1 PART 1 GENERAL 1.1. SECTION INCLUDES Overview of waste management and disposal requirements and procedures RELATED WORK Schedule W1 Waste Management and Disposal Proposed Receiving Facilities Schedule W2 Waste Management and Disposal Waste Tracking Worksheet 1.3. DEFINITIONS Solid Waste: Any waste material (including land-clearing debris) that is sent from the Project site to another location for disposal Land-Clearing Debris: Waste materials resulting from land-clearing that include pre-existing development materials and plant matter, but do not include soil Reused Waste: Waste materials that are sent to a location off-site (e.g. another construction project or product supplier) where they are used in their original form (i.e. without additional processing) Recycled Waste: Waste materials that are sent off-site to a recycling facility where they are used to displace virgin materials as feedstock for manufacturing processes that create new products Landfill Waste: Waste materials that are sent to a landfill site for disposal REFERENCES Ontario. Environmental Protection Act. Ontario Regulation 102/94: Waste Audits and Waste Reduction Workplans Ontario. Ministry of the Environment (MOE). A Guide to waste Audits and Reduction Workplans for Construction and Demolition Projects as Required Under Ontario Regulation 102/ Ontario. Environmental Protection Act. Ontario Regulation 103/94: Industrial, Commercial and Institutional Source Separation Programs Ontario. Ministry of the Environment (MOE). A Guide to Source Separation of Recyclable Materials for Industrial, Commercial and Institutional Sectors and Multi-Unit Residential Buildings as Required Under Ontario Regulation 103/ Canadian Construction Association. Standard Construction Document CCA : A Guide on Construction Environmental Management Planning Canadian Construction Association. Standard Construction Document CCA : A Best Practices Guide to Solid Waste Reduction Canada. Public Works and Government Services Canada National Construction Renovation and Demolition Non-Hazardous Solid Waste Management Protocol CaGBC. Materials & Resources Credit 2: Construction Waste Management. Leadership in Energy and Environmental Design Reference Guide for New Construction & Major Renovations (LEED Canada-NC Version 1.0) Canadian Tire Page 1 of 5

2 Construction Specifications 1.5. OBJECTIVES Minimize the amount of solid waste (including land-clearing debris) generated by construction, renovation and demolition (CRD) activities Of the inevitable solid waste (including land-clearing debris) that is generated by CRD activities, divert more than 75% from landfill (through reuse and recycling) to achieve LEED Canada-NC Version 1.0 credits MRc2.1 and MRc2.2 Construction Waste Management Comply with all applicable Environmental Protection Act of Ontario regulations relating to construction waste management including Ontario Regulation 102/94 and Ontario Regulation 103/ Comply with Canadian Construction Association s Code of Practice outlined in Standard Construction Document CCA to encourage improved waste management practices DESCRIPTION OF WORK The Site Superintendent (or other person designated by the Contractor) shall be responsible for all aspects of Waste Management and Disposal Identify, implement and document measures to achieve the waste management objectives listed above Follow a strategy based on the 3R s hierarchy: Reduce the generation of waste materials at the Project site, Reuse waste materials on other construction sites (when feasible) and Recycle waste materials as feedstock for manufacturing processes that create new products Waste Management and Disposal activities shall include: 1. Arranging waste management service agreements with waste haulers and waste receiving facilities. 2. Supervising on-site waste management activities on a daily basis. 3. Coordinating waste management tasks with Subcontractors to ensure timely and orderly progress of the Work. 4. Preparing waste management documentation and submittals to summarize all shipments of waste materials from the Project site. 5. Reporting waste management progress to the Consultant KICK-OFF MEETING Prior to mobilization on-site, the Contractor shall hold a kick-off meeting with the Consultant to review the Waste Management and Disposal requirements. This meeting shall include a review of: 1. Waste Management and Disposal objectives 2. Waste Management and Disposal requirements and procedures 3. Waste Management and Disposal documentation and submittals 1.8. COORDINATION MEETING Page 2 of 5 Canadian Tire

3 Prior to start of construction, the Contractor (in conjunction with the Consultant) shall hold a coordination meeting with the construction team to explain the Waste Management and Disposal requirements to the Subcontractors. This meeting shall include a review of: 1. Waste Management and Disposal objectives 2. Waste Management and Disposal requirements and procedures 3. Waste Management and Disposal documentation and submittals 1.9. SUBMITTALS Schedule W1 Proposed Receiving Facilities 1. List the proposed receiving facilities for each material identified in paragraph in addition to material sent to landfill. Indicate the material(s) that will be accepted by each facility and whether the material(s) will be reused, recycled or sent to landfill. 2. Submit completed schedule to the Consultant within 14 days after site mobilization Schedule W2 Waste Tracking Worksheet 1. Obtain waybills, invoices, letters and other documentation that clearly indicates the receiving facility, end use (reused, recycled or landfill) and quantity of waste for each shipment of waste generated on the Project site. Record each shipment using the Waste Tracking Worksheet. 2. Submit an up-to-date copy of the Waste Tracking Worksheet and waybills, invoices, letters and other documentation to the Consultant on a monthly basis Final Waste Diversion Report 1. Submit a final report to the Consultant (after substantial completion and prior to demobilization) that contains the final versions of the following: a) Waste Tracking Worksheet(s) b) Waybills, invoices, letters and other documentation supporting each shipment listed in the Waste Tracking Worksheet clearly indicating quantities, end uses and receiving facilities. PART 2 PRODUCTS NOT USED PART 3 EXECUTION 3.1. PROCEDURES Waste Reduction 1. 1 Encourage Suppliers and Subcontractors to retrieve/retain packaging (e.g. skids, plastic wrap, etc.) for reuse. a) Suppliers and Subcontractors must provide a letter stating the item(s) will be reused and documenting the quantity removed from the site. Canadian Tire Page 3 of 5

