Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant
|
|
- Allison Easter Lamb
- 7 years ago
- Views:
Transcription
1 Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant By Ginger Gillin, John Pizzimenti, and Doug Foss, GEI Consultants, Inc., USA, and Jon Jourdonnais, PPL Montana, USA. Abstract The Mystic Lake Project is a high elevation hydroelectric project adjacent to a pristine Rocky Mountain wilderness. On December 17, 2007 the Federal Energy Regulatory Commission issued PPL Montana (PPLM) a new License to continue operating Mystic under FERC s new Integrated Licensing Process. This high head project diverts water from Mystic Lake via pipeline, surge tower and penstocks across steep and geologically active terrain. PPLM needed to demonstrate that it had historically protected the fishery in the two-mile bypass reach and tailwaters and would continue to do so in the future. Additionally, PPLM needed to demonstrate they could protect the aquatic resources in the event of failure of the flowlines. This paper describes how the utility (1) effectively studied the aquatic resources, (2) assessed past effectiveness of their operations and (3) improved the reliability of the project to protect those resources in the future. They accomplished this by building trust Figure 1. Mystic Lake Dam and Reservoir. and consensus with a large stakeholder group who amazingly achieved its collective goals without sacrificing any of the energy or capacity benefits nor the environmental attributes the project has provided since PPLM and stakeholders found ways to maintain the Mystic Project s renewable and peaking power resources and simultaneously meet other important public goals of protecting the natural resources and providing recreational opportunities. Overview Constructed in 1927 in an extreme environment not far from Yellowstone National Park, Mystic Lake is a remarkable example of early 20th century hydropower. Mystic Lake Dam at elevation 7673 feet is in the headwaters of West Rosebud Creek. It took tenacity to overcome the steep, dangerous topography and snowy winters at this high elevation Rocky Mountain site. The 10 Mw powerhouse is 2.3 miles downstream of the dam at elevation 6550 feet. This project develops 1100 feet of head and operates in a peaking mode during the low flow seasons. The elevated storage lake can be drawn down up to 60 feet for winter capacity and energy use. 1
2 On December 17, 2007 the Commission issued the Mystic Project a new license, the first under FERC s new Integrated Licensing Process, or ILP. The bypass reach of West Rosebud Creek between the dam and powerhouse contains a valuable rainbow and brown trout recreational fishery. Previous studies in the bypass reach established a minimum instream flow of 10 cfs between June 1 and September 1, and a 3 cfs flow the rest of the year. They also established a minimum flow of 20 cfs downstream of the Figure Mile Bypass Channel. Elevational profile of the West Rosebud Creek bypass reach. The yellow square at approximately 7,100 ft represents where Maxie Creek enters West Rosebud Creek. project and re-regulated power discharges to reduce peaking fluctuations in the lower river. The project is also a target destination of white water boaters for the June-July runoff. Using consensus based study approaches in the ILP and negotiated settlements based on data, the participants and FERC agreed, to maintain the same historic instream flows to protect the healthy fishery. The aquatic study team however also recognized a failure of the flow line could impact the fishery and aquatic habitats of both the bypass and mainstem river downstream of the hydro. Rock and Ice avalanches are known in the area and could rupture the penstock and cutoff flows to the powerhouse as well as the bypass reach and lower river. Should disruption occur at normal pool elevation the spillway would operate to protect the instream flows. In winter however, when Mystic Lake is below spillway elevation, the project has no mechanism to quickly restore instream flows to the bypass or tailwaters. PPLM s engineers have come up with a solution to bypass the flow line with a new valve at the outlet of the rock tunnel not far from the dam. A 60-inch flow line emerges from the tunnel onto a narrow rock ledge. The site and conditions create numerous Figure 3. Doug Foss inspecting Mystic Lake Penstock via Cable Car Rail Line. 2
3 challenges to design and construct a sufficiently large valve system that would operate under the extreme conditions of a runaway failure under sub-freezing conditions without power. Challenges include (1) potential need for the largest of air cranes (Sikorsky helicopters) for up to a 15 ton valve system; (2) need for erection and maintenance cranes; (3) need for protection from avalanches and rock falls and (4) a remotely controlled but automated system capable of closing under runaway mode. Instream Flow Concerns West Rosebud Creek-Mystic Lake hydrology has an early summer snowmelt driven peak with a low flow winter condition that can actually reach zero discharge due to total freeze up in the upper elevations. The hydropower operations reduce the peak discharge by refilling the reservoir after a gradual 60-foot winter drawdown. Downstream of the project there are two recreational lakes, West Rosebud Lake which has a re-regulating dam and spillway and Emerald Lake downstream of that. Under the previous FERC License PPL had committed to a minimum flow of 20 cfs all year downstream of West Rosebud Lake. Thus historically there was 20 cfs continuously from winter power operations when natural flows might otherwise drop to a fraction of this amount due to freezing conditions. The project was also diverting flows around a steep two-mile section of West Rosebud Creek known as the bypass reach. The key aquatic resource