1 ENVIRONMENTAL RADIATION PROTECTION IN THE UNITED KINGDOM The Environment Agency s approach Clive Williams
2 Outline Introduction Context Tiered assessment approach The way forward 2
3 Introduction Environment Agency - principal environmental regulator in England and Wales Similar agencies for Scotland, Northern Ireland Authorisation of radioactive waste disposals/discharges from: 20 nuclear sites About 900 other users of radioactive substances 3
4 Context (1) - Legislation Need for environmental radiation protection is driven by existing conservation legislation Includes effects of radioactive substances Not (primarily) radiation protection legislation Not perceived or actual radiological hazard International legislation and obligations EU Habitats and Birds Directives OSPAR - Radioactive Substances Strategy Domestic UK legislation Environment Act 1995; Radioactive Substances Act 1993; Conservation (Natural Habitats) Regs
5 Context (2) Existing obligations have prompted UK developments Questions need to be addressed using sound science Need a system to assure the protection of plants and animals from the harmful effects of radiation Environment Agency has taken a lead in this field: R&D on assessment methodology, commissioned jointly by Environment Agency and English Nature Euratom FP5 Project FASSET Euratom FP6 Project ERICA R&D on effects of radiation on animals and plants Continuing links with ICRP, IAEA and OECD-NEA 5
6 Tiered assessment approach 6
7 Purpose EU Habitats and Birds Directives / UK Conservation (Habitats) Regulations Our obligations are to review: Full range of existing environmental permits, in combination All requests for variations to existing permits, or new applications Ensure that no permitted activity results in an adverse effect, either directly or indirectly, on the integrity of identified European Sites (Natura 2000 Sites) 7
8 Assessment Overview Stage 1 Natura 2000 sites which might be affected by authorised releases of radioactive substances identified using simple rules e.g. authorised aerial discharges within 1km Humber Estuary Stage 2: interim methodology produced in
9 Scientific basis of our assessment approach Environment Agency R&D Publication 128 Uses concept of reference organism - similar to EU FASSET and ERICA projects Enter water, air, soil or biota concentrations to calculate dose rates (µgy/h) Provides advice on practical use of methodology, and states assumptions and constraints Includes a range of radionuclides: 3 H, 14 C, 32 P, 35 S, 60 Co, 99 Tc, 90 Sr, 106 Ru, 125 I, 129 I, 131 I, 137 Cs, 210 Po, 226 Ra, 234 Th, 238 U, Pu, 241 Am, 85 Kr, 41 Ar Terrestrial, freshwater and coastal sites 9
10 Assessment Methodology RADIONUCLIDE SOURCE PATHWAY OF EXPOSURE ECOLOGICAL PARAMETERS REFERENCE ORGANISM Compare predicted dose to known biological or ecological effects & guideline values TOTAL ABSORBED DOSE IMPACT 10
11 Assessment Steps R&D 128 approach used by the Agency to produce a spreadsheet to review the maximum permissible radioactive discharge levels from authorised sites Doses calculated were compared with a conservative screening level (set at 5 µgyh -1 ) (Stage 2) Approximately 100 authorisations have been identified that exceed the screening level at 51 Natura 2000 sites Undertake detailed Stage 3 assessment - compare with 40 µgyh -1 assessment value 11
12 Determine authorisations affecting Natura 2000 site (from Stage 2) Obtain Natura 2000 site information Identify any predator/prey for indirect effects Having identified a feature species, determine concentration factors and occupancy factors Determine which reference organism geometry can be used to approximate the feature species geometry Run Assessment 12
13 9.E+01 8.E+01 7.E+01 6.E+01 5.E+01 4.E+01 3.E+01 2.E+01 1.E+01 0.E+00 Radionuclides: OBT, H-3, P-32, P-33, S-35, Co-60, Sr- 90, Tc-99m, Ru-106, I-125, I-129, I-131, Po-210 Other beta/gamma (t1/2 > 8 days) Other alpha Caesium-137 Carbon-14 Macrophyte Bacteria Zooplankton Small b. crust. Benthic mollusc Benthic fish Pelagic fish Large b. crust. Phytoplankton Fish egg Whale Seal Oystercatcher Seabird Dose rate µgyh -1 Snipe Lapwing Predicted Doses (Humber Estuary) 13
