1 Proceedings of Chemistry and Technology Conference PIPOC 2007, Kuala Lumpur, August C2 Effect of new processes on the EFB and POME utilisation F. Schuchardt 1, K. Wulfert 2, D. Darnoko 3, T. Herawan 3 ABSTRACT New processes are characterised by advanced oil separation technologies with zero dilution water (ECO-D System for example) and continuous sterilisation of the FFB. These processes have a deep impact on the amount and composition of waste water (POME). Compared to conventional s the total amount of POME can be reduced from 0.65 m³/ton FFB to 0.45 m³/ton (conventional sterilisation and zero dilution water) and 0.25 m³/ton (continuous sterilisation and zero dilution water). These changes influence the treatment processes and its cost significantly. One process for the EFB and POME utilisation which can fulfil the demand of a sustainable palm oil production is the combined composting of both of the materials. The composting process is used also for biological drying of the POME. The final product of the process is compost or mulch which unifies the nutrients of both in one product. The POME can be used also for biogas production (in fixed bed reactors for POME with low dry matter content and in totally mixed reactors for ECO-D biomass) before composting. The investment cost and profitability of the composting and fermentation process is calculated in detail based on data from practise in Indonesia. The new developments of processes in s can reduce the cost for the waste and waste water treatment up to 35 %. The benefits from biogas production and composting are the energy production, saved POME treatment cost in pond systems, total utilisation of the POME nutrients, reduced cost for the EFB transport and utilisation, higher FFB yields and from CDM. Abbreviations: POM, POME effluent, FFB fresh fruit bunch, EFB empty fruit bunch, CDM (clean development mechanism), DM dry matter, t ton INTRODUCTION Conventional s are considerable polluters of the environment and don t follow the principles of sustainability (Anonym Unilever 2003; Anonym RSPO 2005). In the RSPO principle 5 ( Environmental Responsibility and conservation of natural resources and biodiversity ) is written: Waste is reduced, recycled, and disposed of in an environmentally and socially responsible manner (criterion 5.3), Efficiency of energy use and use of renewable 1 Federal Agricultural Research Centre (FAL), Institute of Technology and Biosystems Engineering, Braunschweig, Germany 2 UTEC Consultant for Development and Application of Environmental friendly Technology GmbH, Bremen, Germany 3 Indonesian Oil Palm Research Institute, Medan (IOPRI), Indonesia 44
2 energy is maximised (criterion 5.4), and Plans to reduce pollution and emissions, including greenhouse gases, are developed, implemented and monitored. The main source of environment pollution in the oil mill is the pond system for the palm oil mill effluent (POME). The anaerobic ponds emit a huge amount of the strong green house gas methane with the biogas and the effluent of the ponds contains nutrients responsible for pollution of surface and ground water. Each ton of produced crude palm oil is responsible for the emission of 46 m³ (32.9 kg) of methane, corresponding 384 m³ (756 kg) CO 2 equivalent. Because climate protection becomes more and more important and especially methane emissions are in focus, it can be expected that the conventional waste water treatment in anaerobic ponds will be banned in the future. Furthermore the palm oil industry will come under pressure, if a huge amount of CPO (crude palm oil) or bio-diesel from CPO as renewable energy source will be exported to western countries. The requirement will arise, that the CPO production has to be sustainable less emissions, no pollution of the environment, implementation of recycling systems, utilization of energy sources, soil conservation by minimization of erosion, protection of rain forest and so on. Under these aspects the palm oil industry will be forced to implement new environmental friendly treatment technologies in their oil mills. Concepts, technical solution and practical experiences for new concepts as EFB composting in combination with POME and biogas production from POME/sludge are available since several years (Schuchardt et al. 1999, Schuchardt et al. 2002a, Schuchardt et al. 2002b, Wulfert et al. 2002; Schuchardt et al. 2006) Alternatives of POME, sludge and EFB treatment and utilization If the POME is not treated in an anaerobic-aerobic pond system, alternatives as follows can be discussed: Aerobic treatment in aerated ponds to avoid methane emissions is not suitable, because of o Enormous demand of current for aerators o Problems with de-sludging of ponds and handling of sludge o Biological problems (COD with 50,000 mg/l is too high for direct aerobic treatment) Anaerobic pre-treatment in a biogas plant and aerobic post-treatment in aerobic ponds is possible, but the aerobic post-treatment is not recommended, because o the aerobic post-treatment has still the problem of sludge sedimentation in the ponds (50 % of COD is suspended organic material, which are not degraded in a digester with relatively short retention time), sludge handling and o methane formation in sludge sediment can not be avoided. o Losses of all nutrients from POME and pollution of rivers and lakes. Technical drying of POME is not suitable, because of high invest- and running costs and high energy demand. Land application of the POME is not recommended, because of the high cost, if the application rate is in balance with nutrient uptake by the oil palm tree (Schuchardt et al., 2005). Furthermore the POME has to be pre-treated anaerobically to fulfil the application regulations (in Indonesia: BOD <5,000 mg O 2 /litre). One result of the anaerobic treatment is emission of methane. Utilization of POME for moistening in combination with EFB composting. This system is recommended, because: o the liquid of POME will be naturally evaporated without any additional energy input (except fuel demand of the turning machine), 45
3 o all nutrients of POME are saved in the compost, o there is no waste water anymore, except leakage and rain water from the composting plant area, o pollution of surface water, ground water and atmosphere can be avoided. Since incineration of empty fruit bunches (EFB) is forbidden because of environment pollution by smoke, land application is the common accepted method of its sustainable utilisation. In praxis the oil mills use different procedures for handling, pre-treatment and distribution: untreated empty fruit bunch are distributed in plantation, negative aspects are: o EFB are still wet with high weight per bunch. o Distribution happens manually. o Danger of Ganoderma boninense and Oryctes rhinoceros (Rhinoceros beetle) if EFB are dumped in heaps. o Slow mineralisation of the nutrients, the fertilizer effect is difficult to calculate. Distribution of chopped fresh EFB, positive aspects are: o Easier to handle. o Distribution can be done manually or mechanised by spreader or blower. o Material has the function of mulch and soil conditioner. o Mineralisation is faster. Compost production from chopped EFB and distribution of compost, positive aspects are: o Less volume and tonnage, in consequence less afford for transport and distribution. o High content of mineralised nutrients, fertilizer effect can be quantified. In some cases s still dump the EFB somewhere in the plantation area (with methane emissions) or burn it in open heaps (with heavy smoke pollution) to get the ash as mineral fertilizer. Palm oil mills with new technologies The discussion about POME treatment is based on an "end of pipe strategy". An alternative is to modernize the production process itself. In s new technologies (so called "new s") had been developed and are in progress (Sivasothy et al. 2005; Sivasothy and Hwa 2006; Chungsiriporn and Prasertsan 2006; Westfalia Separator Industry 2006; Tornroth 2006). These technologies are particularly: New sterilisation processes without condensate instead of conventional autoclave sterilisation. The conventional sterilization creates a condensate flow of 0.20 m³/ton FFB. By modification to a new sterilization processes the condensate can be avoided almost totally. Zero dilution water for oil separation. The conventional oil recovery process as a combination of vertical clarifier and separators needs dilution water for good function. The process creates waste water: 0.45 m³/ton FFB. By using new oil recovery technology (for example "ECO-D" system by Westfalia Company) an addition of dilution water is not necessary anymore and the amount of effluent can be reduced up to 0.25 m³/ton FFB. The total amount of POME can be reduced step by step by implementation of new technologies (table 1). Because the loads of suspended solids, dissolved COD etc. are nearly unaffected by the reduction of water, the dry matter content will increase from 5 % in conventional POME up to 17 % in the biomass discharged from the ECO-D decanter system. 46
