BEST PRACTICE FOR THE DESIGN AND OPERATION OF HIGH HAZARD SITES

Size: px
Start display at page:

Download "BEST PRACTICE FOR THE DESIGN AND OPERATION OF HIGH HAZARD SITES"

Transcription

1 BEST PRACTICE FOR THE DESIGN AND OPERATION OF HIGH HAZARD SITES Lyn Fernie and Jo Fearnley AK EHS & Risk, Aker Kvaerner Engineering Services Ltd, Ashmore House, Stockton on Tees, TS18 3RE. The idea of best practice or good practice for high hazard sites is often discussed, but what does it mean in practice? When designing a new manufacturing site, relevant good practice can be adopted at relatively low cost. However when dealing with older assets, the costs associated with demonstrating that the site was designed, built and operated in accordance with relevant good practice can be significant, especially where a review indicates that equipment upgrades are required. The speaker will discuss the issues associated with the adoption of relevant good practice for high hazard sites. In particular a case study will be utilised to outline the difficulty with defining relevant good practice and the potential costs that can be associated with a good practice improvement program. Keywords: Good Practice; Best Practice; High Hazard; Retrofit; Cost Benefit Analysis; CBA WHAT IS GOOD PRACTICE OR BEST PRACTICE? The concept of good practice is fundamental to the approach to the regulation of health and safety within the Health and Safety Executive (HSE) in the UK, and yet an industry study, (HSE, 2002), showed there is significant inconsistency in the understanding of the phrase across industry groups. Further, the differences between the meanings of good practice and best practice are not consistently understood, and people frequently use the two terms interchangeably, whereas, in relation to high hazard sites in the UK, there are specific definitions used by the HSE for both of these terms. The HSE definitions can be found in an internal HSE document, Assessing compliance with the law in individual cases and the use of good practice (HSE, 2003a). In this paper, good practice is defined as the generic term for those standards for controlling risk which have been judged and recognised by HSE as satisfying the law when applied to a particular relevant case in an appropriate manner. The term best practice is distinguished as being a standard of risk control above the legal minimum.

2 The HSE industry study (2002) also concluded that many industry respondents did not know where to find relevant good practice, and that only a minority of companies make use of cost benefit analysis when determining good practice. REGULATORY FRAMEWORK The HSE expects relevant application of good practice in order for a company to demonstrate that they have reduced risk so far as is reasonably practicable (SFAIRP). There is an hierarchy of health and safety law and this reflects the sources of data (HSE, 2003a). The duty of care requirements are detailed in the Health and Safety at Work Act (HSW Act) 1974, and this is only limited by the SFAIRP principle. This is supported by other legislation such as the Management of Health and Safety at Work Regulations Beneath this are a series of mandatory regulations, which fall into the categories of process, goal-setting and standard-setting, and then there are approved codes of practice (ACoPs), and guidance literature, including Health and Safety guidance (HS(G)). The use of European standards supports the trend towards goal-setting rather than prescriptive regulation. European directives establish broad requirements and identify appropriate standards to achieve their aims. UK national regulations typically adopt these broad requirements within the existing legislative framework but also permit organisations to meet the aims in their own way. However, organisations will need to demonstrate that their methods are as effective as those given in the guidance or ACoP, which can be considered as a best practice document. For high hazard sites, in particular those subject to the Seveso II Directive (EC, 1996), implemented in the UK as the Control of Major Accident Hazards (COMAH) Regulations 1999 (SI, 1999), it is expected that the operator has a complete understanding of all the relevant good practice (RGP) related to the site, activities and chemicals concerned. To help this process the Safety Report Assessment Guides, including the Technical Aspects - Level 3 Guidance (HSE, 2004a) have a cross reference listing of documentation, including ACoPs, HS(G)s and European and British standards. Regulation 4 of the COMAH Regulations requires operators to take all measures necessary (AMN) to prevent major accidents. This is interpreted as the equivalent of reducing risks as low as reasonably practicable (ALARP). Reasonably practicable means that everything must be done to reduce a risk to its lowest possible level, except where the cost of the risk reduction is excessive compared to the size of the risk reduction (HSE, 2004b). The term excessive is usually refered to as grossly disproportionate. TOLERABILITY OF RISK Three regions of risk are defined, delineated by an unacceptable region and a broadly acceptable region; the region in between defining a region of tolerable risk, but only when those risks are ALARP.

3 The HSE s decision making process Reducing Risks, Protecting People (HSE, 2001a) makes some important statements of principle: Principle 1 HSE starts with the expectation that suitable controls must be in place to address all significant hazards and that those controls, as a minimum, must implement authoritative good practice irrespective of situation based risk estimates. Principle 2 The zone between the unacceptable and broadly acceptable regions is the tolerable region. Risks in that region are typical of the risks from activities that people are prepared to tolerate in order to secure benefits in the expectation that: The nature and levels of the risks are properly assessed and the results used properly to determine control measures; The residual risks are not unduly high and kept as low as reasonably practicable (the ALARP principle); and The risks are periodically examined to ensure that they still meet the ALARP criteria, for example, by ascertaining whether further or new controls need to be introduced to take into account changes over time, such as new knowledge about the risk or the availability of new techniques for reducing or eliminating risks. Any risk assessed as unacceptable must be reduced, and cost considerations are not relevant. If the risk has been shown to be in the broadly acceptable region, then the ALARP demonstration may be based on the adherence to codes, standards and established good practice. However these must be shown to be up-to-date and relevant to the operations in question. If the risk has been shown to be in the tolerable region, then the ALARP demonstration needs to be based on the adherence to codes, standards and established good practice, but also on the concept that more can be done to reduce risk. Where further measures can be identified that may reduce the risk, and if the measure is determined to be prima facie reasonable based on engineering considerations, and it cannot be shown that the cost of the measure is grossly disproportionate to the benefit gained, then the operator is duty bound to implement that measure. RELEVANT GOOD PRACTICE When identifying relevant good practice (RGP) for a site it is necessary to establish how the legislation and regulations relate to the site. Further, all relevant ACoPs and HS(G)s need to be identified, and then all other documentation such as European, government, industry, trade and engineering standards. The level of written detail on