questions were then: what effects, positive or negative were these historic operations having on the resources in the bypass? Historic instream flows in the bypass in the previous license were 10 cfs summer (June 1 - August 31) and 3 cfs all other times. This is significantly less flow than would be present without the project. But there were times when the natural winter inflows may have dropped to zero due to extremely low temperatures. Therefore, two key questions were (1) what affects if any, was is the historic instream flow having and (2) had the project maintained its required flows during the past 30 years? In addition, concerns were raised about a lack of ramping rates in the bypass reach, particularly on August 31, when flows would be adjusted from 10 cfs to 3 cfs potentially stranding fish and dewatering macroinvertebrates. Study Plans and Results Hydrologic Records The consulting team digitized all the minimum flow, USGS hydrology and powerhouse discharge records from the past 30 years. When averaged, the project was diverting close to an average of 5 cfs during the low flow season and more than 10 cfs during the summer season. They identified that with the exception of about a total of 52 days during the past quarter century, the project had met its minimum 3 cfs flow bypass requirements. It met nearly all of its 10 cfs summer minimum flow records and any transgressions were minor. Detailed study of the 3 cfs flow violations occurred during two extreme events in two separate winters when the entire system froze and there were no flows entering Mystic 3
4 Lake. There was no evidence that flows had ever dropped to zero in the bypass at any time. Flows of 20 cfs downstream of West Rosebud Lake were likewise historically being met consistently by the project since the construction of the re-regulating dam. The automated re-regulating gate system enabled excess flows to pass. The storage in West Rosebud Lake was sufficient to maintain a minimum discharge of 20 cfs during periods when the powerhouse was not generating. Fishery Populations and Aquatic Habitat The Aquatic Resource Team debated the need for hydraulic models of the bypass habitat and concluded that assessment of the condition of the actual fishery would be the first indicator of the health of the fishery. In addition, the Team agreed to sample and assess the physical habitat of riffles and pools under low flow conditions to determine the extent of usable trout habitat in the bypass reach. Data showed that rainbow trout occupied lower, middle and upper reaches of the bypass wherever slopes were sufficient to create pool habitat (Table 1). Minimum flows appeared adequate to keep these pools full given the hydraulic gradients and geology of the streambed. Total Length Inventoried (ft) Width (ft) Pool Depth (ft) Crest Depth (ft) Riffle Depth (ft) Pocket Pool Depth (ft) Available Spawning Gravel ft^2 Pool to Riffle Ratio Lower Reach :1 Middle Reach :1 Upper Reach :1 Total NA NA NA NA NA NA NA NA NA Table 1. Summary statistics for the November modified R1/R4 habitat survey conducted in the bypass reach of West Rosebud. Creek. Rainbow trout inhabited Mystic Lake and presumably could and did colonize the upper bypass reaches via the spillway. Brown trout which were extant only downstream of the powerhouse were able to colonize the lower bypass areas up to the first major waterfall barrier. Impassable waterfalls occurred throughout sections of the bypass and restricted brown trout to the lower most reach of the bypass Sampling showed healthy populations of rainbow trout in Mystic Lake and rainbow and brown trout in the two lakes downstream of the powerhouse. They also showed densities among the highest known for the state for a stream of this size in the bypass reach. The presence of all life history stages from juvenile through reproductive size adults demonstrated that the system was self-sustaining. These fishery data led to conclusions that instream flows had been protective and that power operations including re-regulation had been prudent in protecting the fisheries around the project area since the last license conditions were imposed. 4
5 Downstream of the re-regulating dam in the mainstem river, habitat assessment showed good trout habitat at low flow conditions. Historic data on the fishery from Montana Fish, Wildlife, and Parks data indicated that this population was healthy, self sustaining and being protected if not enhanced by the 20 cfs minimum flows provided by re-regulated discharges. Herpetology experts conducted aquatic habitat surveys for herptile species around the project and determined no critical habitat exists for sensitive species. At the request of the U.S. Forest Service, the consulting team conducted an analysis of project affects on overall system hydrology using the Nature Conservancy method known as Indicators of Hydrologic Alteration or IHA (Smythe Scientific, version 7, 2005: www:weba.viawest.net/users/csmythe). The greatest change in hydrologic regime below the project was determined to be slightly lowered average peak discharge as a result of storage operations. Therefore, no change in the minimum instream flow was proposed. Riparian biologists conducted plant surveys downstream of the project also to determine if the altered hydrology was affecting habitat. The riparian habitats were found to contain healthy populations of native cottonwoods and other species. Those few altered areas were correlated with land disturbances from livestock and other ranching activities. Plans to monitor riparian conditions were included in the FERC License conditions. Figure 4. View of Mystic Lake and Absorkee. Conclusions The historic and existing minimum flow operations both in the bypass and the reregulated reach of the river were judged by the Aquatic Resource Team to have been protective of the natural aquatic resources. Due to the methodology of measurement and to historic records, it was clear that the Mystic Project had on average contributed closer to 5 cfs on average to the bypass during the minimum flow season. In order to maintain the actual historic flows that have supported the excellent fishery, PPLM agreed to maintain the historic levels which were judged to be typically 5 cfs with the allowance to reduce flows to 4 cfs 11 days each month (September through May). Although this appears to increase in the required bypass flow, in actually it codified continuation of PPLM s actual historic operation which was enhanced due to natural 5
