989 and Home Warranty Insurance David Andrews and Colin Grace Grace Lawyers Pty Ltd a legislative scheme intended to provide significant rights to consumers in

More information

SUMMARY OF MECHANICS LIEN LAW FOR THE DISTRICT OF COLUMBIA

SUMMARY OF MECHANICS LIEN LAW FOR THE DISTRICT OF COLUMBIA SUMMARY OF MECHANICS LIEN LAW FOR THE DISTRICT OF COLUMBIA Section Contents Pre-lien Notice(s) Introduction Section Contents Mechanic s Lien Who is Entitled to a Lien? When to File/Record Where to File/Record

More information

What You Should Know About General Agreements of Indemnity and Why You Should Know It

What You Should Know About General Agreements of Indemnity and Why You Should Know It What You Should Know About General Agreements of Indemnity and Why You Should Know It Summary When a contractor (for purposes of this discussion, contractor includes subcontractor) first seeks surety credit,

More information

QBE European Operations Professional liability

QBE European Operations Professional liability QBE European Operations Professional liability Disclosure of insurance details revisited QBE Professional Liability Disclosure of insurance details revisited/november 2013 1 Disclosure of insurance details

More information

LESPERANCE MENDES. Suite 410, 900 Howe Street, Vancouver BC Canada V6Z 2M4 t 604-685-3567 f 604-685-7505 www.lmlaw.ca

LESPERANCE MENDES. Suite 410, 900 Howe Street, Vancouver BC Canada V6Z 2M4 t 604-685-3567 f 604-685-7505 www.lmlaw.ca Guide to 2-5-10 Warranties LESPERANCE MENDES Suite 410, 900 Howe Street, Vancouver BC Canada V6Z 2M4 t 604-685-3567 f 604-685-7505 www.lmlaw.ca LESPERANCE MENDES Guide to 2-5-10 Warranties The Homeowner

More information

CONDITIONAL PAYMENT BONDS -- PANACEA OR PANDORA? STUART H. SOBEL, ESQ. Siegfried, Rivera, Lerner, DeLaTorre & Sobel, P.A. March, 1998.

CONDITIONAL PAYMENT BONDS -- PANACEA OR PANDORA? STUART H. SOBEL, ESQ. Siegfried, Rivera, Lerner, DeLaTorre & Sobel, P.A. March, 1998. CONDITIONAL PAYMENT BONDS -- PANACEA OR PANDORA? STUART H. SOBEL, ESQ. Siegfried, Rivera, Lerner, DeLaTorre & Sobel, P.A. March, 1998 Introduction In 1991, 713.245 Fla. Stat. ("Conditional Payment Bond

More information

AIA Document A312 TM 1984

AIA Document A312 TM 1984 Performance Bond AIA Document A312 TM 1984 CONTRACTOR (Name and Address): H. B. Barnard, General Corporation 53 West Jackson Boulevard Suite 235 OWNER (Name and Address): The Chicago Society of Alpha Delta

More information

The Mysterious World of Surety Bonding

The Mysterious World of Surety Bonding The Mysterious World of Surety Bonding The Mysterious World of Surety Bonding Robin Federici, CPCU, AAI, ARM, AINS, AIS, CPIW PO BOX 781 NORTH KINGSTOWN, RI 02852 Phone: 401-294-3557 Fax: 401-294-3557

More information

LEGAL ARTICLE FROM DE GRANDPRÉ CHAIT LLP INTERLAWYERS

LEGAL ARTICLE FROM DE GRANDPRÉ CHAIT LLP INTERLAWYERS LEGAL ARTICLE FROM DE GRANDPRÉ CHAIT LLP INTERLAWYERS CONSTRUCTION PROJECTS IN QUEBEC By David H. Kauffman dkauffman@dgclex.com Plus ça change, plus c est la même chose. Planning for a construction project

More information

SCHEDULE 14. Part 1 Performance Bond PERFORMANCE BOND NO.