4 good practice available reflects the nature of the hazards and risks concerned and the complexity of the process or activity. Some good practice may be unwritten, such as well established standard practices adopted in an industry sector, although common custom and practice should not be assumed to be good practice. Good practice is expected to maximise the use of inherent safety, to eliminate or avoid risks where possible, and to control the risk at source physically if possible. It should also minimise the need for procedural controls and personal protective equipment. Good practice may change over time as a result of experience, changes in management practices, cost base improvements, or technological advances, which could all change the expectation of what is established good practice (HSE, 2003a). Therefore it should not be assumed that what was once good practice remains so indefinitely. If an operator wishes to use a different approach to controlling the risk to that in the relevant good practice then they must demonstrate that the residual risk is no greater than that if the good practice had been implemented. Good practice is relevant to risks across the entire site, and each plant section is typically assessed separately, and then a composite view of the site risks compiled, which includes general site risks. As a result there may be a wide variety of good practice that needs to be considered. EXPECTATIONS FOR HIGH HAZARD SITES For a high hazard situation, for example where there is a potential for a large number of people to be harmed in a single event, then meeting good practice alone may be insufficient and additional risk reduction measures may be necessary to reduce the risks ALARP (HSE, 2003a). These should be assessed using cost benefit analysis to identify those which are proportionate, and those which are grossly disproportionate. Where there is a requirement for environmental protection this may constrain the options available for controlling the health and safety risks, and drive the selection of relevant good practice. Where risks arise from uncontrollable external events, such as natural phenomena, then it is the mitigation of the consequences arising that needs to be considered. The process for determining reasonably practicable is: Identify accident scenarios and the relevant measures to prevent, control and mitigate the risks arising for the site. It is not expected that all minor scenarios are considered individually in detail, but only those that have a reasonably foreseeable cause of harm. Those with both on- and off-site consequences need to be identified. When considering societal and individual risks for a site, all

5 contributing plant areas need to be considered together, rather than considering individual hazards. Identify relevant good practice for the whole site, for example relating to the chemicals, the processes and the activities. Implement good practice, unless another equally effective means of risk reduction can be identified. Determine if there are any additional risk reduction measures for the risks identified. Determine whether these additional risk reduction measures are reasonably practicable, i.e. that the associated costs are not grossly disproportionate. Implement those which are reasonably practicable 1. INCORPORATING GOOD PRACTICE INTO NEW PLANT DESIGN When assessing compliance, the HSE expects operators to apply relevant good practice as a minimum for new plant / installations or modification to existing sites (HSE, 2003a). In addition, other potential options for further risk reduction should be considered if they are reasonably practicable, i.e. not grossly disproportionate. Further, it is expected that the design should consider any higher standards that are already being achieved in a similar field elsewhere, which is the current best practice. This reflects the expectation for improvement in standards over time (HSE, 2003b). The consideration of best practice, rather than good practice, is therefore the requirement during the design phase. The design stage of a process is expected to consider inherent safety, such as elimination, reduction and prevention of hazards and risk scenarios, in preference to the need to control and mitigate the consequences. Design encompasses various aspects, from concept selection through to detailed specification, and best practice is expected to consider not just the items of plant equipment, but also all buildings and facilities, the process route selected, the safe limits of operation, man-machine interfaces and other human factor aspects. Consideration of best practice at design stage is also expected for the management system, including roles and responsibilites, procedures for operation and maintainence, training, record keeping, quality assurance and quality control. It is necessary to consider the whole life-cycle for the proposed installation including construction, commissioning, operation, maintenance and decommissioning (HSE, 2003b). There is also the requirement for risk assessment for a high hazard plant. Where a variety of options or techniques exist for assessing risk, then a range of techniques should be used to test the sensitivity of the results. For a new plant it is often not easy to differentiate the costs of good and best practice. Where it is necessary to justify an additional risk reduction measure by a cost benefit analysis then each option should be 1 Note that some risk reduction may be reasonably practicable when applied to specific plant areas rather than across whole the site.

6 assessed by difference compared to the initial cost basis, to determine if any are reasonably practicable to achieve. It is important that the overall risk from the whole site is considered, especially for a high hazard complex, rather than each area being assessed independently (HSE, 2001b). One reason for this is that there is a potential that a risk reduction measure implemented to address one hazard could affect a different hazard elsewhere or an associated risk control measure. Another reason is that risks could be increased by escalation on-site or domino effects off-site. Opportunities for integrated risk reduction measures therefore need to be considered. ASSESSING EXISTING PLANT AGAINST GOOD PRACTICE For an existing plant or installation the HSE maintain the same base standard as for new plant, i.e. that the relevant good practice should be applied. This applies also to retrofits, modifications, upgrades, when completing safety reviews, and when a code or standard is upgraded to a higher level of safety. In judging compliance for existing plant the HSE will be looking for the application of current good practice to the extent necessary to satisfy the relevant legislation and regulations. It is accepted that it might not be reasonably practicable for all good practices or upgrades to good practices to be applied retrospectively to existing plant, however each should be considered, either in full, or as a partial solution, or by considering an alternative risk reduction measure. For an existing facility the existing measures should be compared to the relevant good practice, and any deficiencies identified. To enable a decision as to whether a retrofit is reasonably practicable in order to meet the good practice, it is necessary to complete the accident scenario risk assessment and assess the reduction in risk from the retrofit of the identified good practice measure. The decision is based on a comparison with the current situation, and various options are compared to the same base case. When considering whether a plant meets the ALARP criteria the HSE will prioritise the compliance with good practice by how tolerable the current situation is. Hence any risk assessed as unacceptable must be reduced, and cost considerations are not relevant. Risks in the tolerable region are acceptable if they can be proved to be ALARP, i.e. the cost of implementation of additional risk reduction measures is grossly disproportionate to the reduction in risk achieved. Where a risk is assessed as broadly acceptable there is less driving force to implement further risk reduction measures, if the likelihood of reducing the risk further is small. The cost benefit analysis for determining whether an improvement is reasonably practicable is a comparison between the reduction in risk achieved and the cost involved (in money, time and effort) (HSE, 2001b). The value above which the cost becomes grossly disproportionate will differ for each site, dependant on the level of total risk

