1 Prolongation and Loss and Expense Claims For the Hong Kong Institute of Surveyors Mike Allen BSc FRICS MHKIS MCI Arb FA Cost E FAE CEDR Accredited Mediator 13 th February 2012
2 Contents Introduction The contract price structure Prolongation cost How to analyse such a claim Issues and methods to consider Summary How to present a prolongation claim Suggested further reading Mike Allen 13 th February
3 Introduction In common practice an extension of time is usually awarded before a prolongation or a loss and expense, claim is submitted (terms are interchangeable); The intention of the contract is to allow the Contractor to recover monetary compensation if there is a compensable delay that prevents the Contractor completing the contract work; Generally express or implied in most construction contracts: The client or its representatives shall not hinder or prevent the Contractor from performing his contract obligations; Acts by a client (e.g. instruction, variation order, open-up inspection, etc.) which cause delay to a contract may cause prolonged maintenance of resources by the contractor; Mike Allen 13 th February
4 Introduction (cont d) Therefore prolongation or loss and expense can be simply described as The reimbursement of costs (or rates) which are incurred as a result of delayed work activities. This generally relates to time related costs, such as supervisory staff and the associated support to maintain that supervision. Mike Allen 13 th February
5 Introduction (cont d) Prolongation is found in most construction contracts, which describe it as a reimbursement to which the Contractor is entitled under the provisions of the Contract in respect of prolongation and/or delay; Prolongation cost is not a disruption cost; Prolongation costs consist of the costs of on-site overheads and off-site overheads time related cost; Mike Allen 13 th February
6 The Contract Price Structure 40% 60% 70% DIRECT LABOUR DIRECT PLANT MATERIALS Direct Cost 30% O/H, O/H, PROFIT RISK GENERAL ITEMS, PRELIMS SUPERVISORY STAFF Indirect Cost 35% 65%
7 Prolongation Cost Check the terms of the Contract (what and how); So what is exactly a prolongation cost? Prolongation cost is generally the time (& not fixed) related cost; Time related costs normally represent the costs of the Contractor's site establishment, site overheads, general plant, etc. that are typically affected by a delay to the critical path of the construction work; So when can we claim prolongation cost? The entitlement to prolongation costs incurred as consequence of the delay greatly depends on the contract (variations and neutral events etc). Mike Allen 13 th February
8 Prolongation Cost (cont d) To put it into a simple case study: Party (A) suffers a loss which he is entitled to compensation from party (B) causing the 'injury' (for example a delay), the damages are to put (A) back into the position he was nominally in before the event. The prolongation costs shall be the costs that are actually incurred at the time the delaying events impacted the progress of the Works, instead of the period of extension; What must be priced is the effect of the delay, and it boils down to a clear analysis of the effects of the delay to ascertain the additional supervisory resources which are linked to the delayed events. Mike Allen 13 th February
9 Prolongation Cost (cont d) The SCL protocol says, with regards to this matter: the recoverable prolongation compensation is to be assessed by reference to the period in which the effect of the Employer Event Risk was felt It is clearly intended that, once it is established that additional payment is due for prolongation resulting from Client s delays, the evaluation should relate to the period when the effect of the delay occurs and not to the overrun period at the end of the contract. Mike Allen 13 th February
10 Prolongation Cost Summary What should surveyors look for: Check the contract; Be clear on the body of cost you are valuing; Be clear on what you are considering (prelims and resources affected by the events, that are time related); Value the actual period of delay (not the overrun period); Be guided by a general principle of reimbursement as a result of an event or but for. Mike Allen 13 th February
11 How to analyse such a claim Before the prolongation analysis is being considered, the maintenance of adequate records is an essential ingredient for supporting the prolongation claim; Some of the essential records that are required: Programme (initial plan working sequence and the subsequent changes due to the delaying event); Records of resources (dual if possible); Labour & Plant Schedules; Subcontract daily allocations; Site diary; Records to show any additional supervision mobilisation. Mike Allen 13 th February
12 How to analyse such a claim (cont d) The Contract FIDIC (1999 Edition) Time Extension of Time (GCC 8.4) The Contractor shall be entitled to an EoT if and to the extent that completion is or will be delayed Money Variations (GCC 12 and 13) Claims (GCC 20.1) Refers back to the body of the Contract Mike Allen 13 th February