14 The way forward International developments - This Co-ordination Group In particular, the ICRP s recommendations Radiation effects experiments Targeted on ICRP Reference Animals and Plants Environmentally relevant dose rates Environment Agency is keen to collaborate Testing and validation Field-based measurements IAEA EMRAS Programme, Biota Dose Working Group EU ERICA Project case studies 14
15 Conclusion Recognised need for environmental radiation protection Staged and systematic assessment process in the UK Way forward - work towards an agreed international system 15
Position paper on the implications of deep sea disposal of radioctive waste
Agenda Item 4 English only OSPAR Convention for the Protection of the Marine Environment of the North-East Atlantic Meeting of the Radioactive Substances Committee (RSC) Stockholm (Sweden): 20-23 April
More informationCOUNCIL DIRECTIVE 2013/51/EURATOM
L 296/12 Official Journal of the European Union 7.11.2013 DIRECTIVES COUNCIL DIRECTIVE 2013/51/EURATOM of 22 October 2013 laying down requirements for the protection of the health of the general public
More informationTHE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES
THE DECOMMISSIONING OF THE UK NUCLEAR INDUSTRY S FACILITIES Introduction 1. This statement of the UK Government and devolved administrations policy on the decommissioning of nuclear facilities updates
More informationThe Management of Pharmaceuticals in the Environment (PIE) FAQ. Key questions and answers. Q: How do pharmaceuticals get into the environment?
The Management of Pharmaceuticals in the Environment (PIE) FAQ Key questions and answers Q: How do pharmaceuticals get into the environment? A: Like many foods and supplements that are consumed by humans
More informationIAEA Recommendations on a Decommissioning Plan (DP)
IAEA Recommendations on a Decommissioning Plan (DP) Ernst Warnecke, IAEA-NSRW Patrick O Sullivan, IAEA-NEFW Research Reactor Decommissioning Demonstration Project (R²D²P) Review of a Decommissioning Plan
More informationBest Available Techniques (BAT) for the Management of the Generation and Disposal of Radioactive Wastes
(BAT) for the Management of the Generation and Disposal of Radioactive Wastes A Nuclear Industry Code of Practice This Nuclear Industry on Identifying and Implementing Best Available Techniques (BAT) was
More informationIonizing Radiation, Czech Republic, CMI (Czech Metrology Institute)
Ionizing Radiation, Czech Republic, (Czech Metrology Institute) Calibration or Measurement RADIOACTIVITY 1.0E+00 1.0E+02 Bq cm -2 C-14 1.0E+01 1.0E+02 Bq cm -2 Co-60 1.0E+01 1.0E+02 Bq cm -2 Sr-90 1.0E+01
More informationMEMORANDUM OF UNDERSTANDING BETWEEN THE ENVIRONMENTAL PROTECTION AGENCY AND THE NUCLEAR REGULATORY COMMISSION
MEMORANDUM OF UNDERSTANDING BETWEEN THE ENVIRONMENTAL PROTECTION AGENCY AND THE NUCLEAR REGULATORY COMMISSION CONSULTATION AND FINALITY ON DECOMMISSIONING AND DECONTAMINATION OF CONTAMINATED SITES I. Introduction
More informationNuclear accidents and radioactive contamination of foods 30 March 2011
Food and Agriculture Organization of the United Nations Nuclear accidents and radioactive contamination of foods 30 March 2011 This document is intended to provide basic background information and not
More informationNew environmental liabilities for EU companies
New environmental liabilities for EU companies The ELD applies to all businesses that operate within the EU, even if the parent company is located outside of the EU. The ELD applies to all businesses,
More informationEcosystems and Food Webs
Ecosystems and Food Webs How do AIS affect our lakes? Background Information All things on the planet both living and nonliving interact. An Ecosystem is defined as the set of elements, living and nonliving,
More informationUK ENVIRONMENTAL STANDARDS AND CONDITIONS (PHASE 1) Final report. April 2008
UK Technical Advisory Group on the Water Framework Directive UK ENVIRONMENTAL STANDARDS AND CONDITIONS (PHASE 1) Final report April 2008 (SR1 2006) Final Table of Contents LIST OF TABLES...3 SECTION 1
More informationLiability for ecological damage: the added value of the Environmental Liability Directive for nature conservation
Liability for ecological damage: the added value of the Environmental Liability Directive for nature conservation Valerie Fogleman Consultant, Stevens & Bolton LLP Professor of Law, Cardiff University