6 inflows augmenting controlled releases. During summer months (June through August) the minimum bypass reach flow was kept to 10 cfs. This healthy fishery approach avoided the need to conduct costly and often debatable hydraulic habitat studies. This led to rapid resolution of what is often the most costly aspect of relicensing projects with bypassed instream reaches. PPLM also agreed to ramping the descending bypass minimum flow below 10 cfs to a maximum of 2 cfs per hour when the minimum flow is changed from summer to fall operations August 31 each year. Fish Valve Design PPLM showed good faith and stewardship of the river by recognizing the potential for dewatering the stream even though it might be an unlikely event. PPLM is continuing to work on the design elements of the emergency fish valve and has committed to installing the valve by As envisioned, the valve will provide a means of releasing a minimum of 5 cfs during the low flow season and 10 cfs during the summer season. Most importantly, the new valve will be ready to also maintain instream flows of 20 cfs to the entire river should any catastrophic event prevent water from flowing to the powerhouse. We will report at a future date on the successful implementation of this important safety element of the new Mystic Lake project. Figure 4. Existing configuration of the Mystic Lake flow line and penstock system Authors Ginger Gillin is a Senior Environmental Scientist with GEI Consultants in Sacramento, California. She works on FERC licensing and aquatic biological issues on regulated rivers in the western USA and served as lead aquatic scientist and project manager for this project. 6
7 John Pizzimenti is a Vice President at GEI Consultants in Portland, Oregon. John served as project manager and senior principal consultant for this project. Doug Foss was a Mechanical Engineer and lead engineer for this project from GEI Consultants Bozeman, Montana office. Doug passed away shortly before Mystic received its new license. We dedicate this paper to Doug s memory. He was instrumental in many of the successful elements in this and so many other hydro projects. He will be missed. Jon Jourdonnais is Hydro Licensing and Compliance Manager for PPL Montana in Butte, Montana. Jon led the entire Mystic Lake Relicensing effort and he and PPL Management empowered this team to be the first to successfully license a project under the ILP. 7
Black Canyon Hydroelectric Project FERC Project No. P-14110 Proposed Fish Passage Study Plan September 2012
Black Canyon Hydroelectric Project FERC Project No. P-14110 Proposed Fish Passage Study Plan September 2012 Prepared for Black Canyon Hydro, LLC 3633 Alderwood Avenue Bellingham, WA 98225 Table of Contents
More informationSection 2. Mono Basin Operations
Section 2 Mono Basin Chapter 2 Mono Basin Compliance with State Water Resources Control Board Decision 1631 and Order Nos. 98-05 and 98-07 May 2008 Los Angeles Department of Water and Power Table of Contents
More informationYear 2 7-15-10 Post Restoration Monitoring Summary Rock Creek Project Monitoring and Analysis conducted by Bio-Surveys,LLC. Contact: strask@casco.
Year 2 7-15-10 Post Restoration Monitoring Summary Rock Creek Project Monitoring and Analysis conducted by Bio-Surveys,LLC. Contact: strask@casco.net Project Sponsors include: The City of Corvallis Oregon
More informationWATER STORAGE, TRANSPORT, AND DISTRIBUTION Multi-Dam Systems and their Operation - J.J. Cassidy MULTI-DAM SYSTEMS AND THEIR OPERATION
MULTI-DAM SYSTEMS AND THEIR OPERATION J.J. Cassidy Consulting Hydraulic and Hydrologic Engineer, Concord, California, USA Keywords: Dams, reservoirs, rivers, water storage, dam safety, floods, environment,
More information1997-98 UPPER DESCHUTES R-EMAP TEMPERATURE SUMMARY
1997-98 UPPER DESCHUTES R-EMAP TEMPERATURE SUMMARY Daria G. Mochan Oregon Department of Environmental Quality Laboratory Division Biomonitoring Section 1712 S.W. Eleventh Avenue Portland, Oregon 97201
More informationHydropower. Corps Hydro Plants Non-Federal Plants
Hydropower Corps Hydro Plants Non-Federal Plants at Corps Dams The U.S. Army Corps of Engineers is the largest owner/operator of hydroelectric powerplants in the United States and one of the largest in
More informationColdwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration
More informationENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage
DOEIID-10360 Distribution Category: UC-22S ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage M. J. Sale G. F. Cada
More informationPenticton Creek May 4, 2015 Council Meeting
Penticton Creek May 4, 2015 Council Meeting Penticton Creek Council Meeting May 4, 2015 Penticton Creek in the Early Years Penticton Creek Council Meeting May 4, 2015 Penticton Creek Today Penticton Creek
More informationRuby River Grayling - Gravel Spawning Beds Monitoring Report January 2008
Ruby River Grayling - Gravel Spawning Beds Monitoring Report January 2008 In partnership with Montana Department of Fish, Wildlife, and Parks (FWP), American Wildlands, and Wildlife Forever, the Madison
More informationDISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014. Values Statements.