4 Table 1 POME and sludge from conventional and new s POM Conventional POM "New POM" Parameter Conventional sterilisation Convent. sterilis., new oil recovery New sterilisation, new oil recovery A B C sterilizer condensate m³/t FFB clarification sludge m³/t FFB sum POME m³/t FFB dilution water m³/t FFB POME % DM POME m³/t EFB POME water m³/t EFB In view to the combined treatment of POME/sludge and EFB in table 1 the specific amount of water per ton EFB are also given. It is obvious, that the amount of water related on EFB is strongly influenced by using new technologies. The modernisation of the production process in s has a significant impact on the absolute and related amount of POME and water in POME (m³/ton FFB), the composition (dry matter content, concentration of nutrients, liquid or sludge), the utilisation (type of biogas plant, size of composting plant), and the treatment cost of the POME. RESULTS Concept and further strategy The proposed concept of a sustainable POME and EFB treatment can fulfil the following aspects: Alternative to common procedures as pond system and dumping of EFB. Minimization of pollutions of surface water, ground water and atmosphere (realisation of zero-waste-concept). Minimization of nutrient losses and concentration of all nutrients from POME and EFB in one product. Possibility of biogas production by demand. Creation of CO 2 -certificates. Flexible application for conventional and new s. Acceptable technical and financial afford. The basic lines of the concept are shown in figure 1. The key-process in the concept is the composting of EFB. The chopped EFB are transported to a composting plant and set up to windrows. The heaps can evaporate 70 kg water/(ton EFB*day) because of the high self heating temperature as result of the intensive rotting process (Schuchardt et al.1998; Schuchardt et al. 2002) and would fall dry, if the heaps are not irrigated regularly. Effluents of the POM are used to keep the humidity in the rotting material. The rotting material is mixed and turned by windrow turning machines to optimise the biological process and to maximise water evaporation. The size and costs of a composting plant depends on the amount of water, which have to be evaporated. Under this aspect it is important how much POME accumulate in the 47
5 oil mill. Therefore three alternatives will be considered: A: conventional POM with 0.65 m³ POME/ton FFB, B: new POM with new oil recovery process with 0.45 m³ POME/ton FFB and C: new POM with new technology for sterilization and new oil recovery processes with 0.25 m³ POME/ton FFB. If the POM has a demand or a market for biogas/energy, the POME can be treated in a biogas plant. The produced biogas is used as energy source. Different types of biogas plants are necessary, depending on the kind of effluent. For POME with low dry matter content fixed bed digesters are favoured, for POME with high dry matter content totally mixed digesters are absolutely necessary. After anaerobic pre-treatment the effluent of a biogas plant is used for moistening of the compost heaps. A Conventional B New C conventional autoclave sterilizer, conventional oil recovery conventional autoclave sterilizer, new oil recovery (ECO-D System) new sterilizer, new oil recovery (ECO-D System) POME [m³/t FFB] fixed bed fermenter composting plant totally mixed fermenter alternative compost, mulch Figure 1: Alternative use of POME and ECO-D biomass from conventional and from new s. Process design of anaerobic POME treatment After POME passed the de-oiling (de-oiling pond, oil skimmer) the hot POME is cooled down by a cooler (figure 2). As cooling medium cold process water and/or air is used. The water is pumped via pipe to the waste water treatment plant, where it passes a screen, which separates all solid with a size >0.75 mm (minimization of risk of plugging the fixed bed). The effluent of the screen flows directly into the pre-storage to enable a continuously feeding of the digester 24 hours a day at 7 days a week. For anaerobic treatment a fixed bed digester is chosen, because of its high process stability in view of shock load, variation of feeding rate and COD-concentration (Wulfert et al. 2002). The inflow is fed at the bottom of the digester, pass in up flow mode the support material and flows out on top level. A part of the effluent is used as circulation water and is mixed with the 48
6 fresh waste water coming from pre-storage tank. The circulation flow is necessary to dilute the high polluted waste water to lift the low ph and decrease the acid concentration. The anaerobic bacteria degrade the dissolved organic components of POME during passing the fixed bed and transform them to biogas. The biogas is collected and used as energy source. The effluent of the digester flows by gravity into a post-storage, where a part of the suspended solids settles down. The circulation water to dilute the inflow of the digester is taken out in the upper part of the post-storage. The discharged water is taken out in the bottom part and is pumped to final storage in composting area. The post-storage is constructed as closed tank to collect the biogas, which is produced there still. POME de-oiling cooler biogas biogas waste water treatment plant screen pre-store fixed bed digester recirculation post-store waste water to composting plant Figure 2: Process design of anaerobic treatment of POME with low dry matter content The totally mixed digester is the most common type of type of digesters in biogas plant to treat sludge world wide. The digester is a cylindrical closed steel or concrete tank, equipped with a mixing device, which guarantees a well mixing of the content to avoid the formation of sediment and swimming scum and to ensure a good distribution of fed substrate. For dimensioning of the biogas plant only few parameters are relevant: 1. The hydraulic retention time has to be more than 15 days to ensure that the bacteria grows is higher than the bacteria losses by effluent 2. The loading rate (kg degradable organic matter per m³ digester volume and day) ranges between 2 and 4 kg/(m³ *d) otherwise the risk of overloading increase. 3. The digestion temperature should be kept on constant level; a drop of more than 1 K within short time has an negative impact to the performance of methanogenic bacteria. 4. The composition and characteristics of the sludge, which shall be treated Results of digestion tests with biomass from ECO-D System The digestion test of ECO-D-biomass was done in the laboratory of UTEC. The biomass sample was taken from an ECO-D decanter running in a POM in Malaysia. The digestion tests were done in lab-scale digesters with semi continuous mixing (digestion temp. 38 C). Results of the digestion test: The organic substance can be degraded almost up to 100 %. Within 8 days almost all of organic components can be hydrolysed and transformed to biogas. The specific gas yield is around 112 and 120 m³/ton biomass with a methane content of 60 %. The gas yield reaches the theoretical maximum. 49