4 Construction Specifications 2. Prevent damage of materials due to mishandling, improper storage, and contamination. 3. Where possible, use prefabricated assemblies built at a central facility to avoid waste generation at the site Waste Diversion 1. Contact local salvaging/recycling facilities and arrange for recycling/reuse services. At a minimum, the proposed facilities must recycle/reuse the following waste materials that will be generated throughout construction: 2. Note: a) Land clearing debris b) Asphalt c) Concrete / masonry / stone d) Steel and other metals e) Wood (see note below) f) Gypsum g) Cardboard h) Plastic i) Blue Box waste a) Use of material as landfill cover is not considered as recycling or reuse. b) Incineration of wood waste for power generation is not considered as recycling or reuse. c) Recommended measures for recycling/reusing wood include encouraging Suppliers to reuse wood pallets, sending wood pallets to pallet recycling companies and converting waste wood into landscaping mulch. 3. Provide the Consultant with a list of the proposed receiving facilities within 14 days after site mobilization using Schedule W1 Proposed Receiving Facilities (as per 1.9.1). 4. Designate a central Waste Collection Area onsite that is dedicated to the separation and storage of all waste generated during construction. 5. Provide containers in the Waste Collection Area that are sized to accommodate the separation and storage of expected waste types and quantities. Provide separate containers for each of the following material types: a) Land clearing debris b) Asphalt c) Concrete / masonry / stone Page 4 of 5 Canadian Tire

5 d) Steel and other metals e) Wood f) Gypsum g) Cardboard h) Plastic i) Blue Box waste (as per ) j) Mixed waste k) Other types (as required by salvaging/recycling facilities) 6. Clearly indicate the material type being stored in each container using appropriate signage. 7. All Subcontractors shall use the containers provided in Waste Collection Area. 8. In the event that a Subcontractor is unable to use these containers, or wishes to use a waste material on future projects (e.g. rubble for road base), the Subcontractor must provide waybills, invoices, letters and other documentation that clearly indicates the receiving facility, end use (reused, recycled or landfill) and quantity of waste in each shipment. 9. Follow the salvaging/recycling facilities material acceptance requirements to ensure materials are properly sorted, grouped, and packaged for collection Provide Blue Box recycling bins for cardboard, paper and food and beverage containers near the construction trailer for recycling waste generated by site workers and visitors. Waste deposited in these bins shall adhere to the local recycling program Waste Tracking 1. Coordinate delivery of separated materials to approved salvage or recycling facilities. 2. Record all waste shipments using Schedule W2 Waste Tracking Worksheet as per Retain waybills, invoices, letters and other documentation for inclusion in Final Waste Diversion Report (as per 1.9.3) INSPECTIONS AND MAINTENANCE Conduct daily inspections of containers to check for and remedy cross-contamination Promptly transport containers to receiving facilities when containers are full Ensure the material type is clearly labeled on each container. END OF SECTION 1 2 Revised Canadian Tire Page 5 of 5

Department of Public Works. Recycling policy for buildings and civil infrastructure

Department of Public Works. Recycling policy for buildings and civil infrastructure Department of Public Works Recycling policy for buildings and civil infrastructure A whole-of-government recycling policy for buildings and civil infrastructure Policy statement The Queensland Government

More information

CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT. CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS

CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT. CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS CITY OF CHICAGO DEPARTMENT OF ENVIRONMENT CONSTRUCTION or DEMOLITION SITE WASTE RECYCLING RULES AND REGULATIONS W hereas, pursuant to Chapters 11-4 and 2-30 of the Municipal Code of Chicago (the Code ),

More information

DRAFT Construction & Demolition Recycling Ordinance. Environmental Commission September 2, 2015

DRAFT Construction & Demolition Recycling Ordinance. Environmental Commission September 2, 2015 DRAFT Construction & Demolition Recycling Ordinance Environmental Commission September 2, 2015 Woody Raine, Gena McKinley Austin Resource Recovery Item 6c Outline Prior Council Action Ordinance Development

More information

PUBLIC WORKS DEPARTMENT Resource Recovery & Recycling Division. CONSTRUCTION & DEMOLITION (C&D) WASTE MANAGEMENT PLAN Instructions/General Information

PUBLIC WORKS DEPARTMENT Resource Recovery & Recycling Division. CONSTRUCTION & DEMOLITION (C&D) WASTE MANAGEMENT PLAN Instructions/General Information PUBLIC WORKS DEPARTMENT Resource Recovery & Recycling Division CONSTRUCTION & DEMOLITION (C&D) WASTE MANAGEMENT PLAN Instructions/General Information When Required: It is necessary to complete the C&D

More information

C&D Waste Diversion in Other Jurisdictions. Maria Kelleher 20 th July, 2006

C&D Waste Diversion in Other Jurisdictions. Maria Kelleher 20 th July, 2006 C&D Waste Diversion in Other Jurisdictions Maria Kelleher 20 th July, 2006 Best Practices Research to look at what others are doing is underway Focus on active drivers not passive ones, such as voluntary

More information

CONSTRUCTION AND DEMOLITION (C & D) Waste Management Plan Form:

CONSTRUCTION AND DEMOLITION (C & D) Waste Management Plan Form: CONSTRUCTION AND DEMOLITION (C & D) Waste Management Plan Form: Please complete and submit this form with your building permit application. 80% of all demolition and construction material must be recycled.