DISTRICT VALUES STATEMENTS, GOALS, ACTION ITEMS, AND ONGOING TASKS FOR 2015 Adopted by the Board of Directors December 10, 2014 Values Statements. The Board opposes any new transfers of water from the
More informationBIG CREEK Nos. 1 AND 2 (FERC Project No. 2175) VOLUME 1 (BOOK 1 OF 27 BOOKS) INITIAL STATEMENT, EXHIBITS A, B, C, D AND H (PUBLIC INFORMATION)
BIG CREEK Nos. 1 AND 2 (FERC Project No. 2175) VOLUME 1 (BOOK 1 OF 27 BOOKS) INITIAL STATEMENT, EXHIBITS A, B, C, D AND H (PUBLIC INFORMATION) CD NO. 1 OF 19 CDS Initial Statement Exhibit A: Description
More informationCOMPLIANCE REPORT MUDDY HOLLOW CULVERT REMOVAL FILE NUMBER 25358N
COMPLIANCE REPORT MUDDY HOLLOW CULVERT REMOVAL FILE NUMBER 25358N Submitted by the National Park Service Point Reyes National Seashore Point Reyes Station, California, 94956 Project Description: Muddy
More informationROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN. Evaluation of spring Chinook salmon spawning in Big Butte Creek, 2008
ROGUE RIVER SPRING CHINOOK SALMON CONSERVATION PLAN Evaluation of spring Chinook salmon spawning in Big Butte Creek, 28 Rogue Watershed District Oregon Department of Fish and Wildlife March 29 Introduction
More informationSkaguay Reservoir. FISH SURVEY AND MANAGEMENT DATA Greg A. Policky - Aquatic Biologist (Salida) greg.policky@state.co.
FISH SURVEY AND MANAGEMENT DATA (Salida) greg.policky@state.co.us / 719-530-5525 General Information: Skaguay Reservoir, a 114 acre impoundment, offers good fishing for rainbow and brown trout with an
More informationOctober 11, 2005. Sharon Stohrer State Water Resources Control board P.O. Box 2000 Sacramento, CA 95812-2000
October 11, 2005 Sharon Stohrer State Water Resources Control board P.O. Box 2000 Sacramento, CA 95812-2000 Re: Maidu Cultural and Development Group CEQA Scoping Comments for the Environmental Impact Report
More informationAPPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P-12686. Turbidity Monitoring Plan
APPENDIX F Baker County Mason Dam Hydroelectric Project FERC No. P-12686 Turbidity Monitoring Plan April 2011 857 Table of Contents 1.0 Introduction 1 2.0 Purpose and Scope 2 3.0 Turbidity Monitoring and
More informationBackground Information: The Mamquam River Floodplain Restoration Project
Background Information: The Mamquam River Floodplain Restoration Project The Mamquam River Floodplain Restoration project is being undertaken in partnership with the Squamish River Watershed Society, Fisheries
More informationCHAD R. GOURLEY SPECIALTY EMPLOYMENT
CHAD R. GOURLEY P.O. Box 919 Verdi, Nevada 89439 phone 775.345.9960 cell 775.250.8140 chad_gourley at att.net SPECIALTY Restoration of riverine, spring, and wetland ecosystems, specializing in a process
More informationCITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.
More information121 FERC 62,167 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. Public Utility District No. 1 of Project No. 637-044 Chelan County
121 FERC 62,167 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Public Utility District No. 1 of Project No. 637-044 Chelan County ORDER MODIFYING AND APPROVING LAKE CHELAN FISHERY PLAN,
More informationSand and Silt Removal from Salmonid Streams
Sand and Silt Removal from Salmonid Streams Stream bank erosion Poor land use practices Sources of Sand and Silt Impacts of Sand and Silt Interstitial spaces infilled Little or no flow through the streambed
More informationStream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration
Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria
More informationBull Run River. Water Temperature Evaluation. Prepared by: City of Portland Bureau of Water Works Portland, Oregon
Bull Run River Water Temperature Evaluation Prepared by: City of Portland Bureau of Water Works Portland, Oregon June 2004 Contents Page Preface... 1 Report Purpose... 1 Report Organization... 1 Executive
More informationAN INITIATIVE TO IMPROVE
L OW E R C A R M E L R I V E R A N D L AG O O N F L O O D P L A I N R E S TO R AT I O N A N D E N H A N C E M E N T P R O J E C T AN INITIATIVE TO IMPROVE FLOOD PROTECTION RESTORE AND PROTECT RIPARIAN
More informationNID statement Agreement Disagreement Auburn Ravine: During irrigation and nonirrigation
NID statement Agreement Disagreement Auburn Ravine: 1. NID will not divert the natural flow during times when the flow as measured at NID s Highway 65 gage is less than 8 cfs provided that during those
More informationFrequently Asked Questions (FAQs) on Hydropower
Frequently Asked Questions (FAQs) on Hydropower What are the advantages of Hydropower? A renewable source of energy - saves scarce fuel reserves. Non-polluting and hence environment friendly. Long life
More informationChapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
More informationMay 29, 2015. Mr. Tom Howard Executive Director State Water Resources Control Board P.O. Box 100 Sacramento, CA 95812-0100
May 29, 2015 Mr. Tom Howard Executive Director State Water Resources Control Board P.O. Box 100 Sacramento, CA 95812-0100 Mr. Ron Milligan Operations Manager, Central Valley Project U.S. Bureau of Reclamation
More informationLEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN
1 AUGUST 2011 LEAGUE NOTES ON APPROVED COMMUNITY WATER SUPPLY PLAN KEY ELEMENTS OF THE PLAN: 1. Replace the existing unsafe Ragged Mountain dam with a new dam and raise the reservoir pool level initially
More informationRecreational Enhancements on the Lehigh River Public Information Workshop February 2013
Recreational Enhancements on the Lehigh River Public Information Workshop February 2013 Cooperating Agencies US Army Corps of Engineers Philadelphia District Pennsylvania Fish & Boat Commission Pennsylvania
More informationUTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION
UTILITIZATION OF ECOHYDROLOGIC MODELS IN FLOODPLAIN FISH PASSAGE AND HABITAT RESTORATION EVALUATION Joshua A. Israel, Fish Biologist, U.S Bureau of Reclamation, Sacramento, CA. jaisrael@usbr.gov; Paul
More informationNOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand
Journal of Hydrology (NZ) 44 (2): 131-135, 2005 New Zealand Hydrological Society (2005) NOTE Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand W. E. Bardsley Department
More informationPrattsville Berm Removal Project. 1.0 Project Location
Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed
More informationEnvironmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization
Introduction A visual examination of Doolittle Creek in a highly developed suburban county in Georgia yielded telltale signs of a creek whose original streambed had been altered. Examination of official
More informationYoughiogheny River From Confluence, Pa to Indian Creek Fayette and Somerset Counties
Pennsylvania Fish & Boat Commission Biologist Report Youghiogheny River From Confluence, Pa to Indian Creek Fayette and Somerset Counties August 2012 Electrofishing Survey Originating in the mountains
More informationColumbia River Project Water Use Plan. Monitoring Program Terms of Reference LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN
Columbia River Project Water Use Plan LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN CLBMON-45 Lower Columbia River Fish Indexing Surveys 31 August 2007 1.0 OVERVIEW LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN
More informationSubject: Prospect 3 Hydroelectric Project (FERC 2337-076) Comments on Preliminary Application Document and Scoping Document; and Study Requests
Oregon John A. Kitzhaber, MD, Governor November, 14, 2013 Department of Fish and Wildlife Umpqua Watershed District Office 4192 North Umpqua Highway Roseburg, OR 97470 (541) 440-3353 FAX (541) 673-0372
More informationWalla Walla Bi state Stream Flow Enhancement Study Interim Progress Report. Department of Ecology Grant No. G1400656.
Walla Walla Bi state Stream Flow Enhancement Study Interim Progress Report Department of Ecology Grant No. G1400656 Submitted by: Walla Walla Watershed Management Partnership Walla Walla, WA Walla Walla
More informationProject Theory-Climate Change and Traditional Ecological Knowledge Adaption in the Klamath Basin
Project Theory-Climate Change and Traditional Ecological Knowledge Adaption in the Klamath Basin Frank K. Lake Lead Science and TEK Mentor for project Education 1995 B.S. University of California, Davis.
More informationGold Ray Dam Interagency Technical Team Meeting
Gold Ray Dam Interagency Technical Team Meeting Agenda Public Outreach, Funding, Monitoring EA/BA/Permit Updates Deconstruction Plans Fish Passage & Salvage Plan Hydraulic Modeling Next Steps Public Outreach,
More informationENVIRONMENTAL ISSUES AND MANAGEMENT FOR HYDROPOWER PEAKING OPERATIONS
ENVIRONMENTAL ISSUES AND MANAGEMENT FOR HYDROPOWER PEAKING OPERATIONS Dr. Helen Locher, Hydro Tasmania 4 Elizabeth St, Hobart, Tasmania, Australia helen.locher@hydro.com.au Abstract Many hydropower plants
More informationRestoring Ecosystems. Ecosystem Restoration Services
Restoring Ecosystems Ecosystem Restoration Services 2 Ecosystem Restoration Services AECOM s integrated approach sciencebased planning, with innovative design and execution delivers sustainable and cost-effective
More informationExecutive Summary: PA No. 12 Micro-hydro at Graham Hill Water Treatment Plant
Executive Summary: PA No. 12 Micro-hydro at Graham Hill Water Treatment Plant Description A micro-hydro project at SCWD s Graham Hill Water Treatment Plant (WTP) would replace an exisiting non-operational
More informationGeneral Permit for Activities Promoting Waterway - Floodplain Connectivity [working title]
General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] Purpose These rules set forth the conditions under which a person may, without an individual removal-fill permit
More informationIntroduction to Architecture. Lesson 13: Hoover Dam
Introduction to Architecture Lesson 13: Hoover Dam Back in 2010, my family and I flew to California and then drove to the Grand Canyon via the Hoover Dam. Named after President Herbert Hoover, the Hoover
More informationEarth Science. River Systems and Landforms GEOGRAPHY 1710. The Hydrologic Cycle. Introduction. Running Water. Chapter 14.