7 from the site. The higher the risk from the site, in particular, in terms of the maximum number of potential fatalities from an accident scenario, the higher this value will be. CASE STUDY FOR AN EXISTING INSTALLATION In order to complete the COMAH Safety Report for an existing site, information was required to enable an assessment of the compliance with the current relevant good practice to be carried out. As detailed information was sparse for the ageing and neglected assets, it was necessary to start with some fundamental reviews. There were no recent records of hazard and operability studies, therefore for each asset on the site a process hazard identification and review (PHIR ) was carried out. This enabled a fundamental assessment to be made of the potential accident scenarios associated with the chemicals handled, the process used and the equipment employed in the process. The site handles a variety of chemicals with several processing routes, so when the PHIR documentation was compiled there was a very diverse range of potential scenarios. Of these, one material was identified as giving rise to the most severe consequences due to the hazardous nature of the material and the processing conditions. As a result this plant area was risk assessed as a priority as it would give the worst case accident scenario. This is turn would provide the data to enable the societal risk for the site to be assessed, and hence the benchmark could be set for the proportionality of the site and the level of gross disproportionation used in the cost benefit analysis established. For each plant area, the PHIR enabled the identification of the accident scenarios for that plant. A representative set of accident scenarios was selected, and a full risk assessment carried out, including consequence modelling for fire, explosion and toxic hazards, severity assessment (number of fatalities), frequency assessment and risk summation to asses the individual and societal risks. Once the level of risk and therefore the proportionality for the site had been determined, the representative set of accident scenarios could be further assessed considering ALARP principles. After all processes and activities were fully understood it was possible to review whether all the RGP for the site had been identified. This required that all plant areas, all chemicals handled and all the activities carried out on the site were considered. The sources of RGP consulted included ACoPs, HS(G)s, and Chemical Industry Association (CIA) and American Petroleum Institute (API) guidance. In addition a variety of standards were consulted, such as British (BS), International Standards Organisation (ISO), European Norm (EN) standards. Additional information was sourced from trade and industry bodies, HSE guidance, manufacturer guidelines, and other operators established practice. The next step was to identify the shortfalls against relevant good practice through the use of a series of technical audits leading to production of a gap analysis against the identified RGP benchmarks. It was then necessary to consider how the implementation

8 of improvement measures to address each of the identified gaps versus good practice would reduce risk for one or more of the representative set of accident scenarios. Once all the potential risk reduction elements of good practice that had been identified had been assessed, the residual risk levels were noted. In order to justify whether these risks were ALARP they needed to be reviewed in the light of the residual level of tolerability and any other potential risk reduction measures, such that AMN had been considered. To do this a site meeting with a multidisciplinary team of key personnel used a systematic methodology to determine any other potential risk reduction measures for each of the representative accident scenarios. Risks remaining in the unacceptable region were assessed specifically as a reduction in risk was required regardless of cost. For the other scenarios the achievable risk reduction was compared to the cost of implementation to determine if the measure was proportionate or grossly disproportionate. The outcome of these assessments was a list of recommendations and improvement actions for the site to implement good practice, or implement other risk reduction measures, and so achieve a site where the risks are ALARP. The costs of implementation were based on +/- 50% cost estimates. As each project was progressed through design, the final costs were clarified, and where these were significantly higher than the value used in the process, the assessment was repeated to validate the viability of progressing at an increased cost. For one area of the site, the level of unacceptability of risk from the current operating process was such that it was viable to completely review the process route being used, in the light of current best practice as opposed to good practice. Comparative solutions were identified based on upgrading the existing process route to good practice and retrofitting a completely different process route that was considered best practice. This fundamental process route review outcome is very unusual, but it does indicate how the complications of retrofitting good practice to an existing plant can be so expensive that radical options are worth considering.

9 CONCLUSIONS The concept of good practice is fundamental to the approach to the regulation of health and safety management yet there is significant inconsistency in the understanding of the phrase across industry groups. Further, the differences between the meanings of good practice and best practice are not consistently understood, and people frequently use the two terms interchangeably. The HSE defines good practice as the generic term for those standards for controlling risk which have been judged and recognised by HSE as satisfying the law when applied to a particular relevant case in an appropriate manner, and best practice is distinguished as being a standard of risk control above the legal minimum. The relevant application of good practice is expected by the HSE for a company to demonstrate that they have reduced risk so far as is reasonably practicable (SFAIRP). The HSE starts with the expectation that suitable controls must be in place to address all significant hazards and that those controls, as a minimum, must implement authoritative good practice irrespective of situation based risk estimates. Any risk assessed as unacceptable must be reduced, and cost considerations are not relevant. If the risk has been shown to be in the broadly acceptable region, then the ALARP demonstration may be based on the adherence to codes, standards and established good practice. However these must be shown to be up-to-date and relevant to the operations in question. If the risk has been shown to be in the tolerable region, then the ALARP demonstration needs to be based on the adherence to codes, standards and established good practice, but also what more can be done to reduce risk. The level of written detail on good practice available reflects the nature of the hazards and risks concerned and the complexity of the process or activity. Some good practice may be unwritten, such as well established standard practices adopted in an industry sector, although custom and practice should not be assumed to be good practice. Good practice may change over time therefore it should not be assumed that what was once good practice remains so indefinitely. There may be a wide variety of good practice that needs to be considered. For a high hazard situation meeting good practice alone may be insufficient and additional risk reduction measures may be necessary to reduce the risks ALARP. These should be assessed using cost benefit analysis to identify those which are proportionate, and those which are grossly disproportionate. It is expected that new designs should consider any standards beyond good practice that are already being achieved elsewhere, which is the current best practice in a similar field. The consideration of best practice, rather than good practice, is therefore the requirement during the design phase. In judging compliance for existing plant, the HSE will be looking for the application of current good practice to the extent necessary to satisfy the relevant law. It is accepted that it might not be reasonably practicable for all good practices or upgrades to good

10 practices to be applied retrospectively to existing plant, however each should be considered, and justification is required for not implementing a measure. For each site, dependant on the level of total risk from the site, the value above which the cost becomes grossly disproportionate will change. The higher the risk from the site, in particular, in terms of the maximum number of potential fatalities from an accident scenario, the higher this value will be. If the current operating process has unacceptable residual risk level then it may be viable to completely review the process route being used in the light of current best practice, as opposed to good practice. The complications of retrofitting good practice to an existing plant can be so expensive that radical options are worth considering. REFERENCES EC, Council Directive on the control of major-accident hazards (OJ No L 10 of 14 January 1997( Seveso II Directive) 96/82/EC. SI, The Control of Major Accident Hazards Regulations 1999 Statutory Instrument 1999 No Norwich: HMSO HSE, 2001a. Reducing risks, protecting people HSE s decision making process. Norwich: HMSO HSE, 2001b. Principles and guidelines to assist HSE in its judgements that duty-holders have reduced risk as low as reasonably practicable [online]. Available from: [Accessed 24 November 2004]. HSE, A survey of UK approaches to sharing good practice in health and safety management CRR412. Norwich: HMSO HSE, 2003a. Assessing compliance with the law in individual cases and the use of good practice [online]. Available from: [Accessed 24 November 2004]. HSE, 2003b. Policy and guidance on reducing risks as low as reasonably practicable in Design [online]. Available from: [Accessed 24 November 2004]. HSE, 2004a. Safety report assessment guidance (Technical Guidance) [online]. Available from: [Accessed 24 November 2004]. HSE, 2004b. Frequently asked questions [online]. Available from: [Accessed 24 November 2004].