7 As consequence of the high content of protein it might happen that the ammonia/ammoniac concentration reaches a level, which caused an inhibition of anaerobic bacteria. This problem can be solved by addition of dilution water (c-nhx-max = 5200 mg/l; c-nhx-limit = 4500 mg/l; dilution water 0.16 m³ per ton sludge) Resume: Eco-D biomass is a very good substrate for bio-methanisation. The characteristic of digestion is comparable with other substrates from food industry which are digested successfully in full scale plants already. Process design of anaerobic sludge treatment The biomass from the ECO-D System or the mixture of biomass and condensate is pumped to the biogas plant, where the suspension is stored in a tank (figure 3). The tank is equipped with mixing device to ensure a homogeneous composition. The feeding of the digester happens continuously out of the pre-storage via pump. The mixing device in the digester ensures a good distribution of the substrate. The control of digestion temperature happens via internal or external cooling device. The adjusted temperature level can range between 28 and 40 C. In view to the high ammonia concentration a temperature of 30 to 35 C is proposed. The effluent flows out via overflow by gravity into the closed post-storage, from where it is pumped to composting plant. POME (ECO-D biomass) pump biogas biogas waste water treatment plant pre-store tot. mixed digester cooler post-store waste water to composting plant Figure 3: Process design of anaerobic treatment of POME with high dry matter content Process design of composting plant After chopping the EFB they are formed to heaps for composting. (figure 4). The size of the heaps depends on the size of the turning machine. The selfheating process of the EFB, initiated by the microorganims in the substrate, starts within very short time and water is evaporated to the atmosphere. POME (with or without anaerobic pre-treatment) will be added step by step to the rotting EFB, depending on the water evaporation. The composting process can go on until the substrate is totally stabilized as compost (C/N ratio <15) or it can be stopped at a stabilisation level of mulch (C/N ratio >15); it depends on the further use of the substrate. If compost should be produced as a market product it is necessary to screen it before packaging to have a product with a homogenous structure. The mixture of leakage water and rain water from the composting area is collected in a pond and will be used for irrigation of the heaps (or in plantation area). The floor of the composting area is made by concrete or asphalt, to protect the environment by uncontrolled run-off of the leakage water (with nutrients) and to ensure a controlled turning of the heaps and high compost quality. A protection of the heaps with a geo-textile is not necessary. 50
8 water to the atmosphere EFB chopping composting compost or mulch for plantation POME screening packaging compost for market Figure 4: Process design combined EFB/POME composting Conclusions and consequences for the composting of EFB POME The composting process can be divided into two process stages: Stage 1: o addition of POME o evaporation of the water o biological drying o final product: mulch Stage 2: o stabilisation of the compost o drying period (for screening as market product) o final product: compost At the end of the stage 1 (after 12, 24 and 37 day resp., table 2) the EFB are like wet mulch and not stabilized as compost. The mulch can be used in plantation area for palm oil trees (or other plants) but not in a nursery. The biological degradation of the EFB/POME mixture will go on under the natural soil and climate conditions. If mature compost should be produced, the rotting time should be prolonged for about 30 days more. To produce dry compost for screening and packaging the retention/drying time depends on the climate conditions. The retention time of the EFB in the composting plant is relevant for the cost of the composting process. A reduction of the specific POME amount will reduce the time necessary to evaporate the water. The figures 5 to 9 show the flow sheets and the equipment for the biological drying/composting of EFB and POME. Table 2: Time for biological drying and stabilisation of EFB and POME composting Type of No. biol. drying stabilisation total time product d d d A POM with conventional sterilisation, with dilution water; mulch for composting fresh POME or after fermentation compost B POM with conventional sterilis., new oil recovery, mulch fresh POME for composting compost POM with conventional sterilis., new oil recovery, mulch POME after fermentation for composting compost C POM with new sterilisation, new oil recovery, mulch fresh POME for composting compost POM with new sterilisation, new oil recovery, mulch POME after fermentation for composting compost 51
9 A POM with conventional sterilisation and conventional oil recovery with or without biogas POME EFB oil mill cooler chopping mill belt conveyor channel wheel loader truck composting plant tank pump station piping system composting area turning machine pond leachate no part of compost or mulch cost calculation Figure 5: Equipment of a composting plant for EFB with addition of POME (POM type A) B POM with conventional sterilisation and new oil recovery process (ECO-D System) without biogas B POM with conventional sterilisation and new oil recovery process (ECO-D System) with biogas condensate ECO-D biomass EFB water condensate ECO-D biomass EFB oil mill cooler screw conveyor chopping mill press belt conveyor oil oil mill cooler biogas plant chopping mill belt conveyor mixer channel wheel loader truck pipe wheel loader truck composting plant tank pump station piping system composting area turning machine pond leachate composting plant tank pump station piping system composting area turning machine pond leachate compost or mulch no part of cost calculation Figure 6: Equipment of a composting plant for EFB with addition of POME without biogas production (POM type B) compost or mulch no part of cost calculation Figure 7: Equipment of a composting plant for EFB with addition of POME with biogas production (POM type B) 52
10 C POM with new sterilisation process and new oil recovery process (ECO-D System) without biogas C POM with new sterilisation process and new oil recovery process (ECO-D System) with biogas cleaning water ECO-D biomass EFB water cleaning water ECO-D biomass EFB oil mill channel screw conveyor mixer wheel loader chopping mill press belt conveyor oil oil mill biogas plant pipe chopping mill belt conveyor wheel loader truck composting plant pump station piping system truck composting area turning machine pond compost or mulch leachate no part of cost calculation Figure 8: Equipment of a composting plant for EFB with addition of POME without biogas production (POM type C) composting plant pump station piping system composting area turning machine pond compost or mulch leachate no part of cost calculation Figure 9: Equipment of a composting plant for EFB with addition of POME with biogas production (POM type C) Cost calculation To compare the anaerobic treatment alternatives for the POME the cost calculation based on a biogas production rate of 1,000 m³ methane per day (1,000 l Diesel fuel equivalent or 10,000 kwh). The composting plant is calculated for a 30 t mill with 153,000 tons FFB per year and the full rate of POME/sludge. All prices based on market prices in Indonesia in the years 2006/2007. The data for the cost calculation are given in tables 3 to 8. Table 3: Basic data for cost calculation for anaerobic treatment and composting Maintenance % of investment 2 to 5 Depreciation years 10 Currency 1 EUR 11,000 IDR Capital cost Credit % 70 Equity % 30 Interest % 16 Pay back time years 5 Energy Diesel fuel EUR/l