13 How to analyse such a claim (cont d) The Contract Hong Kong Standard Form (Private Edition With Quantities 2005) Time Extension of Time (GCC 25) an event likely to cause delay to the completion of the Works Fixing new completion is being or is likely to be delayed Money Direct loss and/or expense (GCC27) GCC 27.1 If in the Contractor s opinion, he has incurred or likely to incur direct loss and/or expense GCC 27.2 Quantity Surveyor to ascertain the amount of any direct loss/and expense Mike Allen 13 th February
14 How to analyse such a claim (cont d) Mike Allen 13 th February
15 How to analyse such a claim (cont d) Identify & categorise the delaying event: Compensable delay events that entitle the contractor to an extension of time and to prolongation costs flowing from that event; Excusable delay events that entitle the contractor to an extension of time but where the contractor bears the risk of additional costs that may flow from that event; and Culpable delay events that do not entitle the contractor to either time or money Mike Allen 13 th February
16 How to analyse such a claim Cause Effect Inefficiency Extra Cost Delay...Project Overrun / Extra Cost Mitigation / Acceleration. Extra Cost Three problems that concern our clients; how to 1. Apportion and demonstrate responsibility for disturbance; 2. and link money with time; 3. and maximise certainty of outcome at proportionate cost. Mike Allen 13 th February
17 Issues to consider (cont d) A Employer Delay 1 Employer Delay 2 Delay 1 Impact Delay 2 Impact B C D E Contractor Delay Delay Impact Core Staff Non-Core Staff Prelims Total Delay 1 Delay 1 Linked Linked Time Time Related Related Costs Costs Site Records Site Records Audited Audited Cost Cost Data Data Variations (Overheads) Variations (Overheads) SITE WIDE STAFF ACTIVITY RELATED STAFF SUPPORT AND WELFARE ISSUE ISSUE Delay 2 and relationship with Delay 3 Delay 2 and relationship with Delay 3 CONCURRENCY CONCURRENCY DOMINANT DOMINANT CAUSE CAUSE PROXIMATE CAUSE PROXIMATE CAUSE APPORTIONMENT APPORTIONMENT Mike Allen 13 th February
18 Summary Before valuing the reimbursable cost, how do we determine the level of recovery? The level of recovery of damages for breach of contract is intended, so far as is possible, to put the Contractor in the same position he would have been if he had not sustained the delay for which he is now seeking compensation; When a claim is made under the contract, the specific entitlement that the parties have agreed needs to considered in order to establish the level of costs to which the Contractor will be entitled if he can prove his losses (cost or rates); Mike Allen 13 th February
19 Summary (cont d) What needs to be extracted when preparing a prolongation claim? Identify costs which are recurring and can be identified as being related to ongoing activities or commitments which are, or have been, prolonged as a consequence of the delaying event; What are recurring Site Costs? site staff, site offices, maintenance of site office, utilities, equipment, plants, insurance, etc; Some quarterly/annual costs sensibly should be averaged; Contractor s own & hired plant needs careful consideration; Head office overhead claims (typically formula calculated); Overhead duplication reviews (Variations). Mike Allen 13 th February
20 How to present a Prolongation claim General considerations What the contract says; Objective and audience; Use graphics to assist the explanation; Type of disturbance; Forum for debate; Information available; Timing before or after completion; Proportionality; Clear, simple and substantiated. Mike Allen 13 th February
21 Further suggested reading Prolongation claims and issues related thereto: Henry Boot Construction (UK) Ltd v Malmaison Hotel (Manchester) Ltd [1999] 70 Con LR 32 Royal Brompton Hospital NHS Trust v Hammond and Ors (No.7) [2001] 76 ConLR 148 Laing Management (Scotland) Ltd v John Doyle Construction Ltd [2004] BLR 295 City Inn v Shepherd Construction Ltd [2007] CSOH 190 Society of Construction Law (SCL) Protocol (2002) SCL Paper - Prolongation Claims in Construction Contracts Cost or Value? (2004) by J Battersby. J Molloy and M Charlton Mike Allen 13 th February
22 Mike Allen 14 February
Construction Claims in
Construction Claims in the Gulf ICES CPD Event 12/2012 ADMC Auditorium 19 December 2012 DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Context» Aftermath of 2008 / 2009 financial
Time bars in construction and global claims
Simon Tolson and Jeremy Glover Time bars in construction and global claims Time bars in construction contracts Introduction 1. 2. There is an increasing tendency in construction contracts to include time
Recovery of Overhead and Profit when delay occurs
Recovery of Overhead and Profit when delay occurs When a Contractor has established a right to an extension of time which also carries a right to reimbursement of costs for the delay to his Works, then
Peter D Aeberli. Barrister - Arbitrator - Mediator Adjudicator. The Waiting Game: Extensions of Time
Peter D Aeberli Barrister - Arbitrator - Mediator Adjudicator The Waiting Game: Extensions of Time Determining extensions of time can be as sophisticated an art as designing a building in the first place.