More information

Charrette Small Group Session Friday, January 27. 8:30 am 10:00 am

Charrette Small Group Session Friday, January 27. 8:30 am 10:00 am Construction & Demolition Recycling Charrette Small Group Session Friday, January 27 th 8:30 am 10:00 am What is C&D? As defined by NC DENR, C&D solid waste is solid waste generated solely from the construction,

More information

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot

Construction Management Statement. Residential development at Bywell House, St Mary s Hill, Ascot Construction Management Statement Residential development at Bywell House, St Mary s Hill, Ascot Parking of Vehicles of Site Personnel, Operatives and Visitors Site staff, visitors to the development and

More information

Presenter: Michael Buono, Director of Program Development Environmental Service Management Group, Inc.

Presenter: Michael Buono, Director of Program Development Environmental Service Management Group, Inc. Presenter: Michael Buono, Director of Program Development Environmental Service Management Group, Inc. Exceptional Environmental Performance Series Case Study of High Performance LEED Project Recycling

More information

SECTION 02 42 13 - REMOVAL AND SALVAGE OF CONSTUCTION MATERIAL RECLAMATION OF RESILIENT FLOORING

SECTION 02 42 13 - REMOVAL AND SALVAGE OF CONSTUCTION MATERIAL RECLAMATION OF RESILIENT FLOORING Armstrong World Industries, Inc. Recycle Flooring Specifications Please understand that you are responsible for the accuracy of all project specifications, including any Armstrong guide specifications

More information

TurnerTalk Online Waste Tracking System User s Guide for Reviewers and Haulers. Version 3.0 Date: May 15, 2009 Turner Construction Company

TurnerTalk Online Waste Tracking System User s Guide for Reviewers and Haulers. Version 3.0 Date: May 15, 2009 Turner Construction Company TurnerTalk Online Waste Tracking System User s Guide for Reviewers and Haulers Version 3.0 Date: May 15, 2009 Turner Construction Company Philosophy Our goal at Turner is for every project to be a green

More information

Sustainability in construction at Creighton

Sustainability in construction at Creighton Sustainability in construction at Creighton Like many other higher education campuses and companies Creighton is striving to draft their own policies, procedures and guidelines. Through the support of

More information

Masters in Recreational Surfacing. Playground Surfacing Gymnasium Flooring Fitness Flooring Specialty Surfacing Trail & Pathway Surfacing.

Masters in Recreational Surfacing. Playground Surfacing Gymnasium Flooring Fitness Flooring Specialty Surfacing Trail & Pathway Surfacing. Masters in Recreational Surfacing Playground Surfacing Gymnasium Flooring Fitness Flooring Specialty Surfacing Trail & Pathway Surfacing LEED How Surface America Can Contribute To Obtaining LEED Credits

More information

Avoiding the Landfill: The Recycling of Vinyl Roof Membranes

Avoiding the Landfill: The Recycling of Vinyl Roof Membranes Avoiding the Landfill: The Recycling of Vinyl Roof Membranes With its European counterparts blazing the trail, the North American vinyl (PVC) roofing industry has entered a new phase in its commitment

More information

Required WM Prerequisite 1 Waste Management Plan

Required WM Prerequisite 1 Waste Management Plan Required WM Prerequisite 1 Plan Intent Institute a waste management plan to establish a framework of policies and procedures with a goal of zero waste. Health Issues U.S. hospitals generate approximately

More information

3.1.8 Utilities and Service Systems

3.1.8 Utilities and Service Systems 3.1.8 Utilities and Service Systems This section discusses potential impacts to utilities and service systems, including water, wastewater, and solid waste hauling and disposal, resulting from the implementation

More information

IV. ENVIRONMENTAL IMPACT ANALYSIS L. UTILITIES AND SERVICE SYSTEMS 3. SOLID WASTE AND DISPOSAL

IV. ENVIRONMENTAL IMPACT ANALYSIS L. UTILITIES AND SERVICE SYSTEMS 3. SOLID WASTE AND DISPOSAL IV. ENVIRONMENTAL IMPACT ANALYSIS L. UTILITIES AND SERVICE SYSTEMS 3. SOLID WASTE AND DISPOSAL ENVIRONMENTAL SETTING Within the City, solid waste management, including collection and disposal services

More information

Environmental, Occupational

Environmental, Occupational Colgate Cares This is one in a series of publications describing ColgatePalmolive s various social responsibility programs. If you would like to receive any of the publications in the series listed below,

More information

Memorandum SAN JOSE CAPITAL OF SILICON VALLEY ENVIRONMENT COMMITTEE RECOMMENDATION

Memorandum SAN JOSE CAPITAL OF SILICON VALLEY ENVIRONMENT COMMITTEE RECOMMENDATION T&E AGENDA: 05-07-12 ITEM: d(4) CITY OF ~ SAN JOSE CAPITAL OF SILICON VALLEY TO - TRANSPORTATION AND ENVIRONMENT COMMITTEE Memorandum FROM: Kerrie Romanow SUBJECT: COMMERCIAL SOLID WASTE DATE: TRANSITION

More information

Appendix 19.1 Outline Project Construction and Demolition Plan

Appendix 19.1 Outline Project Construction and Demolition Plan Appendix 19.1 Outline Project Construction and Demolition Plan Environmental Impact Statement Page A19.1.1 of A19.1.6 Appendix 19.1_Outline Project Construction and Demolition Plan OUTLINE PROJECT CONSTRUCTION