SAFETY REPORTS SAFETY REPORTS. Schedule 4-Purpose and Contents of Safety Report

SAFETY REPORTS SAFETY REPORTS. Schedule 4-Purpose and Contents of Safety Report SAFETY REPORTS Reg 4 Every operator shall take all measures necessary to prevent major accidents and limit their consequences to persons and the environment Schedule 4-Purpose and Contents of Safety Report

More information

HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT STANDARDS. OCTOBER 2011- ISSUE No 01. Doc No: HSEC MS 001

HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT STANDARDS. OCTOBER 2011- ISSUE No 01. Doc No: HSEC MS 001 HEALTH, SAFETY, ENVIRONMENT AND COMMUNITY MANAGEMENT S OCTOBER 2011- ISSUE No 01 Doc No: MS 001 Introduction Celtique Energie is in the business of exploring for oil and gas in proven basins in Europe.

More information

LAC 67-2 rev3 - Annex B

LAC 67-2 rev3 - Annex B LAC 67-2 rev3 - Annex B Risk Rating System 1. This guidance provides a simple four Category (A high risk; B1 and B2 - medium risk and C low risk) premises risk rating system based on a business s health

More information

COMAH Competent Authority

COMAH Competent Authority OMH ompetent uthority Inspection of Electrical, ontrol and Instrumentation Systems at OMH Establishments (Operational elivery Guide) Page 1 of 23 Introduction 1 This elivery Guide (G) describes how the

More information

Brochure. Hazard identification and risk assessment For the hazardous process industries

Brochure. Hazard identification and risk assessment For the hazardous process industries Brochure Hazard identification and risk assessment For the hazardous process industries Overview Delivering excellent process safety performance is a given for any operating company in the hazardous process

More information

COMAH Competent Authority Workstream 6

COMAH Competent Authority Workstream 6 COMAH Competent Authority Workstream 6 COMAH On-site Emergency Planning and Mitigation (Operational Delivery Guide) the Competent Authority 1. Purpose 1.1. To ensure: The consequences of a major accident

More information

RISK ASSESSMENT AND USE OF RISK ACCEPTANCE CRITERIA FOR THE REGULATION OF DANGEROUS SUBSTANCES

RISK ASSESSMENT AND USE OF RISK ACCEPTANCE CRITERIA FOR THE REGULATION OF DANGEROUS SUBSTANCES RISK ASSESSMENT AND USE OF RISK ACCEPTANCE CRITERIA FOR THE REGULATION OF DANGEROUS SUBSTANCES Eivind Okstad and Per Hokstad SINTEF Industrial Management, Dept. of Safety and Reliability, N-7465 Trondheim,

More information

How To Monitor Safety Management System Performance

How To Monitor Safety Management System Performance Guidance Note Performance standards and indicators Advice for operators of major hazard facilities on developing meaningful and useful performance standards and indicators for the Safety Management System

More information

Ref: ED Responding to Non-Compliance or Suspected Non-Compliance with Laws and Regulations

Ref: ED Responding to Non-Compliance or Suspected Non-Compliance with Laws and Regulations October 15. 2015 IAASB Ref: ED Responding to Non-Compliance or Suspected Non-Compliance with Laws and Regulations FSR - danske revisorer welcomes this project to ensure consistency between ISAs and the

More information

Health and Safety Executive Safety and environmental standards for fuel storage sites

Health and Safety Executive Safety and environmental standards for fuel storage sites Health and Safety Executive Safety and environmental standards for fuel storage sites Process Safety Leadership Group Health and Safety Executive Safety and environmental standards for fuel storage sites

More information

HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM

HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM HEALTH SAFETY & ENVIRONMENT MANAGEMENT SYSTEM September 2011 OUR HEALTH, SAFETY AND ENVIRONMENT POLICY OUR PRINCIPLE OF DUE CARE We care about the wellbeing of our people and our impact on the environment.

More information

COMAH Competent Authority Inspection of Competence Management Systems at COMAH Establishments

COMAH Competent Authority Inspection of Competence Management Systems at COMAH Establishments COMAH Competent Authority (Operational Delivery Guide) the Competent Authority CONTENTS 1 Introduction... 3 2 Justification... 3 3 Background... 4 4 Purpose of the Programme... 4 5 Scope... 5 6 Targeting

More information

Guidance on Risk Assessment and Control

Guidance on Risk Assessment and Control Guidance on Risk Assessment and Control Page 1 of 18 CONTENTS Section Page Executive Summary 2. FLOWCHART 4. 1. Introduction and Scope 5. Hierarchy of risk control 5. Definitions 5. 2. Related Documents

More information

Controlling fire and explosion risks in the workplace

Controlling fire and explosion risks in the workplace Controlling fire and explosion risks in the workplace A brief guide to the Dangerous Substances and Explosive Atmospheres Regulations Introduction to DSEAR This leaflet provides a brief introduction to

More information

MANAGING THE RISKS OF CHANGE

MANAGING THE RISKS OF CHANGE MANAGING THE RISKS OF CHANGE Dr Andrew Brazier, Consultant www.andybrazier.co.uk [email protected] þ 44 7984 284642 The process industry has always had to deal with changes to plant and equipment,

More information

QUANTITATIVE RISK ASSESSMENT FOR ACCIDENTS AT WORK IN THE CHEMICAL INDUSTRY AND THE SEVESO II DIRECTIVE

QUANTITATIVE RISK ASSESSMENT FOR ACCIDENTS AT WORK IN THE CHEMICAL INDUSTRY AND THE SEVESO II DIRECTIVE QUANTITATIVE RISK ASSESSMENT FOR ACCIDENTS AT WORK IN THE CHEMICAL INDUSTRY AND THE SEVESO II DIRECTIVE I. A. PAPAZOGLOU System Reliability and Industrial Safety Laboratory National Center for Scientific

More information

4. Critical success factors/objectives of the activity/proposal/project being risk assessed

4. Critical success factors/objectives of the activity/proposal/project being risk assessed ARTC Risk Management Work Instruction 2: 1. Conduct Risk Assessment Workshop This Work Instruction provides general guidelines for conducting a generic Risk Assessment workshop. The instructions supplement