Delay, Disruption and Acceleration Costs
Project Services Pty Ltd Delay, Disruption and Acceleration Costs Patrick Weaver FAICD, MCIOB, PMP Introduction Delay and disruption costs are common in the construction and engineering industries and
Hong Kong Institute of Surveyors. Seminar on Conditions of Building Contract Questions and Answers Conducted by Mr. Colin B. Lee
Hong Kong Institute of Surveyors Seminar on Conditions of Building Contract Questions and Answers Conducted by Mr. Colin B. Lee 8/F, Tung Chiu Commercial Central 193 Lockhard Road, Wanchai Hong Kong 13
Who pays the Money for the Time?
Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency
Back to Basics: Professional Indemnity Construction and Engineering
Back to Basics: Professional Indemnity Construction and Engineering December 2015 Table of Contents Table of Contents... 2 Introduction... 3 Part A - Understanding the construction industry... 4 1 Construction
PRACTICE NOTES FOR QUANTITY SURVEYORS
PRACTICE NOTES FOR QUANTITY SURVEYORS Preface Preface A Working Committee with representatives of the Hong Kong Institute of Surveyors, the Association of Consultant Quantity Surveyors and the Hong Kong
Scheduling Best Practices
RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding
International Accounting Standard 11 Construction Contracts
International Accounting Standard 11 Construction Contracts Objective The objective of this Standard is to prescribe the accounting treatment of revenue and costs associated with construction contracts.
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
Bills of Quantity. D. Atkinson December 2000. Nature of Bills
Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and
Construction Contracts
STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.
Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee. 21 March 2011 & 23 March 2011
Understanding variations a contractor's perspective Jonathan Brooks, Tim Tapper, Andrew Ash & Stuart McGee 21 March 2011 & 23 March 2011 Introduction Jonathan Brooks osborneclarke.com osborneclarke.com
How To Account For Construction Contracts In Hong Kong Kongsong Accounting Standard 11
HKAS 11 Issued October 2004Revised March 2010 Hong Kong Accounting Standard 11 Construction Contracts COPYRIGHT Copyright 2011 Hong Kong Institute of Certified Public Accountants This Hong Kong Financial
1 Supplement: IAS 11 Construction contracts
1 Supplement: IAS 11 Construction contracts Introduction In this section we introduce construction contracts. We will look at the required treatments and disclosures under IAS 11. Make sure that you work
7 Contract Costing. Basic Concepts. Contract Costing
7 Contract Costing Basic Concepts Contract Costing Sub-contract Extra work Work Certified Value of Work Certified Cost of work certified Work uncertified Progress Payment Contract costing is a form of
Contractors Claims for Loss and Expense under the Principle Traditional Forms of Irish Building Contract
Dublin Institute of Technology ARROW@DIT Other Resources School of Surveying and Construction Management 2014-03-31 Contractors Claims for Loss and Expense under the Principle Traditional Forms of Irish
GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses
GUIDANCE NOTE 1.5.2 Cost Control: Price Variation Clauses Office of Government Procurement Cost Control: Price Variation Clauses Document Reference GN 1.5.2 v1.0 22 January 2016 2016 Department of Public
BASIC CONCEPTS AND FORMULAE
7 Contract Costing BASIC CONCEPTS AND FORMULAE Basic Concepts 1. Contract costing:- Contract or terminal costing, as it is termed, is one form of application of the principles of job costing. In fact a
MR GREGORY YAU-MING TUNG. (Bachelor of Science in Quantity Surveying with Honours) (Date of Qualification 1987)
CURRICULUM VITAE Name : MR GREGORY YAU-MING TUNG Qualifications: BSc(QS)(Hons) (Bachelor of Science in Quantity Surveying with Honours) (Date of Qualification 1987) LLM (Master of Laws) (Date of Qualification
NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS
NAS 13 NEPAL ACCOUNTING STANDARDS ON CONSTRUCTION CONTRACTS CONTENTS Paragraphs OBJECTIVE SCOPE 1 2 DEFINITIONS 3 6 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 7 10 CONTRACT REVENUE 11 15 CONTRACT
NEC Users Group Workshop Defined Cost