More informationSummary of the role and operation of NHS Research Management Offices in England
Summary of the role and operation of NHS Research Management Offices in England The purpose of this document is to clearly explain, at the operational level, the activities undertaken by NHS R&D Offices
More informationEnvironmental Protection: Environmental Protection Policies, Programs and Procedures REGDOC-2.9.1
Environmental Protection: Environmental Protection Policies, Programs and Procedures REGDOC-2.9.1 September 2013 Environmental Protection: Policies, Programs and Procedures Regulatory Document REGDOC-2.9.1
More informationWASTE STREAM 2Y51 Analytical Services Process Facilities - North Labs
WASTE STREAM 2Y51 Analytical Services Process Facilities North Labs SITE SITE OWNER WASTE CUSTODIAN WASTE TYPE Sellafield Nuclear Decommissioning Authority Sellafield Limited LLW WASTE VOLUMES Stocks:
More informationEstablishing large-scale trans-boundaries MPA networks: the OSPAR example in North-East Atlantic
Establishing large-scale trans-boundaries MPA networks: the OSPAR example in North-East Atlantic Introduction A pledge to establish a representative network of marine and coastal protected areas by 2012
More informationDevelopment of innovative tools for understanding marine biodiversity and assessing good environmental status: the progress of the EU project DEVOTES
Development of innovative tools for understanding marine biodiversity and assessing good environmental status: the progress of the EU project DEVOTES Angel Borja Scientific Symposium 2015, 6-7 May, Malmö,
More informationCHAPTER 9 PERMITTING. 9.2 Scotland 102 9.2.1 Exemption 102 9.2.2 Waste management licence 102 9.2.3 PPC permit 102
CHAPTER 9 PERMITTING 9.1 England and Wales 100 9.1.1 T24 exemption for on-farm AD 100 9.1.2 T25 exemption for off-farm AD 100 9.1.3 Standard rules environmental permits 100 9.1.4 Standard rules for on-farm
More informationSOFTWARE REQUIREMENTS DESCRIPTION AND SOFTWARE DEVELOPMENT PLAN FOR BIOSPHERE MODEL TO ESTIMATE RADIOLOGICAL DOSE IN THE GOLDSIM ENVIRONMENT
SOFTWARE REQUIREMENTS DESCRIPTION AND SOFTWARE DEVELOPMENT PLAN FOR BIOSPHERE MODEL TO ESTIMATE RADIOLOGICAL DOSE IN THE GOLDSIM ENVIRONMENT Prepared for U.S. Nuclear Regulatory Commission Prepared by
More informationThe objective of this chapter is to provide criteria with which to assess the safety of
9 Radiological aspects The objective of this chapter is to provide criteria with which to assess the safety of drinking-water with respect to its radionuclide content. The Guidelines do not differentiate
More informationNational Policy Statement for Nuclear Power Generation (EN-6) Volume I of II
National Policy Statement for Nuclear Power Generation (EN-6) Volume I of II Planning for new energy infrastructure July 2011 Department of Energy and Climate Change National Policy Statement for Nuclear
More informationChatham Rock Phosphate Marine Consent Application. P Kennedy - Environmental Impact Assessment Evidence Summary
Chatham Rock Phosphate Marine Consent Application P Kennedy - Environmental Impact Assessment Evidence Summary My evidence and this summary cover the following matters: Seabed and sediment Discharge and
More informationQuestionnaire for NORM service providers
Questionnaire for NORM service providers This questionnaire is intended for institutes and companies providing services relevant for NORM industries in Belgium. Its objective is to give to Belgian NORM
More informationFukushima Accident: Radioactive Releases and Potential Dose Consequences
Fukushima Accident: Radioactive Releases and Potential Dose Consequences Peter F. Caracappa, Ph.D., CHP Rensselaer Polytechnic Institute ANS Annual Meeting Special Session: The Accident at Fukushima Daiichi
More informationTraining in Emergency Preparedness and Response
Working to Protect People, Society and the Environment Training in Emergency Preparedness and Response Nuclear Safety and Security Programme Nuclear Safety and Security Programme Training in Emergency
More informationEnvironmental aspects of water fluoridation
KEY POINTS Fluorides are very common in the environment. Reviews of the literature and environmental impact assessments have found no evidence of any adverse environmental effects resulting from water.