More information

A guide to our recycling And waste management services

A guide to our recycling And waste management services A guide to our recycling And waste management services SITA UK provides recycling and waste management services for more than 40,000 organisations across the UK These organisations choose SITA UK because

More information

Monitoring & Recording Hazardous & Non-Hazardous Waste

Monitoring & Recording Hazardous & Non-Hazardous Waste GIIRS Emerging Market Assessment Resource Guide: What s in this Guide? I. Definition: What is II. Methods for Disposal: Non-Hazardous Waste III. Methods for Storage and Disposal: Hazardous Waste IV. Additional

More information

ACKNOWLEDGEMENT OF RECEIPT OF THE CITY OF DUBLIN CONSTRUCTION AND DEMOLITION DEBRIS ORDINANCE INFORMATION PACKET

ACKNOWLEDGEMENT OF RECEIPT OF THE CITY OF DUBLIN CONSTRUCTION AND DEMOLITION DEBRIS ORDINANCE INFORMATION PACKET ACKNOWLEDGEMENT OF RECEIPT OF THE CITY OF DUBLIN CONSTRUCTION AND DEMOLITION DEBRIS ORDINANCE INFORMATION PACKET I do hereby acknowledge that I have received the City of Dublin Construction and Demolition

More information

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES

CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES CITY OF VINCENT CONSTRUCTION MANAGEMENT PLAN GUIDELINES INTRODUCTION What is a Construction Management Plan? The City of Vincent requires careful management of construction involving excavation and retention

More information

RESOURCE USE & THE SUPPLY CHAIN

RESOURCE USE & THE SUPPLY CHAIN RESOURCE USE & THE SUPPLY CHAIN as part of the Energy Efficiency Information Grants Program Energy efficiency is one aspect of broader resource efficiency, which is the efficient use and re-use of all

More information

Waste & Recycling Assessment and Audit. Congratulations on completing Step 1 by forming your Green Team!

Waste & Recycling Assessment and Audit. Congratulations on completing Step 1 by forming your Green Team! . Seattle Public Schools can use this editable document as your Assessment. You'll see that many of the answers have already been filled in for you! School Name: Date: Conducted By: Congratulations on

More information

2006 Standard Application Processing Time. 10 months. 14 months

2006 Standard Application Processing Time. 10 months. 14 months Air and Radiation Management Administration General Permit to Construct - without expanded public review Air Quality Permit to Construct - with expanded public review but limited public interest 11 months

More information

Joseph Laquatra and Mark R. Pierce

Joseph Laquatra and Mark R. Pierce Joseph Laquatra and Mark R. Pierce This publication is issued to further Cooperative Extension work mandated by acts of Congress of May 8 and June 30, 1914. It was produced with the coop-eration of the

More information

South Carolina s Recycling Industry

South Carolina s Recycling Industry South Carolina s Recycling Industry Recycling Market Development Advisory Council Created by the Solid Waste Policy and Management Act of 1991, South Carolina s authority on recycling markets is the Recycling

More information

Required Recycling and Incentive Program Survey Summary of Findings April 2002

Required Recycling and Incentive Program Survey Summary of Findings April 2002 Required Recycling and Incentive Program Survey Summary of Findings April 2002 Prepared by: Marta Conklé McGuire Waste Reduction Division Metro Regional Environmental Management Department 600 Northeast

More information

City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For. Construction Management Services for the

City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For. Construction Management Services for the City Of Portsmouth, New Hampshire REQUEST FOR QUALIFICATIONS # 30-10 For Construction Management Services for the Renovation and Expansion of Portsmouth Middle School INVITATION The City of Portsmouth,

More information

CSC-DIVISION 1-MASTER SECTIONS Description

CSC-DIVISION 1-MASTER SECTIONS Description CSC-DIVISION 1-MASTER SECTIONS Description 01 11 00 Summary of Work by Consultant 01 12 00 Multiple Contract Summary by Consultant 01 14 00 Work Restrictions see below 01 21 00 Allowances by Consultant

More information

Contract No. CV / 2007 / 06 Kwai Chung Incineration Plant Demolition and Decontamination Works Site Management Plan for TRIP TICKET SYSTEM

Contract No. CV / 2007 / 06 Kwai Chung Incineration Plant Demolition and Decontamination Works Site Management Plan for TRIP TICKET SYSTEM Site Management Plan for TRIP TICKET SYSTEM (Version 1.3) CONTENT Item Description(s) Page No. 1. Introduction 2-3 2. Disposal of C & D Materials to Designated Disposal Ground 4 3. Site Management Plan

More information

Green Building: Recycling Construction Renovation and Reclamation. Sponsored by:

Green Building: Recycling Construction Renovation and Reclamation. Sponsored by: Green Building: Recycling Construction Renovation and Reclamation Sponsored by: 1 C&D Waste: Market Overview Applying it to Tulsa Lessons Learned Chad Burden, Owner of Green Residential Retrofit in Tulsa

More information

Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut

Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Final Construction Quality Control Plan Non-Public Properties Newhall Street Neighborhood Site Hamden, Connecticut Revision 0 Prepared for: Olin Corporation Cleveland, Tennessee Prepared by: Sevenson Environmental

More information

(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at:

(A) All asbestos-containing waste material shall be deposited as soon as is practical by the waste generator at: 3745-20-05 Standard for asbestos waste handling. [Comment: For dates of non-regulatory government publications, publications of recognized organizations and associations, federal rules, and federal statutory

More information

Florida Department of Environmental Protection

Florida Department of Environmental Protection Florida Department of Environmental Protection Background Mobile vehicle and equipment washing involves washing at a location where vehicles are based (such as a trucking company, warehouse, bus station,