11 Table 4: Cost calculation for biogas plant with fixed bed digester (1000 l diesel fuel equivalent); POM type A Investment cost 1) EUR 486,560 Capital costs EUR/a 148,599 Production cost EUR/a 72,784 Total annual costs EUR/a 221,383 Benefit 2) EUR/a 219,000 Profit calculation Pay back period, year (annuity-method) Actuarial return with reference to total investment Actuarial return with reference to equity a % % ) Components: Preparation work, cooling, pre-storage, digester incl. support material, security device, post-storage, gasholder, de-sulphurication, biogas flare + blower, process measurement and control, switch board room, pipes for water, gas pipes, cable/power supply, traffic area, planning cost 2) Energy-production (Diesel fuel equivalent) Table 5: Cost calculation for biogas plant with totally mixed digester (1000 l diesel fuel equivalent) POM type B/C Investment cost 1) EUR 424,200 Capital costs EUR/a 129,555 Production cost EUR/a 63,298 Total annual costs EUR/a 192,853 Benefit 2) EUR/a 219,000 Profit calculation Pay back period, year (annuity-method) Actuarial return with reference to total investment Actuarial return with reference to equity a % % ,7 1) Components: Preparation work, cooling, pre-storage, digester, mixer, security device, post-storage, gasholder, de-sulphurisation, biogas flare + blower, process measurement and control, switch board room, pipes for water, gas pipes, cable/power supply, traffic area, planning cost 2) Energy-production (Diesel fuel equivalent) Table 7: Overview about cost calculation for the mulch and compost production from EFB and POME without anaerobic pre-treatment of the POME investment difference pay back actuarial return [%] POM No. EUR % EUR a total investm. ref. to equity Only mulch production (biological drying) A 1 749, B 3 680, , C 7 592, , Only compost production A 2 1,158, B 4 871, , C 8 782, ,
12 Table 6: Cost calculation for alternative composting plants in a 30 t oil mill (153,000 t/a) for POM type A, B and C with mulch production and compost production (see table 2) Type of oil mill 1) A A B B B B C C C C Alternative Investment cost 2) EUR 749,705 1,158, , , , , , , , ,972 Capital costs EUR/a 228, , , , , , , , , ,186 Production cost 3) EUR/a 189, , , , , , , , , ,218 Total annual costs EUR/a 418, , , , , , , , , ,404 Benefit 4) EUR/a 607, , , , , , , , , ,774 Profit calculation Pay back period, year (annuity-method) Actuarial return with reference to total investment Actuarial return with reference to equity a % % , ) A: Conventional with conventional autoclave sterilizer and oil recovery B: "New " with conventional autoclave sterilizer and new oil recovery process (ECO-D System) C: "New " with new sterilizer process and new oil recovery process (ECO-D System) 2) components: POME/sludge tank, chopping mill, belt conveyor, screw conveyor, mixer, turning machine, concrete floor 15 cm, dump truck, wheel loader, pond for leakage water, piping system, pump stations, mechanical work, electrical work, planning cost 3) fuel, electricity, labour, maintenance, depreciation, general cost 4) Cost saved for POME treatment in ponds, Value of the nutrients in POME, Reduced cost for compost transport + distribution, Increased FFB production of 2 %, CO 2 -certificate only for POME ,
13 Table 8: Overview about cost calculation for the mulch and compost production from EFB and POME with anaerobic pre-treatment of the POME investment difference pay back actuarial return [%] POM No. EUR % EUR a total investm. ref. to equity Mulch production (biological drying) and biogas production A 1 749, B 5 654, , C 9 566, , Compost production and biogas production A 2 1,158, B 6 845, , C , , CONCLUSIONS New s (Type B with conventional autoclave sterilizer and new oil recovery process and type C with new sterilizer process and new oil recovery process) produce a sludge with high dry matter and COD content ( ECO-D biomass ). The sludge can be used for biogas production in a totally mixed reactor. Compared to conventional s (type A) which should use a fixed bed fermenter for the POME treatment, the investment cost can reduced up to 13 % and the pay back time can reduced from 2.96 to 2.5 years. The biogas production from POME or ECO-D biomass is profitable (calculated on the Diesel fuel energy equivalent and a price of 0.60 EUR/litre) when the gas can be used. The mulch or compost production from EFB with addition of POME/Eco-D biomass is profitable with pay back times between 1.1 and 2.4 years. Compared to conventional palm oil mills (type A) the investment cost can be reduced up to 35 %. With the process of mulch or compost production from EFB in combination with POME or ECO-D biomass (with or without anaerobic fermentation with biogas production before) it is possible to realize a sustainable process in s with zero waste. ACKNOWLEDGEMENT The international research project between Indonesia and Germany was supported by the German Federal Ministry of Education and Research and the Indonesian Oil Palm Research Institute (IOPRI), Medan. REFERENCES Anonym (RSPO) (2005) RSPO principles and criteria for sustainable palm oil production. In: Anon. Anonym (Unilever) (2003) Sustainable Palm Oil - Good agricultural practice guidelines. In: Anon. Chungsiriporn J, Prasertsan S, Bunyakan C (2006) Minimization of water consumption and process optimization of s. Clean Technologies and Environmental Policy 8(3):
14 Schuchardt F, Susilawati E, Guritno P (1998) Influence of C/N ratio and inoculum upon rotting characteristcs of oil palm empty fruit bunch. Anon. Proceedings of 1998 International Palm Oil Conference Bali,Indonesia, September 23-25, 1998, pp Schuchardt F, Susilawati E, Guritno P (1999) Trials about composting of solid wastes from s in Indonesia. Anon. Biological Treatment of Waste and the Environment. Intern.Conference ORBIT 99, September 2-4, 1999, Weimar, Germany, pp Schuchardt F, Darnoko D, Guritno P (2002a) Composting of empty oil palm fruit bunch (EFB) with simultaneous evaporation of oil mill waste water (POME). IOPRI (ed). Enhancing oil palm industry development through environmentally friendly technology. Proceedings of Chemistry & Technology Conference, Nusa Dua Bali, Indonesien, July 8-12, 2002, pp Schuchardt F, Wulfert K, Darnoko D (2002b) A new, integrated concept for combined waste (EFB) and waste water (POME) treatment in s - Technical, economical and ecological aspects. Anon. Enhancing oil palm industry development through environmentally friendly technology. Proceedings of Chemistry & Technology Conference, Nusa Dua Bali, Indonesien, July 8-12, 2002, pp Schuchardt F, Wulfert K, Damoko D (2005) New process for combined treatment of waste (EFB) and waste water (POME) from s - Technical, economical and ecological aspects. Landbauforschung Volkenrode 55(1):47-60 Schuchardt F (2006) Sustainable waste water (POME) and waste (EFB) management in s by a new process. Anon. International Oil Palm Conference Nusa Dua, Indonesien, June 19 23, 2006 ISBN Sivasothy K, Halim RM, Basiron Y (2005) A new system for continuous streilisation of oil palm fresh fruit bumches. Journal of Oil Palm Research 17: Sivasothy K, Hwa T (2006) Continuous sterilisation of palm oil fresh fruit bunches. Anon. International Oil Palm Conference IOPC , Tornroth E (2006): The continuous ECO-D plus oil extraction system- The ultimate solution for sustainable palm oil processing. Anon. International Oil Palm Conference IOPC , Westfalia Separator Industry (2006) Brochure: The ECO-D System. In: Anon. Wulfert K, Darnoko D, Tobing PL, Yulisari R, Guritno P (2002) Treatment of POME in anaerobic fixed bed digesters. Anon. International Oil Palm Conference IOPC 2002, pp
EFFECT OF NEW PALM OIL MILL PROCESSES ON THE EFB AND POME UTILIZATION
Journal of Oil Palm Research (Special Issue - October 2008) EFFECT p. 115-126 OF NEW PALM OIL MILL PROCESSES ON THE EFB AND POME UTILIZATION EFFECT OF NEW PALM OIL MILL PROCESSES ON THE EFB AND POME UTILIZATION
Sewerage Management System for Reduction of River Pollution
Sewerage Management System for Reduction of River Pollution Peter Hartwig Germany Content page: 1 Introduction 1 2 Total emissions 3 3 Discharge from the wastewater treatment plants 4 4 Discharge from
Electricity from Biomass: Indonesia s Potential in the Palm Oil Sector and How to Tap it?
