Peter D Aeberli Barrister - Arbitrator - Mediator Adjudicator
|
|
|
- Leonard Webster
- 9 years ago
- Views:
Transcription
1 Peter D Aeberli Barrister - Arbitrator - Mediator Adjudicator INTRODUCTORY GUIDE TO JCT CONTRACTS November 2002 SESSION 1: GENERAL PRINCIPLES LAW AND INTRODUCTION TO CONSTRUCTION CONTRACTS SECTION A: BASIC RULES OF CONTRACT 1. The law of contact is that part of the law of obligations founded on agreement. 2. The elements of a legally enforceable agreement (a contract): - Offer and acceptance (note: invitation to treat) - Consideration or recognised formality (deed) - Intent to create legal relationships - Certainty of terms - Capacity (individuals, corporations). Consider letters of intent and quasi-contract. 3. Vitiating factors: - Illegality (void) - Mistake (void) - Misrepresentation of fact (voidable). 4. Privity of contract: - Rights and obligations (who can enforce, see Contracts (Rights of Third Parties) Act Transfer of rights to third parties (assignment) - Transfer of obligations to third parties (novation) - Substitute performance (sub-contracting) - Warranting performance to others. 5. The obligations under a contract: - Incorporation of terms - Express and implied terms - Conditions, warranties and innominate terms - Conditions precedent and subsequent - Exemption clauses - Passing of property in goods and materials. 6. Discharge of contracts: 1/1
2 - By performance - By breach of condition - By repudiatory breach of an innominate term - By anticipatory breach - By frustration. 7. Consequence of non performance: - If non payment, debt - If breach, damages (compensatory, must mitigate) - If breach of condition/repudiation, elective right to terminate (release of parties from future obligations) - Exceptionally injunction or specific performance. 8. Defences: - Contract void or voidable - Exemption clauses - Frustration - Statue of limitations - Failure to mitigate. 9. Forum of dispute resolution: - Mediation/conciliation - Adjudication (Housing Grants, Construction and Regeneration Act 1996) - Arbitration (Arbitration Act 1996) - Litigation (County Courts/High Court). SECTION B: OBJECTIVES OF STANDARD FORM CONSTRUCTION CONTRACTS The construction contract is the principal vehicle through which a project will be procured. It does not exist in a vacuum but are, or should be, prepared in response to a number of legal and practical issues, many of which have their roots in the nineteenth century, if not earlier. 1. Setting the parties' primary obligations (what is to be provided for how much, when?) What is to be provided? Consideration should be given to the various procurement routes and their allocation of design/performance risk (traditional, design and build, contract management, management contracting). Consideration should be given to whether there is to be a role for a contract administrator (agent or independent); Merton LB v. Leach (1985) 32 Build LR 51; Beaufort Developments v. Gilbert-Ash [1998] 88 Build LR 1 (HL) 1. Is there to be a maintenance period after completion? How does this affect the employer s right to damages, consider Pearce v. Baxter [1999] BLR 101 (CA). 2 1 Merton Architect acts as agent when supplying contractor with drawings, instructions, levels, and the like and in supervising the progress of the works and seeing that it is properly executed. To the extent that the architect performs these duties, the employer contracts that the architect will perform them with reasonable diligence, skill and care. But were the contract confers on the architect discretionary powers which he must exercise with due regard to interests of contractor and employer, latter does not undertake that he will exercise those powers reasonably, rather than he will leave him free to exercise his discretion fairly and without improper interference. Beaufort suggests that may be an agent in all cases? 2 Pearce A refusal to allow contractor to remedy defects or to give instruction to do so, restricts damages to cost contractor would have incurred in remedying them. Note different relationship between completion and maintenance period in JCT 1/2
3 How is the work to be provided described (drawings, quantities and/or schedules)? Is the work to be described prescriptively or by performance? What is the standard of performance? Are such standards to be express or implied (Sale of Goods Act 1979, Supply of Goods and Services Act 1982, common law)? For terms implied at common law see, for example Merton v. Leach (1985) 32 Build LR Are standards to be objective or subjective (who decides compliance)? Where are standards to be stated (contract conditions, drawings, quantities, specifications, schedules)? When is performance required? What dates are to be fixed, (start, on site, progress and completion dates, phases)? How is completion assessed? Certain contracts refer to Practical Completion. For a consideration of what this means see, for example Jarvis v. Westminster Corporation [1970] 1 WLR 637; Kaye v. Hosier & Dickinson [1972] 1 WLR 146, What is to be paid for? What is the payment route (lump sum, measurement and value, cost plus). Particularly in a lump sum contract, what work is to be paid for? Some lump sum contracts allow provisional sums. These, in effect, introduce packages of measurement and value work. 2. Altering the contracted for performance Why must there be an express power to alter the contracted for performance? Defining the scope of the power to alter performance (quantity and quality of work, method and timing of performance). Determining the consequences of an alteration of performance (cost 5, loss/expense, time). 3. Monitoring and controlling the manner of performance Is a general power to instruct the contractor required? Are provisions needed to allow for monitoring performance (early warning, assessing compliance (quantity, quality, method and time))? Are provisions needed dealing with the possibility of defective work (opening up, testing, removal of defective work, dealing with potentially defective repetitive work)? Are there any restrictions on who performs the contractor's primary obligations (contractor, subcontractors, specialists, suppliers)? If so, who decides? Who is entitled to performance (parties, assigns, third parties)? Are warranties to be provided, if so, on what terms? contracts and ICE contracts. 3 Merton Implied term that employer would not hinder or prevent the contractor from carrying out its obligations in accordance with contract and from executing the work in a regular and orderly manner. No duty on the contractor to check for discrepancies and divergences in the architect s information. 4 Jarvis Probably can be practically complete despite latent defects. But not if patent defects, given the purpose of the maintenance period (substantial performance concept displaced?). All the construction work to be done must be done. Now often a link with the provision of information for the health and safety file. 5 How is the cost of the work assessed, this is one of the purposes of including a bill of quantities, see Henry Boot v, Alstom [2000] BLR 247 (CA). 1/3
4 4. Valuation and timing of payments Balancing cash flow against security for the paying party. Complying with the statutory context (Housing Grants, Construction and Regeneration Act 1996). Interim payment options (valuation of work, activity schedule, milestones). What is included and when (work, materials - unfixed, off-site, advances on account, mobilisation payments)? Determining the time and amount of payments (schedules, bills of quantities). How does the assessment of interim payments relate to the contract sum? Authorising and releasing payment (who decides, status of certificates, interim and final). 5. Risks and sanctions Time and cost risks How does the contract allocate responsibility for delays and additional costs due to delays or disruption in performance (defaults, neutral events). Are damages for late completion to be liquidated. If so how is the rate of damages to be assessed so as to reflect the likely level of loss. Performance risks and sanctions Dealing with non-performance by contractor, sub-contractors or the employer: Suspending performance and determining the contract. Balancing risks by retention of monies, passing of title clauses, rights of suspension (Housing Grants, Construction and Regeneration Act 1996). Consider also bonds, collateral warranties and limits on post completion liability (conclusivety provisions). Injury to persons and property Allocating the risks consequent upon injury to individuals or damage to the works and other property (indemnity and insurance clauses). 6. Dispute resolution Alternative procedures for dispute avoidance, management and resolution (contract administrator, adjudication, arbitration/litigation, mediation). The legal context: Arbitration Act 1996; Housing Grants, Construction and Regeneration Act 1996, s. 108; status of contract administrator s decisions. 1/4
5 INTRODUCTORY GUIDE TO JCT CONTRACTS Peter Aeberli RIBA, ARIAS, FCIArb, Barrister Chartered Arbitrator, Adjudicator, Registered CEDR Mediator November 2002 SESSION 2: AN OVERVIEW OF STANDARD FORM BUILDING CONTRACTS AND JCT CONTRACTS SECTION A: SELECTING AND ASSEMBLING THE CONTRACT PACKAGE 1. Selecting the right contract Consider: - Procurement route - Complexity of project - Need for selected sub-contractors/suppliers - Value of project - Role of contract administrator, if any. 2. Elements of the contract package The agreement (letter or standard form, recitals). The conditions of contract, amendments and supplements (standard/amended/bespoke). Selecting the appropriate form. The appendix (where options are selected). Supporting documentation (drawings, specification, bills of quantities). Related sub-contracts, amendments and supplements. Collateral arrangements (warranties and bonds). 3. Entering into the contract Concluding the contract (note different attestation sections in the JCT Standard Forms): - Made as a simple contract (under hand, orally or by conduct). - Executed as a deed. Signed as such, signature witnessed (or if a registered company, by affixing its seal or signed by two directors or a director and the company secretary), delivered. There may be difficulties if the contract not concluded by signing a standard form. SECTION B: OVERVIEW OF THE JOINT CONTRACTS TRIBUNAL AND JCT CONTRACTS 1. The structure of the JCT (a consensual body with participation from all sectors of the construction industry producing contracts to reflect a negotiated balance of risk). 2. The JCT family of contracts, traditional (JCT98, IFC98, MW98); design and build (WCD 98); cost plus (PC98); management contracting (MC98); and construction management (soon); plus 2/1
6 matching supplements, sub-contracts and warranties; performance bonds (soon); professional services contracts (soon). The JCT produces amendments to its forms, from time to time as appropriate in light of case law, legislation, and changes in practice. It also provides guidance on when to use its forms, see Practice Note The use of MW98. - Where minor building works are to be carried out over a reasonably short period for an agreed lump sum under the direction of an Architect/Contract Administrator. - Where the lump sum is based on drawings, specification and/or schedules, but without detailed measurements (ie a bill of quantities). - Where the value of the contract is generally under 70,000 at 1992 prices. - Where there is no need to control the selection of specialist sub-contractors. This can be done by naming the selected person in the tender documents or, possibly (?), in instructions expending a provisional sum (but see MW98 clause 3.6). But there is no machinery dealing with the consequences of such naming. A direct contract with the person concerned might be preferable (see Practice note M2). 4. The use of IFC98. - Where the traditional procurement route is appropriate (all work adequately specified or specified and billed prior to tender) and a lump sum price is required, the works to be under the direction of an Architect/Contract Administrator. - Where the works of are simple content (although more complex than would be suitable for MW98) involving normally recognised basic trades and skills, the building services are relatively straightforward, and there is no specialist work of a complex nature. - Where there may be a need to pre-select certain sub-contractors (naming) or for phased completion of the works. 5. The use of JCT98. - Where the traditional procurement route is appropriate (all work adequately specified or specified and billed prior to tender and, except for limited cases provided for in the contract, designed by persons for whom employer responsible) and a lump sum price is required (unless approximate quantities version is used). - Where IFC98 is not appropriate. For instance, because the work is not simple or limited to basic skills or trades, where complex services installations or specialist work is required, or where the contract value is high (more than at 1984 prices) or the contact period long (more than a year). - Where contract administrator/architect is to be appointed. 6. The JCT 98 variants. - JCT98 with quantities. Where quantities are prepared in accordance with SMM7. A lump sum for the billed work. - JCT98 with approximate quantities. Where quantities can only be a reasonably accurate forecast of work required. A measurement and value contract. 2/2
7 - JCT98 without quantities. Where quantities are not prepared. A lump sum for the work shown on the drawings and specifications and schedules, if any or, to the extent there are quantities, for those quantities. All three variations are produced in a Private and in a Local Authority edition, the latter containing provisions considered specific to procurement by Local Authorities: - Facility for a contract administrator or Architect - Removal of the Contractor's right to object to replacements of Architect/contract Administrator or Quantity Surveyor where officials of the Local Authority - Contract Documents are in the custody of Employer rather than Architect or Quantity Surveyor - No right to require retention to be put in separate account - The Local Authority can determine the Contractor's employment were latter commits an offence under s. 117(2) of the Local Government Act The notes for JCT98 focus the Private with Quantities version of JCT98. JCT amendments: After first publication, JCT80 was subject to 18 amendments plus amendment TC/94, the most recent being issued in May 1998, there were also numerous published amendments to IFC84 and MW80. JCT80, IFC84 and MW80 have now been re-issued as JCT98, IFC98 and MW98, incorporating all previous amendments except TC/94. Subsequently the JCT has published amendments 1 to 4 to JCT98 and a retention bond option. JCT has also published amendments 1 to 4 to IFC98 and MW All versions of JCT98 include a number of optional provisions as well as clauses that must be completed or selected by the parties completing the appropriate Appendix entry. 8. The JCT produces a number of supplements for use with JCT98 where appropriate. - The Sectional Completion Supplement (not for Without Quantities) for use where phased completion is required. - The Contractor's Designed Portion Supplement where the Contractor is to design a discrete and limited part (not the whole) of the works. Modifications must be made to the Articles of Agreement and the Conditions where these supplements are included. These are explained in the supplements themselves. The details of these supplements are not considered in these notes. 9. The JCT produces a suite of related sub-contracts, warranties and tender forms for use with JCT 98 when sub-contractors are to be selected by the Employer (nomination). Post 1991 these comprise: - NSC/T: Tender forms for use between the Employer (by its Architect) and a proposed Nominated Sub-contractor - NSC/A: The Agreement to be concluded between the Contractor and a Nominated Subcontractor - NSC/C: The Conditions of the Sub-contract between the Contractor and a Nominated 2/3
8 Sub-contractor - NSC/W: The Warranty to be entered into between the Employer and a Nominated Subcontractor - NSC/N: The form to be used by the Architect to nominate a Sub-contractor in accordance with the Main Contract. Detailed consideration of these forms is outside the scope of this course. 10. The JCT produces a similar but more restricted range of supplements and sub-contract forms for use with IFC98, in particular: - A Sectional Completion Supplement for use where phased completion is required. - NAM/T: A tender and agreement form for use where a Named Sub-contractor is to be appointed. - NAM/SC: The Conditions of the Sub-contract between the Contractor and a Named Subcontractor. Two related forms are also produced by other bodies for use with IFC98. - ESA/1: A Warranty to be entered into between the Employer and a Named Subcontractor. - IN/SC: Articles of Agreement for a domestic sub-contract. Detailed consideration of these forms is outside the scope of these notes. 11. The role of consultants under the JCT contracts. Most standard form JCT contracts provide for an Architect/Contract administrator to administer the contract on behalf of the Employer. Some also identify specific functions to be performed by a Quantity Surveyor and a Planning Supervisor. Although such persons have specific functions under the contact they are not parties to the contract and have no power to change its terms. If they fail to exercise any duties required of them the employer is in breach of contract. As regards their powers, the Employer is under the following implied obligations: - Where they act as his agent, that they will act with reasonable skill and care - Where they exercise discretion between the parties, that they will do so with due regard to the interests of both parties and that the Employer will not interfere with the exercise of their discretion - See Merton v. Leach (1985) 32 Build LR 51. None of the other consultants have functions under the contract, they can only provide information to the Architect or, if given functions, the Quantity Surveyor, to enable them to exercise their powers and duties and, if appropriate, to pass on to the Contractor. 2/4