More information

T109 Architectural Technology MTCU Code 60600 Program Learning Outcomes

T109 Architectural Technology MTCU Code 60600 Program Learning Outcomes T109 Architectural Technology MTCU Code 60600 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes* The graduate has reliably demonstrated the ability to 1. communicate with clients,

More information

3.6 SERVICES. This section describes the fire, police, solid waste, and school services for Ames Research Center. A. Fire

3.6 SERVICES. This section describes the fire, police, solid waste, and school services for Ames Research Center. A. Fire 3.6 SERVICES This section describes the fire, police, solid waste, and school services for Ames Research Center. A. Fire Fire protection services at Ames Research Center are currently provided by NASA

More information

Construction & Demolition Waste Management in Green Star Discussion Paper

Construction & Demolition Waste Management in Green Star Discussion Paper Construction & Demolition Waste Management in Green Star Discussion Paper 1 Construction & Demolition Waste Management in Green Star - Discussion Paper Construction & Demolition Waste Management in Green

More information

Source Reduction, on-site handling and processing of Solid waste. CE 431: Solid Waste Management

Source Reduction, on-site handling and processing of Solid waste. CE 431: Solid Waste Management Source Reduction, on-site handling and processing of Solid waste CE 431: Solid Waste Management Functional Elements of Waste Management System Source Reduction/Waste Minimization First element of any waste

More information

Implementation... Educate and Train Your Associates

Implementation... Educate and Train Your Associates Implementation...Educate and Train Your Associates 15 Gather regional manager, warehouse manager, sustainability representative, department leads and department associates for a meeting to educate on the

More information

University Food Trucks are Food Trucks operated by Residential and Dining Enterprises.

University Food Trucks are Food Trucks operated by Residential and Dining Enterprises. MOBILE FOOD VENDOR POLICY 1. Policy With the exception of Special Event Food Trucks and Construction Food Trucks, Mobile Food Vendors may only sell at times and Stanford University campus locations ( Campus

More information

APPENDIX 7-B. Hazardous Materials Management Plan

APPENDIX 7-B. Hazardous Materials Management Plan S TAR-ORION S OUTH D IAMOND P ROJECT E NVIRONMENTAL I MPACT A SSESSMENT APPENDIX 7-B Hazardous Materials Management Plan SX03733 Section 6.0 1.1.1 Hazardous Materials Management Plan 1.1.1.1 Introduction

More information

Alberta Transportation The City of Edmonton The City of Calgary

Alberta Transportation The City of Edmonton The City of Calgary Alberta Transportation The City of Edmonton The City of Calgary PUBLISHING INFORMATION TITLE: PREPARED BY: DOCUMENT HOLDER: Environmental Construction Operations (ECO) Plan Framework Instructions for

More information

Sort it! Bag it! Tote it! Recycle it!

Sort it! Bag it! Tote it! Recycle it! Sort it! Bag it! Tote it! Recycle it! CA RD BOA RD / BOXBOARD Recycling guidelines for property owners, managers, and superintendents for multi-residential properties DURHAM REGION WORKS DEPARTMENT WASTE

More information

KAWARTHA PINE RIDGE DISTRICT SCHOOL BOARD

KAWARTHA PINE RIDGE DISTRICT SCHOOL BOARD KAWARTHA PINE RIDGE DISTRICT SCHOOL BOARD KENNER COLLEGIATE VOCATIONAL INSTITUTE CULINARY ARTS AND CLASSROOM RENOVATIONS 633 Monaghan Road, Peterborough, Ontario Project No. 16010 June 14, 2016 SPECIFICATIONS

More information

MARSHALL UNIVERSITY HAZARDOUS WASTE DISPOSAL SECTION

MARSHALL UNIVERSITY HAZARDOUS WASTE DISPOSAL SECTION MARSHALL UNIVERSITY HAZARDOUS WASTE DISPOSAL SECTION TABLE OF CONTENTS POLICY STATEMENT.2 REFERENCE PROCEDURE 3 l.0 Purpose.3 2.0 Scope 3 3.0 Definitions 4 4.0 Responsibilities 5 5.0 Procedure.7 11/16/2005

More information

GENERAL PERMIT WMGM043

GENERAL PERMIT WMGM043 A. Description: The approval herein granted is for the acceptance, transfer, and processing prior to beneficial use of construction and demolition waste materials as follows: a. Processing by sorting,

More information

City of Key West, Florida Solid Waste Master Plan Executive Summary

City of Key West, Florida Solid Waste Master Plan Executive Summary The City of Key West (City) retained Kessler Consulting, Inc. (KCI) to assist in developing a Solid Waste Master Plan (Plan). The purpose of the Plan is to analyze the City s existing solid waste system,

More information

THE COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT S REVISED ASBESTOS-IN-SOILS REGULATIONS AND THE COLORADO BROWNFIELDS TAX CREDIT

THE COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT S REVISED ASBESTOS-IN-SOILS REGULATIONS AND THE COLORADO BROWNFIELDS TAX CREDIT THE COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT S REVISED ASBESTOS-IN-SOILS REGULATIONS AND THE COLORADO BROWNFIELDS TAX CREDIT Presented by Polly Jessen Kaplan Kirsch & Rockwell LLP January 22,

More information

Sika Sarnafil World Class Roofing and Waterproofing

Sika Sarnafil World Class Roofing and Waterproofing The following is a brief summary of the Leadership in Energy and Environmental Design program (LEED, Version 3) and the sections Sika Sarnafil s roofing systems can help contribute to obtaining LEED points.