SCHEDULE 14. Part 1 Performance Bond PERFORMANCE BOND NO. SCHEDULE 14 BONDS Part 1 Performance Bond PERFORMANCE BOND NO. $ KNOW ALL PERSONS BY THESE PRESENTS, that Contractor s Name as Principal ( the Principal ) and Surety / Insurance Company name and address,

More information

Bond Form Commentary and Comparison

Bond Form Commentary and Comparison Bond Form Commentary and Comparison AIA Document A310 2010, Bid Bond, and AIA Document A312 2010, Performance Bond and Payment Bond INTRODUCTION Since the first publication of The Standard Form of Bond

More information

UNIVERSITY OF MINNESOTA

UNIVERSITY OF MINNESOTA UNIVERSITY OF MINNESOTA Bond Number CONTRACTOR: «Vendor_Name» «Address_1» «Address_2» 00620PAY PAYMENT BOND SURETY (Name and Address as listed in the current Federal Register): OWNER: Regents of the University

More information

574.26 CONTRACTORS' BONDS FOR PUBLIC WORK.

574.26 CONTRACTORS' BONDS FOR PUBLIC WORK. 1 MINNESOTA STATUTES 2011 574.26 574.26 CONTRACTORS' BONDS FOR PUBLIC WORK. Subdivision 1. Citation. (a) Sections 574.26 to 574.32 are the "Public Contractors' Performance and Payment Bond Act," within

More information

Bill 34 The New Limitation Act: Significant Changes and Transition Issues Explained

Bill 34 The New Limitation Act: Significant Changes and Transition Issues Explained Bill 34 The New Limitation Act: Significant Changes and Transition Issues Explained A Presentation for CLE Employment Law Conference 2013 Pan Pacific Hotel Vancouver, BC May 9, 2013 Carman J. Overholt,

More information

RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS

RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS RBI Asset Management (Pty) Ltd P O Box 7192 Halfway House 1685 Tel: 011 805 7933 Fax: (086) 675-9194 E-mail: geoff@rbi.co.za RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS 1. DEFINITIONS These Conditions,

More information

How To Get A Construction Contract In The United States

How To Get A Construction Contract In The United States SOUTH CAROLINA LIEN AND BOND CLAIMS William ( Trey ) W. Watkins, Jr. 145 King Street, Suite 300 Charleston, SC 29401 843-329-9500 1 Introduction to Surety 3 Main differences between Insurance and Bonds

More information

SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND ("Bond") SURETY Address

SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND (Bond) SURETY Address Bond # SUBCONTRACTOR LABOR AND MATERIAL PAYMENT BOND ("Bond") KNOW ALL PERSONS BY THESE PRESENTS; that SUBCONTRACTOR as Principal (the "Subcontractor"), and SURETY as Surety or Co-sureties (hereinafter

More information

THE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT

THE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT Agreement 2006 Page 1 THE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT THIS AGREEMENT made in triplicate this day of 20 THE CORPORATION OF THE CITY OF BURLINGTON (hereinafter called "the City")

More information

Legislative Analysis ABOLISH HOMEOWNER CONSTRUCTION LIEN RECOVERY FUND. House Bills 5830 and 5835 Sponsor: Rep. Richard E. Hammel

Legislative Analysis ABOLISH HOMEOWNER CONSTRUCTION LIEN RECOVERY FUND. House Bills 5830 and 5835 Sponsor: Rep. Richard E. Hammel Legislative Analysis ABOLISH HOMEOWNER CONSTRUCTION LIEN RECOVERY FUND Mitchell Bean, Director Phone: (517) 373-8080 http://www.house.mi.gov/hfa House Bills 5830 and 5835 Sponsor: Rep. Richard E. Hammel

More information

RISK MANAGEMENT IN CONTRACTS

RISK MANAGEMENT IN CONTRACTS RISK MANAGEMENT IN CONTRACTS There are many circumstances in which an Institution will contract with another party including service contracts, sales agreements, leases, practicum placement and affiliation