Electricity from Biomass: Indonesia s Potential in the Palm Oil Sector and How to Tap it? Adrisman Tahar Seminar on Energy from Biomass and Biogas in the Agro-industry Hotel Indonesia Kempinski, Jakarta,
Indonesia: Tapping Indonesia's Agrowaste Potential with Innovative Technology
Indonesia: Tapping Indonesia's Agrowaste Potential with Innovative Technology PEP Information Workshop 10. September 2014 www.exportinitiative.bmwi.de Suitable biogas technologies for Indonesia Frank Schillig,
Introduction to Waste Treatment Technologies. Contents. Household waste
Contents Introduction to waste treatment technologies 3 Section 1: The treatment of recyclable waste 4 Bulking facilities 5 Materials Reclamation Facility (MRF) 6 Reuse and recycling centres 8 Composting
Poultry manure as a substrate for methane fermentation: problems and solutions
Poultry manure as a substrate for methane fermentation: problems and solutions Robert Mazur Ph.D., Jakbu Mazurkiewicz M.Sc. eng. Andrzej Lewicki M.Sc. Eng, Sebastian Kujawiak M.Sc. Eng Poznan University
GUIDELINES FOR LEACHATE CONTROL
GUIDELINES FOR LEACHATE CONTROL The term leachate refers to liquids that migrate from the waste carrying dissolved or suspended contaminants. Leachate results from precipitation entering the landfill and
WASTEWATER TREATMENT OBJECTIVES
WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater
COD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens
COD/BOD 5 Reduction with ROTAMAT Fine and Micro Screens Removal of particulate material from wastewater Eco-efficient use of capital Water pollution control through maximum COD/BOD 5 reduction Service
PROPAK AquaBio Complete Water Restoration Systems
PROPAK AquaBio Complete Water Restoration Systems Conserving natural resources and lowering operating expenses is no longer an option, it is a necessity. Water, sewer and discharge fees are continuing
Technological developments for biogas production and use
Technological developments for biogas production and use Prof. Dr.-Ing. Frank Scholwin www.exportinitiative.bmwi.de Activities of the Institute for Biogas, Waste Management & Energy Scientific Consulting
Bio-CNG plant. Spectrum Renewable Energy Limited, Kodoli, Kolhapur
Bio-CNG plant Spectrum Renewable Energy Limited, Kodoli, Kolhapur Spectrum Renewable Energy Private Limited (SREL) developed a large scale biogas generation and bottling project at Kodoli near Kolhapur
Description of the Water Conserv II Facility
Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has
IGW S.r.l. Sofia 9 giugno 2015 PIÙ MODERNI, PIÙ COMPETITIVI, PIÙ FORTI AMBIENTE ED EFFICIENZA ENERGETICA IN BULGARIA. Organizzazione a cura di
IGW S.r.l. Sofia 9 giugno 2015 PIÙ MODERNI, PIÙ COMPETITIVI, PIÙ FORTI AMBIENTE ED EFFICIENZA ENERGETICA IN BULGARIA Organizzazione a cura di IGW Srl is a service company that deals with the production
Investing in sustainable palm oil production Ex-ante impact assessment of investments in a palm oil mill in Palembang, Indonesia
Investing in sustainable palm oil production Ex-ante impact assessment of investments in a palm oil mill in Palembang, Indonesia Investing in sustainable palm oil production Ex-ante impact assessment of
The City of Boulder 75 th Street Wastewater Treatment Facility
The City of Boulder 75 th Street Wastewater Treatment Facility Wastewater Collection and Treatment The Foundation of Public Health Wastewater Collection Boulder s wastewater collection system, also known
NAWARO BioEnergie AG: a short introduction into our business for BiG>East: Biogas for Eastern Europe
1 2 NAWARO BioEnergie AG: a short introduction into our business for BiG>East: Biogas for Eastern Europe 3 Nawaro s business model fits the situation in CEE Initial situation in many CEE countries 1 2
Brewery Wastewater: 2010 Water and Wastewater Conference. 11.02.2011 Page 1
Brewery Wastewater: Solutions for the Problem By Fred M. Scheer 2010 Water and Wastewater Conference Madison, WI 11.02.2011 Page 1 vr74 What We Will Discuss: Biochemical i Oxygen Demand (BOD): Where does
Advanced Wastewater Treatment Process
7 th Workshop on Greenhouse Gas Inventories in Asia Possibly Co-benefit? Advanced Wastewater Treatment Process Tomonori ISHIGAKI Dept. of Environmental Solution Technology Ryukoku University, Japan Introductory
Oasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS
Oasis Clearwater ENVIRONMENTAL SYSTEMS WASTEWATER TREATMENT ENGINEERS The evolution continues in decentralised wastewater technology... The Process Decentralised wastewater treatment systems are defined
Table 1.1: Typical Characteristics of Anaerobically Digested Wastewater
Solar Detoxification of Distillery Waste Anil K. Rajvanshi and Nandini Nimbkar Nimbkar Agricultural Research Institute (NARI), P.O. Box 44, PHALTAN-415523, Maharashtra E-mail : [email protected] Introduction
1. Introduction. This will also give the farmer outside the EU greater access to markets with stringent safety standards.