More information

15 years A N D. Recycle used ceiling tiles keep them out of the landfill SAVE THE CEILINGS. with the Armstrong Ceiling Recycling Program

15 years A N D. Recycle used ceiling tiles keep them out of the landfill SAVE THE CEILINGS. with the Armstrong Ceiling Recycling Program CEILING RECYCLING PROGRAM 15 years A N D GR OWING Recycle used ceiling tiles keep them out of the landfill SAVE THE CEILINGS with the Armstrong Ceiling Recycling Program Recycling your old ceiling panels

More information

CONSTRUCTION MANAGEMENT REPORT NO. 2

CONSTRUCTION MANAGEMENT REPORT NO. 2 CONSTRUCTION MANAGEMENT REPORT NO. 2 Expansion and Renovation Prepared for: HOLLAND PUBLIC SCHOOLS BOARD OF EDUCATION Date: October 31, 2011 HOLLAND PUBLIC SCHOOLS HIGH SCHOOL EXPANSION AND RENOVATION

More information

1. What do you think are the components of a waste management plan? 2. What do you currently have in place in your school or district?

1. What do you think are the components of a waste management plan? 2. What do you currently have in place in your school or district? Recycling and Waste Management Training Companion Guide BEFORE you watch the web training, answer the following questions: 1. What do you think are the components of a waste management plan? 2. What do

More information

DIVISION I GENERAL REQUIREMENTS SECTION 01005

DIVISION I GENERAL REQUIREMENTS SECTION 01005 Subdivision Requirements Manual Page 1 of 13 PART I - GENERAL 1.1 Description.1 The requirements of this specification shall apply to the contract as a whole and pertain to all of the work as specified

More information

Waste Diversion Update. Quality of Life & Environment Committee January 26 th 2015

Waste Diversion Update. Quality of Life & Environment Committee January 26 th 2015 Waste Diversion Update Quality of Life & Environment Committee January 26 th 2015 Purpose Discuss status of Zero Waste efforts and goals Discuss current outreach programs, partnerships, and policies to

More information

NECESSARY DOCUMENTATION ACCORDING TO the LAW

NECESSARY DOCUMENTATION ACCORDING TO the LAW 1 NECESSARY DOCUMENTATION ACCORDING TO the LAW According to the Law, your company is obliged to submit monthly reports prepared based on the manufacturing specifications and the monthly sales report. Manufacturing

More information

Edmonton Waste Management Centre Contract Review November 2, 2015

Edmonton Waste Management Centre Contract Review November 2, 2015 Edmonton Waste Management Centre Contract Review November 2, 2015 The Office of the City Auditor conducted this project in accordance with the International Standards for the Professional Practice of Internal

More information

SPACE ALLOCATION AND ENCLOSURE DESIGN GUIDELINES FOR TRASH AND RECYCLING

SPACE ALLOCATION AND ENCLOSURE DESIGN GUIDELINES FOR TRASH AND RECYCLING SPACE ALLOCATION AND ENCLOSURE DESIGN GUIDELINES FOR TRASH AND RECYCLING For Residential and New Commercial Construction and Remodel Dated July 1, 2010 If you have any questions regarding the Design Guidelines

More information

Construction and Demolition Waste

Construction and Demolition Waste Re-issued under new categorization in August 2009 as Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers ADV-19 Buildings Department Practice Note

More information

FLORIDA HAZARDOUS WASTE MANAGEMENT REGULATIONS THAT DIFFER FROM FEDERAL REQUIREMENTS

FLORIDA HAZARDOUS WASTE MANAGEMENT REGULATIONS THAT DIFFER FROM FEDERAL REQUIREMENTS FLORIDA HAZARDOUS WASTE MANAGEMENT REGULATIONS THAT DIFFER FROM FEDERAL REQUIREMENTS Chapter 1: Introduction General Notes Lead Agency: Florida Department of Environmental Protection (DEP) Division of

More information

FACTS ABOUT: Recycling MONTGOMERY COUNTY RECYCLING

FACTS ABOUT: Recycling MONTGOMERY COUNTY RECYCLING Maryland Department of the Environment FACTS ABOUT: Recycling MONTGOMERY COUNTY RECYCLING Coordinator/Staff Eileen Kao, Chief, Waste Reduction and Recycling Section Alan Pultyniewicz, Recycling Coordinator

More information

3R Guidebook for Shopping Malls

3R Guidebook for Shopping Malls 3R Guidebook for Shopping Malls CONTENT Page About this Guide 1 What can be learnt from this Guide?... 1 CHAPTER 1: INTRODUCTION Overview of Solid Waste Management in Singapore... 2 Strategies for Sustainable

More information

Recycle whatever can be recycled according to the DHMC Recycling Program! See the intranet site or the last page of this document for details.

Recycle whatever can be recycled according to the DHMC Recycling Program! See the intranet site or the last page of this document for details. Environmental Programs at DHMC are more than just recycling and waste management programs, although these are cornerstones of the Program. Waste and pollution prevention means we re trying to make less

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

Construction & Demolition Waste Management Plan Resource Guide for Contractors

Construction & Demolition Waste Management Plan Resource Guide for Contractors Construction & Demolition Waste Management Plan Resource Guide for Contractors Environmental Utilities Solid Waste Division 2005 Hilltop Circle Roseville, California 95747 916-774-5780 916-774-5798 fax

More information

SENATE... No. 2308. The Commonwealth of Massachusetts. In the Year Two Thousand Fourteen

SENATE... No. 2308. The Commonwealth of Massachusetts. In the Year Two Thousand Fourteen SENATE.............. No. 2308 The Commonwealth of Massachusetts In the Year Two Thousand Fourteen SENATE, Thursday, July 24, 2014 The committee on Ways and Means, to whom was referred the Senate Bill to

More information

Latifa MOUHIR Department Process Engineering and Environment Faculty of Science and Technology Hassan II University. Mohammedia. Morocco.