9 SECTION C: JCT 98 - THE ARTICLES OF AGREEMENT 1. The Articles of Agreement comprise the agreement, the Recitals and the Articles. The agreement identifies the parties to the contract and the date of the agreement. The parties are the Employer and the Contractor. The Employer must appoint a person as Architect, a Quantity Surveyor and a Planning Supervisor. The Recitals are not contract terms. Rather they identify the Works (see clause 1.3), the Drawings and Bills describing those Works and the requirement for an Information Release Schedule (see clause 5.4) and a priced Activity Schedule (see clause , alternative A). The description of the Works must be completed accurately. The Articles identify what is to be paid (article 2) for what (article 1, clause 14) and identify those appointed on behalf of the Employer to operate the contract conditions on his behalf (articles 3 and 4). Article 5 is the adjudication agreement. Article 6 identifies the Planning Supervisor and the Principal Contractor for the purpose of the CDM Regulations (see also clause 1.5). Article 7A is the arbitration agreement, article 7B a litigation option. But note also article 7 in Amendment TC/94 (terrorism cover), if incorporated. 2. Definitions Defined terms are identified with upper case first letters. The definitions are given in clause 1.3. Note also clauses 1.8 and 1.7 dealing with the service of notices, etc and the reckoning of period of days. 3. The Contract Documents These are defined in clause 1.3 and comprise (the Without Quantity version list is different): - The Contract Drawings (what is to be constructed, where) - The Contact Bills prepared in accordance with SMM7 (see clause 2.2.2) - The Articles of Agreement - The Conditions - The Appendix The interrelationship of the Contract Documents and the resolution of discrepancies or divergences in or between the specially prepared documents, such as Contract Drawings, Contract Bills, the Statement in respect of Performance Specified Work, if any, and other information provided by the Architect is governed by clauses 2.2, 2.3 and 2.4. The resolution of divergences between this material and the Statutory Requirements is governed by clause /5
10 SECTION C(1) 6 : MW98 - THE ARTICLES OF AGREEMENT 1. The Articles of Agreement comprise the agreement, the Recitals and the Articles. The agreement identifies the parties to the contract and the date of the agreement, and provides for signatures. The parties are the Employer and the Contractor. The Employer must appoint a person as Architect and as Quantity Surveyor. There is also a role for the Planning Supervisor, if any (see clause 5.9). The Recitals are not contract terms. Their principal function is to identify the work for which the Contractor tendered (The description in the first Recital must be completed accurately) and the drawings, Specification and/or schedules describing the Works. The fifth Recital identifies if the CDM Regulations apply in full (see clause 1.4). The Articles identify what is to be paid (article 2) for what (article 1) and identify those appointed on behalf of the Employer to operate the contract on his behalf (article 3). Article 1 defines the Works (the work described in the first Recital together with any changes instructed under the Contract). Article 6 is the adjudication agreement. Article 4 identifies the Planning Supervisor (two choices) and Article 5 the Principal Contractor, for the purpose of the CDM Regulations (see also clause 1.3). Article 7A is the arbitration agreement, article 7B a litigation option. Note Article 7C. If neither 7A nor 7B selected, arbitration applies. 2. Definitions Defined terms are identified with upper case first letters. There is no separate definitions clause. Note also clauses 1.5 and 1.6 dealing with the services of notices, etc and the reckoning of period of days (see also clause 7.1), and clause 1.7 dealing with the applicable law. 3. The Contract Documents These are defined in the first Recital, are attached to the Agreement, and comprise: - The Contract Drawings (what is to be constructed, where?); - The Contact Specification (what is to be used, how?); - The schedules (of rates, see second Recital) - The Conditions and Supplemental Conditions (fluctuations, tax and dispute resolution). 6 Page: 6 7. Amendments to JCT contracts. The JCT publishes amendments to all its contracts from time to time. Currently there are four published amendments to the MW The role of consultants under the JCT contracts. Most standard form JCT contracts provide for an Architect/Contract administrator to administer the contract on behalf of the Employer. Some also identify specific functions to be performed by a Quantity Surveyor and a Planning Supervisor. Although such persons have specific functions under the contact they are not parties to the contract and have no power to change its terms. If they fail to exercise any duties required of them the employer is in breach of contract. As regards their powers, the Employer is under the following implied obligations: - Where they act as his agent, that they will act with reasonable skill an care - Where they exercise discretion between the parties, that they will do so with due regard to the interests of both parties and that the Employer will not interfere with the exercise of their discretion - See Merton v. Leach (1985) 32 Build LR 51. None of the other consultants have functions under the contract, they can only provide information to the Architect or, if given functions, the Quantity Surveyor, to enable them to exercise their powers and duties and, if appropriate, to pass on to the Contractor. 2/6
11 The interrelationship between the Contract Documents and the resolution of inconsistencies in or between the specially prepared documents, such as Contract Drawings and Specification, is governed by clause 4.1 (obligations additional to those envisaged in the Conditions can be imposed by the specially prepared documents, provided they do not modify, override or affect the Conditions). The resolution of divergences between this material and any statutory obligations is governed by clause 5.1. SECTION C(2): IFC 98 - THE ARTICLES OF AGREEMENT 1. The Articles of Agreement comprise the Agreement, the Recitals and the Articles. The agreement identifies the parties and the date of the agreement. The parties are the Employer and the Contractor. The Employer must appoint an Architect/Contract Administrator (see clause 8.4), a Quantity Surveyor and a Planning Supervisor. The Recitals are not contract terms. Rather they identify the Works (see also article 1), the documents describing those Works, the optional requirement for an Information Release Schedule (see clause 1.7) and an optional priced Activity Schedule (see clause 4.2.1), the applicability of the CDM regulations and, most importantly, the basis on which the contractor s price has been prepared (2 nd recital). Option A being used where there are priced bills, option B where there are no priced bills (see also clauses 1.2, 8.5). The Articles identify what is to be paid (article 2) for what (article 1, clause 4.1) and identify those appointed on behalf of the Employer to operate the contract conditions on his behalf (articles 3, 4). Articles 5 and 6 identify the Planning Supervisor and the Principal Contractor for the purpose of the CDM Regulations (see also clause 1.12). Article 7 identifies whether or not sectional completion applies. Article 8 is the adjudication agreement. Article 9A is the arbitration agreement, article 9B a litigation option. But note also article 7 in Amendment TC/94 (terrorism cover), if incorporated. 2. Definitions Defined terms are identified with upper case first letters. There is a list of definitions in clause 8.3. Note also clauses 1.13 and 1.14 dealing with the service of notices, etc. and the reckoning of period of days, and the option to use Electronic data interchange (EDI) for communications, clause 1.16, Annex The Contract Documents These are defined in the second Recital (see also the first Recital) and comprise: - The Contract Drawings (what is to be constructed, where) - Option A: The Contact Bills (Specification/Schedules of Work/Bills of Quantities) prepared in accordance with SMM7 (see clauses 1.5, 8.5) or Option B: The Specification - The Articles of Agreement - The Conditions including (by implication) The Appendix. The interrelationship of the Contract Documents and the resolution of discrepancies or divergences in or between the specially prepared documents, such as Contract Drawings, Contract Bills and other information provided by the Architect is governed by clauses 1.2, 1.3 and 1.4, but note also clauses 8.1 and 8.2. The resolution of divergences between this material and the Statutory Requirements is governed by clauses 5.2 and 5.3, see also clause /7
12 INTRODUCTORY GUIDE TO JCT 98 Peter Aeberli RIBA, ARIAS, FCIArb, Barrister Chartered Arbitrator, Adjudicator, Registered CEDR Mediator November 2002 SESSION 3: JCT 98: THE CONDITIONS: PART I SECTION A: THE PARTIES' PRIMARY OBLIGATIONS 1. What is to be provided? The Contractor's obligations as regards the Works: - Clause 2.1: The Contractor's primary obligation to carry out and complete the Works as varied (see 1st Recital, clause 4.1, clause 13.1, 13.2, 13.3) and quality and standards to be achieved (both objective and subjective, see clause 30.9) - Clause 1.5: The Contractor to remain wholly responsible for carrying out the Works notwithstanding any obligation of the Architect to the Employer or the appointment of a clerk of works. - Clauses 42.2, 42.3: The Contractor's obligation to provide a Statement in respect of Performance Specified Work and to carry out Performance Specified Work (see clause 42.1) in accordance with that Statement (see clause 42.3) - Clause 5.9: The Contractor's obligation to provide, prior to Practical Completion, as built drawings, information and manuals concerning Performance Specified Work - Clause 6: The Contractor's obligation to comply with the Statutory Requirements (but note clauses and 6.2). - Clause 8.1: The Contractor's obligations as regards materials, goods and workmanship and in respect of the Health and Safety Plan (see also clause 8.2.1) - Clause 9.5: The Contractor s responsibly for the Works, notwithstanding any Nomination of Sub-contractors. - Clause 35.21: Limitation on the Contractor's liability in respect of Nominated Sub- Contractor's Work (principally concerning design). - Clause 35.22: Limitations on Nominated Sub-Contactor s liability to Employer (note clause 1.7 of NSC/C restricts the Nominated Sub-Contractor s liability to the Contractor where it is required to contract with a person, other than the Contractor, under a contract that limits the sub-sub-contractor s liability. - Clause 42.17: The Contractor's obligation to exercise reasonable skill and care in the provision of Performance Specified Work. 3/1
13 Architect s/employer's obligations as regards the Works: 2. When? - Clauses 5.3 and 5.4: The Architect's (as agent) obligation to provide information to the Contractor in accordance with the Information Release Schedule and to enable it to carry out its obligations (note clause 42.3). - Clause 7: The Architect's (as agent) obligation to provide levels. - Clause 35.20: Employer not liable to Nominated Sub-Contractors other than under NSC/W. - Clauses 42.5, 42.6: The Architect s (as agent) powers and obligations concerning the Contractor s Statement in respect of Performance Specified Work. - Clauses 42.14: The Architect s (as agent) obligation to issue instructions concerning the integration of Performance Specified Work into the design. Contractor's obligations after completion of the Works: - Clause 17.2: The Contractor's obligation to make good certain defects, shrinkages or faults in the works appearing within the Defects Liability Period (one period). Implied obligations: - Implied obligations of the Contractor as regards materials, satisfactory quality, probably no fitness for purpose obligation, see Supply of Goods and Services Act 1982, Part I. - Implied obligation of the Employer not to hinder or prevent the Contractor from carrying out and completing the Works. Clause 23.1: Regularly and diligently from the Date of Possession (note limited, optional, power of the Employer to defer giving possession) to the Completion Date (note relationship between Date for Completion and the Completion Date, see clauses 1.3 and 25). Clause 24.1: If the Contractor fails to complete by the Completion Date the Architect issues a certificate to that effect. Clause 17.1: The Architect certifies the date of Practical Completion when in his opinion this is achieved and the Contractor has provided information reasonably required by the Planning Supervisor for the preparation of the health and safety file (see clause 6A.4). Note the Contractor's limited obligations thereafter (see clause 17.2). See also clause for Practical Completion of Nominated Sub-Contractor's work. Clause 18: With the Contractor's consent the Employer can take possession of part or parts of the Work before Practical Completion, Practical Completion of such parts occurring when taken over. If phased completion is required the Sectional Completion Supplement should be used. 3. How much? Article 2: The Contract Sum. - This is generally payable for constructing the Bills of Quantities (see clause 14). But note the use of provisional sums and Approximate Quantities (clause , ) 3/2
14 to introduce elements of cost plus or measurement and value. - It is adjustable (see clauses 13.4, 14, 15.2, 26, 30.6 and 37). SECTION B: ALTERING THE CONTRACTED FOR PERFORMANCE 1. The extent of the power ` Clause 13.1: The Architect's power to issue instructions (see clause 4.1) varying the Works (note clauses , and 42.11). Clause 13.3: The Architect's duty to issue instructions concerning the expenditure of provisional sums. Note the different principles under the Standard Method of Measurement (clause 1.3) concerning defined and undefined work, clauses , 26.7), see also clause 42.8, concerning provisional sums in respect of Performance Specified Work. 2. The cost consequences Clause : Procedures for valuing the work content. Note clause 13.4 (Alternative A, price statement, Alternative B valuation in accordance with clause 13.5, 13.6 and 13.7). Clause 26: Procedures for determining the disruption costs (note clause ), but note position where clause 13.4, alternative A applies). 3. The time consequences Clause 25: Procedures for determining the time consequences (note clause ). 4. Pre-agreeing the cost and time consequences Clause 13A: Procedures for the submission by the Contractor of a quotation concerning the money and time consequences of a Variation and possible acceptance by the Employer (for nonacceptance see clause 13A.4). SECTION C: CONTROLLING AND MONITORING THE MANNER OF PERFORMANCE 1. Instructions to the Contractor Clause 4.1: The Contractor's obligation to comply with instructions of the Architect expressly empowered by the Conditions (note clause 4.2): - Clauses empowering instructions comprise 2.2, 6.1.3, 7, 8.3, 8.4, 8.5, 12, 13.2, 13.3, 17.2, 17.3, 23.2, 32.2, , 34.2, , 35.6, , , , 35.23, , , 35.25, 36.2, 42.4, 42.11, Not all communications between the Architect and Contractor are instructions (see, for example, clauses 13.A.3.2, , , , 35.9, 42.5) - In certain, limited, situations the Employer communicates directly with the Contractor (see, for example, clauses 13A.3, 13A.4, , ). 3/3