More informationStandardised Decommissioning Cost Estimating of WWER-440 Nuclear Power Plants (SCE)
COMMISSION OF THE EUROPEAN COMMUNITIES (5th Framework Programme) Standardised Decommissioning Cost Estimating of WWER-440 Nuclear Power Plants (SCE) Topical Information Meeting on Decommissioning of Nuclear
More informationCROM An Introduction. Juan Carlos Mora Radiation Protection for the Public and the Environment CIEMAT
CROM An Introduction Juan Carlos Mora Radiation Protection for the Public and the Environment CIEMAT Environmental impact assessment Release Transfer to plants and animals Concentration in foodstuffs MODEL(S)
More informationRadiological Protection Principles concerning the Natural Radioactivity of Building Materials
Radiological Protection Principles concerning the Natural Radioactivity of Building Materials European Commission Radiation protection 112 Radiological Protection Principles concerning the Natural Radioactivity
More informationExplanatory Memorandum to the Conservation of Habitats and Species (Amendment) Regulations 2012
Explanatory Memorandum to the Conservation of Habitats and Species (Amendment) Regulations 2012 This Explanatory Memorandum has been prepared by the Environment and Sustainable Development Department and
More informationExamination of National and International Impacts of Adoption of ICRP Recommendations
Examination of National and International Impacts of Adoption of ICRP Recommendations Introduction The U.S. Nuclear Regulatory Commission (NRC) staff has engaged in multiple domestic and international
More informationList of Contents Section 10, Nuclear Safety and Radiation Protection Legislation Page
List of Contents Section 10, Nuclear Safety and Radiation Protection Legislation Page Overview 1 The Radiation Protection (Medical Exposures) Directive 11 The Public Information (Radiological Emergency)
More informationSection 3: Trophic Structures
Marine Conservation Science and Policy Service learning Program Trophic Structure refers to the way in which organisms utilize food resources and hence where energy transfer occurs within an ecosystem.
More informationIntroduction to protection goals, ecosystem services and roles of risk management and risk assessment. Lorraine Maltby
Introduction to protection goals, ecosystem services and roles of risk management and risk assessment. Lorraine Maltby Problem formulation Risk assessment Risk management Robust and efficient environmental
More informationUSE OF IONIZING RADIATION IN THE TEACHING OF PHYSICS AND CHEMISTRY
GUIDE ST 5.3 / 4 MAY 2007 USE OF IONIZING RADIATION IN THE TEACHING OF PHYSICS AND CHEMISTRY 1 Ge n e r a l 3 2 Safety licences and exemption from licensing 3 3 Safety licence-exempt use of radiation 3
More informationRC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay
RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader
More informationIndicator 2.2 - Water Levels in Lake Okeechobee
Indicator. - Water Levels in Lake Okeechobee What is the desired restoration condition? The desired restoration condition for water levels in Lake Okeechobee is to eliminate harmful high and low water
More informationDifferent perspectives towards balancing the triple-bottom-line
Different perspectives towards balancing the triple-bottom-line Craig Ashton BSc (Hons) MSc CEnv MIEMA IEMA Annual Conference, 3rd June 2008 Objectives What is Sustainability Why do different views exist/why
More informationUK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry
UK Strategy for the Management of Solid Low Level Radioactive Waste from the Nuclear Industry August 2010 Executive Summary The UK strategy for the management of solid low level radioactive waste from
More informationLicence condition handbook
Licence condition handbook January 2016 Office for Nuclear Regulation page 1 of 24 The standard licence conditions attached to nuclear site licences Introduction This booklet has been produced as an aide-memoire
More informationDifferent Types of Marine Protected Area