NEC Users Group Workshop Defined Cost [email protected]; July 2014 Turner & Townsend plc July 14 making the difference Introduction Practicalities in assessing of Defined Cost & Disallowed Cost Assumption
GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE. Section 1: Lost property and lost earnings are treated separately
GETTING (BACK TO) BUSINESS INTERRUPTION INSURANCE Section 1: Lost property and lost earnings are treated separately Business interruption insurance (also known as business income protection, profit protection,
A Guide to Small Works. A brief explanation
A Guide to Small Works A brief explanation A Guide to House Extensions/Small Works - a brief explanation Small works are an ongoing, cherished part of DDC's activity and restricted only by distance. Here
Service Level Commitment to Insured Employers
Service Level Commitment to s Hotel Employers Mutual Ltd ABN 34124091470 Hotel Employers Mutual Limited(HEM) is the specialised insurer for the hospitality industry and it is our objective to provide our
International Accounting Standards
International Accounting Standards The Key Issues in IAS 2 and 11 Background In this second of my series on international accounting standards, I have chosen to look at the two standards covering the topic
Tipsheet 11 Hired-In Labour
Tipsheet 11 Hired-In Labour Client version May 2009 Updated January 2011 Contracts for labour hire what are the insurance issues when using hired in workers? What is hired in labour? Under a labour hire
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344
Position Classification Standard for Management and Program Clerical and Assistance Series, GS-0344 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 OCCUPATIONAL INFORMATION... 3 TITLES... 6 EVALUATING
The following Accounting Standards Interpretation (ASI) relates to AS 7. ASI 29 Turnover in case of Contractors
108 Accounting Standard (AS) 7 (revised 2002) Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT
Marginal and. this chapter covers...
7 Marginal and absorption costing this chapter covers... This chapter focuses on the costing methods of marginal and absorption costing and compares the profit made by a business under each method. The
NZQA registered unit standard 25872 version 2 Page 1 of 5. Develop and implement a project plan to deliver on an Infrastructure works contract
Page 1 of 5 Title Develop and implement a project plan to deliver on an Infrastructure works contract Level 5 Credits 15 Purpose People credited with this unit standard are able to: explain relationship
Report of the Employment Status Group - PPF
Introduction Report of the Employment Status Group - PPF This document has been prepared by the Employment Status Group set up under the Programme for Prosperity and Fairness (PPF). The group was set up
NORWEGIAN SUBSEA CONTRACT NSC 05 CONDITIONS OF CONTRACT
NORWEGIAN SUBSEA CONTRACT NSC 05 Introduction to NSC 05 The Norwegian Subsea Contract 05 (NSC 05) is a set of standard conditions developed for contracting within the subsea segment, on the Norwegian continental
STATEMENT OF INSOLVENCY PRACTICE 9 (SCOTLAND) REMUNERATION OF INSOLVENCY OFFICE HOLDERS
STATEMENT OF INSOLVENCY PRACTICE 9 (SCOTLAND) REMUNERATION OF INSOLVENCY OFFICE HOLDERS 1 INTRODUCTION 1.1 This Statement of Insolvency Practice (SIP) is one of a series issued to licensed insolvency practitioners
Construction Contracts
65 Accounting Standard (AS) 7 Construction Contracts Contents OBJECTIVE SCOPE Paragraph 1 DEFINITIONS 2-5 COMBINING AND SEGMENTING CONSTRUCTION CONTRACTS 6-9 CONTRACT REVENUE 10-14 CONTRACT COSTS 15-20
Capital Projects. Providing assurance over effective delivery of projects
Capital Projects Providing assurance over effective delivery of projects Governance and oversight Project Scope and change Reporting and communication Project risk and success factors Delivery Major projects
Accounting for Administrative Overhead In oil and Gas Upstream Industry
Accounting for Administrative Overhead In oil and Gas Upstream Industry Hamdy Rashed, CMA; CAPM Bsc of Accounting and Auditing,, E-mail: [email protected], Website: http://www.accountingsoul.com/
CONTRACT FOR PAYROLL SERVICES. It is agreed by clicking on Acknowledge on the PayMe Australia Pty Ltd Contractors Join Online Form:
CONTRACT FOR PAYROLL SERVICES Introduction This Agreement records the terms and conditions by which the Company has been engaged by the Contractor to perform payroll services for the Contractor. It is
CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS
CONDITIONS FOR SUPPLY OF SKIPS AND CONTAINERS AND FOR THE DISPOSAL OF THE CONTENTS OF THE SKIPS AND CONTAINERS 1. Definitions 1.1 In these Conditions: "Contract" means the contract between Peak Waste Recycling
Sri Lanka Accounting Standard -LKAS 11. Construction Contracts
Sri Lanka Accounting Standard -LKAS 11 Construction Contracts -405- Sri Lanka Accounting Standard -LKAS 11 Construction Contracts Sri Lanka Accounting Standard LKAS 11 Construction Contracts is set out
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices
[Project Name] NZTA Contract No. [Contract Number] Schedule of Prices Schedule of Prices SP1
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects
Productivity: Measurement, Improvement and its Role in Mitigating the Risks of Dispute in Construction Projects Dr. Rashad Zakieh (PMP) 27 April, 2010 Copyright Saudi Aramco, 2010. All rights reserved.
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
Where to Begin 1. What You Need to Know Once You ve Been Injured 2. The People Playing a Role in Your Recovery 5
Where to Begin 1 Contents What You Need to Know Once You ve Been Injured 2 The People Playing a Role in Your Recovery 5 Why You Need a Personal Injury Lawyer 8 Frequently Asked Questions 11 Recovery Diary
Impacts on the construction industry of the new revenue standard
IFRS Impacts on the construction industry of the new revenue standard September 2014 kpmg.com/ifrs Contents The devil is in the detail 1 1 Critical judgements at contract inception 2 1.1 Pre-contract costs
Contractor / Self-employed Person?
Employee? Contractor / Self-employed Person? To avoid misunderstanding or dispute, the relevant persons should understand clearly their mode of cooperation according to their intention and clarify their
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, Claims & Counterclaims
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, 469 (ECCM Workshops 3, 4 & 5) Certified Program التقنيات العملية في إعداد الجدول الزمني والمالي اإلدارة الموقعية
CAPITAL PROJECTS IMPLEMENTATION
CAPITAL PROJECTS IMPLEMENTATION 2.4 Over the years, I have been reporting on the shortcomings encountered during implementation of projects. These include, among others, excessive delays, variation costs,
CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK
CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK SUMMARY The FIDIC Conditions are used extensively on international
Basic Guide. General Conditions of Contract for Construction Works (GCC 2004)
Basic Guide General Conditions of Contract for Construction Works (GCC 2004) February 2008 Preface The Construction Industry Development Board (CIDB) is a national body established by an Act of Parliament
GOVERNMENT OF MALAYSIA
GOVERNMENT OF MALAYSIA Malaysian Public Sector Accounting Standards MPSAS 11 Construction Contracts March 2015 MPSAS 11 Construction Contracts Acknowledgment The Malaysian Public Sector Accounting Standard
Appendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
Commercial leases and insurance claims
Commercial leases and insurance claims by the CILA Property Special Interest Group 31st May 2016 Introduction This paper is intended as a guidance document to understanding commercial leases, particularly
Principles for Remedy
Principles for Remedy Principles for Remedy Public Services Ombudsman for Wales 1 Ffordd yr Hen Gae, Pencoed CF35 5LJ Tel. 01656 641150 Fax: 01656 641199 E-mail: [email protected] Website: www.ombudsman-wales.org.uk
Schedule of Prices. Project Name Contract No. Contract Number
Schedule of Prices Project Name Contract No. Contract Number C3-LS-BP-Issue 2 SP Page 1 Printed 1 March 2011 >: 1. When preparing the schedule
WELCOME Best Practices for Managing Construction Delay and Interference Claims
WELCOME Best Practices for Managing Construction Delay and Interference Claims Kenneth A. Slavens 314.345.6419 Husch Blackwell LLP Topics to be covered Delay Acceleration Disruption Delay Impact on Project
THIS AGREEMENT is made effective as of this day of in the year of.