15 Clause 4.3: Instructions are of no effect unless given or confirmed in writing (see also clause 12, limited status of Clerk of Works' directions). 2. Miscellaneous management procedures Clause 5.1: Custody of Contract Drawings and Bills (The Architect retains originals and provides copies to the Contractor). Clause 5.2: Provision of copies of Contract Documents (note clauses 5.6 and 5.7). Clause 5.8: Distribution of Architect's Certificates (Originals go to the Client, copies to the Contractor, and Nominated Sub-contractors). Clause 10: Contractor's person in charge and authority to receive instructions and directions. 3. Monitoring performance Clause 5.3: Contractor to provide master programme to the Architect initially and after any extension of time decision (note clause 25.2, early warning of all delays). Clause 8.2.1: Proof of materials and goods provided. Clause 11: Architect's right of access to the Works and places where work being prepared for the Works. Clause 12: A Clerk of Works may be appointed as inspector on behalf of the Employer. Clause 42.2: Provision of the Contractor's Statement concerning Performance Specified Work (note clauses 42.3, 42.4, 42.5, 42.6, and 42.15). 4. Controlling who performs and who is entitled to performance Clause 1.12: Third party rights excluded (see the Contract (Rights of Third Parties) Act Clause 8.6: The Architect's power to exclude persons from the site. Clause 19.1: Restrictions on rights of assignment. Note Employer s optional right to assign to a purchaser or lessee of whole development. Clause 19.2: Restrictions on the Contractor's right to sub-contract (see also clause 19.4). Clause 19.3: Listing of persons (3 minimum) required to provide work (thus avoiding Nomination). Clause 19.4: Sub-contract terms (title, and interest on late payments). Clause 29: Work carried out by persons engaged by the Employer (note insurance implications and time and money consequences). Clause 35: Procedures for nominating and, if necessary re-nominating Sub-contractors. - Clause 35.1: Scope of the Architect s power to Nominate. - Clause 35.2: Circumstances in which the Contractor may tender for Nominated Sub- Contract Works. - Clauses : Procedure for Nominating Sub-Contactors. 3/4
16 - Clause 35.13: Payments to Nominated Sub-Contractors to be certified by Architect and provisions for direct payment in the event of Contractor default. Note also clauses and Early payment of Nominated Sub-Contractors. - Clause 35.14: Architect s involvement in granting extensions of time to Nominated Sub- Contractors. Note also clause 26.4: Loss and expense payable to Nominated Sub- Contractors. - Clause 35.15: Architect s Certificate of Non Completion of Nominated Sub-Contractor s work. - Clause 35.16: Architects Certificate of Practical Completion of Nominated Sub- Contractor s work. - Clause 35.24: Re-Nomination procedures. - Clause Architect s involvement in the determination of Nominated Sub- Contractors employment. Clause 36: Procedures for Nominating Suppliers. 3/5
17 INTRODUCTORY GUIDE TO JCT 98 Peter Aeberli RIBA, ARIAS, FCIArb, Barrister Chartered Arbitrator, Adjudicator, Registered CEDR Mediator November 2002 SESSION 4: JCT 98: THE CONDITIONS: PART 2 SECTION D: VALUATION AND TIMING OF PAYMENTS 1. Interim payments Clause 30.1: The timing of and payment in respect of Interim certificates. - Interim Certificates stating amount to be paid and the basis of payment to be issued at the periods stated in the Appendix (monthly unless otherwise stated). - Date of issue is the due date, final date for payment is 14 days from date of issue. Simple interest payable if payment late. - Not later than 5 days after date of issue, the Employer to issue a notice to the Contractor specifying the amounts proposed to be paid and basis of payment. - Any notice of withholding payment to be issued by the Employer not later than 5 days before the final date for payment. - Employer to pay the amount of Interim Certificate unless a notice specifying amount proposed to be paid or notice of withholding payment is issued (clause ), with interest if paid after the final date for payment. Clause 30.2: Amounts to be included in Interim Certificates (gross valuation, principally based on work properly completed (calculated by reference to the Contractor's Priced Activity Schedule, if submitted) less Retention, less total previous certified). - Clause : Amounts subject to retention. - Clause : Amounts not subject to retention. - Clause 30.3: The value of off-site materials and goods to be included where listed in the Contract Bills, provided the conditions in this clause fulfilled (note bond). - Clause 30.4: Calculation of Retention (half Retention released in interim payment immediately following Practical Completion). - Clause 35.13: Payments to Nominated Sub-contractors and Employer's right to make payment direct to Nominated Sub-Contractors and deduct from sums due to the Contractor, where Nominated Sub-Contractors are not paid by the Contractor. 2. Mobilisation (Advance) Payments Clause : If an advance payment is provided for, this is to be paid as stated in the Appendix and reimbursed as provided for in the Appendix (note bond). 4/1 Peter Aeberli November Unauthorised copying is illegal.
18 3. Bond in lieu of retention An alternative to retention is provided in JCT amendment, Optional clause 30.4A. This provides that the provisions relating to retention do not apply, subject to the Contractor providing a bond in lieu of retention in the stated form, the Employer. The amount of retention that would, otherwise, have been deducted must still be calculated and stated by the Architect or, if requested, the Quantity Surveyor. 4. The final payment Clause 30.6: Rules for adjusting the Contract Sum (a lump sum plus add and omits). Clause 30.8: The Final Certificate states the Contract Sum as adjusted and the total amount previously certified as due. The balance of these sums is payable by the Employer or the Contractor as the case may be. The procedure relating to the issue of the Final Certificate is as follows: - Clause 30.6: The Contractor provides documentation necessary for the adjustment of the Contract Sum including in respect of any Nominated Sub-Contractor/Supplier accounts, within 6 months of Practical Completion. Within 3 months of receipt of these documents the Architect/Quantity Surveyor ascertains the Contractor's loss and expense and the Quantity Surveyor prepares a statement of all adjustments to the Contract Sum, these being forwarded to the Contractor with relevant extracts to any Nominated Sub- Contractors. - Clause 30.7: The Architect issues an Interim Certificate (the last) not less than 28 days before issue of the Final Certificate showing gross valuation inclusive of the finally adjusted or ascertained sub-contract sums for Nominated Sub-Contractors. - Clause 30.8: The Architect issues the Final Certificate stating the adjusted Contract Sum, basis of calculation and the amounts previously certified, not later than 2 months after the end of the Defects Liability Period (see clause 17), the date of issue of the Certificate of Completion of Making Good Defects (see clause 7.4) or the date on which the Contractor is sent the Architect/Quantity Surveyor's ascertainment of its loss and expense and the Quantity Surveyor's statement of all adjustments to the Contract Sum, whichever is the latest. - Date of issue is the due date, final date for payment is 28 days from date of issue. Simple interest payable if payment late. - Not later than 5 days after date of issue, the Employer to issue a notice to the Contractor specifying the amounts proposed to be paid and basis of payment. - Any notice of withholding payment to be issued by the Employer not later than 5 days before the final date for payment. - Employer to pay the amount stated as due in the Final Certificate unless a notice specifying the amount proposed to be paid or notice of withholding payment issued. 5. Restrictions on payment Clause 30A and clause 31. Restrictions on payments where the Employer is a contractor for the purpose of the Corporation Taxes Act 1988, and the Income Tax (Sub-Contractors in the Construction Industry) Regulations 1993, as amended (the Construction Industry Scheme). No payments to be made in the absence of a valid Authorisation from the Contractor, as provided for 4/2 Peter Aeberli November Unauthorised copying is illegal.
19 in that legislation). SECTION E: RISKS AND SANCTIONS 1. Time risks Clause 25: The Contractor's entitlement to an extension to the Completion Date where delayed by on or more of the listed Relevant Events (neutral events, fault events, see clauses 25.4, 8.5, and 42.16). See also extensions of the period for completion of Nominated Sub- Contractor's work, clause The procedure for seeking and giving of extensions of time is as follows: - Clause 25.2: The Contractor is to notify the Architect forthwith in writing if it becomes reasonably apparent that the progress of the Works is, or is likely to be delayed, giving particulars, and copying that notice to any Nominated Sub-Contractor concerned. The contractor must update the Architect with further notices as necessary - Clause : If in the Architect's opinion the events relied on by the Contractor in its notice are Relevant Events (see clause 25.4; note catch all at clause , note also clause 42.16) and these are likely to delay the Completion date, the Architect must give the Contractor a fair and reasonable extension of time (using the net extension method) by fixing a new Completion Date, stating which relevant events and whether instructions omitting work have been taken into account. If the Architect does not consider an extension appropriate he must notify the Contractor of this, generally within 12 weeks of the Contractor's notice or not later than the Completion Date, if sooner. The Architect must also notify any Nominated Sub-Contractors of his decisions (see clause ). - Clause : The Architect can fix a completion date earlier than that previously fixed but not earlier than the Date for Completion (see clause ) or so as to shorten an agreed extension (see clause 13A) - Clause : If the Completion Date occurs before Practical Completion, the Architect may, but only within 12 weeks of Practical Completion, fix a later or an earlier Completion Date than that previously fixed, if in his opinion this is fair and reasonable or may confirm the Completion Date previously fixed, but may not fix a date earlier than the Date for Completion (see clause ) or so as to shorten an agreed extension (see clause 13A). The Architect must also notify any Nominated Sub-Contractors of his decisions (see clause ). - Clause 25.4: The Contractor must, nevertheless, use its best endeavours to prevent delay and to do all that may be reasonably required to the satisfaction of the Architect to proceed with the Works. Clause 24: Damages for non-completion by the Completion Date: - Clause 24.1: If the Works are not completed by the Completion Date the Architect issues a certificate to that effect: - Clause 24.2: Then the Employer may by writing, require the Contractor to pay or allow liquidated and ascertained damages at the rate stated in the Appendix for the period between the Completion Date and the date of Practical Completion and may deduct that amount from sums otherwise due to the Contractor, provided that sums to be deducted for the Final Certificate must be notified to the Contractor not later than 5 days before the final date for payment of the amount due under that Certificate. These rights are adjusted if a subsequent extension of time is granted. 4/3 Peter Aeberli November Unauthorised copying is illegal.
20 - These procedures will be ineffective if they are not operated correctly, if the rate stated in the Appendix is a penalty (a sum extravagant in amount compared to the greatest loss that could have resulted from the breach, a sum imposed to terrorise the Contractor into performing, rather than a genuine pre-estimate of the damages likely to be suffered) or if the contract machinery for fixing the Completion Date becomes inoperative. 2. Cost risks Clause 26: Adjusting the Contract Sum for direct loss and/or expense caused whether by postponement of possession or where the listed matters (fault events, see clause 26.2, and clauses 8.5, , and 42.16) materially affect the progress of the Works. The procedure for seeking and awarding loss and/or expense is as follows: - Clause 26.1: If upon the Contractor's written application, which must be made promptly (see clause ) and be particularised (see clauses and ), the Architect is of the opinion that the Contractor has or is likely to incur direct loss and/'or expense, for which it will not be reimbursed under any other provision of the Contract, as a result of possession of the site being deferred (clause ) or because regular progress of the Works or part of the Works has been or is likely to be materially affected by one of the listed matters (see clause 26.2; note catch all. at clause ) he must from time to time ascertain that loss and/or expense or instruct the Quantity Surveyor to do so; the ascertained amount being added to the Contract Sum (see clause 26.6). - Clause : The Contractor must pass to the Architect applications by Nominated Sub-Contractors to the Contractor for loss and expense where these concern matters for which the Employer is responsible, such applications being dealt with similarly to the Contractor's applications. - Clause 26.3: If necessary for the ascertainment of loss and/or expense, the Architect must advise the Contractor in writing of what extension of time he has granted in respect of those Relevant Events that are also matters under clause 26 (see also clause ). Clause 37: Adjusting the Contract Sum for price and tax changes (fluctuations). 3. Property in goods and materials Clause 16.1: Passing of property in unfixed materials and goods on site (note clause 19.4). Clause 16.2: Passing of property in materials and goods off site (note clauses 19.4 and 30.3). 4. Inadequate performance Clause 4.1.2: The Employer's power to engage others to carry out work at the Contractor's expense, where the Contractor fails to comply with an Architect's Instruction and with a subsequent written notice from the Architect requiring such compliance. Clause 8.3: The Architect's power to order the opening up for inspection and/or for testing of work. Clause 8.4: Removal of, or reduction of price to reflect defective work. The Architect's power to order further opening up for inspection and/or testing where work found to be defective (note Code of Practice and time and money consequences, clauses , ). 4/4 Peter Aeberli November Unauthorised copying is illegal.
21 Clause 30.9: Restrictions on the Contractor's liability following issue of the Final Certificate (note clause 30.10). 5. Sanctions for inadequate performance/insolvency Determination by the Employer (Contractor responsible) Clause 27.2: The Employer may, but not unreasonably or vexatiously (see clause ), determine the Contractor's employment where it commits a specified default (clause ). This right is dependent on strict compliance with the following procedure: - Clause : The Architect giving (see clause 27.1) the Contractor a notice specifying its defaults - Clause : The Contractor continuing a specified default for 14 days from receipt of the notice. Whereupon the Employer may, on or within 10 days from the expiry of that period, by further notice determine the employment of the Contractor - Clause : The Employer may also give notice determining the employment of the Contractor where the default is ended or the notice is not given, but a specified default is repeated. Clause 27.3: The Contractor's employment is determined automatically, subject to the possibility of reinstatement by agreement, if it is subject to certain of the listed insolvency events (see clause ). In the case of the other listed insolvency events (see clause ) it may be determined by the Employer (see clauses and ) by notice at any time. Clause 27.4: The Employer may determine the Contractor's employment where the Contractor takes or gives bribes. Clause 27.6: Rights of the parties following determination of the Contractor's employment under clause 27. The Contractor leaves site and no further sums are paid to the Contractor until the Works are completed by others, whereupon the Employer can deduct his losses from sums that would otherwise be due to the Contractor. The Employer may also have a common law action in damages for breach of contract. Note also the Employer s power, other than where an insolvency event`, to take over sub-contracts and supply contracts and pay sub-contractors and suppliers direct (deducing such payments from sums otherwise due to the Contractor) (Clause ). Clause 27.7: Deals with the situation where the Employer decides not to complete the Works following determination of the Contractor's employment under clause 27. Suspension by the Contractor for non payment of amounts due Clause : The Contractor s right to suspend for not payment of amounts due and not the subject of a notice of withholding payment, if default continues for 7 days of a contractor's notice of intention to suspend. The right to suspend ceases on payment being made. Determination by the Contractor (Employer responsible) Clause 28.2: The Contractor may, but not unreasonably or vexatiously (see clause ), determine the Contractor's employment where the Employer commits a specified default (clause ) or a specified suspension event occurs (clause ). This right is dependent on strict compliance with the following procedure: - Clause 28.2: The Contractor giving (see clause 28.1) the Employer a notice specifying the defaults or suspension event 4/5 Peter Aeberli November Unauthorised copying is illegal.