Latifa MOUHIR Department Process Engineering and Environment Faculty of Science and Technology Hassan II University. Mohammedia. Morocco. Latifa MOUHIR Department Process Engineering and Environment Faculty of Science and Technology Hassan II University. Mohammedia. Morocco. E mail: latmouh@gmail.com. INTRODUCTION MEDICAL AND PHARMACEUTICAL

More information

Site waste it s criminal A simple guide to Site Waste Management Plans

Site waste it s criminal A simple guide to Site Waste Management Plans Site waste it s criminal A simple guide to Site Waste Management Plans Introduction 10m tonnes of construction products are wasted every year, at a cost of 1.5 billion Much of this site waste is harmful

More information

Waste management and disposal:

Waste management and disposal: Waste management and disposal: A best practice business guide An ebook produced by FCC Environment 01 Waste management and disposal: a strategy for success Introduction Your guide to waste management FCC

More information

Contracts. Definitions. Guidelines for contractors and subcontractors

Contracts. Definitions. Guidelines for contractors and subcontractors 0. Contractors www.revenue.state.mn.us 128 Sales Tax Fact Sheet What s New in 2014 The sales and use tax on repair and maintenance of certain business equipment has been repealed effective April 1, 2014.

More information

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update

REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS. ATTACHMENTS: 1. Construction Management Update REQUEST FOR BOARD ACTION HENDERSON COUNTY BOARD OF COMMISSIONERS MEETING DATE: March 16, 2011 SUBJECT: PRESENTER: ATTACHMENTS: Construction Management Update David Berry Yes 1. Construction Management

More information

San Francisco Zero Waste Policies & Programs. Jack Macy Department of the Environment City and County of San Francisco

San Francisco Zero Waste Policies & Programs. Jack Macy Department of the Environment City and County of San Francisco San Francisco Zero Waste Policies & Programs Jack Macy Department of the Environment City and County of San Francisco Zero Waste for Sustainability Conserve Resources Need FOUR planets if every one consumed

More information

Cost Estimating for RCRA Financial Assurance

Cost Estimating for RCRA Financial Assurance Cost Estimating for RCRA Financial Assurance A good cost estimate is a key link between an approved permit, plan, or remedy selection and the need to obtain adequate financial assurance Many if not most

More information

4 R Guide Reduce Reuse Recycle Recover

4 R Guide Reduce Reuse Recycle Recover 4 R Guide Reduce Recover 4 R Guide Skanska s Environmental Policy include a long term objective on Zero Waste Generation. This can be achieved by reducing upfront demand, reusing materials wherever possible

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

Waste Management for Hotels and Restaurants. Dan Ruben

Waste Management for Hotels and Restaurants. Dan Ruben Waste Management for Hotels and Restaurants Dan Ruben Presentation Topics 1. Benefits of Effective Waste Management 2. How to Organize a Waste Management Program 3. Reduce 4. Reuse 5. Recycle 6. Purchase

More information

How To Write A Sustainable Resource Management Framework

How To Write A Sustainable Resource Management Framework FORTH REPLACEMENT CROSSING M9 Junction 1a Project Quality Plan: Volume 4 Sustainable Resource Management Framework Construction Issue RSMF 02: May, 2012 FORTH REPLACEMENT CROSSING M9 JUNCTION A1 SUSTAINABLE

More information

Construction Debris & Recycling Program Application General Liability

Construction Debris & Recycling Program Application General Liability Submission Requirements: Construction Debris & Recycling Program Application General Liability 5 years currently valued loss runs Narrative on any Losses in Excess of $10,000 Completed questionnaire, signed

More information

ORDINANCE NO. 3 OF 2009

ORDINANCE NO. 3 OF 2009 PENN TOWNSHIP CUMBERLAND COUNTY BOARD OF SUPERVISORS 1301 Centerville Road Tel: 717-486-3104 Newville, PA 17241 Fax: 717-486-3522 Email: penntwp@kuhncom.net Website: www.penntwpcc.org ORDINANCE NO. 3 OF

More information

Presentation Overview. Site Waste Management Plans: A missed opportunity?

Presentation Overview. Site Waste Management Plans: A missed opportunity? Site Waste Management Plans: A missed opportunity? Presenter: Derek Duckett (CEnv, MIEMA) Project Manager Company: Mabbett & Associates (EH&S Consultants & Engineers) duckett@mabbett.com Presentation Overview

More information

AGRICULTURAL WASTE REDUCTION

AGRICULTURAL WASTE REDUCTION AGRICULTURAL WASTE REDUCTION Thurston County Solid Waste Waste reduction, the combination of waste prevention and recycling efforts, makes good financial sense. In addition to financial advantages, waste

More information

Newport News Shipbuilding Contractor Environmental, Health and Safety Resource Manual Waste Management

Newport News Shipbuilding Contractor Environmental, Health and Safety Resource Manual Waste Management Newport News Shipbuilding Contractor Environmental, Health and Safety Resource Manual Waste Management Newport News Shipbuilding Page 1 WASTE MANAGEMENT 1. Purpose and Scope a. The purpose of this section

More information

Urban Environmental Management in Singapore. Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency

Urban Environmental Management in Singapore. Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency Urban Environmental Management in Singapore Jothieswaran P Chief Engineer Pollution Control Department National Environment Agency Introduction City state comprising a main island and some islets Land