Earth Science GEOGRAPHY 1710 River Systems and Landforms DAVID R. SALLEE Robert W. Christopherson Charlie Thomsen Chapter 14 Introduction Rivers and streams are dynamic systems that continually adjust
More informationHCP Team Meeting. November 18, 2015. icfi.com
HCP Team Meeting November 18, 2015 icfi.com 1 Welcome and Introductions Where are we in the HCP process Hydrology modeling update Native fish survey Fish translocation Finalize covered activities Next
More informationTENNESSEE GAS PIPELINE COMPANY, L.L.C.
TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC & HYDRAULIC CALCULATIONS FOR WATERBODIES CROSSED BY CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,
More informationCHAPTER I: INTRODUCTION. Background
CHAPTER I: INTRODUCTION Background California State Law requires each county to adopt a General Plan for the physical development of the county and any land outside its boundaries which bears relation
More information6.0 Results of Risk Analyses
6. Results of Risk Analyses A risk analysis of the optimized embankment designs for the Salton Sea restoration project was conducted jointly by Kleinfelder and representatives from Reclamation. A risk
More informationArkansas River Corridor Vision & Master Plan
A r k a n s a s R I v e r C o r r I d o r P l a n Arkansas River Corridor Vision & Master Plan July 2005 Indian Nations Council of Governments A r k a n s a s R I v e r C o r r I d o r P l a n Partnership
More informationKevin Kennedy Natural Gas and Special Projects Office
PRELIMINARY ASSESSMENT OF ENERGY ISSUES ASSOCIATED WITH THE KLAMATH HYDROELECTRIC PROJECT Kevin Kennedy Natural Gas and Special Projects Office Jim Woodward Electricity Analysis Office Systems Assessment
More informationTie CornrnonweaGti of Massaciusetts Wecutive Ofiice of Energy andenvironmentacpfiairs 100 Cam6ndjge Street, Suite 900 Boston, NP 021 14
Ocval I.. Palrick CiClVERNOll Ttrnothy P. Murray I IFUTENANl GOVERNOR Ian A. Rowles SECRETARY Tie CornrnonweaGti of Massaciusetts Wecutive Ofiice of Energy andenvironmentacpfiairs 100 Cam6ndjge Street,
More informationPrepared By: Tom Parker Geum Environmental Consulting, Inc.
Prepared By: Tom Parker Geum Environmental Consulting, Inc. Topics covered: Definition of riparian and floodplain restoration Floodplain attributes as a basis for developing criteria for restoration designs
More informationLR 314 Working Group 5 Final Report
LR 314 Working Group 5 Final Report I. Nebraska Department of Natural Resources Table 1. NDNR and NATURAL RESOURCES COMMISSION WATER/INTEGRATED MANAGEMENT PLANNING RELATED RESEARCH, STUDIES AND RELATED
More information1.7.0 Floodplain Modification Criteria
1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:
More informationSTANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208
STANDARDS FOR RANGELAND HEALTH ASSESSMENT FOR SAGEHEN ALLOTMENT #0208 RANGELAND HEALTH STANDARDS - ASSESSMENT SAGEHEN ALLOTMENT #0208 STANDARD 1 - UPLAND WATERSHED This standard is being met on the allotment.