The CreveTope production system is based on studies by CreveTec at ILVO (Oostende, Belgium), and the research station of Aquaculture Farming Technology (Venray, Netherlands) 1. Introduction CreveTope shrimp
LANDFILL GAS TO ENERGY- COMBINED ENGINE AND ORC-PROCESS
LANDFILL GAS TO ENERGY- COMBINED ENGINE AND ORC-PROCESS Dr Petri Kouvo Helsinki Region Environmental Services Authority THIRD INTERNATIONAL SYMPOSIUM ON ENERGY FROM BIOMASS AND WASTE Venice, Italy 8-11
INTERIM TECHNICAL REPORT FIRST 18 MONTH PERFORMANCE SUMMARY FOR ANAEROBIC DIGESTION OF DAIRY COW SLURRY AT AFBI HILLSBOROUGH
INTERIM TECHNICAL REPORT FIRST 8 MONTH PERFORMANCE SUMMARY FOR ANAEROBIC DIGESTION OF DAIRY COW SLURRY AT AFBI HILLSBOROUGH Figure : Photograph of AD plant at AFBI (digester tank left of centre) Peter
EnviTec Biogas Energy from Agricultural and Agro-Industrial Wastes. Eng. Marcello Barbato Sales Manager
EnviTec Biogas Energy from Agricultural and Agro-Industrial Wastes Eng. Marcello Barbato Sales Manager INDEX COMPANY PROFILE PROCESS AND TECHNOLOGY USE OF POME and NAPIER GRASS EnviThan BIOGAS UPGRADE
AP ENVIRONMENTAL SCIENCE 2012 SCORING GUIDELINES
AP ENVIRONMENTAL SCIENCE 2012 SCORING GUIDELINES Question 2 The Fremont School District uses oil to heat school buildings. Go Green! is a new project the district will implement. The superintendent has
Anaerobic Digestion: Biology and Benefits
In: Dairy Manure Management: Treatment, Handling, and Community Relations. NRAES-176, p.63-72. Natural Resource, Agriculture, and Engineering Service, Cornell University, Ithaca, NY, 2005. Anaerobic Digestion:
TALLINN WATER TREATMENT AND SEWERAGE Tuuli Myllymaa
TALLINN WATER TREATMENT AND SEWERAGE Tuuli Myllymaa Tallinn is the capital of Estonia. It has approximately 450,000 inhabitants and the town area is about 150 km 2. Tallinn Water Ltd., owned by the City
Energy from digester gas. Optimised biogas utilisation
Energy from digester gas Optimised biogas utilisation The complete solution The complete solution Our company ENER-G designs, installs and operates biogas combined heat and power (CHP) systems for a variety
EXPERIMENTAL STUDY OF PALM OIL MILL EFFLUENT AND OIL PALM FROND WASTE MIXTURE AS AN ALTERNATIVE BIOMASS FUEL
Journal of Engineering Science and Technology Vol. 8, No. 6 (2013) 703-712 School of Engineering, Taylor s University EXPERIMENTAL STUDY OF PALM OIL MILL EFFLUENT AND OIL PALM FROND WASTE MIXTURE AS AN
Biogas as transportation fuel
Biogas as transportation fuel Summary Biogas is used as transportation fuel in a number of countries, but in Europe it has only reached a major breakthrough in Sweden. All of the biogas plants in Sweden
Bioremediation. Introduction
Bioremediation Introduction In the twentieth century, the ever increase in the global human population and industrialization led to the exploitation of natural resources. The increased usage of heavy metals
Rainwater Harvesting
Rainwater Harvesting With climate change now a reality rather than a speculated possibility, the demand on water resources has gone up, whilst the amount of water available for supply has gone down. Forth
SIX REASONS TO DRY BIOGAS To A LOW DEWPOINT BEFORE COMBUSTION IN A CHP ENGINE STEVEN SCOTT MARKET DEVELOPMENT MANAGER ALTERNATIVE ENERGIES
SIX REASONS TO DRY BIOGAS To A LOW DEWPOINT BEFORE COMBUSTION IN A CHP ENGINE STEVEN SCOTT MARKET DEVELOPMENT MANAGER ALTERNATIVE ENERGIES Filippo Turra Product Manager Cooling Technology INTRODUCTION
Water Recycles poster
Water Recycles poster The "Water ReCycles" poster is designed for students of all ages. It shows the natural water cycle and humans influence on water resources. Raincloud illustration The raincloud in
Heating and cooling with wastewater
WASTE WATER Solutions Heating and cooling with wastewater Recovery of thermal energy from municipal and industrial wastewater Uc Ud Ub Ua a sewer b wastewater shaft with HUBER screen and delivery pump
Rehabilitation of Wastewater Treatment Plant of Sakhnin City in Israel by Using Advanced Technologies
Rehabilitation of Wastewater Treatment Plant of Sakhnin City in Israel by Using Advanced Technologies Yasar Avsar 1, Hussein Tarabeah 2, Shlomo Kimchie 3, Izzet Ozturk 4, Hadi Naamneh 2 1 Yildiz Technical
CLEAN DEVELOPMENT MECHANISM CDM-MP62-A01
CLEAN DEVELOPMENT MECHANISM CDM-MP62-A01 Draft Large-Scale Consolidated Methodology ACM00XX: Natural gas substitution by biogenic methane produced from the anaerobic digestion of organic waste COVER NOTE
Biogas plant Venaria Reale (I) Reference Plant. Customer. Plant data. Commissioned: 2010. La Bellotta Soc. Semplice Agricola (I)
Biogas plant Venaria Reale (I) Customer La Bellotta Soc. Semplice Agricola (I) Commissioned: 2010 Input: Maize silage, Triticale silage Power electric: 999 kw Plant design and process The input material
an overview of trends and approaches
Open Workshop Global Issues pertaining to BioWaste March 15th 212 - Turin, Italy Composting and Anaerobic Digestion, an overview of trends and approaches D. Mainero Working Group "Biological Treatment",
5. State the function of pulveriser. The pulverisers are the equipments which are used to powdered coal.
413 POWER PLANT ENGINEERING PART-A 1. Define Power. Power is the rate at which energy is used (or) Energy/time. 2. What are the types of fuels? Solid fuel Liquid fuel Gaseous fuel (Any one among the above
12 November 2008 *** I:\CIRC\MEPC\01\642.DOC INTERNATIONAL MARITIME ORGANIZATION 4 ALBERT EMBANKMENT LONDON SE1 7SR
INTERNATIONAL MARITIME ORGANIZATION 4 ALBERT EMBANKMENT LONDON SE1 7SR Telephone: 020 7735 7611 Fax: 020 7587 3210 IMO E Ref. T5/1.01 MEPC.1/Circ.642 12 November 2008 2008 REVISED GUIDELINES FOR SYSTEMS
Iron and Steel Manufacturing
Pollution Prevention and Abatement Handbook WORLD BANK GROUP Effective July 1998 Iron and Steel Manufacturing Industry Description and Practices Steel is manufactured by the chemical reduction of iron
Birmingham City University / Students Union Aspects and Impacts Register. Waste. Impacts description
Birmingham City University / Students Union and Impacts Register Waste Production of non - hazardous waste Production of hazardous waste Storage of non - hazardous waste Potential for waste to be disposed
Biogas and landfill gas utilization in Helsinki region waste management. Aino Kainulainen Project Manager Helsinki Region Environmental Services HSY
Biogas and landfill gas utilization in Helsinki region waste management Aino Kainulainen Project Manager Helsinki Region Environmental Services HSY Mission statement Purely better, every day We are responsible
Large Biogas Plants in Denmark -technology and operation experience
Large Biogas Plants in Denmark -technology and operation experience September 9 2004 by Anne Seth Madsen, [email protected] 1 NIRAS Agenda NIRAS Large Biogas Plants in Denmark Large Biogas Plants concept and
Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service
Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components
Provided below is a description of the processes generating wastewater in a poultry plant and a typical pretreatment and full treatment system.
II. PROCESS OVERVIEW Provided below is a description of the processes generating wastewater in a poultry plant and a typical pretreatment and full treatment system. II.1. Wastewater Generation A typical
Carbon Footprint of CMC Hospital for 2013
Carbon Footprint of CMC Hospital for 2013 Carbon footprint of CMC Hospital campus was estimated for the year 2011 and 2012 and the total CO2e emission was estimated at 15271.74 CO2e tons and 15456.61 CO2e
Which of the following can be determined based on this model? The atmosphere is the only reservoir on Earth that can store carbon in any form. A.