STANDARD FORM OF CONSTRUCTION MANAGEMENT AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER (Where the basis of payment is Cost of the Work with a guaranteed maximum price) THIS AGREEMENT is made effective
CONTRACT CONDITIONS FOR LOGISTICS (2014)
CONTRACT CONDITIONS FOR LOGISTICS (2014) The Company provides all items and services on the following Conditions which can be varied only in writing by an Officer of the Company. The Company is a member
RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS
RBI Asset Management (Pty) Ltd P O Box 7192 Halfway House 1685 Tel: 011 805 7933 Fax: (086) 675-9194 E-mail: [email protected] RBI ASSET MANAGEMENT STANDARD CONDITIONS OF BUSINESS 1. DEFINITIONS These Conditions,
Report Building Procurement Methods
Report Building Procurement Methods Research Project No: 2006-034-C-02 The research in this report has been carried out by Project Leader Researchers Project Affiliates Peter Davis Peter Davis Peter Love
Construction Contracts
Compiled Accounting Standard AASB 111 Construction Contracts This compiled Standard applies to annual reporting periods beginning on or after 1 January 2009 that end on or after 30 June 2009. Early application
Applicability / Objective
By Rakesh Agarwal Applicability / Objective APPLICABILITY: applicable to all contracts entered into on or after 1-4-2003 and is mandatory in nature from that date. Based on AS 7 (Construction Contracts)
THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $20 1999 EDITION
THE GOVERNMENT OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION GENERAL CONDITIONS OF CONTRACT FOR BUILDING WORKS $20 1999 EDITION Printed by the Printing Department 1594862 50L 11/99 (Printed on paper made
How To Advise The Director Of Legal Aid
Chapter 7 Guidance Notes to Solicitors Handling Civil Cases 1. Purpose 1.1 These notes are intended to provide guidance on the salient points that you, as solicitor, should pay attention to when advising
NAB CONNECT MERCHANT TRANSACTION REPORTING SERVICE
NAB CONNECT MERCHANT TRANSACTION REPORTING SERVICE Terms and Conditions effective 21.05.07 30091_merch_transact (05/07) Contents Meaning of Words 2 Conditions of Use 2 Liability 3 Fees and Charges 4 Termination
International Financial Reporting. Construction Contracts IAS 11
Construction Contracts IAS 11 2 Construction contract definition Construction Contract is a contract specifically negotiated for the construction of an asset (a building, a bridge) or a combination of
ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS)
ELECTRICITY NORTH WEST LTD GENERAL CONDITIONS OF CONTRACT (BUSINESS) 1. Definitions In these Conditions: "Acceptance Form" means the acceptance form provided by Us to You with the Contract Documentation;
How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner
SHORT FORM PRIME CONTRACT BETWEEN OWNER & CONTRACTOR This Agreement ( Contract ) is made this day of, 20, between ( Contractor ) and ( Owner ) at The work described in Section 1 below shall be performed
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR
CONTRACT FOR THE APPOINTMENT OF AN APPROVED INSPECTOR CIC/AppInsp The Construction Industry Council - Association of Consultant Approved Inspectors contract for the appointment of an approved inspector
Summary. Chapter Five. Cost Volume Relations & Break Even Analysis
Summary Chapter Five Cost Volume Relations & Break Even Analysis 1. Introduction : The main aim of an undertaking is to earn profit. The cost volume profit (CVP) analysis helps management in finding out
Rehabilitation and Return to Work Policy. Overview. Purpose. Scope. Policy
Rehabilitation and Return to Work Policy Overview At NBN Co we are safe, disciplined and reliable. We act on our responsibilities to identify and remove potential and recognised risk to a healthy and safe
Letters, Instructions, etc.
Letters, Instructions, etc. Michael Dunn FRICS FCIArb LLB LLM T: 02079 976 520 and 01274 693 622 E: [email protected] www.rpp.co.uk Delivering Professional Solutions to the Property Industry Introduction
Project manager services
Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism
PPC2000 Contracts RICS East of England and CIOB - Framework and Partnering Agreements CPD 21 June 2010 Richard Cooke. Contents.