A protected area is defined by the IUCN as a clearly defined geographical space, recognised, dedicated and managed, through legal or other effective means, to achieve the long-term conservation of nature
More informationExposures from the Events at the NPPs in Fukushima following the Great East Japan Earthquake and Tsunami
Exposures from the Events at the NPPs in Fukushima following the Great East Japan Earthquake and Tsunami Yoshiharu YONEKURA The 58th session of UNSCEAR, 23 rd May, 2011 1. Impact on Public & Environment
More informationIAEA Action Plan on Nuclear Safety 1
IAEA Action Plan on Nuclear Safety 1 In June 2011 a Ministerial Conference on Nuclear Safety was convened to direct, under the leading role of the IAEA, the process of learning and acting upon lessons
More informationEnvironmental Liability Directive: Meeting the threshold of water damage. Caroline Fielder Senior Legal Advisor 16 January 2013
Environmental Liability Directive: Meeting the threshold of water damage Caroline Fielder Senior Legal Advisor 16 January 2013 Overview Environment Agency s role Definition of water damage A case study:
More informationPUBLICATION OF RESEARCH: UNDERSTANDING THE IMPLICATIONS OF THE EUROPEAN REQUIREMENTS RELATING TO RADON IN DRINKING WATER
DRINKING WATER INSPECTORATE Area 7E, 9 Millbank c/o Nobel House 17 Smith Square London SW1P 3JR Enquiries: 030 0068 6400 E-mail: dwi.enquiries@defra.gsi.gov.uk DWI Website: http://www.dwi.gov.uk 12 October
More informationThe Follow-up IAEA International Mission on Remediation of Large Contaminated Areas Off-Site the Fukushima Daiichi Nuclear Power Plant
NE/NEFW/2013 ORIGINAL: English 23.01.2014 Final Report The Follow-up IAEA International Mission on Remediation of Large Contaminated Areas Off-Site the Fukushima Daiichi Nuclear Power Plant Tokyo and Fukushima
More informationSOURCES AND EFFECTS OF IONIZING RADIATION
SOURCES AND EFFECTS OF IONIZING RADIATION United Nations Scientific Committee on the Effects of Atomic Radiation UNSCEAR 2008 Report to the General Assembly with Scientific Annexes VOLUME II Scientific
More informationA Review of Emerging Gamma Detector Technologies for Airborne. Radiation Monitoring
A Review of Emerging Gamma Detector Technologies for Airborne Steven Bell ANSRI Dublin 2015 12-14 January Radiation Monitoring Airborne radiation Particulates: sub-μm to sub-mm contaminated with fission
More informationRole and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation. G.. d Amored
Sino-Italian Cooperation Project Role and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation G.. d Amored Environmental Protection Agency of Piedmont Region (ARPA
More informationSECURITY ARRANGEMENTS OF RADIATION SOURCES
SECURITY ARRANGEMENTS OF RADIATION SOURCES 1 General 3 2 The party running the radiation practice shall be responsible for security arrangements 3 3 Places of use and storages of radiation sources shall
More informationTHE PRINCIPLE OF JUSTIFICATION
THE PRINCIPLE OF JUSTIFICATION AND ITS RELATION WITH RADIOLOGICAL INFORMED CONSENT IN THE CONTEXT OF EU LAW Legal Adviser at the Instituto Superior Técnico / Campus Tecnológico e Nucler, Lisbon University
More informationwww.irishseedsavers.ie Natural surface water on earth includes lakes, ponds, streams, rivers, estuaries, seas and oceans.
www.irishseedsavers.ie POND LIFE FACT SHEET Natural surface water on earth includes lakes, ponds, streams, rivers, estuaries, seas and oceans. A pond is a small body of fresh water shallow enough for sunlight
More informationDraft IAEA Action Plan on Nuclear Safety
Atoms for Peace Board of Governors General Conference GOV/2011/59-GC(55)/14 Date: 5 September 2011 For official use only Item 3(b) of the Board's provisional agenda (GOV/2011/46) Item 14(b) of the Conference's
More informationThe Closure of the Asse Research Mine
The Closure of the Asse Research Mine Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Second Review Meeting May 17th 2006 Dr. Helmut Bossy Federal
More informationThe Crown Estate recognises that the good management of the marine environment is vital to coastal communities around the UK.