Earth s Cycles 1. Models are often used to explain scientific knowledge or experimental results. A model of the carbon cycle is shown below. Which of the following can be determined based on this model?
Sustainable production of biogas and bioethanol from waste
Sustainable production of biogas and bioethanol from waste Waste - Resources on the wrong way Jens Ejbye Schmidt Head of programme NRG Biomass & Bioenergy Biosystem Division Risø The Technical University
Get Ready For The One Tonne Action Challenge!
Get Ready For The One Tonne Action Challenge! Read through the four elements of the one-tonne challenge - making a difference is easier than you think!! Watt's It All About? As our demand for electricity
WASTEWATER TREATMENT
Freshwater WASTEWATER TREATMENT Water Quality 1. INDICATOR (a) Name: Wastewater treatment. (b) Brief Definition: Proportion of wastewater that is treated, in order to reduce pollutants before being discharged
Environment Impact Assessment of Thermal Power Plant for Sustainable Development
International Journal of Environmental Engineering and Management. ISSN 2231-1319, Volume 4, Number 6 (2013), pp. 567-572 Research India Publications http://www.ripublication.com/ ijeem.htm Environment
Looking after your Septic Tank System
Looking after your Septic Tank System Name: Bought to you by Address: File this in your property file. 0800 TO FLUSH Call 0800 TO FLUSH 1 What do you know about your septic tank system? Just like your
PRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems
PRODUCT SELECTOR Pollution Control, Pumping and Rainwater Harvesting Systems PACKAGE SEWAGE TREATMENT SYSTEM Clearwater treatment plants are ideal for single houses and employ the well proven aerobic biological
Green Gases Practical concepts for reliable sustainable energy supply
Green Gases Practical concepts for reliable sustainable energy supply Ulrike Daniel, International Project Leader and Head of Consultancy EnD-I AG www.end-i.ag Your green energy supplier Landfill Gas Solar
Range of Biogas Plants designed by Krieg & Fischer Ingenieure GmbH
Range of Biogas Plants designed by Krieg & Fischer Ingenieure GmbH Torsten Fischer and Dr. Katharina Backes Krieg & Fischer Ingenieure GmbH Bertha-von-Suttner-Straße 9, D-37085 Göttingen, Germany Tel.:
William E. Dunn Water Reclamation Facility. Facility Overview & Information
William E. Dunn Water Reclamation Facility Facility Overview & Information General Area Served: Plant History Facility Highlights Northern Pinellas County St. Joseph Sound to East Lake Road (E/W) Tampa
ENVIRONMENTAL MANAGEMENT ACCOUNTING IMPLEMENTATION GUIDELINE
ENVIRONMENTAL MANAGEMENT ACCOUNTING IMPLEMENTATION GUIDELINE ENVIRONMENTAL MANAGEMENT ACCOUNTING IMPLEMENTATION GUIDELINE 1. Introduction This guideline follows the Implementation Rules for Company Environmental
1-Some related indicators: Total land area is 1 million Km 2. Only 3% of the land area is arable. The rest 97% is hyper arid desert. The whole lands a
BIO FUEL PRODUCTION IN EGYPT FROM PROMISES TO PRACTICES November 17, 2011 Dr. Ahmed Abd El-Ati Ahmed GBEP Egypt Focal Point 1-Some related indicators: Total land area is 1 million Km 2. Only 3% of the
Harvesting energy with fertilizers
Harvesting energy with fertilizers Sustainable agriculture in Europe 1 Harvesting energy with fertilizers The reason for agriculture s existence is to supply energy to mankind. Agriculture converts solar
aquateam Aquateam - Norwegian Water Technology Centre A/S Report no: 02-051 Project no: O-02033 Project manager: Dr. Bjørn Rusten.
Feasibility study of biological wastewater treatment plants with Salsnes Filter fine mesh sieve primary treatment compared to plants without primary treatment Aquateam - Norwegian Water Technology Centre
Natural and Advanced Treatment Systems for Wastewater Management at Municipal Solid Waste Disposal Site in Developing Countries
Natural and Advanced Treatment Systems for Wastewater Management at Municipal Solid Waste Disposal Site in Developing Countries C. Chiemchaisri Department of Environmental Engineering, Kasetsart University
OPTIONS FOR ENVIRONMENTAL SUSTAINABILITY OF THE CRUDE PALM OIL INDUSTRY IN THAILAND THROUGH ENHANCEMENT OF INDUSTRIAL ECOSYSTEMS
OPTIONS FOR ENVIRONMENTAL SUSTAINABILITY OF THE CRUDE PALM OIL INDUSTRY IN THAILAND THROUGH ENHANCEMENT OF INDUSTRIAL ECOSYSTEMS O. CHAVALPARIT 1, *, W.H. RULKENS 2, A.P.J. MOL 3 and S. KHAODHAIR 1 1 National
This fact sheet provides an overview of options for managing solid
What Is Integrated Solid Waste Management? This fact sheet provides an overview of options for managing solid waste, identifies the important issues you should consider when planning for solid waste management,
Nutrient Removal at Wastewater Treatment Facilities. Nitrogen and Phosphorus. Gary M. Grey HydroQual, Inc. [email protected] 201 529 5151 X 7167
Nutrient Removal at Wastewater Treatment Facilities Nitrogen and Phosphorus Gary M. Grey HydroQual, Inc. [email protected] 201 529 5151 X 7167 1 Agenda Nitrification and Denitrification Fundamentals
High-efficient gas boiler CompactGas
High-efficient gas boiler CompactGas Patented alufer for a high efficiency and low emission. 1 CompactGas (1000-2800). Advantages at a glance. The Hoval CompactGas fulfils all expectations with regard
Independent planners in fermentation
Technology and Knowhow about climate change and sustainable energy! Independent and sustainable engineering in the fields of biogas power plants and biomethane production Kuching, 2. December 2015, Hilton
MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES
MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES John van Rijn INDEVELOPMENT MAINTENANCE OF SMALL WATER SUPPLY, SANITATION AND IRRIGATION SCHEMES Any part of this publication may be
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS
ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF
SoCo: European Overview on soil degradation processes related to agriculture
SoCo Policy Seminar, Brussels, 28 May 2009 1 SoCo: European Overview on soil degradation processes related to agriculture by E. Rusco, L. Montanarella, B. Marechal JRC IES Land management and Natural Hazards
Bioremediation of Petroleum Contamination. Augustine Ifelebuegu GE413
Bioremediation of Petroleum Contamination Augustine Ifelebuegu GE413 Bioremediation Bioremediation is the use of living microorganisms to degrade environmental contaminants in the soil and groundwater
Town of New Castle Utility Department Introduction
Town of New Castle Utility Department Introduction Town of New Castle Utility Department Mission Statement Our commitment is to ensure that our customers receive high quality water and wastewater treatment
ALL YOU NEED TO KNOW...