More information

Construction Bonds Guide

Construction Bonds Guide Construction Bonds Guide by R. Glen Boswall Clark Wilson LLP tel. 604.643.3125 rgb@cwilson.com This is a revised and updated version of a paper originally prepared by Hannelie Stockenstrom in 2007. www.cwilson.com

More information

California Senate Bill 474 Impact on Owners & Contractors

California Senate Bill 474 Impact on Owners & Contractors California Senate Bill 474 Impact on Owners & Contractors Beginning January 1, 2013, project owners, general contractors ( GC ), construction managers ( CM ) and any lower tier contractor who employs subcontractors

More information

California Civil Code 2782.05

California Civil Code 2782.05 California Civil Code 2782.05 (a) Except as provided in subdivision (b), provisions, clauses, covenants, and agreements contained in, collateral to, or affecting any construction contract and amendments

More information

Limiting liability for professional firms

Limiting liability for professional firms Limiting liability for professional firms Introduction Disputes can arise between providers of professional services and their clients or other (third) parties for a number of reasons. Limiting or excluding

More information

Choosing Small Claims or Fast Track Litigation

Choosing Small Claims or Fast Track Litigation Choosing Small Claims or Taking your dispute to court can be a complicated and lengthy process. If your Supreme Court claim is for an amount under $100,000, or if it can be tried in 3 days or less, there

More information

SUMMARY OF MECHANICS LIEN LAW FOR CONNECTICUT. Reviewed Through 2011

SUMMARY OF MECHANICS LIEN LAW FOR CONNECTICUT. Reviewed Through 2011 SUMMARY OF MECHANICS LIEN LAW FOR CONNECTICUT Reviewed Through 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents

More information

Bonding for Contractors. Barrie Construction Association September 17, 2015

Bonding for Contractors. Barrie Construction Association September 17, 2015 Bonding for Contractors Barrie Construction Association September 17, 2015 1 Topics What do bonds do? How does a bond benefit you? How do you get a bond? What are the information requirements? What is

More information

MORTGAGE PART 1 (This area for Land Title Office use) Page 1 of pages

MORTGAGE PART 1 (This area for Land Title Office use) Page 1 of pages LAND TITLE ACT FORM B (Section 225) Province of British Columbia MORTGAGE PART 1 (This area for Land Title Office use) Page 1 of pages 1. APPLICATION: (Name, address, phone number and signature of applicant,

More information

APPENDIX D CONTRACTUAL AGREEMENT (Sample) THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources

APPENDIX D CONTRACTUAL AGREEMENT (Sample) THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources APPENDIX D CONTRACTUAL AGREEMENT (Sample) THIS AGREEMENT made in duplicate, BETWEEN: THE GOVERNMENT OF SASKATCHEWAN as represented by the Minister of Energy and Resources (Hereinafter referred to as the

More information

Managing Construction Risk through Commercial General Liability Insurance

Managing Construction Risk through Commercial General Liability Insurance View the online version at http://us.practicallaw.com/8-574-8645 Managing Construction Risk through Commercial General Liability Insurance ADAM P. HANDFINGER, PECKAR & ABRAMSON, P.C. AND ALEJANDRA EVANS,

More information

Project Management Agreement

Project Management Agreement Project Management Agreement Owner(s) Address Telephone #1 Telephone #2 Email Manager Project description DAVIS DESIGN Inc. Project Management Agreement Owner hereby engages Manager to manage on behalf

More information

Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds

Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds STAFF REPORT June 22, 2005 To: From: Subject: Administration Committee Deputy City Manager and Chief Financial Officer Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds Purpose:

More information

GUARANTEE (Prime Rate)

GUARANTEE (Prime Rate) GUARANTEE (Prime Rate) TERMS YOU NEED TO KNOW In this document, the terms below have the following particular meanings: (a) Credit Document means any present or future agreement between us and the Customer

More information

THE LAND TITLES ACT, 2000

THE LAND TITLES ACT, 2000 THE LAND TITLES ACT, 2000 ROYAL BANK OF CANADA SASKATCHEWAN COLLATERAL MORTGAGE (PRIME RATE) TABLE OF CONTENTS SECTION 1 AMOUNTS SECURED BY THE MORTGAGE AND INTEREST RATE... 2 SECTION 2 TERMS YOU NEED