PPC2000 Contracts RICS East of England and CIOB - Framework and Agreements CPD 21 June 2010 Richard Cooke Contents Background Parties and Contracts Documents Early Involvement Pre-Construction Phase Construction
Statement of Guidance: Outsourcing All Regulated Entities
Statement of Guidance: Outsourcing All Regulated Entities 1. STATEMENT OF OBJECTIVES 1.1. 1.2. 1.3. 1.4. This Statement of Guidance ( Guidance ) is intended to provide guidance to regulated entities on
Civil Law (Wrongs) (Proportionate Liability and Professional Standards) Amendment Act 2004
Australian Capital Territory Civil Law (Wrongs) (Proportionate Liability and Professional Standards) Amendment Act 2004 Contents Page 1 Name of Act 2 2 Commencement 2 3 Legislation amended 2 4 New chapter
What amount of damages is the plaintiff entitled to recover from the defendant? 1
Page 1 of 5 745.07 NEW MOTOR VEHICLES WARRANTIES ACT ( LEMON LAW ) DAMAGES WHEN NOTE WELL: Appendices contain worksheets that the Court may want to provide to the jury, but it is not mandatory to do so.
Third Party Supplier Security
Third Party Supplier Security Managing risk and compliance through external due diligence audits. Presented by: Stephen Higgins 6 th December 2012 To cover When third party supplier security goes wrong...
Liquidated and unliquidated damages
Investing in Infrastructure International Best Legal Practice in Project and Construction Agreements January 2016 Damian McNair Partner, Legal M: +61 421 899 231 E: [email protected] Liquidated
Consultation Document. Reducing the number and costs of whiplash claims. Response from:
Consultation Document Reducing the number and costs of whiplash claims Response from: British Vehicle Rental and Leasing Association River Lodge Badminton Court Amersham BUCKS HP7 0DD Tel: +44 1494 434747
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table
ATTACHMENT 6.02 Generalist Compliance Matrix 2015
ATTACHMENT 6.02 Generalist Compliance Matrix 2015 Nominal Insurer And Schedule 6 - Attachment 6.02 (Compliance Matrix) Page: 1 of 5 s/ Strategic Audits Financial Returns Monthly Attachment L.01 (Internal
CONTRACTING HINTS AND TIPS
CONTRACTING HINTS AND TIPS Contents 1. Contract formation 2. Entire agreement clauses 3. Warranties and indemnities 4. Time of the essence 5. Contract variation 6. Exclusion and limitation clauses 7. Exercising
BMT Tax Depreciation Pty Ltd - Terms of Engagement
BMT Tax Depreciation Pty Ltd - Terms of Engagement 1.0 Definitions and Interpretation 1.1 In this document, unless the context indicates a contrary intention: Agreement means these Terms of Engagement
The South African Council for the Project and Construction Management Professions (SACPCMP)
The South African Council for the Project and Construction Management Professions (SACPCMP) Registration Rules for Professional Construction Mentors in terms of Section 18(1) (c) of the Act, 2000 (Act
Optimization of Clinical Engineering in Private Healthcare
Optimization of Clinical Engineering in Private Healthcare Speaker: James Herbert Organisation: Medi-Clinic Southern Africa Job Title: Technical Specialist - Clinical Engineering About the Speaker: James
Cost VOLUME RELATIONS & BREAK EVEN ANALYSIS
1. Introduction The cost volume profit (CVP) analysis helps management in finding out the relationship of costs and revenues to profit. Cost depends on various factors like Volume of production Product
Technical Journal. Paper 142
Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager
Taking Action. Dispute resolution, legal action and claims for negligence
Taking Action Dispute resolution, legal action and claims for negligence Taking Action Part 3: Dispute Resolution, taking legal action and claims for negligence Introduction If you believe an architect
Marginal Costing and Absorption Costing
Marginal Costing and Absorption Costing Learning Objectives To understand the meanings of marginal cost and marginal costing To distinguish between marginal costing and absorption costing To ascertain
Are you covered? Coverage issues for construction professionals Part 2
Professional Risks - Construction Part 2 June 2015 Are you covered? Coverage issues for construction professionals Part 2 In this two part guide we will be looking at issues that frequently arise when
Professional Development Programme on Enriching Knowledge of the Business, Accounting and Financial Studies (BAFS) Curriculum
Professional Development Programme on Enriching Knowledge of the Business, Accounting and Financial Studies (BAFS) Curriculum Course 1 : Contemporary Perspectives on Accounting Unit 7 : Marginal and Absorption