22 - Clause : The Employer continuing a specified default or the specified suspension event continuing for 14 days from receipt of the notice. Whereupon the Contractor may, on or within 10 days from the expiry of that period, by further notice determine the employment of the Contractor - Clause : The Contractor may also give notice determining the employment of the Contractor where the default is ended or the suspension event ceases, or the notice is not given, but a specified default or suspension event is repeated. Clause 28.3: The Contractor may determine the Contractor's employment if the Employer is subject to a listed insolvency event (see clause ); the Contractor's obligation to carry out and complete the Works being suspended meantime. Clause 28.4: Rights of the parties following determination of the Contractor's employment under clause 28. The Contractor leaves site and is entitled to payment for all work properly executed and for materials on site at that date. The ascertainment to be on the same basis as if the contract had not been determined. The Contractor is also entitled to compensation for removal costs, direct loss and/or damages due to the determination and for the cost of materials properly ordered. The Contractor may also have a common law action in damages for breach of contract. Determination by either party (suspension for neutral events) Clause 28A.1: Either party may, but not unreasonably or vexatiously (see clause 28A.1.3), determine the Contractor's employment where the Works are suspended for a continuous period longer than that stated in the Appendix, because of a specified event (clause 28A.1.1, but note clause 28A.1.2). This right is dependent on strict compliance with the following procedure: - Clause 28A.2: That party giving the other party a notice stating that unless the suspension is terminated within 7 days after receipt the employment of the Contractor will determine; determination occurring if the suspension is not terminated within this period Clause 28A.5: Rights of the parties following determination of the Contractor's employment under clause 28A (see also clause 28A.4). These rights are similar to those that apply where the Contractor determines its employment under clause Injury to persons or property Injury to persons or property other than the Works Clause 20.1: The Contractor's indemnity to the Employer in respect of injury or death to persons. Clause 20.2: The Contractor's indemnity to the Employer in respect of damage to property other than the Works during construction (see clause 20.2) and damage to property caused by the Specified Perils (see clause 22C.1) Clause 21.1: The Contractor's obligation to insure the clause 20 indemnities and provide evidence of insurance. Clause 21.2: The Contractor's obligation (optional) to take out joint names insurance against damage to property caused by collapse, vibration, etc. Injury to the Works Clause 22.1: There are three alternative regimes for insuring the risk of damage to the Works in the joint names of the parties (see clause 22.2 and 22.3), the insurance being required until Practical Completion (see clauses 22A.1, 22B.1, 22C.1 and 22C.2, see also clause ). - Clause 22A: Erection of new buildings, All Risks (see clause 22.2) insured by the 4/6 Peter Aeberli November Unauthorised copying is illegal.
23 Contractor. The Contractor bears the excess and has the risk of any insurance money shortfall (see clause 22A.4.5), other than in respect of uninsured losses due to the withdrawal of terrorism cover (see clause 22A.5). - Clause 22B: Erection of new buildings, All Risks (see clause 22.2) insured by the Employer. The Employer bears the excess and has the risk of insurance money shortfall (see clause 22B.3.5) including the risk of uninsured losses due to the withdrawal of terrorism cover (see clause 22B.4). - Clause 22C: Existing structures (Specified Perils, see clauses 1.3 and 22C.1) and Works in or extensions to existing structures (All Risks, see clause 22.2) insured by the Employer The Employer is entitled to determine the Contractor's employment if insured risk causes loss or damage affecting the work executed (see clause 22C.4). The Employer bears the excess and risk of any insurance money shortfall (see clause 22C.4.4) including the risk of uninsured losses due to the withdrawal of terrorism cover (see clause 22C.5, note also clause 22C.1). It may not always be possible to obtain such insurance on a joint names basis. Employer's loss of liquidated damages Clause 22D: The Contractor's obligation (optional) to insure the Employer for loss of his entitlement to liquidated damages in the event of the Contractor being entitled to an extension of time due to loss or damage to the Works, etc. caused by the Specified Perils (see clauses 1.3 and ). Joint Fire Code Clause 22FC: Optional procedures where the Joint Code of Practice on the Protection from Fire of Construction Sites and Buildings Undergoing Renovation applies. This is a Code of Practice promulgated by insurers to seek and minimise such risks. If applicable, both Employer and Contractor are required to comply with the Code. SECTION F: DISPUTE RESOLUTION Article 5: The Adjudication agreement. Article 7A: The Arbitration agreement. Article 7B: Litigation option. Clause 41A: Adjudication procedures, enforcement and effect on the parties (note clause 30.9 and the Adjudication Agreement, and special procedures where dispute concerns opening up of work, clause under 8.4.4, see clause 41A.5.8). See also the Adjudication Agreement (published separately). Clause 41B: Arbitration, procedures and powers (note clause 30.9). Clause 41C: Legal proceedings (see note on choice between arbitration and litigation). 4/7 Peter Aeberli November Unauthorised copying is illegal.
24 INTRODUCTORY GUIDE TO JCT CONTRACTS Peter Aeberli RIBA, ARIAS, FCIArb, Barrister Chartered Arbitrator, Adjudicator, Registered CEDR Mediator November 2002 SESSION 3(1): MW98: THE CONDITIONS SECTION A: THE PARTIES' PRIMARY OBLIGATIONS 1. What is to be provided? The Contractor's obligations as regards the Works: - Clause 1.1: The Contractor's primary obligation to carry out and complete the Works (see 1st Recital), the quality and standards to be achieved (both objective and subjective). The Contractor s obligation to comply with the Principal Contractor s Health and Safety Plan, if the full CDM Regulations are applicable. - Clause 1.4: The Contractor obligation, if the full CDM Regulations do not apply, to notify the Health and Safety Executive of the project before commencing the Works. - Clause 3.5: The Contractor s obligation to comply with written instructions from the Architect. - Clause 5.1: The Contractor's obligation to comply with the Statutory Requirements. - Clauses 5.7, 5.8, 5.9: The Contractor s obligations in, where appointed Principal Contractor, in respect of the CDM Regulations, and to provide information for the Health and Safety File. Architect s/employer's obligations as regards the Works: - Clause 1.2: The Architect's (as agent) obligation to provide information to the Contractor necessary for the proper carrying out of the Works, and to issue certificates and confirm instructions in writing. - Clause 3.5: The Architect s power to issue written instructions to the Contractor (see, for example, clauses 2.5(?), 3.4, 3.6, 3.7, 4,1, 5.1, 5.9(?), 6.3B), and obligation to confirm oral instructions in writing within 2 days. (Issuing a drawing is not issuing an instruction, what of site meeting minutes?) - Clause 3.7: The Architect s obligation to issue instructions for the expenditure of provisional sums. - Clause 4.1: The Architect s obligation to correct inconsistencies in or between the Contact Drawings, the Contract Specification and the schedules (note also clause 5.1). - Clause 5.6: The Employer s obligations in respect of the Planning Supervisor and, if the Contractor is not the Principal Contractor, the Principal Contractor. Contractor's obligations after completion of the Works: 3/1
25 - Clause 2.5: The Contractor's obligation to make good certain defects, shrinkages or faults in the works appearing within the specified period after practical completion (the defects liability period (not periods!)). 2. When? Implied obligations: - Implied obligations of the Contractor as regards materials, satisfactory quality, probably no fitness for purpose obligation, see Supply of Goods and Services Act 1982, Part I. - Implied obligation of the Employer not to hinder or prevent the Contractor from carrying out and completing the Works. - Implied obligation of the Employer not to not interfere with the exercise of discretion given to the Architect under the Contract (see also clause ). Clauses 1.1, 2.1: Diligently from the date of commencement to the date of completion. (possession cannot be deferred, see clauses 3.6, ), as extended, see clause 2.2. Clause 2.4: The Architect certifies the date of practical completion when in his opinion this is achieved. There is no provision enabling the Employer to take possession of part or parts of the Work before practical completion. Clause 2.5: The Architect certifies the date on which the Contractor has complied with his obligations to make good defects after practical completion (certificate of making good defects). 3. How much? Article 2: The lump sum stated (see clause 4.7). - This is payable for constructing the Contract, Drawings, Contract Specification and the schedule (see clause 4.1, note also clause 5.8). - It is adjustable (see clauses 3.6, 3.7, 4.1, 4.6 (Supplemental Condition A), 5.1(?). - If the Employer is a contractor, the statutory tax deduction scheme applies (see clause 5.3, Supplemental Condition C). - VAT is, if applicable, payable in addition (see Article 2, clause 5.2) SECTION B: ALTERING THE CONTRACTED FOR PERFORMANCE 1. The extent of the power ` Clause 3.6: The Architect's power to issue instructions varying the Works. Clause 3.7: Instructions concerning the expenditure of provisional sums. 2. The cost consequences Clause 3.6: Procedures for valuing the work content of variations and expended provisional sums (work content plus disruption costs). 3. The time consequences 3/2
26 Clause 2.2: Procedures for determining the time consequences. 4. Pre-agreeing the cost consequences Clause 3.6: The cost consequences can be agreed between the Architect and the Contractor prior to the Contractor carrying out the instruction. SECTION C: CONTROLLING AND MONITORING THE MANNER OF PERFORMANCE 1. Instructions to the Contractor Clause 3.5: The Architect s power to issue written instructions to the Contractor (see, for example, clauses 2.5, 3.4, 3.6, 3.7, 4,1, 5.1, 5.9(?), 6.3B), and obligation to confirm oral instructions in writing within 2 days (issuing a drawing is not issuing an instruction, what of site meeting minutes?). - Not all communications with the Contractor are instructions (see, for example, clauses 1.2, 2,2, 2.4, 3.2.1, 4.2.1, 7.2.1). - In certain, limited, situations the Employer communicates directly with the Contractor (see, for example, clauses 1.3, 2.3, 4.4.1, 4.4.2, , , 7.2.1). - The Planning Supervisor can also communicate with the Contractor (see clause 5.9). 2. Monitoring and controlling performance Clause 1.8: Third party rights excluded (see Contract (Rights of Third Parties) Act Clause 3.3: Contractor to have competent person on site. Clause 3.4: The Architect's power to exclude persons from the Works. Clause 3.1: Limits on rights of assignment. Clause 3.2: Limits on the Contractor's right to sub-contract (see also clause 3.2.2, payment protection for sub-contractors). SECTION D: VALUATION AND TIMING OF PAYMENTS 1. Progress payments Clauses 4.2, 4.4: The timing of and payment in respect of interim certificates. - Interim certificates stating amount to be paid, to what it relates and the basis on which it was calculated to be issued at intervals of 4 weeks calculated for the date for commencement (clause 4.2.1). - Date of issue is the due date. The final date for payment is 14 days from date of issue. Simple interest payable if payment late (see clause 4.2.2). - Not later than 5 days after date of issue, the Employer to issue a written notice to the Contractor specifying the amounts proposed to be paid (see clause 4.4.1). - Any notice of withholding payment to be issued by the Employer not later than 5 days 3/3
27 before the final date for payment (clause 4.4.2). - Employer to pay the amount stated as due in the certificate unless a notice specifying the amount proposed to be paid or notice of withholding payment issued (clause 4.4.3). Clause 4.2.1: Amounts to be included in interim certificates (all subject to retention). - Value of the Works properly executed including amounts ascertained or agreed in respect of variations and expended provisional sums. - Value of any materials and goods reasonably and properly brought on site for the purpose of the Works, provided adequately stored and projected against weather and other casualties (note property problems). From these amounts is deducted the retention (usually 5%) and the total due to the Contractor under previous interim certificates (each valuation based on measurement and value using, in practice, any pricing information in the Contract Documents, is always based on the total work completed, less previous valuations). 2. The penultimate certificate Clauses 4.3, 4.4: The timing of and payment in respect of the penultimate certificate. - The penultimate certificate stating amount to be paid, to what it relates and the basis on which it was calculated to be issued within 14 days after the date of practical completion. - Date of issue is the due date. The final date for payment is 14 days from date of issue. Simple interest payable if payment late (see clause 4.2.2). - Not later than 5 days after date of issue, the Employer to issue a written notice to the Contractor specifying the amounts proposed to be paid (see clause 4.4.1). - Any notice of withholding payment to be issued by the Employer not later than 5 days before the final date for payment (clause 4.4.2). - Employer to pay the amount stated as due in the certificate, unless a notice specifying the amount proposed to be paid or notice of withholding payment issued (clause 4.4.3). Clause 4.3: Amounts to be included in the penultimate certificate (all subject to half retention, usually 2.5%). - The total amount to be paid to the Contractor under this contract so far as that amount is ascertainable at the date of practical completion, including amounts ascertained or agreed in respect of variations and expended provisional sums. - This includes tax levy fluctuations, if applicable (see clause 4.6). From these amounts is deducted the total due to the Contractor under previous interim certificates (the clause appears envisage a calculation based on the Contract sum plus add and omits, not measurement and value). 3. The final certificate Clause 4.5: The final certificate states the amount remaining due to the Contractor or due to the Employer as the case may be. This clause also envisages as calculation based on the Contract sum plus add and omits, not measurement and value but finalised in the light of documentation 3/4
28 received from the Contractor. Even if the figures stay the same the Contractor will obtain release of the final portion of retention. Although not expressly stated, the certificate should also show the amounts previously certified as due to the Contractor, the difference being the amount remaining due. The procedure relating to the issue of the Final Certificate is as follows: - Clause : The Contractor provides documentation reasonably required for the computation of the amount to be certified within 3 months of Practical Completion. - Clause : Within 28 days of receipt of such documentation, and provided that the certificate of making good defects has been issued (clause 2.5), the Architect issues the final certificate showing the amount remaining due and stating to what the amount relates and the basis of which it was calculated. - Date of issue is the due date, final date for payment is 14 days from date of issue. Simple interest payable if payment late (Clauses , 4.5.2). - Not later than 5 days after date of issue, the Employer to issue a notice to the Contractor specifying the amounts proposed to be paid and basis of payment (clause ). - Any notice of withholding payment to be issued by the Employer not later than 5 days before the final date for payment (clause ). - Employer to pay the amount stated as due in the final certificate unless notice specifying amount proposed to be paid or notice of withholding payment is issued (clause ). The final certificate is not stated to be conclusive as to any matters. 4. Restrictions on payment Clause 4A, 5.3 and Supplemental Condition C. Restrictions on payments where the Employer is a contractor for the purpose of the Corporation Taxes Act 1988, and the Income Tax (Sub- Contractors in the Construction Industry) Regulations 1993, as amended (the Construction Industry Scheme). No payments to be made in the absence of a valid Authorisation from the Contractor, as provided for in that legislation). SECTION E: RISKS AND SANCTIONS 1. Time risks Clause 2.2: The Contractor's entitlement to an extension to the date for completion where delayed for reasons beyond its control including compliance with Architect s instructions whose issue is not due to a default of the Contractor. Reasons within in the control of the Contractor include default by the Contractor of those employed or engaged by him, or by any supplier. The procedure for seeking and giving of extensions of time is as follows: - The Contractor notifies the Architect in writing if it becomes apparent that the Works will not be completed by the existing date for completion because of such reasons. - Upon such notification the Architect's makes, in writing, a reasonable extension of time for completion of the Works (there is no power to reduce the period). Clause 2.3: Damages for non completion. If the Works are not completed by the date for completion (including any extension to it) the Employer may recover liquidated damages at the contract rate for the Contractor or deduct such damages from amounts due to the Contractor 3/5