More information

A GUIDE TO MECHANIC'S LIENS IN MINNESOTA

A GUIDE TO MECHANIC'S LIENS IN MINNESOTA MULLIGAN & BJORNNES PLLP Attorneys at Law 401 Groveland Avenue Minneapolis, MN 55403 (612) 871-1800 TABLE OF CONTENTS PAGE I. PRE-LIEN NOTICE REQUIREMENTS...3 A. CONTRACTOR PRE-LIEN NOTICE REQUIREMENTS...3

More information

Bankruptcy and Restructuring

Bankruptcy and Restructuring doing business in Canada 102 p Bankruptcy and Restructuring 1. Legislation and Court System The Canadian bankruptcy and insolvency regime is divided between the federal and provincial levels of government

More information

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES

AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES Names of Parties 1. (Company Name) of (Company Address) ( Consultancy ). 2. Redline Group Ltd of 26-34 Liverpool Road, Luton. Beds LU1

More information

STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)

STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) State License #CGC048773 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) This Agreement is made this day of, 200, by and

More information

Surety Bond Tutorial by Lori Kieswetter

Surety Bond Tutorial by Lori Kieswetter Contract Surety Bonds Defined Surety Bond Tutorial by Lori Kieswetter A bond issued by a surety bond company on behalf of a contractor, guaranteeing that the contractor will complete a contract as per

More information

Payment and Performance Surety Bonds in Construction Projects: Perspectives of Owners, Contractors and Sureties

Payment and Performance Surety Bonds in Construction Projects: Perspectives of Owners, Contractors and Sureties Presenting a live 90-minute webinar with interactive Q&A Payment and Performance Surety Bonds in Construction Projects: Perspectives of Owners, Contractors and Sureties Asserting and Defending Surety Bond

More information

G U E S T E S S A Y S

G U E S T E S S A Y S Comparing and Maximizing Performance Bond and Commercial General Liability Protections Frank L. Pohl, Esq. and James C. Washburn, Esq. Often when acting as the prime on a construction project, the design

More information

CAMBRIDGE PROPERTY & CASUALTY SPECIAL REPORT

CAMBRIDGE PROPERTY & CASUALTY SPECIAL REPORT CAMBRIDGE PROPERTY & CASUALTY SPECIAL REPORT MANAGING THE RISK OF INDEPENDENT CONTRACTORS WORKING IN YOUR BUILDING This Special Report was written by Daniel P. Hale, J.D., CPCU, ARM, CRM, LIC, AIC, AIS,

More information

DRAFT Version 1.2 Revision Date: 16/7/10

DRAFT Version 1.2 Revision Date: 16/7/10 LOCAL AUTHORITY SEARCH REPORT INSURANCE POLICY 1. Policy Issuer: Stanley Davis Group Limited trading as York Place Policy Number: SDGLA0001 Definitions In this policy unless the context otherwise requires:

More information

Real Estate Errors & Omissions Indemnity Plan

Real Estate Errors & Omissions Indemnity Plan B R I T I S H C O L U M B I A Real Estate Errors & Omissions Indemnity Plan No. RE0398 Issued by Real Estate Errors and Omissions Insurance Corporation (Herein called the Corporation ) Pursuant to the

More information

REAL ESTATE SELLING YOUR HOME

REAL ESTATE SELLING YOUR HOME Introduction Congratulations on the sale of your home. Selling a home is a major decision and we would like to assist you with the legal requirements. In the event that you choose RDM Lawyers, you can

More information

D None SeePage 2. AlA Document A312

D None SeePage 2. AlA Document A312 AlA Document A312 Performance Bond Confonns with the American Institute ofarchitects, AlA Document A312. Any singular reference to Contractor, Surety, Owner or other party shall be considered plural where