More information

UNIT D: REVIEW HEALTH AND SAFETY PROCEDURES IN WORKPLACES

UNIT D: REVIEW HEALTH AND SAFETY PROCEDURES IN WORKPLACES Elements in this unit are: UNIT D: REVIEW HEALTH AND SAFETY D.1 Prepare to undertake a review of health and safety in a workplace D.2 Carry out a review of workplace health and safety implementation Unit

More information

Guidance on the preparation and use of company risk assessment profiles for transport operators

Guidance on the preparation and use of company risk assessment profiles for transport operators Guidance on the preparation and use of company risk assessment profiles for transport operators As required by The Railways and Other Guided Transport Systems (Safety) Regulations 2006 (ROGS) This guidance

More information

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy Not Protectively Marked Item 6 Appendix B DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Management Policy The Dorset & Wiltshire Fire and Rescue Authority () is the combined fire and rescue authority for

More information

RESEARCH REPORT 151. Good practice and pitfalls in risk assessment HSE

RESEARCH REPORT 151. Good practice and pitfalls in risk assessment HSE HSE Health & Safety Executive Good practice and pitfalls in risk assessment Prepared by the Health & Safety Laboratory for the Health and Safety Executive 2003 RESEARCH REPORT 151 HSE Health & Safety Executive

More information

Total Loss Prevention Developing Identification and Assessment Methods for Business Risks

Total Loss Prevention Developing Identification and Assessment Methods for Business Risks Total Loss Prevention Developing Identification and Assessment Methods for Business Risks Authors: John Evans, Senior Consultant, and Geeta Thakorlal, FIChemE Head Consultant, Granherne Ltd, Leatherhead,

More information

V1.0 - Eurojuris ISO 9001:2008 Certified

V1.0 - Eurojuris ISO 9001:2008 Certified Risk Management Manual V1.0 - Eurojuris ISO 9001:2008 Certified Section Page No 1 An Introduction to Risk Management 1-2 2 The Framework of Risk Management 3-6 3 Identification of Risks 7-8 4 Evaluation

More information

Health, Security, Safety and Environment (HSE)

Health, Security, Safety and Environment (HSE) Health, Security, Safety and Environment (HSE) Content: 1 Objective 2 Application and Scope 21 Application of HSE Directive with underlying documents 22 Scope of HSE Management system 3 Framework for our

More information

Safety Management Systems (SMS) guidance for organisations

Safety Management Systems (SMS) guidance for organisations Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,

More information

OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable)

OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable) OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable) 4.1 General Requirements 4.2 OHS policy Has the organisation an established and maintained

More information

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy

DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy Part Two Part One Not Protectively Marked DORSET & WILTSHIRE FIRE AND RESCUE AUTHORITY Performance, Risk and Business Continuity Management Policy. The Dorset & Wiltshire Fire and Rescue Authority (DWFRA)

More information

CONTRACT RESEARCH REPORT. Best practice for risk based inspection as a part of plant integrity management HSE

CONTRACT RESEARCH REPORT. Best practice for risk based inspection as a part of plant integrity management HSE HSE Health & Safety Executive Best practice for risk based inspection as a part of plant integrity management Prepared by TWI and Royal & SunAlliance Engineering for the Health and Safety Executive CONTRACT

More information

Jonathan Wilson. Sector Manager (Health & Safety)

Jonathan Wilson. Sector Manager (Health & Safety) Jonathan Wilson Sector Manager (Health & Safety) OHSAS 18001:2007 Making Life Easier For Health & Safety Managers Workshop Agenda 1. Introduction 2. Why Manage Health & Safety 3. OHSAS 18001 and OHSMS

More information

Additional Guidance. for application to. HM Government Guide to Fire Safety Risk Assessment Residential Care Premises

Additional Guidance. for application to. HM Government Guide to Fire Safety Risk Assessment Residential Care Premises Additional Guidance for application to HM Government Guide to Fire Safety Risk Assessment Residential Care Premises Good Practice Guidance 2016 Additional Guidance agreed between the National Association

More information

The Control of Major Accident Hazards Regulations (Northern Ireland) 2015

The Control of Major Accident Hazards Regulations (Northern Ireland) 2015 STATUTORY RULES OF NORTHERN IRELAND 2015 No. 325 HEALTH AND SAFETY The Control of Major Accident Hazards Regulations (Northern Ireland) 2015 Made - - - - 26th August 2015 Coming into operation - 28th September

More information

Solihull Clinical Commissioning Group

Solihull Clinical Commissioning Group Solihull Clinical Commissioning Group Business Continuity Policy Version v1 Ratified by SMT Date ratified 24 February 2014 Name of originator / author CSU Corporate Services Review date Annual Target audience

More information

ENTERPRISE RISK MANAGEMENT POLICY

ENTERPRISE RISK MANAGEMENT POLICY ENTERPRISE RISK MANAGEMENT POLICY TABLE OF CONTENTS 1. Purpose... 33 2. Scope... 33 3. Policy... 33 4. Procedure... 33 5. Responsibility and Authority... 44 6. Review of Policy... 55 7. Availability of

More information

Guidance note. Risk Assessment. Core concepts. N-04300-GN0165 Revision 4 December 2012

Guidance note. Risk Assessment. Core concepts. N-04300-GN0165 Revision 4 December 2012 Guidance note N-04300-GN0165 Revision 4 December 2012 Risk Assessment Core concepts The operator of an offshore facility must conduct a detailed and systematic formal safety assessment, which includes

More information

Young people and work experience A brief guide to health and safety for employers

Young people and work experience A brief guide to health and safety for employers Young people and work experience A brief guide to health and safety for employers Introducing young people to the world of work can help them understand the work environment, choose future careers or prepare

More information

Article by Martin Kelly, BSc (Econ) Hons, DIP. Acc, FCA, MBA, MCMI. Examiner in Professional 2 Advanced Corporate Reporting

Article by Martin Kelly, BSc (Econ) Hons, DIP. Acc, FCA, MBA, MCMI. Examiner in Professional 2 Advanced Corporate Reporting IMPAIRMENT - IAS 36 Article by Martin Kelly, BSc (Econ) Hons, DIP. Acc, FCA, MBA, MCMI. Examiner in Professional 2 Advanced Corporate Reporting Introduction Intangible assets, particularly goodwill, have

More information

Policy. VBA Enterprise Risk Management. Governance Unit

Policy. VBA Enterprise Risk Management. Governance Unit Policy VBA Enterprise Risk Management Governance Unit Keywords: Policy; risk; governance. ID: Version no: Status: VBAPOL-0074 2.0 Final Issue date: Date of effect: Next review date: 14/07/2015 14/07/2015

More information

NORSOK STANDARD S-006 Rev 2, December 2003

NORSOK STANDARD S-006 Rev 2, December 2003 NORSOK STANDARD S-006 Rev 2, December 2003 HSE evaluation of contractors This NORSOK standard is developed with broad petroleum industry participation by interested parties in the Norwegian petroleum industry

More information

What is Social Return on Investment (SROI)?