29 under the Contract. In the latter case, the Employer must comply with provisions for giving notice of withholding payments, and, in the case of the final certificate give such a notice not later that the date of issue of that certificate. 2. Cost risks Clause 3.6: The Contractor is entitled to payment for direct loss and expense incurred due to the regular progress of the works being affected by compliance with an Architect s instruction varying the Works or, if applicable, where the Employer has failed to comply with its obligations in respect of the Planning Supervisor or Principal Contractor (see clause 5.6). Clause 4.6: Adjusting the Contract Sum for price and tax changes (fluctuations). If the Contractor suffers loss or damage through other defaults of the Employer, it remedy is by action for breach of contract. 3. Property in goods and materials The contract says nothing about the passing of property in goods or materials, the common law rules apply. 4. Inadequate performance Clause 3.5: The Employer's power to engage others to carry out work at the Contractor's expense, where the Contractor fails to comply with an Architect's instruction, despite a subsequent written notice from the Architect requiring compliance. Clauses 3.5, 3.6: The power to issue instructions is wide enough to enable the Architect to issue instructions concerning the opining up of work and the removal of defective work. The Contract is silent of the cost and time consequences of issuing such instructions. 5. Sanctions for inadequate performance/insolvency Determination by the Employer (Contractor responsible) Clause 7.2.1: The Employer may, but not unreasonably or vexatiously. determine the Contractor's employment where it makes default by failing to proceed diligently with the Works or by wholly or substantially suspending the carrying out of the Works before practical completion or by failing to comply with its contractual obligations as regard the CDM Regulations. This right is dependant on strict compliance with the following procedure (see also clause 7.1. for the manner of giving the required notices): - The Architect giving the Contractor a written notice specifying its default and requiring it to be ended. - The Contractor continuing the default for 7 days from receipt of the notice. - Whereupon the Employer may by further notice determine the employment of the Contractor, determination being effective on receipt of this further notice. Clause 7.2.2: If the Contractor commits a specified act of insolvency the Employer may by written notice determine the Contractor s employment under the Contract (see clause 7.1. for the manner of giving the required notices). Determination takes effect on the receipt of the notice. Clause 5.5: The Employer may cancel the Contract if the Contractor takes or gives bribes. Clause 7.2.3: Rights of the parties following determination of the Contractor's employment under 3/6
30 clause 7.2. The Contractor leaves site and no further sums are paid to the Contractor until the Works are completed by others, whereupon the Employer can deduct his losses from sums otherwise due to the Contractor. The Employer may also have a remedy for breach of contact at common law (see clause 7.2.4) Suspension by the Contractor for non payment of amounts due Clause 4.8: The Contractor s right to suspend performance of its obligations for not payment of amounts due and not the subject of a notice of withholding payment, if default continues for 7 days of a contractor's notice of intention to suspend. The right to suspend ceases on payment being made. Determination by the Contractor (Employer responsible) Clause 7.3.1: The Contractor may, but not unreasonably or vexatiously determine the Contractor's employment where the Employer commits one or more of the specified defaults (clauses 7.3.1, 7.3.2, 7.3.3, 7.3.4). This right is dependent on strict compliance with the following procedure (see clause 7.1. for the manner of giving the required notices): - The Contractor giving the Employer a written notice specifying the default and requiring it to be ended. - The Employer continuing the default for 7 days from receipt of the notice. Whereupon the Contractor may, on or within 10 days from the expiry of that period, by further notice determine the employment of the Contractor - Whereupon the Contractor may by further notice determine the employment of the Contractor, determination being effective on receipt of this further notice. Clause 7.3.2: If the Employer commits a specified act of insolvency the Contractor may by written notice determine the Contractor s employment under the Contract (see clause 7.1. for the manner of giving the required notices). Determination takes effect on the receipt of the notice. Clause 7.3.3: Rights of the parties following determination of the Contractor's employment by the Contractor. The Contractor leaves site and is entitled to payment for the total value of work properly executed and materials on site at that date. The payment to be ascertained on the same basis as if the contract had not been determined. The Contractor is also entitled to compensation for removal costs, direct loss and/or damages due to the determination. and the cost of materials properly ordered. The Contractor may also have a remedy in common law for breach of contract (see clause 7.3.4). 6. Injury to persons or property Injury to persons or property other than the Works Clause 6.1: The Contractor's indemnity to the Employer in respect of injury or death to persons. The Contractor s obligation to back this indemnity with insurance. Clause 6.2 The Contractor's indemnity to the Employer in respect of damage to property other than the Works or the existing structures which the Employer is required to insure (see clause 6.3B). The Contractor s obligation to back this indemnity with insurance. Injury to the Works Clause 6.3: There are two alternative regimes for insuring the risk of damage to the Works. In either case the insurance must be in the joint names of the parties (no subrogation) and is required until practical completion. Thereafter the Employer insures under his normal policies. - Clause 6.3A: Erection of new buildings. Insurance of the Works and unfixed materials and goods against the listed perils to be arranged by the Contractor. If the Works are 3/7
31 damaged by one of the listed perils the contractor is paid the insurance monies against certificates issued by the Architect. The Contractor bears the excess and has the risk of any insurance money shortfall. - Clause 6.3B: Alterations to existing structures. Insurance of the existing structures and of Works and unfixed materials and goods against the listed perils to be arranged by the Employer. If the Works are damaged by one of the listed perils they are reinstated on instruction by the Architect, these instructions being valued as variations. The Employer bears the excess and has the risk of any insurance money shortfall. Such insurance may be difficult to obtain. In either case it is best to operate a separate system of certification for the reinstated work. If the existing structures are destroyed the contract may be frustrated (but see clause ). Clause 6.4: The party arranging insurance to provide, if requested by the other party, evidence that the insurance is in force. SECTION F: DISPUTE RESOLUTION Article 6: The Adjudication agreement. See clause 8.1 and Supplemental Condition D (note also the separately published Adjudication Agreement). Article 7A: The Arbitration agreement. See clause 8.2 and Supplemental Condition E. Article 7B: Litigation option. See clause 8.3. Article 7C: If neither 7A nor 7B selected, 7A applies. 3/8
32 INTRODUCTORY GUIDE TO JCT CONTRACTS Peter Aeberli RIBA, ARIAS, FCIArb, Barrister Chartered Arbitrator, Adjudicator, Registered CEDR Mediator November 2002 SESSION 3(2): IFC 98: THE CONDITIONS: PART I SECTION A: THE PARTIES' PRIMARY OBLIGATIONS 1. What is to be provided? The Contractor's obligations as regards the Works: - Clauses 1.1 and 1.2: The Contractor's primary obligation to carry out and complete the Works as varied (see article 1 and 1 st recital, clauses 3.6, 3.8). The quality and standards to be achieved (both objective and subjective, see also clause 4.7.1). - Clause 5.1: The Contractor's obligation to comply with the Statutory Requirements (but note clauses 5.2, 5.3 and 5.4). - Clause : The Contractor's obligations, where appointed Principal Contractor, as regards the CDM Regulations and the Health and Safety Plan, and, whether or not appointed Principal Contractor, to provide information for the health and safety file. - Clause 3.3.7: Limitation on the Contractor's liability in respect of Named Sub- Contractor's Work (principally concerning design) Architect s/employer's obligations as regards the Works: - Clause 1.4: The Architect s obligation (as agent) to correct inconstancies, etc. in or between the Contract Documents. - Clauses 1.7.1, 1.7.2: The Architect's (as agent) obligation to provide information to the Contractor in accordance with the Information Release Schedule, otherwise where reasonably necessary to explain and amplify the Contract Drawings, and to issue instructions to enable the Contractor to carry out its obligations. - Clause 3.9: The Architect's (as agent) obligation to provide levels. - Clause 5.7.1: The Employer s obligations to ensure that the duties of the Planning Supervisor and the Principal Contractor (where not the Contractor) are carried out. Contractor's obligations after completion of the Works: - Clause 2.10: The Contractor's obligation to make good certain defects, shrinkages or faults in the works appearing not later that 14 days after the expiry of the Defects Liability Period (one period). Implied obligations: 3/1 Peter Aeberli November Unauthorised copying is illegal.
33 - Implied obligations of the Contractor as regards materials, satisfactory quality, probably no fitness for purpose obligation, see Supply of Goods and Services Act 1982, Part I. 2. When? - Implied obligation of the Employer not to hinder or prevent the Contractor from carrying out and completing the Works. Clause 2.1: Regularly and diligently from the Date of Possession (note limited, optional, power of the Employer to defer giving possession, clause 2.2) to the Completion Date as extended, if at all, under clause 2.3. Clause 2.6: If the Contractor fails to complete by the Completion Date the Architect issues a certificate to that effect. Clause 2.9: The Architect certifies the date of Practical Completion when, in his opinion, this is achieved and the Contractor has provided information reasonably required by the Planning Supervisor for the preparation of the health and safety file (see clause 5.7.4). Note the Contractor's limited obligations thereafter (see clause 2.10); the architect issuing a certificate when these have been discharged. Clause 2.11: With the Contractor's consent, the Employer can take possession of part or parts of the Work before Practical Completion, Practical Completion of such parts, and its consequences, occurring when taken over. If phased completion is required the Sectional Completion Supplement should be used. 3. How much? Article 2 : The Contract Sum. - This is payable for constructing either the Contract Bills (recital 2A, clause 1.2), or the Contract Documents, taken together (recital 2B, clause 1.2, but note hierarchy between Drawings and Specification/Schedules), see also clause It is adjustable (see clauses 3.7 (options A and B), 4.5, 4.11). - It is exclusive of VAT, see clause 5.5. SECTION B: ALTERING THE CONTRACTED FOR PERFORMANCE 1. The extent of the power ` Clause 3.6: The Architect's power to issue instructions varying the Works and certain obligations or restrictions concerning the manner of working (see also deemed variations under clauses 1.4, 3.3.1, 5.4.3, 6.3B.3.5 and 6.3C.4.5). Clause 3.8: The Architect's obligation (as agent) to issue instructions concerning the expenditure of provisional sums. See also, work executed for which an Approximate Quantity is included in the Contract Documents. (note SMM7 and footnote to clause 8.3) Clause 3.15: The Architect s power to issue instructions regarding the postponement of work to be executed under the Contract (but note clause 2.2). 2. The cost consequences 3/2 Peter Aeberli November Unauthorised copying is illegal.
34 Clause 3.7: Procedures for valuing the work content of variations. There are two options, Option A (contractor s price statement), Option B (valuation in accordance with the valuation rules). The latter applies if the contractor does not implement Option A. Clause 4.11: Procedures for determining the disruption costs of variations (note clauses , , and position where clause 3.7, Option A applies). 3. The time consequences Clause 2.3: Procedures for determining the time consequences (note clause and position where clause 3.7, Option A applies). SECTION C: CONTROLLING AND MONITORING THE MANNER OF PERFORMANCE 1. Instructions to the Contractor Clause 3.5.1: The Contractor's obligation to comply with instructions of the Architect expressly empowered by the Conditions (note clause 3.5.2), other than those concerning changes to working methods (see clause 3.6.2) to which reasonable objection is taken. - Clauses empowering instructions include 1.4, 1.7.2, 2.10, 3.3.1, 3.3.2, 3.3.3, 3.6, 3.9, 3.12, 3.14, 3.15, 5.2(?)). - Not all communications between the Architect and Contractor are instructions (see, for example, clauses 1.6, 1.7, 1.10, 2.3, 2.6, 2.9, 2.11, 3.9, 4.2, 4.3, 4.6, 4.11, 6.3D.1) - In certain, limited, situations the Employer communicates directly with the Contractor (see, for example, clauses 2.2(?), 7.2.2, 7.3.4), as does the Quantity Surveyor (see for example clause 3.7 (Option A) and the Planning Supervisor (see for example clause 5.7.4). Instructions are of no effect unless given by the Architect in writing, see clause (see also clause 3.10, limited status of the Clerk of Works). Clause 3.5.2: The Contractor may, upon receipt of a purported instruction require the Architect to specify the provision of the Conditions which empowers the issue of that instruction. The instruction being deemed to have been issued under the notified provision unless either party, before compliance, invokes the contract dispute procedures. 2. Miscellaneous management procedures Clause 1.6: Custody of Contract Documents (note also clause 1.8, limits on their use) and provision of copies to the Contractor. Clause 1.9: Distribution of Architect's Certificates. Clause 3.4: Contractor's person in charge and authority to receive instructions and directions. 3. Monitoring performance Clause 3.10: A Clerk of Works may be appointed as inspector on behalf of the Employer. 4. Controlling who performs and who is entitled to performance 3/3 Peter Aeberli November Unauthorised copying is illegal.
35 Clause 1.17: Third party rights excluded (see Contract (Rights of Third Parties) Act Clause 3.1: Limits on rights of assignment. Clause 3.2: Limits on the Contractor's right to sub-contract (note terms of sub-contracts imposed by clauses 3.2.1, and 3.2.3, and the standard form of sub-contract agreement IN/SC). Clause 3.11: Work carried out by persons engaged by the Employer (note the insurance regime for such work). Clause 3.3: Procedures for naming and, if necessary, re-naming Sub-contractors. Note the limited circumstances in which naming is possible (clause 3.3.1, linking with the 1 st recital, and clause 3.3.2, linking with the expenditure of provisional sums, clause 3.8). 3/4 Peter Aeberli November Unauthorised copying is illegal.