More information

RESIDENTIAL LIMITED COVERAGE MORTGAGE MODIFICATION POLICY Issued By WFG NATIONAL TITLE INSURANCE COMPANY

RESIDENTIAL LIMITED COVERAGE MORTGAGE MODIFICATION POLICY Issued By WFG NATIONAL TITLE INSURANCE COMPANY RESIDENTIAL LIMITED COVERAGE MORTGAGE MODIFICATION POLICY Issued By WFG NATIONAL TITLE INSURANCE COMPANY Any notice of claim and any other notice or statement in writing required to be given to the Company

More information

Construction Performance Bond. THIS CONSTRUCTION PERFORMANCE BOND ( Bond ) is dated, is in the penal sum of. Sample Preview CONTRACTOR: Address

Construction Performance Bond. THIS CONSTRUCTION PERFORMANCE BOND ( Bond ) is dated, is in the penal sum of. Sample Preview CONTRACTOR: Address Construction Performance Bond THIS CONSTRUCTION PERFORMANCE BOND ( Bond ) is dated, is in the penal sum of [which is one hundred percent of the Contract Price], and is entered into by and between the parties

More information

Document Comparative

Document Comparative Document Comparative AIA Documents A401 2007 and A401 2007 SP AIA Document A401 2007 SP, Standard Form of Agreement Between Contractor and Subcontractor, for use on a Sustainable Project, establishes the

More information

By Donald A. Odell, Attorney at Law

By Donald A. Odell, Attorney at Law All About Homes Light Commercial & Residential Inspection 24326 Mission Blvd., Suite 7 Hayward, CA 94544 www.allabouthomes.com Mechanic hanic s Liens Law and how it Applies to an Owner of Real Proper operty

More information

Home Building Amendment (Insurance) Act 2009 No 24

Home Building Amendment (Insurance) Act 2009 No 24 New South Wales Home Building Amendment (Insurance) Act 2009 No 24 Contents Page 1 Name of Act 2 2 Commencement 2 Schedule 1 Amendment of Home Building Act 1989 No 147 3 Schedule 2 Amendment of Home Building

More information

How To Understand Surety Bond

How To Understand Surety Bond The Consumer s Guide to Surety Bonds Surety bonds are an incredibly important tool for managing and mitigating risk in the business world. They are an essential and often mandatory production element for

More information

INDEX. bonded contract, 289 insureds, 243. misrepresentation, 291 obtaining, 242

INDEX. bonded contract, 289 insureds, 243. misrepresentation, 291 obtaining, 242 INDEX B non-conforming tender, 284 boiler and machinery insurance, performance bond 241 default by the obligee, 288 coverage, 243 failure to notify, 289 definition of the accident, 245 material variation

More information

STANDARD MORTGAGE TERMS RESIDENTIAL

STANDARD MORTGAGE TERMS RESIDENTIAL Form 3995 (03-2006) STANDARD MORTGAGE TERMS RESIDENTIAL MT060089 Filed: January 6, 2006 Vancouver/New Westminster Land Title Office FILED BY: ROYAL BANK OF CANADA The following set of standard mortgage

More information

Pe r f e c t i n g a. Ne va d a. Caryn S. Tijsseling. Prepared and Presented by. Lewis and Roca LLP 775-321-3426 CTijsseling@LRLaw.

Pe r f e c t i n g a. Ne va d a. Caryn S. Tijsseling. Prepared and Presented by. Lewis and Roca LLP 775-321-3426 CTijsseling@LRLaw. Pe r f e c t i n g a Mechanic s Lien in Ne va d a Prepared and Presented by Caryn S. Tijsseling Lewis and Roca LLP 775-321-3426 CTijsseling@LRLaw.com Overview of Construction Liens The Nevada Revised Statutes

More information

COLLECTING YOUR MONEY THROUGH MECHANIC S LIENS, STOP NOTICES & BONDS

COLLECTING YOUR MONEY THROUGH MECHANIC S LIENS, STOP NOTICES & BONDS COLLECTING YOUR MONEY THROUGH MECHANIC S LIENS, STOP NOTICES & BONDS A Presentation for THE HUMBOLDT BUILDERS EXCHANGE, INC. April 22, 2015 By: Kenneth S. Grossbart Abdulaziz, Grossbart & Rudman P.O. Box