The Crown Estate recognises that the good management of the marine environment is vital to coastal communities around the UK. Much of the activity around the coast is driven locally and we play an important
More informationU.S. EPA s Models for Establishing Cleanup Levels in Soil, Water, Buildings and Streets at Superfund Sites
U.S. s Models for Establishing Cleanup Levels in Soil, Water, Buildings and Streets at Superfund Sites Stuart Walker U.S. Environmental Protection Agency Office of Superfund Remediation and Technology
More informationNational and Major Developments
National and Major Developments An Agency Joint Statement on Pre-application Engagement A Joint Statement by Architecture and Design Scotland, Forestry Commission Scotland, Historic Scotland, Scottish
More informationAppendix B: Cost Estimates
Appendix B: Estimates This appendix presents the estimated costs of the monitoring and supplemental research components presented in Section 3 of this document. A 20% quality assurance and quality control
More informationEnvironmental damage: extending the Environmental Liability Directive into marine waters
www.gov.uk/defra Environmental damage: extending the Environmental Liability Directive into marine waters Consultation on amending the Environmental Damage (Prevention and Remediation) Regulations 2009
More information2010 No. 490 WILDLIFE COUNTRYSIDE. The Conservation of Habitats and Species Regulations 2010
STATUTORY INSTRUMENTS 2010 No. 490 WILDLIFE COUNTRYSIDE The Conservation of Habitats and Species Regulations 2010 Made - - - - 1st March 2010 Laid before Parliament 8th March 2010 Laid before the National
More informationMarine Programme Evidence Plan
www.defra.gov.uk Marine Programme Evidence Plan Policy portfolio: Marine and Fisheries Policy area within portfolio: Marine environment, marine biodiversity, marine and freshwater fisheries Timeframe covered
More informationLegal and governance framework
Annex A Legal and governance framework This annex is a brief guide to the legal and governance framework relevant to research in the UK. It is not intended to be a comprehensive statement of the law or
More informationRadiation Protection from NORM and TENORM in the Oil and Gas Industry: Regulatory and Non-Regulatory Approaches
Radiation Protection from NORM and TENORM in the Oil and Gas Industry: Regulatory and Non-Regulatory Approaches Ruth E. McBurney, CHP Conference of Radiation Control Program Directors, Inc. Presented at
More informationAzeri, Chirag & Gunashli Full Field Development Phase 3 Environmental & Socio-economic Impact Assessment. A10.1 Introduction...
APPENDIX 10 Normally Occurring Radioactive Material (NORM) Contents A10.1 Introduction... A10/3 A10.2 Occurrence & Concentration of NORM in Oil and Gas Operations... A10/4 A10.2.1 Probability of NORM formation
More informationG U Y A N A ACT NO. 11 OF 1996 ENVIRONMENTAL PROTECTION ACT 1996 ARRANGEMENT OF SECTIONS PART I PRELIMINARY SECTION
G U Y A N A ACT NO. 11 OF 1996 ENVIRONMENTAL PROTECTION ACT 1996 ARRANGEMENT OF SECTIONS I assent. SAMUEL HINDS Prime Minister Performing the functions Of the President. PART I PRELIMINARY SECTION 5 th
More informationPolice use of Firearms
CODE OF PRACTICE ON Police use of Firearms and Less Lethal Weapons Contents 1. Introduction 1.1 Purpose of the code 1 1.2 Statutory basis of the code 1 1.3 Weapons covered by this code 2 1.4 Armed support
More informationEnvironmental Permitting Regulations (England and Wales) Environmental 2010 Permitting Regulations (England and Wales) 2007
Environmental Permitting Regulations (England and Wales) Environmental 2010 Permitting Regulations (England and Wales) 2007 Regulatory Guidance Series, No No EPR RSR 73 The regulation of radioactive substances
More informationPROPOSED TERMS OF REFERENCE
Annexure-IV PROPOSED TERMS OF REFERENCE 1.0 Proposed Scope of Work for EIA Study The components of the EIA study include: Detailed description of all elements of the project activities (existing and proposed
More informationQ1 2014. Environmental Emissions Data for Pickering Nuclear ONTARIO POWER GENERATION ONT
OVERVIEW This quarterly report summarizes s environmental emissions data for the year-to-date, including: Radioactive Effluents: Releases to air and water, including discharges to the municipal sewage
More informationWM2012 Conference, February 26-March 1, 2012, Phoenix, Arizona, USA
Radioactive Waste Characterization Strategies; Comparisons Between AK/PK, Dose to Curie Modeling, Gamma Spectroscopy, and Laboratory Analysis Methods- 12194 Steven J. Singledecker, Scotty W. Jones, Alison
More informationBonn Call-for-Action Joint Position Statement by the IAEA and WHO
Bonn Call-for-Action Joint Position Statement by the IAEA and WHO The International Atomic Energy Agency (IAEA) held the International Conference on Radiation Protection in Medicine: Setting the Scene
More informationNORM MANAGEMENT GUIDELINES & PRINCIPLES
Introducing NORM NORM MANAGEMENT Three is glad to present some basic hints about NORM that should be taken onto consideration whilst dealing with these matters The acronym NORMmeans all Naturally Occurring
More informationWater Extraction Permitting Policy
Water Extraction Policy 1 Water Extraction Permitting Policy Department of Environment, Labour & Justice January 2013 Water Extraction Policy 2 EXECUTIVE SUMMARY This document establishes a new policy
More informationHOW TO... Be Aware of Your Environmental Legal Responsibilities
HOW TO... Be Aware of Your Environmental Legal Responsibilities How to... Be Aware of Your Environmental Legal Responsibilities You have legal responsibilities for the impact your business has on the environment.