36 INTRODUCTORY GUIDE TO JCT CONTRACTS Peter Aeberli RIBA, ARIAS, FCIArb, Barrister Chartered Arbitrator, Adjudicator, Registered CEDR Mediator November 2002 SESSION 4(2): IFC 98: THE CONDITIONS: PART 2 SECTION D: VALUATION AND TIMING OF PAYMENTS 1. Interim payments Clauses 4.2(a) and 4.2.3: The timing of and payment in respect of Interim certificates (subject to any agreement as to stage payments). - Interim Certificates stating amount to be paid and the basis of payment to be issued at the periods stated in the Appendix (monthly unless otherwise stated). - Date of issue is the due date, final date for payment is 14 days from date of issue. Simple interest payable if payment late. - Not later than 5 days after date of issue, the Employer to issue a notice to the Contractor specifying the amounts proposed to be paid and basis of payment. - Any notice of withholding payment to be issued by the Employer not later than 5 days before the final date for payment. - Employer to pay the amount of Interim Certificate unless a notice specifying the amount proposed to be paid or notice of withholding payment issued, with interest if paid after the final date for payment. Clause 4.2(c): Interim valuations to be made by the Quantity Surveyor whenever the Architect considers them necessary for the purpose of ascertaining the amount of an interim payment, but the Contractor may submit applications setting out what it considers to be the amount of the valuation. Clauses 4.2(d), and 4.2.2: Amounts to be included in Interim Certificates (gross valuation, principally based on work properly completed (calculated by reference to the Contractor's Priced Activity Schedule, if attached) less 5% Retention, less total previous certified). - Clause 4.2.1: Amounts subject to retention comprise work properly executed, as adjusted for fluctuations, if any, materials and goods reasonably and properly delivered to site, and in the case of listed items, materials and goods off site. - Clause 4.2.2: Amounts not subject to retention, principally insurance premiums, fluctuations, loss and expense, and works concerning the restoration of insured damage. - Clause 4.2.1: The value of off-site materials and goods to be included where listed in the Contract Documents, provided the conditions in this clause fulfilled (note bond). Clause 4.4 (not applicable to Local Authorities): The Employer s interest in the retention to be 1998 Peter Aeberli
37 fiduciary as trustee for the Contractor, with a right of recourse for payment of amounts he is entitled to withhold or deduct from amounts due to the Contractor. 2. Mobilisation Payments Clause 4.2(b) (Not applicable to Local Authorities): If a advance payment is provided for, this is to be paid as stated in the Appendix and reimbursed as provided for in the Appendix (note bond). 3. Interim Payment on Practical Completion Clause 4.3: The timing of and payment in respect of the penultimate certificate. - A penultimate certificate stating amount to be paid, to what it relates and the basis on which it was calculated to be issued within 14 days after the date of Practical Completion (clause 4.3(a)). - Date of issue is the due date. The final date for payment is 14 days from date of issue. Simple interest payable if payment late (clause 4.3(e), see also clause 4.2(a)). - Not later than 5 days after date of issue, the Employer to issue a written notice to the Contractor specifying the amounts proposed to be paid (see clause 4.3(b)). - Any notice of withholding payment to be issued by the Employer not later than 5 days before the final date for payment (clause 4.3(c)). - Employer to pay the amount stated as due in the certificate, unless a notice specifying the amount proposed to be paid or a notice of withholding payment issued (clause 4.3(d)). Clause 4.3(a): Amounts to be included in the penultimate certificate to be assessed on the same basis as interim certificates, with retention on those amounts subject to retention reduced to 2.5%. From these amounts is deducted the total due to the Contractor under previous interim certificates. 4. The final payment Clause 4.5: Rules for adjusting the Contract Sum (a lump sum plus add and omits). Clause : The Final Certificate states the Contract Sum as adjusted and the total amount previously certified as due, the balance being payable by the Employer or the Contractor as the case may be. The procedure relating to the issue of the Final Certificate is as follows: - Clause 4.5: The Contractor provides documentation necessary for the adjustment of the Contract Sum within 6 months of Practical Completion. - Clause 4.5: Within 3 months of receipt of these documents the Architect/Quantity Surveyor prepares a statement of final valuations for variations, and sends a copy of this, and the computations relating to all other adjustments to the Contract Sum, to the Contractor. - Clause : The Architect issues the Final Certificate stating the adjusted Contract Sum, the basis of calculation and the amounts previously certified. This to be issued not later than 28 days after the date on which the Contractor is sent the Architect/Quantity Surveyor's statement of final valuations for variations and computations relating to all 1998 Peter Aeberli
38 other adjustments to the Contract Sum or, if later, of issue of the Certificate of Completion of Making Good Defects (see clause 2.10). - Date of issue is the due date, final date for payment is 28 days from date of issue (clauses (?), ). Simple interest payable if payment late (clause 4.6.2). - Not later than 5 days after date of issue, the Employer to issue a notice to the Contractor specifying the amounts proposed to be paid and basis of payment (clause ). - Any notice of withholding payment to be issued by the Employer not later than 5 days before the final date for payment (clause ). - The Employer to pay the amount stated as due in the Final Certificate unless a notice specifying the amount proposed to be paid or a notice of withholding payment issued (clause ), with interest if paid after the final date for payment. 5. VAT Clause 5.5: VAT to be paid on certified sums, where properly chargeable (see Supplemental Condition A). If condition A1.1 applies, certificates show the VAT payable. If not, the matter is dealt with between the Contractor and the Employer. 6. Restrictions on payment Clause 4A, 5.6 and Supplemental Condition B. Restrictions on payments where the Employer is a contractor for the purpose of the Corporation Taxes Act 1988, and the Income Tax (Sub- Contractors in the Construction Industry) Regulations 1993, as amended (the Construction Industry Scheme). No payments to be made in the absence of a valid Authorisation from the Contractor, as provided for in that legislation). SECTION E: RISKS AND SANCTIONS 1. Time risks Clause 2.3: The Contractor's entitlement to an extension to the Date for Completion where delayed by on or more of the listed Relevant Events (neutral events, fault events, see clause 2.4). The procedure for seeking and giving of extensions of time is as follows: - Clause 2.3: The Contractor is to notify the Architect forthwith in writing if it becomes reasonably apparent that the progress of the Works is, or is likely to be delayed, stating the cause of the delay. The Contractor must also provide information reasonably required by the Architect for the purposes of this clause. - Clause 2.3 (see also clause 2.5): If in the Architect's opinion any causes of delay relied on by the Contractor in its notice are relevant events (see clause 2.4; note catch all, clause ) and these are likely to delay the Date for Completion, including any previous extensions to that date, the Architect must give the Contractor a fair and reasonable extension of time (using the net extension method). Where the cause of delay occurs after the date for Completion, including any extension to that date, a more restricted list of relevant events applies (excluding the neutral events). Note also the relationship of this provision with clause 3.7 (Option A). - Clause 2.3: The Architect may also, up to 12 weeks after Practical Completion, may make an extension of time under this clause whether on reviewing an earlier extension, or otherwise, and whether on not the Contractor has given the requisite notice of delay Peter Aeberli
39 - Clause 2.3: The Contractor must, nevertheless, use its best endeavours to prevent delay and to do all that may be reasonably required to the satisfaction of the Architect to proceed with the Works. Clauses 2.6, 2.7, 2.8: Damages for non-completion by the Date for Completion. - Clause 2.6: If the Works are not completed by the Date for Completion, including any extension to that date, the Architect issues a certificate to that effect, the certificate being cancelled in the event of a subsequent extension of time. - Clause 2.7: Provided such a certificate is issued, and the employer has informed the Contractor in writing before the date of the final certificate that he may seek or deduct liquidated and ascertained damages ( LADs ), the Employer may, not later than 5 days before the final date for payment of the debt due under the final certificate, either require the Contractor to pay the LADs due, or give a notice of withholding payment in respect of those LADs. - These procedures will be ineffective if they are not operated correctly, if the rate stated in the Appendix is a penalty (a sum extravagant in amount compared to the greatest loss that could have resulted from the breach, a sum imposed to terrorise the Contractor into performing, rather than a genuine pre-estimate of the damages likely to be suffered) or if the contract machinery for extending the Completion Date becomes inoperative. 2. Cost risks Clauses 4.11 and 4.12: Adjusting the Contract Sum for direct loss and/or expense caused whether by postponement of possession or where the listed matters (fault events only, see clause 4.12) materially affect the regular progress of the Works. The procedure for seeking and awarding loss and/or expense is as follows: - Clause 4.11: If upon the Contractor's written application, which must be made promptly, the Architect is of the opinion that the Contractor has or is likely to incur direct loss and/'or expense, for which it will not be reimbursed under any other provision of the Contract, as a result of possession of the site being deferred (clause 4.11(a)) or because regular progress of the Works or part of the Works has been or is likely to be materially affected by one of the listed matters (clause 4.11(b), see clause 4.12; note catch all, clause ) he must ascertain that loss and/or expense or instruct the Quantity Surveyor to do so; the ascertained amount being payable under interim certificates (see clause 4.2.2) and added to the Contract Sum (see clause 4.5). - Clause 4.11: The awarding of loss and expense is subject to the proviso that the Contractor shall provide such information required by the Architect, or Quantity Surveyor, as is reasonably necessary for the purposes of this clause. - Clause 4.11: The entitlement to loss and expense is without prejudice to any other rights or remedies the Contractor may possess. Clause 4.9: Adjusting the Contract Sum for price and tax changes (fluctuations). There are two options, tax fluctuations and formula fluctuations, see Supplemental Conditions C and D. 3. Property in goods and materials Clause 1.10: Passing of property in unfixed materials and goods on site to the Employer on payment (note clauses and 4.2.1(b)) Peter Aeberli
40 Clause 1.11: Passing of property in materials and goods off site to the Employer on payment (note also clauses and 4.2.1(c)). 4. Inadequate performance Clause 3.5.1: The Employer's power to engage others to carry out work at the Contractor's expense, where the Contractor fails to comply with an Architect's Instruction and with a subsequent written notice from the Architect requiring such compliance. Clause 3.12: The Architect's power to order the opening up for inspection and/or for testing of work, materials of goods. The cost to be added to the Contract Sum unless allowed for the Contract or the test or inspection shows that the work, materials or goods are not in accordance with the Contract. Clause 3.13: Where defective work, materials or goods are discovered, the Contractor to advise on what action it proposes to take, at no cost to the Employer, to establish that there are no similar failures in the work. If no such advice is given, or the Architect does not accept it, the Architect may instruct the Contractor as to what measures to take. If the Contractor objects to such an instruction, the matter is referred to the contractual dispute resolution procedures and, if the Architect s instruction is found not to be fair and reasonable, the cost and time consequences of compliance fall to the Employer (see clauses and ). Clause 3.14: The Architect s power to order the removal of defective work, materials and goods. Clause 4.7: Restrictions on the Contractor's liability following issue of the Final Certificate, except in respect of matters referred to the contractual dispute resolution procedures within the stipulated periods. No other certificates are conclusive (see clause 4.8). 5. Sanctions for inadequate performance/insolvency Determination by the Employer (Contractor responsible) Clause 7.2: The Employer may, but not unreasonably or vexatiously (see clause 7.2.4), determine the Contractor's employment where it commits a specified default (clauses 7.2.1(a)- (e)). This right is dependent on strict compliance with the following procedure (see also the procedures for giving notices in clause 7.1): - Clause 7.2.1: The Architect giving the Contractor a written notice specifying its defaults - Clause 7.2.2: The Contractor continuing a specified default for 14 days from receipt of the notice. Whereupon the Employer may, on or within 10 days from the expiry of that period, by further notice determine the employment of the Contractor - Clause 7.2.3: If a specified default is ended within the relevant period or a notice of determination is not given, but is repeated, the Employer may upon or within a reasonable time of that repetition give notice determining the employment of the Contractor. Clause 7.3: The Contractor's employment is determined automatically, subject to the possibility of reinstatement by agreement, if it is subject to certain of the listed insolvency events (see clause 7.3.3). In the case of the other listed insolvency events (see clause 7.3.1) it may be determined by the Employer (see clause 7.3.4) by notice at any time. See also the special procedures that govern payment, and the execution of further work (in the latter case see clause 7.5). Clause 7.4: The Employer may determine the Contractor's employment where the Contractor 1998 Peter Aeberli