More information

IN THE SUPREME COURT OF BRITISH COLUMBIA THE LSBC CAPTIVE INSURANCE COMPANY PLAINTIFF NOTICE OF CIVIL CLAIM

IN THE SUPREME COURT OF BRITISH COLUMBIA THE LSBC CAPTIVE INSURANCE COMPANY PLAINTIFF NOTICE OF CIVIL CLAIM Form 1 (Rule 3-1(1)) No. Vancouver Registry IN THE SUPREME COURT OF BRITISH COLUMBIA BETWEEN AND THE LSBC CAPTIVE INSURANCE COMPANY PLAINTIFF DEFENDANT NOTICE OF CIVIL CLAIM This action has been started

More information

E F F E C T I V E M A R C H 1, 2 0 0 9. Indemnity. Plan. Real Estate Errors and Omissions Insurance Corporation. British Columbia

E F F E C T I V E M A R C H 1, 2 0 0 9. Indemnity. Plan. Real Estate Errors and Omissions Insurance Corporation. British Columbia E F F E C T I V E M A R C H 1, 2 0 0 9 Indemnity Plan N Ọ R E 0 3 0 9 Real Estate Errors and Omissions Insurance Corporation British Columbia I N T R O D U C T I O N Why You Need Professional Liability

More information

SUMMARY OF MECHANICS LIEN LAW FOR RHODE ISLAND. With Revisions Through 2011. Section Contents Pre-lien Notice(s)

SUMMARY OF MECHANICS LIEN LAW FOR RHODE ISLAND. With Revisions Through 2011. Section Contents Pre-lien Notice(s) SUMMARY OF MECHANICS LIEN LAW FOR RHODE ISLAND With Revisions Through 2011 Section Contents Pre-lien Notice(s) Name of Notice Who Must Use This Notice When How to Serve Verified or notarized? Section Contents

More information

A Guide To Understanding The Community Association Collection And Foreclosure Process

A Guide To Understanding The Community Association Collection And Foreclosure Process A Guide To Understanding The Community Association Collection And Foreclosure Process What is the initial demand letter? What is a Claim of Lien? What is a thirty (30) day letter? How do you foreclose

More information

IN THE SUPREME COURT OF BRITISH COLUMBIA DOROTHY YOUNG SHELL CANADA LIMITED. Brought under the Class Proceedings Act, R.S.B.C. 1996, c.

IN THE SUPREME COURT OF BRITISH COLUMBIA DOROTHY YOUNG SHELL CANADA LIMITED. Brought under the Class Proceedings Act, R.S.B.C. 1996, c. IN THE SUPREME COURT OF BRITISH COLUMBIA No. L021060 Vancouver Registry Between: And: DOROTHY YOUNG SHELL CANADA LIMITED Brought under the Class Proceedings Act, R.S.B.C. 1996, c. 50 Plaintiff Defendant

More information

Building and Construction Industry Security of Payments Act 2009

Building and Construction Industry Security of Payments Act 2009 Legal Compliance Education & Awareness Building and Construction Industry Security of Payments Act 2009 (South Australian) Life Impact The University of Adelaide What does the Act do? Establishes a process

More information

McLean & Armstrong LLP

McLean & Armstrong LLP Based in West Vancouver, British Columbia, our law firm helps prevent and resolve construction disputes, including those involving collection, delay and tendering issues; defective building claims; and

More information

CITY OF GIG HARBOR PRIVATE PROJECT DEVELOPMENT PERFORMANCE BOND

CITY OF GIG HARBOR PRIVATE PROJECT DEVELOPMENT PERFORMANCE BOND CITY OF GIG HARBOR PRIVATE PROJECT DEVELOPMENT PERFORMANCE BOND City Project EN #: Surety Bond #: DATE POSTED: PROJECT COMPLETION DATE: RE: Gig Harbor Subdivision/Plat/Name: Owner/Developer/Contractor:

More information

Do You Need Title Insurance?