What is Social Return on Investment (SROI)? What is Social Return on Investment (SROI)? Social Return on Investment (SROI) is a process of understanding, measuring and reporting on the social, environmental and economic value created by an organisation.

More information

Fire, Explosion and Risk Assessment Topic Guidance Issue 1

Fire, Explosion and Risk Assessment Topic Guidance Issue 1 Hazard Installations Directorate Offshore Division Fire, Explosion and Risk Assessment Topic Guidance Issue 1 Revision sheet Issue Description Date 1 First issue February 2003 Overview of Topic Guidance

More information

Hazard Operability Studies (HAZOP) Germanischer Lloyd Service/Product Description

Hazard Operability Studies (HAZOP) Germanischer Lloyd Service/Product Description Safety & Risk Management Services Hazard Operability Studies (HAZOP) Germanischer Lloyd Service/Product Description Germanischer Lloyd Service/Product Description Hazard Operability Studies (HAZOP) Contents

More information

BUSINESS CONTINUITY POLICY

BUSINESS CONTINUITY POLICY BUSINESS CONTINUITY POLICY Document Type Corporate Policy Unique Identifier CO-038 Document Purpose To provide a structure through which: i. A comprehensive business continuity management system (BCMS)

More information

Risk Management Policy

Risk Management Policy Risk Management Policy DOCUMENT CONTROL Developed by: Date: Origination: Quality, Systems & Shared s March 2014 Authorised by: Colette Kelleher April 2014 DOCUMENT REVIEW HISTORY Original Circulation date:

More information

British Steel Pension Scheme: Public Consultation Response from the Pension Protection Fund

British Steel Pension Scheme: Public Consultation Response from the Pension Protection Fund British Steel Pension Scheme: Public Consultation Response from the Pension Protection Fund Summary The PPF recognises the Government s commitment to securing a sustainable future for the UK steel industry

More information

RISK 2014. Case Study: Safety in Design Process Development. Engineering Management Systems Engineering Management Systems

RISK 2014. Case Study: Safety in Design Process Development. Engineering Management Systems Engineering Management Systems RISK 2014 1 Case Study: Safety in Design Process Development Mike Hurd, representing 2 Contact details 3 Engineering.Systems.Management @gmail.com Mike Hurd 0432 858 958 This is what it is all about 4

More information

Risk management a practical approach

Risk management a practical approach Risk management a practical approach Introduction Preventing work related accidents and injuries is the primary concern for all those involved in health and safety. Work related accidents and injuries

More information

De Nederlandsche Bank N.V. May 2011. Assessment Framework for Financial Core Infrastructure Business Continuity Management

De Nederlandsche Bank N.V. May 2011. Assessment Framework for Financial Core Infrastructure Business Continuity Management De Nederlandsche Bank N.V. May 2011 Assessment Framework for Financial Core Infrastructure Business Continuity Management Contents INTRODUCTION... 3 BUSINESS CONTINUITY MANAGEMENT STANDARDS... 5 1. STRATEGY

More information

Guideline. Operational Risk Management. Category: Sound Business and Financial Practices. No: E-21 Date: June 2016

Guideline. Operational Risk Management. Category: Sound Business and Financial Practices. No: E-21 Date: June 2016 Guideline Subject: Category: Sound Business and Financial Practices No: E-21 Date: June 2016 1. Purpose and Scope of the Guideline This Guideline sets out OSFI s expectations for the management of operational

More information

CONTROLLED DOCUMENT. Number: Version Number: 4. On: 25 July 2013 Review Date: June 2016 Distribution: Essential Reading for: Information for:

CONTROLLED DOCUMENT. Number: Version Number: 4. On: 25 July 2013 Review Date: June 2016 Distribution: Essential Reading for: Information for: CONTROLLED DOCUMENT Risk Management Strategy and Policy CATEGORY: CLASSIFICATION: PURPOSE: Controlled Number: Document Version Number: 4 Controlled Sponsor: Controlled Lead: Approved By: Document Document

More information

Management of health and safety at work

Management of health and safety at work Management of health and safety at work Management of Health and Safety at Work s 1999 Approved Code of Practice & guidance This is a free-to-download, web-friendly version of L21 (second edition, published

More information

Office for Nuclear Regulation

Office for Nuclear Regulation ONR GUIDE LC17 Management Systems Document Type: ONR Nuclear Safety Technical Inspection Guide Unique Document ID and Revision No: NS-INSP-GD-017 Revision 2 Date Issued: November 2012 Review Date: November

More information

Bridgend County Borough Council. Corporate Risk Management Policy

Bridgend County Borough Council. Corporate Risk Management Policy Bridgend County Borough Council Corporate Risk Management Policy December 2014 Index Section Page No Introduction 3 Definition of risk 3 Aims and objectives 4 Strategy 4 Accountabilities and roles 5 Risk

More information

Business Continuity Policy

Business Continuity Policy Business Continuity Policy St Mary Magdalene Academy V1.0 / September 2014 Document Control Document Details Document Title Document Type Business Continuity Policy Policy Version 2.0 Effective From 1st

More information

Network Risk Assessment Guideline

Network Risk Assessment Guideline Network Risk Assessment Guideline Network Risk Assessment Guideline Table of Contents Revision history... ii 1. Purpose and Scope... 1 2. Definitions, Abbreviations and Acronyms... 1 3. References... 2

More information

Information Security: Business Assurance Guidelines

Information Security: Business Assurance Guidelines Information Security: Business Assurance Guidelines The DTI drives our ambition of prosperity for all by working to create the best environment for business success in the UK. We help people and companies

More information

TRAM: TECHNICAL RISK AUDIT METHODOLOGY FOR COMAH SITES

TRAM: TECHNICAL RISK AUDIT METHODOLOGY FOR COMAH SITES TRAM: TECHNICAL RISK AUDIT METHODOLOGY FOR COMAH SITES Patrick J. Naylor Hazardous Installations Division, Health & Safety Executive, Bootle, L20 3RA, UK. Dr.Tom Maddison Hazardous Installations Division,