More informationPortuguese Health Physics Society: Calibrating Pen Dosimeters with and without a Phantom
Portuguese Health Physics Society: Calibrating Pen Dosimeters with and without a Phantom Fernanda B. C. Nonato, Claudinei T. Cescon and Linda V. E. Caldas, Instituto de Pesquisas Energéticas e Nucleares,
More informationInternational Action Plan On The Decommissioning of Nuclear Facilities
International Action Plan On The Decommissioning of Nuclear Facilities A. Introduction Decommissioning is defined by the International Atomic Energy Agency (the Agency) as the administrative and technical
More informationCONSERVATION AREAS ACT
CONSERVATION AREAS ACT CAP. 30.15 Conservation Areas Act CAP. 30.15 Arrangement of Sections CONSERVATION AREAS ACT Arrangement of Sections Section 1 Short title... 5 2 Interpretation... 5 3 Declaration
More informationBasic principles of radioactive waste management
Title of publication Basic principles of radioactive waste management An introduction to the management of higher activity radioactive waste on nuclear licensed sites Joint guidance from the Office of
More informationINFO-0545 RADIOISOTOPE SAFETY MONITORING FOR RADIOACTIVE CONTAMINATION
INFO-0545 RADIOISOTOPE SAFETY MONITORING FOR RADIOACTIVE CONTAMINATION 1. INTRODUCTION This document provides general guidance for monitoring and controlling radioactive contamination, and relating the
More informationINTERIM WASTE STORE CONSTRUCTION LICENCE EFFECTIVE CONTROL PLAN
Interim Waste Store Construction Licence Application Document IWS-C-LA-D1 INTERIM WASTE STORE CONSTRUCTION LICENCE EFFECTIVE CONTROL PLAN (rev 2) Prepared By Australian Nuclear Science and Technology Organisation
More informationThe implementation of the European Union Environmental Liability Directive
RSPB Briefing January 2006 The implementation of the European Union Environmental Liability Directive Briefing on the main issues arising in relation water I. Introduction The European Union s Environmental
More informationModule Three. Risk Assessment
Module Three Risk Assessment 136 Module Three Introduction to Risk Assessment Time Allotted: 90 Minutes Objectives: Upon completion of this module, the learner will be able to # Define and understand the
More informationSANITATION COUNTRY PROFILE NORWAY
SANITATION COUNTRY PROFILE NORWAY Decision-Making Programmes and Projects Status Capacity-Building, Education, Training and Awareness-Raising Information Research and Technologies Financing Cooperation
More informationSection A: Introduction, Definitions and Principles of Infrastructure Resilience
Section A: Introduction, Definitions and Principles of Infrastructure Resilience A1. This section introduces infrastructure resilience, sets out the background and provides definitions. Introduction Purpose
More informationInventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination
Inventory of Performance Monitoring Tools for Subsurface Monitoring of Radionuclide Contamination H. Keith Moo-Young, Professor, Villanova University Ronald Wilhelm, Senior Scientist, U.S. EPA, Office
More informationAdaptive Management Measures under the Canadian Environmental Assessment Act
Operational Policy Statement Adaptive Management Measures under the Canadian Environmental Assessment Act Purpose This operational policy statement (OPS) provides best practice guidance on the use of adaptive
More informationNuclear Safety Council Instruction number IS-19, of October 22 nd 2008, on the requirements of the nuclear facilities management system
Nuclear Safety Council Instruction number IS-19, of October 22 nd 2008, on the requirements of the nuclear facilities management system Published in the Official State Gazette (BOE) number 270 of November