More information

City of Beaumont, Texas Grading Permit Information

City of Beaumont, Texas Grading Permit Information General Information City of Beaumont, Texas Grading Permit Information The permit application shall be signed by the property owner (or lessee) or his authorized representative and by the contractor (if

More information

CITY of richmond design ConsIderaTIons for CommerCIal ProPerTIes: recycling and garbage

CITY of richmond design ConsIderaTIons for CommerCIal ProPerTIes: recycling and garbage CITY of richmond design considerations for Commercial Properties: Recycling and Garbage 1 design considerations: Recycling and Garbage 1 Introduction Goals, Responsibilities 3 KEY STRATEGIES 4 STORAGE

More information

BROOME COUNTY DEPARTMENT OF AUDIT AND CONTROL SCRAP MATERIALS HANDLING PROCESSES AUDIT JULY 2015

BROOME COUNTY DEPARTMENT OF AUDIT AND CONTROL SCRAP MATERIALS HANDLING PROCESSES AUDIT JULY 2015 BROOME COUNTY DEPARTMENT OF AUDIT AND CONTROL SCRAP MATERIALS HANDLING PROCESSES AUDIT JULY 2015 Alex J. McLaughlin, Comptroller July 28, 2015 Debra A. Preston, County Executive: The Department of Audit

More information

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name

K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY. 1. Applicant's Name K A N S A S DEPARTMENT OF HEALTH AND ENVIRONMENT PERMIT APPLICATION FOR A RECLAMATION FACILITY 1. Applicant's Name Address (Street or Rural Route) (City & State) (Zip) Person to contact Title Phone Fax

More information

More Jobs, Less Pollution:

More Jobs, Less Pollution: Prepared by: Tellus Institute with Sound Resource Management More Jobs, Less Pollution: Growing the Recycling Economy in the U.S. Prepared for: BlueGreen Alliance www.bluegreenalliance.org More Jobs, Less

More information

Too Good to Waste MAKING CONSERVATION A PRIORITY

Too Good to Waste MAKING CONSERVATION A PRIORITY Too Good to Waste MAKING CONSERVATION A PRIORITY Contents 5 7 8 9 10 10 14 18 22 INTRODUCTION > Why Does Alberta Need a Waste Strategy Focused on Conservation? > Principles for Waste Management and Resource

More information

Compactable Construction Waste Collection from Developments with Limited Storage Space

Compactable Construction Waste Collection from Developments with Limited Storage Space Waste Logistics Case Study Compactable Construction Waste Collection from Developments with Limited Storage Space The movement, storage and subsequent removal of mixed construction waste on space-limited

More information

Work Type Definition

Work Type Definition Work Type Definition Page 1-6 details the work type definition. In order to become pre-qualified for this work type, please see the Work Type Submittal Requirements on pages 7-8. I. Description A. Work

More information

waste reduction Environmental Utilities Business Waste Reduction Guide www.roseville.ca.us/ reduceandsave

waste reduction Environmental Utilities Business Waste Reduction Guide www.roseville.ca.us/ reduceandsave waste reduction Environmental Utilities Business Waste Reduction Guide www.roseville.ca.us/ reduceandsave Less Waste = More Profit The City of Roseville generates about 100,000 tons of municipal solid

More information

APPENDIX DC-C REFERENCED CITY OF CHICAGO SPECIFICATIONS AND STANDARDS. November 15, 2010 2010 City of Chicago. Rosemarie S. Andolino Commissioner

APPENDIX DC-C REFERENCED CITY OF CHICAGO SPECIFICATIONS AND STANDARDS. November 15, 2010 2010 City of Chicago. Rosemarie S. Andolino Commissioner Richard M. Daley Mayor Rosemarie S. Andolino Commissioner APPENDIX DCC REFERENCED CITY OF CHICAGO SPECIFICATIONS AND STANDARDS November 15, 2010 2010 City of Chicago Richard M. Daley Mayor Rosemarie S.

More information

Packaging Management Law 5771 2011

Packaging Management Law 5771 2011 1 This is an unofficial translation. The binding version is the official Hebrew text. Readers are consequently advised to consult qualified professional counsel before making any decision in connection

More information

Masters Series LEED. Masters Series Contributions to LEED

Masters Series LEED. Masters Series Contributions to LEED Masters Series LEED Masters Series Contributions to LEED Masters Series wood casegood products may contribute to the individual prerequisites and credits of LEED. Because LEED is a holistic building rating

More information

SUP07-6: Shenandoah Waste Services, LLC Special Use Permit Application for A Materials Recovery Center in a M1 (Industrial) Zoning District

SUP07-6: Shenandoah Waste Services, LLC Special Use Permit Application for A Materials Recovery Center in a M1 (Industrial) Zoning District SUP07-6: Special Use Permit Application for A Materials Recovery Center in a M1 (Industrial) Zoning District Location and Proposed Use The subject 33.76 acre parcel (Tax Map # 42A5 (A) 79) is located on

More information

Application to register for free waste disposal and/or collection service

Application to register for free waste disposal and/or collection service Application to register for free waste disposal and/or collection service Please read the notes attached before completing the application. To qualify for free collection and/or disposal of your waste

More information

City of Toronto Waste Audits Presented to Residual Waste Working Group

City of Toronto Waste Audits Presented to Residual Waste Working Group City of Toronto Waste Audits Presented to Residual Waste Working Group City of Toronto Solid Waste Management Services Policy & Planning Irene Ford Monday February 11 th, 2008 Outline Waste Audits Conducted

More information