More information

OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017

OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017 STRATEGIC CONTEXT OFFSHORE OIL & GAS SECTOR STRATEGY 2014 TO 2017 1 This strategy sets out how HSE s Energy Division will regulate health and safety of the offshore oil and gas industry operating on the

More information

An Integrated Operational Risk Management Framework for Power Generation

An Integrated Operational Risk Management Framework for Power Generation An Integrated Operational Risk Management Framework for Power Generation Ir Stephen W.K. Pang Acting Plant Risk Manager Generation Business Group CLP Power Hong Kong Limited Introduction Excellent risk

More information

Risk Management & Business Continuity Manual 2011-2014

Risk Management & Business Continuity Manual 2011-2014 ANNEX C Risk Management & Business Continuity Manual 2011-2014 Produced by the Risk Produced and by the Business Risk and Business Continuity Continuity Team Team February 2011 April 2011 Draft V.10 Page

More information

Following up recommendations/management actions

Following up recommendations/management actions 09 May 2016 Following up recommendations/management actions Chartered Institute of Internal Auditors At the conclusion of an audit, findings and proposed recommendations are discussed with management and

More information

Business Continuity Management For Small to Medium-Sized Businesses

Business Continuity Management For Small to Medium-Sized Businesses Business Continuity Management For Small to Medium-Sized Businesses Produced by NORMIT and Norfolk County Council Resilience Team For an electronic copy of this document visit www.normit.org Telephone

More information

Emergency Management and Business Continuity Policy

Emergency Management and Business Continuity Policy www.surreycc.gov.uk Making Surrey a better place Emergency Management and Business Continuity Policy 4 TH EDITION June 2011 Title Emergency Management and Business Continuity Policy Version 4.0 Policy

More information

Risk Management at Chevron

Risk Management at Chevron Risk Management at Chevron Jean Bruney AIChE/SACHE Workshop Context for HES Risk Management Corporation Sets policies & expectations Centers of Expertise Establish processes & verify Oversight Level Global

More information

MARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc

MARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc MARCH 2012 Version 1.10 Strategic Risk Policy Update March 2012 v1.10.doc Document History Current Version Document Name Risk Management Policy Statement and Strategic Framework Last Updated By Alan Till

More information

State of Queensland. Published by the Department of Infrastructure and Planning, September 2010, 100 George Street, Brisbane Qld 4000.

State of Queensland. Published by the Department of Infrastructure and Planning, September 2010, 100 George Street, Brisbane Qld 4000. Looking forward. Delivering now. The Department of Infrastructure and Planning leads a coordinated Queensland Government approach to planning, infrastructure and development across the state. State of

More information

A guide for members APES 325 Risk Management for Firms

A guide for members APES 325 Risk Management for Firms A guide for members APES 325 Risk Management for Firms An explanation and introduction to APES 325 Risk Management for Firms Overview of the scope and application of a risk management framework. APES 325

More information

NORTH HAMPSHIRE CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY MANAGEMENT POLICY AND PLAN (COR/017/V1.00)

NORTH HAMPSHIRE CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY MANAGEMENT POLICY AND PLAN (COR/017/V1.00) NORTH HAMPSHIRE CLINICAL COMMISSIONING GROUP BUSINESS CONTINUITY MANAGEMENT POLICY AND PLAN (COR/017/V1.00) Subject and version number of document: Serial Number: Business Continuity Management Policy

More information

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems

For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression Systems BAFE Scheme: SP203-3 Version 1: July 2008 Amendment No: 1 Fire Protection Industry Scheme, Reference SP203 Part 3 For the Design, Installation, Commissioning & Maintenance of Fixed Gaseous Fire Suppression

More information

The Management of Asbestos containing Materials

The Management of Asbestos containing Materials The Management of Asbestos containing Materials Status Owner Approval by University Court Draft Head of Estates and Building 1 Purpose... 1 2 Scope... 3 3 Principles... 4 4 Procedure... 5 5 Accountabilities...

More information

ICHEME SYMPOSIUM SERIES NO. 141

ICHEME SYMPOSIUM SERIES NO. 141 EMERGENCY PLANNING: THE LESSONS FROM RECENT MAJOR ACCIDENTS R D Picken, HM Inspector of Health and Safety Chemical and Hazardous Installations Division Crown Copyright 1997 The UK strategy for dealing

More information

SAFETY and HEALTH MANAGEMENT STANDARDS

SAFETY and HEALTH MANAGEMENT STANDARDS SAFETY and HEALTH STANDARDS The Verve Energy Occupational Safety and Health Management Standards have been designed to: Meet the Recognised Industry Practices & Standards and AS/NZS 4801 Table of Contents

More information

Supplying new machinery

Supplying new machinery A short guide to the law and your responsibilities when supplying machinery for use at work Introduction This leaflet can help you if you are supplying machinery for use at work. It explains the main health

More information

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader

More information

Basics of Sustainability. Environmental Management Systems (EMS)

Basics of Sustainability. Environmental Management Systems (EMS) Basics of Sustainability 5 Environmental Management Systems (EMS) 1 Contents Page Aims... 2 Introduction... 3 Environmental Management Standards (EMS)... 3 Environmental Policy... 4 Planning... 4 Implementation,

More information

Methods of Determining Safety Integrity Level (SIL) Requirements - Pros and Cons

Methods of Determining Safety Integrity Level (SIL) Requirements - Pros and Cons Methods of Determining Safety Integrity Level (SIL) Requirements - Pros and Cons 1 Introduction by W G Gulland (4-sight Consulting) The concept of safety integrity levels (SILs) was introduced during the

More information

Clinical Risk Management: Agile Development Implementation Guidance

Clinical Risk Management: Agile Development Implementation Guidance Document filename: Directorate / Programme Document Reference NPFIT-FNT-TO-TOCLNSA-1306.02 CRM Agile Development Implementation Guidance v1.0 Solution Design Standards and Assurance Project Clinical Risk

More information

Health, Safety and Environment Management System

Health, Safety and Environment Management System Health, Safety and Environment Management System For Bridgeport Energy Ltd Level 7, 111 Pacific Highway North Sydney 2011 June, 2010 DOCUMENT CONTROL Title: Document Number: Health, Safety and Environmental

More information

June 2010 HEALTH, SAFETY, AND ENVIRONMENT MANAGEMENT SYSTEM (HSEMS)

June 2010 HEALTH, SAFETY, AND ENVIRONMENT MANAGEMENT SYSTEM (HSEMS) June 2010 HEALTH, SAFETY, AND ENVIRONMENT MANAGEMENT SYSTEM (HSEMS) TABLE OF CONTENTS PAGE PART I INTRODUCTION Corporate Health, Safety and Environment Policy.. 1 Purpose... 2 HSEMS Framework... 3 PART