More informationOUR CUSTOMERS. Exciting, beautifully designed, excellent quality clothing and homeware that reflects the aspirations and means of our customers
OUR CUSTOMERS Content Our Approach Our aim is to meet or exceed our customers expectations of Next as a company and the products we sell by providing: Exciting, beautifully designed, excellent quality
More informationLEGAL INDEMNITY POLICY OF TITLE INSURANCE FOR COMMERCIAL PROPERTY COVERAGE FOR KNOWN RISK
LEGAL INDEMNITY POLICY OF TITLE INSURANCE FOR COMMERCIAL PROPERTY COVERAGE FOR KNOWN RISK ENGLAND & WALES (FORM KR E&W 03/09) SCHEDULE Online File Number 20499062 Policy Number KR (E&W) - 15317800316 Policy
More informationFUNDAMENTALS OF A STATE S NUCLEAR SECURITY REGIME: OBJECTIVE AND ESSENTIAL ELEMENTS
IAEA NUCLEAR SECURITY SERIES NO. FUNDAMENTALS OF A STATE S NUCLEAR SECURITY REGIME: OBJECTIVE AND ESSENTIAL ELEMENTS Revision 17.04 Page 1 of 20 FOREWORD [TO BE PROVIDED BY THE SECRETARIAT AT A LATER TIME]
More informationBULLETIN. The Senior Statutory Auditor under the United Kingdom Companies Act 2006. April 2008 2008/6
April 2008 The Senior Statutory Auditor under the United Kingdom Companies Act 2006 2008/6 BULLETIN This Bulletin applies to financial years beginning on or after 6 April 2008. The Auditing Practices Board
More informationFreedom of Information Act 2000 (FOIA) Decision notice
Freedom of Information Act 2000 (FOIA) Decision notice Date: 21 January 2016 Public Authority: Address: Mill View Primary School Wealstone Lane Upton-by-Chester Chester CH2 1HB Decision (including any
More informationPRESENTATION 2 MAJOR ENVIRONMENTAL PROBLEMS
UNEP GLOBAL JUDGES PROGRAMME APPLICATION OF ENVIRONMENTAL LAW BY NATIONAL COURTS AND TRIBUNALS PRESENTATION 2 MAJOR ENVIRONMENTAL PROBLEMS OUTLINE OF PRESENTATION A) Major environmental issues B) Responses
More informationCAPITAL WORKS GUIDANCE DOCUMENT
COMMUNITY BUILDINGS TRANSFER PROGRAMME CAPITAL WORKS GUIDANCE DOCUMENT This document has been prepared to assist and advise management groups of community buildings who are involved in Durham County Council
More informationAn Irish Strategy for River Restoration: How it works on the ground. Karen Delanty
An Irish Strategy for River Restoration: How it works on the ground Karen Delanty River Restoration and EU Directives River Restoration in Ireland to-date; TAM (Tourism Angling Measure) Local small scale
More informationEnvironmental Radiation Monitoring in Taiwan
Environmental Radiation Monitoring in Taiwan Introduction: Ching-Chung Huang Radiation Monitoring Center, Atomic Energy Council 823, Cherng-Ching Road, Kaohsiung, Taiwan cchuang @ trmc.aec.gov.tw Chemical,
More informationChemistry 1000 Lecture 2: Nuclear reactions and radiation. Marc R. Roussel
Chemistry 1000 Lecture 2: Nuclear reactions and radiation Marc R. Roussel Nuclear reactions Ordinary chemical reactions do not involve the nuclei, so we can balance these reactions by making sure that
More informationPanel on Economic Development Radiation monitoring after the Japanese Fukushima nuclear power plant incident
CB(1)1882/10-11(01) Information Note Introduction Panel on Economic Development Radiation monitoring after the Japanese Fukushima nuclear power plant incident The Hong Kong Observatory (HKO) started monitoring
More informationIMPLEMENTING THE REGULATORY AUTHORITY INFORMATION SYSTEM (RAIS)
IRPA 12 IMPLEMENTING THE REGULATORY AUTHORITY INFORMATION SYSTEM (RAIS) Buenos Aires, Argentina, 19-24 October, 2008 K. Mrabit Head, Safety and Security Coordination Section Department of Nuclear Safety
More information