Do You Need Title Insurance? Do You Need Title Insurance? By Brian Madigan That s a good question. Prior to 1997, there was no commonly available title insurance in Ontario and yet it was the norm in the United States. Solicitor s

More information

Randy Murray September 10, 2015

Randy Murray September 10, 2015 Randy Murray September 10, 2015 Definition Compare Insurance and Surety Types of Surety Bonds Collateral Reserving 2 Surety Bond is an agreement, issued by an insurance company, that promises to pay one

More information

WRITTEN TESTIMONY OF BRYAN C. SKARLATOS, ESQ. given it powers to collect money and property that far exceed those of any ordinary creditor.

WRITTEN TESTIMONY OF BRYAN C. SKARLATOS, ESQ. given it powers to collect money and property that far exceed those of any ordinary creditor. WRITTEN TESTIMONY OF BRYAN C. SKARLATOS, ESQ. The Internal Revenue Service (the Service ) is a Super Creditor because Congress has given it powers to collect money and property that far exceed those of

More information

MORTENSON CANADA CORPORATION PURCHASE AGREEMENT STANDARD TERMS AND CONDITIONS

MORTENSON CANADA CORPORATION PURCHASE AGREEMENT STANDARD TERMS AND CONDITIONS MORTENSON CANADA CORPORATION PURCHASE AGREEMENT STANDARD TERMS AND CONDITIONS 1. CONTRACT DOCUMENTS. 1.1 The Contract Documents have been made available to Supplier for examination. 1.2 In the event of

More information

Directors Liability under Corporate Taxing Statutes

Directors Liability under Corporate Taxing Statutes Directors Liability under Corporate Taxing Statutes Resource type: Practice Note Status: Maintained Jurisdiction: Canada This Note discusses the liability of directors for withholding and remittance obligations

More information

CONSULTANT AGREEMENT

CONSULTANT AGREEMENT Douglas County School District Re.1 Castle Rock, Colorado CONSULTANT AGREEMENT This agreement, dated effective as of is made and entered into by and between the Douglas County School District Re.1, Douglas

More information

Step One: Determining Whether Lien Rights are Available

Step One: Determining Whether Lien Rights are Available ALABAMA LIEN LAW CHECKLIST This paper presents general information regarding the law of mechanic's liens in Alabama. It should not be construed as legal advice or legal opinion on any specific facts or

More information

3RD ANNUAL CANADIAN CONSTRUCTION INSURANCE LAW: NEW WAYS TO MANAGE RISK AND AVOID LIABILITY

3RD ANNUAL CANADIAN CONSTRUCTION INSURANCE LAW: NEW WAYS TO MANAGE RISK AND AVOID LIABILITY 3RD ANNUAL CANADIAN CONSTRUCTION INSURANCE LAW: Construction projects and insurance policies go hand-in-hand. But it s important to know what s insurable, what s not, and what to look for in purchasing

More information

SECTION 3 AWARD AND EXECUTION OF CONTRACT

SECTION 3 AWARD AND EXECUTION OF CONTRACT SECTION 3 AWARD AND EXECUTION OF CONTRACT 3.01 CONSIDERATION OF BIDS: After the Proposals are opened and read, the approximate estimated quantity of each item multiplied by the unit price bid for that

More information

OWNER S CHECKLIST ISSUES FOR PERFORMANCE AND PAYMENT BONDS Produced by the ABA Forum on the Construction Industry Division 12: Owners and Lenders

OWNER S CHECKLIST ISSUES FOR PERFORMANCE AND PAYMENT BONDS Produced by the ABA Forum on the Construction Industry Division 12: Owners and Lenders OWNER S CHECKLIST ISSUES FOR PERFORMANCE AND PAYMENT BONDS Produced by the ABA Forum on the Construction Industry Division 12: Owners and Lenders Christopher Dunn, Esquire Claramargaret H. Groover, Esquire

More information