More information

A Risk Management Standard

A Risk Management Standard A Risk Management Standard Introduction This Risk Management Standard is the result of work by a team drawn from the major risk management organisations in the UK, including the Institute of Risk management

More information

HAZARDOUS MATERIALS MANAGEMENT ISSUE 2

HAZARDOUS MATERIALS MANAGEMENT ISSUE 2 CONTENTS PAGE 1 AIM 2 2 APPLICATION 2 3 DEFINITIONS 2 4 REASON FOR INCLUSION 2 5 REQUIREMENTS 3 6 PLANT AND EQUIPMENT REQUIREMENTS 3 7 SYSTEM AND PROCEDURAL REQUIREMENTS 5 8 PEOPLE REQUIREMENTS 7 APPENDIX

More information

HUMAN FAILURE IN THE ASSESSMENT OF MAJOR HAZARD RISK: A CASE STUDY FOR THE HUMAN FACTORS SAFETY CRITICAL TASK ANALYSIS (HFSCTA) METHODOLOGY

HUMAN FAILURE IN THE ASSESSMENT OF MAJOR HAZARD RISK: A CASE STUDY FOR THE HUMAN FACTORS SAFETY CRITICAL TASK ANALYSIS (HFSCTA) METHODOLOGY HUMAN FAILURE IN THE ASSESSMENT OF MAJOR HAZARD RISK: A CASE STUDY FOR THE HUMAN FACTORS SAFETY CRITICAL TASK ANALYSIS (HFSCTA) METHODOLOGY Charlotte Hill 1, Liz Butterworth 1 and Steve Murphy 2 1 Human

More information

How To Manage Safety Risk In Aviation

How To Manage Safety Risk In Aviation 4 AVIATION RISK MANAGEMENT AN INTRODUCTION Civil AVIATION AuthORITy of New Zealand BOOKLET FOUR PUBLISHED: JUNE 2013 Preface The Civil Aviation Authority (CAA) published Advisory Circular AC00-4 Safety

More information

ENTERPRISE RISK MANAGEMENT FRAMEWORK

ENTERPRISE RISK MANAGEMENT FRAMEWORK ROCKHAMPTON REGIONAL COUNCIL ENTERPRISE RISK MANAGEMENT FRAMEWORK 2013 Adopted 25 June 2013 Reviewed: October 2015 TABLE OF CONTENTS 1. Introduction... 3 1.1 Council s Mission... 3 1.2 Council s Values...

More information

Section A: Introduction, Definitions and Principles of Infrastructure Resilience

Section A: Introduction, Definitions and Principles of Infrastructure Resilience Section A: Introduction, Definitions and Principles of Infrastructure Resilience A1. This section introduces infrastructure resilience, sets out the background and provides definitions. Introduction Purpose

More information

Performance Indicators in major hazard industries An Offshore Regulator s perspective - Ian Whewell

Performance Indicators in major hazard industries An Offshore Regulator s perspective - Ian Whewell Performance Indicators in major hazard industries An Offshore Regulator s perspective - Ian Whewell Background Much has been written about indicators of health and safety performance and a great deal of

More information

ENGINEERING COUNCIL. Guidance on Risk for the Engineering Profession. www.engc.org.uk/risk

ENGINEERING COUNCIL. Guidance on Risk for the Engineering Profession. www.engc.org.uk/risk ENGINEERING COUNCIL Guidance on Risk for the Engineering Profession www.engc.org.uk/risk This guidance describes the role of professional engineers and technicians in dealing with risk, and their responsibilities

More information

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015

to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 D to Asset Management Policy and Guidance Draft Version 1.4 9 July 2015 This page has been left blank intentionally Page 2 of 24 Page 3 of 24 This page has been left blank intentionally Page 4 of 24 Strategic

More information

An introduction to Functional Safety and IEC 61508

An introduction to Functional Safety and IEC 61508 An introduction to Functional Safety and IEC 61508 Application Note AN9025 Contents Page 1 INTRODUCTION........................................................... 1 2 FUNCTIONAL SAFETY.......................................................

More information

AS/NZS 4801:2001. Safety Management Systems (SMS) Self-Assessment Checklist. Revision 1 (January 2014)

AS/NZS 4801:2001. Safety Management Systems (SMS) Self-Assessment Checklist. Revision 1 (January 2014) AS/NZS 4801:2001 Safety Management Systems (SMS) Self-Assessment Checklist This document restates the requirements of AS/NZS 4801:2001 for Safety Management Systems (SMS) and has been developed to assist

More information

Managing Asbestos Policy

Managing Asbestos Policy Managing Asbestos Policy Liverpool Mutual Homes Page 1 of 16 Table of Contents 1. MANAGEMENT INFORMATION 2. POLICY STATEMENT 3. POLICY AIMS AND KEY OBJECTIVES 4. INTRODUCTION 5. DETAIL 6. LINKS TO LMH

More information

Integrated Risk Management Policy

Integrated Risk Management Policy Integrated Management Policy Document reference number Document developed by Quality and Patient Safety Directorate Revision number 4 Document approved by Quality and Patient Safety Directorate Approval

More information

Hazard Identification, Risk Assessment and Management Procedure. Documentation Control

Hazard Identification, Risk Assessment and Management Procedure. Documentation Control Hazard Identification, Risk Assessment and Management Procedure Reference: Date approved: Approving Body: Implementation Date: Version: 3 Documentation Control GG/CM/007 Trust Board Supersedes: Version

More information

Risk Assessment Tool and Guidance (Including guidance on application)

Risk Assessment Tool and Guidance (Including guidance on application) Risk Assessment Tool and Guidance (Including guidance on application) Document reference number Revision number OQR012 Document developed by 5 Document approved by Revision date October 2011 Responsibility

More information

State Records Guideline No 25. Managing Information Risk

State Records Guideline No 25. Managing Information Risk State Records Guideline No 25 Managing Information Risk Table of Contents 1 Introduction... 4 1.1 Purpose... 4 1.2 Authority... 4 2 Risk Management and Information... 5 2.1 Overview... 5 2.2 Risk management...

More information

Clients in Construction Best Practice Guidance

Clients in Construction Best Practice Guidance Clients in Construction Best Practice Guidance Published in 2009 by the, Metropolitan Building, James Joyce Street, Dublin 1. Copyright The January 2009 Clients in Construction: Best Practice Guidance

More information