41 takes or gives bribes. Clause 7.6: Rights of the parties following determination of the Contractor's employment under clause 7.2 to 7.4. The Contractor leaves site and no further sums are paid to the Contractor until the Works are completed by others, whereupon the Employer can deduct his losses from sums that would otherwise be due to the Contractor. The Employer may also have a common law action in damages for breach of contract (see clause 7.8). Clause 7.7: Deals with the situation where the Employer decides not to complete the Works following determination of the Contractor's employment under clause 27. Suspension by the Contractor for non payment of amounts due Clause 4.4A: The Contractor s right to suspend for not payment of amounts due and not subject of a notice of withholding, if default continues for 7 days of a contractor's notice of intention to suspend. The right to suspend ceases on payment being made. Determination by the Contractor (Employer responsible) Clause 7.9: The Contractor may, but not unreasonably or vexatiously (see clause 7.9.5), determine the Contractor's employment where the Employer commits a specified default (clauses 7.9.1(a)-(d)) or (clause 7.9.2) a specified event occurs, which causes the whole or substantially the whole of the works to be suspended for a continuous period of a month. This right is dependent on strict compliance with the following procedure. See also the requirements for giving notices in clause Clauses 7.9.1, 7.9.2: The Contractor giving the Employer a notice specifying the defaults or suspension event. - Clause 7.9.3: The Employer continuing a specified default or the specified suspension event continuing for 14 days from receipt of the notice. Whereupon the Contractor may, on or within 10 days from the expiry of that period, by further notice determine the employment of the Contractor. - Clause 7.9.4: The Contractor may also give notice determining the employment of the Contractor where the default is ended or the suspension event ceases, or the notice is not given, but a specified default or suspension event is repeated. Clause 7.10: The Contractor may determine the Contractor's employment if the Employer is subject to a listed insolvency event (see clause ); the Contractor's obligation to carry out and complete the Works being suspended meantime. Clause 7.11: Rights of the parties following determination of the Contractor's employment under clauses 7.9 or The Contractor leaves site and is entitled to payment for all work properly executed and for materials on site at that date. The ascertainment to be on the same basis as if the Contractor s employment had not been determined. The Contractor is also entitled to compensation for removal costs, direct loss and/or damages due to the determination and for the cost of materials properly ordered. The Contractor may also have a common law action in damages for breach of contract (see clause 7.12). Determination by either party (suspension for neutral events) Clause 7.13: Either party may, but not unreasonably or vexatiously (see clause ), determine the Contractor's employment where the Works are suspended for a continuous period longer than one or three months (depending of the event) because of a specified event (clauses (a)-(f)). But note clause restricting the Contractor s power to exercise this right. This right is dependent on strict compliance with the following procedure: - Clause : That party giving the other party a notice stating that unless the 1998 Peter Aeberli
42 suspension is terminated within 7 days after receipt the employment of the Contractor will determine; determination occurring if the suspension is not terminated within this period Clauses : Rights of the parties following determination of the Contractor's employment under clause These rights are similar to those that apply where the Contractor determines its employment under clause 7.9 or Injury to persons or property Injury to persons or property other than the Works Clause 6.1.1: The Contractor's indemnity to the Employer in respect of injury or death to persons. Clause 6.1.2: The Contractor's indemnity to the Employer in respect of damage to property other than the Works during construction (see clause 6.1.3) and damage to property caused by the Specified Perils, where clause 6.3C.1 applies (works to existing structures, Employer insures). Clauses and 6.2.2: The Contractor's obligation to insure the clause 6.1 indemnities and provide evidence of insurance. Note the Employer s right to take out the necessary insurance, at the Contractor s expense, if the Contractor fails to do so (clause 6.2.3). Clause 6.2.4: The Contractor's obligation (optional) to take out joint names insurance against damage to property caused by collapse, vibration, etc. Clause 6.2.5: The above provisions do not apply to the Excepted Risks (nuclear incidents and pressure waves from aircraft). Injury to the Works Clause 6.3.1: There are three alternative regimes for insuring the risk of damage to the Works in the joint names of the parties (see clauses and 6.3.3), and with a waiver of subrogation rights against named sub-contractors (see clause 6.3.3) the insurance being required until Practical Completion (see clauses 6.3A.1, 6.3B.1, 6.3C.1 and 6.3C.2, see also clause 2.11, where partial possession occurs.). - Clause 6.3A: Erection of new buildings, All Risks (see clause 6.3.2) insured by the Contractor. The Contractor bears the excess and has the risk of any insurance money shortfall (see clause 6.3A.4.5). - Clause 6.3B: Erection of new buildings, All Risks (see clause 6.3.2) insured by the Employer. The Employer bears the excess and has the risk of insurance money shortfall (see clause 6.3B.3.5). - Clause 6.3C: Existing structures (Specified Perils, see clauses 8.3 and 6.3C.1) and Works in or extensions to existing structures (All Risks, see clause 6.3.2) insured by the Employer The Employer is entitled to determine the Contractor's employment if an insured risk occurs causing loss or damage affecting the work executed (see clause 6.3C.4.4). The Employer bears the excess and has the risk of any insurance money shortfall (see clause 6.3C.4.5). In practice, such joint names insurance may be difficult to obtain. Employer's loss of liquidated damages Clause 6.3D: The Contractor's obligation (optional) to insure the Employer for loss of his entitlement to liquidated damages in the event of the Contractor being entitled to an extension of time due to loss or damage to the Works, etc. caused by the Specified Perils (see clauses 8.3 and 2.4.3) Peter Aeberli
43 Joint Fire Code Clause 6.3FC: Optional procedures where the Joint Code of Practice on the Protection from Fire of Construction Sites and Buildings Undergoing Renovation applies. This is a Code of Practice promulgated by insurers to minimise such risks. If applicable, both Employer and Contractor are required to comply with the Code. SECTION F: DISPUTE RESOLUTION Article 8: The Adjudication agreement. Article 9A: The Arbitration agreement. Article 9B: Litigation option. Clause 9A: Adjudication procedures, enforcement and effect on the parties (note clause 4.7, and special procedures where dispute concerns opening up of work, clause under 8.4.4, see clause 9A5.8). See also the Adjudication Agreement (published separately). Clause 9B: Arbitration, procedures and powers (note clause 4.7). Clause 9C: Legal proceedings (see separately published note on choice between arbitration and litigation) Peter Aeberli
JCT Standard Building Contract 2011 - SBC/Q
JCT Standard Building Contract 2011 - SBC/Q Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: [email protected] www.rpp.co.uk Delivering Professional Solutions to the Property Industry
A JCT 2011 Minor Works Building Contract
A JCT 2011 Minor Works Building Contract A20 JCT MINOR WORK BUILDING CONTRACT (MW) Minor works transparency document Rev A A20 / A20 JCT MINOR WORK BUILDING CONTRACT (MW) JCT MINOR WORKS BUILDING CONTRACT
A Guide to Standard forms of Construction Contract Outlining Key Characteristics and Components
Produced for SCALA and the Local Government Task Force by Rob Tate Dip Arch. Dip TP. Dip Arb. FCIArb. RIBA 01582 516662 [email protected] You can contact the Local Government Task Force tel 020 7837
Terms and Conditions of Offer and Contract (Works & Services) Conditions of Offer
Conditions of Offer A1 The offer documents comprise the offer form, letter of invitation to offer (if any), these Conditions of Offer and Conditions of Contract (Works & Services), the Working with Queensland
CONTRACT CONDITIONS FOR LOGISTICS (2014)
CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector
TT ELECTRONICS INTEGRATED MANUFACTURING SERVICES LIMITED CONDITIONS OF PURCHASE
TT ELECTRONICS INTEGRATED MANUFACTURING SERVICES LIMITED CONDITIONS OF PURCHASE DEFINITIONS In these conditions of purchase: the Buyer means TT electronics integrated manufacturing services Ltd., the Supplier
Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement
Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the
PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED
DATED DAY OF 2015 PERSONAL ALERT SYSTEMS REBATE SCHEME PROVIDER PANER DEED between MINISTER FOR COMMUNITIES AND SOCIAL INCLUSION - and - [INSERT PARTY NAME] ACN [INSERT] Page 1 of 1 TABLE OF CONTENTS BACKGROUND...
Nominated Subcontractors on International Projects: Approaches to Risk Allocation
Nominated Subcontractors on International Projects: Approaches to Risk Allocation September 5, 2005 (he following outline was used in a presentation to the Overseas Construction Association of Japan, Inc.
PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS
PUBLIC SECTOR STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION WORKS 2014 Public Sector Standard Conditions of Contract for Construction Works 2014 Building and Construction Authority First published 1995
JRI S STANDARD TERMS OF PURCHASE. Business Day: a day (other than a Saturday, Sunday or public holiday) when banks in London are open for business.
JRI S STANDARD TERMS OF PURCHASE 1. INTERPRETATION 1.1 Definitions. In these Conditions, the following definitions apply: Business Day: a day (other than a Saturday, Sunday or public holiday) when banks
ENERGY PERFORMANCE CONTRACT
DATED DAY OF ENERGY PERFORMANCE CONTRACT THE CUSTOMER SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT -AND- THE ESCO SPECIFIED IN THE FORMAL INSTRUMENT OF AGREEMENT [This document is a DRAFT provided only
Standard conditions of purchase
Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out
Dated 29 February 2016. Flood Re Limited. Payments Dispute Process. Version 1.0
Dated 29 February 2016 Flood Re Limited Payments Dispute Process Version 1.0 1. General 1.1 The following provisions will apply to all disputes referred to and conducted under this Payments Dispute Resolution
The amount to be included in any such application shall be the amount due to the Sub-Contractor from Cardy which shall be:
Page 1 of 9 1. Initial Works/ Letter of intent (1) Until such time as the Principal Contract has been signed or executed (notification of which will be provided by Cardy to the Sub-Contractor), Cardy will
Standard Conditions of Appointment. Architect s Copy ONLINE VERSION ONLINE VERSION ONLINE VERSION. for an Architect (CA-S-07-A)
Standard Conditions of Appointment for an Architect (CA-S-07-A) Architect s Copy Royal Institute of British Architects RIBA Agreements are produced in association with: the Royal Incorporation of Architects
GOVERNMENT OF MALAYSIA STANDARD FORM OF DESIGN & BUILD / TURNKEY CONTRACT (PWD FORM DB/T)
GOVERNMENT OF MALAYSIA STANDARD FORM OF DESIGN & BUILD / TURNKEY CONTRACT (PWD FORM DB/T) CONDITIONS OF CONTRACT FOR DESIGN & BUILD AND TURNKEY PROJECTS (PWD FORM DB/T) This form has been approved by Attorney
LEAD PROVIDER FRAMEWORK CALL OFF TERMS AND CONDITIONS
LEAD PROVIDER FRAMEWORK CALL OFF TERMS AND CONDITIONS 1 LEAD PROVIDER FRAMEWORK - CALL OFF TERMS AND CONDITIONS - SUMMARY Where an Order Form is issued by the Authority that refers to the Framework Agreement,
DATED 2016 [SURETY] and [CONTRACTOR] and SCHOOL OF ORIENTAL AND AFRICAN STUDIES PERFORMANCE BOND
DATED 2016 [SURETY] (1) and [CONTRACTOR] (2) and SCHOOL OF ORIENTAL AND AFRICAN STUDIES (3) PERFORMANCE BOND relating to NEC3 OPTION A TERM SERVICE CONTRACT FOR INTEGRATED FACILITIES MANAGEMENT SERVICES
BUILDING CONTRACT MEMORANDUM OF AGREEMENT AND CONDITIONS OF CONTRACT
BUILDING CONTRACT MEMORANDUM OF AGREEMENT AND CONDITIONS OF CONTRACT MADE and entered into by and between: (hereinafter referred to as the OWNER); and (hereinafter referred to as the BUILDER) WHEREAS the
This document must be read in conjunction with Beacon Consulting s Fee Proposal. Together they form the Rules and Conditions of Service Delivery.
This document must be read in conjunction with Beacon Consulting s Fee Proposal. Together they form the Rules and Conditions of Service Delivery. CONTENTS CLAUSES Page 1. Services 1 2. Client s Undertakings
Hong Kong Institute of Surveyors. Seminar on Conditions of Building Contract Questions and Answers Conducted by Mr. Colin B. Lee
Hong Kong Institute of Surveyors Seminar on Conditions of Building Contract Questions and Answers Conducted by Mr. Colin B. Lee 8/F, Tung Chiu Commercial Central 193 Lockhard Road, Wanchai Hong Kong 13
The New Standard Construction Contracts: NZS3910, 3916 and 3917
The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of
The RIAI Standard Form of Contract 2012 Edition: a Review
Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2013-1 The RIAI Standard Form of Contract 2012 Edition: a Review Tony Cunningham Dublin Institute
(INDIVIDUALS ONLY) IndContPkge Version: 1.7 Updated: 18 Jul. 03
INDEPENDENT CONTRACTOR PACKAGE (INDIVIDUALS ONLY) IndContPkge Version: 1.7 Updated: 18 Jul. 03 Contents Preface 2 Checklist 3 Helpful Hints 4 Frequently Asked Questions 5 Agreement with an Independent
Central Plumbing (Wellington) Limited
TERMS OF TRADE Central Plumbing (Wellington) Limited The terms of trade set out below govern all supplies of goods and services from Central Plumbing (Wellington) Limited ( Central Plumbing (Wellington),
Explaining an architect s services. General information on the usual tasks undertaken by an architect
Explaining an architect s services General information on the usual tasks undertaken by an architect June 2008 What an architect may do for you Introduction The root cause of disputes and complaints against
Mako Networks Sales & Marketing, Inc. Terms & Conditions for End User System Access, Use & Service Supply
Mako Networks Sales & Marketing, Inc. Terms & Conditions for End User System Access, Use & Service Supply 1. Introduction a. Binding Terms: These terms and conditions constitute a legally binding agreement
Hosting Service Agreement
tesseract-online.com Hosting Service Agreement Cranbox Limited T/A Tesseract Commencement Date: 1. Agreement 1.1. This Agreement is made between you (the 'Customer') and Cranbox Limited trading as Tesseract
Bills of Quantity. D. Atkinson December 2000. Nature of Bills
Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and
1.3 These Conditions may only be amended or varied by written agreement signed by both Parties.
TERMS AND CONDITIONS OF SALE AND PROVISION OF SERVICES 1. Sale of goods / Provision of services 1.1 Monash University ( Monash ) provides the goods and/or services subject to these terms and conditions,
PREFACE. The Contract for the Supply and Delivery of Goods has been prepared for use in supplies contracts which have the following characteristics:
Supply Chain Management Document Number: SCM006 Document Title: Supply Contract Version: 01 Purpose: Standard contract for all supplies of goods PREFACE The Contract for the Supply and Delivery of Goods
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication
BMT Tax Depreciation Pty Ltd - Terms of Engagement
BMT Tax Depreciation Pty Ltd - Terms of Engagement 1.0 Definitions and Interpretation 1.1 In this document, unless the context indicates a contrary intention: Agreement means these Terms of Engagement
MDB Harmonised Particular Conditions
FIDIC Plant and Design-Build Contract MDB Harmonised Particular Conditions 1. Introduction There is a need for FIDIC to provide sample Particular Conditions that render the General Conditions of the 1st
GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES
GENERAL CONDITIONS OF CONTRACT MINOR WORKS AND SERVICES GENERAL CONDITIONS OF CONTRACT FOR MINOR WORKS PAGE 1 BASE D ON WA LOCAL GOVERNMENT ASSOCIATION MODEL 2010 TABLE OF CONTENTS 1 INTERPRETATION 2 RISE
Breed Communications Limited - limited company consultancy agreement 230113
Limited Company Consultancy Master Agreement DATED BETWEEN:- (1) Breed Communications Limited (Company Number 4809384) whose registered office is c/o Hilton Consulting, 119 The Hub, 300 Kensal Rise, London
COMMERCIAL CREDIT ACCOUNT APPLICATION
COMMERCIAL CREDIT ACCOUNT APPLICATION *Mandatory field required to process application Please complete the below form in BLOCK LETTERS ONLY ensuring all information is entered with as much detail as possible.
IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer
THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE
Practice Note Deciding on the appropriate JCT contract
Practice Note Deciding on the appropriate JCT contract This Practice Note is intended to provide assistance in deciding the appropriate form of contract but it is not a substitute for professional advice.
CLIENT / PROJECT MANAGER AGREEMENT
Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT
HICAPS. Provider Agreement. Terms and Conditions
HICAPS Provider Agreement Terms and Conditions This agreement is made up of this booklet and the HICAPS Provider Agreement Details. HICAPS Pty Limited ABN 11 080 688 866 Terms and Conditions 1. Interpretation
Consultant Warranty of [Specify discipline of Consultant]
APPENDIX 7 CONSULTANT WARRANTY d 2015 (1) [Sub-Contractor] (2) [Thurrock Council] (3) [The Employer] Consultant Warranty of [Specify discipline of Consultant] Relating to: Aveley Village Community Hub,
AGENCY AGREEMENT. Between 3Keys Limited company registration number 06841492 6 of Town End Doncaster DN5 9AG ... ... ... ... ... Postcode..
AGENCY AGREEMENT Between 3Keys Limited company registration number 06841492 6 of Town End Doncaster DN5 9AG and Landlord s name/s (all joint landlords):... Landlord s address: (current address and new
SECTION 00900 PERFORMANCE BOND., hereinafter called PRINCIPAL, and
SECTION 00900 PERFORMANCE BOND KNOW ALL PERSONS BY THESE PRESENTS: THAT (Name or Contractor) a (Address of Contractor) (Corporation, Partnership, or Individual), hereinafter called PRINCIPAL, and (Name
New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions
ACRS Lic No. A021974 Lic No. 192237C New-Gen Electrical (ABN 11 514 699 805) Terms & Conditions *Definitions are in clause 19 1. FORMATION OF AGREEMENT 1.1 Acceptance of Quotation The Customer must accept
NZS 3910:2013. Conditions of contract for building and civil engineering construction NZS 3910:2013. New Zealand Standard
New Zealand Standard Conditions of contract for building and civil engineering construction Superseding (in part) NZS 3910:2003 NZS 3910:2013 COMMITTEE REPRESENTATION This Standard was prepared under the
NZIA Standard Construction Contract
New Zealand Institute of Architects Incorporated NZIA Standard Construction Contract NZIA SCC 2014 Between The Principal Norrie Family Trust And The Contractor For Contract Norrie Home At
In force as of 15 March 2005 based on decision by the President of NIB ARBITRATION REGULATIONS
In force as of 15 March 2005 based on decision by the President of NIB ARBITRATION REGULATIONS Contents I. SCOPE OF APPLICATION... 4 1 Purpose of these Regulations... 4 2 Applicability to different staff
Professional Indemnity Select
Allianz Insurance plc Professional Indemnity Select Policy Overview Policy Overview Professional Indemnity Select Contents Thank you for choosing Allianz Insurance plc. We are one of the largest general
Contract for Services PSC Contractor
Contract for Services PSC Contractor Phone: 020 7186 3000 Contract for Services - PSC CONTRACTOR This Agreement is made between: Medicare First Nursing (Part of Capita Plc) whose registered office is at
Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)
Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament
MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS
MODEL CONTRACTS FOR SMALL FIRMS LEGAL GUIDANCE FOR DOING INTERNATIONAL BUSINESS International Trade Centre, August 2010 Contents Foreword Acknowledgements Chapter 1 International Contractual Alliance ITC
ICC UNIFORM RULES FOR CONTRACT BONDS
ICC UNIFORM RULES FOR CONTRACT BONDS issued as ICC publication No. 524, adopted by the ICC Executive Board on 23 April 1993, come into effect on 1 January 1994 Copyright 1993 International Chamber of Commerce.
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
Province of Alberta DRUG PROGRAM ACT. Statutes of Alberta, 2009 Chapter D-17.5. Assented to June 4, 2009. Published by Alberta Queen s Printer
Province of Alberta Statutes of Alberta, Assented to June 4, Published by Alberta Queen s Printer Alberta Queen s Printer 5 th Floor, Park Plaza 10611-98 Avenue Edmonton, AB T5K 2P7 Phone: 780-427-4952
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal
Conditions of Contract
Amberley Main Street Upgrade Contract No. 10/21 10/21 - Amberley Main Street Upgrades CC Page 1 of 24 C Contents Conditions of Contract Table of Contents Page GENERAL CONDITIONS OF CONTRACT 3 FIRST SCHEDULE
ACE Agreement 2: Advisory, Investigatory and other Services (for use in Scotland)
2 ACE Agreement 2: Advisory, Investigatory and other Services (for use in Scotland) for the appointment of a Consultant to undertake any type of services in the built and natural environments except where
9. Unforeseen Delay 9.1 neither party shall be responsible for any losses resulting in the fulfilment of any of the terms of the
STANDARD TERMS AND CONDITIONS OF BUSINESS 1. Definitions 1.1 In the context of these standard terms and conditions of business:- 1.1.1 'the seller' means Entwistle and Joynt Limited of 62 Darlington Street
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
Document A101 2007 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AGREEMENT made as of the in the year (In words, indicate day, month and year.)
International Construction Warranties Limited. Terms & Conditions. Version UK1
International Construction Warranties Limited Terms & Conditions Version UK1 Rules of Registration Version 5 All Companies applying for or taking out a Warranty on a New Development with ICW shall comply
QUOTATION DOCUMENTS TERMS AND CONDITIONS OF AGREEMENT
Page 1 of 5 INTERPRETATION QUOTATION DOCUMENTS TERMS AND CONDITIONS OF AGREEMENT FOR THE SUPPLY AND DELIVERY OF FOODSTUFF OR AMENITIES ITEM(S) FOR THE PERIOD SPECIFIED IN THE AWARD LETTER In these Terms
PROFESSIONAL PRACTICE EXAM MARCH 2009 PAPER 1: THE ARCHITECTURAL PROFESSIONAL AS A PRACTITIONER AND ARCHITECTURAL SERVICE TO THE CLIENT
PROFESSIONAL PRACTICE EXAM MARCH 2009 Instructions to Candidates: 1 All questions are to be answered Where a question is in sections, each answer is to be clearly separated strictly in accordance with
General Terms of Public Procurement in Service Contracts JYSE 2014 SERVICES
General Terms of Public Procurement in Service Contracts January 2015 Contents Introduction...3 Issues to be observed in applying...5 General Terms of Public Procurement in Service Contracts ()...9 1 Definitions...9
COMMERCIAL CONSTRUCTION AGREEMENT. This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between <> ( Owner ) and <> ( Contractor ).
COMMERCIAL CONSTRUCTION AGREEMENT This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between ( Owner ) and ( Contractor ). A. Contractor wishes to enter into the following Contract with
ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS)
ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS) 1. Definitions In these Conditions: "Acceptance Form" means the acceptance form provided by Us to You with the Contract Documentation;
REQUEST FOR QUOTATION/ PURCHASE ORDER
REQUEST FOR QUOTATION/ PURCHASE ORDER Conditions of Contract- Services These Conditions may be varied only by the written agreement of the Council. No terms or conditions put forward at any time by the
Back to Basics: Professional Indemnity Construction and Engineering
Back to Basics: Professional Indemnity Construction and Engineering December 2015 Table of Contents Table of Contents... 2 Introduction... 3 Part A - Understanding the construction industry... 4 1 Construction
NHS Standard Contract 2015/16 General Conditions
NHS Standard Contract 2015/16 Draft for consultation December 2014 NHS Standard Contract 2015/16 Draft for consultation Version number: 1 First published: December 2014 Updated: Prepared by: NA NHS Standard
THIS IS THE APPENDIX F REFERRED TO IN THE FOREGOING AGREEMENT BETWEEN FISHERIES INNOVATION SCOTLAND AND THE CONTRACTOR
THIS IS THE APPENDIX F REFERRED TO IN THE FOREGOING AGREEMENT BETWEEN FISHERIES INNOVATION SCOTLAND AND THE CONTRACTOR APPENDIX F Terms and Conditions 1. Definitions 1.1. In these terms and conditions
Kiwi Wealth KiwiSaver Scheme Trust Deed. Kiwi Wealth Limited Public Trust
Kiwi Wealth Limited Public Trust Table of contents Parties... 1 Background... 1 Operative provisions... 2 1 This Deed witnesses... 2 Preliminary... 2 2 Interpretation... 2 3 Constitution of the Scheme...
AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES
AGREEMENT WITH A SELF-EMPLOYED CONTRACTOR FOR CONSULTANCY SERVICES Names of Parties 1. (Company Name) of (Company Address) ( Consultancy ). 2. Redline Group Ltd of 26-34 Liverpool Road, Luton. Beds LU1
In these conditions "the Company" means Pro Formance Metals Limited
Terms and Conditions of Sale In these conditions "the Company" means Pro Formance Metals Limited 1. ALL CONTRACTS OF SALE - incorporate these Terms and Conditions. Any variation of these Terms and Conditions
fdsfdsfdsfdsfsdfdsfsdfdsfsdfsd Square Box Systems Technical Support Agreement
fdsfdsfdsfdsfsdfdsfsdfdsfsdfsd Square Box Systems Technical Support Agreement Last updated 4 th January 2016 Technical Support Agreement This Technical support agreement is made up of these terms and conditions
Risks in International Consultancy Appointments: The FIDIC White Book
Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction
Contract for Services
Contract for Services PROVIDER CONTRACT FOR THE PROVISION OF LEGAL AID SERVICES AND SPECIFIED LEGAL SERVICES The Parties to this Contract The Secretary for Justice (the Secretary) And (the Provider) The
ANGUS COUNCIL SUPPLEMENTARY CONDITIONS OF CONTRACT. SC 01 - Contract Performance Guarantee Insurance
SC 01 - Contract Performance Guarantee Insurance For contracts equal to or exceeding 750,000 in value the Contractor shall, within 28 days of the date of the award of the Contract, obtain and provide to
BROOKFIELD GLOBAL INTEGRATED SOLUTIONS STANDARD PURCHASE ORDER TERMS FOR SUPPLIES
BROOKFIELD GLOBAL INTEGRATED SOLUTIONS STANDARD PURCHASE ORDER TERMS FOR SUPPLIES Entire Agreement: These standard terms and any Purchase Order will together comprise the complete contract between Brookfield
CONCODE Agreement for the appointment of architects, surveyors and engineers for commissions for minor works STATUS IN WALES ARCHIVED
CONCODE Agreement for the appointment of architects, surveyors and engineers for commissions for minor works 1996 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected]
Payment Processing Agreement
Payment Processing Agreement Dated 2015 Cabcharge Australia Ltd. ( Cabcharge ( Payment Processor Payment Processing Agreement Details 3 General terms 4 1 Access to and use of the System 4 1.1 Access to
Conditions of Contract for CONSTRUCTION
Conditions of Contract for CONSTRUCTION FOR BUILDING AND ENGINEERING WORKS DESIGNED BY THE EMPLOYER Multilateral Development Bank Harmonised Edition June 2010 General Conditions This publication is exclusive
THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $20 1999 EDITION
THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $20 1999 EDITION Printed by the Printing Department 1594862 50L 11/99 (Printed on paper made
Appendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
DASHBOARD CONFIGURATION SOFTWARE
DASHBOARD CONFIGURATION SOFTWARE RECITALS: The Contractor has designed and a web site for Client, and has agreed to maintain the said web site upon the terms and conditions hereinafter contained.] NOW
scotland ACE Agreement 2: Advisory, Investigatory and other Services
2 ACE Agreement 2: Advisory, Investigatory and other Services for the appointment of a Consultant to undertake any type of services in the built and natural environments except where the Client appointing
Doral Mineral Sands Pty Ltd. Standard Terms and Conditions
Doral Mineral Sands Pty Ltd Standard Terms and Conditions 1 Definitions Doral Mineral Sands Pty Ltd Standard Terms & Conditions (2002) 1 1.1 In this Agreement, unless the context otherwise requires: Agreement
Appendix A. Call-off Terms and Conditions for the Provision of Services
Appendix A Call-off Terms and Conditions for the Provision of Services Where an Order Form is issued by the Authority that refers to the Framework Agreement, the Contract is made between the Authority
STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES LE MARK SELF ADHESIVE LTD.
STANDARD TERMS AND CONDITIONS FOR SUPPLY OF GOODS AND SERVICES OF LE MARK SELF ADHESIVE LTD. 1 DEFINITIONS In this document the following words shall have the following meanings: 1.1 "Agreement" means
DOCUMENT. General Purchase Conditions
1. Scope 1.1 These general purchase conditions (hereinafter the GPC ) shall apply to all kinds of materials, articles, products and services related to them, (hereinafter Products ), offered, sold or supplied
TERMS & CONDITIONS CONTRACTOR SERVICES
TERMS & CONDITIONS CONTRACTOR SERVICES JPeak Electrical Contracting ATF JPeak Electrical Contracting Trust ABN 11 700 262 900 JPeak Electrical Contracting ATF JPeak Electrical Contracting Trust ABN: 11
DIRECTORATE OF ESTATES & FACILITIES
DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,
MEGGITT GLOBAL STANDARD PURCHASING CONDITIONS
MEGGITT GLOBAL STANDARD PURCHASING CONDITIONS 1. Definitions In these conditions Buyer means the Meggitt company that places the order (acting where relevant through a business division). Seller means
Appointment Contracts RIBA Agreements 2010
An Overview of the RIBA Appointment Agreements RIBA NW Pt 3 - Chester 16 April 2011 Richard Brindley RIBA RIBA Group Director Membership & professional Support Why do we need a standard form of agreement/contract
STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)
State License #CGC048773 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) This Agreement is made this day of, 200, by and
Introduction to SOP. Background. Background. Principles of SOP Act. Objectives of SOP Act
Introduction to SOP Background Building and Construction Industry Security of Payment (SOP) Act Objectives of Act Principles of Act Key Provisions of Act by Lim Jue Meng Jennifer Leong Ng Cher Cheng Feedback
CONTRACT FOR CONSULTANCY SERVICES. Section 1 Form of Contract
CONTRACT FOR CONSULTANCY SERVICES Equatorial Fidelity Centre 2 nd Floor, Off Waiyaki Way P.O Box 313-00606 Nairobi, Kenya. Tel +254 20 423 5000 Section 1 Form of Contract CONTRACT FOR: [Insert Title here]