ALL YOU NEED TO KNOW... What do you know about your septic tank system? For the purposes of this booklet, a septic tank system refers to any kind of on-site sewage management system including traditional
IWR Integrated Waste Recycling. Integrated System for treatment and recycling of Municipal Solid Waste
IWR Integrated Waste Recycling Integrated System for treatment and recycling of Municipal Solid Waste 1 1. Introduction IWR is an integrated system, realised by different Italian companies, manufacturers
E nv i ro n m e nta l. Biotec 5-7. Sustainable, Reliable, Affordable
E nv i ro n m e nta l Biotec 5-7 Package Sewage Treatment for Residential, Business & Leisure Applications Sustainable, Reliable, Affordable ENTEC BIOTEC 5-7 FROM KINGSPAN ENVIRONMENTAL Package Sewage
WASTE WATER TREATMENT SYSTEM (OPERATING MANUALS )
Page 1 of 76 1.0 PURPOSE The purpose of the Wastewater Treatment System is to remove contaminates from plant wastewater so that it may be sent to the Final Plant Effluent Tank and eventually discharged
12.5: Generating Current Electricity pg. 518
12.5: Generating Current Electricity pg. 518 Key Concepts: 1. Electrical energy is produced by energy transformations. 2. Electrical energy is produced from renewable and non-renewable resources. 4. Electrical
Report Naga City: Septage treatment and wastewater concept for Del Rosario
Report Naga City: Septage treatment and wastewater concept for Del Rosario For the regional project: Integrated Resource Management in Asian cities: the urban Nexus Deutsche Gesellschaft fur Internationale
Mercedes-Benz Biodiesel Brochure
Mercedes-Benz Biodiesel Brochure Contents Definitions of Bio-Based Diesel Fuel Main Quality Characteristics of Straight Biodiesel Risks from the use of Diesel Fuel Containing Biodiesel Impacts of Biodiesel
Brewing Beer efficient and sustainable technologies in regard to energy and raw material input
Brewing Beer efficient and sustainable technologies in regard to energy and raw material input ERSCP workshop, Bregenz, 3 May 2012 Dr. Ludwig Scheller, Dr. Rudolf Michel Huppmann Tuchenhagen Agenda Efficient
BMEI BMEI CO., LTD. Environmental Total Solution Vender. www.bmeiglobal.com
CO., LTD Environmental Total Solution Vender www.bmeiglobal.com COMPANY PROFILE More than 30 years of professional experience in environmental protection technology, the turnover is 150 Million USD in
Stora Enso Fors Ltd Sweden
THE ANALYSIS REPORT OF PLANT NO. 3 Cofiring of biomass - evaluation of fuel procurement and handling in selected existing plants and exchange of information (COFIRING) - Part 2 Stora Enso Fors Ltd Sweden
Electricity: biogas may be used to generate electricity using a gas electric generator set or natural gas boiler system. Electricity may either be
Electricity: biogas may be used to generate electricity using a gas electric generator set or natural gas boiler system. Electricity may either be used onsite or sold to the local utility. Heat: biogas
12:10 Lysotherm : 5 jaar ervaring met innovatieve slibhydrolyse. Bert Geraats (Eliquo)
LYSOTHERM A novel approach to thermal sludge hydrolysis 01.07.2015 ELIQUO WATER GROUP FACTS AND FIGURES STAFF HISTORY FIGURES >200 employees Engineers Technicians Sales, commercial staff 1986 ELIQUO WATER
10 Nuclear Power Reactors Figure 10.1
10 Nuclear Power Reactors Figure 10.1 89 10.1 What is a Nuclear Power Station? The purpose of a power station is to generate electricity safely reliably and economically. Figure 10.1 is the schematic of
www.klmtechgroup.com TABLE OF CONTENT
Page : 1 of 38 Project Engineering Standard www.klmtechgroup.com KLM Technology #03-12 Block Aronia, Jalan Sri Perkasa 2 Taman Tampoi Utama 81200 Johor Bahru Malaysia CAUSTIC AND CHEMICAL TABLE OF CONTENT
Module 16: The Activated Sludge Process - Part II Instructor Guide Answer Key
Unit 1 Process Control Strategies Exercise Module 16: The Activated Sludge Process - Part II Instructor Guide Answer Key 1. What are the six key monitoring points within the activated sludge process? Ans:
Swamp Area Passive Treatment System Kettle Creek Watershed, Clinton County, PA
Swamp AMD Chemistry Swamp Area Passive Treatment System Kettle Creek Watershed, Clinton County, PA A Technical Report for Trout Unlimited and the Kettle Creek Watershed Association Prepared by Hedin Environmental
Finland Biogas Update of the Global Methane Initiative (GMI) Tri-Subcommittee Meeting, Florianópolis Brazil
Finland Biogas Update of the Global Methane Initiative (GMI) Tri-Subcommittee Meeting, Florianópolis Brazil 14 March 2014 Ministry of Agriculture and Forestry, Finland 1 Finland Finland Surface area 338
MANURE COLLECTION AND TRANSFER SYSTEMS IN LIVESTOCK OPERATIONS WITH DIGESTERS. A. C. Lenkaitis GEA Farm Technologies Inc. (Houle USA), Naperville, IL
MANURE COLLECTION AND TRANSFER SYSTEMS IN LIVESTOCK OPERATIONS WITH DIGESTERS A. C. Lenkaitis GEA Farm Technologies Inc. (Houle USA), Naperville, IL INTRODUCTION Manure collection systems are influenced
The Value of Small Digester Technology
The Value of Small Digester Technology M. Charles Gould Extension Educator-Bioproducts and Bioenergy Agriculture and Agribusiness Institute Michigan State University SARE Carbon, Energy and Climate Conference
Compact Sewage Systems in France A technical and cost comparison
2010 Sewage System Approvals Introduction The methods of evaluating systems are fixed by a decree dated 7 th September 2009. All companies wishing to have a system approved must submit a file to the appropriate
Modification and Optimisation of Existing MBT Plants Using BTA Technology
Modification and Optimisation of Existing MBT Plants Using BTA-Technology 177 Modification and Optimisation of Existing MBT Plants Using BTA Technology Torsten Rahn*, Paolo Bozano Gandolfi** *BTA International
Developments and trends shaping the future for Waste-to- Energy technology suppliers
Developments and trends shaping the future for Waste-to- Energy technology suppliers 21 st October 2015 Copenhagen, Denmark Edmund Fleck ESWET President 2 Contents 1. About ESWET 2. Introduction 3. Modern
R-32. The next generation refrigerant for air conditioners and heat pumps
R-32 The next generation refrigerant for air conditioners and heat pumps Daikin is the first company in the world to launch heat pumps and air conditioners charged with R-32. This refrigerant has several
Technologies and trends for anaerobic digestion across Europe: : a survey
Technologies and trends for anaerobic digestion across Europe: : a survey Alberto Confalonieri Gruppo di Studio sul Compostaggio e la Gestione Integrata dei Rifiuti Scuola Agraria del Parco di Monza Anaerobic
Haldor Topsøe Catalysing Your Business
Haldor Topsøe Catalysing Your Business Haldor Topsøe A/S Established: 1940 Ownership: Haldor Topsøe Holding A/S (100%) Annual turnover: ~ 700 MM EUR Number of employees: ~ 2,050 Offices worldwide Copenhagen