More informationMonitoring Riparian Areas With a Camera
Monitoring Riparian Areas With a Camera By Michael DeLasaux 1, Holly George 2, and Philip Mainwaring 3 Riparian areas are next to streams, springs, rivers, ponds and lakes. Physical characteristics that
More informationProposal to the Trinity Adaptive Management Working Group (TAMWG)
Proposal to the Trinity Adaptive Management Working Group (TAMWG) Request that the TAMWG recommend that the Trinity River Restoration Program fund BLM to purchase the Weigel parcel at Gold Bar (river mile
More informationPonds- Planning, Design, Construction
United States Department of Agriculture Soil Conservation Service Agriculture Handbook Number 590 Ponds- Planning, Design, Construction This handbook describes the requirements for building a pond. It
More informationStream Restoration Post-Implementation Annual Monitoring Report Year 2: 2013 Covering the Period of July 2012 to July 2013
NCDA&CS - North Carolina Forest Service Stream Restoration Post-Implementation Annual Monitoring Report Year 2: 2013 Covering the Period of July 2012 to July 2013 For the N.C. Division of Water Quality
More informationFloodplain Connectivity in Restoration Design
Floodplain Connectivity in Restoration Design 2015 Symposium on Restoration in a Contaminated Environment: Lessons Learned and Challenges in Moving Forward Part II April 2015 Karin Boyd Applied Geomorphology,
More informationCARLSON CREEK HYDROELECTRIC PROJECT PRELIMINARY FEASIBILITY EVALUATION AEA GRANT #2195462
CARLSON CREEK HYDROELECTRIC PROJECT PRELIMINARY FEASIBILITY EVALUATION AEA GRANT #2195462 ALASKA POWER & TELEPHONE COMPANY DECEMBER, 2011 CARLSON CREEK HYDROELECTRIC PROJECT PRELIMINARY FEASIBILITY EVALUATION
More informationHUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014
HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014 PRESENTATION TOPICS Analysis Objectives Analysis Dam Removal Plan Dam Remediation Plan Effects Analysis Permit Requirements Decision
More informationRe: Preliminary Permit Application for the Rose Creek Pumped Storage Project
September 12, 2013 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Preliminary Permit Application for the Dear Ms. Bose, Please find attached
More informationThe Teton Creek Restoration Project Summary:
The Teton Creek Restoration Project Summary: The Teton Creek Restoration Project area extends for approximately one mile upstream from the Cemetery Road Bridge and includes the Aspen Pointe, The Aspens
More informationSolar PV panels fitted to roofs. Solar PV panels produce electricity from energy provided by sunlight. 3.5 MWh per system
Solar PV panels fitted to roofs Yearly cost of production Cost per kwh 12.5p Solar PV panels produce electricity from energy provided by sunlight. 3.5 MWh per system 430 per system Solar energy can be
More informationRequest Number 11: Fish and Fish Habitat Compensation Plan
Request Number 11: Fish and Fish Habitat Compensation Plan References: EIS Guidelines Section 16.8.4; EIS Guidelines Section 10; EIS, Vol. 2, Section 12.5.3.2 JRP Context: The EIS states that a Site C
More informationThe Basics of Chapter 105 Waterways and Wetlands Permitting in PA
The Basics of Chapter 105 Waterways and Wetlands Permitting in PA April 17, 2013 Goal To develop a basic understanding of PA Department of Environmental Protection (DEP) and US Army Corps of Engineers
More informationAddendum D. Nomination of Moody Wash ACEC
Addendum D Nomination of Moody Wash ACEC Moody Wash ACEC is hereby nominated by Citizens for Dixie s Future to: BLM St. George Field Office 345 East Riverside Drive St. George, UT 84790 Moody Wash is a
More informationRevising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan
Revising the Nantahala and Pisgah Land Management Plan Preliminary Need to Change the Existing Land Management Plan Throughout the Plan 1. There is a fundamental need for the revised plan to address how
More informationHow To Check For Scour At A Bridge
Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway
More informationFinal Report. Dixie Creek Restoration Project. Funded by Plumas Watershed Forum
Final Report Dixie Creek Restoration Project Funded by Plumas Watershed Forum Plumas Corporation January 2009 1 Background FR-CRM staff presented this project to the Dixie Valley Landowners Association
More informationSPA Annual Report for 2002 September, 2003 Montgomery County Department of Environmental Protection Page 125. Evaluation and Recommendations
Montgomery County Department of Environmental Protection Page 125 Evaluation and Recommendations Monitoring efforts in the Special Protection Areas continue to provide the kind of information needed to
More informationChapter 11. Costs and Funding
Chapter 11. 11.1 Financial Summary...11-1 11.2 Program Costs...11-2 11.2.1 Habitat Conservation Program Costs...11-2 Bull Run Habitat Conservation Measures...11-2 Offsite Sandy River Basin Habitat Conservation
More informationHEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES
HEADWATERS CONTROL STRUCTURE MANAGEMENT POLICY AND OPERATING PROCEDURES INTRODUCTION The Headwaters Control Structure at Gray's Bay is the outlet of Lake Minnetonka to Minnehaha Creek. It is an adjustable
More informationJOB DESCRIPTION. GS-11 $46,006 - $59,801 Annual/Full Benefits GS-12 $55,138 - $71,679 Annual/Full Benefits
OPEN: CLOSE: OR UNTIL FILLED EXEMPT NON-EXEMPT_X_ JOB DESCRIPTION POSITION: RESPONSIBLE TO: SALARY: FLUVIAL GEOMORPHOLOGIST Senior Aquatics Biologist GS-11 $46,006 - $59,801 Annual/Full Benefits GS-12
More informationWater Extraction Permitting Policy
Water Extraction Policy 1 Water Extraction Permitting Policy Department of Environment, Labour & Justice January 2013 Water Extraction Policy 2 EXECUTIVE SUMMARY This document establishes a new policy
More information9.1. Adequacy of Available Data and Monitoring Efforts
9. DATA MANAGEMENT Data management is a crucial aspect of successful implementation of the ARB IRWMP and its component projects. This section discusses the adequacy of available data and monitoring efforts,
More informationHow To Plan A Buffer Zone
Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other
More informationColumbia River Project Water Use Plan. Monitoring Program Terms of Reference
Columbia River Project Water Use Plan Revelstoke Flow Management Plan Monitoring Program Terms of Reference CLBMON-15a Middle Columbia River Physical Habitat Monitoring Revision January 29, 2015 Monitoring
More informationCHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES
GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations
More informationIUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure
IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure (December 2013) IUCN does not engage in projects which involve the design, construction or rehabilitation
More informationHow To Manage Water Resources In The Yakima Basin
Yakima Basin Integrated Water Resource Management Plan October 23, 2014 Presented by Derek Sandison, Director Office of Columbia River Photo Courtesy of Tom Ring Basin size: 6,155 sq. miles Population:
More informationHabitat Quality, Rainbow Trout Occurrence, and Steelhead Recovery Potential Upstream of Searsville Dam
Habitat Quality, Rainbow Trout Occurrence, and Steelhead Recovery Potential Upstream of Searsville Dam Prepared by: Matt Stoecker Biologist Owner Stoecker Ecological December 19, 2014 Table of Contents
More informationOxbow Restoration for Fish Habitat and Water Quality
Oxbow Restoration for Fish Habitat and Water Quality Chris Jones and Aleshia Kenney Iowa Soybean Association U.S. Fish and Wildlife Service ENVIRONMENTAL Programs and Services Partners for Fish and Wildlife
More informationNPLOTH7 GIS Database Development Mission (2619), Bryson (2601), Franklin (2603), Dillsboro (2602) Final Report
NPLOTH7 GIS Database Development Mission (2619), Bryson (2601), Franklin (2603), Dillsboro (2602) Final Report Introduction Duke Power Nantahala Area (Duke) is in the process of relicensing the Mission,
More informationRESTORATION AND ENHANCEMENT OF SOUTHERN CALIFORNIA LAGOONS
RESTORATION AND ENHANCEMENT OF SOUTHERN CALIFORNIA LAGOONS by Hany Elwany, Ph.D. Scripps Institution of Oceanography Headwaters to Oceans Conference 25 October 2003 CE Ref #03-22 San Diego County Lagoons
More informationSteelhead Recovery in San Juan and Trabuco Creeks Watershed
Steelhead Recovery in San Juan and Trabuco Creeks Watershed Are there fish now? Overview Final San Juan and Trabuco Creeks Watershed Management Plan Fish & Game Implementation NOAA Steelhead Recovery and
More information2013 Hardwater Lake Aquatic Vegetation Control Plan LDWF, Inland Fisheries
a. 2013 Hardwater Lake Aquatic Vegetation Control Plan LDWF, Inland Fisheries 1. Waterbody type natural backwater lake off of Little River in Grant Parish. It is a wooded alluvial floodplain lake that
More informationSTATE OF CALIFORNIA STATE WATER RESOURCES CONTROL BOARD
STATE OF CALIFORNIA STATE WATER RESOURCES CONTROL BOARD ) In the matter of: ) City of Los Angeles Department of Water and Power, ) Water Right Licenses Nos. 10191 and 10192 ) ) SETTLEMENT AGREEMENT REGARDING
More information5.14 Floodplains and Drainage/Hydrology
I-70 East Final EIS 5.14 Floodplains and Drainage/Hydrology 5.14 Floodplains and Drainage/Hydrology This section discusses floodplain and drainage/hydrology resources and explains why they are important
More informationRestoring Anadromous Fish Habitat in Big Canyon Creek Watershed. Summary Report 2002
Restoring Anadromous Fish Habitat in Big Canyon Creek Watershed Summary Report 2002 DOE/BP-00005268-5 November 2002 This Document should be cited as follows: "Restoring Anadromous Fish Habitat in Big Canyon
More informationOutlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
More informationDeWitt Pipeline Rehabilitation/Replacement Project Environmental Assessment
Final DeWitt Pipeline Rehabilitation/Replacement Project Environmental Assessment Prepared for U.S. Forest Service Wasatch-Cache National Forest Logan Ranger District and Utah Department of Environmental
More informationResolving complex issues with large scale river restoration; a case study: the San Joaquin River in California
IWA Publishing 2011 Water Practice & Technology Vol 6 No 4 doi:10.2166/wpt.2011.074 Resolving complex issues with large scale river restoration; a case study: the San Joaquin River in California William
More informationRestoration Planning and Development of a Restoration Bank
Restoration Planning and Development of a Restoration Bank Black Creek Pioneer Village, South Theatre 8:30 a.m. to 3:30 p.m. Habitat Restoration and Environmental Monitoring Projects Section Restoration
More informationPlan Groundwater Procurement, Implementation and Costs, prepared for the Brazos River Authority, July 2005.
6 Conjunctive Use 6.1 Lake Granger Augmentation 6.1.1 Description of Option Rapid population growth and development in Williamson County require additional water supplies throughout the planning period.
More informationAddendum. Use Attainability Analysis for Site Specific Selenium Criteria: Alkali Creek. February 23, 2009
Addendum Use Attainability Analysis for Site Specific Selenium Criteria: Alkali Creek February 23, 2009 Prepared by MWH Americas, Inc. Prepared for EnCana Oil and Gas (USA) Inc. Page 2 Responses to Comments
More information